SSG Ng01017365 Gen Cs 6180 00001 c01 River Dredging Procedure
SSG Ng01017365 Gen Cs 6180 00001 c01 River Dredging Procedure
SSG Ng01017365 Gen Cs 6180 00001 c01 River Dredging Procedure
Proprietary Information: This document contains proprietary information and may not be partly or wholly reproduced
without prior written permission from Shell Petroleum Development Company
Revision Philosophy
Revisions for review will be issued at R01, with subsequent R02, R03, etc as required.
Revisions for review will be issued at D01, with subsequent D02, D03, etc. as required for DED
Deliverables
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03, etc as
required.
Documents approved for Construction will be issued at C01, C02, C03, etc as required
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc as required
Narrative sections revised from previous approved issues are to be noted in the table below and/or
highlighted in the RH margin (using the appropriate revision status) thus: A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected
areas and by the use of a triangle containing the revision status.
If a document is cancelled the document will be issued at the next sequential number and suffixed with
a X. For example if 02R is the current revision then 03X will be the Cancelled revision
All revisions to this document must be approved by the relevant Technical authority
Revision History
1.0 INTRODUCTION 4
7.0 HSE 11
The project scope includes all works necessary for, arising out of and incidental to the
Engineering, Procurement, Installation and Commissioning of 16” x 34km Southern Swamp
Sales Gas Evacuation Pipeline from the Tunu CPF of Ekeremor Local Government Area in
Bayelsa State to the EA Riser Platform – A (EARP-A) Offshore Nigeria.
The 16” x 34km SSAGS Sales Gas Evacuation Pipeline shall be installed from the Pig launcher
platform around 354,360E 97051.1N at Tunu Central Processing Facilities (TCF) in Ekeremor
Local Government Area of Bayelsa State and will hook up to a pre-installed riser flange at EA
Riser Platform.
CONTRACTOR: The entity assigned to perform the works related to Project Scope of Work.
COMPANY, which will execute part of the project scope under a subcontract.
Project Manager shall ensure that information concerning the work is available on site.
Site Manager shall follow the provisions of this procedure to ensure that the
contents are applied and shall be responsible for safe use, handling
and storage all lifting and rigging equipment on Site. He will appoint
a responsible person to supervise and control all activities.
Construction Manager shall ensure that the quality of the work is maintained.
Quality Manager shall be responsible to carry out all testing and inspection activities to
verify that this procedure is followed and all associated
documentation are collated.
QC Supervisor shall be responsible to monitor and co-ordinate on site all the
inspection and test activities, collect all relevant Quality Records
verifying its adequacy and make sure if the records are correctly
filled out and archived.
Surveyor shall be responsible for performing all necessary checks and
inspections to ensure the dredger dredges the river profile as
established in the alignment sheet. Shall perform post dredge
surveys to confirm the crossing profile is as per specification.
Dredge Master Shall ensure the dredger and all associated facilities are maintained
in fit for purpose status, coordinate the dredging crew and maintain
liaise with the surveyor to ensure the dredging profile is as per
design.
All equipment and key personnel shall be pre-mobilized and certified by COMPANY pre-
mobilization team prior to commencement of operations and this shall be revalidated regularly on
expiration.
Note: Survey, speed boat, excavator and multicat tug operators are already resident at the work location.
Prior to the commencement of any construction operations a survey along the centre-line of each
crossing will be carried out. The survey will encompass the entire length of the crossing between
the points where the pipeline departs from normal cover on either side of the watercourse. The
levels of the land section and the watercourse profile will be recorded using an echo sounder-
bottom profiler in accordance to the methodologies described and explained in the “Pre
Engineering Survey Procedure” SSG-NG01017365-GEN-LA-6180-00001_C01.
A geotechnical survey to determine the type of soil about to be dredge has been performed and
informed the suitability of the dredger for the operation (SSG-NG01017365-GEN-LA-2373-
00026_C03).
This survey information will be as a basis for comparing the syrvey information that will be
generated during the dredging and excavation activities described in this document.
