Flange-Handbook (Installation and Maintenance) PDF
Flange-Handbook (Installation and Maintenance) PDF
Flange-Handbook (Installation and Maintenance) PDF
Handbook
December 2017/Rev. 05
Copyright © 2012
Norwegian Oil and Gas
Design: Mintra AS
Table of Contents
1. General Introduction 06-13
7. Appendix 149-208
1General Introduction
1 General Introduction
1.1 Background
7
1 General Introduction
1.2 HSE Precautions
9
1 General Introduction
1.3 Checklist for the Work Package
11
1 General Introduction
1.4 Execution
13
2ASME RTJ
ASME RTJ 2
ASME RTJ
metal-to-metal seal on both the inside and outside
diameters. Since the deformation is permanent, the
sealing ring cannot be reused. The main principle
is that the ring material is
softer than the material in
the flanges. It is the
gasket that should be
deformed, and not the
ring track.
17
2 ASME RTJ
2.2 Disassembly
ASME RTJ
Check that the spring-loaded pipe
supports are unloaded and placed
in a locked position. That pipes and
equipment are secured against
shifting if support is missing with the
removal of bolts in the flanges.
19
2 ASME RTJ
2.2 Disassembly
ASME RTJ
3. Ensure that the tool has an appropriate
counterhold. The counterhold keys shall be
placed on the same bolts as the wrenches. The
counterhold keys shall prevent the nuts from
rotating during disassembly.
4. Loosen 1/2 a turn at a time, and otherwise follow
the procedure for cross wrenching, until the
tension is taken off the bolts.
5. Loosen the bolts until there are a couple of
millimeters clearance between the nuts and the
flange. Carefully hit the flange with a hammer so
that the gasket loosens.
21
2 ASME RTJ
2.2 Disassembly
WARNING:
With use of a hydraulic spreader, it is
important to remember the following:
• If there is one or more bolts stuck in the
flange’s bolt hole, this can mean that there is
tension in the pipe system. In that case, great
care should be taken in further disassembly of
the flange, and potentially securing the pipe
should be considered.
• Contact a technical supervisor if there is doubt
or a need for action.
WARNING:
With use of a hydraulic spreader, it is
important to remember the following:
• Never stick fingers between the flanges before
a safety block is installed and the spreaders
are unloaded.
• Use the handle on the spreader when taking
out or moving the tool.
ASME RTJ
1. For safety reasons, not all bolts should be taken
out before the flange is open.
2. Use two spreaders,
hydraulic or mechanical,
opposite each other. This
yields an even opening of
the flange.
3. It is important that the
spreaders have full
contact with both flange
surfaces before they are
pressurized.
4. Insert safety blocks when
the desired opening is
reached using hydraulic
spreaders. The flange will
then rest on the safety
blocks.
5. Keep the lowest bolts to
prevent the sealing ring
from falling out.
6. Then take out the sealing ring with its own tool.
Be careful so that the gasket track and flange are
not damaged.
23
2 ASME RTJ
2.3 Inspection
Just before the flanges are disassembled and
cleaned, the seal surfaces should be inspected.
ASME RTJ
ASME RTJ
shall also be reported to a technical supervisor. Bolts
and nuts should be checked for damage and the
threads should be cleaned. Normally, galvanized
bolts should not be reused.
1. The surface roughness of the inclined surfaces in
the ring track should be checked visually against
the RA standard (should have a reference point
for roughness measurement).
2. The surface roughness should not exceed
1.6 micrometers (μm).
25
2 ASME RTJ
2.4 Alignment
ASME RTJ
1. The object with dealing with skews is to find out
where the flanges have the largest gap.
2. Insert all the bolts in the flange connection.
3. With alignment of the flange connection, no more
than half of the number of bolts in the flange
connection should be used, and neighboring
bolts shall not be used so that there is always
at least one unused bolt between bolts that are
used for alignment.
4. Tighten any bolt in the area where the gap
between the flange surfaces is greatest, with
40% of the given moment for a torque tool, or
40% of the B-pressure for a wrench tool. Use
the lowest possible number of bolts to align the
flanges.
5. The object when dealing with skews is to go
around the entire flange connection several
times during the process until the flanges are
parallel.
