C01 Samplequestions Jan2013
C01 Samplequestions Jan2013
C01 Samplequestions Jan2013
A. Planning
B. Control
C. External
D. Decision-making
Question 2
CIMA defines management accounting as:
“The application of the principles of accounting and financial management to create, protect,
preserve and increase value for the _________________ of for-profit and not-for profit
enterprises in the public and private sectors”.
A. Auditors
B. Stakeholders
C. Owners
D. Customers
Question 3
Which of the following statements are true?
A. 1 and 2 only
B. 2 and 3 only
C. 1 and 3 only
D. None of the above
Question 4
Which of the following words complete the statement below?
A. Shadow, Internal
B. Financial, Internal
C. Financial, External
D. Internal, Budget
Question 5
Which THREE of the following statements about CIMA are true?
Question 6
ABC absorbs fixed production overheads in one of its departments on the basis of machine
hours. There were 100,000 budgeted machine hours for the forthcoming period. The fixed
production overhead absorption rate was £2·50 per machine hour.
Question 7
The audit fee paid by a manufacturing company would be classified by that company as:
Question 8
Question 9
A company uses the repeated distribution method to reapportion service department costs. The
use of this method suggests
A. The company’s overhead rates are based on estimates of cost and activity levels, rather
than actual amounts
B. There are more service departments than production cost centres
C. The company wishes to avoid under- or over-absorption of overheads in its production
cost centres
D. The service departments carry out work for each other
Question 10
Which ONE of the following costs would NOT be classified as a production overhead cost in a
food processing company?
Question 11
An engineering firm operates a job costing system. Production overhead is absorbed at the rate
of $8.50 per machine hour. In order to allow for non-production overhead costs and profit, a
mark up of 60% of prime cost is added to the production cost when preparing price estimates.
The estimated requirements of job number 808 are as follows:
The estimated price notified to the customer for job number 808 will be
A. $22,256
B. $22,851
C. $23,446
D. $24,160
Question 12
The diagram represents the behaviour of a cost item as the level of output changes.
A. Discounts are received on additional purchases of material when certain quantities are
purchased.
B. Employees are paid a guaranteed weekly wage, together with bonuses for higher levels
of production.
C. A licence is purchased from the government which allows unlimited production.
D. Additional space is rented to cope with the need to increase production.
Question 13
A hospital’s records show that the cost of carrying out health checks in the last five accounting
periods have been as follows:
A. $17,515
B. $17,570
C. $17,625
D. $17,680
Question 14
Question 15
The following data have been collected for four cost types; W, X, Y, and Z at two activity levels.
Where V = variable, SV = semi-variable and F = fixed, assuming linearity, the four cost types W,
X, Y and Z are respectively:
W X Y Z
A. V F SV V
B. SV F V SV
C. V F V V
D. SV F SV SV
Question 16
Fixed costs are conventionally deemed to be:
Question 17
Based on the data below, what is the amount of the overhead under-/over-absorbed?
A. $20,957 under-absorbed
B. $21,015 over-absorbed
C. $21,015 under-absorbed
D. $41,972 under-absorbed
Question 18
The following details have been extracted from the receivables records of X:
June $100,000
July $150,000
August $130,000
Customers paying in the month after sale are entitled to deduct a 2% settlement discount.
Invoices are issued on the last day of the month.
The amount budgeted to be received in September 2011 from credit sales is:
A. $115,190
B. $116,750
C. $121,440
D. $123,000
Question 19
Question 20
A. $115,000
B. $120,000
C. $136,000
D. $160,000
Question 21
A. Extended lead time between the preparation of the functional budgets and the master
budget.
B. Difference between the budgeted output and the breakeven output.
C. Additional capacity available which can be budgeted for.
D. Deliberate over-estimation of costs and under-estimation of revenues in a budget.
Question 22
RS is currently preparing the production budget for Product A and the material purchase budget
for material X for the forthcoming year. Each unit of Product A requires 5 kgs of material X.
The anticipated opening inventory for Product A is 5,000 units and the company wishes to
increase the closing inventory by 30% by the end of the year.
The anticipated opening inventory for material X is 50,000 kgs and in order to avoid stock outs
the required closing inventory has been increased to 60,000 kgs.
The Sales Director has confirmed a sales requirement of 70,000 units of Product A.
