Project Management: Critical Path Method
Project Management: Critical Path Method
Project Management: Critical Path Method
Project Management
Wiediartini, SE, MT
@ PPNS,
2011
NETWORK TECHNIQUES
PERT CPM
-Program Evaluation and Critical Path Method
Review Technique Developed by El Dupont
- developed by the US for Chemical Plant
Navy with Booz Shutdown Project- about
Hamilton Lockheed same time as PERT
- on the Polaris
Missile/Submarine
program 1958
• AON—activity-on-node
• AOA—activity-on-arrow
Node ID Earliest start,Earliest finish
A (0,10)
10 (0,10)
Time Remaining
Latest start,Latest finish
Table 3.1
© 2008 Prentice Hall, Inc. 3 – 16
AON Network for
Milwaukee Paper
Activity A
A
(Build Internal Components)
Start
Activity B
Start B (Modify Roof and Floor)
Activity
Figure 3.6
© 2008 Prentice Hall, Inc. 3 – 17
AON Network for
Milwaukee Paper
Activity A Precedes Activity C
A C
Start
B D
Activities A and B
Precede Activity D Figure 3.7
© 2008 Prentice Hall, Inc. 3 – 18
AON Network for
Milwaukee Paper
F
A C
E
Start H
B D G
H
1 Dummy 6 7
Activity (Inspect/
Test)
D
3 5
(Pour
Concrete/
Install Frame) Figure 3.9
© 2008 Prentice Hall, Inc. 3 – 20
Determining the Project
Schedule
Perform a Critical Path Analysis
The critical path is the longest path
through the network
The critical path is the shortest time in
which the project can be completed
Any delay in critical path activities
delays the project
Critical path activities have no slack
time
© 2008 Prentice Hall, Inc. 3 – 21
Determining the Project
Schedule
Perform a Critical Path Analysis
Activity Description Time (weeks)
A Build internal components 2
B Modify roof and floor 3
C Construct collection stack 2
D Pour concrete and install frame 4
E Build high-temperature burner 4
F Install pollution control system 3
G Install air pollution device 5
H Inspect and test 2
Total Time (weeks) 25
Table 3.2
© 2008 Prentice Hall, Inc. 3 – 22
Determining the Project
Schedule
Perform a Critical Path Analysis
Earliest start (ES) = earliest time at which an activity can
Activity Descriptionstart, assuming all predecessorsTime (weeks)
have
A Build internal components
been completed 2
EarliestBfinish (EF)
Modify roof and
= earliest floor
time 3
at which an activity can
C be finished
Construct collection stack 2
LatestD start (LS)
Pour=concrete
latest timeandatinstall
which frame
an activity can4
E start so as to not delay
Build high-temperature burnerthe completion
4
F Install time of thecontrol
pollution entire project
system 3
LatestGfinish (LF) = latest
Install time bydevice
air pollution which an activity has5 to
be finished so as to not delay the
H Inspect and test 2
completion time of the entire project
Total Time (weeks) Table
25 3.2
© 2008 Prentice Hall, Inc. 3 – 23
Determining the Project
Schedule
Perform a Critical Path Analysis
Activity Name
or Symbol
A Earliest
Earliest ES EF
Start Finish
Latest LS LF Latest
Start 2 Finish
EF = ES + Activity time
ES EF = ES + Activity time
Start
0 0
2 EF of B =
ES ES of B + 3
0
Start
0 of B
B
0 0 3
3
© 2008 Prentice Hall, Inc. 3 – 29
ES/EF Network for
Milwaukee Paper
A C
0 2 2 4
2 2
Start
0 0
B
0 3
2 2
Start
0 0
= Max (2, 3) D
0
3 7
B
0 3
3
4
© 2008 Prentice Hall, Inc. 3 – 31
ES/EF Network for
Milwaukee Paper
A C
0 2 2 4
2 2
Start
0 0
B D
0 3 3 7
3 4
2 2 3
Start E H
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
Figure 3.11
LS = LF – Activity time
2 2 3
Start E H
0 0 4 8 13 15
13 15
0 4 2
B D – Activity time
LS = LF G
0 3 3 7 8 13
3 4 5 LF = EF
of Project
© 2008 Prentice Hall, Inc. 3 – 36
LS/LF Times for
Milwaukee Paper
A C F
0 2 2 4 4 7
10 13
2 2 3
Start E H
0 0
LF =4 Min(LS
8 of 13 15
following activity) 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
A C F
0 2 2 4 4 7
2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
8 13
3 4 5
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Slack = LS – ES or Slack = LF – EF
A 0 2 0 2 0 Yes
B 0 3 1 4 1 No
C 2 4 2 4 0 Yes
D 3 7 4 8 1 No
E 4 8 4 8 0 Yes
F 4 7 10 13 6 No
G 8 13 8 13 0 Yes
H 13 15 13 15 0 Yes
Table 3.3
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-
temperature burner
F Install pollution
control system
G Install air pollution
device
H Inspect and test
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-
temperature burner
F Install pollution
control system
G Install air pollution
device
H Inspect and test