FS Rkef 02
FS Rkef 02
FS Rkef 02
(FY 2014)
Report
March, 2015
1
Table of contents
1
2. P RESENT CONDITIONS OF THE STEEL INDUSTRY IN
TECHNOLOGIES
2.1.1 P R E S E N T C O N D I T I O N S O F T H E S T E E L I N D U S T R Y I N V I E T N A M
Figure 2.1-1 shows the trend of steel consumption, steel production and steel self sufficient ratio
in this decade in Vietnam. Steel consumption grew to double from 2004 through 2011 backed by
high growth of the economy of Vietnam. The government tight-money policy for inflation restraint
in 2011 collapsed a real-estate bubble and forced to slow down the steel consumption, but it
gradually increases again recently. The increasing rate of production exceeds that of consumption
from 2004 through 2011, and the self-sufficiency ratio tends to increase. In 2012 and 2013, the
self-sufficiency ratio decreases slightly, because low-priced import steel from China in particular
has increased.
16,000 50%
Steel Cosumption
Steel Cosumption, Crude Steel product
10,000 30%
steel
8,000 25%
6,000 20%
15%
4,000
10%
2,000 5%
0 0%
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Figure 2.1-1 Transition of crude steel production rate, steel consumption rate and self sufficient
ratio1
One major issue of the steel industry in Vietnam includes imbalance between supply and demand.
Productive capacity of some products such as rebar and rod becomes superabundant.
2
Another major issue is the production cost. Outdated and small facilities are still left, and at the same
time new facilities have started in operation after 2000. It is said that old facilities cannot show their
efficiency, and new facilities cannot handle them sufficiently. This situation cannot control
competitive production cost. Meanwhile electric power price in Vietnam has been held down
politically. At present electric power price is 6 ~7 US cents/kwh, but it will be raised to 8 ~9 US
cents/kwh in 2020 according to Master Plan. On the other hand, low price steel from China tends to
increase. In order to overcome this situation, cost down of the steel production must be required from
now.
2.1.3 E N E R G Y C O N S U M P T I O N C O N D I T I O N O F S T E E L I N D U S T R Y I N V I E T N A M .
Through documents and a field work, the amount of energy saving and CO2 reduction potentials are
calculated when Japanese technologies are introduced.
UNIDO Vietnam Mission Report3 in 2011 and UNIDO Seminar4 in 2012 show energy intensity
(GJ/t-steel) and CO2 emission rate (kg-CO2/t-steel) of 18 steel companies joining Vietnam steel
association. Fig.2.1-2 shows both average value of CO2 emission and specific electric power
consumption calculated from energy intensity. CO2 emission and specific electric power consumption
is assumed to be almost 1.5 times as much as that of Japan.
In Figure 2.1-3, operation conditions and their operational indecis are arranged.
2
JETRO Hanoi Center March, 2011
3
UNIDO, "Energy and Resource Efficiency in the Vietnamese Steel Industry", July 2011
4
Green Industry Initiative and Promotion of Green Technologies 20120828-Green_Industry.pdf, (UNIDO
Seminar, Tokyo (2012))
3
1600
Electric power, kWh/t-liquid steel (2011/7) (Hot metal ratio/50%)
1400
Electric power,、CO2 Emission
800
600
400
200
0
L E O M K Q G J N A H D P I F C R B Average Japan
Figure 2.1-2 Specific electric power consumption and CO2 emission rate of 18 steel companies
joining Vietnam Steel Association
(Unit of data in Japan is expressed as “per t-steel billet”)
4
Figure 2.1-3 EAF operation condition and its operational index of 18 steel companies joining Vietnam Steel Association
Operation Condition Operation Index