27
2 ASME RTJ
2.4 Alignment
WARNING:
ASME RTJ
and prepare for the job in advance.
1. Flange and seal surfaces should be checked
for damage, corrosion and wear, and that the
ring track is free of coatings from paint and
preservative. There should not be any paint on
the flange surfaces on any side of the ring track.
2. The flange’s contact surface against the nuts
should also be free of any thick layer of paint
and preservative, which can cause bolts to fail
to tighten after assembly. Only primer can be
accepted under the contact surfaces of the nut.
3. Clean seal surfaces. Steel brushes or approved
emery paper may be used for this. Approved
solvents and cloths may be used for final
cleaning.
4. Clean along the ring track. Ensure that the
cleaning doesn’t create radial tracks in the seal
surface. It is especially important to remove
imperfections in a radial direction.
29
2 ASME RTJ
2.5 Assembly
2.5.2 Bolts
ASME RTJ
The bolt’s labeling is stamped on the one end of the
bolt.
The bolting chart provides information about the
bolts, the type of bolt and nut material, and any
washers that should be used.
It includes a list of tools (for bolt diameters over 1"),
number of bolts, bolt diameter, bolt length, key width,
tightening force, the torque moment that the bolt
should be tightened with, or A and B pressure if a
hydraulic wrench equipment will be used.
The bolting chart also indicates
which type of lubrication should
be used on bolts and nuts.
31
2 ASME RTJ
2.5 Assembly
2.5.2 Bolts
ASME RTJ
2.5.2 Bolts
ASME RTJ
7. Nuts that are assembled with a wrench shall
be lubricated on the contact surface towards
the flange and on the first two threads near
the flange.
33
2 ASME RTJ
2.5 Assembly
2.5.3 Tightening
ASME RTJ
2.5.3 Tightening
ASME RTJ
The following safety steps should be taken when the
tool is in use:
1. Maintain a safe distance from the tool while the
tool is pressurized.
2. Do not attempt to hold or adjust the tool when it
is in operation.
3. Do not leave the work-site with a pressurized
tool.
4. Use a wire to secure loose tools with work at
heights.
See Appendix “Safety moments”.
35
2 ASME RTJ
2.6 Follow-up Inspection
ASME RTJ
and sign “Activity and inspection schedule” after
each time that the flanges are assembled and the
bolt connections are tightened with the prescribed
moment/tightening force.
6. Old markings on the
flange should be
removed, and a new
label sheet should
be hung on the
flange connection.
37
2 ASME RTJ
2.6 Follow-up Inspection
Exceptions:
ASME RTJ
ASME RTJ
39
3ASME RF/FF
ASME RF/FF 3
ASME RF/FF
not be reused.
43
3 ASME RF/FF
3.1 Flange and Gasket
Weld-neck
Slip-on
Screwed
Socket-weld
Lapped
Blind
ASME RF/FF
Check that the spring pipe supports
are unloaded and set in a locked
position.
45
3 ASME RF/FF
3.2 Disassembly
WARNING:
With use of a hydraulic spreader, it is
important to remember the following:
ASME RF/FF
If there is one or more bolts stuck in the flange’s
bolt hole, this can mean that there is tension in
the pipe system. In that case, great care should
be taken in further disassembly of the flange,
and potentially securing the pipe should be
considered. Contact a technical supervisor if
there is doubt or a need for action.
47
3 ASME RF/FF
3.2 Disassembly
ASME RF/FF
be needed to perform an
internal, visual inspection
of pipes/equipment. If there
is damage, this should be
reported to a technical
supervisor. Any tension
in the pipe system should
be reported to a technical
supervisor. Bolts and nuts should be checked
for damage and the threads should be cleaned.
Normally, galvanized bolts should not be reused.
• The surface roughness on the seal surface
should be checked visually against the RA
standard (should have a reference number
for roughness measurement). The surface
roughness should not exceed 6.3 micrometers
(μm) for pressurized systems (3.2 micrometers
(μm) for vacuum service).
49
3 ASME RF/FF
3.3 Inspection
ASME RF/FF
supervisor for evaluation of risk and
any corrective measures.
See ASME PCC-1-2010 Appendix E for extra
guidelines.
Permitted manufacturing tolerances can mean that
the flange surfaces do not have the same distance
around the entire flange connection, i.e. that the
flange surfaces are not parallel.
