Donn Grid Suspension System
Donn Grid Suspension System
Donn Grid Suspension System
Suspension Systems
General Offices USG DONN brand suspension systems are the original exposed grid
Hotels
system developed in the 1950’s and still a world leader in technology
and innovation.
Retail Malls
Covering almost every conceivable application, the designer and
Banks
contractor alike have the choice of the traditional 24mm DONN DX
Reception/lobbies system, or the more sophisticated appearance of the 15mm DONN
Centricitee.
Board Rooms
Food Preparation Areas For fire protection and safety, DONN DXL can provide a number of
different Fire Resistant Rating (FRR/FRL) ceiling design options
Fire rated areas combined with the appropriate USG Firecode acoustical ceiling panel.
Contents Page
Components 4-7
Accessory Applications 8
System Layouts 9
Installation and Good Design Practice 10-11
Maximum Allowable Loads 12-15
Lighting Installation 16-17
Transition to Plasterboard Ceilings 18-20
Fire Rating & Seismic Design 21
USG Acoustical Ceiling Panels 22
General Information 23
© 2011
DONN Brand
®
System Components Advantages
Exposed Grid
DONN® DX®
24mm Exposed Grid
Applications
Q
Medium Standard 32mm 1200mm DX30M-1200 A, B, C, D
ta
DONN Brand DX Suspension System
R R
A B C D
Square Edge (SQ) Shadowline Shadowline (SL) Shadowline
Tapered (SLT) Bevel (SLB)
Main Tee (Fire Rated) Main Tee (Fire Rated) 38mm 3600mm DXL38D-3600 A, B, C, D
Deep
Cross Tee (Fire Rated) 38mm 1200mm DX38D-1200 A, B, C, D
50mm 100mm 100mm
Cross Tee (Fire Rated) 38mm 600mm DX30D-0600 A, B, C, D
3600mm
© 2011
DONN Brand
®
System Components Acoustical
Ceiling Systems
Exposed Grid
DONN® CENTRICITEE®
15mm Exposed Grid
1. Imperial and non-standard lengths/modules available subject to minimum order quantities and lead times.
2. Limited suitability. Refer to individual acoustical panel brochures
© 2011
System Components
Construction Details Wall Angles
Donn Brand Wall Angles are formed from prepainted, hot dipped galvanised steel. Ends are all square cut
Standard MT45-3600/MT55-3600 Standard Seismic
1.8mm
10mm
Temporary (selfdrilling screw)
1.8mm fixing to be removed after
19mm bracing installed.
Trim to be fixed to wall, max 600mm centres. Fixing to Main or Cross Tee
be relevant to wall strata eg plug and screw or suitable
42mm
precedence of type and quantity of fixing. Wall Channel to be fixed at max 600mm centres
26mm
1.8mm
19mm
1.8mm
10mm 19mm
Centricitee MXT45-3600 Crimping Option Teg Tab block option Field Cutting Option
1.8mm
22mm
1.8mm
14mm
Shadowline MS45-3000
Cut, then form end with 6mm Trimmed perimeter panels hand rebated to match
15mm
1.8mm
© 2011
System Components
Accessories
MT/CT Converter WSC18 (for SQ edge panels) WSC38 (for rebated 24mm)
Joins Main Tees at 90˚ Revoe Partition Attachment Clip WSC38-9 (for rebated 15mm)
© 2011
Construction
Details Accessory Applications
The following information will help you select and use the appropriate accessories. Many of the
accessories are multifunctional. Transitions from soffits or flat surfaces can be easier with the use of
accessories.
• Transition Clip joints require at least one (1) hanger within 300mm.
• Splice Clip joints require one (1) hanger within 150mm of splice.
90˚ outside corner using Transition Clip 90˚ inside corner with channel molding at top edge
US3600
channel
molding
main tee or cross tee cross tee
transition clip
main tee
tee
wall angle
DGSC-180 The primary purpose of the Splice DGSC-180 Another common use of the
Splice Clip Clip is to join two field cut Splice Clip Splice Clip is joining two grid tees
Application A Application B
to length in-line main tees. that are intersecting off module,
such as a utility opening. The link
joining the bend down tabs on
Splice Clip (A) cut the clip is cut allowing it to be
folded on the slotted bend line.
