Scheduling and Sequencing: - Presented by

Download as pdf or txt
Download as pdf or txt
You are on page 1of 34

SCHEDULING AND SEQUENCING

-Presented by
Akanksha Gupta
Scheduling

• Scheduling: The allocation of resources over time to accomplish


specific tasks.
• Demand scheduling: A type of scheduling whereby customers are
assigned to a definite time for order fulfillment.
• Workforce scheduling: A type of scheduling that determines when
employees work.
• Operations scheduling: A type of scheduling in which jobs are
assigned to workstations or employees are assigned to jobs for
specified time periods.
Introduction
Operations scheduling is critical to the success of an organization;
however, it can be a very complicated task. Effective schedules are
needed to meet promised customer delivery dates or inventory
targets.

It covers the following areas in particular:


- assign job to a particular work center/ machine
- time of assignment of job and completion
- allocation of resources like manpower and materials
- time sequence of operations
- feedback and control function to take care of deviations
Work Centre

• A work center is an area in a business in which productive resources


are organized and work is completed

• Can be a single machine, a group of machines, or an area where a


particular type of work is done
Performance Measures
From the manager’s perspective, identifying the performance
measures to be used in selecting a schedule is important. If the
overall goals of the organization are to be achieved, the schedules
should reflect managerially acceptable performance measures. The
following list describes the most common performance measures
used in operations scheduling.

Job Flow Time: The amount of shop time for the job is called job
flow time. It is the sum of the moving time between operations,
waiting time for machines or work orders, process time (including
setups), and delays resulting from machine breakdowns,
component unavailability, and the like.
Performance Measures
Makespan: The total amount of time required to complete a group
of jobs is called makespan.

Past Due: The measure past due can be expressed as the amount of
time by which a job missed its due date (also referred to as
tardiness) or as the percentage of total jobs processed over some
period of time that missed their due dates.

Work-in-Process Inventory: Any job in a waiting line, moving


from one operation to the next, being delayed for some reason,
being processed, or residing in component or subassembly
inventories is considered to be work-in-process inventory.
Performance Measures
Total Inventory: The sum of scheduled receipts and on-hand inventories
is
the total inventory.

Utilization: The percent of work time productively spent by a machine or


worker is called utilization.

These performance measures often are interrelated.

An understanding of the interactions of job flow time, makespan,


past due, WIP inventory, total inventory, and utilization can make
scheduling easier.
Manufacturing Process
Objectives of Operations
Scheduling
• Making efficient use of the labour.

• Making best possible use of the equipments that are


available for the use.

• Increasing the profit.

• Increasing the output.

• Improving the service level.


Objectives of Operations
Scheduling
• Maximizing the delivery performance i.e. meeting the
delivery dates.

• Minimizing the inventory.

• Reducing the manufacturing time.

• Minimizing the production costs.

• Minimizing the worker costs.


Functions of Operations Scheduling

• Allocation of the resources.

• Shop floor control.

• Making maximum use of the plant at minimum possible


cost.

• Ensure that the needs of the manpower are optimum.

• Determination of the sequence of the jobs.


Functions of Operations Scheduling

• Specifying the start and the end time for each job (actively
scheduled).

• Getting quick feedback from the shops regarding the


delays and the various interruptions.

• Possess up – to – date information for the availability of


the materials, expected delivery dates etc.

• Possess up – to – date data on the machine regarding its


breakdown, servicing etc.
Types of Scheduling

Types of Operations Scheduling are as follows:

1. Forward operations scheduling –


• Classified on the basis of the time.
• All the activities are scheduled from the date of the planned order
release.
• First task of the job is scheduled.
• Its subsequent task is scheduled on the scheduled completion of the
first task.
• Like this, accordingly all the tasks of the job are scheduled.
Types of Scheduling

2. Backward operations scheduling –

• Also classified on the basis of the time.

• Activities are scheduled from the date or the planned receipt date.

• The last activity is scheduled first.

• Time of the start of the last task is considered as the time for the start
of the previous activity.
Shop Floor Control (SFC)

Schedule and monitor day-to-day job shop production • Also called


production control and production activity control (PAC) •
Performed by production control department

• Loading - check availability of material, machines, and labor

• Sequencing - release work orders to shop and issue dispatch lists for
individual machines

• Monitoring - maintain progress reports on each job until it is complete


Loading

Process of assigning work to limited resources

• Perform work with most efficient resources

• Use assignment method of linear programming to determine


allocation
Sequencing

• Prioritize jobs assigned to a resource

• If no order specified use first-come first-served (FCFS)

• Other Sequencing Rules

• FCFS - first-come, first-served

• LCFS - last come, first served • DDATE - earliest due date

• CUSTPR - highest customer priority • SETUP - similar required setups

• SLACK - smallest slack • CR - smallest critical ratio

• SPT - shortest processing time • LPT - longest processing time


Sequencing Jobs
• Operations schedules are short-term plans
designed to implement the sales and
operations plan
• An operation with divergent flows is often
called a job shop
– Low-to medium-volume production
– Utilizes job or batch processes
– The front office would be the equivalent for a
service provider
– Difficult to schedule because of the variability in
job routings and the continual introduction of new
jobs to be processed
Sequencing Jobs

