1 Brick masonry in superstructure with CM (1:6) prop: using traditional bricks from approved quarry including Cost and Conveyance of all
materials like cement, sand, bricks, water etc., to site, including materials, all operational, incidental and labour charges such as mixing
cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
2 Ornamental plastering to ceiling 12mm thick in CM (1:3) with dubara sponge finish including Cost and Conveyance of all materials like cement,
sand, water etc., to site, including other taxes on all materials, all operational, incidental and labour charges such as mixing mortar,
finishing, scaffolding, lift charges, including cutting of Grooves wherever necessary as directed by Engineer-in-charge, curing, etc., complete
for finished item of work.(APSS 901& 903 )
3 Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20mm thick (average) mixed with water proofing compound
manufactured by reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement, laid over roof slab when it is green, finished
smooth with a floating coat of neat cement and thread lining at regular intervals of 45cmx45cm including Cost and Conveyance of all materials
like cement, sand, water proofing compound, water etc., to site, on all materials, all operational, incidental and labour charges such as
mixing mortar, laying, rounding off at junctions of wall and slab, rendering smooth with thread lining, curing, lift charges, etc., complete for
finished item of work (APSS No. 901 & 903)
4 Plastering 12mm thick double coat in CM (1:6) 8mm thick base coat and top coat CM(1:4) of 4mm thick with dubara sponge finish including c/c
of all materials like cement, sand,water etc., to site, other taxes on all materials, all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer-in-charge, finishing, curing,
etc., complete for finished item of work. (APSS 901,903 & 904) - Internal Walls
5 Plastering 12mm thick double coat in CM (1:5) 8 mm thick base coat and CM (1:3) of 4mm thick top coat with dubara sponge finish including c/c
of all materials like cement, sand,water etc., to site, other taxes on all materials, all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer-in-charge, finishing, curing,
etc., complete for for finished item of work. (APSS 901,903 & 904) - External Walls
13 Supply and fixing of Country Wood Door Double shutter fully pannlled door of size 1.05 x 2.10mt with frame made of well seasonedCountry
Woodscantlings of size 100 x 75mm mm and shutter made of side rails 125mm X38, top rail 125mmX38mm, bottom rail 125mmX38mm and
intermediate rails of 125 x 38 mm and panels - 8 no's are of 25mm thick as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300
mm long aluminium aldrop-1 no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no, 150mm long Tower bolts - 1no's alumium,
200mm long Tower bolts - 1no's alumium,Aluminium fancy handles 150mm long 1no's, with necessary screws complete including cost and
conveyance of all materials and labour charges etc. complete as per specifications (APSS NO.1001 & 1002)
16 Supply and fixing of Window size 1.50 x 1.35 mt withCountry Woodframe of size 75x100mm and S/F of 4Nos. MS Hold fasts, incl. all labour
charges such as making window frame only and fiXing 11 Nos. 16mm plain safety bars in to frame etc,
18 Supply and Fixing of 15-18mm thick Polished Shahabad stone slab (Tandur Blue Variety 1st quality) in Single piece with the edges flat nosed and
set over a CC Bed(1:5:10) 12mm thick, and fixing in position with neat cement paste including c/c of all materials like cement, sand, water,
stones etc. to site, and other taxes on all materials, all operational, incidental and labour charges such as dressing of stones to the required
sizes, mixing of cement mortar, fixing in position, curing, lift charges etc., complete for finished item of work for Risers (APSS No.701 & 707)
19 Skirting with 15 to 18mm thick polished shahbad stone 100mm height in CM (1:5) with
20 Whiting to new walls and ceiling in two coats with Surya cem or equavalent quality to give an even shade after throughly brushing the surface
to remove all loose powdered materials including c/c of all materials and water to site, & other taxes, all operational, incidental and labour
charges such as cleaning the surface, painting, curing etc., complete for finished item of work. (APSS No.901 & 908)
21 Painting to New walls with two coats of snowcem paints of approved brand and shade over base coat of appropriate distemper primer of
approved brand making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials,
including c/c of all materials, cost of brushes, water to site, etc., & other taxes, all operational, incidental and labour charges such as
scaffolding charges, lift charges, curing etc.,complete for finished item of work in all floors for external Walls.(APSS No. 911)
22 Painting to new wood work with two coats of ready mixed synthetic enamel paint first quality all shades over a base coat of wood primer
making three coats in all to give an even shade after thoroughly brushing the surface to remove all remains of loose powdered materials,
including c/c of all materials, site and other taxes, all operationa, incidental and labour charges etc., complete for finished item of work in all
flooring for external walls. (APSS No.1201,1207 &1212).
23 Electrical Work
24 Sanitory and water supply
The estimate is prepared with SSR 2014-15 and submitted for Technical sanction.
Sn Measurements Total
Description of item Nos. Qty Rate/Per
o Amount
L B D
1 2 3 4 5 6 7 8 9
1 Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 2m
in Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including
shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P,
labor charges etc., complete for finished item of work for Foundation of Building. (APSS No.
308)
For SBC 20 TN/sqm only
F1 Type
1 x 6 1.80 1.80 1.65 32.08
F2 Type
1 x 3 1.35 1.35 1.65 9.02
For long walls
(8.92-(1.35*0.50+1.80*1.5)) 1 x 2 5.55 0.60 0.60 3.99
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
72.69
Unskilled labour charges As Per RSSR 72.70 312.13 2269.00
Cum. 10cum
6.62
Page 5 of 245
6.62 4538.17 30055.00
Cum. Cum.
5.26
Cum. Cum.
4 Random Rubble stone masonry, in CM (1:6) prop: (Cement: Sand) using hard granite stones
from approved quarry including cost and conveyance of all materials like Granite stones,
cement, sand, water, etc., to site Excluding seigniorage charges,Including, Countryes &
other taxes on all materials, all operational, incidental, and labor charges such as cutting
stones to required size and shape, mixing of cement mortar, constructing masonry, curing
etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)
in GROUND FLOOR
Below Ground level
For long walls
(8.92-(0.30*2) 1 x 2 8.32 0.45 0.50 3.74
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.45 0.50 1.15
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.45 0.50 2.13
For Filling the Footing
pits upto RR Level 1 x 4 1.57 0.45 0.95 2.68
For Filling the Footing
pits upto RR Level 1 x 4 1.12 0.45 0.95 1.92
Steps
14.69
Cum.
Material charges including skilled and semi-skilled labour charges
14.69 3959.41 58164.00
5 Coursed Rubble stone masonry in CM (1:6) prop: (Cement: Sand) using hard granite stones
from approved quarry including cost and conveyance of all materials like Granite stones,
cement, sand, water, etc., to site Excluding seigniorage charges,Including, Countryes &
other taxes on all materials, all operational, incidental, and labor charges such as cutting
stones to required size and shape, mixing of cement mortar, constructing masonry, curing
etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)
in GROUND FLOOR
Above Ground level
For long walls
(8.92-(0.30*2) 1 x 2 8.32 0.45 0.30 2.25
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.45 0.30 0.69
Page 6 of 245
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.45 0.30 1.28
4.22
Material charges including skilled and semi-skilled labour charges
4.25 4301.00 18279.00
6 Vibrated reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403)
Total 7.83
Column C1 Type Including Sill level 4" rise 1 x 5 0.23 0.30 3.40 1.17
Column C2 TypeIncluding Sill level 4" rise 1 x 4 0.23 0.30 3.40 0.94
2.11
Or Say 2.81
Cum. PerCum.
D) Plinth beams
Total 4.02
Total 4.46
7 Plain reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403) for
LINTELS (G.F.)
Ground floor
0.50
8 Vibrated reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403) FOR
SUNSHADE 0.60 M WIDE.
For Ground floor
Page 8 of 245
9 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to (1:3:6)
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size HBG
(SS5) metal from from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, Excluding seigniorage charges,Including,
Countryes & other taxes on all materials, all operational, incidental and labour charges such
as mixing, laying, curing concrete, etc., complete for finished item of work for Bed Blocks
10 Brick Masonry in superstructure with CM (1:6) prop: using second class bricks from approved
source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of
all materials like cement, sand, bricks, water etc., to site, Excluding seigniorage
charges,Including, Countryes & other taxes on all materials, all operational, incidental and
labor charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
GROUND FLOOR
Back & fornt(8.92-0.23-0.50*0.30) 1 x 2 8.54 0.23 3.10 12.18
Page 9 of 245
11 Filling with useful available excavated earth (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating
each deposited layer by watering and ramming including all operational, incidental, labor
charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 &
310)
For Excavated Trenches
F1 Type
1 x 6 1.80 1.80 1.65 32.08
F2 Type
1 x 3 1.35 1.35 1.65 9.02
For long walls
(8.92-(1.35*0.50+1.80*1.5)) 1 x 2 5.55 0.60 0.60 3.99
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
72.69
72.69
70 % Excavated Earth 50.88 267.16 13594.00
Cum. Per Cum
12 Filling with carted gravel (excluding rock) in trenches, sides of foundations and basement
with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including all operational, incidental, labor charges, hire charges of T
& P etc., complete for finished item of work. (APSS NO. 309 & 310)
For Excavated Trenches
F1 Type
1 x 6 1.80 1.80 1.65 32.08
F2 Type
1 x 3 1.35 1.35 1.65 9.02
For long walls
(8.92-(1.35*0.50+1.80*1.5)) 1 x 2 5.55 0.60 0.60 3.99
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
13 Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20 mm
thick (average) mixed with water proofing compound manufactured by reputed
manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement, laid over roof slab
when it is green, finished smooth with a floating coat of neat cement and thread lining at
regular intervals of 45cmx45cm including cost and conveyance of all materials like cement,
sand, water proofing compound, water etc., to site, seigniorage charges, sales & other
taxes on all materials, all operational, incidental and labour charges such as mixing mortar,
laying, rounding off at junctions of wall and slab, rendering smooth with thread lining,
curing, lift charges, etc., complete for finished item of work (APSS No. 901 & 903).
Over the FF Slab (Qty as per Slab)
Qty Vide Item 6(f) 77.87
Page 10 of 245
For Septic tank Inside
1 x 1 7.68 0.23 1.76
14 Ornamental plastering to ceiling 12mm thick in CM (1:3) with dubara sponge finish including
cost and conveyance of all materials like cement, sand, water etc., to site, Excluding
seigniorage charges,Including, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing mortar, finishing, scaffolding, lift charges,
93.02
15 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of
4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials
like cement, sand, water etc., to site, seigniorage charges, Countryes & other taxes on all
materials, all operational, incidental and labor charges such as mixing mortar, scaffolding
charges, lift charges, including cutting of Grooves wherever necessary as directed by
Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904) For Internal walls
In side Area
In VO Room all Round
1 x 1 14.02 3.35 47.01
In Sarpanch Room all Round 1 x 1 14.02 3.35 47.01
In Corridor all Round 1 x 1 10.36 3.35 34.75
In Meeting hall all Round 1 x 1 24.54 3.35 82.27
In Toiltet Rooms
1 x 2 6.10 3.35 40.88
251.92
Deductiions
over doors D1
1 x 3 0.90 2.00 5.40
over doors D2
1 x 2 0.75 2.00 3.00
Page 11 of 245
over windows W
1 x 6 0.90 1.35 7.29
Ventilaters 1 x 3 0.75 0.60 1.35
17.04
234.88
16 Plastering 20 mm thick in two coats with base coat of 16 mm thick in CM (1:6) and top coat
of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all
materials like cement, sand, water etc., to site, seigniorage charges, Countryes & other
taxes on all materials, all operational, incidental and labor charges such as mixing mortar,
scaffolding charges, lift charges, including cutting of Grooves wherever necessary as
directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of
Wall for finished item of work. (APSS 901,903 & 904) For External walls
Out Side
Back side & Frontside
1 x 2 9.15 3.47 63.44
left & right side
1 x 2 8.50 3.47 58.97
17 Flooring with15-18 mm thick polished Shabad stones (Tandur Blue 1st.Variety) of size 0.457
M x 0.457M set over a base coat of CM (1:8), 12mm thick (joints of stone must be flushed)
over 100mm thick C.C. bed already laid only after it is properly cured, cleaned, moistered
and where necessary treated with neat cement slurry and jointed with neat cement paste
to full depth, including cost and conveyance of all materials like cement, sand, water,
flooring stones etc. to site, seigniorage charges, Countryes and other taxes on all materials,
all operational, incidental and labour charges such as dressing of flooring stones to the
required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete
for finished item of work.(APSS No.703 & 701) (GROUND FLOOR)
In VO Room
1 x 1 3.35 3.66 12.26
In Sarpanch Room 1 x 1 3.35 3.66 12.26
In Corridor 1 x 1 1.52 3.66 5.57
In Meeting hall 1 x 1 8.08 4.19 33.85
Door sills of D1
3 x 1 0.90 0.23 0.62
Door sills of D2
2 x 1 0.75 0.23 0.35
Door sills of D
1 x 1 1.50 0.23 0.35
65.26
Page 12 of 245
18 Providing Skirting to internal walls to 10 Cm height with 15-18 mm thick polished
Shahabad stone slab ( Tandur Blue Variety 1st quality) with length equal to flooring stones
set over a base coat of CM (1:5), 12mm thick and jointed with neat cement paste to full
depth (joints of stone should be flushed), including cost and conveyance of all materials like
cement, sand, water, flooring stones etc. to site, seigniorage charges, sales and other taxes
on all materials, all operational, incidental and labour charges such as dressing of flooring
stones to the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges
etc., complete for finished item of work.(APSS No.701 & 707)
In VO Room
1 x 1 14.02 0.10 1.40
In Sarpanch Room 1 x 1 14.02 0.10 1.40
In Corridor 1 x 1 10.36 0.10 1.04
In Meeting hall 1 x 1 24.54 0.10 2.45
Door sills of D
3 x 2 0.90 0.10 -0.54
Door sills of D1
2 x 2 0.75 0.10 -0.30
Door sills of D2
1 x 2 1.50 0.10 -0.30
5.15
19 Flooring with Ceramic Tiles of 7.3mm thick 1st. quality of any shade as approved by Engineer
- in - charge set over a base coat of CM (1:8), 12mm thick laid over flooring bed / V.R.C.C.
slab, with neat grey cement slurry of honey like consistency spread at the rate of 3.3 Kgs of
cement per Sq.m and jointed with neat white cement paste mixed with pigment of matching
shade including cost and conveyance of all materials like cement, sand, water, ceramic tiles
etc. to site, seigniorage charges, sales and other taxes on all materials, all operational,
incidental and labour charges such as mixing of cement mortar, laying, curing, lift charges
etc., complete for finished item of work.(APSS No.701 & 707)
In Toiltet Rooms
1 x 2 2.06 1.68 6.90
door sills
1 x 2 0.75 0.12 0.17
7.07
20 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as approved by
Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick and neat cement
paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment
of matching shade including cost and conveyance of all materials like cement, sand, water,
tiles, etc. to site, seigniorage charges, sales and other taxes on all materials, C921 such as
mixing of cement mortar, laying in position, curing, lift charges etc., complete for finished
item of work (APSS No.701 & 707)
Toilet rooms All round
(7+7+4+1.5)
1 x 1 5.94 1.22 7.25
7.25
20 Flush Pointing to RRS Masonry in CM(1:3) Prop: including cost and conveyance of all
materials like cement, sand, water etc., to site, Excluding seigniorage charges,Including,
Countryes & other taxes on all materials, all operational, incidental charges and labour
charges such as mixing mortar, finishing, curing, etc., complete for finished item of work.
(APSS 901,906)
Front & back side 1 x 2 9.15 0.75 13.73
Page 13 of 245
Left& right side 1 x 2 8.51 0.75 12.77
Deduct Steps 1 x 1 1.65 0.75 -1.24
25.26
21 Supply and fixing of salwood Door single shutter fully pannlled door of size .90 x 2.1mt
with frame made of well seasoned sal Wood scantlings of size 100 x 75mm and bottom
reeper of size 75x38mm and shutter made of side rails 125mm X38, top rail 125mmX38mm,
bottom rail 175mmX38mm and intermediate rails of 125 x 38 mm and panels - 4 no's are of
25mm thick as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long
aluminium aldrop-1 no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no,
150mm long Tower bolts - 1no's alumium, 200mm long Tower bolts - 1no's
alumium,Aluminium fancy handles 150mm long 1no's, with necessary screws complete
including cost and conveyance of all materials and labour charges etc. complete as per
specifications (APSS NO.1001 & 1002)
22 Supply and fixing of salwood Door single shutter fully pannlled door of size .75 x 2.1mt
with frame made of well seasoned teak Wood scantlings of size 100 x 75mm and bottom
reeper of size 75x38mm and shutter made of side rails 125mm X38, top rail 125mmX38mm,
bottom rail 125mmX38mm and intermediate rails of 125 x 38 mm and panels - 4 no's are of
25mm thick as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long
aluminium aldrop-1 no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no,
150mm long Tower bolts - 1no's alumium, 200mm long Tower bolts - 1no's
alumium,Aluminium fancy handles 150mm long 1no's, with necessary screws complete
including cost and conveyance of all materials and labour charges etc. complete as per
specifications (APSS NO.1001 & 1002)
23 Supply and fixing of Sal wood Door Double shutter fully pannlled door of size 1.50 x
2.10mt with frame made of well seasoned sal wood scantlings of size 100 x 75mm mm and
shutter made of side rails 125mm X38, top rail 125mmX38mm, bottom rail 125mmX38mm
and intermediate rails of 125 x 38 mm and panels - 8 no's are of 25mm thick as per
approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long aluminium aldrop-1
no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no, 150mm long Tower bolts
- 1no's alumium, 200mm long Tower bolts - 1no's alumium,Aluminium fancy handles
150mm long 1no's, with necessary screws complete including cost and conveyance of all
materials and labour charges etc. complete as per specifications (APSS NO.1001 & 1002)
24 Supply and fixing of Window size 0.90 x 1.35 mt with sal wood frame of size 75x100mm
along with II class teak wood three shutters made with styles& rails of 100mmx30mm thick
with 12mm prelaminated particle board both side laminated interior grade and S/F of 4Nos.
MS Hold fasts, 6Nos. MS tower bolts 100mm long. 6 Nos. MS Hinges 75mm long,2Nos MS
Handles 3 Nos window stays. incl. all labour charges such as making window frame & shetter
25 Manufacture supply and fixing of RCC Jali ventilators size 0.60 x 0.75 m in position of
including cost and conveyance of all materials and labour charges complete for finished item
of work.
Ventilaters 1 x 3 0.75 0.60 1.35
Page 14 of 245
Material charges including skilled and semi-skilled labour charges
1.35 355.00 479.00
26 Whiting to new walls and ceiling in two coats with Surya cem or equavalent quality to give
an even shade after thoroughly brushing the surface to remove all loose powdered materials
including cost and conveyance of all materials and water to site, Countryes & other taxes,
all operational, incidental and labour charges such as cleaning the surface, painting, curing
etc., complete for finished item of work for internal walls. (APSS No.901 & 908)
For Ceiling Portion 93.05
For Internal walls 234.90
327.95 or say 327.95 347.31 11390.00
27 Painting to New walls with two coats of snowcem paints of approved brand and shade over
base coat of appropriate distemper primer of approved brand making three coats in all to
give an even shade after thoroughly brushing the surface to remove all loose powdered
materials, including c/c of all materials, cost of brushes, water to site, etc., & other taxes,
all operational, incidental and labour charges such as scaffolding charges, lift charges,
curing etc.,complete for finished item of work in all floors for external Walls.(APSS No. 911)
For External walls 131.80
For Basement 25.30
157.10 or say 157.10 1638.50 25741.00
28 Painting to New wood work with two coats of ready mixed synthetic enamel paint first
quality all shades to give an even shade over base coat Primar with Luppam finishing after
thouroughky brushing the surface to remove all remains including cost and conveyance of
all materials to site, Countryes & other taxes, all operational, incidental and labour charges
etc., complete for finished item of work.(3 coats) (APSS No. 1201 & 1212).
over doors D 3'-0"x7'-0"
1 x 3 2.25 0.90 2.10 12.76
over doors D1 2'-6"x7'-0"
1 x 2 2.25 0.75 2.10 7.09
over doors D2 4'-0"x7'-0"
1 x 1 2.25 1.20 2.10 5.67
Window W 3'-0"x4'-6"
1 x 5 2.75 0.90 1.35 16.71
42.23
30 Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985)
of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in
position with cover blocks of approved size and binding wire of 20SWG, forming grills for
reinforcement work as per approved designs and drawings including cost and conveyance of
bars from approved sources to site of work, including cost and conveyance of binding wire,
cover blocks and all operational, incidental, and labour charges such as cutting, bending,
placing in position, tying etc., and Countryes & other taxes,on cost of all materials complete
for finished item of work (APSS No.126) in all floors.
For Footings 300.00
For Columns 600.00
For Plinth Beams 600.00
For Roof Beams 800.00
For Roof Salb 750.00
For Lintels and Chazza 100.00
3150.00
M.T Per MT
Electrical Work
Page 15 of 245
31 Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI MARK) concealed in Roof Slabs with
all required accessories including masonary work and labour charges etc., complete.
30.00 30.00 71.78 2153.00
Rmt Per Rm
32 Supplying and Fixing of 25mm dia 2.0 mm thick PVC Conduit pipe concealed in wall with all
required accessories including chiselling the wall whereever necessaty including masonary
work for Light,fan and separate plug point wiht T.W.Deep box including all labour charges
etc & complete.
30.00 30.00 88.20 2646.00
Rmt Per Rm
33 Wiring with 2 of 14/0.3mm (1.0 Sq.mm) Finolex P.V.C. insulated F.R. flexible copper cable
(ISI MARK) in existing pipe with 6A switch control and 3/2 pin sockets fixing on separate
board including all labour charges etc., complete.
1 x 1 20.00 20.00 455.97 9119.00
points Per Points
34 Supply and fixing of 6A 3 pin wall plug socket with 6A switch control on a common switch
board with earth continuity including wire leads, earth connections along with all labour
charges etc., complete.
1 x 1 2.00 2.00 131.30 263.00
nos Per Nos
35 Supply and fixing of 6A 5pin socket with switch in anodised GI box and front plate complete
with fixing accessories etc., including labour charges complete as required confirming to IS.
(independent)
1 x 1 2.00 2.00 245.80 492.00
nos Per Nos
36 Run of Mains: Supply & run of 2 of 1100V grade FRLS 2.5 Sq.mm & 1 run of 1.5 Sq.mm PVC
insulated Copper wires, in existing pipe including all accessories, labour charges complete
as required confirming to IS.
1.50 Sqm 1 x 1 30.00 30.00 42.13 1264.00
Rmt Per Rm
37 Supply and fixing of LAN outlet with anodised GI box of with front plate and plug in type
Networking socket.
1 x 1 2.00 2.00 0.00
nos Per Nos
38 Supply and fixing of Telephone outlet with anodised GI box with front plate and other
accessories.
1 x 1 2.00 2.00 0.00
nos Per Nos
39 Supply and fixing SPN Distribution board with IP-20 protection suitable for single phase Earth
Leakage Circute Braker (ELCB) / Residual Current Circute Braker (RCCB) / Double Pole (DP)
Isolator as incomer and 10kA SP MCBs as out going including internal connections and labour
charges for surface / flush mounting etc., complete.
1 x 1 1.00 1.00 3146.00 3146.00
No Per Nos
Page 16 of 245
41 Supply of 1200 mm (48") sweep 230V, A.C 50 Hz.Ceiling fan (ISI Mark) with 3 Blades and
double ball bearings with all standard accessories.
S/F Fans 1 x 1 4.00 4 1797.40 7190.00
Nos Per Nos
42 Supply and Transportation of 1x40W patty type tube light luminaire with copper choke,
starter etc., including 1No 40W tube etc., complete.
S/F Tubes 1 x 1 5.00 5 471.48 2357.00
Nos Per Nos
trap Hindware/Parryware/Neycer - ISI Mark 630x450 mm including cost and conveyance of all
44 Supplying and fixing TV shape mirror with plastic frame size 609.6 mm x 457 .2 mm
0.00 0.00
No Per Nos
45 S& F GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI
fittings including the cost of pipe & its fittings & labour charges complete 20mm
dia.
20MM dia 30.00 206.00 6180.00
Rm Per Rm
46 Prince/ Sudhakar make or equivalent quality PVC /SWR pipes & fittings ( as per ISI
47 Prince/ Sudhakar make or equivalent quality PVC /SWR pipes & fittings ( as per ISI
48 Supply,fixing of 110 mm deep PVC floor traps of self cleansing design with outlet
size of 75mm diameter of approved make, including making connection with PVC
soil/waste pipes using rubber gaskets and top shall be cover with removable CP
strainer, etc., complete 110mm deep PVC floor traps(101.6)
2.00 144.00 288.00
Nos Per Nos
51 Supply, and fixing of approved make Vent cowl above the Soil & waste pipes for
Page 17 of 245
Nos Per Nos
53 Supplying & fixing 150 mm x 100 mm SWG gully traps of ISI make conforming to ISI
651 & 4127 with C.I Grating & Constg. Brick masonry in CM 1:6 prop. Intermediate
chamber and fitted with 304.8 mm x 288.6mm (12"x9") C.I Frame and hinged cover.