© 2011
Construction
Details System Layouts
5 12
00
3
4
1 3
Cross Tee
QRC 2 6
tab
0
60
5
12
00
4
Cross Tee 1 6 4
QRC 7
tab
3
0
60
© 2011
Requirements and
Good Design
Practices
Installation DONN® Brand
Exposed Grid
Suspended ceilings are finished products intended for interior use and should be treated accordingly.
Delivery, Storage and - All materials shall be delivered in their original, unopened packages and stored for as short a time as possible, in
Handling an enclosed shelter providing protection from exposure to the elements and damage by/to other trades. Damaged,
deteriorated or obviously faulty material is not to be installed and shall be removed from the premises.
- Materials should be handled in such a manner as to prevent racking distortion or physical damage.
Installation - Ceiling layout should be planned prior to installation to determine grid configuration, direction etc. and to ensure that all
fixing points are compatible with structural members and/or other services.
- Installation of exposed grid shall not begin until the building is closed in, fully glazed, roof watertight and residual
moisture from wet trades such as plaster, concrete and terrazzo has dissipated.
- Mechanical and electrical ductwork above the suspension system shall be completed before installation of the suspension
system.
Main Tee - For standard installations Main Tees are spaced at 1200mm centres.
- Where heavy ceiling panels are used, close Main Tees in to 600mm centres. Refer Loadings pages 12-15
- Main Tee integral splices are to be offset from each other across the ceiling. Where this cannot be avoided, aligned
splices shall be mechanically fastened with a pop-rivet, tek screw or similar.
Cross Tee - Cross Tees interlock with opposing Cross Tees through the Main Tee web slots to form the required module.
QRC tab - A positive “click” is heard when the DONN QRC tab correctly engages.
- The Cross Tee being installed should be inserted on the left side of the already
Butt Cut Lay-on
Cross
installed Cross Tee.
Cross
Tee Tee - Slots are punched along the Main Tee for convenience at 100mm centres for
DONN Main Tee / Cross Tee Engagement metric systems and 6” for imperial systems.
- Main and Cross Tees can be arranged in a variety of module configurations - see Loadings pages 12-15 for standard
common layouts.
Suspension - Main Tee hangers are spaced at 1200mm centres, no more than 600mm from the perimeter Wall Trim or 150mm
from the Main Tee splice or 200mm from the Main Tee / Cross Tee joint. For heavier ceilings closer spacings may be
required and/or hangers provided through the Cross Tee. Wider spacing may be allowable - see Loadings pages 12-15
or contact your USG Ceiling Specialist.
- For Cross Tees not directly attached to walls and where building movement may be anticipated and there is a risk of
them losing support, provide extra hangers or suitable restraint to the Cross Tees. (eg ACM7 Seismic Clip)
- Where ceilings are back-braced for seismic restraint, do not attach grid to walls. Provide one hanger within 200mm of
the end of every Main Tee and Cross Tee, or suitable support to allow for movement. (eg ACM7)
Multi
- 2.5mm diameter straightened galvanised wire located through the
DONN
Wall Angle hold down pre punched convenience holes in the Main Tee bulb or web and
clip secured with three tight 360° turns.
2.5mm Galvanised
- 2.5mm wire or 5mm galvanised rod with the DONN CL315
Steel Wire suspension clip over the bulb.
(5mm Rod Optional)
DONN DONN - 5mm rod with the CL2424 clip through prepunched hole in the web
Main Tee CrossTee or bulb of DONN Centricitee or DONN DX grid.
USG
Acoustical - Flat steel strip or Wall Angle secured to the tee web with fasteners
Panel
the greater of 50kg or ultimate load from AS/NZS 2785.
- DONN Direct Fixing Clips between bulb holes only (no less than 10mm).
- Hangers are not to be bent or kinked as a means of levelling the grid or for any other reason.