Production EAF SPH EBT Cooling Ladle Warm EAF electric power EAF electric power EAF electric CC energy RHF Energy EAF Tap to CO2
Plant ,x10,000t/y Capacity Pane Furnac or Hot consumption consumption power Consumptio consuption Electrode tap Emission Factor*2 Reference 1 Reference 2
No *1 *1
*1 ,t/ch e charge ,GJ/t-liquid steel ,kWh/t-steel consumption n GJ/t-billet consumptio ,min ,kg CO2e/t-steel
(2011/7) (2011/7) *3 ,kWh/t-steel GJ/t-billet n
(2012/8) *8, *3 kg/t-billet
less advanced
1 A Private 20 15-20 × × × ○ ○ 2.7 540 672 0.5 1.5 3.4 96 690 Stage-1
plant, fig4
more advanced
2 B Private 25 60 ○ ○ ○ ○ × 4.1 820 706 0.4 no mill 2.7 60 1,180 Stage-1
plant, fig4,10
less advanced
3 C Public 7 15-20 × × × × × 3.45 690 754 0.2 no mill 4.1 70 930 Stage-1
plant, fig4
less advanced
4 D Public 10 15-20 × × × ○ ○ 3.1 620 602 0.3 1.6 3.1 80 720 Stage-1
plant, fig4
more advanced
5 E Private 45 60 ○ ○ ○ ○ ○ 2.1 420 717 0.2 1.2 1.45 60 620 Stage-1
plant, fig4,10
more advanced
6 F Public 50 60 ○ ○ ○ ○ × 3.3 660 593 0.3 1.7 1.35 45 820 Stage-1
plant, fig4,10
7 G Public 2.6 520 564 3.8 150 520 Stage-2
Hot metal
8 H Public 3.1 620 660 2.6 75 1,450 Stage-2
ratio50%,fig19, HP
9 I Public 3.25 650 646 5.8 158 780 Stage-2
10 J Private 2.6 520 655 3.3 110 790 Stage-2
11 K Private 2.55 510 586 3.3 80 720 Stage-2
12 L Private 2 400 459 2.7 80 530 Stage-2
13 M Private 2.55 510 561 3 90 580 Stage-2
14 N Private 2.6 520 593 3.15 110 620 Stage-2
more advanced
15 O Private >50 2.2 440 494 2.7 76 750 Stage-2
plant, fig4,10
16 P Public 3.15 630 684 2.25 56 800 Stage-2
RHF:CGF、low
17 Q Private 2.6 520 586 3 80 590 Stage-2 production/ Fig18
18 R Private 3.8 760 892 4 120 930 Stage-2
Average of 18 min 2.0 400 1.2 1.4 45 520
companies
max 4.1 820 1.7 5.8 158 1450
(Oxygen consumption
=30~50Nm3/t-steel *3) ave 2.9 575 1.5 3.1 89 779
Japan level 380 *4 0.6-1.2 *6 530 *5
world revel 1.7 *1 345 *7 0.3 *1 0.5 *1 1.1 *7
Table2 Table7, Fig12
UNIDO Report *1→ Fig21 Fig5,6 p.9 p.9 p.9 p.9 Fig5,6,7,9,21 Table2 Table2 Fig17 Fig20
Fig5,6,10 Fig17 Table4
*1: UNIDO, "Energy and Resource Efficiency in the Vietnamese Steel Industry", July 2011, *2: Total on and off site emissions
*3: From Nguyen Thi Ngoc Tho (Energy Efficiency and Conservation Center of Ho Chi Minh City) "Overview of Steel and Paper Industry – Energy Saving Potential"2012,
and *1 (calculated with using 5.0GJ/MWh)。
*4: Handbook of Iron and Steel 5th edition, the 1st volume p.322 (2014), *5: Ferrum Vol.3 (1998) No.1, *6: Handbook of Iron and Steel 5th edition, the 6th volume p.216 (2014)
*7: P.Dahlmann, R.Fandrich and H.B.Lüngen: Stahl Eisen, 132(2012), Nr.10, 29
*8: Green Industry Initiative and Promotion of Green Technologies 20120828-Green_Industry.pdf, (UNIDO Seminar, Tokyo (2012))
5
2.2 T H E T E C H N O L O G I E S P O S I T I V E L I ST
We selected here the proposals for energy saving technologies which are effective in applying to the
Vietnamese steel industry by careful study and organization of the energy saving technologies for
EAF steelmaking mainly in Japan, and by comparison with such lists as 'the List of Energy-Saving
Technologies’ which is one of the deliverables from “the Global Warming Mitigation Technology
Promotion Project” so far. The Positive List has been drawn up simultaneously with and is
substantially similar to the Customized List of “the Promotion of ISO14404 (Calculation method of
carbon dioxide (CO2) emission intensity from iron and steel production)” in the FY2014
“Fundamental Projects on International Standardization and Dissemination of Energy Savings (Joint
Research and Development and Promotion of International Standards on Energy Savings)”.
