Epri HPS PDF
Epri HPS PDF
Epri HPS PDF
Prepared by
International Energy Associates Limited
Washington, D.C.
Recommended Guidelines for the
Operation and Maintenance of
Feedwater Heaters
CS-3239
Research Project 1887-3
Final Report, September 1983
Prepared by
Principal Investigators
F. L. Wadsworth
T. J. Kielar
Subcontractor
POWERFECT, INC.
53 East Cedar Street
Livingston, New Jersey 07039
Principal Investigator
M. C. Catapano
Consultant
R. R. Noe
Prepared for
and
Copyr~ghtd 1983 Electrlc Power Research Institute, Inc. All rights reserved
NOTICE
This report was prepared by the organ~zat~on(s) named below as an account of work sponsored by the Electr~c
Power Research Institute, Inc. (EPRI) and the Ed~sonElectric Institute (EEI). Neither EPRI. EEI, members of EPRI,
the organizationis) named below, nor any person acting on behalf of any of them: (a) makes any warranty,
express or impl~ed,with respect to the use of any information, apparatus, method, or process d~sclosedin t h s
report or that such use may not infringe privately owned rights; or (b) assumes any l ~ a b i l ~ t ~we~st hrespect to the
use of, or for damages resulting from the use of, any ~nforrnaton,apparatus, method, or process disclosed in
t h ~ sreport.
Prepared by
Internatonal Energy Assoc~atesL~miled
Washington, D.C.
ABSTRACT
Previous EPRI surveys, studies, and workshops have identified feedwater heater (FWH)
problems as having a significant impact on fossil plant performance and availabil-
ity. One of the root causes of these problems is the current lack of comprehensive
standards, guidelines and procedures for assisting utility personnel in the opera-
tion and maintenance of their FWH systems. The guidelines in this publication have
been developed to help correct the problem by providing utility personnel with ex-
planations of the principal failures experienced in the past, their symptoms, prac-
tical techniques to avoid or minimize the problems, and other recommendations for
improving operation, maintenance, and management of FWH systems. The guidelines are
essentially a collation of the experiences of those utilities and individuals who
have experienced some success in coping with FWH problems. Comments and suggestions
from users are solicited to help EPRI make future edition(s) of these guidelines
more complete and more beneficial tc the utilities.
EPRI PERSPECTIVE
PROJECT DESCRIPTION
Failure of feedwater heaters (FWHs) has a significantly adverse effect on the avail-
ability and thermal efficiency of both fossil fueled and nuclear power plants, with
especially severe financial consequences for baseloaded units. EPRI Final Report
CS-1776, Failure Cause Analysis--Feedwater Heaters (April 1981), identifies six
major categories of FWH problems in fossil fueled plants and recommends approaches
to reducing their severity. EPRI Final Report CS-3184, Corrosion-Related Failures
in Feedwater Heaters (July 1983), provides further information into generic failure
modes of commonly used materials in FWHs and how to control them. A growing body
of knowledge on nuclear plant FWHs complements these findings with data on their
specific operating conditions.
Utility personnel need guidelines to assist them to apply this information to their
specific requirements for operation, maintenance, and repair or replacement of FWHs.
This final report for RP1887-3 addresses those needs. It will be complemented with
the results from RP1887-1, Recommended Design and Procurement Guidelines for Feed-
water Heaters in Large Power Generating Units; these results will be published later
this year.
PROJECT OBJECTIVE
The specific objective of this study was to prepare guidelines that utility person-
nel can apply to develop detailed procedures and policies to meet their specific
requirements for operation, maintenance, and replacement of closed FWHs.
PROJECT RESULTS
These guidelines contain four main sections. The first describes the general con-
figuration of closed FWHs. The second section addresses the six problem categories
identified by EPRI CS-1776 in terms of causes, symptoms, operating practices to
correct or minimize the causes and symptoms, and recommendations for alleviating
them. The analysis required to limit FWH and plant operations whenever one or more
FWHs are out of service is described in the third section, and the final section
gives a basis for assessing a repair or replacement decision for a FWH.
The scope of this publication is limited for several reasons. There is too much
detailed information available to include all that is pertinent. Detailed proce-
dures must be prepared for each plant depending on its equipment, configuration, and
operating requirements. Operators and maintenance personnel must obtain accurate
current information from vendors for this purpose.
This document will be of interest to utility engineers and plant operators who are
responsible for planning and conducting the operation, maintenance, and repair of
closed FWHs in all types of plants. This preliminary guide is promulgated with the
intention to improve it on the basis of user comments as'well as new developments.
vii
CONTENTS
Section Page
2.1.1 O v e r v i e w Of M a j o r P r o b l e m A r e a s 2-1
2.1.3 Symptoms Of L e v e l C o n t r o l A n d D r a i n s C o o l e r
Zone Problems
2.1.4 O p e r a t i o n a l Practices T o A v o i d O r M i t i g a t e
Problems
2.2.1 Overview
2.2.2 Symptoms Of V i b r a t i o n P r o b l e m s
2.2.3 O p e r a t i n g A n d M a i n t e n a n c e Practices To A v o i d
O r M i t i g a t e V i b r a t i o n Damage
2.3.1 Overview
2.3.4 O p e r a t i o n a l Practices T o A v o i d O r M i t i g a t e
Damage
Section Page
2.4.3 D e t e c t i o n Of Water C h e m i s t r y - R e l a t e d
Problems
2.4.5 C h e m i s t r y C o n s i d e r a t i o n s R e l a t e d To
D e s i g n And System M o d i f i c a t i o n s
2.5.1 Overview
2.5.3 O p e r a t i o n a l P r a c t i c e s To Avoid O r M i t i g a t e
Steam Impingement Damage
2.6.1 Overview
2.7 Miscellaneous
2.7.2 Welded V e r s u s B o l t e d P a r t i t i o n P l a t e s
4.1 Overview 4- 1
Figure
2-33 Welded P a r t i t i o n P l a t e
2-34 Bolted P a r t i t i o n P l a t e
Table Page
.
to the individual plant environment.
For the same reason, it is essential that the operators and maintenance
personnel obtain from the vendors and use accurate, updated information
regarding their FWHs. In addition to vendor manuals, the utility should
have arrangement drawings of each FWH showing the details, dimensions,
and materials used for its internals, as well as all penetrations and
instrument connections. This EPRI guide should be helpful when used &
addition to the official documentation for the individual FWH, but
utility personnel should be cautioned not to rely on generic guides (or
even textbooks) in place of the official hardware-specific documentation.
The same limitation applies to operating and maintenance procedures.
Practices that experience has shown to be effective are recommended
throughout this guide. However, these recommendations are submitted for
the consideration of the utilities; they should be followed only when
properly approved and promulgated by the utility.
It is recognized that this guide would be more complete with several
sections added. One such section should be devoted to detailed advice
concerning the "dos and don'ts' of FWH procurement, including the many
considerations needed in developing a good purchase specification.
Assistance in this area is badly needed by the utilities and is being
pursued in a separate EPRI project.
*Based upon EPRI's 1980-1981 survey as summarized in EPRI Report CS-1776, "Failure
Cause Analysis - Feedwater Heaters. "
A t t h e back of t h e g u i d e a r e c o p i e s o f t h e "User Feedback Form," which a r e p r o v i d e d
t o f a c i l i t a t e feedback from t h e u s e r s . They c a n b e f i l l e d o u t , removed, and m a i l e d
back t o EPRI t o h e l p f o c u s improvements f o r t h e n e x t e d i t i o n o f t h e g u i d e i n t h o s e
a r e a s t h a t a r e needed by t h e u t i l i t i e s . Any p h o t o g r a p h s , good p r o c e d u r e s , o r o t h e r
i t e m s t h a t m i g h t be of i n t e r e s t t o o t h e r s would a l s o be welcomed.
Section 1
1.1 GENERAL
~ lmodern,
l l a r g e s t e a m power p l a n t s u s e a p r o c e s s o f r e g e n e r a t i v e f e e d w a t e r h e a t -
i n g t o i n c r e a s e t h e o v e r a l l c y c l e e f f i c i e n c y of t h e p l a n t and t o minimize induced
thermal s t r e s s e s i n the b o i l e r . T y p i c a l p l a n t s u t i l i z e two t y p e s o f f e e d w a t e r
h e a t e r s (FWHs): l o w - p r e s s u r e and h i g h - p r e s s u r e . Many a l s o have i n t e r m e d i a t e -
p r e s s u r e EWHs.
HEATER SUPPORT
DESUPERHEATING
TUBE SUPPORTS ZONE BAFFLES
(See Figure
For Typical
HEATER SUPPORl TIE RODS DRAINS SUBCOOLING FEEDWATER Channel Conf
AND SPACERS ZONE BAFFLES IN LET urations)
SAFETY VALVE
SUPPORT PLATES
CONDENSATE W E
OPGf GLILSS
MANWAY COVER
TUSE SHEET
PARTITION
FEEDWATER INLET
COVER
ELLIPTICAL HEAD
I HE>IISPHERIC.\L HEAD
FEEDWATER OUTLET
PASS PARTITION
COVER
PASS PARTITION
BOLTED RE-MOVABLECOVER
I !?iS;OV.ABLE COVER FULL OPESING
.
prevent impingement damage to the tubes.
Condensing Zone: This is the largest zone in the FWH. Steam exiting the
desuperheating zone is condensed as it traverses through the condensing
zone. Also, any drains from higher pressure FWHs flow into the con-
densing zone through the drains inlet nozzle. An impingement plate is
installed just inside this nozzle to protect the tubes from these
flashing drains. The condensing zone is vented continuously to remove
non-condensibles. The vent system typically consists of one or more
perforated vent pipes installed along the length of the tube bundle.
(Many other designs are also used to accomplish this function.) Non-
condensibles collect in these pipes and then pass through shell vent
connections to the deaerator or the main condenser. An orifice, in-
stalled in the vent discharge, is sized to result in a flow rate equal to
0.5% of the total steam flow entering the FWH.
Electric Power Research Institute (EPRI) surveys and workshops continue to indicate
a strong need for improving the knowledge and experience of utility personnel in-
volved in the operation, maintenance, and replacement of feedwater heaters (FWHs).
It is particularly important that such personnel understand the principal problems
that have already been experienced many times throughout the industry. Only with a
good understanding of these problems will they be able to avoid, detect, and mini-
mize similar problems in their own systems. Accordingly, this section of the guide
addresses each major problem area identified by previous EPRI surveys* and provides
comments and recommendations from the combined experience of the FWH experts who
contributed to this effort. In selecting material for the following sections, the
emphasis has been to focus on those key points that experience has shown to be most
essential for proper operation and maintenance of FWH systems.
Few people give much thought to the phenomenon or realize that if a given weight of
saturated water decreased in pressure from 100 psia to - 5 psia, approximately 24%
p l a t e a t a p p r o x i m a t e l y t h e s h e l l mid-point s e r v e s a s t h e c l o s u r e o f t h e f u l l 1800
arc. The s h r o u d i n g is l e a k t i g h t s u c h t h a t t h e c o n d e n s a t e e n t e r s an opening a t t h e
bottom o f t h e d r a i n s c o o l e r , away from t h e t u b e s h e e t , and c o m p l e t e l y f l o o d s t h e o u t -
s i d e s u r f a c e of t h e t u b e s a s it f l o w s p a s t b a f f l i n g t o t h e o u t l e t end, which i s
l o c a t e d c l o s e t o t h e back o f t h e t u b e s h e e t .
I n t h e long d r a i n s c o o l e r , t h e s h r o u d i n g r u n s t h e f u l l l e n g t h o f t h e t u b i n g b u t
encompasses o n l y a p o r t i o n of t h e t u b e s i n t h e f i r s t p a s s . The f l a t p l a t e p o r t i o n
o f t h e s h r o u d i n g p a s s e s between t h e t u b e rows, and t h e a r c d e p t h v a r i e s depending
upon t h e amount o f t u b e s u r f a c e r e q u i r e d f o r s u b c o o l i n g . The c o n d e n s a t e e n t e r s a
l o n g d r a i n s c o o l e r a t t h e end f a r t h e s t from t h e t u b e s h e e t and f l o w s t h e f u l l l e n g t h
p a s t t h e b a f f l i n g t o t h e e x i t , which is l o c a t e d c l o s e t o t h e back o f t h e t u b e s h e e t .
Table 2-1
2-3
Feed Out
Drains Cooler
Shrouding
4
M i n i m Liquid Level Drains Cooler
D r a b s Cooler
Shrouding
Feed Out
M i n i m Liquid Level
r
Drains C o o l e r
Shrouding
T'
-l t
Drains Out Feed In
Drains Cooler
Shrouding
2-4
In the case of the long drains cooler, the minimum operating level should be main-
tained above the flat plate of the shrouding. In the case of the short drains
cooler, the minimum operating level should be maintained at a point where the en-
trance into the shrouding (the "snorkel" area) is always covered, even throughout
plant transients. A horizontal unit, of course, does have the capability of storing
relatively large quantities of water such that the level can be maintained within a
few inches in the vertical direction.
