The ORC Option in Cement Plant
The ORC Option in Cement Plant
The ORC Option in Cement Plant
turbines are both inefficient and by producing and using green electricity. based factory. These compact and scalable
unstable as most steam turbines under AQYLON proposes a range of solutions units allow for rapid implementation
10MW are not designed to overcome for up to 10MWe. The system recovers and low erection costs. Bypasses on the
flow fluctuations. exhaust heat from the preheater and/or thermal oil loop as well as on the organic
• Condensing pressure is below clinker coolers. The process is kept safe fluid closed loop prevent any interference
atmospheric pressure, resulting in as a bypass is intalled on the stack and with normal cement plant operations. Low
the need for complex and expensive equipment complies with a producer’s pressure design and low revolution speed
vacuum and purging equipment. process. of the turbine offer simplicity in operation,
• Maintenance costs are increased by Electricity can be produced from 3MWth reliability and minimal maintenance
the need to have two operators in many and 180°C with AQYLON’s ATM-1000H requirements.
cases. system. High electrical efficency of up to Advantages of the design include:
• The steam turbine’s necessity to use a 23.6 per cent can be achieved. In addition, • high availability (above 97 per cent),
cooling water tower is also an issue: the system has a low footprint as it is fully • high efficiency of the cycle with typical
– there is always a risk of blowdown containerised. isentropic efficiency of the turbine
– the cooling tower needs chemical For its ORC solution, AQYLON proposes: (above 85 per cent)
pre-treatment as well as make- • complete turnkey solutions • retention of efficiency at partial load,
up water, leading to increased • standard high temperature ORC even at very low partial load
maintenance costs. modules in containers offering • a fully automated design with no
• In case of shutdown, the risk of easier transportation (ISO standard overnight operator.
freezing is high in some countries. containers), easier and faster on-site
• In case of failure, the complete system installation (everything is pre-piped and Untapping potential
needs to shut down. pre-connected), and avoidance of heavy The market potential for WHR at a cement
civil works (only some concrete plots factory is huge. AQYLON is well positioned
The AQYLON ORC solution are needed to put the containers on) with its containerised products to
The AQYLON ORC solution is to use this • complete financed solutions, where implement the benefits of ORC solutions
untapped potential by valorising waste the end-user does not need to invest. worldwide.
heat into electricity. In addition, AQYLON In terms of technical flexibility, all To date, AQYLON’s heat recovery
ORC solutions allow industries to meet equipment is mounted in standard 20ft or projects worldwide total about 30MW and
energy transition regulations requirements 40ft containers at the company’s France- demand is growing. n
INTERNATIONL CEMENT REVIEW MAY 2017 ©Copyright Tradeship Publications Ltd 2017