Detail Engineering of Pressure Control Vent Project

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ID Task Name Duration Start Finish October 2008 November 2008

14 Sep '08 21 Sep '08 28 Sep '08 05 Oct '08 12 Oct '08 19 Oct '08 26 Oct '08 02 Nov '08 09 Nov '08
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 DETAIL ENGINEERING OF 36 days? Mon 15/09/08 Wed 05/11/08
PRESSURE CONTROL VENT
PROJECT
2 DETAIL ENGINEERING PROCESS 36 days Mon 15/09/08 Wed 05/11/08

3 GENERAL ACTIVITIES 36 days Mon 15/09/08 Wed 05/11/08

4 Coordination (Opening) 5 days Mon 15/09/08 Fri 19/09/08


5 Isometrics check 3 days Fri 31/10/08 Wed 05/11/08
6 Site visit 5 days Mon 22/09/08 Fri 26/09/08
7 DOCUMENTS 12 days Mon 29/09/08 Wed 15/10/08
8 Preliminary study general review 3 days Mon 29/09/08 Wed 01/10/08

9 Process simulation 3 days Thu 02/10/08 Mon 06/10/08


10 Hydraulic calculations 3 days Tue 07/10/08 Thu 09/10/08
11 Process data for control valves 1 day Fri 10/10/08 Fri 10/10/08

12 Process data for instruments 1 day Fri 10/10/08 Fri 10/10/08

13 Lines list 2 days Fri 10/10/08 Tue 14/10/08


14 Tie-Ins list 2 days Fri 10/10/08 Tue 14/10/08
15 Calculation memory 3 days Fri 10/10/08 Wed 15/10/08
16 DRAWINGS 4 days Fri 10/10/08 Thu 16/10/08
17 Process flow diagram (PFDs) 2 days Fri 10/10/08 Tue 14/10/08

18 Piping and instrumentation diagram 2 days Wed 15/10/08 Thu 16/10/08


(P&IDs) Process
19 DETAIL ENGINEERING PIPING 16 days Mon 22/09/08 Tue 14/10/08
20 GENERAL ACTIVITIES 16 days Mon 22/09/08 Tue 14/10/08

21 Site survey 5 days Mon 22/09/08 Fri 26/09/08


22 Bidding document - Piping scope of 3 days Tue 07/10/08 Thu 09/10/08
work
23 Tie in list support 2 days Fri 10/10/08 Tue 14/10/08
24 DOCUMENTS 6 days Thu 02/10/08 Thu 09/10/08
25 Piping stress calculation 5 days Thu 02/10/08 Wed 08/10/08

26 Tie ins construction spec 3 days Tue 07/10/08 Thu 09/10/08

27 Material take off 3 days Thu 02/10/08 Mon 06/10/08


28 DRAWINGS 6 days Mon 29/09/08 Mon 06/10/08
29 General arragement drawings 3 days Mon 29/09/08 Wed 01/10/08
(Update on existing drawings)
30 Isometric drawings 3 days Thu 02/10/08 Mon 06/10/08
31 DETAIL ENGINEERING AUTOMATION AND 33 days? Mon 15/09/08 Thu 30/10/08
CONTROL
32 GENERAL ACTIVITIES 10 days? Mon 15/09/08 Fri 26/09/08

33 Site visit 5 days Mon 22/09/08 Fri 26/09/08


34 Construction items description/List 1 day? Mon 15/09/08 Mon 15/09/08

35 DOCUMENTS 23 days Mon 29/09/08 Thu 30/10/08


36 Design criteria 2 days Mon 29/09/08 Tue 30/09/08
37 Instrument index 1 day Fri 17/10/08 Fri 17/10/08
38 Input / Output signal list 1 day Fri 17/10/08 Fri 17/10/08
39 Material take off (Electrical conn) 3 days Wed 22/10/08 Fri 24/10/08

40 Material take off (Pneumatic & 3 days Wed 22/10/08 Fri 24/10/08
Process conn)
41 I&C cable list 2 days Mon 27/10/08 Tue 28/10/08
42 Control valves spec 5 days Wed 01/10/08 Tue 07/10/08
43 Electronic pressure transmitters 5 days Wed 01/10/08 Tue 07/10/08
spec