It is important to recognize that the level within a FWH is not necessarily the same
at all locations. The level can vary, depending on the pressure that exists at the
surface of the condensate, which is a function of the position of the steam inlet,
the design of the internals, and the flow through the unit. Discussions with ex-
perienced utility and vendor engineers indicate that these phenomena have been ob-
served under test conditions in the past. One thing that was established is that
the level can vary significantly from the back of the tubesheet to the other end of
the FWH. Under certain circumstances of operation, it could have a reverse slope;.
it could even have a two-way slope with a peak in the middle or vice versa. Main-
taining a suitable level as the condensate approaches the drains cooling zone of the
EWH is essential. It is especially important to maintain the level above the en-
trance at all times. Therefore, the location of the liquid level control instru-
mentation should be as close as practical to that region. A mistake often made is
to provide liquid level control sensor points that are located physically a signif-
icant distance from the areas of concern. Some years ago, there was an experience
at a utility in Europe where it was determined that the water level at the U-bend
end was 18 inches higher than at the drains cooler entrance. An investigation re-
vealed that the FWH was very poorly designed. The heater was designed along the
principles governing water-to-water heat exchangers, which did not provide enough
clearance for steam flow. Therefore, large pressure drops occured, resulting in the
great level variations. Because both water and steam are present in a FWH, each
zone must be considered individually during design. It is important that the shell
side of a FWH with a horizontal drains cooler be as free of obstruction as possible
and that it be properly sized so that there is good distribution of steam without
undue pressure drop.
A d d i t i o n a l l y , t h e t u r b i n e m a n u f a c t u r e r s may h a v e o v e r p l a y e d t h e i r role i n i m p r e s s i n g
upon t h e u t i l i t i e s and t h e o p e r a t i n g p e r s o n n e l o f t h e power p l a n t t h a t t h e i n d u c t i o n
o f water i n t o t h e t u r b i n e must be avoided a t a l l c o s t s . T h i s p o i n t h a s been
s t r e s s e d i n many t e c h n i c a l p a p e r s and v e n d o r m a n u a l s to t h e e x t e n t t h a t t h e o p e r a -
t o r s i n t h e c o n t r o l room a r e s o w e l l a w a r e o f t h i s w a r n i n g t h a t t h e i r r a t i o n a l e f o r
p r o p e r o p e r a t i o n o f FWHs is sometimes c l o u d e d . They f e a r t h a t t h e p o s s i b i l i t y o f
i n d u c i n g w a t e r i n t o t h e t u r b i n e b y a l l o w i n g a h i g h w a t e r l e v e l i n t h e EWHs is s o
g r e a t t h a t a p r i m e c o n c e r n is t o e n s u r e t h a t t h e l e v e l s t a y s a s l o w a s p o s s i b l e .
T h i s l i n e o f r e a s o n i n g sometimes l e a d s to t h e c o n c l u s i o n t h a t a z e r o w a t e r l e v e l i s
d e s i r a b l e b e c a u s e i t p r o v i d e s maximum t u r b i n e p r o t e c t i o n .
I t may b e h e l p f u l t o t h i n k o f d r a i n s t h a t a r e a b o u t t o f l a s h l i k e a n e x p l o s i v e ,
w h i c h i f h a n d l e d p r o p e r l y , c a n b e b o t h managed and t r a n s p o r t e d . However, i f t h e y
a r e n o t h a n d l e d p r o p e r l y , t h e y w i l l e x p l o d e w i t h t e r r i f i c f o r c e and c a u s e damage.
The d e t o n a t o r m u s t b e removed f r o m t h e e x p l o s i v e . How c a n t h i s o b j e c t i v e b e accom-
plished with the flashing? The f l a s h i n g c o n d i t i o n s h o u l d b e e l i m i n a t e d , s t a r t i n g
w i t h t h e s u c t i o n o f t h e d r a i n s c o o l e r a l l t h e way down t o t h e d r a i n s c o n t r o l v a l v e .
T h i s c a n b e a c c o m p l i s h e d by m a i n t a i n i n g t h e p r o p e r l e v e l i n t h e d r a i n s c o o l e r . Not
o n l y s h o u l d t h e l i q u i d l e v e l c o n t r o l l e r b e l o c a t e d a t t h e p o i n t where c o n d e n s a t e
e n t e r s t h e d r a i n s c o o l e r , b u t a l o c a l g a g e g l a s s s h o u l d b e i n s t a l l e d a t t h e same
location for visual level verification. I t is a l s o a good i d e a f o r t h e l o w e r r a n g e
o f t h e c o n t r o l l e r t o b e no l o w e r t h a n t h e b o t t o m o f t h e s h e l l so t h a t t h e f u l l r a n g e
is e f f e c t i v e . A n y t h i n g below t h e s h e l l b o t t o m is u s e l e s s , and o n e s h o u l d n o t p r o -
mote t h e i d e a t h a t a n o p e r a t o r would a l l o w t h e l e v e l t o d r o p t h a t low.
I n a v e r t i c a l c h a n n e l down FWH, t h e f i r s t t h i n g t o o b s e r v e is t h a t t h e c a p a c i t a n c e *
i n a t h r e e - z o n e FWH i s a p p r o x i m a t e l y h a l f t h a t i n a two-zone FWH b e c a u s e , a s shown
i n F i g u r e 2-2, t h e s p a c e t h r o u g h w h i c h t h e d e s u p e r h e a t e r s h r o u d i n g p e n e t r a t e s is
e l i m i n a t e d i n computing t h e c a p a c i t a n c e . I n a two-zone FWH, a l l o f t h e c r o s s - s e c -
t i o n a l a r e a around both p a s s e s o f tubes is a v a i l a b l e f o r maintaining t h e l e v e l .
T h o s e t u b e s n o t i n c o r p o r a t e d w i t h i n t h e d r a i n s cooler a r e c o n s i d e r e d i n e f f e c t i v e
s u r f a c e b e c a u s e t h e y a r e submerged and s e r v e n o r e a l h e a t t r a n s f e r p u r p o s e . How-
e v e r , t h i s a r r a n g e m e n t i m p r o v e s t h e c a p a c i t a n c e f a c t o r a s compared t o a t h r e e - z o n e
design.
* C a p a c i t a n c e , a s r e l a t e d t o t h e a d e q u a c y o f d e s i g n i n g a c o n t r o l s s y s t e m , is d e f i n e d
a s t h e s t o r a g e volume ( u s u a l l y g a l l o n s ) o f l i q u i d p r e s e n t p e r i n c h o f l e v e l c h a n g e
i n t h e l e v e l c o n t r o l range.
Steam I n
Drains
Drains Outlet
2-8
In a three-zone FWH, one must pay special attention to the distance between the top
of the drains cooling zone and the exit of the desuperheating zone because it is
important to maintain the drains water level between these two points. A well-
designed FWH should have the exit of the desuperheating zone well above* the drains
cooling zone and a low liquid level that is maintained several inches** above the
drains cooling zone. High-level conditions that allow the overflow of water into
the desuperheating zone are detrimental to the life of that zone.
The vertical FWH, by its nature, will usually have considerably less capacitance
than a horizontal FWH. Unless the diameter of the shell is such that adequate ca-
pacitance is provided, it is somewhat analogous to controlling the level in a straw:
the minute that one starts sucking, the level will disappear. It is imperative to
provide enough volume so that the load changes do not drive the level out of the
designed control range due to lack of capacitance. Table 2-2 shows the desired
reservoir capacity needed by most# control systems in gallons per inch of depth,
depending upon the quantity of the drains that are being handled. Practical exper-
ience has shown that if these guidelines are followed, it is possible to control the
level within the 25-45 inch span typically recommended by experienced personnel.
However, it is noted that many FWHs now in existence have a smaller band, which may
demand superior performance from the level control system.
For proper level control, it may be necessary to increase the shell diameter for a
given tube bundle diameter so that the proper capacitance is available. Figure 2-3
displays a modification that was made on a FWH in just that manner. The lower por-
tion of the FWH shell was enlarged to what is referred to as a belly band. This
modification not only provides greater capacitance, but also lowers the velocity of
the flashed steam (from inlet drains) as it exits from the lower portion of the FWH.
Figure 2-4 shows internals of the same FWH that had its shell enlarged. A portion
of the drains cooling zone shroud was cut away (as indicated by the white line) to
increase the difference in elevation between the drains cooling and desuperheating
zones from approximately 14-24 inches. In considering such a modification, it is
*At least 24 inches (and preferably more to accommodate fluctuations in level con-
trol).
#performance and capability depend upon the response of the system being used.
Typically, systems in use today are represented in Table 2-2.
Table 2-2
It has been stated that the lowest water level allowed should be at least several
inches above the top of the drains cooler. For reasons of economy, some may desire
smaller FWHs, not allowing room for such a margin at the low level. It must be
remembered that if the water level should drop below'the shroud itself, there will
be steam but no drains going into the drains cooler, which is not the way to operate
the unit.
In a two-zone FWH, by these same guidelines, the level is easier to maintain, with-
out increasing the size of the shell, inasmuch as the complete shell cross-section
minus the cross-section of all tubes is available for the required capacitance
levels.
One special circumstance that can develop in a three-zone vertical FWH is where the
desuperheating zone surface is less than the drains cooling surface. In such a
case, it becomes necessary to artificially raise the top of the desuperheating zone
so as to meet the aforementioned level range criteria. This can be accomplished by
providing special baffling at the bottom of the desuperheating zone, thereby cre-
ating a dead zone from that point down to the tubesheet. When this happens, there
may be a tendency to skimp on realistic control ranges leading to operational prob-
lems. There is also a possibility that some novel design of drains cooler will be
attempted to cut its height. Over the years, there have been a number of variations
of two-pass shellside drains cooler (otherwise called "double-shrouded" or "reverse
flow syphon-drains cooler") designs that have rarely worked. These supposedly will
allow maintaining an operating level a few inches above the backside of the tube-
sheet. Although some of these designs might work at stable load conditions and with
no imperfections in the manufacturing process, actual operating conditions make them
impractical. Flashing in the upflow pass invariably occurs, and the drains cooler
becomes ineffective.
2.1.1.3 Vertical Channel Up Feedwater Heaters. A vertical channel up FWH that in-
cludes a drains cooler is subject to similar difficulties of flashing during varying
load conditions. In this design, the drains cooler shrouding encloses several rows
of tubes, and water level is maintained at the bottom of the shell (U-bend end).
These drains must be lifted to the top of the unit, and the potential for flashing
is exceptionally high.
2.1.2 Examples Of D r a i n s C o o l e r Problems
F i g u r e 2-5 shows p i c t u r e s o f t y p i c a l damage from f l a s h i n g i n d r a i n s c o o l i n g zones.
I t i s i m p o r t a n t t o n o t e t h a t t h e f l a s h i n g t h a t t a k e s p l a c e is s o v i o l e n t t h a t t h e
b a f f l e s and s h r o u d s have been t h i n n e d , t u b e s d e s t r o y e d , and welds c r a c k e d . When
t h i s happens, t h e a b i l i t y t o o p e r a t e t h e FWH i n a normal manner is l o s t and a d d i -
t i o n a l problems d e v e l o p t h a t must b e c o r r e c t e d ; i f t h e y a r e n o t , t h e d e s t r u c t i o n o f
t h e FWH f o l l o w s r a p i d l y . A few examples o f t y p i c a l problems a r e c i t e d below f o r
emphasis :
Case 3: A weld c r a c k e d i n a s h i e l d p l a t e i n a p o r t i o n of t h e d r a i n s
c o o l e r shroud o f a v e r t i c a l c h a n n e l down FWH. The weld c r a c k s were de-
t e c t e d a f t e r o b s e r v i n g t h e i n a b i l i t y t o c o n t r o l t h e l e v e l . The FWH was
p r o p e r l y r e p a i r e d and r e t u r n e d to s e r v i c e .
.
stable load operation.
Figure 2-6. Vertical Channel Down Feedwater Heater With Welded Blister
2-16
In summary, the experience of the experts who contributed to this guide clearly
points to flashing and improper operation of drains cooling zones as one of the
most important contributors to the failure of FWHs, particularly in horizontal
FWHs. This judgment is supported by the failure analysis data summarized in EPRI
Report CS-1776. The utility survey on which that report was based also showed that
the real cause of many FWH failures was never determined. gain, experience sug-
gests that many of the "unknowns" could have belonged in the level control and
drains cooler zone category.
EPRI Report CS-1776 also contains a concise summary of drains subcooler problems as
discussed in the literature. Pages 4-1 through 4-14 are recommended reading for
operators to gain further understanding of the operation of the level control sys-
tem and the drains subcooler zone as well as the major problems to be avoided. A
good appreciation of the experiences outlined above and in CS-1776 will help plant
personnel avoid or minimize many of the problems that threaten the life of their
feedwater FWHs.
An unusual noise that is often heard (like marbles in a bottle) is the sound of
flashing. It is not unusual to detect this type of sound downstream of the drains
control valve. However, when a similar noise is heard upstream of the valve, then
i t is an indication of potentially damaging flashing. Today's technology has pro-
duced equipment that is capable of differentiating between noises to pinpoint a
certain type. Acoustic monitors are available on the market that give the user an
opportunity to first establish that a flashing noise exists and then to quickly
determine whether this condition exists upstream of the drains control valve.
For comprehensive, accurate performance tests, the ANSI/ASME Performance Test Codes
(PTC 12.1, 1978) should be used as a detailed guide. However, for routine trouble-
shooting and quick checks of FWH performance, the simple test outlined below can be
made without a complete heat balance, special instrumentation, or elaborate compu-
tations. The test form shown in Figure 2-7 can be used to determine uncorrected
terminal temperature difference (TTD) and the approach for comparison with design
figures for these parameters, Note that the uncorrected TTD developed in line 4 of
Figure 2-7 for the "actual" column is different (for simplicity) from the corrected
TTD* developed in PTC 12.1 as indicated below:
The TTD is, in effect, a measure of the heat transfer capability of the FWH. The
higher the terminal temperature difference above design (if the value is positive),
the poorer the performance of the FWH. The actual measurements can only be com-
pared to the values obtained during performance tests to see whether any serious
change is taking place. If for the same conditions the TTD is substantially higher,
then the FWH has problems.
The "approach" in line 7 is the difference between the drains outlet temperature
and the feedwater inlet temperature.