2.00
568.00 1136.00
Per Nos
54 Providing & placing on Terrace polyethylene water storage tank with Double layer
approved brand & manufacture with cover and suitable locking arrangement &
making necessary holes for inlet & outlets and overflow pipes but without fittings &
base support for tanks.( From ssr rates sno 311)
500.00 6.00 3000.00
Lt Per Lt
55 Supplying, laying, jointing and testing 101.6 mm SWG SP-1 pipes of ISI make
conforming to ISI 651 & 4127 with airtight cement joints in CM 1:5:1 prop.including
excavation of trenches and socket pits in any soil (except rock requiring blasting)
56 Supply of SWG junctions (Ts& Ys) confirming to IS standereds with length of barrel
60 cm for 150x150
1 0.00
Nos Per Nos
#REF!
57 Seigniorage Charges 1 8926.00 8926.00
#REF!
Page 18 of 245
DETAIED CUM ABSTRACT ESTIMATE
Sn Measurements Total
Description of item Nos. Qty Rate/Per
o Amount
L B D
1 2 3 4 5 6 7 8 9
1 Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 2m
in Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including
shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P,
labor charges etc., complete for finished item of work for Foundation of Building. (APSS No.
308)
For SBC 20 TN/sqm only
F1 Type
1 x 7 1.80 1.80 1.65 37.42
F2 Type
1 x 5 1.35 1.35 1.65 15.04
For long walls
(12.80-(1.35*1.0+1.80*2)) 1 x 2 7.85 0.60 0.60 5.65
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
87.57
Cum. 10cum
For MGS Hall and Toilet (Deleted forwant of sanction) 1 x 1 3.66 8.05 0.08
6.83
Cum. Cum.
6.29
Cum. Cum.
4 Random Rubble stone masonry, in CM (1:6) prop: (Cement: Sand) using hard granite stones
from approved quarry including cost and conveyance of all materials like Granite stones,
cement, sand, water, etc., to site Excluding seigniorage charges,Including, Countryes &
other taxes on all materials, all operational, incidental, and labor charges such as cutting
stones to required size and shape, mixing of cement mortar, constructing masonry, curing
etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)
in GROUND FLOOR
Below Ground level
For long walls
(12.80-(1.35*1.0+1.80*2)) 1 x 2 7.85 0.45 0.50 3.53
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.45 0.50 1.15
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.45 0.50 2.13
For Filling the Footing
pits upto RR Level 1 x 5 1.57 0.45 0.95 3.36
For Filling the Footing
pits upto RR Level 1 x 5 1.12 0.45 0.95 2.39
Steps
18.70
Cum.
Page 20 of 245
5 Coursed Rubble stone masonry in CM (1:6) prop: (Cement: Sand) using hard granite stones
from approved quarry including cost and conveyance of all materials like Granite stones,
cement, sand, water, etc., to site Excluding seigniorage charges,Including, Countryes &
other taxes on all materials, all operational, incidental, and labor charges such as cutting
stones to required size and shape, mixing of cement mortar, constructing masonry, curing
etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)
in GROUND FLOOR
Above Ground level
For long Back walls(12.80-(0.30*2+1*.23) 1 x 2 11.97 0.45 0.30 3.23
7.84
6 Vibrated reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403)
Total 9.78
Column C1 Type Including Sill level 4" rise 1 x 7 0.23 0.30 3.40 1.64
Column C2 TypeIncluding Sill level 4" rise 1 x 5 0.23 0.30 3.40 1.17
2.81
Or Say 3.74
Cum. PerCum.
D) Plinth beams
Page 21 of 245
IPB for toilets 1 x 3 1.35 0.23 0.30 0.28
Total 6.09
Total 5.82
7 Plain reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403) for
LINTELS (G.F.)
Ground floor
0.50
Page 22 of 245
8 Vibrated reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403) FOR
SUNSHADE 0.60 M WIDE.
For Ground floor
9 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to (1:3:6)
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size HBG
(SS5) metal from from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, Excluding seigniorage charges,Including,
Countryes & other taxes on all materials, all operational, incidental and labour charges such
as mixing, laying, curing concrete, etc., complete for finished item of work for Bed Blocks
10 Brick Masonry in superstructure with CM (1:6) prop: using second class bricks from approved
source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of
all materials like cement, sand, bricks, water etc., to site, Excluding seigniorage
charges,Including, Countryes & other taxes on all materials, all operational, incidental and
labor charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
GROUND FLOOR
Back & fornt((8.92+.23-2*.30-1*.23) 1 x 2 8.32 0.23 3.10 11.86
Page 23 of 245
4 Doors D1 1 x 3 0.90 0.23 2.10 1.30
3 Doors D2 1 x 2 0.75 0.23 2.10 0.72
1 Doors D 1 x 1 1.50 0.23 2.10 0.72
8 over windows W 1 x 5 0.90 0.23 1.35 1.40
Ventilaters 1 x 2 0.75 0.23 0.60 0.21
Lintels On Door & Windows 0.50
Bed Blocks 0.35
5.20
Net quantity 42.43
orsay 42.45
Cum.
Material charges including skilled and semi-skilled labour charges 42.45 4926.34 209123.00
Cum. Per Cum
11 Filling with useful available excavated earth (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating
each deposited layer by watering and ramming including all operational, incidental, labor
charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 &
310)
For Excavated Trenches
F1 Type
1 x 7 1.80 1.80 1.65 37.42
F2 Type
1 x 5 1.35 1.35 1.65 15.04
For long walls
(12.80-(1.35*1.0+1.80*2)) 1 x 2 7.85 0.60 0.60 5.65
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
87.57
70 % Excavated Earth 61.30 267.16 16377.00
Cum. Per Cum
12 Filling with carted gravel (excluding rock) in trenches, sides of foundations and basement
with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including all operational, incidental, labor charges, hire charges of T
& P etc., complete for finished item of work. (APSS NO. 309 & 310)
For Excavated Trenches
F1 Type 1 x 7 1.80 1.80 1.65 37.42
F2 Type 1 x 5 1.35 1.35 1.65 15.04
For long walls
(12.80-(1.35*1.0+1.80*2)) 1 x 2 7.85 0.60 0.60 5.65
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
For Basement Filling
In rooms 1 x 1 12.58 8.05 0.60 60.74
124.24
Deductions
PCC (1:5:10)& PCC (1:4:8), 9.73
RR Masonory, 18.70
Footings ,pedastals, 11.24
Columns below Gl 1.89
Internal Plinth beams 6.09
47.65
Total Filling Qty required 124.24 - 47.65 76.59
Total available Excavated earth using 70%
Unskilled labour charges
76.59 - 61.30 15.29 444.09 6791.00
cum Per Cum
Page 24 of 245
13 Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20 mm
thick (average) mixed with water proofing compound manufactured by reputed
manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement, laid over roof slab
when it is green, finished smooth with a floating coat of neat cement and thread lining at
regular intervals of 45cmx45cm including cost and conveyance of all materials like cement,
sand, water proofing compound, water etc., to site, seigniorage charges, sales & other
taxes on all materials, all operational, incidental and labour charges such as mixing mortar,
laying, rounding off at junctions of wall and slab, rendering smooth with thread lining,
curing, lift charges, etc., complete for finished item of work (APSS No. 901 & 903).
Over the FF Slab (Qty as per Slab)
Qty Vide Item 6(f)
For Septic tank Inside
1 x 1 7.68 0.23 1.76
14 Ornamental plastering to ceiling 12mm thick in CM (1:3) with dubara sponge finish including
cost and conveyance of all materials like cement, sand, water etc., to site, Excluding
seigniorage charges,Including, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing mortar, finishing, scaffolding, lift charges,
91.98
Page 25 of 245
15 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of
4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials
like cement, sand, water etc., to site, seigniorage charges, Countryes & other taxes on all
materials, all operational, incidental and labor charges such as mixing mortar, scaffolding
charges, lift charges, including cutting of Grooves wherever necessary as directed by
Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904) For Internal walls
In side Area
In VO Room all Round
1 x 1 14.02 3.35 47.01
In Sarpanch Room all Round 1 x 1 14.02 3.35 47.01
In Corridor all Round 1 x 1 10.36 3.35 34.75
In Meeting hall all Round 1 x 1 24.54 3.35 82.27
In MGS hall all Round 1 x 1 23.16 3.35
In MGS hall Toilet wall 1 x 1 6.71 3.35
In Toiltet Rooms
1 x 2 6.10 3.35 40.88
251.92
Deductiions
doors D1
4 1 x 3 0.90 2.00 5.40
doors D2
3 1 x 2 0.75 2.00 3.00
doors D
1 1 x 1 1.50 2.40 3.60
windows W
8 1 x 5 0.90 1.35 6.08
3 Ventilaters 1 x 2 0.75 0.60 0.90
18.98
232.94
16 Plastering 20 mm thick in two coats with base coat of 16 mm thick in CM (1:6) and top coat
of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all
materials like cement, sand, water etc., to site, seigniorage charges, Countryes & other
taxes on all materials, all operational, incidental and labor charges such as mixing mortar,
scaffolding charges, lift charges, including cutting of Grooves wherever necessary as
directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of
Wall for finished item of work. (APSS 901,903 & 904) For External walls
Out Side
Back side & Frontside
1 x 2 9.15 3.47 63.44
left & right side
1 x 2 8.50 3.47 58.97
Page 26 of 245
17 Flooring with15-18 mm thick polished Shabad stones (Tandur Blue 1st.Variety) of size 0.457
M x 0.457M set over a base coat of CM (1:8), 12mm thick (joints of stone must be flushed)
over 100mm thick C.C. bed already laid only after it is properly cured, cleaned, moistered
and where necessary treated with neat cement slurry and jointed with neat cement paste
to full depth, including cost and conveyance of all materials like cement, sand, water,
flooring stones etc. to site, seigniorage charges, Countryes and other taxes on all materials,
all operational, incidental and labour charges such as dressing of flooring stones to the
required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete
for finished item of work.(APSS No.703 & 701) (GROUND FLOOR)
In VO Room
1 x 1 3.35 3.66 12.26
In Sarpanch Room 1 x 1 3.35 3.66 12.26
In Corridor 1 x 1 1.52 3.66 5.57
In Meeting hall 1 x 1 8.08 4.19 33.85
In MGS hall 1 x 1 7.92 3.66
Door sills of D1
4 3 x 1 0.90 0.23 0.62
Door sills of D2
3 3 x 1 0.75 0.23 0.52
Door sills of D
1 1 x 1 1.20 0.23 0.28
65.36
5.21
19 Flooring with Ceramic Tiles of 7.3mm thick 1st. quality of any shade as approved by Engineer
- in - charge set over a base coat of CM (1:8), 12mm thick laid over flooring bed / V.R.C.C.
slab, with neat grey cement slurry of honey like consistency spread at the rate of 3.3 Kgs of
cement per Sq.m and jointed with neat white cement paste mixed with pigment of matching
shade including cost and conveyance of all materials like cement, sand, water, ceramic tiles
etc. to site, seigniorage charges, sales and other taxes on all materials, all operational,
incidental and labour charges such as mixing of cement mortar, laying, curing, lift charges
etc., complete for finished item of work.(APSS No.701 & 707)
In Toiltet Rooms
1 x 2 2.06 1.68 6.90
In Toiltet Rooms of MGS
1 x 1 2.13 1.22
door sills
1 x 3 0.75 0.12 0.26
7.16
Page 27 of 245
orsay 7.20 9086.44 6542.00
20 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as approved by
Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick and neat cement
paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment
of matching shade including cost and conveyance of all materials like cement, sand, water,
tiles, etc. to site, seigniorage charges, sales and other taxes on all materials, C921 such as
mixing of cement mortar, laying in position, curing, lift charges etc., complete for finished
item of work (APSS No.701 & 707)
Toilet rooms All round
(7+7+4+1.5)
1 x 1 5.94 1.22 7.25
In Toiltet Rooms of MGS (6.75*2+5.5+3.5) 1 x 2 6.86 1.22
7.25
20 Flush Pointing to RRS Masonry in CM(1:3) Prop: including cost and conveyance of all
materials like cement, sand, water etc., to site, Excluding seigniorage charges,Including,
Countryes & other taxes on all materials, all operational, incidental charges and labour
charges such as mixing mortar, finishing, curing, etc., complete for finished item of work.
(APSS 901,906)
Front & back side 1 x 2 9.14 0.75 13.72
Left& right side 1 x 2 8.51 0.75 12.77
Deduct Steps 1 x 1 1.65 0.75
Deduct Steps 1 x 1 2.25 0.75 -1.69
24.80
21 Supply and fixing of CountryDoor single shutter fully pannlled door of size .90 x 2.1mt with
frame made of well seasoned Countryscantlings of size 100 x 75mm and bottom reeper of
size 75x38mm and shutter made of side rails 125mm X38, top rail 125mmX38mm, bottom rail
175mmX38mm and intermediate rails of 125 x 38 mm and panels - 4 no's are of 25mm thick
as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long aluminium
aldrop-1 no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no, 150mm long
Tower bolts - 1no's alumium, 200mm long Tower bolts - 1no's alumium,Aluminium fancy
handles 150mm long 1no's, with necessary screws complete including cost and conveyance
of all materials and labour charges etc. complete as per specifications (APSS NO.1001 &
1002)
3.00 1991.20 5974.00
Nos Per Each
22 Supply and fixing of CountryDoor single shutter fully pannlled door of size .75 x 2.1mt with
frame made of well seasoned teak Wood scantlings of size 100 x 75mm and bottom reeper of
size 75x38mm and shutter made of side rails 125mm X38, top rail 125mmX38mm, bottom rail
125mmX38mm and intermediate rails of 125 x 38 mm and panels - 4 no's are of 25mm thick
as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long aluminium
aldrop-1 no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no, 150mm long
Tower bolts - 1no's alumium, 200mm long Tower bolts - 1no's alumium,Aluminium fancy
handles 150mm long 1no's, with necessary screws complete including cost and conveyance
of all materials and labour charges etc. complete as per specifications (APSS NO.1001 &
1002)
over doors D1 2'-6"x7'-0"
1 x 3 2.00 1938.83 3878.00
Page 28 of 245
Nos Per Each
23 Supply and fixing of Country Door Double shutter fully pannlled door of size 1.50 x 2.10mt
with frame made of well seasoned Countryscantlings of size 100 x 75mm mm and shutter
made of side rails 125mm X38, top rail 125mmX38mm, bottom rail 125mmX38mm and
intermediate rails of 125 x 38 mm and panels - 8 no's are of 25mm thick as per approved
design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long aluminium aldrop-1 no,125mm
long aluminium butt hinges 4 No's, Door stoppers-1 no, 150mm long Tower bolts - 1no's
alumium, 200mm long Tower bolts - 1no's alumium,Aluminium fancy handles 150mm long
1no's, with necessary screws complete including cost and conveyance of all materials and
labour charges etc. complete as per specifications (APSS NO.1001 & 1002)
24 Supply and fixing of Window size 0.90 x 1.35 mt with Countryframe of size 75x100mm along
with II class teak wood three shutters made with styles& rails of 100mmx30mm thick with
12mm prelaminated particle board both side laminated interior grade and S/F of 4Nos. MS
Hold fasts, 6Nos. MS tower bolts 100mm long. 6 Nos. MS Hinges 75mm long,2Nos MS Handles
3 Nos window stays. incl. all labour charges such as making window frame & shetter and
25 Manufacture supply and fixing of RCC Jali ventilators size 0.60 x 0.75 m in position of
including cost and conveyance of all materials and labour charges complete for finished item
of work.
Ventilaters 1 x 2 0.75 0.60 0.90
Material charges including skilled and semi-skilled labour charges
0.90 355.00 320.00
26 Whiting to new walls and ceiling in two coats with Surya cem or equavalent quality to give
an even shade after thoroughly brushing the surface to remove all loose powdered materials
including cost and conveyance of all materials and water to site, Countryes & other taxes,
all operational, incidental and labour charges such as cleaning the surface, painting, curing
etc., complete for finished item of work for internal walls. (APSS No.901 & 908)
For Ceiling Portion 92.00
For Internal walls 232.95
324.95 or say 324.95 347.31 11286.00
28 Painting to New wood work with two coats of ready mixed synthetic enamel paint first
quality all shades to give an even shade over base coat Primar with Luppam finishing after
thouroughky brushing the surface to remove all remains including cost and conveyance of
all materials to site, Countryes & other taxes, all operational, incidental and labour charges
etc., complete for finished item of work.(3 coats) (APSS No. 1201 & 1212).
over doors D 3'-0"x7'-0"
4 0.33 x 3 2.25 0.90 2.10 4.21
over doors D1 2'-6"x7'-0"
3 0.33 x 2 2.25 0.75 2.10 2.34
over doors D2 4'-0"x7'-0"
1 0.33 x 1 2.25 1.20 2.10 1.87
Window W 3'-0"x4'-6"
8 0.33 x 5 2.75 0.90 1.35 5.51
13.93
Page 29 of 245
or say 13.95 1021.60 1425.00
29 Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985)
of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in
position with cover blocks of approved size and binding wire of 20SWG, forming grills for
reinforcement work as per approved designs and drawings including cost and conveyance of
bars from approved sources to site of work, including cost and conveyance of binding wire,
cover blocks and all operational, incidental, and labour charges such as cutting, bending,
placing in position, tying etc., and Countryes & other taxes,on cost of all materials complete
for finished item of work (APSS No.126) in all floors.
For Footings 375.00
For Columns 820.00
For Plinth Beams 760.00
For Roof Beams 900.00
For Roof Salb 1000.00
For Lintels and Chazza 200.00
4055.00
M.T Per MT
Electrical Work
30 Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI MARK) concealed in Roof Slabs with
all required accessories including masonary work and labour charges etc., complete.
50.00 50.00 71.78 3589.00
Rmt Per Rm
31 Supplying and Fixing of 25mm dia 2.0 mm thick PVC Conduit pipe concealed in wall with all
required accessories including chiselling the wall whereever necessaty including masonary
work for Light,fan and separate plug point wiht T.W.Deep box including all labour charges
etc & complete.
40.00 35.00 88.20 3087.00
Rmt Per Rm
32 Wiring with 2 of 14/0.3mm (1.0 Sq.mm) Finolex P.V.C. insulated F.R. flexible copper cable
(ISI MARK) in existing pipe with 6A switch control and 3/2 pin sockets fixing on separate
board including all labour charges etc., complete.
1 x 1 25.00 22.00 455.97 10031.00
points Per Points
33 Supply and fixing of 6A 3 pin wall plug socket with 6A switch control on a common switch
board with earth continuity including wire leads, earth connections along with all labour
charges etc., complete.
1 x 1 2.00 2.00 131.30 263.00
nos Per Nos
34 Supply and fixing of 6A 5pin socket with switch in anodised GI box and front plate complete
with fixing accessories etc., including labour charges complete as required confirming to IS.
(independent)
1 x 1 2.00 1.00 245.80 246.00
nos Per Nos
35 Run of Mains: Supply & run of 2 of 1100V grade FRLS 2.5 Sq.mm & 1 run of 1.5 Sq.mm PVC
insulated Copper wires, in existing pipe including all accessories, labour charges complete
as required confirming to IS.
1.50 Sqm 1 x 1 45.00 40.00 42.13 1685.00
Rmt Per Rm
36 Supply and fixing of LAN outlet with anodised GI box of with front plate and plug in type
Networking socket.
Page 30 of 245
1 x 1 2.00 2.00 0.00
nos Per Nos
37 Supply and fixing of Telephone outlet with anodised GI box with front plate and other
accessories.
1 x 1 2.00 2.00 0.00
nos Per Nos
38 Supply and fixing SPN Distribution board with IP-20 protection suitable for single phase Earth
Leakage Circute Braker (ELCB) / Residual Current Circute Braker (RCCB) / Double Pole (DP)
Isolator as incomer and 10kA SP MCBs as out going including internal connections and labour
charges for surface / flush mounting etc., complete.
1 x 1 1.00 1.00 3146.00 3146.00
No Per Nos
40 Supply of 1200 mm (48") sweep 230V, A.C 50 Hz.Ceiling fan (ISI Mark) with 3 Blades and
double ball bearings with all standard accessories.
S/F Fans 1 x 1 4.00 1797.40 0.00
Nos Per Nos
41 Supply and Transportation of 1x40W patty type tube light luminaire with copper choke,
starter etc., including 1No 40W tube etc., complete.
S/F Tubes 1 x 1 4.00 471.48 0.00
Nos Per Nos
trap Hindware/Parryware/Neycer - ISI Mark 630x450 mm including cost and conveyance of all
43 Supplying and fixing TV shape mirror with plastic frame size 609.6 mm x 457 .2 mm
0.00 0.00
No Per Nos
44 S& F GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI
fittings including the cost of pipe & its fittings & labour charges complete 20mm
dia.
20MM dia 30.00 206.00 6180.00
Rm Per Rm
45 Prince/ Sudhakar make or equivalent quality PVC /SWR pipes & fittings ( as per ISI
46 Prince/ Sudhakar make or equivalent quality PVC /SWR pipes & fittings ( as per ISI
Page 31 of 245
47 Supply,fixing of 110 mm deep PVC floor traps of self cleansing design with outlet
size of 75mm diameter of approved make, including making connection with PVC
soil/waste pipes using rubber gaskets and top shall be cover with removable CP
strainer, etc., complete 110mm deep PVC floor traps(101.6)
2.00 144.00 288.00
Nos Per Nos
50 Supply, and fixing of approved make Vent cowl above the Soil & waste pipes for
ventilation as required to avoid foul smell. 110mm
2.00 19.00 38.00
Nos Per Nos
52 Supplying & fixing 150 mm x 100 mm SWG gully traps of ISI make conforming to ISI
651 & 4127 with C.I Grating & Constg. Brick masonry in CM 1:6 prop. Intermediate
chamber and fitted with 304.8 mm x 288.6mm (12"x9") C.I Frame and hinged cover.
2.00
568.00 1136.00
Per Nos
53 Providing & placing on Terrace polyethylene water storage tank with Double layer
approved brand & manufacture with cover and suitable locking arrangement &
making necessary holes for inlet & outlets and overflow pipes but without fittings &
base support for tanks.( From ssr rates sno 311) 2000lts
500.00 6.00 3000.00
Lt Per Lt
54 Supplying, laying, jointing and testing 101.6 mm SWG SP-1 pipes of ISI make
conforming to ISI 651 & 4127 with airtight cement joints in CM 1:5:1 prop.including
excavation of trenches and socket pits in any soil (except rock requiring blasting)
55 Supply of SWG junctions (Ts& Ys) confirming to IS standereds with length of barrel
60 cm for 150x150
1 0.00
Nos Per Nos
1339206.00
56 Seigniorage Charges 1 9660.00 9660.00
Page 32 of 245
58 QC charges @ 0.5% 1 6696.00
1429218.00
Page 33 of 245
DETAIED CUM ABSTRACT ESTIMATE
Sn Measurements Total
Description of item Nos. Qty Rate/Per
o Amount
L B D
1 2 3 4 5 6 7 8 9
1 Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 2m
in Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including
shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P,
labor charges etc., complete for finished item of work for Foundation of Building. (APSS No.
308)
For SBC 20 TN/sqm only
F1 Type
1 x 7 1.80 1.80 1.65 37.42
F2 Type
1 x 5 1.35 1.35 1.65 15.04
For long walls
(12.80-(1.35*1.0+1.80*2)) 1 x 2 7.85 0.60 0.60 5.65
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
87.57
Cum. 10cum
For MGS Hall and Toilet (Deleted forwant of sanction) 1 x 1 3.66 8.05 0.08
6.83
Cum. Cum.
6.29
Cum. Cum.
4 Random Rubble stone masonry, in CM (1:6) prop: (Cement: Sand) using hard granite stones
from approved quarry including cost and conveyance of all materials like Granite stones,
cement, sand, water, etc., to site Excluding seigniorage charges,Including, Countryes &
other taxes on all materials, all operational, incidental, and labor charges such as cutting
stones to required size and shape, mixing of cement mortar, constructing masonry, curing
etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)
in GROUND FLOOR
Below Ground level
For long walls
(12.80-(1.35*1.0+1.80*2)) 1 x 2 7.85 0.45 0.50 3.53
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.45 0.50 1.15
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.45 0.50 2.13
For Filling the Footing
pits upto RR Level 1 x 5 1.57 0.45 0.95 3.36
For Filling the Footing
pits upto RR Level 1 x 5 1.12 0.45 0.95 2.39
Steps
18.70
Cum.
Page 35 of 245
5 Coursed Rubble stone masonry in CM (1:6) prop: (Cement: Sand) using hard granite stones
from approved quarry including cost and conveyance of all materials like Granite stones,
cement, sand, water, etc., to site Excluding seigniorage charges,Including, Countryes &
other taxes on all materials, all operational, incidental, and labor charges such as cutting
stones to required size and shape, mixing of cement mortar, constructing masonry, curing
etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)
in GROUND FLOOR
Above Ground level
For long Back walls(12.80-(0.30*2+1*.23) 1 x 2 11.97 0.45 0.30 3.23
7.84
6 Vibrated reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403)
Total 9.78
Column C1 Type Including Sill level 4" rise 1 x 7 0.23 0.30 3.40 1.64
Column C2 TypeIncluding Sill level 4" rise 1 x 5 0.23 0.30 3.40 1.17
2.81
Or Say 3.74
Cum. PerCum.
D) Plinth beams
Page 36 of 245
IPB for toilets 1 x 3 1.35 0.23 0.30 0.28
Total 6.09
Total 5.82
7 Plain reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403) for
LINTELS (G.F.)
Ground floor
0.50
Page 37 of 245
8 Vibrated reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size HBG
(SS5) machine crushed metal from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as centering, shuttering, scaffolding, lift charges,
machine mixing, laying concrete, vibrating, curing concrete etc, complete but excluding
cost of steel and its fabrication charges for finished item of work (APSS No.402 & 403) FOR
SUNSHADE 0.60 M WIDE.