In the following, we explain a basic process for an EAF steel mill, the Positive List in which the
proposals for effective energy saving technologies are listed, and the technologies in the List which
are subject to application examination in this study.
2.2.1 O V E R V I E W O F E L E C T R I C F U R N A C E S T E E L M I L L
EAF steel mill consists of a steelmaking process and a rolling process. In the former process, an
electric arc furnace (EAF) and a ladle furnace (LF) are mainly used for manufacturing semi-finished
products, and in the latter, the semis are converted into finished products.
It can be said that the steelmaking process is a process for manufacturing semi-finished products by
electric furnace steelmaking method. Electric furnace steelmaking method is, different from blast
furnace steelmaking method, basically a batch process method. On the other hand, a rolling process is
a continuous operation process in the same way as that of a blast furnace method.
Figure 2.2-1 shows a flowchart illustrating the process for manufacturing carbon steel products at
EAF steel mill. The flowchart explains the process from raw materials to carbon steel products
through electric furnace steelmaking method. EAF steel mills use recycled scraps (from bridges,
buildings and vehicles, etc.) and/or domestic scraps originated from production plants as raw
materials, while integrated steel mills use iron ore. The domestic generation of scraps is low in
Vietnam, and for most of them Vietnam relies on imports from other advanced steelmaking countries
such as US. In a series of smelting and refining process (electric furnace steelmaking), these steel
scraps are melted in an EAF, impurities are removed and the molten steel is adjusted at given
components and temperature. In the next process, a continuous caster produces a few types of
semi-products (such as billets, blooms and slabs) as source materials for rolling from molten steel.
The semi products are rolled several times at each of rolling mills after reheated at RHF, and so on
and converted into finished products such as rebar, wire rods and flat bars.
6
Scrap
スクラップ Scrap Ladle
炉外精錬 Continuous Semi
鋳片(鋼片)
Scrap
スクラップ スクラップ配合 EAF
電気炉 連続鋳造
yard
ヤード mixing Furnace
(取鍋精錬) Casting Products
半製品
Scrap
電炉工場への Scrap
電気炉へバケットで
スクラップ搬入
Bringing in スクラップを装入
charging
billet
ビレット
bloom
ブルーム
バケット
bucket
Tapping
出 鋼 スラブ
Slab
RHF
加 熱炉 Rolling
圧延機 Mill Major Products
主な製品
Steel Rod棒鋼圧延機
Rolling Mill Rolling Mill Middle
Rough 粗圧延 中間圧延Rolling Mill Finishing
仕上圧延 Rolling Mill
Light
小形棒鋼steel bars
Middle Finishing
線材圧延機
Wire Rolling Mill Rolling Rolling
仕上圧延機 Cooling ステルモア
Cooling
Rough 粗圧延機 Mill
Rolling Mill 中間圧延機 Mill Zone
冷水ゾーン クーリング Wire rod
線材
(NTブロックミル) Conveyor
コンベアー
RHF加熱炉:
: Flat Steel Rolling
平鋼圧延機
1000~1200 deg.C
1000~1200℃ Mill Rough Rolling
粗圧延 Mill Middle Rolling Mill Finishing
中間圧延 仕上圧延Rolling Mill
平鋼
Flat steel
2.2.2 S U P E R I O R E N E R G Y S A V I N G T E C H N O L O G I E S A T EAF S T E E L M I L L S I N J A P A N
In this study, we screen suitable technologies for the Vietnamese steel industry from among the
superior energy saving technologies mainly for the electric furnace steelmaking method and the
reheating method at rolling process in Japan, and select applicable ones for the candidate steelworks
from among the suitable ones.
First of all, we organize and classify Japanese superior energy saving technologies into elemental
technologies.
5
Non- Integrated Steel Producers! Association : http://www.fudenkou.jp/manu_01.html
7
(1) E N E R G Y S A V I N G T E C H N O L O G I E S F O R EAF S T E E L M A K I N G M E T H O D
As mentioned above, EAF steelmaking method is, different from blast furnace steelmaking method,
basically a batch process in which molten steel is tapped every 40 to 80 minutes. The key factors in
energy saving technologies for EAF steelmaking method are improvement of heat transfer efficiency
into scraps and molten steel as well as reduction of thermal radiation from the furnace body. In EAF
process, the early phase is the scrap melting period during which scraps are mainly melted, and the
later phase is the refining period during which the temperature of molten steel is increased and the
component of it is adjusted. Therefore, it is effective to utilize the appropriate technology in response
to each of the operational situations and it is important to properly control the appropriate technology
in accordance with the change of the process.