- Hangers or bracing are not to be fixed to, or closer than 150mm to plenum building services e.g. ducting, sprinkler
pipes.
- Fixing of the hanger to the structure above with proprietary fasteners shall be installed in accordance with their
manufacturers recommendations, be suitable for the structure material and comply with any required Standards. Such
fasteners shall have a design ultimate strength the greater of 50kg (0.5kN) minimum, or load requirements of AS/NZS
2785 Clause 3.2.2 (c).)
- Hangers using the CL315 clip shall not vary from the vertical by more than 5°.
- Where hangers are splayed up to a maximum of 45° to the vertical, they should always have an equally applied hanger
in the opposite direction.
- Suspension method and position may be dependant on load requirements. See Step 3 tables pages 13 and 15.
10 © 2011
Requirements and
Good Design
Practices
Installation DONN® Brand
Exposed Grid
Trapeze wires pick up USG DONN Exposed Main vertical Ceiling will want
mid-point of span to Grid or suspension greater to go this way.
carry the load USG Drywall Grid than allowable
suspension span
Wall Perimeter A variety of different Wall Angle profiles are available to suit the Donn Brand systems and designer’s requirements. See
Wall Angles page 6 for details.
- Typically fix trim to walls or bulkheads up to 600mm centres maximum.
Panel Hold Down Clips Clips may be required for seismic restraint, fire ratings or wind uplift on ceiling panels.
- Typically install 2 Hold Down Clips (steel or other) per parallel tee (Cross or Main). This will give four points per panel
restraint.
- Where frequent access in to the plenum is anticipated, some clips can have one side removed to allow clipping one
side of the tee but access on the other.
- Ensure clips are of a type suitable for DONN DX or DONN Centricitee and for the thickness of acoustical panel being
clipped.
Plenum Depths Minimum plenum depths for the ease of removal of
- 600 x 600mm panels = 150mm
- 1200 x 600mm panels = 200mm
Where lesser plenum depth is required, particularly under non-continuous structure or services, like joists/purlins or
ducts, side loading of ceiling panels can further reduce the depth in these areas to 70mm (subject to panel thickness).
Cutting DONN Grid and Wall Angle systems are easily cut on site with aviation snips or fine toothed band or hack saws.
Ceiling Acoustics Acoustical absorption and sound transmission can be controlled to desired levels with the appropriate selection from
the extensive range of USG acoustical ceiling panels. See page 22 for an overview selection. Consult your USG Ceiling
Specialist for advice on a total acoustical ceiling system.
Fire Rating Main, Cross Tees and perimeter trims are non-combustible (BS476 Part 4).
DONN DXL grid system and appropriate USG Firecode acoustical ceiling panel provide floor/ceilings, roof/ceilings
assembly Fire Ratings up to 1 hour. Refer to USG Fire Rated Grid brochure for full details.
Please consult USG Interiors for regional compliance and availability.
Lighting/Air Handling Most standard luminaires, louvres, grills and linear diffusers integrate with the standard module configurations. Refer
Lighting Installation pages 16-17 for specific details.
Thermal Properties DONN suspension systems are unaffected by thermal movement between ambient temperature variations of 10˚ to 30˚C.
Health and Safety The material composition represents no health hazard. When handling, take care and ensure that safe work practices are
adhered to at all times. Some products may have surface treatments and sharp edges/ends. All reasonable care should
be taken when handling or installing to avoid any potential injury to self or others. Users should be properly trained and
supervised in the use and handling of these materials. Appropriate personal protective equipment should be used when
necessary eg: gloves/glasses etc. to avoid any potential injuries.
Maintenance - Cleaning - Remove ceiling panels, then perform necessary cleaning of the grid with non-solvent based commercial
cleaner.
- Painting - Repainting of grid system members should be with a high quality solvent based paint for use over metal
surfaces and applied as recommended by the paint manufacturer.
