Measurement Sheet
Measurement Sheet
Measurement Sheet
17.08 Demolision of the broken staircase upto Beam 'A' and disposal of material.
6 3
Total quantity to previous month m
0 3
Total quantity this month m
6 3 3
Total to date m 6 m
Demolision of the R.C walls on one side of the staircase and at the end of the lowest landing and
17.09
disposal of material
Total quantity to previous month 10 m3
0 3
Total quantity this month m
Total to date 10 m3 10 m
3
Fendering system
17.23 removal of 150x100x2.5m timber fenders Total no removed 4 no
4 no
............................................................. .........................................................
Contractor's Representative Resident Engineer