51
3 ASME RF/FF
3.4 Alignment
ASME RF/FF
your evaluation, and the space around the
flange.
3. After the first alignment, all the bolts are inserted
that can move freely in the flange’s bolt holes. If
not all the bolts move freely, the alignment tool
should be moved, and the flange is aligned until
all the bolts move freely.
4. Lock the flange connection when the flanges are
parallel. This is done by screwing in all the bolts.
WARNING:
53
3 ASME RF/FF
3.5 Assembly
3.5.1 Gasket
ASME RF/FF
1. Opening between the flanges should be larger
than the thickness of the gasket so that this is
not damaged during assembly.
2. A new gasket should always be inserted when
sealing flanges that have been opened.
3. Check that you have the correct gasket
according to the bolting table and that it is free of
damage.
4. NOTE! In some cases, especially with small pipe
wall thickness, gaskets with ASME standard
inner diameter can mean that the diameter is too
small, so that the gasket sticks into the tube. This
can be avoided by selecting a gasket with the
correct inner diameter.
55
3 ASME RF/FF
3.5 Assembly
3.5.1 Gasket
3.5.2 Bolts
ASME RF/FF
used. This includes a list of tools (for bolt diameters
over 1"), number of bolts, bolt diameter, bolt length,
key width, tightening force, the torque moment
that the bolt should be tightened with, or A and B
pressure if a hydraulic wrench equipment will be
used. The bolting chart also indicates which type of
lubrication should be used on bolts and nuts.
57
3 ASME RF/FF
3.5 Assembly
3.5.2 Bolts
3.5.2 Bolts
ASME RF/FF
8. The bolts should move freely through the
opposite flange.
The friction in a screw connection is difficult to
predict accurately since this is dependent on a long
list of variable factors. Since most of the moment
is directed at countering friction, it is important that
the threads of the bolt and nut are checked and
lubricated.
59
3 ASME RF/FF
3.5 Assembly
3.5.3 Tightening
3.5.3 Tightening
ASME RF/FF
2. Do not attempt to hold or adjust the tool when it
is in operation.
3. Do not leave the work-site with a pressurized
tool.
4. Use a wire to secure loose tools with work at
heights.
See Appendix “Safety moments”.
61
3 ASME RF/FF
3.6 Follow-up Inspection
ASME RF/FF
6. Old markings on the
flange should be
removed, and a new
label sheet should be
hung on the flange
connection.
63
3 ASME RF/FF
3.6 Follow-up Inspection
Exceptions:
For non-dangerous help/support issues, the
“Activity and inspection schedule”, and labeling of
the flange connections may be ignored for ASME
pressure ratings of 150 and 300, where the operating
ASME RF/FF
ASME RF/FF
65
4API 6A Type 6B/BX
API 6A Type 6B/BX 4
69
4 API 6A Type 6B/BX
4.1 Flange and Gasket Type 6BX
71
4 API 6A Type 6B/BX
4.2 Disassembly
73
4 API 6A Type 6B/BX
4.2 Disassembly
75
4 API 6A Type 6B/BX
4.2 Disassembly
WARNING:
With use of a hydraulic spreader, it is
important to remember the following:
• If there is one or more bolts stuck in the
flange’s bolt hole, this can mean that there is
tension in the pipe system. In that case, great
care should be taken in further disassembly of
API 6A Type 6B/BX
WARNING:
With use of a hydraulic spreader, it is
important to remember the following:
• Never stick fingers between the flanges before
a safety block is installed and the spreaders
are unloaded.
• Use the handle on the spreader when taking
out or moving the tool.
77
4 API 6A Type 6B/BX
4.3 Inspection
79
4 API 6A Type 6B/BX
4.4 Alignment
81
4 API 6A Type 6B/BX
4.4 Alignment
WARNING:
83
4 API 6A Type 6B/BX
4.5 Assembly
85
4 API 6A Type 6B/BX
4.5 Assembly
4.5.2 Bolts
4.5.2 Bolts
87
4 API 6A Type 6B/BX
4.6 Tightening
89
4 API 6A Type 6B/BX
4.7 Follow-up Inspection
91
5NCF5 Compact
NCF5 Compact 5
NCF5 Compact
Metal-to-metal sealing ring deformation is checked.