- Paint colour - Powder coating: Ameron Coatings - Product Code PE522 polyester matt
Colour Code 9249AN ANOGRAIN Pacific White
- Wet spray Ameron Coatings - Product Code 640 Amercryl (acrylic lacquer)
Colour Code 100322 Pacific White NZ
Materials Main and Cross Tees are a double web design, roll formed from hot dipped galvanised steel with prepainted galvanised
steel cap. Cross Tees have a DONN QRC high tensile steel tab clinched to each end, zinc chromate finish.
Partitions A partitions mass may impact on the installation requirements of a suspended ceiling due to seismic movement.
Partitions should not be rigidly fixed to the suspended ceiling where possible, but can be fixed with provision for seismic
or other building movement. The Revoe Clip accessory can be used for this. Refer to the USG Seismic Design Guide for
full details.
© 2011
11
DONN DX
24mm Loadings -
Maximum Allowable
To determine which is the most appropriate and cost effective grid combination compliant with AS/NZS 2785:2000
Suspended Ceilings - Design and Installation, use the following calculations.
Step 1
Maximum Load Calculations G= Grid Weight + Panel Weight + Lights/Fixtures/Insulation etc Weight
Ultimate Limit State
G= + + = kg/m2
1.1 Factored Dead Load
A A = x 1.4 Therefore Maximum Load A = kg/m2
Notes: 1. Load calculations 1.1 and 1.2 are based on AS/NZS 2785:2000 Clause 3.3.5(a). Load calculation 1.2 is based on a
minimum Service Load of 3.0 kg/m² as required by the Standard. The contractor is to confirm that this load will not be
exceeded, or alter the calculation accordingly. If Service Load U is NOT a requirement, use calculation 1.1 values only.
2. These tables apply to areas of buildings that have no openings to the outside, such as doors, windows, ducts etc. In all
other cases the appropriate design loading must be determined by the project structural engineer in accordance with
AS/NZS 2785:2000 Clauses 3.3.5(b) or (c).
3. Standard testing and installation for suspension is at 1200mm centres. Wider centres may be allowable - refer to respective
grid combination tables. Hangers must be within 200mm maximum of Main Tee / Cross Tee connection.
4. Heavy lighting or other mechanical services shall be supported on the main tees, included in the dead load 1.1 above,
able to be supported by the selected grid combination, and/or should be independently supported if greater than 10kg
(NZS4219).
5. All point loads shall be fixed under suspension point on Main Tees only and hanger capacity should be checked against
Step 3.
6. Loadings are laboratory tested in accordance with AS/NZS 2785 with a deflection limit of L/360. Maximum allowable
system loads take into account continuous spans and are applicable for ceilings 2.4 metres or longer. For ceilings shorter
than 2.4 metres use a minimum of two hangers
7. Seismic considerations for in-plane loads may take precedence in determining the required grid combination (refer to the
USG Seismic Design Guide)
8. Not all products may be available in all areas.
9. For non-standard modules eg. 750 x 750mm etc. contact USG for availability and lead times prior to specification.
Step 2 From the grid diagrams below and opposite, select a ceiling layout and hanger spacing where the :
Maximum Load (from Step 1, above) is less than or equal to the Maximum Allowable Load from the Tables.
Alternative Grid Layouts
This will guide you as to the minimum grid combinations to use to fully comply.
19.7
Maximum allowable load kg/m²
DX30D-3600 DX30D-1200 DX30S-600 31.3 25.9 19.7 15.5 11.6 N/A 1.11
DXL38D-3600 DX38D-1200 DX30D-600 19.0 19.0 14.5 N/A N/A N/A 1.29
Fire Rated Grid
DX38D-3600 DX30D-1200 DX30D-600 31.8 31.8 30.1 21.3 15.4 N/A 1.21
12 © 2011
DONN DX
24mm Loadings -
Maximum Allowable
Alternative Grid Layouts Grid Combinations Hanger Spacing (mm) System Weights
Main Tee Cross Tee Cross Tee
1200
2
1000 1100 1350 1500 1800 kg/m
DX30D-3600 DX30D-1200 DX30S-600 15.9 15.9 15.9 15.5 11.6 N/A 1.10
DX38D-3600 DX38D-1200 DX30D-600 21.9 21.9 21.9 21.3 15.4 N/A 1.30
DX55D-3600* DX38D-1200 DX30D-600 21.9 21.9 21.9 21.9 20.4 11.8 1.42
*(to special order)
1200mm x 1200mm
Maximum allowable load kg/m²
Use a hanger type and location greater than the Maximum Allowable Loads from the tables above.
