MAIN COMPONENTS PATENTED TECHNOLOGY

The new ground improvement method is


> vibration free so it can be used
EPICYLIC GEARBOX
immediately next to sensitive sites or
FOR INNER FEED
ASSEMBLY neighbouring buildings
> Less power required

> Fuel savings


ROTARY HEAD
(DRIVES OUTER
DRILLING > Only two plant items required
ASSEMBLY)

> Fast to set up

STONE HOPPER
> No high pressure water or air
injection required therefore
less mess

OUTER DRILLING > Bottom feed – can be used in collapsing soils


ASSEMBLY

Binder can be introduced to provide rigid


> inclusions in the soil – no
expensive concrete delivery trucks
or pumps required
OUTER TOOL-TIP > No creation of liquefaction
and possible machine
instability due to vibrations

> No high wear and high


maintenance high frequency
TIP OF FEED vibrating parts
ASSEMBLY
> Proven technique in a number
of different soil types

> Recognised by international


geotechnical engineering design
companies

NON VIBRATION STONE COLUMNS SYSTEM


Method opens up new foundation No introduction of high pressure water or
possibilities, where previously stone air required so relatively mess free. Sites
columns/ground improvement could not be immediately adjacent to sensitive
considered due to vibrations and nuisance. environments completed.
Graded filter selected materials can be used The tooling is a hybrid drilling assembly,
so columns are more resistant to clogging this allows tool penetration through hard
in liquefaction events. Columns remain layers and removes the requirement for predrilling, that
is often required for vibrating tooling.
effective for multiple events.
2 TECHNICAL DATA / DATI TECNICI
TECHNICAL SPECIFICATIONS

HYDRAULIC RIG B175XP B200XP


Tool diameter* 480 ÷ 550 mm 480 ÷ 620 mm

Final column diameter* 600 ÷ 800 mm 600 ÷ 850 mm

Max. depth* 11 m 13,5 m

Torque of rotary head 175 kNm 210 kNm

Diesel engine - power 194 kW 239 kW

Weight of equipment ~ 43000 kg ~ 64000 kg

* Subject to ground conditions

WORKING PHASES

1. Drilling and 2. Extraction and 3. Final Stone Column


compacting stone feeding

Method builds complete columns at all times, so Fuel and Cost Savings on traditional stone column
there is no-void space introduction to allow column systems. No additional power packs are required,
contamination at any time, unlike methods where a only one rig to perform the job.
plunging motion is used. Can be attached to a conventional rotary piling rig,
thus a truly multi-purpose machine that can be
converted back to other techniques is possible.