In addition to the general data recorded at the top of this form, critical readings
to be gathered are:
Lines 3 & 6: Temperature reading of the feedwater flow at the EWH outlet
and inlet connections;
r Line 5: Temperature of the drains as they leave the FWH shell; and
Lines 2, 4, and 7 do not involve data gathering in the plant but are obtained from
the steam tables (for Line 2) or simple arithmetic (Lines 4 and 7).
GENERATING STATION U N I T NO.
DATE TIME
ACTUAL DESIGN
CONDITION CONDITION
0 0
3. Feedwater o u t l e t temperature F F
5. Drains o u t l e t temperature
6. Feedwater i n l e t temperature
7. "Approach"
Item 5 -
I t e m 6 = Item 7
8. Feedwater flow
any o v e r l o a d c o n d i t i o n . I t would be an e x c e l l e n t p r a c t i c e f o r p l a n t o p e r a t o r s t o
know t h e v e r s a t i l i t y o f any FWH t h a t might b e r e q u i r e d t o o p e r a t e under abnormal
conditions. ( S e c t i o n 3 a d d r e s s e s t h i s a r e a i n more d e t a i l . )
e r a t e i n a s t e a d y s t a t e c o n d i t i o n w i t h o u t problems may e x h i b i t s i g n i f i c a n t f l u c t u -
a t i o n o f w a t e r l e v e l when c y c l i c a l c o n d i t i o n s a r e e x p e r i e n c e d . T h i s p o i n t empha-
s i z e s t h e need f o r t h e o p e r a t o r s to r e c o g n i z e t h a t blowing steam t h r o u g h a d r a i n s
c o o l e r is n e v e r a p r o p e r o p e r a t i n g p r a c t i c e . One s h o u l d b e l o o k i n g f o r a l e v e l t h a t
is r e l a t i v e l y steady. While undergoing l o a d c h a n g e s , t h e r e s h o u l d b e some l e v e l
f l u c t u a t i o n ; b u t upon r e t u r n t o s t e a d y s t a t e , even a f t e r g o i n g from a 100% l o a d t o a
25% l o a d , t h e l e v e l s h o u l d s t a b i l i z e . I f i t d o e s n o t , t h e swinging o f t h e l e v e l is
an i n d i c a t i o n o f problems i n t h e s y s t e m ( p r o b a b l y c o n t r o l s ) under s t e a d y o p e r a t i o n
t h a t should be i n v e s t i g a t e d . The t e s t t h a t was p r e v i o u s l y d e s c r i b e d i s a g u i d e t o
a c c o m p l i s h t h i s end.
I t is e s s e n t i a l t h a t t h e o p e r a t o r s u n d e r s t a n d t h e i m p o r t a n c e o f t h e d r a i n s o u t l e t
c o n t r o l v a l v e w i t h r e s p e c t to c o n t r o l l i n g t h e w a t e r l e v e l w i t h i n t h e power p l a n t FWH
system, Many c o n t r o l v a l v e s a r e n o t p r o p e r l y s i z e d and o p e r a t e d f o r t h e s e r v i c e
intended. The tendency seems to b e to o v e r s i z e t h e c o n t r o l v a l v e s and, i n a d d i t i o n ,
t o o p e r a t e w i t h t h e v a l v e s opened wider t h a n n e c e s s a r y . A b a s i c mistake is n o t
r e a l i z i n g t h a t when t h e v a l v e is opened w i d e r t h a n n e c e s s a r y , t h e r e c o u l d be
f l a s h i n g upstream o f t h e v a l v e , whereas t h e f l a s h i n g s h o u l d t a k e p l a c e o n l y down-
stream of t h e valve s e a t . Again, i t i s i m p o r t a n t t o remember t h a t t h e p a s s i n g o f
f l u i d t h r o u g h a c e r t a i n a r e a is a f u n c t i o n n o t j u s t o f t h e p r e s s u r e and open s p a c e ,
b u t a l s o o f t h e d e n s i t y and volume o f t h e f l u i d and t h e geometry o f t h e a r e a . When
f l a s h i n g is a l l o w e d upstream o f t h e v a l v e , t h e f l u i d volume and v e l o c i t y i n c r e a s e
d r a m a t i c a l l y , and a v a l v e s i z e d on t h e b a s i s o f p a s s i n g o n l y w a t e r c o u l d b e t o o
s m a l l t o p a s s t h e m i x t u r e o f f l a s h e d steam and w a t e r (two-phased f l o w ) .
In one set of tests, identical drain quantities were passed by the liquid level
control valve when it was adjusted manually to only 60% open, as compared to what it
was passing when wide open under automatic control. When the valve was only 60%
open, the pressure drop through it was high enough that the upstream pressure re-
mained sufficient to preclude flashing; when the valve was wide open, the pressure
condition at the point of inlet was such that flashing was occurring ahead of the
valve. Therefore, with the limited valve opening, only hot water was passing
through, whereas a combination of hot water and steam was flowing across the valve
seat when the valve was wide open. Even though the same quantity of drains flowed
in each instance, the 100% open valve condition was most likely damaging the valve
trim (i.e., the valve plug and the seat).
Similarly, another utility developed problems with a LP FWH drains valve to the
condenser. Upon investigation, the operating personnel were asked to override the
controls of this valve, which was not passing the required quantity of drains while
it was fully open. When the valve was manually set to a position 50% open, an in-
creasing level was experienced for a short period of time, followed by a decrease to
the design level. Prior to that adjustment, it was decided to bypass the drains
from the upstream FWH to the condenser, rather than to cascade to the lowest pres-
sure FWH, thereby minimizing flow through that troubled valve. When the real prob-
lem was recognized and solved, the operators returned to the cascading mode without
further difficulties.
Performance o f a l i q u i d l e v e l c o n t r o l s y s t e m is d e p e n d e n t upon p r o p e r m o n i t o r i n g a s
w e l l a s t h e a b i l i t y o f a l l components t o d o t h e i r job. T h e r e f o r e , it is n e c e s s a r y
t o know where t h e v a r i o u s l e v e l s s h o u l d be i n a FWH. For e a c h FWH t h e r e s h o u l d be a
s i m p l e s k e t c h o f t h e i n t e r n a l s s i m i l a r t o t h a t shown i n F i g u r e 2-9, which i n d i c a t e s
where t h e low t u b e i s , how many t u b e s s h o u l d b e submerged, and what happens when t h e
l e v e l moves from h i g h to low. The o p e r a t o r s i n t h e power p l a n t s h o u l d have a s u f -
f i c i e n t u n d e r s t a n d i n g o f what a low o r h i g h l e v e l means and how l e v e l s s h o u l d f l u c -
t u a t e during t r a n s i e n t s . F i g u r e s 2-10 and 2-11 d e p i c t b o t h h i g h and low s h e l l l e v -
e l s for a horizontal situation. F i g u r e 2-11 c l e a r l y i l l u s t r a t e s where a f l a s h i n g
c o n d i t i o n d e v e l o p s when a l e v e l is m a i n t a i n e d too l o w .
The l a c k o f u n d e r s t a n d i n g c o n c e r n i n g t h e l e v e l s on t h e FWHs c a n b e c o r r e c t e d by
r e q u e s t i n g a d d i t i o n a l i n f o r m a t i o n s o t h a t t h e u t i l i t i e s have p r o p e r d r a w i n g s and
information. One u t i l i t y p o s t s t h e s e l e v e l s i n t h e c o n t r o l room on d i a g r a m s s i m i l a r
t o F i g u r e 2-12. The example shows a v e r t i c a l c h a n n e l down u n i t , i n d i c a t i n g t h e
l o c a t i o n s o f t h e low p o i n t , t h e h i g h p o i n t , t h e normal w a t e r l e v e l , and t h e d i s -
t a n c e s between them. A l s o i n f e r r e d from t h i s d i s p l a y is t h e number o f i n c h e s
746 U q u b e s --
3/4" O.D. And 15/16" A P i t c h
Band O f L e v e l From Low To High 2-7/8" --
2r17
-Trip Out
i
-High W.L.
- Normal W. L . I
f
Entrance To
Drains Cooler
41-11/16" I
Drains Cooler
-
Steam Inlet
Drains
Out
* .) - I
/
I Back Of
Tube Shell
I
I
I
Figure 2-12. Level I n d i c a t i o n s O f A V e r t i c a l Channel Down Feedwater Heater
2-27
remaining before damaging conditions are established within the FWHs. For instance,
in a vertical channel down unit, the level is shown where the drains cooler water is
going to flow into the desuperheating zone and create problems leading to the de-
struction of tubes and baffles as the steam exits from the desuperheating zone.*
One experienced vendor suggested that the utilities be warned not to place much
faith in the location of level benchmarks that the manufacturer often places on the
outside of the FWH shell. These are intended to indicate the optimum water level,
but there are two drawbacks to relying on such benchmarks. First, the utility can-
not be sure that the benchmark is really in the correct position for optimum FWH
performance. Second, the level indication may not represent the true level in the
vicinity of the entrance to the drains cooler, as discussed earlier in Section
2.1.1.1. For these reasons, some FWH experts recommend that after the new FWH is
installed and operating, it should be checked to ensure that the designed approach
temperature is achieved at the intended "normal" level. If not, the "normal" level
should be adjusted to achieve the optimum approach temperature, while avoiding any
sharp increase in approach at the low-level end of the operating range. Figure 2-13
is a plot of an actual test performed on a horizontal FWH to check liquid level set
points. The level was raised to 3 inches or more above the bottom tubes (12 inches
above the bottom of the shell in this FWH). After temperatures had stabilized,
performance data were recorded and plotted. Then the level was lowered in succes-
sive steps to obtain and plot additional data. The resulting curves of outlet pres-
sure and approach showed significant breaks or "knees" at 6 inches on the level
indication scale. At this critical level, flow velocity was increasing rapidly from
flashing and the pressure drop was increasing across the drains cooler. Using this
type of data, the "normal" level was set to meet the designed approach, ensuring
that that point was well above the critical level (approximately 2 inches above the
critical level for this particular FWH). It is suggested that the optimum arrange-
ment for most horizontal FWHs is an operating range (including the low-level alarm
setpoint) completely above the critical level with the normal level at the designed
approach. It is also important to provide ample separation between the normal oper-
ating range and both the high- and the low-level alarm setpoints to avoid spurious
alarms for normal plant transients. If it is necessary to plug some of the lower
tubes in a horizontal FWH, it is wise to repeat this procedure for checking levels
by temperature performance; higher level setpoints may be needed.
*In the example shown, this point is 2 inches above trip out or 42 inches above
the entrance to the drains cooler.
S H E L L LIQUID LEVEL-INCHES
ABOVE BOTTOM 10 OF SHELL
Figure 2-13. Example Of Data Used To Check Level Vs. Temperature Performance.
(This EWH is different from those represented by other figuxes in this section.)
Source: Feedwater Heater Operation, F.H. Linley, Jr., Southwestern Engineering Co.,
Annual Conference of the Southeastern Electric Exchange, New Orleans, LA, April 1983.
If following the above procedure leads to a "normal" level somewhat higher than the
manufacturer's benchmark, no harm will be done. However, if it leads to lowering
the level, the utility must be very careful because a normal level that is close to
the snorkel input to the drains cooler (in a horizontal FWH) or within 2 inches of
the top of the drains cooler shroud (vertical, head-down FWH) may provide too little
margin for power excursions, allowing steam to flow directly into the drains cooler.
~f in doubt, or if the drains cooler approach temperature indicates that significant
level adjustment is necessary, it is prudent to discuss this problem with the vendor
and ensure that the decisions reached are based on a sound engineering judgment of
all factors applying to the specific installation. Ensuring proper level control
throughout the FWH's life is essential to avoiding the serious problems described
herein.
The practice mentioned earlier of "jacking open" valves or "short stroking" valves
to prevent water induction to the turbine is destructive and costly. Valves should
not be jacked open or short stroked in any power plant. Instead, proper maintenance
and, in some cases, preventive maintenance will permit proper operation. Valves
tend to leak and must be repaired, and some need repacking on a regular basis. It
is important that valves be capable of performing the function for which they were
intended. This is true not only in reference to control valves; it also applies to
isolation valves and check valves in steam lines as well as in drain lines. Too
often, such valves are ignored and will not perform their designed function because
of the lack of preventive or corrective maintenance.
During operation and layup periods, crud deposits can build up on floats, liquid
level sensors, and regulator valves, causing malfunction of the level control sys-
tem. The plant's preventive maintenance program should include periodic inspection
and cleaning of those components as well as a review of chemistry control procedures
to minimize the deposits. Another worthwhile preventive maintenance action is peri-
odic inspection for steam leaks, especially in the vicinity of the electronic con-
trols for the level control system. Corrective maintenance may be needed not only
to stop the leaks but, in some cases, to relocate sensitive control modules away
from such steam sources.
Taking appropriate data and adjusting the drains control system for proper operation
as discussed earlier is an example of a good preventive maintenance practice that
can ensure proper system operation if the individual components are kept in good
working condition. When in excellent condition, the control system of a power plant
that is cycling can still maintain good performance. When there are sticking valves
or controllers, system damage is likely to be occurring somewhere in the plant.
