NTC
NTC
NTC
INTRODUCTION TO CORPORATION
The ongoing infrastructure development journey for NTC began in 1996 when it
was created with few local exchanges and analog microwave. However, today
NTC has developed its own infrastructure to an extent where it can be called an
independent IT and telecom operator capable of meeting the challenges of the
deregulated environment and meeting the objectives for which it was created.
NTC started its operations in 1996 with only 5 local exchanges all over Pakistan
and an analog microwave link not capable of supporting the digital transmission.
To carry out its operations, it was mainly dependent on PTC infrastructure and
used its transit network, international gateways, transmission network, IN
platform etc. to carry out its operations. The copper network in the access
provided to NTC was not sufficient to cater for its subscriber base and meet the
required quality of service parameters. NTC had no arrangements for direct
interconnect with cellular operators as a result it had to pay substantial part of its
revenues to PTCL for 3rd party termination. Data services being essential
demand of NTC customers could not be met due to non availability of
infrastructure. Billing of NTC customers was carried out through PTC initially and
through Pakistan Computer Bureau. The main challenge for NTC at that time
was to reduce this dependency on other operators to minimum as soon as
possible to fulfill its obligations and to sustain itself in the deregulated
environment in which PTC was to be privatized.
The main focus in the initial years was to develop its own basic infrastructure
that included optical fiber transmission backbone, transit network, billing system
and multi services data network (MSDN) beside expansion of its switching
network to un-served areas to cover as much of its subscriber base as possible.
It purchased 2 fibers from PTC in the main optical fiber backbone and equipped
it with 622 Mbps SDH systems. It expanded its exchanges in different cities to
gain access to its customers along with laying of copper cable. These exchanges
were converted into transit exchanges to provision long distance services on
NTC network and to have direct interconnects with cellular and other operators.
The establishment of NTC MSDN was a major milestone, achieved in 2001
which enabled NTC to provide multiple data services such as dial- up, DSL, Web
hosting and internet etc. to its customers. Another milestone achievement in
National history is in placement of Pakistan education & Research Network
(PERN) project. The project is providing 155 Mbps international connectivity to
59 universities connected all over Pakistan. The billing system was developed in
first 4 years which made it possible for NTC to do its own billing.
Future Thoughts:
Being aware of the new technologies, demand for new services and converged
network NTC is in the process of upgrading and expanding its network. Migration
from conventional TDM network to IP based Next Generation Network has been
planned and being implemented. The 622 Mbps optical fiber backbone not able
to meet the requirement of bandwidth hungry applications is being upgraded to
10 Gbps DWDM based technology. To improve the efficiency ERP solution has
been planned and under process of implementation. To gain access to NTC
users efforts are being made for frequency allocation and as a stop gap
arrangement virtual WLL connections are being provided to NTC subscribers. To
provide value added service from its own platform NTC is planning its own IN
platform. Very soon NTC subscribers will be hearing NTC operators for customer
relations, call booking and complaints through its state-of-the-art call center.
Multi services access network has been planned to be as close to the user on
fiber as possible to extend multiple services from a single platform. Plan for
replacing analog microwave with digital is being made so that NTC can meet the
requirements in case of disasters and can provide an alternate to optical fiber
backbone. The co-location facilities are being planned to facilitate new entrants
in performing their operations.
NTC has traveled a long way in developing its infrastructure in lines with the
technological and market trends. NTC is determined to provide an infrastructure
required to meet its objectives and to support the nation and GOP in achieving
its objectives.
Business Volume:
There is no doubt that telecom section in Pakistan is progressing by leaps and
bounds, same is the case with the business volume of this sector. NTC is divided
into five main regions in Pakistan, namely:
Islamabad Region
Lahore Region
Karachi Region
Peshawar Region
Quetta Region
As far as Corporation’s lands, buildings, exchanges & OSP, carrier & coaxial
cable, microwave equipments, optical fiber system, office furniture and
equipment, computer equipment, vehicles, multi-service data network (MSDN),
books, etc. are concerned the total worth becomes Rs. 4,008,641,436 (almost
4008.7 M) according to consolidate summary of operating fixed assets 2005-
2006
Profile of Employees:
NTC is one of the major and leading telecom service providers of GoP with
3300 highly educated, professional, trained and dedicated assets in the form of
human resource, who is ready and confident to undertake all projects of Telecom
and IT sector. These employees include Professional, Managers, Engineers
(from both foreign and local universities), Diploma Holders, and Graduates for
both higher and middle levels; while intermediate and matriculate for lower level
in the hierarchy. The number of employees is also increasing with the passage of
time owing to the expansion in the network / exchanges of NTC, particularly with
the advent of new millennium, human resource of NTC is increasing with rapid
speed to cope up with the drastic changes in the business environment. On one
hand this increase shows, the increasing numbers of human resource while on
other hand it reflects the rapid growth of the corporation. There are 96272
(almost 01 Lac) connections are working, with installed capacity of 117509 with
switching network of 106 exchanges spread in 56 cities of land of opportunity—
Pakistan.
About 70 new exchanges are being planned out of which 46 exchanges have
been entrusted to PTCL for its installation on turn key basis and remaining lines
were to be installed by NTC itself. The strength of Human resource of NTC is
divided into following category:
WHAT'S NEW:
Internet Charges through Telephone Bills
number.
www.ntc.net.pk ).
bills.
access.
DEPARTMENTS OF NTC
There are six division of NTC Central Region, Lahore. The GM office is main division
that control and Supervised the all divisions.
(Hierarchy of NTC Central Region, Lahore)
Telephone:
Basic Telephony
Calling Card
ISDN-Integrated Service Digital Network
BRI-Basic Rate INterface
PRI-Primary Rate Interface
Supplementry Services
Network Solutions for valued
Multi-Services Data Network:
Transmission Services:
Dark Fiber
Media (Junction)
Co-Location:
Telephonic Services
NTC has provided more than 1,05,000 working connections of telephone to its
government subscribers throughout the country.
To meet the requirements of its subscribers NTC is operating following switching and
transmission media services with various new installations in progress.