For Ground floor
9 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to (1:3:6)
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size HBG
(SS5) metal from from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, Excluding seigniorage charges,Including,
Countryes & other taxes on all materials, all operational, incidental and labour charges such
as mixing, laying, curing concrete, etc., complete for finished item of work for Bed Blocks
10 Brick Masonry in superstructure with CM (1:6) prop: using second class bricks from approved
source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of
all materials like cement, sand, bricks, water etc., to site, Excluding seigniorage
charges,Including, Countryes & other taxes on all materials, all operational, incidental and
labor charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift
charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
GROUND FLOOR
Back & fornt((8.92+.23-2*.30-1*.23) 1 x 2 8.32 0.23 3.10 11.86
Page 38 of 245
4 Doors D1 1 x 3 0.90 0.23 2.10 1.30
3 Doors D2 1 x 2 0.75 0.23 2.10 0.72
1 Doors D 1 x 1 1.50 0.23 2.10 0.72
8 over windows W 1 x 5 0.90 0.23 1.35 1.40
Ventilaters 1 x 2 0.75 0.23 0.60 0.21
Lintels On Door & Windows 0.50
Bed Blocks 0.35
5.20
Net quantity 42.43
orsay 42.45
Cum.
Material charges including skilled and semi-skilled labour charges 42.45 4926.34 209123.00
Cum. Per Cum
11 Filling with useful available excavated earth (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating
each deposited layer by watering and ramming including all operational, incidental, labor
charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 &
310)
For Excavated Trenches
F1 Type
1 x 7 1.80 1.80 1.65 37.42
F2 Type
1 x 5 1.35 1.35 1.65 15.04
For long walls
(12.80-(1.35*1.0+1.80*2)) 1 x 2 7.85 0.60 0.60 5.65
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
87.57
70 % Excavated Earth 61.30 267.16 16377.00
Cum. Per Cum
12 Filling with carted gravel (excluding rock) in trenches, sides of foundations and basement
with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including all operational, incidental, labor charges, hire charges of T
& P etc., complete for finished item of work. (APSS NO. 309 & 310)
For Excavated Trenches
F1 Type 1 x 7 1.80 1.80 1.65 37.42
F2 Type 1 x 5 1.35 1.35 1.65 15.04
For long walls
(12.80-(1.35*1.0+1.80*2)) 1 x 2 7.85 0.60 0.60 5.65
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 5.13 0.60 0.62 1.89
For cross walls
(8.280-(1*1.80 +1.35) 1 x 1 9.48 0.60 0.62 3.50
For Basement Filling
In rooms 1 x 1 12.58 8.05 0.60 60.74
124.24
Deductions
PCC (1:5:10)& PCC (1:4:8), 9.73
RR Masonory, 18.70
Footings ,pedastals, 11.24
Columns below Gl 1.89
Internal Plinth beams 6.09
47.65
Total Filling Qty required 124.24 - 47.65 76.59
Total available Excavated earth using 70%
Unskilled labour charges
76.59 - 61.30 15.29 444.09 6791.00
cum Per Cum
Page 39 of 245
13 Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20 mm
thick (average) mixed with water proofing compound manufactured by reputed
manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement, laid over roof slab
when it is green, finished smooth with a floating coat of neat cement and thread lining at
regular intervals of 45cmx45cm including cost and conveyance of all materials like cement,
sand, water proofing compound, water etc., to site, seigniorage charges, sales & other
taxes on all materials, all operational, incidental and labour charges such as mixing mortar,
laying, rounding off at junctions of wall and slab, rendering smooth with thread lining,
curing, lift charges, etc., complete for finished item of work (APSS No. 901 & 903).
Over the FF Slab (Qty as per Slab)
Qty Vide Item 6(f) 110.89
For Septic tank Inside
1 x 1 7.68 0.23 1.76
14 Ornamental plastering to ceiling 12mm thick in CM (1:3) with dubara sponge finish including
cost and conveyance of all materials like cement, sand, water etc., to site, Excluding
seigniorage charges,Including, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing mortar, finishing, scaffolding, lift charges,
91.98
Page 40 of 245
15 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of
4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials
like cement, sand, water etc., to site, seigniorage charges, Countryes & other taxes on all
materials, all operational, incidental and labor charges such as mixing mortar, scaffolding
charges, lift charges, including cutting of Grooves wherever necessary as directed by
Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904) For Internal walls
In side Area
In VO Room all Round
1 x 1 14.02 3.35 47.01
In Sarpanch Room all Round 1 x 1 14.02 3.35 47.01
In Corridor all Round 1 x 1 10.36 3.35 34.75
In Meeting hall all Round 1 x 1 24.54 3.35 82.27
In MGS hall all Round 1 x 1 23.16 3.35
In MGS hall Toilet wall 1 x 1 6.71 3.35
In Toiltet Rooms
1 x 2 6.10 3.35 40.88
251.92
Deductiions
doors D1
4 1 x 3 0.90 2.00 5.40
doors D2
3 1 x 2 0.75 2.00 3.00
doors D
1 1 x 1 1.50 2.40 3.60
windows W
8 1 x 5 0.90 1.35 6.08
3 Ventilaters 1 x 2 0.75 0.60 0.90
18.98
232.94
16 Plastering 20 mm thick in two coats with base coat of 16 mm thick in CM (1:6) and top coat
of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all
materials like cement, sand, water etc., to site, seigniorage charges, Countryes & other
taxes on all materials, all operational, incidental and labor charges such as mixing mortar,
scaffolding charges, lift charges, including cutting of Grooves wherever necessary as
directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of
Wall for finished item of work. (APSS 901,903 & 904) For External walls
Out Side
Back side & Frontside
1 x 2 9.15 3.47 63.44
left & right side
1 x 2 8.50 3.47 58.97
Page 41 of 245
17 Flooring with15-18 mm thick polished Shabad stones (Tandur Blue 1st.Variety) of size 0.457
M x 0.457M set over a base coat of CM (1:8), 12mm thick (joints of stone must be flushed)
over 100mm thick C.C. bed already laid only after it is properly cured, cleaned, moistered
and where necessary treated with neat cement slurry and jointed with neat cement paste
to full depth, including cost and conveyance of all materials like cement, sand, water,
flooring stones etc. to site, seigniorage charges, Countryes and other taxes on all materials,
all operational, incidental and labour charges such as dressing of flooring stones to the
required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete
for finished item of work.(APSS No.703 & 701) (GROUND FLOOR)
In VO Room
1 x 1 3.35 3.66 12.26
In Sarpanch Room 1 x 1 3.35 3.66 12.26
In Corridor 1 x 1 1.52 3.66 5.57
In Meeting hall 1 x 1 8.08 4.19 33.85
In MGS hall 1 x 1 7.92 3.66
Door sills of D1
4 3 x 1 0.90 0.23 0.62
Door sills of D2
3 3 x 1 0.75 0.23 0.52
Door sills of D
1 1 x 1 1.20 0.23 0.28
65.36
5.21
19 Flooring with Ceramic Tiles of 7.3mm thick 1st. quality of any shade as approved by Engineer
- in - charge set over a base coat of CM (1:8), 12mm thick laid over flooring bed / V.R.C.C.
slab, with neat grey cement slurry of honey like consistency spread at the rate of 3.3 Kgs of
cement per Sq.m and jointed with neat white cement paste mixed with pigment of matching
shade including cost and conveyance of all materials like cement, sand, water, ceramic tiles
etc. to site, seigniorage charges, sales and other taxes on all materials, all operational,
incidental and labour charges such as mixing of cement mortar, laying, curing, lift charges
etc., complete for finished item of work.(APSS No.701 & 707)
In Toiltet Rooms
1 x 2 2.06 1.68 6.90
In Toiltet Rooms of MGS
1 x 1 2.13 1.22
door sills
1 x 3 0.75 0.12 0.26
7.16
Page 42 of 245
orsay 7.20 9086.44 6542.00
20 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as approved by
Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick and neat cement
paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment
of matching shade including cost and conveyance of all materials like cement, sand, water,
tiles, etc. to site, seigniorage charges, sales and other taxes on all materials, C921 such as
mixing of cement mortar, laying in position, curing, lift charges etc., complete for finished
item of work (APSS No.701 & 707)
Toilet rooms All round
(7+7+4+1.5)
1 x 1 5.94 1.22 7.25
In Toiltet Rooms of MGS (6.75*2+5.5+3.5) 1 x 2 6.86 1.22
7.25
20 Flush Pointing to RRS Masonry in CM(1:3) Prop: including cost and conveyance of all
materials like cement, sand, water etc., to site, Excluding seigniorage charges,Including,
Countryes & other taxes on all materials, all operational, incidental charges and labour
charges such as mixing mortar, finishing, curing, etc., complete for finished item of work.
(APSS 901,906)
Front & back side 1 x 2 9.14 0.75 13.72
Left& right side 1 x 2 8.51 0.75 12.77
Deduct Steps 1 x 1 1.65 0.75
Deduct Steps 1 x 1 2.25 0.75 -1.69
24.80
21 Supply and fixing of salwood Door single shutter fully pannlled door of size .90 x 2.1mt
with frame made of well seasoned sal Wood scantlings of size 100 x 75mm and bottom
reeper of size 75x38mm and shutter made of side rails 125mm X38, top rail 125mmX38mm,
bottom rail 175mmX38mm and intermediate rails of 125 x 38 mm and panels - 4 no's are of
25mm thick as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long
aluminium aldrop-1 no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no,
150mm long Tower bolts - 1no's alumium, 200mm long Tower bolts - 1no's
alumium,Aluminium fancy handles 150mm long 1no's, with necessary screws complete
including cost and conveyance of all materials and labour charges etc. complete as per
specifications (APSS NO.1001 & 1002)
22 Supply and fixing of salwood Door single shutter fully pannlled door of size .75 x 2.1mt
with frame made of well seasoned teak Wood scantlings of size 100 x 75mm and bottom
reeper of size 75x38mm and shutter made of side rails 125mm X38, top rail 125mmX38mm,
bottom rail 125mmX38mm and intermediate rails of 125 x 38 mm and panels - 4 no's are of
25mm thick as per approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long
aluminium aldrop-1 no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no,
150mm long Tower bolts - 1no's alumium, 200mm long Tower bolts - 1no's
alumium,Aluminium fancy handles 150mm long 1no's, with necessary screws complete
including cost and conveyance of all materials and labour charges etc. complete as per
specifications (APSS NO.1001 & 1002)
Page 43 of 245
Nos Per Each
23 Supply and fixing of Sal wood Door Double shutter fully pannlled door of size 1.50 x
2.10mt with frame made of well seasoned sal wood scantlings of size 100 x 75mm mm and
shutter made of side rails 125mm X38, top rail 125mmX38mm, bottom rail 125mmX38mm
and intermediate rails of 125 x 38 mm and panels - 8 no's are of 25mm thick as per
approved design with fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long aluminium aldrop-1
no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no, 150mm long Tower bolts
- 1no's alumium, 200mm long Tower bolts - 1no's alumium,Aluminium fancy handles
150mm long 1no's, with necessary screws complete including cost and conveyance of all
materials and labour charges etc. complete as per specifications (APSS NO.1001 & 1002)
24 Supply and fixing of Window size 0.90 x 1.35 mt with sal wood frame of size 75x100mm
along with II class teak wood three shutters made with styles& rails of 100mmx30mm thick
with 12mm prelaminated particle board both side laminated interior grade and S/F of 4Nos.
MS Hold fasts, 6Nos. MS tower bolts 100mm long. 6 Nos. MS Hinges 75mm long,2Nos MS
Handles 3 Nos window stays. incl. all labour charges such as making window frame & shetter
25 Manufacture supply and fixing of RCC Jali ventilators size 0.60 x 0.75 m in position of
including cost and conveyance of all materials and labour charges complete for finished item
of work.
Ventilaters 1 x 2 0.75 0.60 0.90
Material charges including skilled and semi-skilled labour charges
0.90 355.00 320.00
26 Whiting to new walls and ceiling in two coats with Surya cem or equavalent quality to give
an even shade after thoroughly brushing the surface to remove all loose powdered materials
including cost and conveyance of all materials and water to site, Countryes & other taxes,
all operational, incidental and labour charges such as cleaning the surface, painting, curing
etc., complete for finished item of work for internal walls. (APSS No.901 & 908)
For Ceiling Portion 92.00
For Internal walls 232.95
324.95 or say 324.95 347.31 11286.00
27 Painting to New walls with two coats of snowcem paints of approved brand and shade over
base coat of appropriate distemper primer of approved brand making three coats in all to
give an even shade after thoroughly brushing the surface to remove all loose powdered
materials, including c/c of all materials, cost of brushes, water to site, etc., & other taxes,
all operational, incidental and labour charges such as scaffolding charges, lift charges,
curing etc.,complete for finished item of work in all floors for external Walls.(APSS No. 911)
For External walls 141.15
For Basement 24.80
165.95 or say 165.95 1638.50 27191.00
28 Painting to New wood work with two coats of ready mixed synthetic enamel paint first
quality all shades to give an even shade over base coat Primar with Luppam finishing after
thouroughky brushing the surface to remove all remains including cost and conveyance of
all materials to site, Countryes & other taxes, all operational, incidental and labour charges
etc., complete for finished item of work.(3 coats) (APSS No. 1201 & 1212).
Page 44 of 245
over doors D 3'-0"x7'-0"
4 1 x 3 2.25 0.90 2.10 12.76
over doors D1 2'-6"x7'-0"
3 1 x 2 2.25 0.75 2.10 7.09
over doors D2 4'-0"x7'-0"
1 1 x 1 2.25 1.20 2.10 5.67
Window W 3'-0"x4'-6"
8 1 x 5 2.75 0.90 1.35 16.71
42.23
29 Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985)
of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in
position with cover blocks of approved size and binding wire of 20SWG, forming grills for
reinforcement work as per approved designs and drawings including cost and conveyance of
bars from approved sources to site of work, including cost and conveyance of binding wire,
cover blocks and all operational, incidental, and labour charges such as cutting, bending,
placing in position, tying etc., and Countryes & other taxes,on cost of all materials complete
for finished item of work (APSS No.126) in all floors.
For Footings 375.00
For Columns 820.00
For Plinth Beams 760.00
For Roof Beams 900.00
For Roof Salb 1000.00
For Lintels and Chazza 200.00
4055.00
M.T Per MT
Electrical Work
30 Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI MARK) concealed in Roof Slabs with
all required accessories including masonary work and labour charges etc., complete.
50.00 50.00 71.78 3589.00
Rmt Per Rm
31 Supplying and Fixing of 25mm dia 2.0 mm thick PVC Conduit pipe concealed in wall with all
required accessories including chiselling the wall whereever necessaty including masonary
work for Light,fan and separate plug point wiht T.W.Deep box including all labour charges
etc & complete.
40.00 35.00 88.20 3087.00
Rmt Per Rm
32 Wiring with 2 of 14/0.3mm (1.0 Sq.mm) Finolex P.V.C. insulated F.R. flexible copper cable
(ISI MARK) in existing pipe with 6A switch control and 3/2 pin sockets fixing on separate
board including all labour charges etc., complete.
1 x 1 25.00 22.00 455.97 10031.00
points Per Points
33 Supply and fixing of 6A 3 pin wall plug socket with 6A switch control on a common switch
board with earth continuity including wire leads, earth connections along with all labour
charges etc., complete.
1 x 1 2.00 2.00 131.30 263.00
nos Per Nos
34 Supply and fixing of 6A 5pin socket with switch in anodised GI box and front plate complete
with fixing accessories etc., including labour charges complete as required confirming to IS.
(independent)
1 x 1 2.00 1.00 245.80 246.00
nos Per Nos
35 Run of Mains: Supply & run of 2 of 1100V grade FRLS 2.5 Sq.mm & 1 run of 1.5 Sq.mm PVC
insulated Copper wires, in existing pipe including all accessories, labour charges complete
as required confirming to IS.
1.50 Sqm 1 x 1 45.00 40.00 42.13 1685.00
Page 45 of 245
Rmt Per Rm
36 Supply and fixing of LAN outlet with anodised GI box of with front plate and plug in type
Networking socket.
1 x 1 2.00 2.00 0.00
nos Per Nos
37 Supply and fixing of Telephone outlet with anodised GI box with front plate and other
accessories.
1 x 1 2.00 2.00 0.00
nos Per Nos
38 Supply and fixing SPN Distribution board with IP-20 protection suitable for single phase Earth
Leakage Circute Braker (ELCB) / Residual Current Circute Braker (RCCB) / Double Pole (DP)
Isolator as incomer and 10kA SP MCBs as out going including internal connections and labour
charges for surface / flush mounting etc., complete.
1 x 1 1.00 1.00 3146.00 3146.00
No Per Nos
40 Supply of 1200 mm (48") sweep 230V, A.C 50 Hz.Ceiling fan (ISI Mark) with 3 Blades and
double ball bearings with all standard accessories.
S/F Fans 1 x 1 6.00 4 1797.40 7190.00
Nos Per Nos
41 Supply and Transportation of 1x40W patty type tube light luminaire with copper choke,
starter etc., including 1No 40W tube etc., complete.
S/F Tubes 1 x 1 8.00 4 471.48 1886.00
Nos Per Nos
trap Hindware/Parryware/Neycer - ISI Mark 630x450 mm including cost and conveyance of all
43 Supplying and fixing TV shape mirror with plastic frame size 609.6 mm x 457 .2 mm
0.00 0.00
No Per Nos
44 S& F GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI
fittings including the cost of pipe & its fittings & labour charges complete 20mm
dia.
20MM dia 30.00 206.00 6180.00
Rm Per Rm
45 Prince/ Sudhakar make or equivalent quality PVC /SWR pipes & fittings ( as per ISI
Page 46 of 245
46 Prince/ Sudhakar make or equivalent quality PVC /SWR pipes & fittings ( as per ISI
47 Supply,fixing of 110 mm deep PVC floor traps of self cleansing design with outlet
size of 75mm diameter of approved make, including making connection with PVC
soil/waste pipes using rubber gaskets and top shall be cover with removable CP
strainer, etc., complete 110mm deep PVC floor traps(101.6)
2.00 144.00 288.00
Nos Per Nos
50 Supply, and fixing of approved make Vent cowl above the Soil & waste pipes for
ventilation as required to avoid foul smell. 110mm
2.00 19.00 38.00
Nos Per Nos
52 Supplying & fixing 150 mm x 100 mm SWG gully traps of ISI make conforming to ISI
651 & 4127 with C.I Grating & Constg. Brick masonry in CM 1:6 prop. Intermediate
chamber and fitted with 304.8 mm x 288.6mm (12"x9") C.I Frame and hinged cover.
2.00
568.00 1136.00
Per Nos
53 Providing & placing on Terrace polyethylene water storage tank with Double layer
approved brand & manufacture with cover and suitable locking arrangement &
making necessary holes for inlet & outlets and overflow pipes but without fittings &
base support for tanks.( From ssr rates sno 311) 2000lts
1000.00 6.00 6000.00
Lt Per Lt
54 Supplying, laying, jointing and testing 101.6 mm SWG SP-1 pipes of ISI make
conforming to ISI 651 & 4127 with airtight cement joints in CM 1:5:1 prop.including
excavation of trenches and socket pits in any soil (except rock requiring blasting)
55 Supply of SWG junctions (Ts& Ys) confirming to IS standereds with length of barrel
60 cm for 150x150
Page 47 of 245
1 0.00
Nos Per Nos
#REF!
56 Seigniorage Charges 1 9753.00 9753.00
#REF!
Page 48 of 245
DETAIED CUM ABSTRACT ESTIMATE
Sn Measurements
Description of item Nos. Qty Rate/Per
o
L B D
1 2 3 4 5 6 7 8
1 Vibrated reinforced cement concrete corresponding M15 grade as per IS 456 equivalent to
(1:1.5:3) prop: nominal mix (Cement: fine aggregate: coarse aggregate using 20mm size
HBG (SS5) machine crushed metal from approved quarry including cost and conveyance of
all materials like cement, fine aggregate (Sand), coarse aggregate, water etc. to site
Excluding seigniorage charges,Including, Countryes & other taxes on all materials, all
operational, incidental, and labor charges such as centering, shuttering, scaffolding, lift
charges, machine mixing, laying concrete, vibrating, curing concrete etc, complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS No.402
& 403)
A) For Column Footings
0.34 8943.65
Or Say 0.41
0.45 11440.60
Cum. PerCum.
2 Brick Masonry in superstructure with CM (1:8) prop: using second class bricks from
approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, sand, bricks, water etc., to site, Excluding
seigniorage charges,Including, Countryes & other taxes on all materials, all operational,
incidental and labor charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS
No. 501 & 504).
For ZPHS building
Parapet wall to varndah 1 x 1 30.45 0.23 0.95 6.65
Page 49 of 245
3 Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20
mm thick (average) mixed with water proofing compound manufactured by reputed
manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement, laid over roof
slab when it is green, finished smooth with a floating coat of neat cement and thread
lining at regular intervals of 45cmx45cm including cost and conveyance of all materials
like cement, sand, water proofing compound, water etc., to site, seigniorage charges,
sales & other taxes on all materials, all operational, incidental and labour charges such as
mixing mortar, laying, rounding off at junctions of wall and slab, rendering smooth with
thread lining, curing, lift charges, etc., complete for finished item of work (APSS No. 901
& 903).
Over 6th Class 1 x 1 10.00 5.50 55.00
240.05
Or Say 240.05 4514.95
4 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat
of 4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all
materials like cement, sand, water etc., to site, seigniorage charges, Countryes & other
taxes on all materials, all operational, incidental and labor charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary
as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces
of Wall for finished item of work. (APSS 901,903 & 904) For Internal walls
In side Area
Parapet wall to varndah 1 x 2 35.20 0.95 66.88
5 Flooring with15-18 mm thick polished Shabad stones (Tandur Blue 1st.Variety) of size
0.457 M x 0.457M set over a base coat of CM (1:8), 12mm thick (joints of stone must be
flushed) over 100mm thick C.C. bed already laid only after it is properly cured,
cleaned, moistered and where necessary treated with neat cement slurry and jointed
with neat cement paste to full depth, including cost and conveyance of all materials like
cement, sand, water, flooring stones etc. to site, seigniorage charges, Countryes and
other taxes on all materials, all operational, incidental and labour charges such as
dressing of flooring stones to the required sizes, mixing of cement mortar, laying,
jointing, curing, lift charges etc., complete for finished item of work.(APSS No.703 & 701)
(GROUND FLOOR)
Class Rooms
1 x 2 7.32 6.10 89.19
Varandah 1 x 2 7.32 1.80 26.35
Door sills of D
2 x 1 1.20 0.23 0.55
Page 50 of 245
116.09
10.26
7 Supply and fixing of salwood Door single shutter fully pannlled door of size 1.05 x
2.1mt AND bottom reeper of size 75x38mm and shutter made of side rails 125mm X38,
top rail 125mmX38mm, bottom rail 175mmX38mm and intermediate rails of 125 x 38 mm
and panels - 4 no's are of 25mm thick as per approved design with fixtures of 6 nos of 9" '
z" holdfasts, 300 mm long aluminium aldrop-1 no,125mm long aluminium butt hinges 4
No's, Door stoppers-1 no, 150mm long Tower bolts - 1no's alumium, 200mm long Tower
bolts - 1no's alumium,Aluminium fancy handles 150mm long 1no's, with necessary
screws complete including cost and conveyance of all materials and labour charges etc.
complete as per specifications (APSS NO.1001 & 1002)
Only shutters
2.00 4411.22
8 Supply and fixing of Window size 1.50 x 1.35 mt with sal wood frame of size 75x100mm
along with II class teak wood three shutters made with styles& rails of 100mmx30mm
thick with 12mm prelaminated particle board both side laminated interior grade and S/F
of 4Nos. MS Hold fasts, 6Nos. MS tower bolts 100mm long. 6 Nos. MS Hinges 75mm
long,2Nos MS Handles 3 Nos window stays. incl. all labour charges such as making window
frame & shetter and fiXing 11 Nos. 16mm plain safety bars in to frame etc,
Window W 3'-0"x4'-6"
1 x 1 1.50 1.35 1.00 7507.48
9 Supply , manufacture, making to specified design andLabour charges for fabricating steel
works like Window Grills, Compound Wall Grills, Iron Doors, Windows including cost of
welding rods, power charges, excluding cost of fixing in position
Iron grills 1210.00
1210.00 79.00
Page 51 of 245
Kg Per Kg
10 Painting to new walls with 2 coats of water proof cement paint of apporved brand and
shade over a base coat of approved cement primer grade I making making 3 coats in all to
give an even shade after thourughly brushing the surface to remove all dirt and remains of
loose powdered materials, including cost and conveyance of all materials to work site and
all operational, incidental, labour charges etc. complete for finished item of work as per
SS 912 for internal walls
Inside walls
7th Class 1 x 1 7.40 6.30 46.62
8th Class 1 x 1 7.40 6.30 46.62
9th Class 1 x 1 7.40 6.30 46.62
10th Class 1 x 1 6.00 4.80 28.80
Computer Room ceiling 1 x 1 6.00 4.80 28.80
Varandah in front 07,08,09 1 x 1 22.50 2.05 46.13
Varandah in front 10th Computer Room 1 x 1 12.60 2.60 32.76
Chajja both 1 x 1 22.50 0.90 20.25
Chajja both 1 x 1 12.60 0.90 11.34
7th Class 1 x 1 31.00 3.00 93.00
8th Class 1 x 1 31.00 3.00 93.00
9th Class 1 x 1 31.00 3.00 93.00
Varandha side walls 1 x 2 2.05 3.00 12.30
varandaface side 1 x 1 22.50 3.00 67.50
venrandah entablature walls 1 x 1 22.50 1.00 22.50
varandah parapet 1 x 1 20.10 1.00 20.10
10th Class 1 x 1 21.60 3.00 64.80
Computer Room ceiling 1 x 1 21.60 3.00 64.80
varandah side walls 1 x 2 2.60 3.00 15.60
varadah faces 1 x 1 12.60 3.00 37.80
varandah entablature walls 1 x 1 12.60 1.00 12.60
varandah parapet 1 x 1 11.40 1.00 11.40
Deductions 916.34
Doors 1 x 5 1.05 2.10 11.03
Windows 1 x 15 1.05 2.10 33.08
44.11
872.23
346.95 or say 872.23 525.00
11 Painting to New walls with two coats of snowcem paints of approved brand and shade
over base coat of appropriate distemper primer of approved brand making three coats in
all to give an even shade after thoroughly brushing the surface to remove all loose
powdered materials, including c/c of all materials, cost of brushes, water to site, etc., &
other taxes, all operational, incidental and labour charges such as scaffolding charges, lift
charges, curing etc.,complete for finished item of work in all floors for external Walls.