The sealing force between ring and ring track is
not affected by dynamic forces since the tension
in the bolts is taken up by the flange surface. This
contributes to a static connection with nearly no
flange movement, even when large dynamic forces
are transmitted. This eliminates the need for post
tightening of the bolts.
95
5 NCF5 Compact
5.2 Disassembly
NCF5 Compact
97
5 NCF5 Compact
5.2 Disassembly
NCF5 Compact
rotating during disassembly.
4. Loosen 1/6th of a turn at a time (60 degrees),
and otherwise follow the procedure for cross
wrenching, until the tension is taken off the bolts.
5. Loosen the bolts until there are a couple of
millimeters clearance between the nuts and the
flange. Carefully hit the flange with a hammer so
that the gasket loosens.
99
5 NCF5 Compact
5.2 Disassembly
WARNING:
With use of a hydraulic spreader, it is
important to remember the following:
• If there is one or more bolts stuck in the
flange’s bolt hole, this can mean that there is
tension in the pipe system. In that case, great
care should be taken in further disassembly of
the flange, and potentially securing the pipe
should be considered.
NCF5 Compact
WARNING:
With use of a hydraulic spreader, it is
important to remember the following:
• Never stick fingers between the flanges before
a safety block is installed and the spreaders
are unloaded.
• Use the handle on the spreader when taking
out or moving the tool.
NCF5 Compact
101
5 NCF5 Compact
5.2 Disassembly
NCF5 Compact
5. Keep the lowest bolts to prevent the sealing ring
from falling out.
6. Then take out the sealing ring with its own
tool. Be careful that neither the ring track, seal
surfaces or a flange is destroyed.
103
5 NCF5 Compact
5.3 Inspection
NCF5 Compact
NCF5 Compact
105
5 NCF5 Compact
5.3 Inspection
NCF5 Compact
NCF5 Compact
flange. etc. with sanding or filing.
Damage to the sealing ring. Change with a new one.
107
5 NCF5 Compact
5.3 Inspection
NCF5 Compact
flange surfaces are not parallel. In such cases,
the bolts must be tightened in the area where the
distance between the flange surfaces is greatest.
109
5 NCF5 Compact
5.4 Alignment
NCF5 Compact
111
5 NCF5 Compact
5.4 Alignment
WARNING:
NCF5 Compact
along the ring track and along the heel and outer
diameter, so that there are no radial tracks on
the surfaces. You should pay careful attention to
damage in a radial direction.
113
5 NCF5 Compact
5.5 Assembly
NCF5 Compact
NCF5 Compact
Check all of the markings on the ring to be certain
that it has the correct material quality in the event of
a deviation within the color coding.
115
5 NCF5 Compact
5.5 Assembly
NCF5 Compact
117
5 NCF5 Compact
5.5 Assembly
5.5.2 Bolts
5.5.2 Bolts
NCF5 Compact
7. The bolts should move freely through the
opposite flange.
The friction in a screw connection is difficult to
predict accurately since this is dependent on a long
list of variable factors. Since most of the moment
is directed at countering friction, it is important that
the threads of the bolt and nut are checked and
lubricated.
119
5 NCF5 Compact
5.6 Tightening
recommendations.
The following safety steps should be taken when the
tool is in use:
1. Maintain a safe distance from the tool while the
tool is pressurized.
2. Do not attempt to hold or adjust the tool when it
is in operation.
3. Do not leave the work-site with a pressurized
tool.
4. Use a wire to secure loose tools with work at
heights.
*See Appendix “Safety moments”.
NCF5 Compact
If it is difficult to close the flange connection on the
outer edge with the given force or moment in the
bolting chart, it is recommended to first check that all
bolts are lubricated as recommended.
If one or both flanges are connected to a very stiff
pipe part or equipment mount, the resistance against
closing the flange connection may be higher than it
would normally be. Then place half of the number of
tools diametrically against each other, in other words,
so that four tools pull two and two neighboring bolts
diametrically opposed to each other, for example.
Ref. different tightening procedures in “Appendix”.
121
5 NCF5 Compact
5.7 Follow-up Inspection
NCF5 Compact
assembly and final bolt tightening, both should have
signed with date at the end of a job.