Following value added services are also planned for the users:
CLI, SMS, Internet with maximum 22 Kbps downloading speed, Call Forwarding and
Call Waiting.
Calling Card
NTC international calling cards are available in denomination of Rs. 250 and 500. NTC
calling cards are exclusively dial able from NTC numbers only.
Universal Access Number (UAN) service is ideal for organizations engaged in facilitating
General Public, help lines, marketing of products or services.
Government Institutes
United nation organizations
Ministries/ help lines Shipping Lines
Consumer Products Companies
Educational Institutes
Provincial Govt. Departments
Trading Companies
Motorway Police/FIA
Foreign Embassies
Insurance Companies
PTV/Radio Pakistan Stock Exchanges
Utility Services
SERVICES
Following the detail of services provided by the organization to its valuable customers.
Telephonic Services
Calling Card
Transmission Services
Internet
Intranet
Web Hosting
Video Conferencing
Co-location
PERN
Telephonic Services:
NTC has provided more than 1,05,000 working connections of telephone to its
government subscribers throughout the country.
To meet the requirements of its subscribers NTC is operating following switching
and transmission media services with various new installations in progress.
39 main switching units.
69 remote digital line units.
Microwave links as its long haul media.
Following value added services are also planned for the users:
Calling Card:
NTC international calling cards are available in denomination of Rs. 250 and
500. NTC calling cards are exclusively dial able from NTC numbers only.
Transmission:
Dark Fiber
Bandwidth bottlenecks can slow data traffic, sometimes at the last mile. This is
because most fiber optics networks do not extend all the way to the businesses
in need of service. NTC provides its own metro dark fiber service laterals in
Islamabad, Karachi, and Lahore, Peshawar and Sargodha and that can deliver
this last mile to ensure fast connections. NTC telecom solutions will remove
bandwidth as an obstacle to your growth without major capital expenditures or
maintenance obligations. Now NTC lease its dark fiber pairs in the above
mentioned cities. Dark fiber pair lease will be point to point for which NTC shall
be responsible for maintenance of Dark Fiber.
Media (Junction)
A leased circuit is a dedicated link between two fixed locations for exclusive use
of the customer. NTC provides leased line services to other service providers
and corporate customers for interconnecting offices, mobile switches and all
telecom switching and distribution equipments all over Pakistan, a leased circuit
may be speech circuit, a data circuit or a telegraph circuit, the terminating
equipment at both ends is telephone without dialing facility both way signaling
and speech is possible. Leased line charges depend on distance or type of
circuit or bandwidth
Internet:
ADSL
NTC has now embarked on the challenging industry of Telecommunications in
Pakistan thereby offering Digital Subscriber Line (DSL) Services
(ADSL/G.SHDSL/HDSL) over the existing phone lines. These High-Speed digital
communication services will go a long way in meeting the overdue demand of
our Government, Educational and Business community in resolving the “last
mile/local loop” issues. With NTCs DSL service, it is possible to receive high
data rates at low cost and optimum performance. A DSL line can carry both data
and voice signals and the data part of the line is continuously connected.
ISDN
Integrated Services Digital Network or ISDN in short, is essentially a network of
fast and highly reliable connections that bring voice, data and video together all
on one digital line. Besides individual users, the NTC-ISDN service also suits
corporate users with a small LAN and who are looking for low-cost network
access to the Internet. With its dial-on-demand technology, it automatically drops
a connection after a pre-defined amount of idle time, and reconnects when you
wish to reaccess the Internet. That's a lot of time, not to mention money, saved.
With the personal NTC-ISDN service, it is possible to access the internet using
both ISDN and analogue phone lines.
Dial-Up
Keeping in view, the requirement of internet making it a commodity in today’s
world NTC embarked upon the mission to provide low price quality access to the
Cyber world and set up top of the notch Access Servers in collaboration with
custom made billing and accounting system. At this moment NTC’s dialup
service is available to all the government functionaries across Pakistan. With
clear pipe IPLCs users always get the smooth Internet surfing experience at
virtually no cost.
Intranet:
As major autonomous bodies and corporate clients are becoming aware of the
vulnerabilities of Internet and the threats associated with it in exchanging
sensitive data, Intranet is becoming popular with each passing day. Now
corporates want to make transactions with complete sense of security and
confidentiality. Using broadband network NTC is providing complete Intranet
solutions with amalgam of technologies naming Dxx, DSL and ATM, which
provides complete network solution to your door steps
G.SHDSL
DXX
Web Hosting:
NTC Power Platform Hosting Solutions meet specific hosting requirements by
simplifying the challenges of any configuration. Our Hosting and Access
Solutions provide the service, flexibility, reliability and responsiveness need to
satisfy all clients’ requirements, business and technical.
NTCs reliable platform gives access to database development tools such as
Active Server Pages (ASP), MS Access, My SQL, PhP, MS-SQL server, Oracle
Open Database Connectivity (ODBC) support and helps clients to get the most
from latest in Web-authoring excellence.
Video Conferencing:
NTC has completed this challenging project which is directly related to overall
objectives of IT Action plan and the concept of E-Governance. NTC has
deployed state of the art hardware and designed a scalable network by means of
which fast, reliable, secure and real time access will be possible between the top
Federal and Provincial Government officials for better and closer communication
without physical displacement
Co-Location:
Space (Open, Covered), Dishes/Antennas on NTC Towers and AC/DC Power
Supply
NTC has its country wide Network of Microwave stations, exchanges and offices.
Now NTC proffer the facility of co-location (Space, Dishes/Antennas on NTC
towers, Power Supply) to Licenced Telecom Operatos to provide the facility for
rapid network expansion/ Growth. Our Co-Location service supports your
expanding network needs with a secure, redundant environment and provides
dedicated space for your equipment. We give you a gateway to the industry’s
most robust local and regional optical networks, allowing you to take advantage
of the best infrastructure having secure access, redundant power supplies, fire
detection systems and 24x7 support capabilities available.