(APSS No. 911)
For External walls 1 x 1 23.10 3.60 83.16
For Back side 1 x 1 23.10 2.50 57.75
Front side 1 x 2 9.05 3.60 65.16
Back side of Comp Room 1 x 1 26.80 3.60 96.48
Front side 1 x 1 26.80 2.50 67.00
Page 52 of 245
sides 1 x 2 8.15 3.60 58.68
For window chazza s 2 x 5 1.70 0.65 5.53
for Compound wall 1 x 2 10.60 1.75 37.10
1 x 2 12.60 1.65 41.58
1 x 2 32.20 1.70 109.48
1 x 2 14.60 1.50 43.80
1 x 2 5.70 1.50 17.10
682.82
46.20 or say 682.82 1638.50
12 Painting to New wood work with two coats of ready mixed synthetic enamel paint first
quality all shades to give an even shade over base coat Primar with Luppam finishing
after thouroughky brushing the surface to remove all remains including cost and
conveyance of all materials to site, Countryes & other taxes, all operational, incidental
and labour charges etc., complete for finished item of work.(3 coats) (APSS No. 1201 &
1212).
15 x 3 1.50 1.35 83.53
Page 53 of 245
Asst. Exe. Engineer Dy. Executive.Engineer
PRI Yacharam PRSD Rajendranagar
Page 54 of 245
BNRGSK)] at
Total
Amount
3041.00
754.00
5148.00
52121.00
Page 55 of 245
108381.00
29362.00
Page 56 of 245
68286.00
6475.00
8822.00
7507.00
7635.00
95590.00
Page 57 of 245
45792.00
Page 58 of 245
111880.00
15770.00
566564.00
28328.00
2861.00
975.00
Page 59 of 245
598728.00
Page 60 of 245
Construction of Community Hall at RB Nagar in Shamshabad(v&m)
SANITARY &WATER SUPPLY DATA 2013-14
1 Supply & fixing 580mm x 440mm size white virerous orissa pan with attached footrests of approved make
confirming to IS 2556 (part - III) with 'P' or 'S' trap, including 10 lit. low level PVC flusihing system confirming to
IS 7231 with all internal fittings, CI brackets, 32mm dia CP flush pipe, 15mm dia 450mm long PVC connerctor,
15mm dia Cp brass strop cock 300 grams of ISI make, cutting and making good the walls and floors wherever
required including cost & conveyance of all material to work site, all labour charges for all operations for fixing
etc., complete for finished item of work.
(BMW-G.08) Supply & fixing of PVC low level system parry Each 1455 1 1455.00
ware, slim line with internal components &
short bend: 10 Litres capacity Single Flush
BMW-D.14 Supplying and Fixing European Water Closet Each 1785 1 1785.00
of 1st quality conforming to
IS:2556-Part-2-1973 of Hindustan / Neycer or
Parryware make white glazed
with S trap
(BMW-G.08) Supply & fixing of PVC low level system parry Each 1455 1 1455.00
ware, slim line with internal components &
short bend: 10 Litres capacity Single Flush
BMW-E.09 S&F of 12.7mm N.P bib tap indian make 300 g Each 258 1 258.00
Over Heads : 14.00 258.00 0.00 0.00
Total rate per each Rs 258.00
3 Supplying and fixing 4" (101.6 mm ) multi floor trap with Jali- UPVC/SWR Pipe fittings of standard make of ISI
Brand ncluding fixing in CM1:3 prop. and cost and conveyance of all materials at site complete for finished item
of work.
a) 110 mm dia
BMW-G.13 110 mm dia 3 M Single Socket PVC/SWR pipe Each 484 1 484.00
- 4 Kg/sq.cm - Prince/Sudhakar or any ISI
Brand
BMW-F.17 a) S & F Gunmetal Gate (GM peet) valve as Each 914.00 1 914.00
per IS -778 Class - I, Indian make heavy type
- 25 mm NB Size
14 Providing of PVC casing pipe 160 mm dia of 6 Kg / cm2 including cost of labour & materials
Code Unit Rate Coefficient Amount
16 Supply and fixing of SWG pipe of ISI make conforming to ISI 651 4" dia (100 mm) including cost, conveyance of
materials, labour charges etc. complete for fininshed item of work.
Code Unit Rate Coefficient Amount
Material
BMW-A.15 Supply of SWG SP-1 pipe conforming to ISI
651 - 4" dia (101.6mm) Rm 181.00 1 181.00
Over Heads : 14.00 181.00 0.00 0.00
Muncpal Limits 0.00 0 0.00
Total per 1.00 Rm Rs 181.00
4 Supply of Sintex /Aqua tech or equivalent Polyethylene water storage tank double layer conforming to ISI
12701/96 mark with lid.
Code Unit Rate Coefficient Amount
Material
BMW-G.01 Lt 6.00 1 6.00
Executive Engineer
PR (PIU) Division Hyderabad
Ele data
3 P.V.C. Conduit (Concealed)
1.4.2 Supply and Fixing of 25mm dia 2.00 mm thick PVC
(a) pipe (ISI MARK) concealed in wall with all
BLD-ELEC required accessories including masonary work
-1-4 and labour charges etc., complete.
Ele data
b) Labour charges :
Skilled Electrician day 0.67 515.00 345.05
Semi Skilled Electrician day 2 375.00 750.00
Helpers day 0.67 405.00 271.35
Add Mucipal Limits 0.40 1366.40 546.56
C) Cost for 100 RM 4212.96
Rate per Metre = C/100 42.13
OVER HEADS 0% 42.13 0
Rate per 1 RM RS 42.13
3.1.4 Supply and run of 2 of 36/0.3mm (2.5 Sq.mm) F.R
P.V.C. insulated flexible copper cable in existing
pipe for mains inlcuding all labour charges etc.,
complete.
Ele data
Note : Labour Charges proposed for 1point
8 2.1.5 considering
Supply and 15 per day
fixing of 16A 3pin / 6A 3pin plug
socket with indicator lamp and 16Amps fuse unit
and 16 Amps switch control (5 in one) on decolam
sheet covered board including earth connection
and all labour charges etc., complete on wall.and
as per 2.1.5 of Sta revised data of BLD -ELEC-
2.1.5
a) Material
900 mm (36") / 1200 mm (48") / 1400 mm (56") each 1 1600.00 1600.00
Ceiling Fan Bajaj/Crompton/orient make only
ELEC-5.1.1
Transportation Charges on Unit Cost 0.01 16.00
Rate per Each 1616.00
OVER HEADS 0% 1616.00 0
Rate per Each RS 1616.00
9.7.3 Labour Charges
11 5 Labour charges for Fixing of Ceiling fan and
regulator including transportation and giving
connections with twin core wire etc., complete.
Ele data
a) Material
ELEC-1.6.8 23/0060 Twin Core wire 100M 1 1040.00 10.40
Unforseen item works, such as painting to down LS 10.00
rod, screws and Cover frame etc.,
b) Labour charges.
Skilled Electrician day 0.125 515.00 64.38
Helper day 0.125 405.00 50.63
Add Mucipal Limits 0.40 115.00 46.00
Rate per Each 181.40
OVER HEADS 0% 181.40 0
Rate per 1 RM RS 181.4
Rate per Each RS 1797.40
12 9.7.2 Supply and erecting Stepped type electronic
6 Regulator for ceiling fans 900/1200/1400mm
sweep complete erected on existing board.and as
per 9.7.26 of Sta revised data of BLD -ELEC-
9.7.26
a) Material
ELEC-1.7.12 Stepped type electronic Regulator each 1 220.00 220.00
b) Labour charges.
Semi skilled Electrician day 0.1 405.00 40.50
Add Mucipal Limits 0.40 40.50 16.20
Rate per Each 276.70
OVER HEADS 0% 276.70 0
Rate per Each RS 276.7
Note : Labour is Considered for 10 jobs / day
9.7.1 EXHAUST FANS
13 6 Supply of fresh air exhaust fan of light duty 250V
A.C.50Hz.. 225 mm (9") / 300mm size (12") 1350
R.P.M Metallic body plastic blades, wire mesh,
etc., complete.and as per 9.7.16 of Sta revised
data of BLD -ELEC-9.7.16
a) Material
ELEC-5.1.11 225 mm (9") / 300mm (12") L.D. Exhaust Fan each 1 1350.00 1350.00
Transportation Charges on Unit Cost 0.01 13.50
Rate per Each 1363.50
OVER HEADS 0% 1363.50 0
Rate per Each RS 1363.5
14 9.7.3 Labour charges for fixing of Exhaust fan in wall
6 with necessary connections and masonary work of
making hole, finishing etc., complete 9.7.36
a) Material
ELEC-1.6.8 23/0060 Twin flat wire 100M 1 1040.00 10.40
Cement kg 25 5954.92 148.87
b) Labour charges.
Skilled Electrician day 0.25 515.00 128.75
Helper day 0.25 405.00 101.25
Mason day 0.25 480.00 120.00
Add Mucipal Limits 0.40 350.00 140.00
Rate per Each 649.27
OVER HEADS 0% 649.27 0
Rate per Each RS 649.27
Note :1. Labour is Considered for 6 jobs / day
15 8.2.2 Supply and Transportation of 1x36/40W box type
tube light luminaire with copper / VPIT Choke,
condensor, starters etc., and 1No 36/40W tube
etc., complete.and as per 8.2.2 of Sta revised
data of BLD -ELEC-8.2.2
a) Material
ELEC-3.6.5 1x40/36 box type T.L fitting each 1 766.00 766.00
ELEC-3.7.7 36/40 Tube each 1 45.00 45.00
Ele data
Sundries and rounding off
Rate per each 811.00
OVER HEADS 0% 811.00 0
Rate per Each RS 811
16 Fixing of 40W tube light luminaire on wall /
Ceiling with / TW round blocks with all
accessories including giving connections and all
labour charges etc., complete.7.9.3
a) Material
ELEC-1.6.8 23/0060 twin core flexible copper cable M 1 10.40 10.40
ELEC-1.4.23 & screws with rawal plugs each 2
ELEC-8.16 1.24 2.48
ELEC-8.1.31 T.W round blocks each 2 7.00 14.00
Cement and sand etc., LS 2.00
b) Labour charges
Skilled Electrician/carpenter day 0.1 515.00 51.50
Semi skilled Electrician / Helper day 0.1 375.00 37.50
Add Mucipal Limits 0.40 89.00 35.60
Rate per each 153.48
OVER HEADS 0% 153.48 0
Rate per Each 153.48
RS 964.48
BLD-ELEC-5-1 a) Material
18 Supply and fixing of 3-Phase Meter Board with 18"
x30" size Peta Board with 3 No. of 32A, 415 V Fuse
Unit and 32A Standard make including giving
internal connections
Manpower
Electrician ( Licensed ) 440.00
CSSR-M-005 day 1 440.00
Lineman Electric / Telephone 440.00
CSSR-M-076 day 1 440.00
Add LA chrges 0.00
0.00% 0.00 495.00
Miscellaneous
ELEC-8.1.6 Rawl Plugs Nos 4 28.00 112.00
TW / PVC Round Blocks 28.00
ELEC-8.1.31 No 4 7.00
Rate per each 2727.60
OVER HEADS 0% 2727.60 0
Rate per Each 2727.6
20 4.4.3 Supply and fixing TPN Distribution board with IP-
20 protection suitable for 3 phase ELCB / RCCB /
FP Isolator as incomer and 10kA SP MCBs as outing
going including internal connection and labour
charges for surface / flush mounting etc.,
complete.and as per 4.4.3 of Sta revised data of
BLD -ELEC-4.4.3
Ele data
Skilled Electrician day 0.5 440.00 220.00
Semi Skilled Electrician day 1 375.00 375.00
Helpers day 1 345.00 345.00
Sundries such as TW Plugs, Screws Cement etc, LS
a) Material
ELEC-3.6.8 1x40 patty type T.L. fitting each 1 273.00 273.00
ELEC-3.7.16 40W FTL each 1 45.00 45.00
Sundires and rounding off
Rate per each 318.00
Labour Charges 153.48
OVER HEADS 0% 471.48 0
Rate per Each RS 471.48
a) Material
ELEC-3.1.1 1x40W WP flourscent street light fitting. each 1 1400.00 1400.00
Ele data
BLD-ELEC-4-4 4.4 DISTRIBUTION BOARDS
4.4.1 Supply and fixing SPN Distribution board with IP-
20 protection suitable for single phase Earth
Leakage Circute Braker (ELCB) / Residual Current
Circute Braker (RCCB) / Double Pole (DP) Isolator
as incomer and 10kA SP MCBs as out going
including internal connections and labour charges
for surface / flush mounting etc., complete.4.4.1
a) Material
ELEC-8.1.52 Earth Work Excavation of Hard gravel Soil with cum 0.85 220.00 187.00
ELEC-8.1.52 small boulder
Excavation of for trench
Hard Gravel1st soils
step offorsize 1.5 x 2nd
trench 0.6 cum 0.9 220.00 198.00
x 0.9extra
Step
25% m size
of (5'x2'x3')
for 1.2 x 0.6 xtrench
narrow 1.2 m &(Civil SSR)back
pit and (4'x2'x4')
filling 0.25 385.00 96.25
ELEC-8.1.55 with
40mmSand,
dia 'B'Coke,
ClassSalt
G.I etc.,
pipe and leveling Mtr 2.5 355.00 887.50
25 x 6 mm (1"X 1/4") G.I Flat duly drilled 12mm Each
holes (4 Nos) of 200 mm (8") length 0.942 37.00 34.85
Executive Engineer
Ele data
PR (PIU) Division Hyderabad
Ele data
SPECIFICATION REPORT
Accompanying the Estimate for the work Construction of Community Hall at RB
Nagar in Shamshabad(v&m) Ranga Reddy District.
Estd.Cost: Rs:5.00 Lakhs Grant: CDP -2015-16.
The above work is administratively sanctioned for Rs:5.00 Lakhs under CDP 2015-16 Grant vide District
Collector, Ranga Reddy District Procs. No. 495/CDP/Rajendranagar/MLA/2015, , Dated:11.04.2016. Accordingly, the detailed
Estimate Accordingly the Estimate was techincally sanctioned for Rs:5.00 Lakhs by the Executive Engineer, PIU Division
Hyderabad, vide TS No: T2/ /2016-17; Dated:25.01.2017. Now, the working Estimate is prepared as per the plan requested by
the GP, Shamshabad and accordingly with following provisions up to the sanctioned amount.
1) Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 2m in Loamy and Clayey Soils like B.C.
Soils, red earth & Ordinary Gravel (SS 20-B) including shoring, strutting, sheeting, planking and dewatering including cost of hire
charges of T & P, labour charges etc., complete for finished item of work for Foundation of Building.(APSS No. 308)
2) Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix (cement: fine
aggregate: Coarse aggregate) using 40mm size HBG (SS5) metal from approved quarry including cost and conveyance of all
materials lik
3) Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using hard granite stones from approved quarry including cost
and conveyance of all materials like Granite stones, cement, sand, water, etc., to site including seigniorage charges, Countryes
4) Coursed Rubble stone masonry in CM (1:8) prop: (Cement: Sand) using hard granite stones from approved quarry including cost
and conveyance of all materials like Granite stones, cement, sand, water, etc., to site including seigniorage charges, Countryes
5) Plain Cement Concrete corresponding to M20 grade as per IS 456 equivalent to (1:1.5:3) proportion nominal mix (cement: fine
aggregate: Coarse aggregate) using 20mm size HBG (SS5) metal from approved quarry including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, Countryes & other taxes on all
6) RCC M- 20 all
materials, Nominal mix (Cement:fine
operational, incidental, aggregate: coarse aggregate)
and labor charges corresponding
such as mixing, laying andtoramming
Table 9 ofconcrete
IS 456 using 20mm
in layers size graded
in position not
machine
exceeding crushed hard granite
15cm, finishing metal (coarse
top surface, curingaggregate) from approved
concrete, including quarry
contractor including
profit cost and for
etc., complete conveyance of allofmaterials
finished item work. like
cement
7) Plain reinforced cement concrete corresponding M20 grade as per IS 456 equivalent to (1:1.5:3) prop: nominal mix (Cement: fine
aggregate: coarse aggregate using 20mm size HBG (SS5) machine crushed metal from approved quarry including cost and
conveyance
8) Filling with useful available excavated earth (excluding rock) in trenches,sides of foundation and basement with intial lead in
layers not exceeding 15cm thick consolidating each deposited layer by watering and ramming including all operational,incidental
9) Filling with carted gravel (excluding rock) in trenches, sides of foundations and basement with initial lead in layers not
exceeding 15cm thick, consolidating each deposited layer by watering and ramming including all operational, incidental, labor
char
10) Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8mm to 40mm diameters,
cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG,
forming
11) Supply and fixing of Country wood Door double shutter fully panelled door of size 1.05 x 2.1mt with frame made of well
seasoned country Wood scantlings of size 100 x 75mm and shutter made of side rails 100mm X 32mm, top rail 100 mmX32
mm, bottom rail 1 of 25mm dia 2.00mm thick surface P.V.C. pipe (ISI MARK) with all accessories fixing on chromium plated
12) Supply and Fixing
metallic base saddles including all labour charges, including contractor profit etc etc., complete for run of mains and as per 1.3.2
13) o
Supply and Fixing of Foundation stone of Black Granite of size 4'00"x2'6" including engraving letters in golden colour including
cost and conveyance of all materials and labour charges etc. complete.
14) LS Amount for Unforeseen items
The Working Estimate is prepared as per the sanctioned estimate rates (i.e. with SSR 2016-17) and submitted
for according Technical Approval.
1) Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other deleterious material
and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated
suitable material as per Technical Specification 305 MORD / 304 MORTH including contractor profit
58.58
11.63
Cum. Cum.
Page 46 of 245
Measurements Rate/P Total
Sno Description of item Nos. Qty
L B D
er Amount
1 2 3 4 5 6 7 8 9
3) Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using hard granite stones
from approved quarry including cost and conveyance of all materials like Granite stones, cement, sand,
water, etc., to site including seigniorage charges, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as cutting stones to required size and shape, mixing of cement mortar,
constructing masonry, curing ,including contractor profit etc., complete for finished item of work for
foundation and basement including contractor profit (APSS No. 601 & 615) of AP Revised data BLD -CSTN-
6-13
1 x 1 13.00 0.45 0.45 2.63
1 x 1 3.00 0.45 0.45 0.61
1 x 1 3.35 0.45 0.45 0.68
1 x 1 3.25 0.45 0.45 0.66
1 x 1 1.92 0.45 0.45 0.39
1 x 1 3.50 0.45 0.45 0.71
1 x 1 1.37 0.45 0.45 0.28
1 x 1 5.30 0.45 0.45 1.07
7.03 3959.41 27835.00
4) Coursed Rubble stone masonry in CM (1:8) prop: (Cement: Sand) using hard granite stones
from approved quarry including cost and conveyance of all materials like Granite stones, cement, sand,
water, etc., to site including seigniorage charges, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as cutting stones to required size and shape, mixing of cement mortar,
constructing masonry, curing,including contractor profit etc., complete for finished item of work for
foundation and basement (APSS No. 601 & 615) in GROUND FLOOR of AP Revised data BLD -CSTN- 6-6
(0.70 +
1 x 1 13.00 0.45 3.51
0.50)/2
1 x 1 3.00 0.45 0.65 0.88
(0.65 +
1 x 1 3.35 0.45 0.94
0.60)/2
(0.65 +
1 x 1 3.25 0.45 0.80
0.45)/2
1 x 1 1.92 0.45 0.75 0.65
(0.65 +
1 x 1 3.50 0.45 1.06
0.70)/2
1 x 1 1.37 0.45 0.75 0.46
(0.45 +
1 x 1 5.30 0.45 1.37
0.70)/2
9.67 4186.66 40485.00
Cum. Per Cum
5) Plain Cement Concrete corresponding to M20 grade as per IS 456 equivalent to (1:1.5:3)
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 20mm size HBG (SS5) metal
from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc. to site, including seigniorage charges, Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as mixing, laying and ramming concrete in layers in position not
exceeding 15cm, finishing top surface, curing concrete, including contractor profit etc., complete for
finished item of work.
For Steps 0 x 11 0.90 0.30 0.15 0.00
0 x 8 0.90 0.30 0.15 0.00
0.00 7921.85 0.00
Cum. per Cum.