• An operation with line flow is often called a


flow shop
– Medium- to high-volume production
– Utilizes line or continuous flow processes
– The back office would be the equivalent for a
service provider
– Tasks are easier to schedule because the jobs
have a common flow pattern through the system
Job Shop Sequencing

Shipping Department
Raw Materials

Legend:
Batch of parts
Workstation
Copyright © 2010
Figure J.1Pearson
– Diagram of a Manufacturing Job Shop Process
Education, Inc. Publishing as
Prentice Hall.
Priority Sequencing Rules
• First-come, first-served (FCFS)
• Earliest due date (EDD)
• Critical ratio (CR)
(Due date) – (Today’s date)
CR =
Total shop time remaining
 A ratio less than 1.0 implies that the job is behind
schedule
 A ratio greater than 1.0 implies the job is ahead of
schedule
 The job with the lowest CR is scheduled next
Copyright © 2010 Pearson
Education, Inc. Publishing as
Prentice Hall.
Priority Sequencing Rules
• Shortest processing time (SPT)
• Slack per remaining operations (S/RO)
Due Today’s Total shop
date – date – time remaining
S/RO =
Number of operations remaining

 The job with the lowest S/RO is scheduled next

Copyright © 2010 Pearson


Education, Inc. Publishing as
Prentice Hall.
Sequencing One Workstation
• Single-dimension rules
• A job’s priority assignment based only on
information waiting for processing at the
individual workstation (e.g., FCFS, EDD, and
SPT)

Copyright © 2010 Pearson


Education, Inc. Publishing as
Prentice Hall.
Multiple-Dimension Rules
• The priority rules CR and S/RO incorporate information
about the remaining workstations
 S/RO is better than EDD with respect to the
percentage of jobs past due but usually worse
than SPT and EDD with respect to average job
flow times
 CR results in longer job flow times than SPT, but
CR also results in less variance in the distribution
of past due hours
 No choice is clearly best; each rule should be
tested in the environment for which it is intended

Copyright © 2010 Pearson


Education, Inc. Publishing as
Prentice Hall.
Multiple Workstations

• Identifying the best priority rule to use at a


particular operation in a process is a complex
problem because the output from one
operation becomes the input to another
• Computer simulation models are effective
tools to determine which priority rules work
best in a given situation

Copyright © 2010 Pearson


Education, Inc. Publishing as
Prentice Hall.
Scheduling a Two-Station Flow Shop

• In single-workstation scheduling, the makespan is the same


regardless of the priority rule chosen
• In the scheduling of two or more workstations in a flow shop,
the makespan varies according to the sequence chosen
• Determining a production sequence for a group of jobs to
minimize the makespan has two advantages
– The group of jobs is completed in minimum time
– The utilization of the two-station flow shop is maximized

Copyright © 2010 Pearson


Education, Inc. Publishing as
Prentice Hall.
Scheduling Jobs for
Multiple Workstations
• Priority sequencing rules can be used to schedule more than one
operation. Each operation is treated independently.
• Identifying the best priority rule to use at a particular operation
in a process is a complex problem because the output from one
process becomes the input for another.
• Computer simulation models are effective tools to determine
which priority rules work best in a given situation.
• When a workstation becomes idle, the priority rule is applied to
the jobs waiting for that operation, and the job with the highest
priority is selected.
• When that operation is finished, the job is moved to the next
operation in its routing, where it waits until it again has the
highest priority.
Scheduling Problems

• One machine, many jobs


• Two machines, many jobs
• Three machines, many jobs
• Many machines, many jobs
One machine, many jobs

• Total time is independent of sequence


• SPT minimizes average flow time
• Examples- Mumbai airport
Two machines, many jobs

• All Jobs follow same sequence – Johnson’s


Rule
• Jobs have different sequence – Jackson’s Rule
• Johnson’s 3 machine rule
Johnson’s Rule
• Minimizes makespan when scheduling a group of jobs on
two workstations
Step 1: Scan the processing time at each workstation and
find the shortest processing time among the jobs not yet
scheduled. If two or more jobs are tied, choose one job
arbitrarily.
Step 2: If the shortest processing time is on workstation 1,
schedule the corresponding job as early as possible. If the
shortest processing time is on workstation 2, schedule the
corresponding job as late as possible.
Step 3: Eliminate the last job scheduled from further
consideration. Repeat steps 1 and 2 until all jobs have been
scheduled.

Copyright © 2010 Pearson


Education, Inc. Publishing as
Prentice Hall.
Gantt Progress Chart

Gantt Progress Chart for an Auto Parts Company


Start activity
Scheduled activity time
Finish activity Current
date Actual progress
Nonproductive time

Job 4/17 4/18 4/19 4/20 4/21 4/22 4/23 4/24 4/25 4/26

Ford

Plymouth

Pontiac
Gantt Workstation Chart

Gantt Workstation Chart for Hospital Operating Rooms


Thank You

You might also like