Detail Engineering of Pressure Control Vent Project
Detail Engineering of Pressure Control Vent Project
Detail Engineering of Pressure Control Vent Project
14 Sep '08 21 Sep '08 28 Sep '08 05 Oct '08 12 Oct '08 19 Oct '08 26 Oct '08 02 Nov '08 09 Nov '08
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 DETAIL ENGINEERING OF 36 days? Mon 15/09/08 Wed 05/11/08
PRESSURE CONTROL VENT
PROJECT
2 DETAIL ENGINEERING PROCESS 36 days Mon 15/09/08 Wed 05/11/08
40 Material take off (Pneumatic & 3 days Wed 22/10/08 Fri 24/10/08
Process conn)
41 I&C cable list 2 days Mon 27/10/08 Tue 28/10/08
42 Control valves spec 5 days Wed 01/10/08 Tue 07/10/08
43 Electronic pressure transmitters 5 days Wed 01/10/08 Tue 07/10/08
spec
Project: Project 1211-03 - YARA Task Progress Summary External Tasks Deadline
Date: Tue 23/09/08
Split Milestone Project Summary External Milestone
Page 1
ID Task Name Duration Start Finish October 2008 November 2008
14 Sep '08 21 Sep '08 28 Sep '08 05 Oct '08 12 Oct '08 19 Oct '08 26 Oct '08 02 Nov '08 09 Nov '08
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
44 Final control elements calculations 5 days Wed 01/10/08 Tue 07/10/08
(Control valves)
45 Technical construction specification 2 days Wed 29/10/08 Thu 30/10/08
for instrumentation installations
46 REQUISITIONS 11 days Wed 08/10/08 Thu 23/10/08
47 Control valv requisition 2 days Wed 08/10/08 Thu 09/10/08
48 Transmitters requisition 2 days Wed 08/10/08 Thu 09/10/08
49 Cables requisition 2 days Mon 20/10/08 Tue 21/10/08
50 Tubing Y & accessories 2 days Wed 22/10/08 Thu 23/10/08
requisition
51 Electrical material requisition 2 days Mon 20/10/08 Tue 21/10/08
Project: Project 1211-03 - YARA Task Progress Summary External Tasks Deadline
Date: Tue 23/09/08
Split Milestone Project Summary External Milestone
Page 2