The ability to bypass drains on the shell side is also desirable. It is impossible
for the drains to be handled normally when they are increased beyond the drains
cooler flow capability. In such a case, the bypass or spill of drains to the con-
denser will probably be mandatory. This deficiency is presect in many installations
in the United States. Usually, this bypass to the condenser is called the dump
valve or high-level spill valve. Many installations have two-position (non-modu-
lating) open or closed valves that open wide to the condenser upon indication of
high level in the FWH. With a good design, and under normal operating conditions,
the drains control valve should be capable of passing the flow from a higher to a
lower pressure FWH with the valve modulating not on the high open side but somewhere
in the middle range. Under abnormal circumstances, the valve should be able to open
up to the full capacity. Only when this drains control valve is incapable of pass-
ing the flow should the dump valve be called on to act. At that point, the dump
valvz should be opened slowly and modulated like the control valve. Flashing is
again a concern because the system reaches a region of much lower pressure. If
drains go from a HP FWH operating at 600-800 psi (via the bypass) to the condenser,
which is operating on 1 psia, the hazard of introducing a low-pressure region into
the drains cooler is very real, especially if the dump valve is not operating and
modulating the way it should.
An extreme example is an instance when one unit had a dump valve from a HP EW3 to
the condenser stick in the open position. This vertical EWH was shaking on its
foundation. Calculations later showed that the pressure decreased to the point that
all drains cooler drains were flashing and the pressure was so low that there was
fluid at sonic velocity inside that one FWHts drains cooler. Again, the valves that
are drain valves leading into a low-pressure region should be modulating valves, not
open or closed valves. As such, they should be identified as "drains cooler bypass
control valves," and the term "dump valves" should be eliminated.
A utility that uses quick-opening drains cooler bypass control valves should consi-
der modification. When doing so, consideration should be given to the recommenda-
tion that a drains cooler bypass control valve should always be located in a sepa-
rate line that taps off from a shell connection located ahead of the drains cooler.
Many existing installations locate this valve in a branch line off the main drains
line. In so doing, all of the emergency dump flow must first pass through the
drains cooler baffling. Since this flow is usually in excess of design conditions,
and also in a flashing state, considerable damage to the drains cooler internals can
be expected when the drains bypass valve in such a location goes into operation.
Tubes vibrate at discrete frequencies that depend on the tube geometry, tube ma-
terial, and fluid densities. The lowest frequency is called the natural frequency.
2-32
The forces imposed on a tube by shell-side fluid flow fluctuate at certain frequen-
cies that are dependent on the flow rate and the geometry of the flow area. The
fluctuating forces will often cause the tube to vibrate, but damage results only if
the amplitude of the tube vibration is sufficient to cause (1) stresses in the tube
or tube joint that exceed the endurance limit for fatigue failure, (2) collision
between adjacent tubes, or (3) frettins wear between the tube and tube support
plate. The amplitude of tube vibration is the product of the static deflection and
the magnification factor !CMF). The static deflection is the non-vibrating tube
displacement caused by the lift and drag forces due to fluid flow over the tube.
The value of CMF depends on the ratio of the flow frequency to the tube natural
frequency and on the Level of system damping. When the frequency ratio is near
unity (resonance), large amplitude vibration can occur.
Much research on vibration in heat exchangers has been conducted in recent years by
the Heat Transfer Research Institute, Oak Ridge National Laboratories, and many
others. A recent literature search sponsored by EPRI identified numerous articles
pertinent to FWH application. A summary of that material, including brief explana-
tions of the principle theories for predicting vibration behavior, is contained in
Section 3.0 of EPRI Report CS-1776, "Failure Cause Analysis - Feedwater Heaters."
This reference was distributed to the utilities and should be read by FWH engineers
for background information and utility experience as reported in recent years.
Short explanations are provided therein for theoretical matters that are beyond the
scopz of this guide but are of real interest in appreciating tube vibration problems
(e.g., vortex shedding, turbulent buffeting, fluidelastic whirling).
Many of the conditions leading to damage by tube vibration can be resolved at the
purchasing stage by practical, common sense limits imposed in the specification. As
a minimum, the manufacturer should be asked to address transient and overload con-
ditions in his vibration analysis and to demonstrate how he determined the design to
be adequate for such conditions as well as normal operation. For reference, it
should be recognized that the maximum unsupported tube lengths recommended in Heat
Exchange Institute (HEI) and Tubular Exchange Manufacturers Association (TEMA) guide-
lines are not conservative, although they may be adequate for flows experienced in
normal operation. Some rWHs may see 200% or even 300% load when the next upstream
FWHS are isolated for repair; this condition may double or triple the steam flow and
cause excessive vibration if the FWH was not designed to accommodate this situation.
With regard to the last of the above items, it is important to note that tolerances
on tube holes in baffles and support plates must not be reduced too low just to
reduce vibration; proper allowance must be left for tube length expansion and con-
traction during temperature changes to preclude tube drag wear at supports, es-
pecially in horizontal FWHs. Typical tolerance is 1/64 inches (-0156 inches).
This point is less applicable to vertical FWHs where the tube weight does not rest
on support plates (which serve as spacers rather than as supports).
EPRI Report CS-1776 contains a summary and comparison of industry standards related
to vibration as published by HE1 and TEMA. That report also concludes that these
standards are inadequate with respect to preventing vibration problems; however,
pages 3-25 through 3-33 of the report are recommended reading for FWH engineers and
should be of assistance until improved guidelines are developed.
The following sections will describe the effects of the vibration phenomenon on the
various zones within a FWH on the shell side: the condensing zone, the drains cool-
ing zone, and the desuperheating zone.
2.2.1.1 Tube Vibration In The Condensinq Zone. There are two areas in the con-
densing zone that can be affected by destructive tube vibration. One area is the
U-tube area as shown in Figure 2-14. The unsupported tube length in the U-tube area
historically has been far greater than it should be. Even competent manufacturers
commonly followed the T?3MA guidelines that specify an unsupported tube length on the
U-tube rear support. The recommendation of TEMA in this instance is not considered
satisfactory for FWH power plant application. Experience has shown that one should
go beyond the TEMA requirement. As a general rule for U-tube bundles, it is recom-
mended that special supporting spacers or strapping be used to support (and separ-
ate) U-tubes for any unit where the outer tube limits are greater than 24 inches in
diameter. To make this rule of thumb clearer, if the outer tube limit is 48 inches
in diameter, every tube bend that is in the 24-48 inch diameter range should be
supported at U-bends. Figure 2-14 clearly indicates the condition of a large tube
bundle where the U-bends were not properly supported. Figure 2-15 shows the re-
placed bundles where baffles were provided at the U-bends for proper tube separation
and support.
P I v r a 2-78, T a k e Vibration Daaaqe A t %e O-Bend
S p e c i a l a t t e n t i o n must be p a i d where d r a i n s i n l e t o r s t e a m i n l e t o r b y p a s s e s a r e
a d m i t t e d a t t h e U-bend end. Impact p l a t e s a t t h e s e l o c a t i o n s must be anchored w i t h
g r e a t c a r e b e c a u s e t h e y a r e s u b j e c t t o v i b r a t i o n due t o t h e change i n p h a s e of t h e
l i q u i d a t t h e f l o w c o n d i t i o n s t h a t may e x i s t . The b e s t method of i n t r o d u c i n g d r a i n s
beyond t h e U-tubes i n h o r i z o n t a l FWHs i s t o p r o v i d e an e x t e n d e d chamber o f t h e s h e l l
i t s e l f beyond t h e U-tubes w i t h t h e p r o p e r b a f f l e plate/dam t o s e p a r a t e t h e d r a i n s
i n l e t from t h e U-bends p r o p e r . Such a dam s h o u l d have p r o v i s i o n s f o r s e p a r a t i o n o f
t h e f l a s h i n g steam a t t h e t o p and f l o w d r a i n s a t t h e bottom. F i g u r e 2-16 shows one
c o n f i g u r a t i o n f o r t h i s purpose.
Another a r e a of c o n c e r n f o r t u b e v i b r a t i o n i s w i t h i n t h e b u n d l e i t s e l f i n t h e con-
d e n s i n g zone. I n a d d i t i o n t o improper t u b e s u p p o r t l e n g t h , t h e major c a u s e o f t u b e
v i b r a t i o n on a condensing zone s t r a i g h t p o r t i o n is t h e v e l o c i t y o f t h e condensing
s t e a m w i t h i n t h e s h e l l around t h e bundle. Two major m i s t a k e s a r e made i n t h i s a r e a .
The f i r s t m i s t a k e i s p r o v i d i n g a s h e l l t h a t is t o o s m a l l i n d i a m e t e r , t h u s i n d u c i n g
high velocity. The second m i s t a k e is p r o v i d i n g s u p p o r t s t h a t e x t e n d t o t h e i n s i d e
d i a m e t e r ( I D ) o f t h e s h e l l and a r e made such t h a t v e r y l i t t l e a r e a is a v a i l a b l e f o r
f l o w around t h e v a r i o u s s u p p o r t s . F i g u r e 2-17 i l l u s t r a t e s how FWHs have been modi-
f i e d by c u t t i n g a p o r t i o n o f t h e s u p p o r t p l a t e s , t h e r e b y p r o v i d i n g improved opening
of flow a r e a a t t h e s u p p o r t l o c a t i o n s . T h i s is o n e a r e a t h a t c a n be a d d r e s s e d i n
t h e s p e c i f i c a t i o n s t a g e , t h e r e v i e w o f drawing d e t a i l s s t a g e , and d u r i n g i n s p e c t i o n
o f t h e manufacturing f a c i l i t i e s . I t d o e s n o t i n v o l v e e x p e n d i t u r e s o f money, b u t it
d o e s r e q u i r e c o o p e r a t i o n o f t h e vendor." The same t y p e o f e f f o r t c a n b e made w i t h
e x i s t i n g u n i t s i n t h e f i e l d where it becomes n e c e s s a r y , f o r r e a s o n s o f m a i n t e n a n c e
o r r e p a i r , t o g a i n access t o t h e t u b e bundle. The s c a l l o p i n g o f s u p p o r t p l a t e s by
c u t t i n g w i t h a c u t t i n g wheel o r by b u r n i n g is a s i m p l e t a s k t h a t h a s been done suc-
c e s s f u l l y on many o c c a s i o n s . T h i s modification reduces t h e v e l o c i t y through t h e
s h e l l and m i n i m i z e s t h e d e s t r u c t i v e c o n d i t i o n s e x i s t i n g w i t h i n a s h e l l t h a t is t o o
s m a l l i n o r i g i n a l design. I n v e r t i c a l FWHs, t h i s m o d i f i c a t i o n s h o u l d b e compli-
mented w i t h t h e u s e o f dam s t r i p s on t h e s t e a m i n l e t s i d e o f t h e s u p p o r t p l a t e s t o
p r e v e n t c o n d e n s a t e t h a t a c c u m u l a t e s o n t h e s u p p o r t p l a t e s from c a s c a d i n g back i n t o
t h e vapor stream. Formulas e x i s t t o v e r i f y t h e c o r r e c t n e s s o f t h e EWH s h e l l dimen-
sion. The vendor s h o u l d be r e q u i r e d to d e m o n s t r a t e how h e u s e d t h e s e f o r m u l a s i n
e n s u r i n g p r o p e r geometry between t h e s h e l l and t h e t u b e b u n d l e .
* U n l e s s c l e a r l y r e q u i r e d t o d o s o i n t h e p r o c u r e m e n t p r o c e s s , some v e n d o r s a r e
s t i l l r e l u c t a n t t o a l l o w r e v i e w o f t h e i r p r o p r i e t a r y d e s i g n s and may n o t p r o v i d e
adequate drawings t o t h e u t i l i t y .
2.2.1.2 Tube Vibration In the Subcooling Zone. The subcooling zone has to be re-
cognized as a turbulent zone within a FWH. In a previous section, it was indicated
that an explosive condition may exist in the subcooling zone due to flashing. Pre-
vious comments regarding baffle spacing, tube pitch, and support plate configuration
that were made for the condensing zone are equally valid for the subcooling zone.
Consideration of unusual modes of operation, therefore, must be addressed at the
specification stage and, for existing equipment, has to be recognized during oper-
ation, preventive maintenance, and corrective maintenance activities. Pr~perprep-
aration of baffles at the cut line, where the tube is resting, to eliminate sharp
corners within the hole or half-hole has to be assured. Proper areas must be pro-
vided at the entrance and exit of the drains cooler and at baffle cuts so that ve-
locities are within reasonable ranges.
~t is also important to emphasize the proper assembly of the tube bundles both in
repair shops and new fabricating facilities to minimize vibration in the subcooling
zone as well as in the other zones. Errors made in the design or manufacture of the
shell and/or tube bundle that will cause flow restriction of steam or condensate
will increase velocities beyond design intention and this could bring about unac-
ceptable vibration.
s h e l l s o r d r i l l i n g 1/2-inch t o 1-inch h o l e s a t c e r t a i n l o c a t i o n s t o p e r m i t t h e i n -
t r o d u c t i o n of l i g h t s and b o r o s c o p e s i n t o t h e bundle a t t h e r e g i o n o f t u b e f a i l u r e .
There a r e v e r y good, f l e x i b l e b o r o s c o p e s on t h e m a r k e t today t h a t p e r m i t v i s u a l
e x a m i n a t i o n o f t h e damaged a r e a s a s w e l l a s t h e a b i l i t y t o t a k e p h o t o g r a p h s wherever
such i n s t r u m e n t s c a n r e a c h . However, i n some s t a t e s doing t h i s w i t h o u t having an
"R" stamp o r informing o n e ' s i n s u r a n c e u n d e r w r i t e r may v o i d t h e Sec. V I I I stamp on
the vessel. I t i s a d v i s e d t h a t r e s p o n s i b l e a g e n t and code r e p r e s e n t a t i v e s f i r s t b e
approached. I t i s u n f o r t u n a t e t h a t some u t i l i t i e s have n o t y e t a c q u i r e d t h e h a b i t
o f d e t e r m i n i n g t h e r e g i o n ( i - e . , l o c a t i o n and e l e v a t i o n ) and t h e c a u s e s o f f a i l u r e .