①Scrap Melting Enhancement Technology during scrap melting period
The scrap melting period is a period during which electrodes are plugged into, strike an arc on, and
melt the scraps charged in the furnace with the large current conducting in. Therefore, it is an
important operation technique to keep on flowing large and stable electrical current.
Regarding the technology for improving scrap melting efficiency, we have the auxiliary heating
burner technology as well as the hardware and software to supply large and stable electric current.
Generally, there is generated what is called “a cold spot” at the scraps in the furnace where electric
current is hard to flow, which causes delay in melting scraps, extension of the melting period and
increase in radiation loss of an arc. A burner for melting enhancement at “a cold spot” is usually
equipped in order to realize enhancement of scrap melting and reduction in radiation loss of an arc.
The burner for EAFs uses an auxiliary fuel such as heating oil, heavy oil and LNG, and supplements
scrap melting with high temperature flames obtained by burning the fuel effectively with enough
oxygen. The burner is set at “a cold spot” and solves the imbalance of partial melting. When the
burner is used during the scrap melting period, higher heat transfer efficiency is attained at “a cold
spot”. Melting period is also shortened by optimizing the position and the utilization of highly
efficient burner, and therefore energy efficiency is increased.
Cold Spot
Scrap
Burner
Oxygen
Fuel
Figure 2.2-2 Image of inside-EAF and burners during scrap melting process
②Radiation Loss Reduction Technology from the end of melting period to refining period
The refining period is a period during which almost all of scraps are melted and the molten steel is
subject to adjustment of its component and temperature for tapping. From the end of the scrap melting
8
period to the refining period, melting of scraps is almost completed, an arc from electrodes exposes in
the furnace, and thermal radiation of the arc often increases.
The slag foaming technology is utilized as a countermeasure against the thermal radiation. The
principle of the technology is explained as follows: carbon particles are blown with oxygen into the
molten slag on the molten metal, CO gas bubbles are generated in the molten slag, the slag foams with
the gas bubbles, electrodes are covered with the foamed slag, the thermal radiation of an arc decreases
and the efficiency of heat into the molten metal is increased. The technology can also enhance the
heat transfer into the molten steel and reduce the thermal radiation to the furnace body because high
temperature atmosphere is created in the furnace due to secondary combustion of CO gas which is
generated by blowing carbons and oxygen (Secondary Combustion Technology).
This requires introduction and installation of the carbon-oxygen blowing equipment, and it is a key
point to design the suitable blowing facilities according to the local situations because the effect will
change depending on the installation site and the number of burners.
Foaming Slag
Arc
Pulverized Coal
Oxygen
Figure 2.2-3 Image of inside-EAF and carbon injection during refining process
Figure 2.2-4 shows the energy saving technologies supporting the electric furnace steelmaking
method in Japan.
9
Figure 2.2-4 Major Energy saving technologies for EAF
Classfied Energy Tehcnologies Title Equipment and system for
Saving Technologies technologies
Scrap melting ① Scrap melting acceleration High efficiency burner, High
technologies technologies efficiency oxygen lance
② Radiation loss reduction High efficiency carbon injection,
technologies during refining High efficiency oxygen lance
process
EAF control system ③ Process control EAF for scrap High efficiency power input control
melting and refining system
Applecation of high ④ Higher Power input ・High efficiency Transformer and
efficiency equipment technologies Reactance technologies
for EAF ・Low impedance conducter arm
Waste recovery ⑤ High temperature scrap Environmental Economical arc
technologies preheater furnace
⑥ Waste heat recovery Waste heat recovery technologies
technologies of EAF from EAF waste gas
Improvement of fuel ⑦ High efficicncy preheater for Regenerative burner or oxygen/fuel
efficiency ladle preheating burner system for ladle preheating
(2) E N E R G Y S A V I N G T E C H N O L O G I E S F O R RHF
Major consumption sources of energy in a rolling process are the fuels at RHF and the electric power
required for rolling. RHF consumes more energy because billets or slabs must be heated to higher
than 1000 deg.C there. We suppose that advanced technologies are not sufficiently applied to fuel
saving at RHF, particularly in Vietnam. Figure 2.2-5 shows the technologies supporting energy
savings at RHFs in Japan.