123
6Clamp Connections
Clamp Connections 6
127
6 Clamp Connections
6.2 Disassembly
Connections
Clamp
129
6 Clamp Connections
6.2 Disassembly
(see warning).
Clamp
Connections
NOTE! Clamp
The bolts and
nuts should not be
removed before the clamp
is released and can freely rotate
around the hub.
131
6 Clamp Connections
6.2 Disassembly
Table 6.1
Number of turns
Hub Opening in mm
360 degrees
2" 2 6 mm
3" 2.5 8 mm
4" 3.25 10 mm
6" 7 22 mm
8" 8 25 mm
10" 9.25 29 mm
12" 11.5 36 mm
14" 12.5 40 mm
H16 12.5 40 mm
H20 13.5 43 mm
H24 13 41 mm
Connections
Clamp
Extra:
Connections
An 8" hub should have 4 turns per nut so that the Clamp
total slack per bolt is 8 turns or 25 mm. The sealing
ring now should be pressurized and the clamp
should be free to rotate.
If the clamp can now rotate freely, further work with
disassembling the clamp may continue.
133
6 Clamp Connections
6.2 Disassembly
WARNING:
Connections
Clamp
WARNING:
135
6 Clamp Connections
6.3 Inspection
Immediately after
the connection is
disassembled and
cleaned, it should inspected.
Additional inspection
personnel may be needed to
perform an internal, visual inspection of pipes/hub
and with welds between hub and pipe/equipment.
If there is damage, this should be reported to a
technical supervisor. Any tension in the pipe system
should be reported to a technical supervisor.
Bolts and nuts should be checked for damage and
the threads should be cleaned. Normally, galvanized
bolts should not be reused.
Troubleshooting leaks
or more information about troubleshooting
F
leaking flanges refer to: Appendix “Checklist
for leaking flanges”.
Connections
Clamp
137
6 Clamp Connections
6.5 Assembly
Connections
Clamp
139
6 Clamp Connections
6.5 Assembly
6.5.2 Bolts
Connections
1. Nuts and bolts without markings should not be Clamp
used.
2. The bolt’s threads and the nut’s contact surface
should be checked for damage and wear.
141
6 Clamp Connections
6.6 Tightening
Connections
Clamp
143
6 Clamp Connections
6.7 Follow-up Inspection
Connections
Clamp
145
6 Clamp Connections
6.7 Follow-up Inspection
Connections
Clamp
147
7Appendix
Appendix 7
150-151
152-163
164-166
168-171
172-173
174-200
201-203
204-205
206-207
7 Appendix
7.1 Safety Moments
Appendix
151
7 Appendix
7.2 Tool Use
NCF5
Loosen 1/6th of a turn at a
time. Follow the procedure
for cross wrenching, until the
tension is taken off the bolts.
153
7 Appendix
7.2 Tool Use
Appendix
155
7 Appendix
7.2 Tool Use
157
7 Appendix
7.2 Tool Use
159
7 Appendix
7.2 Tool Use
Appendix
161
7 Appendix
7.2 Tool Use
163
7 Appendix
7.3 Bolt Tables
ISO PN 20 - ASME Class 150 ISO PN 50 - ASME Class 300
Flange Bolts Bolts
PN inch bolt nut bolt nut bolt nut bolt nut
number dia. dia. dia. number dia. dia. dia.