Page 47 of 245
Measurements Rate/P Total
Sno Description of item Nos. Qty
L B D
er Amount
1 2 3 4 5 6 7 8 9
Cum. Per Cum
C) For Columns
D) Plinth beams
7) Filling with useful available excavated earth (excluding rock) in trenches,sides of foundation and basement
with intial lead in layers not exceeding 15cm thick consolidating each deposited layer by watering and
ramming including all operational,incidental ,labour charges,hire charges of T&P complete for finished item
of work.(APSS NO. 309 & 310) of AP Revised data BLD-CSTN-2-9
Page 48 of 245
Measurements Rate/P Total
Sno Description of item Nos. Qty
L B D
er Amount
1 2 3 4 5 6 7 8 9
8) Filling with carted gravel (excluding rock) in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming
including all operational, incidental, labor charges, hire charges of T & Pincluding contractor profit etc.,
complete for finished item of work. (APSS NO. 309 & 310) of AP Revised data BLD -CSTN- 2-9
(0.60 +
Inside Of Room 1 x 1 11.00 3.70 28.49
0.70)/2
(0.45 +
1 x 1 12.00 0.75 4.50
0.55)/2
32.99 444.09 14651.00
cum per cum
9) Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8mm to
40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of
approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs
and drawings including cost and conveyance of bars from approved sources to site of work, including cost
and conveyance of binding wire, cover blocks and all operational, incidental, and labour charges such as
cutting, bending, placing in position, tying including contractor profit etc., and Countryes & other taxes,on
cost of all materials complete for finished item of work (APSS No.126) in all floors. and as per revised data
BLD-CSTN-4-1
TOTAL Rs 500000.00
Page 49 of 245
COMPARATIVE STATEMENT
Construction of Community Hall at RB Nagar in Shamshabad(v&m)
Estd.Cost: Rs:5.00 Lakhs 15% EMF(W&CW) of ZPGF
Sl. Description of item As per Sanctioned estimate As per Working Estimate Excess Less Rem
No. Quantity Rate/per Amount Quantity Rate/per Amount arks
Earthwork in excavation for structures as per drawing
and technical specifications Clause 305.1 including
1) setting out, construction of shoring and bracing, removal 25.920 312.13 8090.00 58.580 312.130 18285.00 10195.00 0.00
of stumps and other deleterious material and disposal
upto a lead of 50 m, dressing of side
MTs 1 MT MTs 1 MT
Supply and fixing of fully panelled Window frame and
shutters of size 0.90 x 1.35 mt with country wood frame
13) of size 75x100mm and S/F of 4 Nos. MS Hold fasts, incl. 0.000 0.00 0.00 0.000 0.00 0.00 0.00 0.00 -
all labour charges such as making window frame and
shutters and fiXing 10 Nos.of 12 m
MTs 1 MT MTs 1 MT
Supply and fixing of fully panelled Window frame and
shutters of size 0.90 x 1.35 mt with country wood frame
13) of size 75x100mm and S/F of 4 Nos. MS Hold fasts, incl. 0.000 0.00 0.00 0.000 0.00 0.00 0.00 0.00 -
all labour charges such as making window frame and
shutters and fiXing 10 Nos.of 12 m
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
1 2 3 4 5.00 6
BLD-CSTN-2-1 1 Earthwork in excavation for structures as per drawing
and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing, removal of
stumps and other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom and backfilling
in trenches with excavated suitable material as per
Technical Specification 305 MORD / 304 MORTH
Unit : 1 cum
Taking output : 10 cum
a) Labour
Mazdoor ( Unskilled) No 3.64 350.00 1274.00
Add 75% for foundations Cum 0.75 1274.00 955.50
Add Mucipal Limits 0.40 2229.50 891.80
Cost for 10 cum 3121.30
Add 13.615 % overhead charges, Contractor profit 3121.30 0.00000 0.00
Rate per 1 cum 3121.30
Seigniorage charges Cum 10.00 0.00 0.00
Rate Per 10Cum 3121.30
Rate per 1cum Rs 312.13
BLD-CSTN-2-7 1 Earthwork in excavation Hord Rock (blasting prohibited)
up to 3.0 m depth
Unit : 10 cum
Taking output : 10 cum
a) Labour
Mazdoor ( Unskilled) No 5.20 350.00 1820.00
Add Mucipal Limits 0.40 1820.00 728.00
b) Machinory
Air Compressor 210/250Cfm hr 6.00 640.10 3840.60
As per Errata 2- Jack hammers of Pneumatic breakers @1 Cfm/hr @6hr d 12.00 349.00 4188.00
/breaker
Cost for 10 cum 10576.60
Add 13.615 % overhead charges, Contractor profit 10576.60 0.00000 0.00
Rate per 1 cum 10576.60
Seigniorage charges Cum 10.00 0.00 0.00
Rate Per 10Cum 10576.60
Rate per 1cum Rs 1057.66
BLD-CSTN-2-8 2 Supplying and filling sand in trenches ,sides of the
Amnedment
foundations and basement with initial lead in layers not
6.2
exceeding 15 cm thick consolidatiing each depposited layer
by watering and rampping including cost and conveyance of
water to work site and all operational incidental ,labour
charges hire charges and T & O Complete for finished item
APSS 309 &310)
Unit : 1 cum
Taking output : 1 cum
a) Labour
Mazdoor ( Unskilled) No 0.31 350.00 108.50
Datas Page 58
59
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Add Mucipal Limits 0.40 108.50 43.40
Sand for filling Cum 1.00 764.24 764.24
Water Kl 0.10 103.00 10.30
926.44
Add 13.615 % overhead charges, Contractor profit 926.44 0.00000 0.00
Add Seign Charges Cum 1.00 40.00 40.00
966.44
Rate per 1 cum Rs 966.44
BLD-CSTN-2-9 3 Supplying and filling gravel in trenches ,sides of the
Amnedment
foundations and basement with initial lead in layers not
A(3)
exceeding 15 cm thick consolidatiing each depposited layer
by watering and rampping including cost and conveyance of
water to work site and all operational incidental ,labour
charges hire charges and T & O Complete for finished item
APSS 309 &310)
Unit : 6 cum
Taking output : 6 cum
a) Labour
Mazdoor ( Unskilled) No 3.12 350.00 1092.00
Add Mucipal Limits 0.40 1092.00 436.80
Gravel for filling Cum 6.00 176.93 1061.58
Water Kl 0.72 103.00 74.16
2664.54
Add 13.615 % overhead charges, Contractor profit 2664.54 0.00000 0.00
Add Seign Charges Cum 6.00 0.00 0.00
2664.54
Rate per 1 cum Rs 444.09
BLD-CSTN-1 MORTARS
BLD-CSTN-1-1 4 Cement Mortar (1 : 1)
Unit : 1cum
A. MATERIALS:
Cement kg. 1440.00 5954.92 8575.08
Sand (including 5% wastage) cum 1.05 2967.85 3116.24
B. MACHINERY
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 350.00 70.00
Add Mucipal Limits 0.40 70.00 28.00
Grand Total Rs 11789.32
BLD-CSTN-1-3 5 Cement Mortar (1 : 2)
Unit : 1cum
A. MATERIALS:
Cement kg. 720.00 5954.92 4287.54
Sand (including 5% wastage) cum 1.05 2967.85 3116.24
B. MACHINERY
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 350.00 70.00
Add Mucipal Limits 0.40 70.00 28.00
Grand Total Rs 7501.78
BLD-CSTN-1-4 6 Cement Mortar (1 : 3)
Unit : 1cum
Datas Page 59
60
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
A. MATERIALS:
Cement kg. 480.00 5954.92 2858.36
Sand (including 5% wastage) cum 1.05 2967.85 3116.24
B. MACHINERY
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 350.00 70.00
Add Mucipal Limits 0.40 70.00 28.00
Grand Total Rs 6072.60
BLD-CSTN-1-5 7 Cement Mortar (1 : 4)
Unit : 1cum
A. MATERIALS:
Cement kg. 360.00 5954.92 2143.77
Sand (including 5% wastage) cum 1.05 2967.85 3116.24
B. MACHINERY
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 350.00 70.00
Add Mucipal Limits 0.40 70.00 28.00
Grand Total Rs 5358.01
BLD-CSTN-1-6 8 Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement kg. 288.00 5954.92 1715.02
Sand (including 5% wastage) cum 1.05 2967.85 3116.24
B. MACHINERY
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 350.00 70.00
Add Mucipal Limits 0.40 70.00 28.00
Grand Total Rs 4929.26
BLD-CSTN-1-7 9 Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement kg. 240.00 5954.92 1429.18
Sand (including 5% wastage) cum 1.05 2967.85 3116.24
B. MACHINERY
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 350.00 70.00
Add Mucipal Limits 0.40 70.00 28.00
Grand Total Rs 4643.42
BLD-CSTN-1-8 10 Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement kg. 180.00 5954.92 1071.89
Sand (including 5% wastage) cum 1.05 2967.85 3116.24
B. MACHINERY
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 350.00 70.00
Add Mucipal Limits 0.40 70.00 28.00
Grand Total Rs 4286.13
Datas Page 60
61
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
BLD-CSTN-3-5 11 Plain Cement concrete (1:4:8) using 40 mm metal with
concrete mixture. All work upto plinth level.
nominal mix (cement: fine aggregate: Coarse aggregate)
using 40mm size HBG (SS5) metal from approved quarry
including cost and conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site, including
seigniorage charges, Countryes & other taxes on all
materials, all operational, incidental, and labor charges
such as mixing, laying and ramming concrete in layers in
position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete for finished item of work for
Foundations and Flooring Bed (APSS No. 402)
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 5954.92 964.70
Coarse aggregate 40 mm cum 0.90 1307.09 1176.38
Sand of Concrete cum 0.45 2767.85 1245.53
Water for Curing Kl 1.20 77.00 92.40
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 472.60 472.60
C. LABOUR:
Mason 1st class day 0.10 480.00 48.00
Mazdoor (unskilled) day 1.39 350.00 486.50
Add Mucipal Limits 0.40 534.50 213.80
Water Charges 1% 4699.91 0.01 47.00
Grand Total 4746.91
Add 13.615 % overhead charges, Contractor profit 4746.91 0.00000 0.00
Rs 4746.91
Add Seign Charges of Metal cum 0.90 75.00 67.50
Add Seign Charges of Sand cum 0.45 40.00 18.00
Rate per 1 cum 4832.41
BLD-CSTN-3-7 12 Plain Cement concrete (1:5:10) using 40 mm metal with
Concrete mixture. using 40mm size HBG (SS5) metal from
approved quarry including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc.
to site, including seigniorage charges, Countryes & other
taxes on all materials, all operational, incidental, and
labor charges such as mixing, laying and ramming concrete
in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item
of work for Foundations and Flooring Bed (APSS No. 402)
All work upto plinth level.
Unit = 1cum
A. MATERIALS:
Cement kg 129.60 5954.92 771.76
Coarse aggregate 40 mm cum 0.90 1307.09 1176.38
Sand of Concrete cum 0.45 2767.85 1245.53
Water lncluding curing Kl 1.20 103.00 123.60
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 472.60 472.60
C. LABOUR:
Mason 1st class day 0.10 480.00 48.00
Datas Page 61
62
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Mazdoor (unskilled) day 1.39 350.00 486.50
Add Mucipal Limits 0.40 534.50 213.80
Grand Total 4538.17
Add 13.615 % overhead charges, Contractor profit 4538.17 0.00000 0.00
Rate per 1 cum Rs 4538.17
Add Seign Charges of Metal cum 0.90 75.00 67.50
Add Seign Charges of Sand cum 0.45 40.00 18.00
Rate per 1 cum 4623.67
BLD-CSTN-6- 13 RR Masonry in CM (1:6) Cement: Sand) using hard granite
12
stones from approved quarry including cost and
conveyance of all materials like Granite stones, cement,
sand, water, etc., to site including seigniorage charges,
Countryes & other taxes on all materials, all operational,
incidental, and labor charges such as cutting stones to
required size and shape, mixing of cement mortar,
constructing masonry, curing etc., complete for finished
item of work for foundation and basement (APSS No. 601 &
615)
Unit = 1cum
A. MATERIALS:
Cement kg 79.20 5954.92 471.63
CR Stone cum 0.44 592.45 260.68
Rough Stone cum 0.50 773.93 386.97
Bond Stones( 0.25 x 0.25 x 0.45-0.60 ) cum 0.16 1201.55 192.25
Sand of Mortor cum 0.33 2967.85 979.39
B. LABOUR:
Mason 1st class day 1.20 480.00 576.00
Mazdoor (unskilled) day 2.00 350.00 700.00
Add Mucipal Limits 0.40 1276.00 510.40
Grand Total 4077.32
Add 13.615 % overhead charges, Contractor profit 4077.32 0.00000 0.00
BASIC COST per 1 cum Rs 4077.32
Add Seign Charges of Stone cum 1.10 75.00 82.50
Add Seign Charges of Sand cum 0.33 40.00 13.20
BASIC COST per 1 cum 4173.02
BLD-CSTN-6- 14 RR Masonry in CM (1:8)
13
Unit = 1cum
A. MATERIALS:
Cement kg 59.40 5954.92 353.72
CR Stone cum 0.44 592.45 260.68
Rough Stone cum 0.50 773.93 386.97
BondStones 7Nos( 0.25 x 0.25 x 0.45-0.60 ) cum 0.16 1201.55 192.25
Sand of Mortor cum 0.33 2967.85 979.39
B. LABOUR:
Mason 1st class day 1.20 480.00 576.00
Mazdoor (unskilled) day 2.00 350.00 700.00
Add Mucipal Limits 0.40 1276.00 510.40
Grand Total 3959.41
Add 13.615 % overhead charges, Contractor profit 3959.41 0.00000 0.00
BASIC COST per 1 cum Rs 3959.41
Datas Page 62
63
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Add Seign Charges of Stone cum 1.10 75.00 82.50
Add Seign Charges of Sand cum 0.33 40.00 13.20
BASIC COST per 1 cum Rs 4055.11
BLD-CSTN-6.6 15 CRS Masonry in CM (1:6) 2nd Sort (Cement: Sand) using
hard granite stones from approved quarry including cost
and conveyance of all materials like Granite stones,
cement, sand, water, etc., to site including seigniorage
charges, Countryes & other taxes on all materials, all
operational, incidental, and labor charges such as cutting
stones to required size and shape, mixing of cement
mortar, constructing masonry, curing etc., complete for
finished item of work for foundation and basement (APSS
No. 601 & 615)
Unit = 1cum
A. MATERIALS:
Cement kg 76.80 5954.92 457.34
CR Stone ( 30x30x60Cm) cum 0.94 592.45 556.90
Bond Stones( 0.25 x 0.25 x 0.45-0.60 ) 7Nos. 0.16 1201.55 192.25
Sand of Mortor cum 0.32 2967.85 949.71
B. LABOUR:
Mason 1st class day 1.50 480.00 720.00
Mazdoor (unskilled) day 2.32 350.00 812.00
Add Mucipal Limits 0.40 1532.00 612.80
Grand Total 4301.00
Add 13.615 % overhead charges, Contractor profit 4301.00 0.00000 0.00
Rs 4301.00
Add Seign Charges of Stone cum 1.10 75.00 82.50
Add Seign Charges of Sand cum 0.32 40.00 12.80
BASIC COST per 1 cum Rs 4396.30
BLD-CSTN-6.6 16 CRS Masonry in CM (1:8) 2nd Sort
Unit = 1cum
A. MATERIALS:
Cement kg 57.60 5954.92 343.00
CR Stone ( 30x30x60Cm) cum 0.94 592.45 556.90
Bond Stones ( 0.25 x 0.25 x 0.45-0.60 ) 7Nos. 0.16 1201.55 192.25
Sand of Mortor cum 0.32 2967.85 949.71
B. LABOUR:
Mason 1st class day 1.50 480.00 720.00
Mazdoor (unskilled) day 2.32 350.00 812.00
Add Mucipal Limits 0.40 1532.00 612.80
Grand Total 4186.66
Add 13.615 % overhead charges, Contractor profit 4186.66 0.00000 0.00
Rs 4186.66
Add Seign Charges of Stone cum 1.10 75.00 82.50
Add Seign Charges of Sand cum 0.32 40.00 12.80
BASIC COST per 1 cum Rs 4281.96
BLD-CSTN-7-1 17 Flush Pointing with CM (1:3) to Brick / CRS Masonry
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40 5954.92 85.75
Datas Page 63
64
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Sand of Mortor cum 0.03 2967.85 89.04
B. LABOUR:
Mason 2nd class day 0.50 405.00 202.50
Mazdoor (unskilled) day 0.74 350.00 259.00
Add Mucipal Limits 0.40 461.50 184.60
Grand Total 820.89
Add 13.615 % overhead charges, Contractor profit 820.89 0.00000 0.00
Rs 820.89
Add Seign Charges of Sand cum 0.03 40.00 1.20
BASIC COST per 10 sqm Rs 822.09
BLD-CSTN-3- 20 RCC M- 20 Nominal mix (Cement:fine aggregate: coarse
13
aggregate) corresponding to Table 9 of IS 456 using
20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost
and conveyance of all materials like cement, Sand of
Concrete coarse aggregate, water etc., to site and
including sales & other taxes on all materials including
all operational, incidental and labour charges such as
machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges for
finished item of work, but excluding centering,
shuttering.
Datas Page 64
65
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
centering charges for labour 845.00
Add Extra on L.C of centreing 845.00 0.40 338.00
9419.85
Add 13.615 % overhead charges, Contractor profit 9419.85 0.00000 0.00
Rate per Cum Rs 9419.85
Add Seign Charges of Metal cum 0.90 75.00 67.50
Add Seign Charges of Sand cum 0.45 40.00 18.00
Rate per 1 cum Rs 9505.35
c Plinth beams
BASIC COST per 1 cum 7921.85
centering charges for Materials 1335.00
centering charges for labour 1281.00
Add Extra on L.C of centreing 1281.00 0.40 512.40
11050.25
Add 13.615 % overhead charges, Contractor profit 11050.25 0.00000 0.00
Rate per Cum Rs 11050.25
Add Seign Charges of Metal cum 0.90 75.00 67.50
Add Seign Charges of Sand cum 0.45 40.00 18.00
Rate per 1 cum Rs 11135.75
B COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN
BUILDINGS
For Ground Floor
A. MATERIALS:
20mm HBG graded metal cum 0.90 1677.09 1509.38
Sand for concrete cum 0.45 2767.85 1245.53
Cement (As per CE PR MGNREGS memo) Kgs 400.00 5954.92 2381.97
B. LABOUR:
1st Class Mason day 0.17 480.00 80.16
2nd Class Mason day 0.17 405.00 67.64
Mazdoor (Both Men and Women) day 4.70 350.00 1645.00
Add Mucipal Limits 0.40 1792.80 717.12
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 472.60 472.60
40 mm neelde Vibrator hour 1.00 184.00 184.00
Water (including for curing) kl 1.20 103.00 123.60
BASIC COST per 1 cum Rs 8427.00
a Lintels
BASIC COST per 1 cum 8427.00
centering charges for Materials 1133.00
centering charges for labour 1360.00
Add Extra on L.C of centreing 1360.00 0.40 544.00
Rate per Cum Rs 11464.00
GF FF SF
Basic Rate 11464.00 11464.00 11464.00
Add Lift Charges @ 10% on LC 10% 0.00 441.39 882.78
Add Hire Charges for Centering on Scaffolding @10% of 10% 136.00
Labour Charges of Centering Rs 1211.0
Add 13.615 % overhead charges, Contractor profit 0.00000
0.00 0.00 0.00
Rate per Cum 11464.00 11905.39 12482.78
Add Seign Charges of Metal 0.90 67.50 67.50 67.50
Add Seign Charges of Sand 0.45 18.00 18.00 18.00
Rate per 1 cum Rs 11549.50 11990.89 12568.28
Datas Page 65
66
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
b Columns
BASIC COST per 1 cum 8427.00
centering charges for Materials 341.00
centering charges for labour 1909.00
Add Extra on L.C of centreing 1909.00 0.40 763.60
Rate per Cum Rs 11440.60
GF FF SF
Basic Rate 11440.60 11440.60 11440.60
Add Lift Charges @ 10% on LC 10% 0.00 518.25 1036.50
Add Hire Charges for Centering on Scaffolding @10% of 10% 190.90
Labour Charges of Centering Rs 1603.00
Add 13.615 % overhead charges, Contractor profit 0.00000
0.00 0.00 0.00
Rate per Cum Rs 11440.60 11958.85 12668.00
Add Seign Charges of Metal 0.90 67.50 67.50 67.50
Add Seign Charges of Sand 0.45 18.00 18.00 18.00
Rate per 1 cum Rs 11526.10 12044.35 12753.50
Datas Page 66
67
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
centering charges for labour 1820.00
Add Extra on L.C of centreing 1820.00 0.40 728.00
Rate per 10 Sqm Rs 11599.23
GF FF SF
Basic Rate 11599.23 11599.23 11599.23
Add Lift Charges @ 10% on LC 10% 389.34 778.69
Add Hire Charges for Centering on Scaffolding @10% of 10% 182.00
Labour Charges of Centering Rs 1520.00
Add 13.615 % overhead charges, Contractor profit 0.00000
0.00 0.00 0.00
Rate per 10 Sqm 11599.23 11988.57 12559.92
Add Seign Charges of Metal 0.90 67.50 67.50 67.50
Add Seign Charges of Sand 0.45 18.00 18.00 18.00
Rate per 1 cum Rs 11684.73 12074.07 12645.42
Datas Page 67
68
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Add Extra on L.C of centreing 1870.00 0.40 748.00
Rate per 10 Sqm Rs 16815.15
GF FF SF
Basic Rate 16815.15 16815.15 16815.15
Add Lift Charges @ 10% on LC 10% 0.00 396.34 792.69
Add Hire Charges for Centering on Scaffolding @10% of 10% 187.00
Labour Charges of Centering Rs 1570
Add 13.615 % overhead charges, Contractor profit 0.00000
0.00 0.00 0.00
Rate per 10 Sqm 16815.15 17211.49 17794.84
Add Seign Charges of Metal 1.58 118.13 118.13 118.13
Add Seign Charges of Sand 0.79 31.50 31.50 31.50
Rate per 1 cum Rs 16964.78 17361.12 17944.46
c Sunshades 75 mm at fixed end and 50mm at free end
Cost per Rm rmt 0.0375 6781.23 254.30
centering charges for Materials Sqm 0.60 224.00 134.40
centering charges for labour Sqm 0.60 209.00 125.40
Add Extra on L.C of centreing 125.40 0.40 50.16
564.26
Datas Page 68
69
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
BLD-CSTN-4-1 26 Providing High Yield Strength Deformed (HYSD)/ Thermo
Amendment
11.7 Mechanically Treated (TMT) / Mild steel (MS) steel bars
dt01.08.11
item 29 (Fe 415/ Fe 500 grade as per IS 1786-1979) of different
diameters for RCC works , including labour charges for
straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved
materials and size and tying and lap-splicing with binding
wire of 18 SWG, forming grills for reinforcement work as
per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all
incidental, operational, labour charges such as cutting,
bending, placing in position, tying including sales and other
taxes on all materials etc., complete for finished item of
work in all floors.( APSS No.126)
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps and wastage t 1.05 32065.83 33669.12
Binding wire VP308 kg 6.00 61.00 366.00
845 (b) Labour for cutting, bending, shifting to site, tying and
placing in position
Blacksmith / Bar bender day 10.00 565.00 5650.00
Mazdoor (Unskilled) day 10.00 350.00 3500.00
Add Mucipal Limits 0.40 9150.00 3660.00
(a+b) 46845.12
(c) Overheads on (a+b) @ 14% 46845.12 0.00000
0.00
Rate per t = a+b+c Rs 46845.12
BLD-CSTN-5-4 22 Brick Masonry in CM (1:6) with 2nd class Bricks
iv
traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement kg 48.00 5954.92 285.84
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 5299.78 2713.49
Sand for Mortor cum 0.20 2967.85 593.57
B. LABOUR:
Mason 1st class day 0.24 480.00 115.20
Mason 2 class
nd day 0.56 405.00 226.80
Mazdoor (unskilled) day 1.89 350.00 661.50
Add Mucipal Limits 0.40 1003.50 401.40
Grand Total Rs 4997.80
Gorund Floor
BASIC COST per 1 cum Cum 1.00 4997.80 4997.80
Add Scaffolding Charges Cum 1.00 0.00 0.00
4997.80
Add 13.615 % overhead charges, Contractor profit 4997.80 0.00000
0.00
Rs 4997.80
GF FF SF
Basic Rate 4997.80 4997.80 4997.80
Datas Page 69
70
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Add extra for Scaffolding Material Charges @ Rs 9.93 Sqm 4.348 43.18 86.35
Add extra for Scaffolding labour Charges @ Rs 58.66 Sqm / 4.348 255.05 334.84
77.01
Add Labour Comp on LC 0.00 0 0.00 0
Add Hire Charges for Centering on Scaffolding @ 50% of 50% 167.42
Labour Charges of Centering (Rs334.83+Rs 66.97 ) =401.81
Add 13.615 % overhead charges, Contractor profit 0.00 0.00 0.00 0.00
Rate per Cum 4997.80 5296.03 5586.41
Add Seign Charges of Bricks 512.00 19.71 19.71 19.71
Add Seign Charges of Sand 0.20 8.00 8.00 8.00
BASIC COST per 1 cum Rs 5025.51 5323.74 5614.12
BLD-CSTN-5-5 23 Brick Masonry in CM (1:8) with Bricks traditional size 23
v
x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement kg 36.00 5954.92 214.38
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 5299.78 2713.49
Sand for Mortor cum 0.20 2967.85 593.57
B. LABOUR:
Mason 1st class day 0.24 480.00 115.20
Mason 2 class
nd day 0.56 405.00 226.80
Mazdoor (unskilled) day 1.89 350.00 661.50
Add Mucipal Limits 0.40 1003.50 401.40
BASIC COST per 1 cum Rs 4926.34
GF FF SF
Basic Rate 4926.34 4926.34 4926.34
Add extra for Scaffolding Material Charges @ Rs 9.93 Sqm 4.348 43.18 86.35
Add extra for Scaffolding labour Charges @ Rs 61.83 Sqm / 4.348 268.84 381.67
87.78
Add Labour Comp on LC 0.40 0 107.53 152.67
Add Hire Charges for Centering on Scaffolding @ 50% of 50% 267.17
Labour Charges of Centering (Rs334.83+Rs 66.97 ) =401.81
Datas Page 70
71
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Basic Rate 1612.99 1612.99 1612.99
Add extra for Scaffolding Material Charges @ Rs 2.37 Sqm 10 23.70 47.40
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement kg 31.68 5954.92 188.65
Sand of Concrete (Screened ) cum 0.11 2967.85 326.46
Top Coat in CM(1:3), 4 mm thick
Cement kg 19.20 5954.92 114.33
Sand of Concrete cum 0.04 2967.85 118.71
Seigniorage charges for F.A cum 0.15
B. LABOUR:
Mason 1st class day 0.63 480.00 302.40
Mason 2 class
nd day 1.47 405.00 595.35
Mazdoor (unskilled) day 3.90 350.00 1365.00
Add Mucipal Limits 0.40 2262.75 905.10
BASIC COST per 10 sqm Rs 3916.00
GF FF SF
Basic Rate 3916.00 3916.00 3916.00
Add extra for Scaffolding Material Charges @ Rs 0.99 Sqm 10 9.90 19.80
Add extra for Scaffolding labour Charges @ Rs 6.18 Sqm/ 10 61.80 87.80
Rs 8.78 Sqm
Add Labour Comp on LC 0.40 0 24.72 35.12
Add Hire Charges for Centering on Scaffolding @ 10% of 50% 43.90
Labour Charges of Centering Rs 83
Add 13.615 % overhead charges, Contractor profit 0.00 0.00 0.00 0.00
3916.00 4012.42 4102.62
Add Seigniorage charges 0.15 6.00 6.00 6.00
BASIC COST per 10 sqm Rs 3922.00 4018.42 4108.62
BLD-CSTN-8- 26 Plastering with CM 2 coats, 20 mm thick, base coat in CM
10
(1:6), 16 mm thick and top coat in CM (1:4), 4mm thick
with Dubara sponze finishing.