Servers
NTC has established its core setup at three prime locations. More over portals
from various government, semi-government and private companies are also co-
located at NTC multiple data network nodes.
Dark Fiber
Bandwidth bottlenecks can slow data traffic, sometimes at the last mile. This is
because most fiber optics networks do not extend all the way to the businesses
in need of service. NTC provides its own metro dark fiber service laterals in
Islamabad, Karachi, Lahore, Peshawar and Sargodha and that can deliver this
last mile to ensure fast connections. NTC telecom solutions will remove
bandwidth as an obstacle to your growth without major capital expenditures or
maintenance obligations. Now NTC lease its dark fiber pairs in the above
mentioned cities. Dark fiber pair lease will be point to point for which NTC shall
be responsible for maintenance of Dark Fiber.
Media (Junction)
A leased circuit is a dedicated link between two fixed locations for exclusive use
of the customer. NTC provides leased line services to other service providers
and corporate customers for interconnecting offices, mobile switches and all
telecom switching and distribution equipments all over Pakistan, a leased circuit
may be speech circuit, a data circuit or a telegraph circuit, the terminating
equipment at both ends is telephone without dialing facility both way signaling
and speech is possible. Leased line charges depend on distance or type of
circuit or bandwidth.
Video Conferencing
NTC, has completed this challenging project which is directly related to overall
objectives of IT Action plan and the concept of E-Governance. NTC has
deployed state of the art hardware and designed a scalable network by means of
which fast, reliable, secure and real time access will be possible between the top
Federal and Provincial Government officials for better and closer communication
without physical displacement.
Near future which will provide a centralized Information Help desk and complaint
center.
PERN: (Pakistan Education and Research Network )
Background
Pakistan Education and Research Network (PERN) are part of the overall vision
and objectives of IT Action Plan that was launched by Prof. Dr. Atta-ur-Rahman
as Minister of Science and Technology. The project is financed by the
Government of Pakistan in cooperation with PTCL (Pakistan Telecommunication
Company Limited) Research and Development funds. The network is designed,
operated, and maintained by NTC (National Telecommunication Corporation).
The project is aimed to be an integral part of the overall Education System of the
country and is designed to interlink all Public / Private Sector Chartered
Universities / Degree awarding Institutes registered with Higher Education
Commission, Government of Pakistan.
Inauguration
The project was launched by the ex- President of Pakistan General Pervez
Musharraf.
Sponsors
Higher Education Commission
Ministry of Science and Technology (IT and Telecomm Division)
PTCL
Objectives
In its first phase the project is planned to provide:
PERN Architecture
Future Expansion
In the first phase of the project 56 educational institutions have been connected
through PERN. Rest of the 59 HEC recognized universities in Pakistan will be
connected in the PERN-II project phase.
Major HR Issues
Personal Information / Profile
Info regarding Family / Dependents
Transfer / Posting of Employees
Training Received / Required
Penalties
Complete Leave Record (Leave dBase)
Marketing
How it Works:
UAN consists of 6 digits, preceded by 3 digit code of 111, common to all UANs.
Example 111 - 20 20 20.
UAN operates on Existing telephone connections without disturbing normal
phone number
UAN works both in multiline PABX and multi phone connections. The incoming
call hunts for a free junction or free phone connecting instantly.
UAN service can also be used for facsimile
Co-Location
TARIFF GUIDE
ISP Tariffs
Internet Dial-Up
Unlimited (Monthly)
Internet ADSL
Connectivity Additional
Package Download Allowed
512Kbps @ Rs. Per 100 MB
Note:
Other Charges
Internet ISDN
Internet ISDN
Extra Usage CP
Package Usage Linit Speed Rate
Charges C
1.5 GB 128 Kbps Rs 800/-
ISDN Rs 40/100 MB Fre
3 GB 128 Kbps Rs 1,200/-
Other Services
Static IP (Monthly)
Package Rat
Static IP 100/- pe
One free e-mail box of 2MB with same login will be given against ISDN pacakge only.
CPE/NTBT will remain property of NTC and will be retrieved after closure of service.
Web Hosting
Web Hosting
Web Space
Complimentary E-
Apache Rates
Space IIS Rates (Rs.) mail boxes 5MB
(Rs.)
each
8MB 3,500/- 3,000/- 5
16MB 6,000/- 5,000/- 5
32MB 9,500/- 8,000/- 10
64MB 14,500/- 13,000/- 10
128MB 21,500/- 20,000/- 15
256MB 30,500/- 29,000/- 15
512MB 42,000/- 40,000/- 20
1 GB 57,000/- 50,000/- 20
Database Support
MS-SQL/MySQL
Space IIS Access (Rs.) ORACLE
(Rs.)
02Mb 200/- - -
05Mb 300/- 500/- -
08Mb 500/- 1,000/- 1,500/-
16Mb 900/- 1,800/- 2,700/-
32Mb 1,600/- 3,500/- 5,000/-
64Mb 3,000/- 6,500/- 9,000/-
128Mb 5,000/- 11,000/- 16,000/-
256Mb 8,500/- 20,000/- 30,000/-
512Mb 15,000/- 35,000/- 50,000/-
1024Mb 25,000/- 60,000/- 85,000/-
Hosting Components
INTRANET
Leased Line
Distance Charges Per Annum Per Km. (Pak Rs.)
Distance charges are exclusive of General Sales Tax (GST). The GST
@15% shall be payable as per CBR letter no. 1(17)STR/2000, dated 30-11-
2001
The circuit length may be taken as per road mileage between the points
connected by the circuits i.e from end to end including (Local lead).
Charges will be pay able on monthly basis in advance. The bills will be
payable within 7 days from the date of issue. In case of default, 5%
surcharge will be levied. Non payment beyond 14 days shall warrant
disconnection of the service. Default beyond 30 days shall warrant
disconnection of all services provided by the NTC.
The short term requirements ranging from few hours to few days shall be
charged on daily basis with a rate adjustment factor of 1.5 and shall be
subject availability of the facility.
Leased line tariff will not be available for voice and for reselling.