Without some i n v e s t i g a t i o n , a n a l y s i s , and judgment, i t is i m p o s s i b l e t o d e t e r m i n e
t h e m o d i f i c a t i o n s n e c e s s a r y t o t h e FWH o r t o o p e r a t i n g and maintenance p r o c e d u r e s .
A similar type of philosophy may also be followed when the shell sizing is such that
excessive velocities exist in the condensing zone. It is possible to provide an
additional bleed steam inlet on the shell side or to relocate a bleed steam inlet
such that the flow of steam travels equally in two directions, rather than in one
direction. These are all judgments that can be made very quickly with appropriate
inspection and analysis and can save a utility money while increasing plant per-
formance. HE1 Standards for Closed Feedwater Heaters, third edition, relates to
this matter in a limited fashion on pages 6 and 7. According to good design prac-
tice, the steam inlet should be located taking into account the thermal center line
such that good distribution is accomplished without creating excessive localized
velocities even when the nozzle entrance velocity criteria is being met. Depending
on shell size, it may be advisable to locate the inlet nozzle above the thermal
center in vertical installations. Problems can become acute when a utility decides
to replace a tube bundle that requires more surface due to a material change. In
trying to use an existing shell in such a case, the clearance between the tube bun-
dle and shell may become too tight, inviting vibration damage due to excessive steam
velocities.
The principal factors that increase the severity of tube-inlet erosion-corrosion are
high water turbulence, low pH, high 02, and relatively low temperature (less than
400°~). Section 5.0 of EPRI Report CS-1776, "Failure Cause Analysis - Feedwater
Heaters," provides additional explanations, a summary of key material in the lit-
erature, and the results of a recent industry survey that should be read as back-
ground for better understanding of this problem.
2.3.2 ~ e s i g nConsiderations
Material selection and other design considerations offer many opportunities to min-
imize the effects of erosion-corrosion. The susceptibility of various metals to
tube-inlet erosion is indicated in Table 2-3. Most susceptible to attack are the
carbon steels, followed by high copper alloys, monel, and stainless steel.
TUBE MATERIALS USED FOR FEEDWATER HEATERS AND OTHER HEAT EXCHANGERS
I N POWER PLANT APPLICATIONS
Leach-
General Inter- i n g or Erosion- Stress
Copper-Based Attack Crevice Pitting granular Parting Corrosion Corrosion
Arsenical Admiralty
Arsenical Copper
Copper-Nickel (90/10)
Copper-Nickel (80l20)
Copper-Nickel (70/3 0 )
Nickel-Based Alloys
N
I
MONEL 400 SB- 163 5 5 6 7 2 6 6
Ferrous Alloys
C a r b o n Steel
S t a i n l e s s Steel
T y p e 304
*SUSCEPTIBILITY LEDGER
Scale o f : 0 t o 10
Where: 0 = Immune
1 0 = E x t r e m e l y Susceptible
b o r o s c o p e i n s p e c t i o n o f t h e f i r s t 6 i n c h e s o f a random number o f f i r s t - p a s s t u b e s
s h o u l d a l s o b e made f o r e a r l y d e t e c t i o n o f e r o s i o n symptoms s u c h a s e x c e s s i v e m e t a l
p o l i s h i n g o r wear. I f e r o s i o n is d e t e c t e d , i t is w i s e t o i n s p e c t even f a r t h e r down
the tube (perhaps 10 inches or more) to be sure the damage does not extend farther
than was first apparent. One way to detect the failure of a tube-to-tubesheet weld
is by pressurizing the shell side with air to 15-30 pounds and utilizing a solution
of soap at the face of the tubesheet. Any bubbles appearing within the confines of
the tube inside diameter (ID) would indicate that the tube leaks. Any bubbles
showing distinctly around the tube weld itself are tube-to-tubesheet joint failures.
3. Every time a tube is plugged, the velocity through remaining tubes in-
creases. As more tubes need to be plugged, a running check should be
riade to be sure that excessive velocities do not cause rapid destruction.
Plan for realistic retubing or replacement, allowing proper lead times
for work to be done.
1. Install metal tube inserts of high erosion resistance in the inlet pass.
Explosive installation would be preferable, but mechanical expanding can
be done if conditions are ideal.
2. Add flow diffusers on the inlet pass to minimize turbulence in the tube
entrance area.
5. When a tube needs plugging, use extra care to assure that adjacent tubes
are not damaged in the process. use mechanical plugs where applicable
(low pressure only). Otherwise, thin thimble-type plugs could be used
and will require a minimum amount of heat concentration to properly weld
into place.
6. DO not safety plug tubes adjacent to the failed tube without checking for
actual need. Equipment is now available in the service industry to in-
dividually test each tube for soundness. If an adjacent tube has been
severely damaged due to secondary impingement from the failed tube, this
can be detected quickly by hydrostatic tube testing.
7. With the help of the plant's water chemist and/or an outside consultant,
determine a compatible water chemistry (especially pH and 02 control)
related to FWH tubes and the rest of the feedwater system. Anytime a
change is made to a water treatment system, a check of the tubing in all.
FWHs, heat exchangers, and condensers should be made to assure compatabil-
ity.
There are many problems and inadequacies in dealing with the metals used in FWHs,
and none is totally immune to corrosion. The nature and aggressiveness of the en-
vironment determines, to a large extent, the degree and the type of corrosion. It
is misleading to consider a power plant environment as benign. All of the following
major categories of corrosion have been experienced in feedwater systems:
Crevice corrosion;
Pitting;
Intergranular corrosion;
Erosion-corrosion; and
Stress corrosion.
2.4.1.1 uniform Corrosion Or General Attack. The uniform loss of the metal sur-
face is brought about by a chemical or electrochemical reaction. An average cor-
rosion rate can be established by measurement in mils per year, and the metal life
expectancy can be predicted. This form of corrosion is responsible for the great-
est destruction of metal by weight, but it is not as insidious as other types that
lack uniformity and predictability. General corrosion attacks are most evident in
c a r b o n s t e e l , b u t a l s o o c c u r t o a l e s s e r d e g r e e i n n o n - f e r r o u s m e t a l s and s t a i n l e s s
steel.
2.4.1.4 Pitting. T h i s u n i q u e t y p e o f a n o d i c r e a c t i o n is an a u t o c a t a l y t i c p r o c e s s
c o n t i n u o u s l y f e e d i n g i n its p r o d u c t . P i t t i n g i s one o f t h e most d e s t r u c t i v e and
i n s i d i o u s forms o f c o r r o s i o n a t t a c k . I t is e x t r e m e l y l o c a l i z e d and p r o d u c e s des-
t r u c t i o n o f m e t a l by p i e r c i n g . Most p i t s d e v e l o p and grow downward from h o r i z o n t a l
s u r f a c e s i n t h e d i r e c t i o n of g r a v i t y . Fewer p i t s d e v e l o p on v e r t i c a l s u r f a c e s and
o n l y r a r e l y d o p i t s grow upward, o p p o s i t e g r a v i t y . Similar t o crevice corrosion
a t t a c k , p i t t i n g r e q u i r e s a long i n c u b a t i o n p e r i o d t o d e v e l o p , b u t once s t a r t e d , t h e
pit penetrates the metal at an ever-increasing rate. Low fluid velocities and/or
stagnation are associated with pits. Stainless steel alloys ate more susceptible to
pitting corrosion than are other metals.
2.4.1.6 Selective Leaching Or Parting. The removal of one element from a solid
alloy by the process of corrosion is known as selective leaching or parting. The
two best known examples of selective leaching are dezincification and graphitiza-
tion. The first describes a process by which selective removal of zinc takes place
in brass alloys. The affected alloy can be readily detected by the red or copper
color in contrast to the original yellow color and by its brittleness and porosity.
Graphitization is selective leaching of the iron or steel matrix in cast iron leav-
ing the graphite network. The cast iron appears to become graphitized, as it has
the appearance of graphite and can be cut easily with a pen knife. Another example
is the leaching of nickel from 70/30 copper-nickel tubing. One utility reports that
layers of almost pure copper were found as thick as -010 inches on tube exteriors
and .002 inches to -004 inches on tube interiors.
Vital to the control of the environment is the effectiveness of the water treatment.
The all-volatile treatment, also known as "zero solids," is a method of boiler water
treatment that entails the use of ammonia and/or hydrazine for pH conditioning and
dissolved oxygen scavenging. This method is used widely in the industry. Complete
reaction of hydrazine with oxygen produces nitrogen and water. As a byproduct of
this reaction, ammonium hydroxide is formed. Residuals of oxygen, ammonia, and
acid-forming gas such as C02 can also concentrate in certain zones of the system or
exchanger. The resulting environment is potentially hazardous to all
copper, copper-nickel, and nickel-copper alloys.
It is important to recognize that the chemistry of the water can vary considerably
throughout the feedwater system, For this reason the system should be monitored and
adjusted by chemical treatment at multiple points to ensure key components are not
,exposed to unhealthy conditions. A recent survey in one plant showed variations in
p~ from 7.2 to 10.4 at different points in the feedwater system.
Lack of monitoring of these control limits to ensure that they remain in the design
range will, with t h e , result in tube failures of one kind or another. For in-
stance, if there were an ammonia attack, which starts the exfoliation deterioration
of the outside surfaces of copper and nickel tubing, such a failure may first be
indicated by difficulty in maintaining a stable liquid level even under steady load
operation. Upon inspection, it may be seen that the entrance to the drains cooling
zone may be severely blocked by deposits on the tubes as shown in Figure 2-19.
Failure of copper-nickel tubes by exfoliation may not be detected immediately but
will be quite apparent with time as shown in Figure 2-20. This condition might
well be aggravated by poor venting practices that allow a concentration of gases or
Table 2-4
Primary Condensate
Economizer Inlet
Boiler Water
mmhos --
mmhos Max. 3.5
PPm Max. 0.25
8.5 - 9.0
PPm Zero
Make-Up (Externally
Treated Supply)
*Note: These are not recommended limits; they are examples for illustrative pur-
poses only.
-- - --- .Limits
Control -. Deslred Range
Primary
--. --
.
Condensate
Before Treatment
Silica
pH
Conductivity Bef. Exch. mmhos
Conductivity Aft. Exch. mmhos
After Treatment
pH
Ammon ia
Hydrazine
Deaerator Out=
Oxygen
Economizer Inlet
Boiler Water
Saturated Steam
Silica Max. 2 5 . 0 ~
Ammonia Max. 0.4
Make-Up (Externally
Treated Supplyl
*Note: These are lot recommended limits; they are examples for illustrative
purposes only.
2-57
ammonia in selected zones. An inspection of the vent system and the position of
the valves and the orifices may indicate if problems can be expected in this region.
Ensure that proper chemistry limits are established, monitored, and main-
tained ;
.
Inspect for signs of corrosion problems as indicated above; and
2-58
The above actions must be carefully tailored to the individual plant and may re-
quire expert assistance from feedwater system corrosion experts as well as from
vendor representatives. Two specific areas that are often neglected need special
emphasis here because recent field experience shows that many utilities are neg-
lecting them without full appreciation of the corrosion damage likely to result in
their FWHs. They are the blanketing and venting of FWHs to prevent corrosion from
oxygen and non-condensibles that promote corrosive attack. The areas are addressed
in the following two subsections.
The manufacturer's instruction book provided with each FWH should include specific
instructions on blanketing when needed. The utility should ensure that such
2-59
instructions are available to the operators and are specifically applicable to the
FWH(s) in question. If such guidance is lacking, it should be obtained from the
vendor and from other feedwater systems' chemistry experts as necessary. Once the
necessary blanketing needs are known, they should be clearly promulgated in the
operating instructions and meticulously followed despite the inconvenience during
short outages. This point has been emphasized here because a recent survey of op-
erating coal plants revealed that many operators are aware of the blanketing re-
quirements for their EWHs but consider them optional, rather than mandatory. A
typical comment was to the effect that "our procedures call for nitrogen blanketing
but usually we are too busy in short outages." This observation suggests that man-
agement should be more involved in these plants. If operating requirements are
unreasonable, they should be reviewed and improved. Until they are properly
changed, the requirements should be mandatory and should be followed at all times.
The importance of venting the shell side cannot be overemphasized. On the shell
side, non-condensibles of the various kinds (e.g., oxygen, ammonia) can signifi-
cantly reduce the heat transfer rate as well as contribute to corrosion attack of
tubes and supports. Even stainless steel is not immune to corrosion attack if
chlorides are present with the oxygen. According to most manufacturers and the HE1
standard for closed FWHs, it is necessary that all FWHs be vented continuously
through the vent connections provided. Minimum provisions should be made for vent-
ing 1/2 of 1% of the vapor entering the shell.
A proper venting system should be set up starting with the venting internals in the
FWH shell. It is strongly recommended that internal air manifolds or channels be
provided for all types of FWHs. Such internal full-length manifolds or channels of
various types are usually provided by the manufacturer; however, if they are not,
they should be requested by the users. Providing a venting system connected to the
air manifolds will assure that the venting of the FWH shell can be accomplished in
a reasonably short period of time.
There are basically two types of vents: the startup vents and the continuous vents.
Sometimes vents serve a dual purpose and are so identified in the drawings as
"startup and continuous vents." Startup vents purge the shell of all air and non-
condensibles during the initial phase of the cycle. During plant startup, venting
to the atmosphere is satisfactory when FWHs are operated above atmospheric pressures
at all loads as long as the proper sonic conditions can be developed across the
orifice. If the FWHs are not operated above atmospheric pressure, the startup
vents should be connected to lower-pressure equipment in the system (surface con-
densers or deaerators) that is capable of removing non-condensible gases. Acces-
sible valves should be provided in the lines to close these vents after startup.
