Crushing Concrete Cylinders at 28 Days of Precast 111 Nos.
Crushing Concrete Cylinders at 28 Days of Precast 111 Nos.
Crushing Concrete Cylinders at 28 Days of Precast 111 Nos.
Part - 1
NOTICE-REQUEST FOR INSPECTION RFI NO: MD-512-0G00-CN-CV-RFI-KB64-00
`
Project Title : UMM WU'AL PHOSPHATE PROJECT Asset Group Name: SEG
Plant/Unit No.: U&I PROJECT Plant/Package Name : UMM WU'AL PHOSPHATE PROJECT
Contractor has verified that the work is complete and Contractor : SEG
inspected in compliance the following specification
QA/QC Name : Shamshuddin
Part II
Attended : Yes No