Survey shall verify the on bottom profile and ground level advised on the AFC RoW drawings and
reports the presence and any changes in location of submarine cables, pipelines or features from
the AFC deliverables. These levels shall be used for the calculation of the dredged volumes unless
any major changes are observed. On the completion of dredging at a site, the Contractor shall
survey the excavation, take soundings and there from present detailed cross sections and
computations for the purpose of establishing dredging quantities.
Pre and post dredge surveys shall be done to determine the effects of the dredging on the river
morphology and immediate marine conditions. Echo sounding shall be utilised to determine the
profile of the dredged section.
The turbidity (TNU) of the river (300 meters radius) shall also be surveyed by measuring the
turbibdity of samples of water obtained within 300 meters of the dredging activity before the
dredging activity and after the dredging activity.
Clearing and stumping of all trees and bushes within the pegged areas for dredging work shall be
executed after survey works.
The bushes and trees shall be moved where practicable to the perimeter of the acquired land area
and be processed into a bundwall to prevent the dredged spoil from spilling into the surrounding
third party property. This bund wall shall be made with a combination of ‘chicoco’ mud and the
felled trees and brushed to a neight of about 2 meters high and 2 meters width.
The disposal of felled trees, cleared bushes and stumps within the acquired boundaries shall
comply with Section 3 of the Standard Construction Specifications.
The dredge used for the excavation of the crossing will be governed by the crossing depth.
Generally the crossing excavation will be carried out using a barge-mounted excavator dredge.
Where the required depth is in excess of that at which the excavator dredge can operate efficiently
or economically a cutter-suction dredge will be utilised in conjunction with the excavator dredge to
excavate the deeper part of the crossing profile.
The excavation method for each crossing will be governed by the availability of access to the
crossing. Where the access to the crossing is such that the Long Boom Equipped Spudded Barge
cannot be mobilised to the crossing then excavation will be carried out using Long boom Swamp
excavator with long-reach dipper-arm. Where the width and depth of the crossing are such that
these items of equipment cannot operate efficiently or economically then access for the long boom
excvator will be made either by excavating floatation ditch from the nearest available access point
or by removal of overhanging tree branches along the creek which is to be crossed to permit the
Barge mounted long boom excavator to pass along the creek to the crossing point.
5.4.2 LONG BOOM SWAMP EXCAVATOR WITH LONG REACH REACH DIPPER ARM
At crossings of narrow creeks which cannot be accessed by Spudded Barge Mounted Long Boom
Excavator the excavation will be carried out either by Long Boom Swamp Excavator.
This equipment will excavate the crossing profile in the same way as the Spudded Barge Mounted
Long Boom excavator but will be assisted, where necessary, by swamp buggies which will double-
handle the excavated material away from the excavation and into any extra-width temporary right of
way and in the additional temporary right of way obtained by Contractor to accommodate the
volume of material necessarily excavated to form the specified crossing profile.
Survey and control of excavation depth will be as described for excavator dredge excavation.
Where the width and depth of the access ways to the Tie In Point Location are such that these
items of equipment cannot operate efficiently or economically then access will be made either by
excavating floatation ditch from the nearest available access point or by removal of overhanging
tree branches along the nearest creek to permit the short boom swamp excavator floating on a
small barge to pass along the creek to the Tie In Point Location.
The dredged spoils especially the spoils from the long or short boom swamp excavation shall be used
to backfill the pipeline after the laying activities. The spoils shall be backfilled in such a manner that
the top soil which was the first to be removed will be the last to be replaced.
7.0 HSE
The work and all the connected activities performed will be monitored, verified and recorded in
accordance with the Project HSE Plan SSG-NG01017365-GEN-HX-5798-00001_A01.
All personnel involved in the dredging operation shall have Safety Induction Training prior to
commencing work on the project. All operators of excavators and dredgers will be experienced and with
a proven track record of operating the particular piece of equipment on which they are employed.
SSG-NG01017365-GEN-CS-6180-00001_C01 RIVER DREDGING PROCEDURE
Page 11 of 12
In particular, Contractor shall submit to Company the documents relevant to the pre-engineering survey
records and as-built survey records.