Datas Page 71
72
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement kg 43.20 5954.92 257.25
Fine aggregate (Screened sand) cum 0.18 2967.85 534.21
Top Coat in CM (1:4), 4 mm thick
Cement kg 14.40 5954.92 85.75
Fine aggregate (Screened sand) cum 0.04 2967.85 118.71
B. LABOUR: 0.00
Mason 1st class day 0.63 480.00 302.40
Mason 2 class
nd day 1.47 405.00 595.35
Mazdoor (unskilled) day 3.90 350.00 1365.00
Add Mucipal Limits 0.40 2262.75 905.10
BASIC COST per 10 sqm Rs 4163.77
GF FF SF
Basic Rate 4163.77 4163.77 4163.77
Add extra for Scaffolding Material Charges @ Rs 0.99 Sqm 10 9.90 19.80
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3 cum 0.21 6072.60 1275.25
TBSC-G.II-04
Water proof compound BMt H01 kg 2.00 55.00 110.00
B. LABOUR
Mason 1st class day 0.66 480.00 316.80
Mason 2nd class day 1.54 405.00 623.70
Mazdoor (unskiled) day 3.70 350.00 1295.00
Add Mucipal Limits 0.40 2235.50 894.20
Grand Total 4514.95
Rs 4514.95
GF FF SF
Basic Rate 4514.95 4514.95 4514.95
Add extra for lift charges @10% of Labour Chagres 10% 312.97 625.94
Datas Page 72
73
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
Add 13.615 % overhead charges, Contractor profit 0.00000
0.00 0.00 0.00
4514.95 4827.92 5140.89
Add Seigniorage charges 0.21 8.40 8.40 8.40
BASIC COST per 10 sqm Rs 4523.35 4836.32 5149.29
BLD-CSTN-2-9 44 Filling the Excavated soils in trenches ,sides of the
Amnedment
foundations and basement with initial lead in layers not
Sno 17 &
Page13 of exceeding 15 cm thick consolidatiing each depposited layer
CSSR by watering and rampping including cost and conveyance of
water to work site and all operational incidental ,labour
charges hire charges and T & O Complete for finished item
APSS 309 &310)
Unit : 6 cum
Taking output : 6 cum
a) Labour
Mazdoor ( Unskilled) No 3.12 350.00 1092.00
Water Kl 0.72 103.00 74.16
Add Mucipal Limits 0.40 1092.00 436.80
1602.96
Add 13.615 % overhead charges, Contractor profit 1602.96 0.00000 0.00
Rate per 6 cum 1602.96
Rate per 1 cum Rs 267.16
BMT .F .30 45 Supplying & fixing collapsible steel shutters with vertical,
double channel of 20 x10x2 mm of 100 mm centre ,Bracers
with flat iron 40x40x6 mm with 38 mm dia steel pulleys,
the top, bottom and side vertical frames of the collapsible
gate with 65x65mmx8mm
MS Angle and middle guide rail at site height with
65mmx8mmMS flat for the pulleys to guide and fixed with
necessary hold fasts,bolts, nuts, rivets, locking
arrangements, stoppers, handles, all accessories all fixtures
and painted with one coat of approved steel primer etc.,
complete for finished item of work as per special spn 1105
2503.00
Add 13.615 % overhead charges, Contractor profit 2503.00 0.00000 0.00
BASIC COST per 1 Sqm Rs 2503.00
881 BMM-V.15 47 Supply , manufacture, making to specified design
andLabour charges for fabricating steel works like Window
Grills, Compound Wall Grills, Iron Doors, Windows including
cost of welding rods, power charges, excluding cost of
fixing in position
Unit = 1Kg
Cost of MS Steel kgs 1.00 37.00 37.00
Labour Charges for making TBSC T.I -16 kgs 1.00 26.00 26.00
Labour Charges for making BMM V15 kgs 1.00 4.00 4.00
Add Mucipal Limits 0.40 30.00 12.00
79.00
Add 13.615 % overhead charges, Contractor profit 79.00 0.00 0.00
BASIC COST per 1 KG Rs 79.00
Datas Page 73
74
Amount
Index-code S No Description Unit Quantity Rate Rs.
Rs.
DBSECTION_2:
Select from Lead Chart
Datas Page 74
DETAILED SUB ESTIMATE FOR ELECTRIFICATION
Electrical Work
1 SB73.Supplying and Fixing of 25mm dia 2.0 mm thick PVC Conduit pipe concealed in
wall with all required accessories including chiselling the wall whereever necessaty
including Masonary work for Light,fan and separate plug point wiht T.W.Deep box
including all labour charges etc & complete
In Walls 900.00 900.00
Rmt Rmt
nos nos
nos nos
11 Supply and fixing of LAN outlet with anodised GI box of with front plate and plug in
type Networking socket.
1 x 1 10.00 10.00
nos nos
0.00 0.00
12 Supply and fixing of Telephone outlet with anodised GI box with front plate and other
accessories.
1 x 1 2.00 2.00
nos nos
2.00 0.00
13 Supply and fixing SPN Distribution board with IP-20 protection suitable for single phase
Earth Leakage Circute Braker (ELCB) / Residual Current Circute Braker (RCCB) / Double
Pole (DP) Isolator as incomer and 10kA SP MCBs as out going including internal
connections and labour charges for surface / flush mounting etc., complete.
1 x 1 4.00 4.00
No nos
4.00 3146.00
as per size specified in the Data, using 40mm dia 'B' class GI pipe of 2.5 Mtrs length with
necessary accessories with hume pipe ring duly providing staggered holes including
filling with equal proportion of Salt and Charcoal in layers and all labour charges etc.,
15 Supply and Transportation of 1x40W patty type tube light luminaire with copper choke,
16 Supply of 1200 mm (48") sweep 230V, A.C 50 Hz.Ceiling fan (ISI Mark) with 3 Blades
and double ball bearings with all standard accessories.
S/F Fans 1 x 1 86.00 86.00
Nos
86.00 1797.40 154576.00
17 Supply and erecting Stepped type electronic Regulator for ceiling fans
900/1200/1400mm sweep complete erected on existing board.and as per 9.7.26 of Sta
revised data of BLD -ELEC-9.7.26
For Fans 1 x 1 86.00 86.00
1 Supplying & Fixing of Indian Pattern White Glazed 1st Quality of ISI Orissa Pan with "P" or
"S" trap Hindware/Parryware/Neycer - ISI Mark 630x450 mm including cost and conveyance
2 Supplying and Fixing European Water Closet of 1st quality conforming to IS:2556-Part-2-
1973 of Hindustan / Neycer or Parryware make white glazed with 'P' trap
For Principal Room 2 x 1 2.00
3 Supplying and fixing TV shape mirror with plastic frame size 609.6 mm x 457 .2
mm
4.00 513.00 2052.00
4 S& F GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI
fittings including the cost of pipe & its fittings & labour charges complete
20 MM dia 150.00 206.00 30900.00
Rm Per Rm
5 S & F Gunmetal Gate (GM peet) valve as per IS -778 Class - I, Indian make heavy
type - 25 mm NB Size
20 MM dia 8.00 621.00 4968.00
6 B89.Prince/ Sudhakar make or equivalent quality PVC /SWR pipes & fittings ( as
per ISI standards) 4kg/cm2 75mm dia.(double socket)
Rm Per Rm
7 B90.Prince/ Sudhakar make or equivalent quality PVC /SWR pipes & fittings ( as
Rm Per Rm
8 Supply,fixing of 110 mm deep PVC floor traps of self cleansing design with outlet
size of 75mm diameter of approved make, including making connection with PVC
soil/waste pipes using rubber gaskets and top shall be cover with removable CP
strainer, etc., complete 110mm deep PVC floor traps(101.6)
10.00 144.00 1440.00
Nos Each
Nos Each
[Prince/Sudhakar or any ISI Brand] including cost and conveyance of all materials
11 Supply, and fixing of approved make Vent cowl above the Soil & waste pipes for
ventilation as required to avoid foul smell. 110mm
10.00 19.00 190.00
Nos Each
13 Supplying & fixing 150 mm x 100 mm SWG gully traps of ISI make conforming to
ISI 651 & 4127 with C.I Grating & Constg. Brick masonry in CM 1:6 prop.
Intermediate chamber and fitted with 304.8 mm x 288.6mm (12"x9") C.I Frame
and hinged cover.
20.00 455.00 9100.00
14 Providing & placing on Terrace polyethylene water storage tank with Double
layer approved brand & manufacture with cover and suitable locking
arrangement & making necessary holes for inlet & outlets and overflow pipes but
without fittings & base support for tanks.( From ssr rates sno 311) 2000lts
8000.00 6.00 48000.00
Lt Per Lt
15 Supplying, laying, jointing and testing 152.4mm SWG SP1 pipes of ISI make
confirming to ISI 651 and 4127 with air tight cement joints in CM1.5:1 propot.
Including excavation of tremches and socket pits in any soil(except rock with
wiring blasting) upto 1524mm depth and refilling with watering and tamperibg.
17 Supplying, laying, jointing and testing 101.6 mm SWG SP-1 pipes of ISI make
conforming to ISI 651 & 4127 with airtight cement joints in CM 1.5:1 prop.
Including excavation of trenches and socket pits in any soil (except rock
requiring blasting) up to 1524 mm(5'0") depth and refilling with watering and
tamping.
Rm Per Rm
18 Supplying, laying, jointing and testing 101.6 mm SWG SP-1 pipes of ISI make
conforming to ISI 651 & 4127 with airtight cement joints in CM 1:5:1
prop.including excavation of trenches and socket pits in any soil (except rock
requiring blasting) up to 914.4 mm (3'0") depth and refilling with watering and
tamping
Rm Per Rm
Nos Each
19 Supplying & Fixing Indian make Flat Back Wash Hand Basin
(HSW/Parryware/Neycer) 1st quality conforming to IS:2556-Part-4:1972 with
waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting with
parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal
bore Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/
Senior/ Nice/ Esso or equivalent complete with standard CI brackets including
woodenblock: 450 x 300 mm - Double C.P. Pillar cock
10.00 1832.00 18320.00
19 Supplying & Fixing white glazed flat back Bowl urinals of size 440 mm x 265
mm x 315 mm with internal flushing rim fixed with screws complete Indian
make (HSW/Parry/Neycer) conforming to IS:2556-1995
20 Supply and fixing of NP BIP tap indian make 300 grams SSRNo 182
3 PCC (1:4:8) prop nominal mix (cement:FA:CA) using 40mm size HBG (SS5) metal from
approved quarry (obtained by blasting) including Cost and Conveyance of all materials like
cement,sand,CA,water etc. to site, including all operational, incidental,& labour charges such
as mixing,laying and ramming CC in layers in position not exceeding 15cm,finishing
topsurface,curing concrete, etc,complete for finished item of work for Foundations and
Flooring Bed (APSSNo.402)
10 Brick Masonry in superstructure with CM (1:6) Prop of 230 mm thick wall using 2nd class
traditional Bricks of size 23x11x7cm having minimum crushing strength of 50 kg/cm2 including
Cost and Conveyance of all materials scaffolding charges, etc., complete for finished item of
work. (APSS No. 501 & 504).
For Long wals 2 x 1 10.00 0.35 2.100 14.70
6 Plain Cement Concrete corresp.to M20 grade Nominal mix , Metal of 20mm size HBG (SS5)
metal from approved quarry including Cost and Conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site, including all operational, incidental and labour
charges such as mixing, laying, curing concrete for 21 days etc., complete for finished item of
work. (APSS No. 402) but excluding cost of steel and its fabrication charges for finished item of
work
F) For flooring bed
Page 82 of 245
6 Vibrated reinforced Cement Concrete corresp.to M20 grade Design mix , Metal of 20mm size
HBG (SS5) metal from approved quarry including Cost and Conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including all operational, incidental and
labour charges such as mixing, laying, curing concrete for 21 days etc., complete for finished
item of work. (APSS No. 402) but excluding cost of steel and its fabrication charges for finished
item of work
F) For Roof Slab(1:1.5:3) Prop.125 mm thick Ground Floor
35.06
35.10 12616.41 44284.00
sqm 10 sqm
14 Providing Plastering with CM (1:3) prop. 20mm thick (average) mixed with water proofing
compound at 1Kg/bag of cement, laid over roof slab when it is green, finished smooth with a
floating coat of neat cement and thread lining at regular intervals of 45cmx45cm including
Cost and Conveyance of all materials complete for finished item of work (APSS No. 901 & 903).
(CSSR)
For Bottom 1 x 1 10.00 3.000 30.00
142.39
142.40 4514.95 64293.00
Sqm Per 10 Sqm
33 Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of
8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in position
with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement
work as per approved designs and drawings including cost and conveyance of bars from
approved sources to site of work, including cost and conveyance of binding wire, cover blocks
and all operational, incidental, and labour charges such as cutting, bending, placing in
position, tying etc., and Countryes & other taxes,on cost of all materials complete for finished
item of work (APSS No.126) in all floors.
For Roof Slab 150 mm thick 300.00 1 300.00
Page 83 of 245
DETAILED SUB ESTIMATE FOR BORE WELL AND PUMP SET
Construction of Community Hall at RB Nagar in Shamshabad(v&m)
Sl.
Name of Component Nos Rate Total Amount
No
1 2 3 4 5
1 Drilling of Bore well by down the hole
hammer DTH drilling of finished dia of 163
mm dia in all formation to a depth
specification and reaming the bore th the
required dia to suit lowering of 175 mmdia 125x2Nos 270.00 72900.00
caseibg average pressure of 7kgs / sq cm
conducting yield test inclusive of all other
charges in all over the dist
9027.00
Sl.
Name of Component Nos Rate Total Amount
No
1 2 3 4 5
1 Manufacture,supply, and delivery of MS
angle make furniture to Comadate 4
students in the bench with table,drawer 200 2500.00 500000
facility
1 F 2 3 4 5 6 7 8 9 10 11
1 MBG01.Unskilled labour charges Earth work excavation and
depositing on bank with initial lead of 10m and initial lift of
2m in Loamy and Clayey Soils like B.C. Soils, red earth &
Ordinary Gravel (SS 20-B) including shoring, strutting,
sheeting, planking and dewatering including cost of hire
charges of T & P, labour charges etc., complete for finished
item of work for Foundation of Building.(APSS No. 308)
For SBC 20TN/sqm only
F1 Type
1 x 6 2.00 2.00 1.65 39.60
F2 Type
1 x 12 1.80 1.80 1.65 64.15
F3 Type
1 x 1 1.35 1.35 1.65 3.01
144.07
MBG +1
Unskilled labour charges As Per RSSR 144.10 0.00 0.00 0.00
Cum. 1cum
3 MBG+5 PCC (1:5:10) prop nominal mix (cement: FA: CA) using
Page 86 of 245
For Wall (D1-D7)
(20.40-3.50*1.80-2*2.0- 1 x 1 9.13 0.60 0.10 0.55
0.50*1.350-0.30)
2.44
MBG +5
26.44 4538.17 119974.00 119974.00
Cum. Cum.
Total Amount
Page 87 of 245
4 MBG06.PCC (1:4:8) prop nominal mix (cement:FA:CA) using
40mm size HBG (SS5) metal from approved quarry (obtained
by blasting) including Cost and Conveyance of all materials
like cement,sand,CA,water etc. to site, including all
operational, incidental,& labour charges such as mixing,laying
and ramming CC in layers in position not exceeding
15cm,finishing topsurface,curing concrete, etc,complete for
finished item of work for Foundations and Flooring Bed
(APSSNo.402)
F1 Type
1 x 6 2.00 2.00 0.15 3.60
F2 Type
1 x 12 1.80 1.80 0.15 5.83
F3 Type
1 x 1 1.35 1.35 0.15 0.27
10.79
MBG +4
10.80 4746.91 51267.00 51267.00
Cum. Cum.
21.22
For Steps at
Entrance 1 1 x 1 5.40 3.00 0.15 2.43
Page 88 of 245
For steps at
Entrance 2 1 x 1 4.20 3.00 0.15 1.89
9.45
11.83
42.50
Cum.
MBG +6
42.50 4077.32 173286.00 173286.00
7 Vibrated reinforced Cement Concrete corresp.to M20 grade
Design mix , Metal of 20mm size HBG (SS5) metal from
approved quarry including Cost and Conveyance of all
materials like cement, sand, coarse aggregate, water etc. to
site, including all operational, incidental and labour charges
such as mixing, laying, curing concrete for 21 days etc.,
complete for finished item of work. (APSS No. 402) but
excluding cost of steel and its fabrication charges for finished
item of work
A) For Column Footings
F1 Type
1 x 6 1.85 1.85 0.40 8.21
F2 Type
1 x 12 1.65 1.65 0.38 12.25
F3 Type
1 x 1 1.20 1.20 0.30 0.43
Total 20.89
20.90
Cum.
MBG +7
20.90 8943.65 186922.00 186922.00
Cum. Per Cum
B) Pedastals
Pedastal P1 Type
1 x 4 0.60 0.60 0.60 0.86
Pedastal P2 Type
1 x 15 0.45 0.45 0.60 1.82
2.68
Cum.
Page 89 of 245
MBG +8
2.68 9419.85 25245.00 25245.00
Cum. Per Cum
6.58
MBG +11
6.58 11440.60 75279.00 75279.00
Cum. PerCum.
4.43
MBG +12
4.43 11958.85 52978.00 52978.00
Cum. PerCum.
1.28
Or Say 1.28
MBG +12A
1.28 12668.00 16215.00 16215.00
Cum. PerCum.
D) Plinth beams
External Beams
EPB ( A1-A7)
(20.40-7*0.3) 1 x 1 18.30 0.30 0.30 1.65
EPB( D1-D7)
(20.40-7*0.3) 1 x 1 18.30 0.30 0.30 1.65
EPB ( A1-D1)
(8.175-3*0.38) 1 x 1 7.04 0.30 0.30 0.63
EPB (A1) & A2 For Stair case 1 x 2 1.50 0.30 0.30 0.27
Page 90 of 245
EPB ( D1) & D2 )
For Entrance Foyer 1 x 2 1.50 0.30 0.30 0.27
EPB ( D1) & D2 )
For Entrance Foyer 1 x 1 3.00 0.30 0.30 0.27
EPB ( A7-D7)
(8.175-3*0.38) 1 x 1 7.04 0.30 0.30 0.63
Internal Beams
5.37
IPB ( B1-B2)
(3.3-0.3) 1 x 1 3.00 0.30 0.30 0.27
IPB ( A2-D2)
(8.175-3*0.38) 1 x 1 7.04 0.30 0.30 0.63
IPB ( A3-D3)
(8.175-2*0.45) 1 x 1 7.28 0.30 0.30 0.65
IPB (A4-D4)
(8.175-2*0.45) 1 x 1 7.28 0.30 0.30 0.65
IPB ( A5-D5)
(8.175-3*0.38) 1 x 1 7.04 0.30 0.30 0.63
IPB ( A6-D6)
(8.175-3*0.38) 1 x 1 7.04 0.30 0.30 0.63
IPB ( C5-C7)
(3.6+3.30-0.30/2-0.38) 1 x 1 6.37 0.30 0.30 0.57
For Attached Toilet PB
(3.915+0.23-2*.38) 1 x 1 3.39 0.15 0.30 0.15
Total 4.27
9.64
Cum.
MBG +9
9.64 11050.25 106524.00 106524.00
Cum. Per Cum.
MLB ( A1-A2)
(3.3+0.3) 1 x 1 3.60 0.23 0.30 0.25
B1 ( A2-A7)
(3.3*4+3.6+0.30) 1 x 1 17.10 0.23 0.30 1.18
B2 ( B1-B2)
(3.3+0.30) 1 x 1 3.60 0.23 0.30 0.25
B 3( B5-B7)
(3.6+3.3+0.30) 1 x 1 7.20 0.23 0.30 0.50
B4 (C1-C7)
(3.3*5+3.6+0.30) 1 x 1 20.40 0.23 0.30 1.41
Total 9.02
MBG +13
9.05 11024.63 99773.00 99773.00
Cum. Per Cum.
Page 91 of 245
MLB ( A1-A2)
(3.3+0.3) 1 x 1 3.60 0.23 0.30 0.25
B1 ( A2-A5)
(3.3*4+0.30) 1 x 1 13.50 0.23 0.30 0.93
B2 ( B1-B2)
(3.3+0.30) 1 x 1 3.60 0.23 0.30 0.25
B4 (C1-C4)
(3.3*3+3.6+0.30) 1 x 1 20.40 0.23 0.30 1.41
B6 (A1-D1)
(8.175+0.23) 1 x 1 8.41 0.23 0.30 0.58
B7 (A2-D2)
(8.175+0.23) 1 x 1 8.41 0.23 0.30 0.58
B8 ( A3-D3)
(8.175+0.23) 1 x 1 8.41 0.23 0.45 0.87
B8 ( A4-D4)
(8.175+0.23) 1 x 1 8.41 0.23 0.45 0.87
B9 ( A5-C5)
(3.915+0.23) 1 x 1 4.15 0.23 0.300 0.29
6.03
MBG +14
6.05 11383.31 68869.00 68869.00
Cum. Per Cum.
MLB ( A1-A2)
(3.3+0.3) 1 x 1 3.60 0.23 0.30 0.25
B2 ( B1-B2)
(3.3+0.30) 1 x 1 3.60 0.23 0.30 0.25
B6 (A1-B1)
(3.108+1.50+0.23) 1 x 1 4.84 0.23 0.30 0.33
B6 (A1-B1)
(3.108+1.50+0.23) 1 x 1 4.84 0.23 0.30 0.33
1.16
MBG +14 A
1.20 11902.10 14283.00 14283.00
Cum. Per Cum.
169.91
sqm
MBG +15
169.91 12616.41 214365.00 214365.00
sqm 10 sqm
6.48
sqm
MBG +15A
6.48 16815.15 10896.00 10896.00
sqm 10 sqm
Page 92 of 245
Deduct 1 x -1 3.30 3.000 -9.90
91.14
sqm
MBG +16
91.14 13005.75 118534.00 118534.00
sqm 10 sqm
19.90
sqm
MBG +16A
19.90 17794.84 35412.00 35412.00
sqm 10 sqm
13.48
sqm
MBG +17
13.48 13294.54 17921.00 17921.00
sqm 10 sqm
13.48
sqm
MBG +18
13.48 13683.88 18446.00 18446.00
sqm 10 sqm
8 RCC M20 Grade Design mix using 20mm size HBG(SS5) machine
crushed from approved quarry including Cost & Conveyance of
all materials like cement,FA,CA,water etc. to site including
C429 & other taxes on all materials all operational,incidental
& labour charges such as centering,shuttering,scaffolding,lift
charges,machine mix,laying CC,curing CC etc,complete but
excluding cost of steel & its fabrication charges for finishd
item of work for Lintels (APSSNo.402&403) For Lintelssteel and
its fabrication charges for finished item of work (APSS No.402
& 403) for LINTELS (G.F.)
Ground floor
Page 93 of 245
Over Doors D4 1 x 4 1.15 0.23 0.15 0.16
1.41
MBG +19
1.45 11464.00 16623.00 16623.00
Cum. per Cum.
First Floor
Or Say 1.01
Cum.
MBG +20
1.01 11905.39 12024.00 12024.00
Cum. per Cum.
9 RCC M20 Grade Design mix using 20mm size HBG(SS5) machine
crushedincluding Cost & Conveyance of all materials including
C429 & other taxes on all materials all operational, incidental
& labour charges such as centering,shuttering,scaffolding,lift
charges,machine mix,laying CC,curing CC etc,complete but
excluding cost of steel & its fabrication charges
(APSSNo.402&403)for Sunshades 75 mm thick at fixed
end 50 mm thick at free end
Ground Floor
On Windows W1 1 x 12 1.75 21.00
Total 25.20
Rmt
MBG +21
25.20 564.26 14219.00 14219.00
Rmt per Rmt
First Floor
On Windows W1 1 x 6 1.75 10.50
Page 94 of 245
On Windows W2 1 x 1 2.20 2.20
Total 18.90
MBG +22
18.90 615.37 11631.00 11631.00
Rmt per Rmt
First Floor
For Doors 4 x 10 0.23 0.20 0.13 0.23
For Windows 4 x 9 0.23 0.20 0.13 0.21
For Ventilators 2 x 2 0.23 0.20 0.13 0.02
total 0.46
Material charges including skilled and semi-skilled labour charges
0.50 5733.19 0.00
Cum. per Cum.
Page 95 of 245
Deductiions
Doors D1 1 x 2 1.20 0.23 2.10 1.16
Lintles on Door
and Windows
Page 96 of 245
Over Doors D4 1 x 3 1.15 0.23 0.15 0.12
Deductiions 17.53
Door D3 1 x 1 0.90 0.23 2.10 0.43
Lintles on Door
and Windows
Page 97 of 245
Wall A6-D6
(8.175+0.3-3*.38) 1 x 1 7.34 0.115 2.875 2.43
Wall A7-D7
(8.175+0.3-3*.38) 1 x 1 7.34 0.115 2.875 2.43
Toilet between Wall
(3.8) 1 x 1 3.80 0.115 3.175 1.39
Lintles on Door
and Windows
FIRST FLOOR
For Wall B1-B5
(3.3*3+0.30-4*.3) 1 x 1 9.00 0.115 2.875 2.98
For Wall C1-C5
(3.3*4+0.30-5*.3) 1 x 1 12.00 0.115 3.175 4.38
For Wall A2-B2
(3.108-.23-2*.0.38) 1 x 1 2.80 0.115 2.875 0.93
For Wall A3-B3
(3.108-.23-2*.0.38) 1 x 1 2.80 0.115 2.725 0.88
For Wall A4-B4
(3.108-.23-2*.0.38) 1 x 1 2.80 0.115 2.725 0.88
For Wall C3-D3
(3.108-.23-2*.0.38) 1 x 1 2.80 0.115 2.725 0.88
For Wall C4-D4
(3.108-.23-2*.0.38) 1 x 1 2.80 0.115 2.725 0.88
Deductiions 11.81
Doors D3 1 x 6 0.90 0.115 2.10 1.30
Lintles on Door
and Windows
Doors D3 1 x 6 1.30 0.115 0.15 0.13
SECOND FLOOR
For paprapet wall (A1-A5)
(3.3*4+0.30-5*.30) 1 x 1 12.00 0.115 1.200 1.66
For paprapet wall(D1-D5)
(3.3*4+0.30-5*.30) 1 x 1 12.00 0.115 1.200 1.66
Page 98 of 245
For paprapet wall (A1-D1)
(8.175+0.30-3*.38) 1 x 1 7.34 0.115 1.200 1.01
For paprapet wall (A5-D4)
(8.175+0.30-3*.38) 1 x 1 7.34 0.115 1.200 1.01
For Wall Projections of Head
room 1 x 2 1.20 0.115 1.200 0.33
For Wall offest
1 x 1 1.50 0.115 1.200 0.21
5.88
MBG +31A
5.88 7650.46 44985.00 44985.00
Cum. per Cum.