Project: Project 1211-03 - YARA Task Progress Summary External Tasks Deadline
Date: Tue 23/09/08
Split Milestone Project Summary External Milestone

Page 1
ID Task Name Duration Start Finish October 2008 November 2008
14 Sep '08 21 Sep '08 28 Sep '08 05 Oct '08 12 Oct '08 19 Oct '08 26 Oct '08 02 Nov '08 09 Nov '08
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
44 Final control elements calculations 5 days Wed 01/10/08 Tue 07/10/08
(Control valves)
45 Technical construction specification 2 days Wed 29/10/08 Thu 30/10/08
for instrumentation installations
46 REQUISITIONS 11 days Wed 08/10/08 Thu 23/10/08
47 Control valv requisition 2 days Wed 08/10/08 Thu 09/10/08
48 Transmitters requisition 2 days Wed 08/10/08 Thu 09/10/08
49 Cables requisition 2 days Mon 20/10/08 Tue 21/10/08
50 Tubing Y & accessories 2 days Wed 22/10/08 Thu 23/10/08
requisition
51 Electrical material requisition 2 days Mon 20/10/08 Tue 21/10/08

52 DRAWINGS 14 days Fri 10/10/08 Thu 30/10/08


53 Process connection details 3 days Fri 10/10/08 Wed 15/10/08
(Hookup's)
54 Electrical connection details 3 days Fri 10/10/08 Wed 15/10/08
(Hookup's)
55 Pneumatic connection details 3 days Fri 10/10/08 Wed 15/10/08
(Hookup's)
56 Instruments support details 3 days Fri 10/10/08 Wed 15/10/08

57 Loop diagrams 2 days Wed 29/10/08 Thu 30/10/08


58 Electric and electro-pneumatic 2 days Thu 16/10/08 Fri 17/10/08
instrum. Location and electric routes
drawing
59 Pneumatic and local instruments 2 days Mon 20/10/08 Tue 21/10/08
location and pneumatic routes
drawing
60 CAPEX PROJECTS 34 days Mon 22/09/08 Mon 10/11/08
61 TENDER No. 012 24 days Mon 06/10/08 Mon 10/11/08
62 Site survey 4 days Mon 06/10/08 Thu 09/10/08
63 Evaluation of existing situation / 20 days Fri 10/10/08 Mon 10/11/08
Technical report
64 TENDER No. 013 21 days Mon 22/09/08 Tue 21/10/08
65 Site survey 5 days Mon 22/09/08 Fri 26/09/08
66 Stress analysis 5 days Wed 15/10/08 Tue 21/10/08
67 Isometric 5 days Tue 07/10/08 Tue 14/10/08
68 Specification for topographycal study 5 days Mon 29/09/08 Fri 03/10/08

69 TENDER No. 014 30 days Mon 22/09/08 Tue 04/11/08


70 Update P&ID, line list and tie-in list, 5 days Fri 17/10/08 Thu 23/10/08
support to ITB package
71 Exiting pump information review / pump 2 days Wed 15/10/08 Thu 16/10/08
requisition
72 Site survey 5 days Mon 22/09/08 Fri 26/09/08
73 General scope for construction 5 days Tue 28/10/08 Tue 04/11/08

74 Piping bill of materials 3 days Mon 27/10/08 Wed 29/10/08


75 Isometrics 5 days Wed 15/10/08 Tue 21/10/08
76 Diasmantling ISOS 3 days Wed 22/10/08 Fri 24/10/08
77 Electrical bill of materials 5 days Mon 06/10/08 Fri 10/10/08
78 Update of one line diagram 5 days Mon 29/09/08 Fri 03/10/08
79 Electrical support to ITB 3 days Tue 14/10/08 Thu 16/10/08
80 Exixting pumps foundation review 5 days Mon 06/10/08 Fri 10/10/08

81 Pumps foundation calculation 5 days Tue 14/10/08 Mon 20/10/08

82 Foundation drawings 3 days Tue 21/10/08 Thu 23/10/08


83 Civil bill of materials 5 days Tue 21/10/08 Mon 27/10/08

Project: Project 1211-03 - YARA Task Progress Summary External Tasks Deadline
Date: Tue 23/09/08
Split Milestone Project Summary External Milestone