As a general rule, vents should not be cascaded to other FWHs because doing so may
lead to the accumulation of harmful gasses that will cause severe corrosion to FWH
internals. This recommendation is made by HE1 (Standards for Closed Feedwater
Heaters, 3rd edition, p. 8.) and is supported by the experience of seasoned main-
tenance managers and FWH specialists who have witnessed severe damage to FWH trains
with cascaded vents. However, one large utility reports successful experience with
cascaded vents and advises that they can be used (with some thermal benefits) if
careful attention is paid to the following points.
Ensure that the vent system is designed to vent 1/2 of 1% of the entering
steam plus 100% of the mass of any cascaded vents through an orifice that
has been properly calibrated for this purpose.
Use venting designs that vent the full length of the tube bundle.
Continuous vents are provided for the purpose of withdrawing non-condensible gases
from the shell space during operation. As mentioned above, it is usually necessary
that these vent lines be individually connected to the steam surface condenser or
the deaerator (rather than cascaded to lower-stage FWHs). It is suggested that
continuous vent lines be open at startup along with the startup vents so that vent-
ing of the shell space can take place quickly. Continuous vent lines should be
provided with orifices to limit and control the amount of steam vented together
with the non-condensibles to the lower-pressure deaerator or steam surface
condenser. These orifices should be located outside the FWH; however, some manu-
facturers provide internal orifices that are located within the FWH shell. Such a
design will lead to problems that are very difficult to trace, should the orifices
become plugged or damaged. It is a mistake to accept such a design that cannot be
properly inspected and maintained through the intended life of the FWH.
F\w Shell 1
-isolation Valves* 1 I I
-
I I ___)
To Deaerator
Or Condenser
/
Vent Line
Startup Bypass Valve
(Locpted Near Second
Tee To Provide Crud
Collection Leg Up-
'/ stream of Valve)
Figure 2-22. A Continuous Vent Orifice With Startup Bypass Valve. (*Isolation
valves permit inspection and maintenance during system operation. This section
of line should be higher than the bypass valve line to avoid water seal or crud
trap. )
other particles during startup because such heavy particles will tend to follow a
straight-line path even with the bypass valve open.
For proper operation of equipment, it is important that all vent lines be as free
of bends and restrictions as possible. Sharp bends and low spots without traps add
to the possibility of foreign materials getting lodged in the line and restricting
flow.
It is important to make sure that the vent lines are, in fact, connected and that
they are properly utilized during operation. At a Northeast utility, a FWH that
had a severe case of exfoliation was returned to the shop. upon examination, it
was discovered that all vents were still plugged as originally shipped to the util-
ity. The vents were never functional, resulting in the failure of the FWH in a
short period of time.
The point of admission and method of admission of chemicals for water treatment must
also be looked at as possible problems, should the concentrations become heavier at
one point in a cycle as compared to another. This would be of special concern if
chemical additives are being admitted in a batch-type fashion, rather than at a
continuous rate (varied or fixed). ~f it is absolutely necessary for high concen-
trations of any additive to be present in any specific localized area, be sure that
it is compatible with the materials it will be contacting. In making a tube selec-
tion for a FWH (whether it is a replacement or a new unit), all of these factors
need to be taken into account; if they are not, the likelihood of encountering cor-
rosion damage may be unacceptably high.
Many problems in the older plants today relate to the fact that a water treatment
system was changed from a phosphate to an all-volatile treatment system without
proper consideration of the potential damage that could be done to the existing tube
materials in the condensers and the EWHs. If it was absolutely necessary to change
to a system that added significant amounts of ammonia, the water chemists and the
plant engineers should have considered all aspects of the change carefully. At a
minimum, it would have been appropriate to investigate methods of venting the FWHs
and condensers and to develop some means of protective lay-up of this equipment
during plant outages. Whenever the moist surface (internal or external) of a tube
is given an opportunity to dry in an atmosphere where existing contaminants will
first dissolve in that moisture and then dry out as some corrosive salt, the plant
is inviting problems.
About the same time that many plants changed their water chemistry, they also began
to operate on a cycling system, rather than the full load for which the unit was
designed. When a plant is started up several times a month, as compared to once a
year, the operators have a strong tendency to neglect their start-up vents. The
resultant buildup of non-condensibles adds further to the problem of corrosion with-
in the system. The point here is to understand that as the operating characteris-
tics of a plant change, the designed chemistry control limits and procedures may
become inadequate. Therefore, it is critical that the system be completely re-
viewed. In this case, evaluating the chemistry effects on the boiler and turbine
alone is not enough; the steam, condensate, and feedwater sub-systems must be con-
sidered as integral, coordinated parts of the overall system.
Having experienced the problems outlined above, some power plant engineers are be-
ginning to consider sophisticated and expensive materials such as Inconel and In-
coloy 400. It is possible that such expense may not be necessary in many cases if a
change in operating procedure were considered that might allow some less costly
material to be used.
One of the materials that is gaining more acceptability because of its higher re-
sistance to stress corrosion problems and good resistance to erosion is type 439
stainless steel. Recent experience suggests that this material is economical for LP
E'WHs. In addition, it appears suitable for replacing carbon steel and copper alloy
tubes in LP FWHs without requiring excessive increases in shell diameters or FWH
lengths. It has also been utilized in some HP EWHs; however, there is inadequate
long-term performance data available to make further comment at this time.
4. Dry steam leaves the desuperheater zone and enters the moist condensing
zone at excessive velocities;
The damaging results of steam impingement action are shown dramatically in the
following photographs:
Figures 2-23 and 2-24: Tube destruction from steam impingement at the de-
superheater exit of a three-zone FWH.
Figure 2 - 2 6 : Impingement erosion of the shell itself with some erosion pits
penetrating 50% of a 5/8-inch shell. (Complete shell penetration has occurred
in some other cases similar to this one.)
Figure 2-27: A HP FWH shell that has been cut to gain access to a fallen
impact plate. The plate was quite small and was improperly welded in the
desuperheating zone.
Figure 2-28: Impingement damage to the tubes that were exposed after the
impact plate in the figure became dislodged.
Actual experience has shown that most impingement problems are discovered only
after a tube or tubes have failed and water level control becomes very difficult or
impossible. Visual inspection for location of tube failure will then verify that
it is in an area where an impact plate should be or in an area of possible high
velocity.
Some utilities have begun a practice of checking all or most of their FWH tubes by
eddy-current testing at each annual outage. In this way, a wear pattern can be
detected from year to year. Direct impingement, however, can cause problems very
quickly, in which case loss of water level control will probably be the first sign
of a problem. Another means of checking for excessive thinning of tube walls is to
conduct hydrostatic pressure tests on individual tubes during the first general
Relative to the design of impact plates, HEI1s Standard For Closed Feedwater Heaters
refers to 45O impingement as a minimum standard. The purchaser must-be certain
that he clearly identifies his concern on this matter, recognizing that some ex-
perienced engineers prefer a wider angle of impingement protection. Furthermore,
the user must identify the normal maximum flow rates for steam and drains inlets
and also any overload conditions that could take place due to variations in op-
erating modes.
Although many p e r s o n s t o d a y r e c o g n i z e t h a t t h e n o z z l e s s h o u l d b e s i z e d f o r an o v e r -
load condition, it is r a r e f o r a u s e r t o i n d i c a t e t h a t t h e d e s i g n o f t h e i n t e r n a l
flow p a s s a g e s and t h e impact p l a t e s h o u l d a l s o t a k e t h e s e o v e r l o a d c o n d i t i o n s i n t o
account. One d o e s n o t s o l v e a problem by making a n o z z l e l a r g e r and t h e n having a
r e s t r i c t e d a r e a between t h e impingement p l a t e and s h e l l ID, e t c . , once t h e f l o w
enters the shell.
p a c t p l a t e w i l l b e i n s t a l l e d i n t h e c l o s e d FWH t o a s s u r e t h a t t h i s p l a t e w i l l n o t
dislodge i t s e l f a f t e r a s h o r t period of operation. V a r i o u s FWHs have d i f f e r e n t
d e s i g n s o f impact p l a t e s ; t h e m o s t rugged would i n c l u d e a s t r e n g t h weld t o a t l e a s t
o n e , b u t p r e f e r a b l y two, s u p p o r t p l a t e s o r s u p p o r t b a r s . Tack welding o r minimal
f i l l e t weld d e s i g n s s h o u l d be a v o i d e d . Damage w i l l o c c u r soon a f t e r a p l a t e i s
dislodged. I£ t h i s happens w i t h i n f i v e y e a r s o f s t a r t - u p , equipment l i f e w i l l be
severely shortened. Steam impingement d i r e c t l y on t h e t u b e s w i l l c r e a t e damage,
and s i g n i f i c a n t amounts o f s u r f a c e c a n b e l o s t from t h i s f a i l u r e i n a s h o r t t i m e .
y e a r s (and o n e t h a t c a n b e s o l v e d o n l y by p r o p e r q u a l i t y c o n t r o l d u r i n g manufac-
t u r e ) is t h a t of l e a v i n g an impact p l a t e o u t of t h e FWH; damage t h e n o c c u r s w i t h i n
weeks a f t e r t h e p l a n t s t a r t s up. Sometimes t h i s happens when a n e n g i n e e r f o r t h e
u t i l i t y changes t h e l o c a t i o n o f a nozzle o r adds a nozzle l a t e i n t h e design s t a g e ,
such t h a t a m a n u f a c t u r e r may r e l o c a t e t h e n o z z l e on t h e s h e l l , b u t t h e d e t a i l s of
t h e i n t e r n a l components d o n o t g e t t h e p r o p e r a t t e n t i o n and a c o n n e c t i o n f o r steam
o r d r a i n s a d m i s s i o n is p u t on a s h e l l w i t h o u t p r e l o c a t i n g t h e impact p l a t e t o pro-
tect t h e t u b e s . I t is n e c e s s a r y t o e n s u r e p r o p e r c o o r d i n a t i o n and i n s p e c t i o n t o
p r e v e n t t h i s t y p e of f a i l u r e .
I n v e r t i c a l FWHs i f c o n d e n s a t e l e a k s i n t o t h e d e s u p e r h e a t i n q zone it w i l l be p i c k e d
u p by t h e r i s i n g s t e a m and c a r r i e d w i t h damaging f o r c e a g a i n s t t h e F W H ' s i n t e r n a l s .
To a v o i d t h i s problem o n e u t i l i t y i n s i s t s upon f u l l p e n e t r a t i o n welds f o r t h e de-
s u p e r h e a t i n g zone p l a t i n g and f o r t h e i n l e t steam p e n e t r a t i o n j o i n t s . After fabri-
c a t i o n , t h e j o i n t s a r e w a t e r t e s t e d i n t h e shop t o e n s u r e t h a t t h e y d o n o t l e a k .
. Insist that the vendor show how these clearances have been determined
adequate for. abnormal as well as normal conditions;
.
of tubes in that area indicate excessive polishing; and
TOO often, the apparent savings expected from keeping the existing shell are more
than offset by future problems when the tube bundle-to-shell relationship is too
tight. When these problems show up after the FWH warranty runs out, the frustra-
tions become even worse.
The principal reference here is EPXI Report CS-1776, "Failure Cause Analysis - Feed-
water Heaters," which has already been distributed by EPRI to the utilities. Sec-
tion 8.0 and Appendix D of that report are devoted to tube-plugging techniques and
problems and should be studied carefully by utility personnel who are responsible
for improvements in this area. (Excerpts from EPRI Report CS-1776 have been used in
the following subsections where they are applicable to the scope of this guide.)
2.6.2.3 Welded Plug. The use of welded plugs (shaped to allow expansion), when
carefully welded at the edge to sound, clean base metal, has resulted in trouble-
free repairs. However, welded plugs or clusters of plugs that formed massive, rigid
welded areas have often developed peripheral weld or ligament cracks. The hollow
"thimblew-shaped welded plug is fabored by some experts because of its ability to
withstand many cycles of thermal expansion and contraction without cracking.
2.6.2.5 Seal Plug. Plugs having various types of packing or seal material have
been used for years for plugging condenser tubes and LP and IP FWH tubes. Although
some of these plugs have performed satisfactorily for long periods (several years),
this technique is more often considered a temporary repair to be followed by per-
manent plugging when more time and proper conditions are available, However, with
the latest technological advances in this field, seal plugs capable of withstanding
up to 5,000 psig and 600°~ have been used successfully in HP FWHs. Their use as
permanent plugs when tubesheet ligaments are deteriorated is worthy of serious
consideration.
The desire to minimize the downtime of a baseloaded plant is commendable, but rush-
ing the maintenance actions to the extent that there is inadequate time for proper
troubleshooting, analysis, and repair is false economy. Not only will the repair be
of marginal reliability, but the causes of the initial tube leaks will probably
remain obscured until it is too late to save the FWH. The result is usually a story
of repeated failures, temporary fixes, no clear diagnosis, and finally urgent re-
placement of a FWH that might have had a reasonable life with proper maintenance
actions.
. use rapid, temporary plugging measures only when there is sound justifi-
cation (e.g., to keep a FWH operational for a few more days before a
scheduled outage). Such a decision may be reasonable if it is based on a
sound understanding of the FWH and its apparent problems and if the prop-
er troubleshooting, diagnosis, and repair follow in a well-planned
manner.
Before the "permanent" repairs are attempted, ensure that the location
of the leak(s) is determined and documented. An air test of the shell
side to 15-30 psi will permit a good soap test of the tubes and tubesheet.