255.07
Deductions
PCC (1:5:10) 26.44
PCC (1:4:8) 10.79
RR Masonory, 25.54
Footings ,pedastals, 23.57
Columns below Gl 1.26
Internal Plinth beams 4.27
For Cons of SP tank 17.30
3.70x2.75x1.70
109.16
Total Filling Qty required 255.07 - 109.16 145.91
MBG +23 Total available Excavated earth using 70% 100.87 267.16 26948.00 26948.00
Unskilled labour charges
Cum. per Cum.
Page 99 of 245
14 .Filling with gravel (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not
exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including cost and Cost and Conveyance
of water to site and all operational, incidental, labour
charges, sales and other taxes etc, hire charges of T & P etc.,
complete for finished item of work. (APSS NO. 309 & 310)
145.91 - 100.87 45.04
MBG +24 Material Component 45.04 0.00 0.00 0.00
cum per cum
MBG +25 Un skilled labour Component 45.04 0.00 0.00 0.00
cum per cum
213.24
MBG +46
213.25 4514.95 96281.00 96281.00
Sqm Per 10 Sqm
216.83
MBG +32
216.85 1612.99 34978.00 34978.00
Sqm 10 sqm
FIRST FLOOR
Head Room 1 x 1 4.73 3.00 14.19
103.16
MBG +33
103.20 1812.39 18704.00 18704.00
Sqm 10 sqm
SECOND FLOOR
Head Room 1 x 1 4.73 3.00 14.19
Sun Shades on Opening
for Both Sides 2 x 1 1.60 0.60 1.92
16.11
MBG +33A
16.15 1995.55 3223.00 3223.00
Sqm 10 sqm
345.82
MBG +34
345.85 3916.00 135435.00 135435.00
Sqm 10 sqm
First Floor
Record Room
(2*3.18+2*3.0) 1 x 1 12.36 3.175 39.24
Computer Room
(2*6.8+2*3.0) 1 x 1 19.60 3.175 62.23
PO Room
(2*3.07+2*3.0) 1 x 1 12.14 3.175 38.54
APO Room
(2*3.18+2*3.0) 1 x 1 12.36 3.175 39.24
Ladies Toilet
(2*1.39+2*3.0) 1 x 1 8.78 3.175 27.88
Crosswalls of
Toilet 2 x 2 1.39 3.175 17.65
Gents Toilet
(2*2.06+2*3.0) 1 x 1 10.12 3.175 32.13
Cross wall Toilet
1 x 2 1.20 3.175 7.62
Cross wall Toilet
1 x 2 2.06 3.175 13.08
Corridor Portion
2*(3.3*4)+2*1.50 1 x 1 29.40 3.175 93.35
Head Room
(0.15+3.0+1.50+3.0+1.50+ 1 x 1 12.30 (3+2.7)/2 35.06
3.0+0.15)
Deductiions 406.02
Doors D3 1 x 7 0.90 2.10 13.23
371.77
MBG +35
371.80 4012.42 149182.00 149182.00
Sqm 10 sqm
Second Floor
Head Room
(0.15+3.0+1.50+3.0+1.50+ 1 x 1 12.30 (3+2.7)/2 35.06
3.0+0.15)
Deductiions 35.06
Doors D3 1 x 1 0.90 2.10 1.89
On Windows W2 1 x 1 1.80 1.30 2.34
4.23
30.83
MBG +35A
30.85 4102.62 12657.00 12657.00
Page 103 of 245
Sqm 10 sqm
. 200.02
MBG +36
200.05 4163.77 83296.00 83296.00
Sqm 10sqm
. 210.77
MBG +37
210.80 4260.19 89805.00 89805.00
Sqm 10sqm
. 136.32
MBG +37 A
136.35 4350.39 59318.00 59318.00
Sqm 10sqm
78.78
orsay 236.81
Sqm
MBG +49
236.81 5881.67 139284.00 139284.00
Sqm 10 sqm
orsay 10.14
Sqm
Total 27.37
MBG +56
27.37 6286.86 17207.00 17207.00
Sqm 10 sqm
3.58
orsay 7.30
Sqm
MBG +50
7.30 9086.44 6633.00 6633.00
Sqm 10 sqm
16.31
orsay 16.31
Sqm
Page 107 of 245
MBG +54
16.31 8996.45 14673.00 14673.00
Sqm 10 sqm
41.28
Material charges including skilled and semi-skilled labour charges
41.28 820.89 0.00
Sqm 10 sqm
24 Supply and fixing of salwood Door single shutter fully pannlled door
of size 1.20 x 2.1 mt with frame made of well seasoned sal Wood
scantlings of size 100 x 75mm and bottom reeper of size 75x38mm
and shutter made of side rails 125mm X38, top rail 125mmX38mm,
bottom rail 175mmX38mm and intermediate rails of 125 x 38 mm and
panels - 4 no's are of 25mm thick as per approved design with
fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long aluminium aldrop-1
no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no,
150mm long Tower bolts - 1no's alumium, 200mm long Tower bolts
- 1no's alumium,Aluminium fancy handles 150mm long 1no's, with
necessary screws complete including cost and conveyance of all
materials and labour charges etc. complete as per specifications
(APSS NO.1001 & 1002)
D1 Main Entrance 1 x 2 2
D2 Meeting Hall 1 x 1 1
MBG +38
3.00 #REF! #REF! #REF!
Nos Per Each
D3 (0.90x2.10)GF 1 x 5 Nos 5
D3 (0.90x2.10)FF 1 x 7 Nos 7
MBG +39
12 #REF! #REF! #REF!
Nos Per Each
26 Supply and fixing of salwood Door single shutter fully pannlled door
of size 0.75 x 2.1mt with frame made of well seasoned teak Wood
scantlings of size 100 x 75mm and bottom reeper of size 75x38mm
and shutter made of side rails 125mm X38, top rail 125mmX38mm,
bottom rail 125mmX38mm and intermediate rails of 125 x 38 mm and
panels - 4 no's are of 25mm thick as per approved design with
fixtures of 6 nos of 9" ' z" holdfasts, 300 mm long aluminium aldrop-1
no,125mm long aluminium butt hinges 4 No's, Door stoppers-1 no,
150mm long Tower bolts - 1no's alumium, 200mm long Tower bolts
- 1no's alumium,Aluminium fancy handles 150mm long 1no's, with
necessary screws complete including cost and conveyance of all
materials and labour charges etc. complete as per specifications
(APSS NO.1001 & 1002)
D4(0.75x2.10) 1 x 3 Nos 3
1 x 3 Nos 3
MBG +40
6 #REF! #REF! #REF!
Nos Per Each
27 Supply and fixing of Window size (W1) 1.35 x 1.30 mt with sal
wood frame of size 75x100mm along with II class teak wood
three shutters made with styles& rails of 100mmx30mm thick
with 12mm prelaminated particle board both side laminated
interior grade and S/F of 4Nos. MS Hold fasts, 6Nos. MS tower
bolts 100mm long. 6 Nos. MS Hinges 75mm long,2Nos MS
Handles 3 Nos window stays. incl. all labour charges such as
making window frame & shetter and fiXing 11 Nos. 16mm plain
safety bars in to frame etc,
W1(1.35x1.30) GF 1 x 12 1.35 1.30 12
W1(1.35x1.30) FF 1 x 6 1.35 1.30 6
MBG +41
18 #REF! #REF! #REF!
Nos Per Each
Sqm
MBG +58 748.50 347.31 25996.00 25996.00
Sqm 10 sqm
Sqm
MBG +59 588.50 1638.50 96426.00 96426.00
Sqm 10 sqm
32 Painting to New wood work with two coats of ready mixed synthetic
enamel paint first quality all shades to give an even shade over base
and labour charges etc., complete for finished item of work.(3 coats)
199.77
or say 199.80
Sqm
MBG +60
199.80 1021.60 20412.00 20412.00
Sqm 10 Sqm
Total Amount
33 Supply and fixing of 110mm dia ISI mark PVC rain water spouts
of 2.5mm thick including Cost of necessary pvc bends, shoes
and M.S.clamps and all other accessories and fixing in
position including cost and conveyance of all materials to
site , seigniorage charges Countryes and other taxes on all
materials, all operational, incidental and labour cahrges such
as fixing in alignment etc., complete for finished item of
work.(APSS NO1328)
For Rain water Spouts
pipes 3 x 3 3.50 31.50
34 Providing high yield strength deformed (HYSD) steel bars (Fe
415 grade as per IS 1786-1985) of 8mm to 40mm diameters,
cutting, bending, to required sizes and shapes placing in
position with cover blocks of approved size and binding wire
of 20SWG, forming grills for reinforcement work as per
approved designs and drawings including cost and conveyance
of bars from approved sources to site of work, including cost
and conveyance of binding wire, cover blocks and all
operational, incidental, and labour charges such as cutting,
bending, placing in position, tying etc., and Countryes & other
taxes,on cost of all materials complete for finished item of
work (APSS No.126) in all floors.
For Footings 0.83
MBG +61
50.00 88.20 4410.00 4410.00
35 BB74.Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI
MBG +62
100.00 71.78 7178.00 7178.00
36 Wiring with 2 of 14/0.3mm (1.0 Sq.mm) Finolex P.V.C.
insulated F.R. flexible copper cable (ISI MARK) in existing pipe
with 6A switch control and 3/2 pin sockets fixing on separate
board including all labour charges etc., complete.
IN GF & FF 1 x 1 64.00 64.00
points points
MBG +63
64.00 455.97 29182.00 29182.00
37 Supply and fixing of 6A 3 pin wall plug socket with 6A switch
control on a common switch board with earth continuity
including wire leads, earth connections along with all labour
charges etc., complete.
IN GF & FF 1 x 1 20.00 20.00
nos nos
MBG +64
20.00 131.30 2626.00 2626.00
38 Supply and fixing of 6A 5pin socket with switch in anodised GI
box and front plate complete with fixing accessories etc.,
including labour charges complete as required confirming to
IS.(independent)
IN GF & FF 1 x 1 9.00 9.00
nos nos
MBG +65
9.00 324.80 2923.00 2923.00
39 Run of Mains: Supply & run of 2 of 1100V grade FRLS 2.5
Sq.mm & 1 run of 1.5 Sq.mm PVC insulated Copper wires, in
existing pipe including all accessories, labour charges
complete as required confirming to IS.
Supply and run of 2 of
36/0.3mm (1.5 Sq.mm)
1 x 1 75.00 75.00 0.00
Supply and run of 2 of
36/0.3mm (2.5 Sq.mm)
1 x 1 50.00 50.00
Rmt
MBG +66
50.00 56.25 2813.00 2813.00
40 Supply and fixing of LAN outlet with anodised GI box of with
front plate and plug in type Networking socket.
1 x 1 2.00 2.00
MBG +68
2.00 0.00 0.00
42 Supply and fixing SPN Distribution board with IP-20 protection
suitable for single phase Earth Leakage Circute Braker
(ELCB) / Residual Current Circute Braker (RCCB) / Double Pole
(DP) Isolator as incomer and 10kA SP MCBs as out going
including internal connections and labour charges for
surface / flush mounting etc., complete.
1 x 1 1.00 1.00
No nos
MBG +69
1.00 3146.00 3146.00 3146.00
43 Providing independent earthling by excavating a trench to a
depth of 2.1 M in all soils, as per size specified in the Data,
using 40mm dia 'B' class GI pipe of 2.5 Mtrs length with
necessary accessories with hume pipe ring duly providing
staggered holes including filling with equal proportion of Salt
and Charcoal in layers and all labour charges etc., complete
for small quarters.
For Buildinng 1 x 1 1.00 1
Nos
MBG +70
1.00 2593.60 2594.00 2594.00
45 Supply and Transportation of 1x40W patty type tube light
luminaire with copper choke, starter etc., including 1No 40W
tube etc., complete.
MBG +71
S/F Tubes 1 x 1 28.00 28 471.48 13201.00 13201.00
Nos Each
#REF!
1 2 3 4 5 6 7 8 9 10 11 12
1 Footing F1 2 2 x 16 2.30 147.20 0.89 131.01
2 Footing F2 10 18 2 x 12 2.00 864.00 0.62 535.68
3 Footing F3 10 8 2 x 10 1.65 264.00 0.62 163.68 830.37
4 Pedstal P1 10 6 1 x 8 1.05 50.40 0.62 31.25
5 Pedstal P2 10 18 1 x 8 0.90 129.60 0.62 80.35 111.60
6 Log Bar Column C1 20 4 1 x 4 0.45 7.20 2.46 17.71
Log Bar Column C1 16 4 1 x 8 7.50 240.00 1.57 376.80
Lateal ties Column C1 8 4 1 x 42.333 1.40 237.07 0.39 92.46
7 Log Bar Column C2 20 2 1 x 4 7.50 60.00 2.46 147.60
Log Bar Column C2 16 2 1 x 4 7.50 60.00 1.57 94.20
Lateal ties Column C2 8 4 1 x 42.333 1.30 220.13 0.39 85.85
8 Column C3 16 9 1 x 8 7.50 540.00 1.57 847.80
Lateal ties Column C3 8 4 1 x 42.333 1.30 220.13 0.39 85.85
9 Column C4 16 13 1 x 4 7.50 390.00 1.57 612.30
Column C4 12 13 1 x 4 7.50 390.00 0.89 347.10
Lateal ties Column C4 8 4 1 x 42.333 1.30 220.13 0.39 85.85 2793.52
10 Main Steel Plinth Beam Ext 16 1 2 x 3 74.37 446.22 1.57 700.57
VS 8 1 1 x 476 1.10 523.38 0.39 204.12
Plinth Beam
16 1 2 x 2 85.56 342.24 1.57 537.32
Main Steel Internal
VS 8 1 1 x 550 1.10 605.44 0.39 236.12
Plinth Beam
16 1 2 x 2 15.00 60.00 1.57 94.20
Main Steel Internal
VS 8 1 1 x 80 0.80 64.00 0.39 24.96 1797.29
11 Main Steel Roof Beam B1 16 1 2 x 2 11.10 44.40 1.57 69.71
Eatra 16 1 6 x 1 0.90 5.40 1.57 8.48
VS 8 1 1 x 66 1.20 79.20 0.39 30.89
12 Main Steel Roof Beam B2 16 1 2 x 2 17.70 70.80 1.57 111.16
Eatra 16 1 10 x 1 0.90 9.00 1.57 14.13
VS 8 1 1 x 106 1.20 127.20 0.39 49.61
13 Main Steel MLB 20 1 2 x 2 4.00 16.00 2.46 39.36
Eatra 16 1 2 x 2 0.90 3.60 1.57 5.65
VS 8 1 1 x 23 1.20 27.20 0.39 10.61
14 Main Steel Roof Beam B3 16 1 2 x 2 15.10 60.40 1.57 94.83
Eatra 16 1 8 x 2 0.90 14.40 1.57 22.61
VS 8 1 1 x 91 1.20 108.80 0.39 42.43
16 Main Steel Roof Beam B4 16 1 2 x 2 7.50 30.00 1.57 47.10
Eatra 16 1 4 x 2 0.90 7.20 1.57 11.30
VS 8 1 1 x 40 1.20 48.00 0.39 18.72
17 Main Steel Roof Beam B5 16 1 2 x 2 33.30 133.20 1.57 209.12
Eatra 16 1 18 x 1 0.90 16.20 1.57 25.43
VS 8 1 1 x 202 1.20 242.40 0.39 94.54
18 Main Steel Roof Beam B6 16 1 2 x 2 9.15 36.60 1.57 57.46
Eatra 16 1 1 x 1 4.02 4.02 1.57 6.31
Eatra 16 1 4 x 1 0.90 3.60 1.57 5.65
VS 8 1 1 x 55 1.20 66.00 0.39 25.74
19 Main Steel Roof Beam B7 16 1 2 x 2 9.15 36.60 1.57 57.46
Eatra 16 1 1 x 2 4.02 8.04 1.57 12.62
Eatra 16 1 4 x 1 0.90 3.60 1.57 5.65
VS 8 1 1 x 55 1.20 66.00 0.39 25.74
20 Main Steel Roof Beam B8 16 1 2 x 2 10.35 41.38 1.57 64.97
Eatra @Bottom 16 1 1 x 1 3.00 3.00 1.57 4.71
Eatra @Bottom 20 1 1 x 1 2.43 2.43 2.46 5.98
Eatra @ top 16 1 1 x 1 0.80 0.80 1.57 1.26
Eatra @ top 16 1 1 x 2 3.40 6.80 1.57 10.68
Eatra @ top 20 1 1 x 2 1.21 2.42 2.46 5.95
VS 8 1 1 x 63 1.20 75.57 0.39 29.47
21 Main Steel Roof Beam B9 25 1 2 x 2 8.85 35.38 3.85 136.21
Eatra @Bottom 20 1 1 x 2 4.43 8.85 2.46 21.77
Eatra @ top 20 1 2 x 3 2.00 12.00 2.46 29.52
VS 8 1 1 x 59 1.20 70.76 0.39 27.60
22 Main Steel Roof Beam B10 16 1 2 x 2 8.70 34.78 1.57 54.60
Eatra @ top 16 1 2 x 4 1.00 8.00 1.57 12.56
VS 8 1 1 x 58 1.20 69.56 0.39 27.13
23 Main Steel Roof Beam B11 16 1 1 x 3 8.70 26.09 1.57 40.96
Main Steel 16 1 1 x 2 8.70 17.39 1.57 27.30
Eatra @ top 16 1 2 x 4 1.00 8.00 1.57 12.56
VS 8 1 1 x 58 1.20 69.56 0.39 27.13 1642.67
19 Main Steel Lintels 10 38 2 x 2 1.60 243.20 0.62 150.78
VS 6 38 1 x 11 0.90 364.80 0.22 80.26 231.04
Sun Shade 8 38 1 x 11 0.90 376.20 0.39 146.72
6 38 1 x 5 1.60 304.00 0.22 66.88 213.60
23 Main Steel Roof Salb 8 1 1 x 53.6 11.10 594.96 0.39 232.03
Dis Steel 8 1 1 x 74 8.34 617.16 0.39 240.69
Eatra @ top 8 1 6 x 26.8 0.90 144.72 0.39 56.44
Eatra @ top 8 1 4 x 36 1.00 144.00 0.39 56.16
Roof Salb Head
8 1 1 x 44.267 3.90 172.64 0.39 67.33
23 Main Steel Room
Dis Steel 8 1 1 x 22 6.94 152.68 0.39 59.55
Eatra @ top 8 1 2 x 22.133 1.00 44.27 0.39 17.27
Eatra @ top 8 1 2 x 10.333 1.25 25.83 0.39 10.07
23 Main Steel Roof Salb 8 1 1 x 53.6 18.00 964.80 0.39 376.27
Dis Steel 8 1 1 x 112.00 8.34 934.08 0.39 364.29
Eatra @ top 8 1 6 x 26.8 0.90 144.72 0.39 56.44
Eatra @ top 8 1 2 x 56 1.50 168.00 0.39 65.52 1602.06
Waist Salb GF &
12 2 2 x 13 6.00 312.00 0.89 277.68
23 Main Steel FF
Dis Steel 8 2 2 x 26.00 1.30 135.20 0.39 52.73
Eatra @ top 12 1 2 x 6 1.20 14.40 0.89 12.82
Eatra @ top 12 1 2 x 6 2.70 32.40 0.89 28.84 372.07
Total 9594.22 9594.22
Construction of Community Hall at RB Nagar in Shamshabad(v&m)
LEAD CHART 2016-17 Ranga Reddy Dist
Convey-ance Charges Initial Cost Total Cost
Loading Un Loading
Deduct (Excluding
charges charges
Sl. No. Description S.No. Unit Quarry Item NO Page no Lead in KM Lead charges
13.615 %
Net Lead
Initial rate Machine
Blasting Seigneorage Excluding Excluding Seineorage
over Excluding Crushing
(As per SoR) charges charges charges 13.615 % Over 13.615 % Over Charges )
head S/C charges
heads heads
charges
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18)
1 Cement (14.08.13) 183 MT Local - 5900.00 54.92 5954.92
5 Sand for Filling 27 Cum Venkatapur 27 20 & CAD 16.00 222.60 26.68 195.92 560.00 40.00 8.32 764.24
6 Sand for Concrete 27 Cum Bodhan 27 20 & CAD 230.00 2499.00 299.47 2199.53 560.00 40.00 8.32 2767.85
7 2nd Class Bricks 1 1000 Nos Local TBSC-A.I 17 10.00 236.60 28.35 208.25 5000.00 38.50 45.77 45.77 5299.78
40mm HBG metal SS5,
8 118 Cum Pasumamula 30-F 12 42.00 525.00 62.91 462.09 620.00 155.00 70.00 75.00 1307.09
machine crushed
9 20mm HBG SS5 M/c chips 116 Cum Pasumamula 28-D 12 42.00 525.00 62.91 462.09 916.00 229.00 70.00 75.00 1677.09
10 13.5/12.5 mm HBG SS5 M/c chips Cum Pasumamula 27-C 12 42.00 525.00 62.91 462.09 822.00 205.50 70.00 75.00 1559.59
11 Rough Stone ( 20x20x75Cm @ Rs 21.00 /Each) 64 Cum Kothwalguda 64 22 5.00 84.00 10.07 73.93 700.00 75.00 773.93
12 CR stone ( 30x30x060 @Rs 28.00 /Each) 14 Cum Kothwalguda 14 20 5.00 84.00 10.07 73.93 518.52 75.00 592.45
13 Through stone(25x25x45cm 60cm @ Rs 37.00/Each) 76 Cum Kothwalguda 76 22 5.00 84.00 10.07 73.93 1127.62 75.00 1201.55
14 Bond stones ( 25x25x45cm -60cm @Rs 37.00 /Each) M182 B Cum Kothwalguda M182 B 41 5.00 84.00 10.07 73.93 1127.62 75.00 1201.55
15 Gravel 88 Cum Local 34 25 5.00 84.00 10.07 73.93 103.00 30.00 176.93
Polished Shabad stone (15-18)mmthick Hyderabad
16 21 10Sqm TBSC-B.I-03 19 20.00 72.18 8.65 63.53 1650.00 5.99 2.99 1722.51
/Cuddupah 40MM stone slab Rs 960/Sqm
17 Man mazdoor 350
18 Woman mazdoor 350
19 Semi skilled Mason/Electrician / 2nd Class Carpentor or Painter /Balck smith/Bar bender /Helper 405
20 Skilled Mason /1st Class Carpentor / /Concrete operater Muncipal allowance MA 40% 480
21 1st Class Painter/ Allowance Over Heads OH 0.000% 415
22 Skilled Electrician 13.615% 515
23 Bar Bendar Water Rural 77.00 565
24 Plumber Urban 103.00
1) This to certify that the proposed leads over and above initial 1kM
2) This to certify that the proposed leads of the work is true and nearet to the best of my knowledge
3) This to certified that the stone requires blasting
4) This to certified that the proposed work is located with in the Muncipal limits of 12 KM
2 PCC (1:5:10) prop nominal mix (cement: FA: CA) using 40mm size HBG (SS5) metal from
approved quarry including Cost and Conveyance of all materials like cement, sand, CA,
water etc. to site, including all operational, incidental, and labour charges such as
mixing, laying and ramming CC in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete for finished item work for Foundations and
Flooring Bed (APSSNo.402)
For Ramp
1 x 1 3.65 1.50 0.15 0.82
0.82
0.85 4538.17 3857.00
Cum. Per Cum.
3 Brick Masonry in superstructure with CM (1:8) Prop of 230 mm thick wall using 2nd class
traditional Bricks of size 23x11x7cm having minimum crushing strength of 50 kg/cm2
including Cost and Conveyance of all materials scaffolding charges, etc., complete for
finished item of work. (APSS No. 501 & 504).
For Ramp Portion
1 x 1 3.65 1.50 (0.90+0.00)/2 2.46
2.46 4926.34 12119.00
Cum. per Cum.