PROJECTS
The ongoing infrastructure development journey for NTC began in 1996 when it
was created with few local exchanges and analog microwave. However, today
NTC has developed its infrastructure to an extent where it can be called an
independent IT and telecom operator capable of meeting the challenges of the
deregulated environment and meeting the objectives for which it was created.
DWDM
NTC DWDM network consists of 80 DWDM and 112 SDH nodes equipped with different
flavors of SDH data rates and various ring structures. The network has been designed in
such a way that 8 Lambda's will be readily available for loading of any type of
wavelength supported services especially keeping in view of new emerging
technologies like IP over DWDM to handle the imminent bulky demand of IP traffic.
MSD
NTC NTC has established a Multi-Services Data Network (MSDN) project for providing various data services includ
media applications to Govt. and semi-Govt. organizations in federal / provincial capitals and other major cities of the
MSDN is performing a multi-role action in meeting the bandwidth requirements of government & allied departments.
basic philosophy of the said network is to provide connectivity for Internet / Intranet and also be able to support Valu
services. Govt. of Pakistan is actively deliberating on launching its E-Governance program to promote information te
Exchange of data information between ministries and their regional offices and access of information by the public is
essential element for its success. NTC Multi-Services Data Network will act as backbone to provide required connec
The main objectives for implementing MSDN is to provide dedicated platform for all governmental e-enabled activitie
connectivity for other organizations like SBP, NBP, AGPR, NAB etc., ISP setup for government and semi-governmen
organizations, video conferencing facility, intercity connectivity etc. Information from the network will be accessible t
variety of information-handling devices, such as PCs, interactive TVs, telephones, or future devices that combine th
attributes of all three, as well as through wireless devices such as pagers, wireless phones, personal digital assistan
(PDAs), and future broadband devices. NTC’s Multi-Services Data Network is designed in such a way that 06 High-
Core Network Switches in Islamabad, Lahore, Karachi, Faisalabad, Peshawar & Quetta are interconnected using O
Fibre SDH backbone on 34 Mbps(E3) while more than 30 Access Network Nodes are spread all over the country. T
connected to the nearest ATM Node either on 34 Mbps (E3) or on multiple of E1s. Moreover NTC is in the process o
establishing its own transport media of 10 Gbps(DWDM) on both sides of Indus River (on existing MAIN & ALTERN
routes) between Peshawar & Karachi. The MSDN backbone will be shifted on new media soon after its completion.
second core technology being used is Packet over Sonet (PoS) Juniper M-20 routers for exclusively routing IP traffi
three main cities Islamabad, Lahore and Karachi. MSDN is a secure, well managed & state of the art technology ne
complete ISP setup is established at Islamabad while Internet and Intranet services are being offered all over the co
MSDN basic services include Dialup, ISDN, DSL, Intranet circuits, Web Hosting and E-Mail etc. Future services incl
Added Services like Personal Web Space, SMS Gateway, WAP Gateway, Fax Gateway Unified Messaging System
Electronic Telephone Directory Services, Roaming Internet Access facility, VPNs, Retrieval of E-mail on PSTN (EWS
platform) telephone connection (text to speech translation), Information about E-mail on telephone line, Dial-out on i
(VoIP) etc.
Project is part of the NTC’s road map for shifting from traditional TDM networks to IP
based NGN network. The completion of this project will enable NTC to reduce OPEX of
the NTC telecom infrastructure and cater for future bandwidth demand for telecom
services.
Project involves installation of 3 x Core Routers at Islamabad, Lahore & Karachi, 3 X
Access Routers at Islamabad, Lahore & Karachi and 18 x Access Routers at various
locations of Pakistan. The project is under execution and will be completed by Sept,
2008.
Coastal Fiber Communication Link from Karachi to Gawadar
Keeping in view the Govt. of Pakistan objective to establish Gawadar as trade corridor
by establishing deep sea port at Gawadar, NTC planned to connect Gawadar to its
Nation wide telecom network. Accordingly, Project for establishment of Coastal Fiber
Communication link from Karachi to Gawadar through Optical Fiber Systems was
planned and approved by ECNEC in year 2002.
NTC has laid 270 KM Optical Fiber Cable from Karachi to Gawadar and installed 2.5
Gbps (STM-16) SDH system at Port Qasim, Hub, Agore, Ormara, Badook, Pasni,
Gwadar and Jiwani. The project in execution stage and likely to be completed in year
2008.
Optical Fiber Access Network for Provision of Telecom Services to Foreign Missions
and other Places at Islamabad
Project has been planned to provide state of the art telecom facilities including voice
and data services to Foreign Missions and other important Govt. offices in Islamabad
through Optical Fiber. The project is in execution stage and after completion it will
provide 1500 new lines for voice and 160 lines for data (PRI, ADSL etc) connectivity.
Project involves laying of NTC Optical Fiber Access Network (OFAN) at 10 x sites
namely Russian embassy, UK embassy, Indonesian embassy, Asif Plaza (Blue Area), F-
7 Markaz, OGDCL, Quaid-e-Azam University, Serena Hotel, Nadra HQs and PINSTECH
Nilore besides installation of PCM/SDH at NCP and ISI Shahdara offices to meet the
requirements of these important Govt. entities.
Provision of Optical Fiber Access Network (OFAN) at Saudi Pak Tower, Islamabad.
Project has been planned to provide state of the art telecom facilities including voice
and data services to NTC designated subscribers at Saudi Pak Tower, UN offices and
other government offices in the vicinity. The project includes laying of Optical Fiber
Cable, UG Cable distribution network and provision of 450 lines Optical Network Unit.
The project is in execution stage and after completion it will provide 450 new lines for
voice and 30 DSL connections, 5 PRI and 8 BRIs. The project is likely to be completed
by July 2008.
Project has been planned to provide state of the art telecom facilities including voice
and data services to Governmnet Offices situated in G-8,G-9 and G-10 Islamabad
through Optical Fiber.This Project is in exectuion stage and after completion it will
provide 515 new lines for voice and 25 lines for data (PRI, ADSL etc) connectivity.