STEP 3 Use of these tables must take into account any point loads.
Maximum Allowable Loads
Using a bulb hole Using a web hole Using a CL315 Clip Using a DFS200 Strap
(kg/m2) with Main Tees at
1200mm spacing. - ø 2.5 wire - ø 2.5 wire (between bulb holes only
- CL 2424 - CL 2424 no less than 10mm)
(if at 600mm spacing double the Allowable
Load)
Hanger spacing 1200 1350 1500 1200 1350 1500 1200 1350 1500 1200 1350 1500
DX30D-3600 N/A N/A N/A 33.3 29.6 26.6 40.8 36.3 32.6 N/A N/A N/A
DX38D-3600 31.5 28.0 25.2 48.7 43.3 38.9 49.0 43.6 39.2 37.6 33.4 30.1
(ø 2.5 wire
DXL38D-3600 only) N/A N/A N/A 48.7 N/A N/A N/A N/A N/A N/A N/A N/A
DX55D-3600 46.2 41.1 37.0 45.1 40.1 36.1 62.5 55.6 50.0 78.0 69.3 62.4
© 2011
1
DONN DXT
Centricitee Loadings -
15mm
Maximum Allowable
To determine which is the most appropriate and cost effective grid combination compliant with AS/NZS 2785:2000
Suspended Ceilings - Design and Installation, use the following calculations.
Step 1
Maximum Load Calculations G= Grid Weight + Panel Weight + Lights/Fixtures/Insulation etc Weight
Ultimate Limit State
G= + + = kg/m2
1.1 Factored Dead Load
A A = x 1.4 Therefore Maximum Load A = kg/m2
Notes: 1. Load calculations 1.1 and 1.2 are based on AS/NZS 2785:2000 Clause 3.3.5(a). Load calculation 1.2 is based on a
minimum Service Load of 3.0 kg/m² as required by the Standard. The contractor is to confirm that this load will not be
exceeded, or alter the calculation accordingly. If Service Load U is NOT a requirement, use calculation 1.1 values only.
2. These tables apply to areas of buildings that have no openings to the outside, such as doors, windows, ducts etc. In all
other cases the appropriate design loading must be determined by the project structural engineer in accordance with
AS/NZS 2785:2000 Clauses 3.3.5(b) or (c).
3. Standard testing and installation for suspension is at 1200mm centres. Wider centres may be allowable - refer to
respective grid combination tables. Hangers must be within 200mm maximum of Main Tee / Cross Tee connection.
4. Heavy lighting or other mechanical services shall be supported on the main tees, included in the dead load 1.1 above,
able to be supported by the selected grid combination, and/or should be independently supported if greater than 10kg
(NZS4219).
5. All point loads shall be fixed under suspension point on Main Tees only and hanger capacity should be checked against
Step 3.
6. Loadings are laboratory tested in accordance with AS/NZS 2785 with a deflection limit of L/360. Maximum allowable
system loads take into account continuous spans and are applicable for ceilings 2.4 metres or longer. For ceilings shorter
than 2.4 metres use a minimum of two hangers
7. Seismic considerations for in-plane loads may take precedence in determining the required grid combination (refer to the
USG Seismic Design Guide)
9. For non-standard modules eg. 750 x 750mm etc. contact USG for availability and lead times prior to specification.
Step 2 From the grid diagrams below and opposite, select a ceiling layout and hanger spacing where the :
Maximum Load (from Step 1, above) is less than or equal to the Maximum Allowable Load from the Tables.
Alternative Grid Layouts
This will guide you as to the minimum grid combinations to use to fully comply.