4 Plastering with CM 2 coats, 20 mm thick, base coat in CM (1:6), 16 mm thick and top coat
in CM (1:4), 4mm thick with Dubara sponze finishing. with dubara sponge finish including
c/c of all materials like cement, sand,water etc., to site, other taxes on all materials, all
Grooves,finishing, curing, etc., complete for for finished item of work. (APSS 1001,1003 &
1004)
For Ramp Sides
1 x 1 3.65 0.45 1.64
For Ramp Side
1 x 1 1.50 0.90 1.35
For Ramp Top 1 x 1 3.65 1.500 5.48
8.47 3916.00 3317.00
5 Add Jungle Cutting along pheripory for Collage premises 431.00
Sub Total 19980.00
1 2 3 4 5 6 7 8 9 10
BLD 145 Painting, Priming Coat on New Wood BLD -
-CSTN- 268 Work Muncipal Limit 0.40
CSTN-
12-6- 12-6-
Unit: 10 sqm Over Heads 0.00
A. MATERIALS :
Wood Primer BMT J05 0.70 135.00 94.50
B. LABOUR
Painter 0.70 320.00 224.00
Add Muncipal Limits 224.00 0.40 89.60
Sundries including brushes, soap, putty etc., 0.01 408.10 4.08
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and 1.00
below 3 m in length
Labour :—
Carpenter 17.70 480.00 8496.00
Man Mazdoor 8.80 350.00 3080.00
Add Muncipal Limits ### 0.40 4630.40
Sundries including nails, screws etc., LS
Total Per Cum of Wood Work 16206.40
2 Supply and fixing of Country wood Door
Single shutter fully panelled door of size
0.75 x 2.1mt with frame made of well
seasoned country Wood scantlings of size
100 x 75mm and using Flush door
shutters, solid bond wood block board type
with commercial ply on both faces.: 30 mm
thick conforming to IS:2202 as per approved
design with fixtures of 6 nos of 9" ' z"
holdfasts, 300 mm long MS Iron coted
aldrop-1 no, 125mm long MS iron butt
hinges 3 No's, Door stoppers-1 no, 150mm
long MS coated Tower bolts 1- no's MS iron
coated fancy handles 150 mm -2 nos with
necessary screws complete including cost
and conveyance of all materials and labour
charges etc. complete as per specifications
(APSS NO.1001 & 1002)
3903.06
Add 14% overhead charges, Contractor profit 3903.060 0.00 0.00
BASIC COST per Each 3903.06
Door size 0.75X2.10 M (Frame )
frames
verticals 2 2.10 0.100 0.075 0.032 25497.19 815.91
horizontals 1 0.90 0.100 0.075 0.007 25497.19 178.48
labour charges 0.039 16206.40 632.05
wood primer 2.25/3 0.75 2.1 1.180 412.18 48.64
MS Zhold fasts 6 12.00 72.00
Transportation charges 1 50.00 50.00
1797.08
Add 14% overhead charges, Contractor profit 1797.080 0.00 0.00
Cost of Frame .0.75m x2.10M 1797.08
Cost of Shutters 0.75m x2.10M 2105.98
4288.51
Add 14% overhead charges, Contractor profit 4288.510 0.00 0.00
BASIC COST per Each 4288.51
1848.68
Add 14% overhead charges, Contractor profit 1848.680 0.00 0.00
BASIC COST per Each Frame Only 1848.68
(0.90x2.10)m
BASIC COST per Each Shutters Only 2439.83
(0.90x2.10)m
4 Supply and fixing of Country wood Door
double shutter fully panelled door of size
1.05 x 2.1mt with frame made of well
seasoned country Wood scantlings of size
100 x 75mm and using Flush door
shutters, solid bond wood block board
type with commercial ply on both faces.:
30 mm thick conforming to IS:2202 as per
approved design with fixtures of 6 nos of 9" '
z" holdfasts, 300 mm long MS Iron coted
aldrop-1 no, 125mm long MS iron butt
hinges 6 No's, Door stoppers-2 no, 150mm
long MS coated Tower bolts 3- no's MS iron
coated fancy handles 150 mm -2nos with
necessary screws complete including cost
and conveyance of all materials and labour
charges etc. complete as per specifications
(APSS NO.1001 & 1002)
MS Power coated Butt hings with screws 125 Nos BMT-G-29 3 31.00 93.00
mm
MS Power Coated aldrop with bolts 300 mm Nos BMT-G-45 1 164.00 164.00
long
MS power coated Door stopper Nos BMT G53 1 46.00 46.00
MS power coated Handle 125 mm long BMT G35 3 31.00 93.00
4672.87
Add 14% overhead charges, Contractor profit 4672.870 0.00 0.00
BASIC COST per Each 4672.87
Door size1.05 X2.10 M (Frame only)
frames
verticals 2 2.10 0.100 0.075 0.032 25497.19 815.91
horizontals 1 1.20 0.100 0.075 0.009 25497.19 229.47
labour charges 1 0.041 16206.40 664.46
wood primer 2.25/3 1.05 2.1 1.650 412.18 68.01
MS Zhold fasts 6 12.00 72.00
1 50.00 50.00
1899.85
Add 14% overhead charges, Contractor profit 1899.850 0.00 0.00
Door Frame only (1.05 x2.10) 1899.85
Door Shutters only (1.05x2.10) 2773.02
Index
S No Description Nos L B D Qty Rate Amount Rs.
-code
1 2 3 4 5 6 7 8 9 10
BLD 145 Painting, Priming Coat on New Wood Work
-CSTN- 268
12-6- Muncipal Limit 0.40
Unit: 10 sqm Over Heads 0.00
A. MATERIALS :
Wood Primer BMT J05 L 0.70 135.00 94.50
B. LABOUR
Painter day 0.70 320.00 224.00
Add Muncipal Limits 224.00 0.40 89.60
Sundries including brushes, soap, putty etc., 0.01 408.10 4.08
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and cum 1.00 Extra
below 3 m in length
Labour :—
Carpenter day 17.70 480.00 8496.00
Man Mazdoor day 8.80 350.00 3080.00
Add Muncipal Limits 11576.00 0.40 4630.40
Sundries including nails, screws etc., LS
Total Per Cum of Wood Work 16206.40
BLD- 2 Supply and fixing of Country wood Door
CSTN-
Single shutter fully panelled door of size
11-2
0.75 x 2.0 mt with frame made of well
seasoned country Wood scantlings of size
100 x 75mm and shutter made of side rails
100mm X 32mm, top rail 100 mmX32 mm,
bottom rail 100mmX 32 mm and
intermediate rails of 100mm x 32 mm and
planks s - 5 no's of 25mm thick as per
approved design with fixtures of 6 nos of 9" '
z" holdfasts, 300 mm long MS Iron coted
aldrop-1 no, 125mm long MS iron butt
hinges 6 No's, Door stoppers-2 no, 150mm
long MS coated Tower bolts 3- no's MS iron
coated fancy handles 150 mm -2nos with
necessary screws complete including cost
and conveyance of all materials and labour
charges etc. complete as per specifications
(APSS NO.1001 & 1002)
frames
verticals 2 2.00 0.100 0.075 0.030 25497.19 764.92
MS Power coated Butt hings with screws 125 Nos BMT-G-29 6 31.00 186.00
mm
MS Power Coated aldrop with bolts 300 mm Nos BMT-G-45 1 164.00 164.00
long
MS power coated Door stopper Nos BMT G53 2 46.00 92.00
4828.50
1711.62
1762.38
6055.10
1813.56
frames
verticals 2 2.00 0.100 0.075 0.030 25497.19 764.920
1864.34
7520.56
1976.30
MS Power Coated Tower bolts 150 @ Top Nos BMT -G15 2 35.00 70.00
MS Power Coated Tower bolts 150 @ Bottam Nos BMT -G15 2 35.00 70.00
MS Power coated Butt hings with screws 100 mm LONG Nos BMT -G28 4 21.00 84.00
Friction stay hinges for windows Nos BMT G71 2 97.00 194.00
Cost of 12 mm Square Rods 10 nos 0.900 9.000 1.13 10.170 37.00 376.29
4301.89
Cost of 12 mm Square Rods 10 nos 0.900 9.00 1.13 10.170 37.00 376.29
2372.65
MS Power Coated Tower bolts 150 @ Top Nos BMT -G15 3 35.00 105.00
MS Power Coated Tower bolts 150 @ Bottam Nos BMT -G15 3 35.00 105.00
MS Power coated Butt hings with screws 100 mm LONG Nos BMT -G28 6 21.00 126.00
Friction stay hinges for windows Nos BMT G71 3 97.00 291.00
5941.24
2989.53
MS Power Coated Tower bolts 150 @ Top Nos BMT -G15 3 35.00 105.00
MS Power Coated Tower bolts 150 @ Bottam Nos BMT -G15 3 35.00 105.00
MS Power coated Butt hings with screws 100 mm LONG Nos BMT -G28 6 21.00 126.00
Friction stay hinges for windows Nos BMT G71 3 97.00 291.00
6908.40
3362.08
Index
S No Description Nos L B D Qty Rate Amount Rs.
-code
1 2 3 4 5 6 7 8 9.00 10
145 Painting, Priming Coat on New Wood Work
BLD
-CSTN-
268
12-6-
Muncipal Limit 0.40
Unit: 10 sqm Over Heads 0.00000
A. MATERIALS :
Wood Primer BMT J05 L 0.70 158.00 110.60
B. LABOUR
Painter day 0.70 405.00 283.50
Add Muncipal Limits 283.50 0.40 113.40
Sundries including brushes, soap, putty etc., 0.01 507.50 5.08
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and cum 1.00 Extra
below 3 m in length
Labour :—
Carpenter day 17.70 480.00 8496.00
Man Mazdoor day 8.80 350.00 3080.00
11576.00 0.40
Add Muncipal Limits 4630.40
Sundries including nails, screws etc., LS
Total Per Cum of Wood Work Rs 16206.40
7776.20
2878.90
2956.81
9785.66
3034.19
3112.10
12382.45
3277.39
MS Power Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 2 38.00 76.00
MS Power Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 2 38.00 76.00
MS Power coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 4 23.00 92.00
Friction stay hinges for windows Nos TBSC -P-II -15 2 107.00 214.00
Cost of 12 mm Square Rods 10 nos 0.900 9.000 1.13 10.170 37.00 376.29
6942.67
Frames
verticals 3 1.35 0.100 0.075 0.030 49394.00 1481.82
Cost of 12 mm Square Rods 10 nos 0.900 9.00 1.13 10.170 37.00 376.29
3640.80
MS Power Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS Power Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS Power coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Cost of 12 mm Square Rods 10 nos 1.20 12.000 1.13 13.560 37.00 501.72
9678.29
Frames
verticals 4 1.35 0.100 0.075 0.041 49394.00 2025.15
Cost of 12 mm Square Rods 10 nos 1.20 12.000 1.13 13.560 37.00 501.72
4769.71
MS Power Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS Power Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS Power coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Cost of 12 mm Square Rods 10 nos 1.50 15.000 1.13 16.950 37.00 627.15
11198.43
Frames
verticals 4 1.35 0.100 0.075 0.041 49394.00 2025.15
Cost of 12 mm Square Rods 10 nos 1.50 15.000 1.13 16.950 37.00 627.15
5267.11
MS Power Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS Power Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS Power coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Cost of 12 mm Square Rods 10 nos 1.35 13.500 1.13 15.255 37.00 564.44
9299.84
Frames
verticals 4 1.35 0.100 0.075 0.041 49394.00 2025.15
5035.38
MS Power Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS Power Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS Power coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Cost of 12 mm Square Rods 10 nos 1.80 18.000 1.13 20.340 37.00 752.58
11805.17
Frames
verticals 5 1.30 0.100 0.075 0.049 49394.00 2420.31
Cost of 12 mm Square Rods 10 nos 1.80 18.000 1.13 20.340 37.00 752.58
6480.12
Frames
verticals 4 1.20 0.100 0.075 0.036 49394.00 1778.18
horizontals 2 1.35 0.100 0.075 0.020 49394.00 987.88
shutter verticals 2X3 1.08 0.075 0.032 0.015 65861.00 987.92
shutter rails 3x3 0.52 0.075 0.032 0.011 65861.00 724.47
Planks 3x2 0.23 0.478 0.025 0.016 65861.00 1053.78
labour charges 0.098 16206.40 1588.23
BLD- Furniture - Iron - for External doors
CSTN-
(Schedule Item 292)
11-7
MS Power Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS Power Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS Power coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Screws nos BMT M 21 90 0.89 80.10
MS Zhold fasts 300mm long 40x40x5 Mm BMS W 16 4 35.00 140.00
wood primer 2.75 1.20 1.20 3.960 512.58 202.98
Cost of 12 mm Square Rods 9 nos 1.20 10.80 1.13 12.204 37.00 451.55
Transportation charges 1 100.00 100.00
8782.09
Add 13.615 % overhead charges, Contractor 0.000 8782.09 0.00
profit
BASIC COST per Each RS 8782.09
Window size1.20 x 1.20mts (Frame only)
Frames
verticals 4 1.20 0.100 0.075 0.036 49394.00 1778.18
horizontals 2 1.35 0.100 0.075 0.020 49394.00 987.88
labour charges 0.056 16206.40 907.56
BLD- Furniture - Iron - for External doors
CSTN-
(Schedule Item 292)
11-7
Index
S No Description Nos L B D Qty Rate Amount Rs.
-code
1 2 3 4 5 6 7 8 9 10
145 Painting, Priming Coat on New Wood Work
BLD
-CSTN-
268
12-6-
Muncipal Limit 0.40
Unit: 10 sqm Over Heads 0.00
A. MATERIALS :
Wood Primer BMT J05 L 0.70 158.00 110.60
B. LABOUR
Painter day 0.70 405.00 283.50
Add Muncipal Limits 283.50 0.40 113.40
Sundries including brushes, soap, putty etc., 0.01 507.50 5.08
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and cum 1.00 Extra
below 3 m in length
Labour :—
Carpenter day 17.70 480.00 8496.00
Man Mazdoor day 8.80 350.00 3080.00
11576.00 0.40
Add Muncipal Limits 4630.40
Sundries including nails, screws etc., LS
Total Per Cum of Wood Work Rs 16206.40
5010.70
1860.96
1913.94
6250.79
1967.43
2020.41
7736.53
2136.89
MS powder Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 2 38.00 76.00
MS powder Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 2 38.00 76.00
MS powder coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 4 23.00 92.00
Friction stay hinges for windows Nos TBSC -P-II -15 2 107.00 214.00
Cost of 12 mm Square Rods 10 nos 0.900 9.000 1.13 10.170 37.00 376.29
4730.32
Frames
verticals 3 1.35 0.100 0.075 0.030 25497.19 764.92
Cost of 12 mm Square Rods 10 nos 0.900 9.00 1.13 10.170 37.00 376.29
2541.56
MS powder Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 2 38.00 76.00
MS powder Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 2 38.00 76.00
MS powder coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 4 23.00 92.00
Friction stay hinges for windows Nos TBSC -P-II -15 2 107.00 214.00
Cost of 12 mm Square Rods 10 nos 1.20 12.000 1.13 13.560 37.00 501.72
6295.24
Frames
verticals 4 1.35 0.100 0.075 0.041 25497.19 1045.38
Cost of 12 mm Square Rods 10 nos 1.20 12.000 1.13 13.560 37.00 501.72
3312.00
MS powder Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS powder Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS powder coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Cost of 12 mm Square Rods 10 nos 1.50 15.000 1.13 16.950 37.00 627.15
7507.48
Frames
verticals 4 1.35 0.100 0.075 0.041 25497.19 1045.38
Cost of 12 mm Square Rods 10 nos 1.50 15.000 1.13 16.950 37.00 627.15
3689.92
MS powder Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS powder Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS powder coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Cost of 12 mm Square Rods 10 nos 1.35 13.500 1.13 15.255 37.00 564.44
6839.36
Frames
verticals 4 1.35 0.100 0.075 0.041 25497.19 1045.38
3505.99
MS powder Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS powder Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS powder coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Cost of 12 mm Square Rods 10 nos 1.80 18.000 1.13 20.340 37.00 752.58
8756.60
Frames
verticals 5 1.30 0.100 0.075 0.049 25497.19 1249.36
Cost of 12 mm Square Rods 10 nos 1.80 18.000 1.13 20.340 37.00 752.58
4376.47
Frames
verticals 4 1.20 0.100 0.075 0.036 25497.19 917.90
horizontals 2 1.35 0.100 0.075 0.020 25497.19 509.94
shutter verticals 2X3 1.08 0.075 0.032 0.015 31076.90 466.15
shutter rails 3x3 0.52 0.075 0.032 0.011 31076.90 341.85
Planks 3x2 0.23 0.478 0.025 0.016 31076.90 497.23
labour charges 0.098 16206.40 1588.23
BLD- Furniture - Iron - for External doors
CSTN-
(Schedule Item 292)
11-7
MS powder Coated Tower bolts 150 @ Top Nos TBSC -P-I -15 3 38.00 114.00
MS powder Coated Tower bolts 150 @ Bottam Nos TBSC -P-I -15 3 38.00 114.00
MS powder coated Butt hings with screws 100 mm LONG Nos TBSC -P-II -10 6 23.00 138.00
Friction stay hinges for windows Nos TBSC -P-II -15 3 107.00 321.00
Screws nos BMT M 21 60 0.89 53.40
MS Zhold fasts 300mm long 40x40x5 Mm BMS W 16 4 35.00 140.00
wood primer 2.75 1.20 1.20 3.960 512.58 202.98
Cost of 12 mm Square Rods 9 nos 1.20 10.80 1.13 12.204 37.00 451.55
Transportation charges 1 100.00 100.00
5956.23
Add 13.615 % overhead charges, Contractor 0.000 5956.23 0.00
profit
BASIC COST per Each RS 5956.23
Window size1.20 x 1.20mts (Frame only)
Frames
verticals 4 1.20 0.100 0.075 0.036 25497.19 917.90
horizontals 2 1.35 0.100 0.075 0.020 25497.19 509.94
labour charges 0.056 16206.40 907.56
BLD- Furniture - Iron - for External doors
CSTN-
(Schedule Item 292)
11-7
Index
S No Description Nos L B D Qty Rate Amount Rs.
-code
1 2 3 4 5 6 7 8 9.00 10
145 Painting, Priming Coat on New Wood Work
BLD
-CSTN-
268
12-6-
Muncipal Limit 0.40
Unit: 10 sqm Over Heads 0.00
A. MATERIALS :
Wood Primer BMT J05 L 0.70 145.00 101.50
B. LABOUR
Painter day 0.70 345.00 241.50
Add Muncipal Limits 241.50 0.40 96.60
Sundries including brushes, soap, putty etc., 0.01 439.60 4.40
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and cum 1.00 Extra
below 3 m in length
Labour :—
Carpenter day 17.70 480.00 8496.00
Man Mazdoor day 8.80 350.00 3080.00
Add Muncipal Limits 11576.00 0.40 4630.40
Sundries including nails, screws etc., LS
Total Per Cum of Wood Work Rs 16206.40
12836.40
3919.36
4022.51
16797.36
4125.20
4228.35
21801.10
4444.18
MS Powder Coated Tower bolts 150 @ Top Nos BMT -G15 2 37.00 74.00
MS Powder Coated Tower bolts 150 @ Bottam Nos BMT -G15 2 37.00 74.00
MS Powder coated Butt hings with screws 100 mm LONG Nos BMT -G28 4 22.00 88.00
Friction stay hinges for windows Nos BMT G71 2 104.00 208.00
Cost of 12 mm Square Rods 10 nos 0.900 9.000 1.13 10.170 37.00 376.29
10983.52
Frames
verticals 3 1.35 0.100 0.075 0.030 76280.00 2288.40
Cost of 12 mm Square Rods 10 nos 0.900 9.00 1.13 10.170 37.00 376.29
4869.94
MS Powder Coated Tower bolts 150 @ Top Nos BMT -G15 3 37.00 111.00
MS Powder Coated Tower bolts 150 @ Bottam Nos BMT -G15 3 37.00 111.00
MS Powder coated Butt hings with screws 100 mm LONG Nos BMT -G28 6 22.00 132.00
Friction stay hinges for windows Nos BMT G71 3 104.00 312.00
Cost of 12 mm Square Rods 10 nos 1.20 12.000 1.13 13.560 37.00 501.72
15528.25
Frames
verticals 4 1.35 0.100 0.075 0.041 76280.00 3127.48
Cost of 12 mm Square Rods 10 nos 1.20 12.000 1.13 13.560 37.00 501.72
6399.55
MS Powder Coated Tower bolts 150 @ Top Nos BMT -G15 3 37.00 111.00
MS Powder Coated Tower bolts 150 @ Bottam Nos BMT -G15 3 37.00 111.00
MS Powder coated Butt hings with screws 100 mm LONG Nos BMT -G28 6 22.00 132.00
Friction stay hinges for windows Nos BMT G71 3 104.00 312.00
Cost of 12 mm Square Rods 10 nos 1.50 15.000 1.13 16.950 37.00 627.15
18215.62
Frames
verticals 4 1.35 0.100 0.075 0.041 76280.00 3127.48
Cost of 12 mm Square Rods 10 nos 1.50 15.000 1.13 16.950 37.00 627.15
7028.83
MS Powder Coated Tower bolts 150 @ Top Nos BMT -G15 3 37.00 111.00
MS Powder Coated Tower bolts 150 @ Bottam Nos BMT -G15 3 37.00 111.00
MS Powder coated Butt hings with screws 100 mm LONG Nos BMT -G28 6 22.00 132.00
Friction stay hinges for windows Nos BMT G71 3 104.00 312.00
Cost of 12 mm Square Rods 10 nos 1.35 13.500 1.13 15.255 37.00 564.44
13091.96
Frames
verticals 4 1.35 0.100 0.075 0.041 76280.00 3127.48
6745.05
MS Powder Coated Tower bolts 150 @ Top Nos BMT -G15 3 37.00 111.00
MS Powder Coated Tower bolts 150 @ Bottam Nos BMT -G15 3 37.00 111.00
MS Powder coated Butt hings with screws 100 mm LONG Nos BMT -G28 6 22.00 132.00
Friction stay hinges for windows Nos BMT G71 3 104.00 312.00
Cost of 12 mm Square Rods 10 nos 1.80 18.000 1.13 20.340 37.00 752.58
16996.75
Frames
verticals 5 1.30 0.100 0.075 0.049 76280.00 3737.72
Cost of 12 mm Square Rods 10 nos 1.80 18.000 1.13 20.340 37.00 752.58
8559.94
Frames
verticals 4 1.20 0.100 0.075 0.036 76280.00 2746.08
horizontals 2 1.35 0.100 0.075 0.020 76280.00 1525.60
shutter verticals 2X3 1.08 0.075 0.032 0.015 152561.00 2288.42
shutter rails 3x3 0.52 0.075 0.032 0.011 152561.00 1678.17
Planks 3x2 0.23 0.478 0.025 0.016 152561.00 2440.98
labour charges 0.098 16206.40 1588.23
BLD- Furniture - Iron - for External doors
CSTN-
(Schedule Item 292)
11-7
MS Powder Coated Tower bolts 150 @ Top Nos BMT -G15 3 37.00 111.00
MS Powder Coated Tower bolts 150 @ Bottam Nos BMT -G15 3 37.00 111.00
MS Powder coated Butt hings with screws 100 mm LONG Nos BMT -G28 6 22.00 132.00
Friction stay hinges for windows Nos BMT G71 3 104.00 312.00
Screws nos BMT M 21 90 2.00 180.00
MS Zhold fasts 300mm long 40x40x5 Mm BMS W 69 4 35.00 140.00
wood primer 2.75 1.20 1.20 3.960 444.00 175.82
Cost of 12 mm Square Rods 9 nos 1.20 10.80 1.13 12.204 37.00 451.55
Transportation charges 1 100.00 100.00
13980.85
Add 13.615 % overhead charges, Contractor 0.000 13980.85 0.00
profit
BASIC COST per Each RS 13980.85
Window size1.20 x 1.20mts (Frame only)
Frames
verticals 4 1.20 0.100 0.075 0.036 76280.00 2746.08
horizontals 2 1.35 0.100 0.075 0.020 76280.00 1525.60
labour charges 0.056 16206.40 907.56
BLD- Furniture - Iron - for External doors
CSTN-
(Schedule Item 292)
11-7
Unit = 1 cum
Materials :—
Teak wood large scantlings over 2 m and cum 1.00 Extra
below 3 m in length
Labour :—
Carpenter day 17.70 480.00 8496.00
Man Mazdoor day 8.80 350.00 3080.00
Add Muncipal Limits 11576.00 0.40 4630.40
Sundries including nails, screws etc., LS
Total Per Cum of Wood Work Rs 16206.40
4 Supply and fixing of Country wood Door double shutter fully panelled door of size 1.05 x 2.1mt with
frame made of well seasoned country Wood scantlings of size 100 x 75mm and shutter made of side rails
100mm X 32mm, top rail 100 mmX32 mm, bottom rail 100mmX 32 mm and intermediate rails of 100mm x 32
mm and planks s - 5 no's of 25mm thick as per approved design with fixtures of 6 nos of 9" ' z" holdfasts,
300 mm long MS Iron coted aldrop-1 no, 125mm long MS iron butt hinges 6 No's, Door stoppers-2 no, 150mm
long MS coated Tower bolts 3- no's MS iron coated fancy handles 150 mm -2nos with necessary screws
complete including cost and conveyance of all materials and labour charges etc. complete as per
specifications (APSS NO.1001 & 1002)
6454.32
2043.10
7 Supply and fixing of fully panelled Window frame and shutters of size 0.90 x 1.35 mt with country wood
frame of size 75x100mm and S/F of 4 Nos. MS Hold fasts, incl. all labour charges such as making window
frame and shutters and fiXing 10 Nos.of 12 mm square safety bars in to the frame etc,including applying
primory coat, cost and conveyance of all materials .
MS Powder Coated Tower bolts 150 @ Top Nos BMT -G15 2 37.00 74.00
MS Powder Coated Tower bolts 150 @ Bottam Nos BMT -G15 2 37.00 74.00
MS Powder coated Butt hings with screws 100 mm LONG Nos BMT -G28 4 22.00 88.00
Friction stay hinges for windows Nos BMT G71 2 104.00 208.00
Cost of 12 mm Square Rods 10 nos 0.900 9.000 1.13 10.170 37.00 376.29
4760.01
Frames
verticals 3 1.35 0.100 0.075 0.030 25497.19 764.92
Cost of 12 mm Square Rods 10 nos 0.900 9.00 1.13 10.170 37.00 376.29
2533.94