Project involves laying of OFAN at 04 x sites namely Passort Office (G-8), ERRA Office
(G-8), FIA Building (G-9), New District Courts (G-10) alongwith Secondry OSP network
to meet the requirements of these important Govt. Entities. The project is likely to be
completed by October 2008.
Project has been planned to provide state of the art telecom facilities including voice
and data services to Pakistan Atomic Energy Commission (PAEC) HQs in Islamabad
through Optical Fiber. The Project is in exectuion stage and after completion it will
provide 460 new lines for voice and 100 DSL connections, 1 PRI and 5 BRIs.The project
is likely to be completed by July 2008.
The project aims at providing Bandwidth /Interconnectivity to Ministries for their existing
LAN setup and provides its services of transparent LAN between Ministries. Presently
DSL connections have been provided with copper solutions which are being replaced
with optical fiber connectivity. The said arrangement will ensure quality and high data
rate services to Ministries. This project costs around Rs.25M.
The users connected on LAN are increasing so the requirement of bandwidth also
increases. As a pilot project six Ministries/ Divisions have been provided internet access
through fiber optic. For left over Ministries/ Divisions, a comprehensive project has been
prepared and would be implemented very soon.
PROJECTS
Expansion of Existing Cabinets and Installation of New Cabinets for MSU Quetta
Project has been planned to provide state of the art telecom facilities to NTC
subscribers in Shahbaz Town, Chaman Housing Scheme Quetta. The project has been
planned for laying of Primary & Secondary UG cable in the area where NTC network is
not available. This project will help in providing the basic & advanced telecom facilities
to its designated subscribers in the same areas. Almost 180 telephones connection
initially will be taken on NTC network. This project is likely to be completed in August,
2008.
Project has been planned to provide state of the art telecom facilities to Foreign
Missions and other places at Islamabad. The project has been planned for laying of UG
cable distribution network at seven locations, where Optical Network Unit (ONU’s) are
installed to provide the good quality in order to meet the present and future demand of
NTC . Moreover after completion this project approx 1500 numbers could be shifted
from PTCL tie cable apart from covering 1150 new numbers where NTC has no OSP
network at present. This project is likely to be completed in Feb, 2009.
Switch Expansion of 512 Lines from 3744 to 4256 alongwith laying of 900 pairs Primary
OSP lines for 07 Cabinets of NTC RDLU Civil Secretariat Lahore including DFA of 100
Pairs
Project has been planned to provide state of the art telecom facilities to NTC designated
subscribers in vicinity of NTC RDLU Civil Secretariat Lahore. The project after its
completion will result in the total increase of 530 NTC connections, with 335 new
telephone connections and conversion of 195 connections from PTCL to NTC network.
The project is in execution stage and it likely to be completed by July 2008.
Switch expansion of 500 lines from 2042 to 2542 lines alongwith laying of 1200 Primary,
700 Secondary OSP lines at NTC MSU Garden Town Lahore.
Project has been planned to provide state of the art telecom facilities to NTC designated
subscribers in vicinity of NTC MSU Garden Town Lahore. The project after its
completion will result in the total increase of 500 NTC connections. The project is in
execution stage and it likely to be completed by November 2008.
Expansion of 1320 lines OSP Network alongwith 1328 lines expansion of switch of MSU
Cantt, 600 lines OSP alongwith 608 lines expansion in RLDU Khyber and replacement
of 200 pairs old paper core UG cable of MSU Cantt
Project has been planned to expand OSP of NTC MSU Cantt and RDLU Khyber Road
Peshawar and replacement of old paper core cable at Cantt Exchange Peshawar. The
project will provide telecom facilities to NTC designated subscribers including Govt. and
defense offices, University campus. The project will greatly help in increasing NTC
customer base. The project is in execution stage and it likely to be completed by
November 2008.
Provision of Data Communication Setup to AGPRA (PIFRA) through Optical Fiber Cable
at PIFRA Karachi, Lahore, Islamabad and Quetta Cities.
Project has been planned to provide Data Communication facilities to Auditor General of
Pakistan against PIFRA project through Optical Fiber Cable at PIFRA Karachi, Lahore,
Islamabad and Quetta Cities. The Project involves laying of Optical Fiber Cable (OFC)
and installation of SDH (STM-1) equipment. The OFC has been laid while the
procurement of SDH (STM-1)equipment is in process.
Laying of OFC from E-9 to F-11 to H-11 Police Acacemy for formation of Ring and laying
of OFC to NDU E-9 Islamabad.
Project has been planned for Laying of OFC (10 KM) from E-9 to F-11 to H-11 Police
Academy for formation of Ring and Laying of OFC (2.3 KM) to NDU E-9, Islamabad.
Establishment of OFC network in the area will enable NTC to provide data and apeech
circuits on fiber with better QoS as such NTC has no optical fiber network in the area.
Moreover establishment of OFC network will ebale NTC to increase its subscriber base
in the area which has many Govt. offices situated in close proxmity. The project is
started recently and will be completed within year 2008.
Project has been planned to provide state of the art telecom facilities to NTC designated
subscribers in the brewery area. It is expected that almost 236 telephone connections
will be taken on NTC network immediately after the installation of exchange as most of
Govt. offices, Universities and Colleges are located in Brewery Area. The project will
greatly help in increasing NTC customer base. The project is in execution stage and it
likely to be completed by June 2008.
Project has been planned to provide state of the art telecom facilities including voice
and data services to NTC designated subscribers including PIA, SNGPL and other Govt.
Departments. It is expected that 200 new numbers will be extended through this
network while 50 numbers will be converted from PTCL to NTC network. The project is
in execution stage is likely to be completed shortly.
References:
Most of the material is collected during my internship by the respected heads of different
departments, NTC Website and also by assignments.