A. 68,500 units
B. 71,500 units
C. 76,500 units
D. 80,000 units
Question 23
RS is currently preparing the production budget for Product A and the material purchase budget
for material X for the forthcoming year. Each unit of Product A requires 5 kgs of material X.
The anticipated opening inventory for Product A is 5,000 units and the company wishes to
increase the closing inventory by 30% by the end of the year.
The anticipated opening inventory for material X is 50,000 kgs and in order to avoid stock outs
the required closing inventory has been increased to 60,000 kgs.
The Sales Director has confirmed a sales requirement of 70,000 units of Product A. What will be
the purchases budget for material X?
A. 347,500 kgs
B. 350,000 kgs
C. 357,500 kgs
D. 367,500 kgs
Question 24
A. Factor which limits the activities of the organisation and is often the starting point in
budget preparation.
B. Budgeted revenue expected in a forthcoming period.
C. Main budget into which all subsidiary budgets are consolidated.
D. Overestimation of revenue budgets and underestimation of cost budgets, which
operates as a safety factor against risk.
Question 25
Question 26
Overtime premium is
A. The additional amount paid for hours worked in excess of the basic working week.
B. The additional amount paid over and above the normal hourly rate for hours worked in
excess of the basic working week.
C. The additional amount paid over and above the overtime rate for hours worked in excess
of the basic working week.
D. The overtime rate.
Question 27
A standard cost is
Question 28
X operates a standard marginal costing system. The following budgeted and standard cost
information is available:
A. $18,000 adverse
B. $3,000 adverse
C. $3,000 favourable
D. $18,000 favourable
Question 29
Y operates a standard marginal costing system. The following budgeted and standard cost
information is available:
A. $15,000 adverse
B. $14,250 adverse
C. $14,250 favourable
D. $15,000 favourable
Question 30
Which ONE of the following factors could explain a favourable direct material usage variance?
A. More staff were recruited to inspect for quality, resulting in a higher rejection rate.
B. When estimating the standard product cost, usage of material had been set using ideal
standards.
C. The company had reduced training of production workers as part of a cost reduction
exercise.
D. The material price variance was adverse.
Question 31
G repairs electronic calculators. The wages budget for the last period was based on a standard
repair time of 24 minutes per calculator and a standard wage rate of $10.60 per hour.
Based on the above information, the actual wage rate during the period was:
Question 32
P operates a standard marginal costing system. The following budgeted and standard cost
information is available:
A. $35,000 adverse
B. $13,000 adverse
C. $13,000 favourable
D. $35,000 favourable
Question 33
XYZ operates an integrated accounting system. The material control account at
31 March 2011 shows the following information:
$ $
Balance b/d 50,000 Production overhead control account 10,000
Creditors 100,000 ? 125,000
Bank 25,000 Balance c/d 40,000
175,000 175,000
The $125,000 credit entry represents the value of the transfer to the
Question 34
R makes one product, which passes through a single process. Details of the process account
for period 1 were as follows:
Output 18,800 kg
Normal losses 5% of input
There was no work-in-progress at the beginning or end of the period. Process losses have no
value.
A. $437
B. $441
C. $460
D. $465
Question 35
In a standard cost bookkeeping system, when the actual material usage has been greater than
the standard material usage, the double entry to record this is:
A. Debit the material usage variance account, Credit the raw material control account
B. Credit the material usage variance account, Debit the raw material control account
C. Debit the material usage variance account, Credit the work-in-progress account
D. Credit the material usage variance account, Debit the work-in-progress account
Question 36
A company produces a single product that passes through two processes. The details
for process 1 are as follows:
Normal losses are 15% of input in process 1 and without further processing any losses can be
sold as scrap for $1 per kg.
The output for the period was 18,500 kg from process 1.
There was no work-in-progress at the beginning or end of the period.
What value (to the nearest $) will be credited to the process 1 account in respect of the normal
loss?
A. Nil
B. $3,000
C. $4,070
D. $5,250
Question 37
A company has been asked to quote for a job. The company aims to make a net profit of
30% on sales. The estimated cost for the job is as follows:
Variable production overheads are recovered at the rate of £2 per labour hour.
Fixed production overheads for the company are budgeted to be £100,000 each year and
are recovered on the basis of labour hours.