15 1/2" 4 14 22 1/2" 7/8" 4 14 22 1/2" 7/8"
20 3/4" 4 14 22 1/2" 7/8" 4 16 24 5/8" 1-1/15"
25 1" 4 14 22 1/2" 7/8" 4 16 24 5/8" 1-1/16"
32 1-1/4" 4 14 22 1/2" 7/8" 4 16 24 5/8" 1-1/15"
40 1-1/2" 4 14 22 1/2" 7/8" 8 20 30 3/4" 1-1/4"
50 2" 4 16 24 5/8" 1-1/16" 8 16 24 5/8" 1-1/15"
65 2-1/2" 4 16 24 5/8" 1-1/16" 8 20 30 3/4" 1-1/4"
80 3" 4 16 24 5/8" 1-1/16" 8 20 30 3/4" 1-1/4"
90 3-1/2" 8 16 24 5/8" 1-1/16" 8 20 30 3/4" 1-1/4"
100 4" 8 16 24 5/8" 1-1/16" 8 20 30 3/4" 1-1/4"
125 5" 8 20 30 3/4" 1-1/4" 8 20 30 3/4" 1-1/4"
150 6" 8 20 30 3/4" 1-1/4" 12 20 30 3/4" 1-1/4"
200 8" 8 20 30 3/4" 1-1/4" 12 24 36 7/8" 1-7/16"
250 10" 12 24 36 7/8" 1-7/16" 16 27 41 1" 1-5/8"
300 12" 12 24 36 7/8" 1-7/16" 16 30 46 1-1/8" 1-13/16"
350 14" 12 27 41 1" 1-5/8" 20 30 46 1-1/8" 1-13/16"
400 16" 16 27 41 1" 1-5/8" 20 33 50 1-1/4" 2"
450 18" 16 30 46 1-1/8" 1-13/16" 24 33 50 1-1/4" 2"
500 20" 20 30 46 1-1/8" 1-13/16" 24 33 50 1-1/4" 2"
600 24" 20 33 50 1-1/4" 2" 24 33 50 1-1/4" 2"
650 26" 24 33 50 1-1/4" 2" 28 42 65 1-5/8" 2-9/16"
700 28" 28 33 50 1-1/4" 2" 28 42 65 1-5/8" 2-9/16"
750 30" 28 33 50 1-1/4" 2" 28 45 70 1-3/4" 2-3/4"
800 32" 28 39 60 1-1/2" 2-3/8" 28 48 75 1-7/8" 2-15/16"
850 34" 32 39 60 1-1/2" 2-3/8" 28 48 75 1-7/8" 2-15/16"
900 36" 32 39 60 1-1/2" 2-3/8" 32 52 80 2" 3-1/8"
950 38" 32 39 60 1-1/2" 2-3/8" 32 39 60 1-1/2" 2-3/8"
1,000 40" 36 39 60 1-1/2" 2-3/8" 32 42 65 1-5/8" 2-9/16"
1,050 42" 36 39 60 1-1/2" 2-3/8" 32 42 65 1-5/8" 2-9/16"
1,100 44" 40 39 60 1-1/2" 2-3/8" 32 45 70 1-3/4" 2-3/4"
Appendix
165
7 Appendix
7.3 Bolt Tables
ISO PN 250 - ASME Class 1500 ISO PN 420 - ASME Class 2500
Flange Bolts Bolts
PN inch bolt nut bolt nut bolt nut bolt nut
number dia. dia. dia. number dia. dia. dia.
15 1/2" 4 20 30 3/4" 1-1/4" 4 20 30 3/4" 1-1/4"
20 3/4" 4 20 30 3/4" 1-1/4" 4 20 30 3/4" 1-1/4"
25 1" 4 24 36 7/8" 1-7/16" 4 24 36 7/8" 1-7/16"
32 1-1/4" 4 24 36 7/8" 1-7/16" 4 27 41 1" 1-5/8"
40 1-1/2" 4 27 41 1" 1-5/8" 4 30 46 1-1/8" 1-13/16"
50 2" 8 24 36 7/8" 1-7/16" 8 27 41 1" 1-5/8"
65 2-1/2" 8 27 41 1" 1-5/8" 8 30 46 1-1/8" 1-13/16"
80 3" 8 30 46 1-1/8" 1-13/16" 8 33 50 1-1/4" 2"
90 3-1/2"
100 4" 8 33 50 1-1/4" 2" 8 39 60 1-1/2" 2-3/8"
125 5" 8 39 60 1-1/2" 2-3/8" 8 45 70 1-3/4" 2-3/4"
150 6" 12 36 55 1-3/8" 2-3/16" 8 52 80 2" 3-1/8"
200 8" 12 42 65 1-5/8" 2-9/16" 12 52 80 2" 3-1/8"
250 10" 12 48 75 1-7/8" 2-15/16" 12 64 95 2-1/2" 3-7/8"
300 12" 16 52 80 2" 3-1/8" 12 68 100 2-3/4" 4-1/4"
350 14" 16 56 85 2-1/4" 3-1/2"