ORGANIZATIONAL STRUCTURE:
Main Offices:
NTC is divided into five main regions, namely: Islamabad Region, Lahore
Region, Karachi Region, Peshawar Region and Quetta Region with many
main team members designated as Member Tech. and Member Finance who
and GM Admin work directly under guidance of Chairman, however they are also
team. GM Admin and GM HRM have their respective Directors in all five regions.
while they further lead their sub-ordinates in regional headquarters. On the other
hand Member Tech. leads Chief Engineer who further leads GM Tech. and GM
There are 219 different offices / sites under Regional Directorate Lahore which
are situated in five major cities of Punjab i.e., Lahore, Faisalabad, Gujranwala,
Multan, Rawalpindi, etc. The detail of offices under NTC, Lahore Region is
attached as an Annexure-B.
Organizational Structure
Chairman
Member GM GM GM Member
(Tech.) (HRM) (Admin.) (Marketin (Fin.)
GM GM Dir.
(Tech.) (IT) (Fin.)
Dir Dir
(Tech.) (IT)
DD MKT
AD MKT
MO-I SO-I
MO-II SO-II
AD MKT
MO-I SO-I
MO-II SO-II
Commercialization:
With positive results there the ideas become more concrete through test
marketing and
finally are launched for commercialization.
10.3 Pricing Strategy:
Mobilink is a market leader in subscribers and always introduces a reasonable
price for
their products with good quality.
Mobilink pricing strategies for new products;
Positioning Strategy;
Mobilink uses both premium strategy (high price & high quality) and good
value
strategy (low price & high quality) for their new products.
Mobilink also uses the “marketing skimming strategy” for new “products and
market
penetration’ for existing products.
10.4 Distribution Strategy:
Distributing the products in the market is one of the major functions of any
distribution
center on behalf of the principal. As it is said in the previous section that
Mobilink treats
every principal as a separate business unit, so the distribution process for all
the
principals vary considerably with each other.
• Extensive nationwide distribution network positioned to lunch new products
as well as
service existing ones.
• 18 Offices
• 250 Cities.
• 475 frachises
• enhancing relationships with third party distributors to enhance penetration.
Mobilink divide the whole Pakistan in three regions for the better take up of the
distributions and to increase the sale in efficient way below are the details of
the
regions;
1. Central
2. South
3. North
41
10.5 Promotional Strategy:
Mobilink give the desirable information in the print ads to the target market in
order
to inform the customers about the benefit of their products. Whenever Mobilink
introduced new products they give ads on print media at regular intervals. So
that the
customer is informed about the new product.
For their matured products they give ads with different gaps in the
newspapers. The
newspapers they use are: The NEWS, DAWN, and JUNG
Radio
Radio is a good local acceptance, high geographic and demographic selectivity
and low
cost advertisement.
Magazines
The Magazines advertisement high geographic and demographic selectivity,
credibility
and prestige and high quality reproduction, long life and good pass along
readership.
Outdoor Advertising
Outdoor Advertisement flexibility high repeat exposure low cost low message
competition, good positional selectivity
For example
Sing Boards
Bill Boards
Banners
Public Relation
It is communication efforts that are designed to favorably influence attitudes
toward an
organization, its products and policies. Mobilink is not just a quality product
services
supplier, but also a socially conscious corporate citizen. It has been equally
involved in
promoting and funding several community welfare projects through aggregate
revenue
Mobilink is a professionally managed, organization.
Opportunities:
• Expansion in new geographical areas
• Providing per second billing
• Providing more value added services
• Expanding into new markets (DSL)
• Coverage Expansion is the fastest way to capture the remaining addressable
market –1st mover advantage. Developing Network in uncovered areas at a
fast
pace
• Ensure seamless mobility
• Infrastructure sharing – reducing operational & fixed costs
• Use technology to go beyond GSM’s usual limits 35Km which can be doubled
Threats:
• Pressure on Quality of Service (QoS)
• Increased competition
• Price sensitivity
• Declining quality
• With MNP in place the basic product becoming homogeneous could force
mass
exodus of the consumer to better offerings
• MNP conversion cost could have negative implication on ROI
• Technology improvements – a continuous process and threat
• Declining market share
• Decline in profits due to price wars
• New entrants (China Mobile)
• Mobile industry overall is at a saturation point
53
CONCLUSION & RECOMMENDATIONS FOR IMPROVEMENT
13-Conclusions
During my internship, I have pointed out following conclusions:
_ Best environment of marketing department.
_ Strong marketing policies.
_ Imported machinery.
_ Qualified and motivated staff.
_ Strong market leader
_ Awareness of products
_ Customer satisfaction procedure is very good.
_ High financial resources.
_ More customers in International market.
_ Fully computerized system of production.
_ RD&C department is working tirelessly.
_ Every department is working with the standards of ISO 9001 and ISO 14001.
_ Research product and development procedure is very good.
_ Marketing strategies are always made to keep in mind the current market
situation and competitor’s analysis.
_ Marketing personnel continuous visit to existing customer for getting new
orders.
Recommendations
On the basis of my studies and analysis, following areas are recommended to
improve
the results of the organization.
_ The company should arrange the proper training program relevant to
technical
knowledge of product; this would improve the efficiency of marketing
department.
_ Hired only those employees having technical background qualification with
MBA.
_ Meeting should be arranged with production manager for discussion about
complaints on monthly basis
_ The company should focus the attention to customer services and proper
complaint handling to improve the company image in the market.
_ The company should arrange the visit of marketing manager, Regional
manager
for the covering, and studding of international market.
_ The company is going for expansion; therefore company should increase the
staff of marketing department for better results.
_ Decision making power should be decentralized in each region.
_ The company should improve the communication process among the
different
departments for getting better results.
_ Appreciation and monetary regard is necessary on better performance of
sales
executives.