DXT38D-3600 DXT38D-1200 DXT30D-600 28.2 23.3 17.8 14.1 11.3 N/A 1.10
Maximum allowable
1 © 2011
DONN DXT
Centricitee Loadings -
15mm
Maximum Allowable
Alternative Grid Layouts Grid Combinations Hanger Spacing (mm) System Weights
Main Tee Cross Tee Cross Tee
1200
2
1000 1100 1350 1500 1800 kg/m
Maximum allowable
Cross Nogged 1200mm x 600mm DXT30D-3600 DXT30D-1200 12.8 12.8 11.1 N/A N/A N/A 0.70
load kg/m²
DXT38D-3600 DXT38D-1200 17.1 17.1 17.1 14.1 11.3 N/A 0.85
Maximum allowable
Cross Nogged 600mm x 600mm
DXT30D-3600 DXT30D-1200 DXT30D-600 12.8 12.8 11.1 N/A N/A N/A 0.93
load kg/m²
DXT38D-3600 DXT38D-1200 DXT30D-600 17.1 17.1 17.1 14.1 11.3 N/A 1.10
Maximum allowable
1200mm x 1200mm
DXT30D-3600 DXT30D-1200 12.8 12.8 11.1 N/A N/A N/A 0.47
load kg/m²
600mm x 600mm
DXT30D-3600 DXT30D-600 35.2 29.1 22.2 17.6 14.2 N/A 0.93
load kg/m²
600mm x 1200mm
DXT30D-3600 DXT30D-600 35.2 29.1 22.2 17.6 14.2 N/A 0.70
load kg/m²
Use a hanger type and location greater than the Maximum Allowable Loads from the tables above.
STEP 3 Use of these tables must take into account any point loads.
Maximum Allowable Loads
Using a bulb hole Using a web hole Using a CL315 Clip Using a DFS200 Strap
(kg/m2) with Main Tees at
1200mm spacing. - ø 2.5 wire - ø 2.5 wire (between bulb holes only
- CL 2424 - CL 2424 no less than 10mm)
(if at 600mm spacing double the Allowable
Load)
Hanger spacing 1200 1350 1500 1200 1350 1500 1200 1350 1500 1200 1350 1500
DXT30D-3600 N/A N/A N/A 33.3 29.6 26.6 40.8 36.3 32.6 N/A N/A N/A
DXT38D-3600 31.5 28.0 25.2 48.7 43.3 38.9 49.0 43.3 39.2 37.6 33.4 30.1
© 2011
1
Construction Details
Lighting Installation
As worldwide leaders in acoustical ceiling systems, USG Interiors works with the major lighting manufacturers to ensure system
compatibility is maintained. The following guidelines are designed to assist in the correct specification and installation of light
fittings in USG’s DONN Brand Exposed Grid and acoustical ceiling systems.
Luminaire Positioning Typical recessed pan fitting arrangements are shown below. Main Tees at 1200mm centres are shown horizontal, with
suspension at 1200mm centres.
DONN BRAND Grid Profiles When recessed pan fittings use Profile D Main Tee S Cross Tee M Cross Tee D Cross Tee
the top of the DONN tee bulb for DONN
support, use the same height CENTRICITEE
tee profiles for even support
38 38
15 15
DONN DX
38 38
32
25
24 24 24 24
Fittings occupying a full ceiling module e.g 1200 x 600 / 600 x 600 etc. locate on the bulb of the tee or sit inside the tee and rest
on the flange. With either method a positive fixing to the grid is recommended for safety reasons. This is required by the NZ
Standard NZS 4219 (see over). For Australia ref. AS2946 for interface compatibility.
1 © 2011
Construction Details
Lighting Installation
Ceiling Panel Mounted Fittings Light fittings mounted through USG acoustical ceiling panels shall not rely on the ceiling panel for support. Their weight shall be
transferred back to the grid by:
Side End
a) Simple supports across Elevation Elevation
the back of the ceiling panel
Common Recessed This table is intended as a general guide only. All products may not be available in all areas. Local manufacturers may also
Luminaire Options provide compatible options. For full luminaire details and options, contact the nearest Lighting Company office.