There are 10,000 budgeted labour hours each year. Other costs in relation to selling,
distribution and administration are recovered at the rate of £50 per job.
A. £572
B. £637
C. £700
D. £833
Question 38
A company produces a single product that passes through two processes. The details for
process 1 are as follows:
Normal losses are 15% of input in process 1 and without further processing any losses can be
sold as scrap for £1 per kg.
The output for the period was 18,500 kg from process 1.
There was no work-in-progress at the beginning or end of the period.
A. $88,813
B. $90,604
C. $91,956
D. $94,063
Question 39
In an integrated bookkeeping system, when the actual production overheads exceed the
absorbed production overheads, the accounting entries to close off the production overhead
account at the end of the period would be:
A. Debit the production overhead account and credit the work-in-progress account.
B. Debit the work-in-progress account and credit the production overhead account.
C. Debit the production overhead account and credit the profit and loss account.
D. Debit the profit and loss account and credit the production overhead account.
Question 40
In a standard cost bookkeeping system, when the actual material price exceeds the standard
price, the double entry to record the difference in price is:
A. Debit the material price variance account and credit the raw material control account
B. Credit the material price variance account and debit the raw material control account
C. Debit the material price variance account and credit the work-in-progress account
D. Credit the material price variance account and debit the work-in-progress account
Question 41
Which of the following are characteristics of service costing?
A. (i) only
B. (ii) only
C. (i) and (ii) only
D. All of them
Question 42
The incomplete process account relating to period 4 for a company which manufactures paper
is shown below:
Process account
Units $ Units $
Material 4,000 16,000 Finished goods 2,750
Labour 8,125 Normal loss 400 700
Production overhead 3,498 Work in progress 700
There was no opening work in process (WIP). Closing WIP, consisting of 700 units, was
complete as shown:
Material 100%
Labour 50%
Production overhead 40%
Losses are recognised at the end of the production process and are sold for $1.75 per unit.
A. $21,052.50
B. $21,587.50
C. $22,122.50
D. $22,656.50
Question 43
A. Semi-variable cost
B. Total cost
C. Variable cost
D. Fixed cost
Question 44
Question 45
W Ltd makes leather purses. It has drawn up the following budget for its next financial period:
Question 46
ZK has been asked to quote a price for a special job that must be completed within one week.
The job requires a total of 100 skilled labour hours and 50 unskilled labour hours. The current
employees are paid a guaranteed minimum wage of $525 for skilled workers and $280 for
unskilled workers for a 35-hour week.
Currently, skilled labour has spare capacity amounting to 75 labour hours each week and
unskilled labour has spare capacity amounting to 100 labour hours each week. Additional skilled
workers and unskilled workers can be employed and paid by the hour at rates based on the
wages paid to the current workers.
The materials required for the job are currently held in inventory at a book value of $5,000. The
materials are regularly used by ZK and the current replacement cost for the materials is $4,500.
The total scrap value of the materials is $1,000.
What is the total relevant cost to ZK of using skilled and unskilled labour on this job?
A. Nil
B. $375
C. $775
D. $1,540
Question 47
ZK has been asked to quote a price for a special job that must be completed within one week.
The job requires a total of 100 skilled labour hours and 50 unskilled labour hours. The current
employees are paid a guaranteed minimum wage of $525 for skilled workers and $280 for
unskilled workers for a 35-hour week.
Currently, skilled labour has spare capacity amounting to 75 labour hours each week and
unskilled labour has spare capacity amounting to 100 labour hours each week. Additional skilled
workers and unskilled workers can be employed and paid by the hour at rates based on the
wages paid to the current workers.
The materials required for the job are currently held in inventory at a book value of $5,000. The
materials are regularly used by ZK and the current replacement cost for the materials is $4,500.
The total scrap value of the materials is $1,000.
What is the relevant cost to ZK of using the materials in inventory on this job?
A. $1,000
B. $3,500
C. $4,500
D. $5,000
Question 48
Question 49
Year $
1 50,000
2 120,000
3 200,000
Using a discount rate of 8%, the net present value of the project to the nearest $’000 is $ .
Question 50
Which THREE of the following statements are advantages of the internal rate of return (IRR)
method of investment appraisal?
C01-Answers