Bubbles on the tube ID indicate a tube leak, whereas bubbles between the
tube and the ligament indicate a leakage path around the tube, through
the tubesheet. The approach to plugging will, of course, be different
depending upon these determinations,
Be sure to determine (and document) the location of the leak along the
length of the tube as well as which leg (of a U-tube). This information
is essential for analyzing the probable cause(s) of the tube leaks. Var-
ious types of tube-leak location detectors are available on the market
today. An alternative method used by some utilities on vertical FWHs is
to rig a length of transparent plastic tubing up along the outside of the
shell and connect its lower end to a shellside fitting. Then the shell
can be vented and filled with water until leakage is observed through the
faulty tube. ~f the water filling is stopped at that point, the level in
the tubing will stabilize at the same level as the leak in the tube.
Careful measurement of this point will document the distance of the leak
along the tube length.
Compare the visual evidence of tube and tubesheet conditions with the
construction details of the FWH before selecting the details of the opti-
mum repair technique. The engineer should have the following types of
information on hand (as a minimum) for these considerations: the nature
of the tube-to-tubesheet joint (expanded? rolled? explosion welded? to
what extent? tube diameter at various depths in the tubesheet? metals
used in tube, tubesheet, and cladding?); conditions of the tubesheet
Ligaments; geometry of tube rolling (Does tube rollover interfere with
plugging? ~f so, the rollover will have to be reamed).
2.6.3.2 Lack Of Good Procedures. isc cuss ions with numerous utility personnel have
shown that there is a widespread lack of confidence in the tube-plugging procedures
available to the utilities. In many cases, the plugging procedures recommended by
the FWH vendor at the time the FWH was purchased have proven inadequate or imprac-
tical for application in the plant environment. Tube plugging is a rapidly devel-
oping art. Many promising techniques are available today that were not in ex-
istence (or were untried) when FWHs and their manuals were purchased 10 years ago.
Accordingly, periodic review and updating of plugging procedures is necessary.
Practical recommendations to obtain and follow sound plugging procedures are:
When convinced that the optimum procedures have been determined, be sure
they are formally promulgated for use without deviation. If deviations
become necessary, require formal approvals. Change the written procedure
if necessary to improve it, but do not tolerate sloppy adherence or per-
sonal variations from the specified "optimumw procedures.
~ecognizing that the vendor will probably adopt newer and better plugging
techniques in the future, it would be wise to commit him, at purchase, to
furnish any improved procedures applicable to the new FWH whenever they
may be identified throughout its life.
2.6.3.7 Poor Design: Lack Of Access. Many maintenance personnel have reported
serious concern about the FWH designs that provide poor access for maintenance.
Some were adamant that access to their hemispherical head configurations was so bad
as to be unsafe for carrying out prescribed welding procedures. One company re-
ported a policy change whereby all FWHs procured in the future would have full
access to the tubesheet areas, and the hemispherical head configuration would no
longer be used. Apparently other utilities have been reluctant to spend more money
f o r s u c h improved a c c e s s . O t h e r s b e l i e v e t h a t t h e h e m i s p h e r i c a l head geometry c a n
be a d e q u a t e on l a r g e FWHs i f a t t e n t i o n is p a i d t o t h i s c o n c e r n d u r i n g FWH d e s i g n by
r e q u i r i n g manways o f a d e q u a t e s i z e . ( S e e s e c t i o n 2 . 7 . 3 f o r examples o f improved
a c c e s s f o r maintenance.)
r a r e l y have i n f o r m a t i o n on t h e c o n d i t i o n o f t h e s u r r o u n d i n g t u b e s a n d , t h e r e f o r e ,
may d e c i d e t o p l u g them a s an i n s u r a n c e measure a g a i n s t t h e i r f a i l u r e soon a f t e r
r e t u r n i n g t h e FWH t o s e r v i c e . Many good t u b e s have been plugged u n n e c e s s a r i l y f o r
t h i s reason. I n a d d i t i o n , e x p e r i e n c e h a s shown t h a t i n s u r a n c e p l u g g i n g must be
a c c o m p l i s h e d c a r e f u l l y t o a v o i d a d d i t i o n a l weld f a i l u r e s from t h e e x p a n s i o n and
c o n t r a c t i o n o f weld r e p a i r a r e a s . To a v o i d u n n e c e s s a r y i n s u r a n c e p l u g g i n g , some
u t i l i t i e s have a d o p t e d t h e t e c h n i q u e o f h y d r o s t a t i c t e s t i n g o f s u s p e c t t u b e s . Only
t h o s e t h a t f a i l ( l e a k ) a t 1 . 5 t i m e s t h e i r r a t e d p r e s s u r e a r e plugged. S p e c i a l test
k i t s are c o m m e r c i a l l y a v a i l a b l e t o f a c i l i t a t e t h i s t y p e o f p r e s s u r e t e s t i n g .
2.6.3.9 L a t e D e t e c t i o n Of Leaks
When a t u b e f a i l s , t h e h i g h - p r e s s u r e feedwater escapes i n a very high-velocity stream
t h a t impinges on t h e FWH i n t e r n a l s i n c l u d i n g o t h e r t u b e s . Q u i t e o f t e n , 5-10 s u r -
r o u n d i n g t u b e s a r e d e s t r o y e d o r damaged b e f o r e t h e problem i s d e t e c t e d and t h e FWH
is i s o l a t e d . T h i s problem i s o b v i o u s l y most a c u t e i n t h e HP FWHs. Much less t u b e
p l u g g i n g would be r e q u i r e d i f t h e u t i l i t y had a r a p i d means o f d e t e c t i n g t h e i n i t i a l
tube leak. Very few u t i l i t i e s i n t h e U.S. have s u c h a c a p a b i l i t y on t h e i r FWHs,
a l t h o u g h some have i n s t a l l e d a c o u s t i c s y s t e m s t o d e t e c t l o o s e p a r t s and t u b e l e a k s
i n boilers. I n most U . S . p l a n t s , t h e f i r s t i n d i c a t i o n o f FWH t u b e f a i l u r e s is
e i t h e r (1) loss of w a t e r i n v e n t o r y o r ( 2 ) a n a b n o r m a l l y h i g h , u n s t a b l e w a t e r l e v e l
i n t h e FWH.
Neither EPRI nor the study team for this project is in a position to endorse this,
particular system as the best for leak-detection purposes. However, the acoustic
principle is sound, and there is no reason that this type of instrumentation cannot
be designed for simple and reliable use in the manner indicated. The cost of such a
system should be reasonable and well worth the investment, especially for H P FWHs on
baseloaded plants. (Refer to Section 4 . 0 for typical examples of the high cost of
E'WH outages on baseloaded plants. )
2.7 MISCELLANEOUS
2.7.1 The Tubesheet/Channel-Barrel Transition Radius
A design problem common to many FWHs presently in service is that the corner radius
in the forging of the tubesheet face to the channel-barrel transition is too small.
Cracks that originate in this area can result in the catastrophic failure of the
entire forging as shown in Figure 2-31.
Figure 2-32 shows data from tests that were performed in the 1960s on model tube-
sheet forgings to determine the influence of the corner radius and the intensity of
stresses in that region as a result of small radii in high-pressure closures. It is
readily seen that the smaller the corner radius in the forging, the higher the
stresses are with increased operating and test pressure. This phenomenon of high,
concentrated stresses on high-pressure forgings is a very serious defect in many
FWBs. Manufacturers attempt to provide the most economical closure (i.e., the thin-
nest) and in so doing consider the smallest possible ID, thus aggravating the prob-
lem.
I
I
I
I
I
NOISE LEVEL
100
AT P R E S S U R I Z A T I O N
1
TIME (HOURS)
TP - 6,000 psi
TP - 5,000 psi
TP - 4,000 psi
TP - 3,000 psi
TP - 2,000 psi
TP - 1,000 psi
I£ the guidelines for a minimum radius and the Charpy ttVt' notch test requirements
are met, then the possibility of catastrophic and dangerous faiLure of the forging
should not be a problem.
2-89
Figure 2-34. Bolted Partition Plate
a good maintenance and repair approach. The utilization of davits such that the
manhole cover can be removed quickly and efficiently without great effort is an
added feature.
Section 3
If a FWH (or group of FWHs) is bypassed, the feedwater will enter the next stage
FWH at a colder temperature, and that FWH will extract additional steam. Over-
loading up to 300% has been experienced. Large steam flows and the resulting high
drains flows can do catastrophic damage to the FWH from flashing, tube vibration,
*"Satisfactory operation" as used here means that the FWH should have the capacity
of passing the abnormal flows without damage to the equipment for the duration
of the abnormal condition.
**One major utility is now purchasing a large number of replacement FWHs and is
requiring that each one be capable of carrying the overload caused by isolation
of the next upstream (lower-pressure) FWH.
erosion, etc. To avoid this damage, the changes in flow that will be needed to
ensure proper velocities and reasonable pressure drops through all zones of the
remaining FWHs must be carefully analyzed. At the same time, it is important to
remember that turbines and boilers must also be considered. The turbine is affect-
ed when some EWHs are not operational, since steam will not be extracted from all
the design points, thus creating an imbalance in the turbine. However, recommenda-
tions for reduction of load with any and all combinations of FWHs out of service
can and should be obtained from the turbine manufacturer to remedy this situation.
Restrictions are present also in the boiler. If the temperature of the feedwater
at the economizer inlet drops too low, the economizer might suffer thermal shock or
the boiler could be fired too hard, creating problems in the superheating tubes and
in the boiler wall tubes also. Again, the boiler manufacturer should supply infor-
mation stating the minimum feedwater temperature that can be tolerated by the
boiler, and any other limitations which may apply. Figure 3-1 is an example of the
reply received by one utility upon making such a request. The specific boiler in
question was designed to receive feedwater at 530% at 100% power. The vendor
recommended a minimum feedwater temperature of 350°~ to avoid thermal shock to the
economizer. To prevent damage to the superheat tubes, it was also recommended that
during periods of reduced feedwater temperature, the boiler should be operated at
or below the appropriate line on the graph. For example, if feedwater temperature
was reduced to 4 2 3 O ~ ,and it was desired to fire the boiler at 708, it would be
necessary to accept a decrease in superheat of 60% below the designed value. Con-
versely, with a 6 0 O ~reduction in superheat, the boiler should not be fired above
70%. Thus, it is apparent that communication between utility engineers and vendors
is essential in prolonging the service life of not only the FWHs but also the other
major components in the system.
Having acquired the turbine limits for flow, the next step was to analyze the limi-
tations of the FWHs themselves. Helpful in this effort was information concerning
the operating history of each FWH. Information such as the age of the FWH, tube
material, condition of the tubes and FWH components, when it will be replaced, the
number of tubes plugged, and performance test data (terminal temperature difference,
and approach temperatures) is invaluable when evaluating FWHs, for their ability to
handle load. In Case 1, the utility engineer was aware that FWHs 57B and 58B had
already deteriorated due to erosion at the inlet end and pitting with as much as a
50% wall reduction in many tubes. This condition required additional load re-
strictions. He then went through an iterative process to derive what those limits
should be. Assuming a flow of 2,200,000 lb/hr to the boiler to be acceptable, this
flow was split evenly between the two strings of FWHs. By the time the feedwater
exited from the LP FWHs, it had attained a temperature of 3 8 4 O ~at a shell side
pressure of 200 psia. As before, half of the flow (1,100,000 lbs/hr) continued on
to the inlet of the B string HP FWHs; however, the remaining flow was directed
through a bypass line because HP FWHs 57A and 58A were inoperative. Because of the
aforementioned deteriorated tube condition of HP FWHs 57B and 58B, a judgment was
made to limit the velocity through the FWH to 6 feet per second (ft/sec.). This
measure would prolong the life of the tubes. Since each HP FWH had a different
number of tubes plugged, they had to be individually analyzed. From flow calcu-
lations performed on FWH 57B, it was determined that the maximum flow that could be
allowed through the tubes and still maintain a velocity of 6 ft/sec was 500,000
lbs/hr.* Therefore, provisions were made to bypass the remaining 600,000 lb/hr
through an internal orifice made in the partition plate on the channel that was
sized by using a standard equation. The purpose of the orifice was to divert some
of the water from the tubes and to provide an opportunity for mixing the water at
the outlet of the FWH. In this way, the amount of overloading on a FWH can be
*By reducing the feedwater flow, the steam quantity extracted on the shell side
was also limited. Reducing steam quantities automatically reduces the velocities
in the desuperheating and subcooling zones, which also prolongs FWH life.
limited, thus prolonging its life. Similar calcuations were performed for FWH 5 8 B ,
which showed that only 450,000 lbs/hr needed to be bypassed through an internal
orifice.
By limiting the efficiency of the FWH strings, which must be done to preserve the
life of the FWKis, it is important to consider what the effects will be on the
boiler. As can be seen in Figure 3-2, the temperature at the economizer inlet was
4 2 7 O ~ ,whereas the normal inlet temperature at 1008 load was 530°~. Correspondence
with the boiler manufacturer indicated that 320°~ was the minimum temperature that
should enter the boiler; therefore, the boiler did not place any restrictions in
this case. However, from the graph shown in Figure 3-1, which was supplied by the
boiler manufacturer, it can be seen that at 4 2 7 O ~and 100% load, there is approxi-
mately a 110°~ loss of superheat. This information must be relayed to the turbine
manufacture, who will determine if the loss will be detrimental to the turbine.
For Case 1, this did not present a problem; therefore, the 15% load restriction was
imposed to prevent further deterioration of the FWHs.
From Figure 3-2, one could determine the megawatt net generated with the calculated
parameters, which in this case was 275 MW. Therefore, generating 275 MW with two
HP FWHs removed from service should not further degrade the equipment.