*These options may be used with DONN Centricitee when used in conjunction with a 3.5mm prismatic diffuser.
TIP: When specifying lighting, ensure the grid type is clearly identified in the lighting section
e.g. DONN Centricitee 15mm exposed grid
DONN DX 24mm exposed grid.
Standards Australia - AS2946 - 1991 Suspended Ceilings, Recessed Luminaires and Air Diffusers - Interface Requirements for Physical
Compatibility. This standard details primarily the dimensional limitations and how they suit different ceiling grid system types.
New Zealand - NZS 4219 - 2009 Specification for Seismic Resistance of Engineering Systems in Buildings. This standard
covers building services in close proximity, attached to, or passing through suspended ceilings. Relevant clauses pertaining to
lighting are paraphrased below:
2.24 Electrical reticulation shall be independently supported, or allowance shall be made for relative building or ceiling
movement.
2.25.2 All luminaires shall be positively clamped or fixed to the ceiling grid system.
2.25.3 All luminaires weighing greater than 10kg shall have two supports from the structure above. Each support shall be
capable of supporting the full luminaire’s weight.
2.25.4 Surface mounted luminaires shall be fixed to the ceiling grid with at least two fixtures that completely surround the tee.
2.29.1 All ceiling suspended services including luminaires not exceeding 10kg in weight, shall be positively secured to the
ceiling grid, or to the structure above, but not supported by the ceiling panels or tiles. Separate equipment supports
are not necessary if the equipment is adequately fastened to the grid, and the grid has been specifically designed to
withstand both the gravity and seismic loading from the equipment.
The contents of this section have been compiled in good faith based on current industry information at time of printing. Whilst
USG Interiors has taken all care to ensure accuracy, it cannot be held liable for information that is: inappropriate for its application;
changed after publication or availability of all products in all areas.
For additional help contact your nearest Lighting Company office or USG Interiors.
© 2011
1
System Components
Construction Details Transition to a
Plasterboard Ceiling
The Donn® DX® and CENTRICITEE® acoustical suspension systems are totally compatible with our new USG Drywall
Grid Suspension System making it easy to transition between flat drywall and acoustical ceilings.
Flush or offset transitions are possible. Additional cross tees are necessary at drywall edge to provide adequate support
(as shown on plan view).
hanger
drywall acoustical
cross tees acoustical lay-in panel
cross tees
C
19 acoustical
main tee
drywall main tee
D
acoustical 19/20
main tee
gypsum panel
acoustical ceiling
drywall ceiling
line of drywall
extra 1200mm
drywall cross
tees (gypsum
panel support) ø
1 © 2011
(by others)
drywall
main tee
C
Construction Details
19
drywall bead
(by others)
drywall bead
drywall acoustical (by others) gypsum panel
gypsum panel
main tee panel acoustical ceiling drywall ceiling
C D
19 19
hanger
drywall acoustical hangers hanger
main tee main tee
channel
50 mm 50 mm cross tee molding main tee channel molding tee
acoustical
acoustical panel
38 mm gypsum panel drywall bead acoustical gypsum panel
panel
15 mm or panel gypsum panel
24 mm
C alt D alt D alt2
19 19 19
acoustical
cross tee
drywall
QRC slot for drywall cross tee square edge
cross tee acoustical panel
DG - DX
10/13mm gypsum panel acoustical
transition clip
© 2011
1
Construction Details
Transition to a
Plasterboard Ceiling
Main Tee Direction - keep acoustical and drywall main tees in line
Option 1
FASTEN TO MAIN TEE TO PREVENT
MOVEMENT IF REQUIRED
MT / CT converter flush MT / CT
transition converter
clip
ACOUSTICAL
MAIN TEE
-4 #4
CONVERTER
-4 #4
CONVERTER SQUARE EDGE
ACOUSTICAL PANEL
additional cross tee for 10/13mm Donn acoustical square edge
gypsum panel support gypsum board main tee at acoustical panel
ADDITIONAL transition junction
$'