There are following HRM operations being practiced in NTC Regional Directorate, Lahore:
Firing / Termination
Industrial Relations
Managing the human resources is the core issue of the day for each and every
Telecommunication Corporation (NTC) is also striving its best as far as the issue of
“managing the human resources” is concerned. These HRM operations are led by the
while Assistant Director (HRM) at all five regions—Lahore, Peshawar, Islamabad, Karachi,
Quetta, led and assisted by a team of professionals. HRM looks deeply on HR variables
like: high commitment, T&D, high Job security, etc. Lahore Region is working on
regarding HR that is updated on regular intervals under the guidance of AD HRM. The
Major HR Issues
Penalties
hiring / recruitments were started by advertising in almost all famous issues, of both
languages—Urdu and English, of capital cities of Pakistan by inviting the applications from
the suitable experienced professionals. After scanning all these applications short listed
candidates were invited for taking test / interview by the higher authorities. Then last and
final step in this regard was taken by preparing final list of the incumbents. This list was
forwarded to the GM, HRM, NTC, Islamabad for approval and other HR / Admin actions.
With the change in the technology, NTC has initiated a technological start of its hiring /
recruitment process from advertising in both electronic and print media as well as at
Database Registration Authority) office along-with their CNID Cards. An Online test is
conducted avoid any leakage in the process of hiring / recruitment. NADRA compiles
the online results and sends to HRM, NTC Headquarters Islamabad for further
processing at their end. These results are given proper percentage and once again
short listed candidates are called for final interviews. Online testing has not only
removed the taint of nepotism and favouritism from NTC, but also enlisted the
organization in adapting technological change with the pace of time. NTC is staunch
percentage of females in the field of technology—IT &T, the ratio of female to male is
negligible in the corporation. Nonetheless, a few key posts are occupied by the female
officers at top management level in the hierarchy of NTC, along-with many assistants,
The average time span for events in the recruitment pipeline is 41 days, however it
varies according to the nature of job and availability of suitable incumbent. The
Sequence of Events
After hiring / recruiting, incumbent have to follow the prevailing rules and regulations of
incumbent, if required, depending upon the conditions. However for this purpose, there
are following steps taken by the management in order to take any action against the
1. Counseling
2. Explanation
3. Disciplinary Action
4. Warning
5. Charge Sheet
6. Penalty
1. Counseling:
A register is maintained in the office of the Assistant Admin. Concerned officer mark
mistake / misbehave / misconduct / Error / Flaw of the incumbent and inform him for
corrective action.
2. Explanation:
After not availing the chance of counseling, incumbent have to face the written
explanation from the higher ups in order to commit any lapse / negligence in the duties.
3. Disciplinary Action:
On not receiving satisfactory answer / response from the incumbent, authority takes
disciplinary action against the incumbent in the light of Estacodes and E & D Rules
1973.
4. Warning:
5. Charge Sheet:
A charge sheet is prepared against incumbent and sent to him via registered mail /
advertises through print media, after not receiving satisfactory reply in defense.
6. Penalty:
Final phase of this chain ends with direct or indirect penalty in the form of demotion,
removal from service, financial penalty, transfer, etc. in order to make corrective
actions wherever necessary which might stake the whole career of the incumbent.
However, if incumbent is not satisfy with the procedure, he / she makes sue in the
court against in-just action of authority. Rights of the incumbent are fully protected at
every stage, he / she is given full liberty in order to pursue their cases within the NTC
are tagged in one / any / all sources including: personal file, service book, regional
Training and development is a centripetal force of HRM that revolves the incumbent to the
center of its organization in order to meet rapid changes in today’s technological world. As
sessions for its 3300 professional employees all over the Pakistan. In last decade,
Telecom Foundation (TF) has given the gigantic task to train the NTC employees at all
levels. TF executes all these training and development session at its main campus at
Haripur, some other programs were taught at all regional schools of TF. TSC, Haripur also
assists TF. Assistant Director (HRM) refer the incumbents to the relevant Divisional
Engineer in order to relieve the personals to join the training session. However managerial
and advance training held nationally and internationally are allowed by the permission of
Remuneration system is well followed by the latest rules and regulations prevailing in the
telecom sector. Direct payments, benefits, perquisites, etc. are added up into salary slip of
the incumbent and paid through National Bank of Pakistan (NBP) while indirect payments
including bonus, rewards, etc. are further added to the incumbent’s personal bank
However some rewards and bonuses are also arranged for the employees. Few of them
are as under:
Benevolent Advance
Deduction of loans is made on easy installments detail of which is mentioned in the salary
slip of incumbent.
House Requisition and Medical Allowance are added up into the salary slip. There is fixed
ceiling of outdoor medical (i.e., 02 basic salaries per year, but expired after completing the
fiscal year) while there is no limit of indoor ceiling is (i.e., 100% is returned to the
A suitable amount is allocated for dental treatment (i.e., 02 basic salaries per year, but this
amount is not expired after completing the fiscal year and carried forward to the next fiscal
year).
Prolonged / Chronic diseases are also claimed by the approval of the Director (HR). There
Payroll section basically deals with payment of salaries and wages to the employees and workers.
Like other sections, payroll is also computerized. Salary of permanent, contractual and deputed
staff is given against salary slips; while daily wages staff is given their wages against the days they
have worked in the corporation; however stipend is given to trainees. The salary slip contain Name,
Designation, Working Station, BPS, Personal No., Job Nature, GPF Account and NTN No. along-
with the Pay and Allowance and Deductions. The detail of last two given as under as specimen:
Any discrepancy is being forwarded, by the employee on the receipt of pay roll slip, to
Accounts Department for further clarification. All salary / wages are transferred to the
the GoP, however corporation has minutely changed it according to the demand of IT&T
Like many other organization, NTC has also to face the legal issues of both internal and
external customers. For this purpose, Headquarters / Regional Directorates hire the
services of professional advocate from High Court or Supreme Court depending upon the
Legal issues and court cases are dealt under the advice and supervision of HR
department itself. Many legal / court cases are perused by the hired advocates /
1. Bank Fraud
8. Clashes / disputes with other organization in order to lay down the OSP network
organic whole. Here in NTC, HR management is contributing well in bridging the gape
between (among) departments, which is, in fact, the real hallmark of HRM. HRM
both efficiency and effectiveness of NTC as a whole that strengthens the overall objectives
HR management of NTC is the most vigilant among its competitor under the control of
control and command of ministry of information technology and telecom (IT&T) Federal
Govt. of Pakistan. Having its profound relations and roots with Pakistan
Telecommunication Company Ltd. (PTCL), NTC tries hard not only to maintain the
relations between the two friendly competitors, but also improving it day-by-day. NTC has
also strong relations with Telecom Foundation (TF) of Pakistan which provides training
and development (T&D) along-with execution of different projects. While on the Wireless
front, NTC has also strengthens its relations with management of V PTCL—the pioneer of
No doubt, the rapid change of mobile technology has altered the human attitude as a
whole, so NTC never ever ignores this factor and building good relations with all GSM and
between workload and social life of the incumbent. To balance the work at workplace and
social life at home-front, HR department provides 15 days rest and recreation leaves to
every incumbent with one basic pay. HR department also believes in the renowned
phenomenon of Quality of Work-life (QWL) and strives its best to make incumbent friendly
at work so that his / her faculties should focus on maximum output which ultimately
increase the effectiveness of the corporation which helpful in achieving the set goals.