These energy saving technologies for RHF are expected to be strong candidates applicable for the
10
Vietnamese steel industry, and they are listed in the Positive List as concretely applicable equipment,
in the same way as the technologies for EAF steelmaking method.
In the Positive List, there are listed the feasible technologies applicable for the Vietnamese steel
industry considering those energy saving technologies described above, in reference to the following
documents:
①FY2013 Global Warming Mitigation Technology Promotion Project
”Technologies Customized List & Technologies One by One Sheets (Ver.2)” regarding energy
saving, a deliverable from the report “A Study on Project Development Planning to Disseminate
Energy Saving Technologies in the Iron and Steel Industry in India”
②FY2012 Small and Medium-sized Enterprises Support Survey
“The Current State of the Technologies for Practical Use of Unused Sensible Heat and Waste
Thermal Energy at Electric Furnace Steel Mills (The Results of Questionnaire)”, a deliverable from
the report “Survey on the Actual Conditions of Iron & Steel Industry Regarding the Effective
Utilization of Waste Thermal Energy and the Saving of Energy”
③ The State-of-the-Art Clean Technologies (SOACT) for Steelmaking Handbook (2nd Edition), Dec.
2010, available at http://asiapacificpartnership.org/japanese/soact2nd.aspx.
④Japanese Technologies for Energy Savings/GHG Emissions Reduction, NEDO, 2008 Revised
Edition (hereinafter referred to as NEDO), available at http://www.nedo.go.jp/content/100107259.pdf
⑤Best Available Techniques (BAT) Reference Document for Iron and Steel Production, EU, Latest
Edition, Mar. 2012 (hereinafter referred to as EU-BAT), available at
http://ftp.jrc.es/pub/eippcb/doc/IS_11_17-06-2011.pdf.
⑥Available and Emerging Technologies for Reducing GHG Emissions from the Iron and Steel
Industry, USA-EPA BACT, Latest Edition, Oct. 2010 (hereinafter referred to as EPA-BACT),
available at http://www.epa.gov/nsr/ghgdocs/ironsteel.pdf.
2.2.3 T H E P O S I T I V E L I S T O F E N E R G Y S A V I N G T E C H N O L O G I E S F O R E L E C T R I C
FURNACE STEELMAKING IN VIETNAM
Figure 2.2-6 is the Positive List of the energy saving technologies for steelworks in Vietnam
classified into three categories according to the section 2.1 and the sub-section 2.2.2.
11
Figure2.2-6 Technologies positive list for Vietnam Steel Industry with EAF
The summaries of the energy saving technologies are shown by category in the following. In
addition, we are explaining the technologies reviewed as recommendation in this study.
No.1, 2 are the energy saving technologies by raising the charging temperature of raw materials (DRI,
HBI, scraps) into an EAF.
No.3 is the technology to attain energy saving due to the melting time savings by
high-secondary-voltage (arc elongation) and low-secondary-current operation with
large-capacity transformers.
12
No.4 is the technology to achieve an increase in the effective electric power due to reduction of the
reactance by using aluminum-alloy conductor support arms to support the electrodes on the
secondary side of the power supply.
No.5 is the energy saving technology due to conversion of EAF current from alternating current (AC)
to direct current (DC).
No.6 is the technology to accomplish energy saving due to enhancement of scrap melting by blowing
coke breeze or fossil fuels simultaneously with oxygen. Supersonic injection burners called
coherent burners are used for the technology to improve the heat of combustion of metal and the
cutting of scraps at the cold spot efficiently.
No.7 is called EBT (Eccentric Bottom Tapping), and attains energy saving due to power reduction by
bottom tapping instead of by tilting of the furnace. It also has secondary effects on improvement
of limestone’s and ferroalloys’ yields and savings of tapping time.
No.8 is the equipment to generate steam by sensible heat of EAF exhaust gases, and steam recovery is
expected to reduce fuel consumption.