400 16" 16 64 95 2-1/2" 3-7/8"
450 18" 16 68 100 2-3/4" 4-1/4"
500 20" 16 76 110 3" 4-5/8"
600 24" 16 90 130 3-1/2" 5-3/8"
650 26"
700 28"
750 30"
800 32"
850 34"
900 35"
950 38"
1,000 40"
1,050 42"
1,100 44"
Appendix
1,150 46"
1,200 48"
Inches Metric
Bolts Thread pitch Nut size Bolts Size Thread pitch Nut size
Size Inch mn. mm
3/8" 16 11/16" 17.5 M3 1.25 13
7/16" 14 3/4" 19 M10 1.5 17
112" 13 7/8" 22.2 M12 1.75 19
9/16" 12 15/16" 23.8 M14 2 22
5/3" 11 1-1/16" 27 M16 2 24
3/4" 10 1-1/4" 31.7 M18 2.5 27
7/8" 9 1-7/16" 36.5 M20 2.5 30
1" 8 1-5/8" 41.3 M22 2.5 32
1-1/8" 8 1-13/16" 46 M24 3 36
1-1/4" 8 2" 50.8 M27 3 41
1-3/8" 8 2-3/16" 55.6 M30 3.5 or 3.0 46
1-1/2" 8 2-3/8" 60.3 M33 3.5 or 3.0 50
1-5/8" 8 2-9/16" 65.1 M36 4.0 or 3.0 55
1-3/4" 8 2-3/4" 69.8 M39 4.0 or 3.0 60
1-7/8" 8 2-15/16" 74.6 M42 4.5 or 3.0 65
2" 8 3-1/8" 79.4 M45 4.5 or 3.0 70
2-1/4" 8 3-1/2" 88.9 M48 5.0 or 3.0 75
2-1/2" 8 3-7/8" 98.4 M52 5.0 or 3.0 80
2-3/4" 8 4-1/4" 108 M56 5.5 or 4.0 85
3" 8 4-5/8" 117.5 M60 6.0 or 4.0 90
3-1/4" 8 5" 127 M64 6.0 or 4.0 95
3-1/2" 8 5-3/8" 136.5 M68 6.0 or 4.0 100
3-3/4" 8 5-3/4" 146 M72 6.0 or 4.0 105
4" 8 6-1/8" 155.6 M76 6.0 or 4.0 110
M80 6.0 or 4.0 115
M85 6.0 or 4.0 120
M90 6.0 or 4.0 130
Appendix
167
7 Appendix
7.4 Tables ASME RTJ, gap
Nominal diameter [inches]
Class Class Class Class Class Class Class
150 300 400 600 900 1500 2500
NPS NPS NPS NPS NPS NPS NPS
1/2 1/2
1/2
3/4 3/4 1-1/2 or 1/2
3/4
1
1 1 1 3/4
1-1/4
1-1/4 1-1/4 1-1/4 1
1-1/2
1-1/2 1-1/2 1-1/2
1-1/4
2
2 2 1-1/2
2
2-1/2
2-1/2 2-1/2 2
21.2
2-1/2
3
3 (2) (2)
3 (2) (2) 3
3
3-1/2
3-1/2 3-1/2
3
4
4 4 4 4
4
4
5
5 5 5 5
5
6
5
6 6 6 6
Appendix
6
6
8
8 8 8 8
3 3
4
4 4 4
4 Example
4 Class 150 NPS 4:
4 4 4 4 The flange connec-
4 tion has a nominal
4 4 4 4 gap of 4 mm.
4
4 4 4 Explanation
3 Class: Pressure
4 rating NPS 4: 4"
6 5 3 flange
3
4
6 5 3
3
3
4
6 5 4
3
4
6 5
3
4
6 6 5 4
4
3
4
6 6 5 4
4
4
3
Appendix
6 6 5 4
3
4
4
6 6 5 4
169
7 Appendix
7.4 Tables ASME RTJ, gap
Nominal diameter [inches]
Class Class Class Class Class Class Class
150 300 400 600 900 1500 2500
NPS NPS NPS NPS NPS NPS NPS
8
8
10
10 10 10 10
10
10
12
12 12 12 12
12
14
12
14 14 14
14
14
16
16 16 16
16
16
18
18 18 18
18
18
20
20 20 20
20
20
24
24 24 24
24
24
Appendix
4
5
4
6 6 5 4
4
6
4
6 6 5 4
5
3
8
6 6 5
4
6
3
6 6 5
4
8
3
6 5 5
5
8
3
6 6 5
5
10
3
6 6 6
6
11
Appendix
171
7 Appendix
7.5 Tables API 6A Type 6B, gap
173
7 Appendix
7.6 Spring Supports
Appendix
175
7 Appendix
7.6 Spring Supports
Appendix
Figure 1.
