Questionnaire For Quantity Surveyor
Questionnaire For Quantity Surveyor
Questionnaire For Quantity Surveyor
Q1 Are you conversant with FIDIC form of contract and ‘CESMM3’ (Civil
Engineering Standard Method of Measurements).
Note: The candidate is not likely to be conversant with CESMM3 since in India,
this document is not used anywhere. If his answer is yes, then he can be
asked to quote the names of some of the section of the CESMM3, such as
If the candidate conveys his ignorance about CESMM3 but states that he has
knowledge of FIDIC, then we can proceed with Q2 to Q30 below. If he conveys
his ignorance about CESMM3 as well as FIDIC, then proceeding with the
interview may not be of any use.
Questionnaire – Page 1 of 6
Q5. What do you understand by a Defect Liability Certificate.
A5. This is the certificate that is issued at end of the Defect Liability
Period, once the contractor has completed all the snags and
outstanding works in the contract.
Q9. What are the events which fall under employer’s risk in respect of damage
to works?
A9. The employer’s risks are;
(a) War, revolution, civil war
(b) Damage from radioactive or nuclear radiations
(c) Damage from pressure waves of supersonic aircrafts
(d) Acts of God
(e) Damage due to occupation of the works by employer
(f) Damage due to design of works by employer
Questionnaire – Page 2 of 6
A draft Final Statement is to be submitted by the contractor within 56
days of the issuance of the Defect Liability Certificate and shall
include the value of all the works done + value of all the claims.
Upon agreement of the draft Final Statement value between the
contractor and engineer, the contractor shall submit the Final
Statement.
Q12. What is the difference between the function of a Bill of Quantities in a Re-
measurement Contract and a Lump Sum Contract.
A12. The Bill of Quantities is considered a Bill of approximate quantities
in re-measurement contract, and the final value of the works is
ascertained based on the actual final re-measured quantities using
the rates from the Bill of Quantities.
Q13. What is the authority of the engineer to instruct a variation in the contract.,
i.e. what kind of variation can be ordered by the Engineer and under which
clause.
A13. The engineer can instruct the variation under clause 51.1 for the
following items.
Questionnaire – Page 3 of 6
(c) If BOQ does not contain any similar item, then a suitable rate is to
be agreed between the engineer and the contractor.
(d) Failing above, the Engineer shall fix the rate
Q17. Give some examples of the clauses in the FIDIC, which can form the
basis of a claim.
A17. (a) Clause 6.3 Delay in issuance of the drawings by engineer.
(b) Clause 12.2 Adverse physical conditions
(c) Clause 20.3 Loss or damage due to employer’s risk
(d) Clause 36.5 Additional test
(e) Clause 40 Suspension of works
Q18 What clause deals with Extension of Time in the contract and what are the
grounds based on which the contractor may request for an extension of
time
A18. The clause 44 deals with the extension of time. The grounds for
requesting an extension of time are as follows.
Questionnaire – Page 4 of 6
(b) Head office overheads based on the head office overheads %age
quoted by the contractor in the BOQ or as substantiated by the
contractor on actual.
Q20. What is the remedy in the contract, if the contractor disagrees with the
engineer on any of the matter?
A20. Arbitration under clause 67
Q21 What rate should be paid for material on site? Invoice rate or the rate
worked out from material %breakdown of BOQ rate.
A21. Lesser of the two.
Q23 What is the command for calculating an area of a closed figure in Autocad.
A23. Enquiry-----Area-----click the end points or the boundary of the
figure.
Questionnaire – Page 5 of 6
Q27. Draw a typical sketch for a pier showing the pile cap and piling
Q28 Draw a typical sketch for a bridge deck showing the post tensioning
strands
Q30. Are you conversant with CPM method of networked programs. What do
you understand by critical path and float.
A30. Critical path is the path in a program along which the float is the
least
(Or 0). Float is the time which can be defined as the (Late Start - Early
Start) or (Late finish – Early Finish)
Questionnaire – Page 6 of 6