Plumbing Method Statement

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Plumbing

Method Statement
Guidance Note 23
Jul 16

1
Plumbing Method Statement
A Basic Guide to preparation

Introduction

This Guidance Note gives practical information about creating a method statement.

A completed sample template has been included in Appendix 1 and a blank template in
Appendix 2. If you wish to use the template in Appendix 2 to construct your own documents,
you must ensure that all references to Alcumus SafeContractor Accreditation have been
removed and the final documents are clearly incorporated into your existing safety
management system.

A method statement is an ideal way of recording the hazards involved in a specific work
activity and communicating the risk and precautions required to all those involved in the
work, including those undertaking the work and their immediate managers.

A method statement should be developed in conjunction with a risk assessment and


together these demonstrate a safe system of work. The method statement needs be clear,
no longer than necessary, and not over complicated. The document should avoid
ambiguities or generalisations, which could lead to confusion, and layout a step-by-step
sequence of work to describe how the activity is to be carried out safely.

Format

The actual format is dependent on the work being undertaken and the organisational
arrangements in place but generally the following headings should be present:
 Organisation/company in control of the operation
 Named individual responsible for the activity and its safety
 Name of method statement originator and authorisation date
 Arrangements for changing/deviating from method statement
 General description of activity
 Location of activity including access and restrictions
 General working environment considerations, e.g. temperature and wind speed
 Protection of others, e.g. members of the public
 Emergency procedures, including location of emergency equipment
 Identity of operatives (and any specific training or certification required)
 Requirements for Personal Protective Equipment
 Plant and equipment used, including safety precautions and restrictions
 Materials information e.g. hazard information and storage/transport requirements
 Work sequence, including associated risks and required control measures for each
stage
 Safety checks/clearances at specific stages
 Final clearance that activity is completed to specification

SA GN 23 (V2) 2
www.alcumusgroup.com
Jul 2016
www.safecontractor.com
 Any other additional information that may be relevant.

The list above is not exhaustive and a method statement may or may not include each and
every item. However, as a minimum it must achieve the following objectives:
 It should be up to date, identifiable and its source accountable.
 It should contain the sequence of works.
 It should identify the associated risks and control measures.
 It should state actions/authorisation required to deviate from method statement.

Appendix 1 is a sample method statement. It can be as simple or as detailed as the job/risk


requires, so long as it meets the four main objectives.

SA GN 23 (V2) 3
www.alcumusgroup.com
Jul 2016
www.safecontractor.com
Appendix 1

Plumbing Method Statement

Contract Manager: Joe Bloggs Site Supervisor: David Jones

Originator: Joe Bloggs Position: Contracts Manager Date: 01/11/2013

Strict adherence to this method statement is critical to the health and safety of all engaged
in the work.
Any deviation must first be authorised by the Site Supervisor.
Planned Task/Activity Description:
Replace Ball Valve to Water Tank.
Location and Access: (attached plan as appropriate)
Located on flat roof through access door into plant room.
Working Environment & Restrictions:
Flat roof accessed through locked door. Mandatory use of Mansafe system required.
Protection of others:
Men at work sign attached to roof access door, additional signage displayed at work area.
Emergency Procedures:
Normal site emergency procedures will apply.
Operatives/Competence:
1x City and Guilds trained Plumber with safe use of harness training.
Personal Protective Equipment:
Overalls, Safety Harness, Gloves, Goggles, Safety Footwear
Plant & Equipment:
Isolation lock and general hand tools
Materials Handling/Storage & Safety Information:
All material in manageable individual lengths

SA GN 23 (V2) 4
www.alcumusgroup.com
Jul 2016
www.safecontractor.com
Critical Stages: (must be undertaken in correct sequence)

1. Attend Induction, sign for permit and obtain access door key
2. If no information is available on the site water treatment regime/water quality
checks, contact office for further clearance to work
3. Access to roof through locked door
4. Once on roof attach harness to fixed safety restraint system
5. Follow set walkway to plant room
6. Isolate supply to Water Tank using Isolation Lock
7. Drain tank
8. Remove defective Ball Valve and replace
9. Remove Isolation
10. Re-Fill Water Tank and test new Ball Valve
11. Return to access door via set walkway
12. Return key and sign off permit.

Final Clearance: (Work/Activity completed to satisfaction).

Name Position: Date:

SA GN 23 (V2) 5
www.alcumusgroup.com
Jul 2016
www.safecontractor.com
Appendix 2

Blank Method Statement Template

Contract Manager: Site Supervisor:


Originator: Position: Date:
Strict adherence to this method statement is critical to the health and safety of all engaged
in the work.
Any deviation must first be authorised by the Site Supervisor.
Planned Task/Activity Description:

Location and Access: (attached plan as appropriate)

Working Environment & Restrictions:

Protection of others:

Emergency Procedures:

Operatives/Competence:

Personal Protective Equipment:

Plant & Equipment:

Materials Handling/Storage & Safety Information:

Critical Stages: (must be undertaken in correct sequence)

Final Clearance: (Work/Activity completed to satisfaction).

Name Position: Date:

© Copyright Alcumus SafeContractor 2016


This publication may be freely reproduced, except for advertising, endorsement or commercial
purposes.

SA GN 23 (V2) 6
www.alcumusgroup.com
Jul 2016
www.safecontractor.com

You might also like