177
7 Appendix
7.6 Spring Supports
Figure 2.
Appendix
Figure 3.
179
7 Appendix
7.6 Spring Supports
Preset Lock
(Both Sides)
Helical Coil
Spring Travel/Load
Indicator (lower
face of internal
pressure plate)
Stainless Steel
Travel/Load
Scale
Turnbuckle
Appendix
Figure 4.
181
7 Appendix
7.6 Spring Supports
TOP PLATE
PRESSURE
PLATE
CAN SECTION
LOCKING STUD
BOTTOM PLATE
TURNBUCKLE
Figure 5.
Appendix
INFINITELY VARIABLE
LOCKING/BALANCING DEVICE
Figure 6.
183
7 Appendix
7.6 Spring Supports
Figure 7.
locked spring
Appendix
Figure 8.
185
7 Appendix
7.6 Spring Supports
Figure 9.
Appendix
LOCKED UNLOCKED
Figure 10.
LOCKED UNLOCKED
Appendix
Figure 11.
187
7 Appendix
7.6 Spring Supports
Figure 12.
Appendix
189
7 Appendix
7.6 Spring Supports
Bell Crank
LEVER
P1 x D = Fd
Figure 13.
Appendix
191
7 Appendix
7.6 Spring Supports
Figure 14.
There is a little guide that marks the spring’s position
in relation to the total movement the spring permits
(see figure 15). On the scale, two positions are
normally labeled. The one position corresponds
Appendix
193
7 Appendix
7.6 Spring Supports
INFINITELY VARIABLE
LOCKING/BALANCING DEVICE
195
7 Appendix
7.6 Spring Supports
197
7 Appendix
7.6 Spring Supports
7.6.7 Inspection
7.6.7 Inspection
Appendix
199
7 Appendix
7.6 Spring Supports
7.6.7 Inspection
Figure 17.
Example-drawing of a hanging arrangement with
springs.
Appendix
Figure 18.
Example of a detailed drawing of a spring. Note that the
locking nuts are in a locked position and a spring is loaded.
2: Is the ring in accordance with the pipe spec or the bolting chart? ___________
A: Is the ring deformed? _________ Is it deformed evenly? _________
Is it deformed at points? _________
B: Is there movement in the ring when it is put into the track? ___________
C: With use of a new ring is there movement in that?____________
D: Is the blind flange used? _________ Is this free of damage?___________
E: Have the rings been used several times?_____________
F: Have the flanges been used several times? _____________
G: Is the ring track within tolerances? ___________
Appendix
H: Are there foreign elements in the seal surface? ________ If so what? _______
Date:__________________ Signature:____________________________
201
7 Appendix
7.7 Checklist for Leaking Flanges
203
7 Appendix
7.8 Example of Tightening Sheet
PIPE SPEC:
PIPE DIM:
Type Material
Gasket:
Date:
Done by:
TIGHTENING
Tool:
Pump
pressure:
Moment:
Date:
Done by:
Appendix
Appendix
205
LEAK TEST
PRESSURE OK DATE SIGNATURE
N2 - TEST
also includes
N2/Helium
TEST WITH DD.MM.YY INITIALS
PRESSURE ERROR
Gas test
Process
pressure
TEST WITH DD.MM.YY INITIALS
PRESSURE ERROR
7 Appendix
7.9 Example: “Activity and Inspection Schedule”
Operating System
Mechanic
Supervisor
Dimension Ø"
Date Signature Date Signature Date Signature The back side can also be used if
needed
207
7 Appendix
Appendix
Appendix
209
Notes
211
Notes
213
Notes
215
If you have any questions, feedback or comments on the
contents of the handbook, contact the head of Expertise
Development for the Norwegian Oil and Gas
Association via the switchboard, telephone number +47
51 84 65 00.
www.norskoljeoggass.no