There is also a relaxation of 40 earned leaves and 20 casual leaves other than
miscellanies leaves allowed to the incumbent according to the rules of corporation along-
To avoid mommy wars, NTC relax in the timing of female workers in the organization. So,
keeping in view the concepts of equity and gender description, no late sitting or holiday
There are total 3300 highly educated, professional, trained and dedicated assets in the
form of human resource, including Professionals, Managers, Engineers (from both foreign
also acquire the services of number of new employees with the passage of time owing to
the expansion in the network / exchanges of NTC, particularly with the advent of new
millennium, human resource of NTC is increasing with rapid speed to cope up with the
Employees (Direct Hiring), Vested (from PTCL), Contractual Employees, Daily Wages, On
Deputation (from Army Signal Corp), and Internees. To lead these 3.5 thousand
employees, there is a group of almost 75 HR personals scattered into five different region
of Pakistan. There are almost 15-20 people working in HR department. As far as NTC
regional Headquarters, Lahore is concerned, there are 20 people working under the good
conduct of Assistant Director Human Resource (AD HR) who is directly answerable to
Director Human Resource at NTC Headquarters, Islamabad, and also support Regional
Directorate, NTC, Lahore. The HR team of regional headquarters, Lahore is the crew of 20
AD HR
Assistant HR
UDCs
IT Team
LDC
Attendants
G.M (HRM)
G.M (HRM)
(H/Q Level)
(H/Q Level)
Director (HRM)
Director (HRM)
(H/Q Level)
(H/Q Level)
Assistant
Assistant
(01 Post)
(01 Post)
U.D.C D.C.A
(02U.D.C
Post) (01D.C.A
Post)
(02 Post) (01 Post)
L.D.C D.E.O
(03L.D.C
Post) (01D.E.O
Post)
(03 Post) (01 Post)
Organizational Chart NTC
(HRM Wing-- Regional Directorate)
Assistant Director
Assistant Director
(HRM) (Lahore Region)
(HRM) (Lahore Region)
Assistant
Assistant
A.D (HRM)
A.D Region)
(Lahore (HRM)
(Lahore Region)
L.D.C
L.D.C
L.D.C
D.E.O U.D.C L.D.C
(01D.E.O
Post) U.D.C
(01 Post)
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
Page 59 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
departments
operational area
are concerned.
Weaknesses:
emerging technologies.
Page 60 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
employees.
customers.
with competitors
insufficient staff.
Opportunities:
pace.
Page 61 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
Threats:
Page 62 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
DEPARTMENT:
foremost duty of HRM to make sure that wastage of human or other resources in
the organization be cured, by applying different techniques which better suit the
situation.
praise worth as they not only devise some new techniques in the light of
strategies of HR world into practical form. However, ideal situation never exists in
Hiring / Recruitment:
1. NTC HRM attracts, motivates and retains incumbent well with the
Page 63 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
accordingly.
Firing / Termination:
Mostly HRM nominates right personals for training in the weak areas of
Page 64 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
given outlines and give test; these tests are not checked, in this
these learners.
IBM, but corporation failed to get desired output. For this purpose
Compensation:
Page 65 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
completion of contract.
3. Out of two annual bonuses, employees did not collect their 2nd
7. Two tier wage theory, for civilian and military men, pave the way for
service.
party claim.
Page 66 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
1. NTC has hired the services of legal adviser on contract basis who
less interest legal issues faced by NTC and have much interest in
scarcity of HR.
autocratic decisions.
Industrial Relations:
1. There are good relations with IT&T giant in Pakistan, i.e., PTCL, yet
Page 67 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
1. Rest and Recreating (R/R) leaves have been abolished since last
two years
the employees.
badly.
Page 68 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
IMPROVEMENT:
are resembled with the original thoughts and concepts of HRM, however there is
still a room for improvement in it. Following are the recommendations for
basis.
vice versa.
Page 69 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
and development.
trust and faith in the corporation and also to get employees loyalty
towards corporation.
the corporations.
Page 70 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
HRM efforts.
13. Order for restoration of Rest and Recreating (R/R) leaves should be
14. On re-directing 15 R/R leaves financial benefit of one basic pay for
16. Two tier wage theory, for civilian and military men, which pave the
17. To avoid the clash between army men and civilian personals,
“Theory-Y”.
the organization, yet most of the military men have not much
experience about relevant telecom field. So, most of the time they
chance to lead.
Page 71 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
introduced.
corporation.
24. HRM should contact the employees deputed outside the country,
Page 72 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
29. There must be performance appraisal system for both daily wages
arranged.
life-risk at work-place.
14.2 Finale:
may pave the way towards the improvement of HR department in the corporation
otherwise concept of “treating all employees fairly”, will fade away that must
concluded that overall HR System is working good, though having some flaws,
Page 73 of 74
Khalil ur Rehman
MBA (Marketing)
Roll #: J-123456-
yet have the capacity to remove them. If HRM department of NTC consider
be in the favour of corporation due to which incumbent will pay more attention
organization. This increase in effectiveness and efficiency will definitely plain the
way for achieving what is set in mission and vision statements of corporation.
Page 74 of 74