Case 2 (Figure 3-3) presents the dramatic example of all of the LP FWHs from both
strings being removed from service. In many utilities, this situation becomes a
fairly high probability when the ability to bypass individual FWHs or a pair of
FWNs is non-existent. One LP FWH that needs to be repaired can force the removal
of a11 the LP FWHs in that string from service.
Case 2 (Figure 3-3) was handled in the same manner as Case 1. The turbine manu-
facturer indicated that for this condition there was no need to limit feedwater
flow; therefore, the plant engineers analyzed the FWHs themselves. It was readily
apparent that even healthy HP FWHs would not be adequate to handle the increased
load. Again, these FWHs were already deteriorated to the extent that internal ori
fices were installed to bypass some of the flow. Having already dealt with Case 1
as well as a variety of other cases of degraded operation enabled the support en-
gineer to quickly estimate the overall reduction in feedwater flows that would be
necessary to permit safe operation of the remaining FWHs. To verify that these
estimates were correct, he performed the calculations already outlined in the pre-
vious example to ultimately arrive at an economizer inlet temperature of 3 8 8 O ~and
a flow that was throttled to 1,400,000 lbs/hr. For this set of parameters, the
boiler does not impose a reduction in load, although there will be a corresponding
loss of superheat of approximately 1 4 0 ~ ~ .
A consultation with the turbine manu-
facturer resulted in the determination that the loss of superheat at that rate of
steam flow did not necessitate a turbine restriction. Again, it is emphasized that
if limitations were not imposed on the operation of the HP FWHs, they would have
quickly deteriorated, condemning the plant to a forced outage. Serious damage to
the boiler would have been the result of operation without any FWHs. Many boiler
failures can be ascribed to operation in this manner.
The use of the above examples is not intended to be a blanket endorsement of the
use of internal orifices to limit flow through degraded FWHs. In the case cited,
this particular solution was implemented after careful analysis as a temporary
improvement to a bad situation. If a FWH has individual feedwater by-pass valves,
it would normally be better to use them, in which case orifices should not be needed.
These cases vividly illustrate the type of limiting operational guidelines dictated
by the removal of FWHs from service. By considering the protection of the turbine,
boiler, and E%HS simultaneously, it is possible to attain the highest reasonable
power output without destroying the plant in the process.
Section 4
4.1 OVERVIEW
I t h a s been common p r a c t i c e f o r some u t i l i t i e s t o f o l l o w t h e "10% r u l e " f o r d e t e r -
mining when t o r e p l a c e a f e e d w a t e r h e a t e r (FWH): when t h e number o f plugged t u b e s
r e a c h e s 10% of t h e t o t a l , t h e EWH is r e p l a c e d . * However, e x p e r i e n c e h a s shown t h a t
such a s i m p l e c r i t e r i o n is i n a d e q u a t e f o r making p r u d e n t , economical d e c i s i o n s on
whether t o r e p l a c e o r t o c o n t i n u e to r e p a i r FWHs. I n S e c t i o n 2.5 and F i g u r e 2-28,
a n example is g i v e n of a c a t a s t r o p h i c t u b e f a i l u r e caused by a l o o s e impact p l a t e
t h a t r u p t u r e d more t h a n 10% o f t h e t u b e s . Once t h e c a u s e of t h a t f a i l u r e was d e t e r -
mined, t h e impact p l a t e was r e - i n s t a l l e d c o r r e c t l y , and no more f a i l u r e s were ex-
p e r i e n c e d on t h a t FWH. No d e - r a t i n g o f p l a n t c a p a c i t y was i n v o l v e d and no measura-
b l e h e a t r a t e d e g r a d a t i o n was n o t e d . I n c a s e s such a s t h i s where permanent r e p a i r s
a r e f e a s i b l e and economical, spending l a r g e sums of money t o r e p l a c e FWHs is c l e a r l y
not the correct solution. On t h e o t h e r hand, t h e r e a r e many s i t u a t i o n s where FWH
r e p l a c e m e n t would b e a p p r o p r i a t e l o n g b e f o r e 10% of t h e t u b e s have f a i l e d .
The p u r p o s e of t h i s s e c t i o n i s t o a s s i s t u t i l i t i e s i n d e v e l o p i n g a n o r d e r l y p r o c e s s
f o r d e c i d i n g whether t o r e p l a c e t r o u b l e s o m e FWHs and, i f s o , when. Recent d i s -
c u s s i o n s w i t h p l a n t e n g i n e e r s , u t i l i t y h e a d q u a r t e r s managers, and e x p e r i e n c e d FWH
v e n d o r s show t h a t many u t i l i t i e s have n o t p r o g r e s s e d v e r y f a r beyond t h e "10% r u l e "
and s t i l l r e l y h e a v i l y on " g u t f e e l i n g s " i n t h i s d e c i s i o n p r o c e s s . Until the util-
i t y management makes a d e t e r m i n e d commitment f o r improvement i n t h i s a r e a , m i l l i o n s
o f d o l l a r s w i l l be wasted e a c h y e a r i n poor performance o f t h e p l a n t s i n v o l v e d .
Age considerations;
Materials of construction;
It is also highly desirable to have key information tabulated for ready reference in
the appropriate utility support organization to assist in the considerations out-
lined in the following subsections. One utility with an excellent plant performance
record and a strong program for FWH system improvement uses data of the type indi-
cated in Tables 4-1 through 4-4. Information in these tables will be used for il-
lustrative purposes in some of the examples outlined in the remainder of this sec-
tion. There are many ways to tabulate data and many ways to estimate figures such
as those displayed in these tables. No attempt has been made to criticize or im-
prove upon these real-life examples. Instead, they are presented as an illustration
of the general type of information that utilities need to have on hand for long-term
planning and repair/replace consideration.
The JWH performance loss cost, which is a direct result of the heat rate
degradation of the plant with the defective FWH isolated during continued
plant operation. (Some utilities call this the "efficiency" cost.) Each
Table 4-1
CuN i Admiralty
Admiralty Ars. Cu.
Admiralty Ars. CU.
CuNi Admiralty
80-20 CuNi Admiralty
80-20, 70-30 CuNi Admiralty
80-20, 70-30 CuNi Admiralty
80-20 CuNi Admiralty
80-20 CuNi Admiralty
80-20 CuNi Admiralty
70-30 CuNi Admiralty
W 70-30 CuNi Admiralty
Monel 400/SS-316 Admiralty
W Monel 400 ~dmiralty
Monel 400/SS-316 Admiralty
Carbon Steel Admiralty
Carbon Steel Admiralty
Monel 400 Monel 400/Admiralty
Carbon Steel SS304
Carbon Steel 55304
Carbon Steel SS304
Carbon Steel SS304
Table 4-3
P l a n t Capacity T o t a l Performance
Station-Unit Heater Loss Cost/Month And C a p a c i t y
Type & Performance ( 1) S p r i n g O r F a l l Loss Cost Range
Service Heater Loss Cost/Month ( 2 ) Summer ( 3 ) Winter P e r Month
E-6&7 A $ 22,290 (1
( 1 2 7 & 133 MW) (2)
Coal (3)
(Peaking 80%) B 6,020 (1)
(2
(31
C 5,970 (1)
D 9,050 (2)
E 10,540 (3
OOc-lbrd'
ulmrd'
N o l a -
U n W E
N N N N
>>>>
Table 4-4
(6)
(5) P o t e n t i a l * Thermal (81
(1) % of H e a t e r ' s Load With Next P e r c e n t a g e Of
Station ( 2) ( 31 (4) Contribution t o Up-Stream H e a t e r ( 7) Total Train
Unit(s) Heater OFRise BTU/HTR Total Train Cut-out-% o f Performance Performance
(Mw) Number Hydraulic XlOOO Thermal R i s e Design $/Month Per Heater
A-5 A 222
(572 MW) B 198
Coal C 175
D 213
E 138
-
F1 189.2% avg.
F2
200
1 and 2 153
( 6 5 MW) 221
Coal 146
-
180% avg.
( 61
(5) P o t e n t i a l * Thermal (8)
(1) % of H e a t e r ' s Load With Next Percentage Of
Station (2) (3 (4) Contribution t o Up-Stream H e a t e r ( 7) Total Train
Unit(s) Heater OFRise BTU/HTR Total Train Cut-out-% of Performance Performance
(Mw) Number Hydraulic Xl 000 Thermal R i s e Design $/Month Per Heater
I A1 177
1 , 2, and 3 A2 177
(860 MW) B1 f 75
Nuclear B2 175
C1 138
C2 138
D1 14 1
D2 141
E1 12 1
E2 12 1
F1 150.4% avg.
F2
F3
FWH outage results in a performance cost that can be determined by the
following formula:
Performance Cost =
The plant capacity loss cost, which is usually the largest single cost
factor for baseloaded plants. In most cases, the plant should be de-
rated while the FWH is isolated, and the cost of replacement power to
make up for that derating constitutes the plant capacity loss cost (also
called "replacement power" cost) :
FWH repair costs, which include the costs of materials and maintenance
labor for troubleshooting and (in this case) tube plugging. For the
troublesome FWH with recurrent tube failures, such repair costs are usu-
ally minor in comparison to the performance and availability costs cited
above.
Two examples are cited below to illustrate the high costs of FWH outages and the
variable nature of the factors contributing to those costs.
Example 1
Using data for Plant A-5 in Table 4-3, assume that low-pressure (LP) FWH D is ex-
periencing tube failures of one or more tubes per incident with approximately three
incidents per year, randomly spaced over the various seasons. In this plant, all
FWHs can be isolated individualy, and company policy permits working inside the
channel area of LP FWHs while the plant is operating after waiting one day to dem-
onstrate that the isolation valves are holding and temperatures are stabilized.
Under these conditions, each FWH outage requires approximately six days for trou-
bleshooting, data collection, and repair. Therefore, the plant operates with a
performance heat rate loss of:
The utility has estimated (Table 4-3) this performance loss to be approximately
$40,700 per month of FWH downtime. For this example, then, the FWH performance
loss is estimated at: .6 x $40,700, or approximately $24,400.
Since the availability loss varies widely from season to season, this utility has
estimated these costs for three season categories as shown in Table 4-3. In winter,
Plant A-5 is needed at full power most of the time, and replacement power for
forced outages and deratings comes from expensive sources (old coal plants or com-
bustion turbines within the company or purchased power from other companies). In
spring and fall, full power is needed less often, and relatively inexpensive power
is available within the company to make up for Plant A-5's shortcomings. Since we
have assumed that FWH D fails randomly in each of the four seasons, then:
A rough estimate of repair costs for three men and materials might be $5,00O/outage
or $15,00O/year.
Example 2
For the same plant, A-5, assume a similar frequency of tube failures for HP FWH A.
Although this FWH can also be isolated by itself, safety considerations make it in-
advisable to enter the channel area for repairs with only one-valve protection.
Therefore, the FWH stays isolated for an average of 1-1/2 months before a planned
or forced outage provides sufficient opportunity for repair. This leads to an
average of 3 x 1-1/2 = 4-1/2 months of FWH outage per year. Rough cost estimates
are:
These examples are not average EWH situations. To make the point that
FWH down time can be very expensive, we have purposely chosen a base-
loaded plant that is normally run at or near full power. The utility is
naturally quite reluctant to shut the whole plant down to repair one
EWH. In addition, the safety rules (in this example) do not permit
working on the H P FWH while the plant is operating, even if the iso-
lation valves hold. The result is an unacceptable capacity loss cost
while the EWH sits isolated for long periods of time each year. This
particular cost would be much lower (perhaps zero) for a peaking plant
or for other situations in which replacement power was not so much
higher in cost.
Repair costs are usually more expensive for H P FWHs than for LP FWHs.
However, they are relatively insignificant compared to the performance
and capacity loss costs, at least in this type of recurring maintenance
activity for baseloaded plants.
Although the costs illustrated in these examples are usually the princi-
pal costs of continued operation of the troublesome FWHs, there are
other cost considerations of a less tangible nature associated with the
other factors described in the following subsections. Such costs should
be recognized even if they are more difficult to quantify.
In the case of the "dead" FWH, it may be wise to open it, as was done to the FWH
shown in Figure 4-1. Such inspections are recommended for learning or confirming
the real causes of failure and for improved understanding of FWH problems. For
example, this practice will often reveal secondary problems that would have ruined
the FWH in another year or two of operation. Failure to learn these lessons fre-
quently leads to the purchase of replacement FWHs with some of the same weaknesses.
Likewise, new E'WHs may be ruined.by failure to correct the deficient operating pro-
cedures that may have been the cause of some of the original FWH's deterioration.
The basic lesson within the scope of this publication is that the managers at the
plant and in the utility support offices must analyze their problems and their
solutions to them thoroughly and in a well-coordinated manner to gain fiscal sup-
port within the company for FWH (and other) improvement programs. That same anal-
ysis is also needed by utility higher management to educate and convince the util-
ity commissions that regulatory improvements are needed to provide rate-base sup-
port for well-conceived programs of long-term benefit to the public as well as to
the utility stockholders.
It is hoped that this publication will help motivate utilities to develop the badly
needed improvement programs for efficient operation, maintenance, and management of
their FWHs. The organized analysis mentioned above must come from management ini-
tiative. Using that analysis for supportable decisions in the repair/replace
planning process is also a key responsibility of management at all levels.
USER FEEDBACK FORM
6. Name and telephone number of the individual who may be called for
additional discussion of your comments:
6. Name and telephone number of the individual who may be called for
additional discussion of your comments:
6. Name and telephone number of the individual who may be called for
additional discussion of your comments:
EPRI 3412 Hillview Avenue, Palo Alto, California 94304 PO Box 10412, Palo Alto, California 94303 USA
800.313.3774 650.855.2121 ikbkcoriQcr>ri.con~ www.epri.com