No.9 is the technology for preheating tapping ladles, and there are two types of burner systems:
9.1 Regenerative burner system: efficient reuse of sensible heat of waste gas generated during
preheating of ladles for heating of combustion air used for the preheating of ladles,
9.2 Oxygen/fuel burner system: rapid heating is possible.
No.10 is the technology of automatic lifting system for electrodes to attain the desired current value
during the scrap melting and it can save the power consumption.
No.11 is the automatic control technology for the optimization of EAF operation and classified into
the four types of systems:
11.1 Automatic following system of preset patterns for power supply
11.2 Automatic operation system using exhaust gas analysis data as an indicator
11.3 Automatic assessment system for the optimization of melt-down period according to acoustic
sound and higher harmonic waves generated in the furnace in order to reduce the power
consumption rate
11.4:Fuzzy logic control system for electrodes due to multivariate analysis.
No.12 is the technology of carbon-oxygen injection for foaming slag in order to improve the thermal
efficiency by covering an arc with the foamed slag.
Among the technologies described above, we select the following three technologies as what should
be introduced according to this study and describe their details below:
・ No.6 Oxy-fuel Burners/Lancing (together with enough capacity of Direct Suction Type
Dust Collector)
・ No.11 .4 Control and Automation for EAF Optimization:Optimum Regulation System
with multi-variable control using Fuzzy logic
・ No.9.2 Ladle Preheating: Oxygen/fuel burner Total system
13
“No.6 Oxy-fuel Burners/Lancing (together with enough capacity of Direct Suction Type
Dust Collector)”
Figure 2.2-7 is the photograph of “Oxy-fuel Burners/Lancing (or Supersonic Burner)”.
Effective length〜2m
length〜2m
The effect of the door burner is described as follows: Generally, EAF has an opening for discharging
slag (de-slagging) in the furnace, and the de-slagging is carried out through this opening during the
refining period. The slag opening is equipped with a slag door as the air outside can intrude into the
14
furnace through it. Therefore, the slag door is closed during the scrap melting period in order to
prevent the outside air from infiltrating into the furnace. It is a key factor for progressing energy
savings to prevent the furnace from being cooled due to the air infiltration. On the other hand, it is
often the case that a burner/lance is equipped at the slag opening because there is no appropriate
position for setting up the burners/lances. That causes heat loss due to the lower temperature in the
furnace as the slag door must be open even during the scrap melting period and the air outside can be
easily absorbed in the furnace. The door burner is the technology for solving these problems. It
enables the utilization of burners/lances with the slag door closed and fuels/oxygen gas can be
efficiently supplied. Therefore, this effect can reduce in the power consumptions and the operation
hours.
The Oxy-fuel Burner/Lancing can be used not only as a burner with auxiliary fuel during the scrap
melting period, but also as a carbon injection facility for slag foaming at the end of the scrap melting
period and during the oxidizing period.
Figure 2.2-9 shows an integrated burner system equipped with a door burner which consists of all
as described above.
However, the application of this Oxy-fuel Burners/Lancing technology requires careful attention to
the following points:
・ Sufficient precipitation capacity is necessary for collecting gas and dust in the EAF, the lack of
collecting capacity causes energy loss because energy source like gas goes outside of the furnace.
・ it is possible to reduce the power consumption rate, nevertheless it requires auxiliary fuels for
scrap melting, Therefore, the reduction in power consumption does not often lead directly to
energy saving. We need to estimate the total reductions in energy savings and CO2 emissions
after due consideration of the auxiliary fuel consumptions.
15
An EAF is a batch process and there are many factors for controlling it. The control of electrodes is
one of the most important ones. In particular during the scrap melting period, it is necessary to
optimally control the position of electrodes and the input of electric power, and to give more electric
current efficiently to scraps because they collapse, fall and move as they melt. We can achieve more
efficient melting of scraps by properly controlling the electrodes.
Efficient input of electric power can be attained by the application of the new Power Regulation
System to controlling the electrodes. Figure 2.2-10 shows an overview of the Optimal Power
Regulation System.
Identification of
the
Mechanical Mast Position DIGITAL
system SIGNAL
PROCESSOR
SETPOINT CARD
I:Current
RA:Arc Resistance
Z:Impedance
VA: Arc Voltage
CORRECTION OF PI
PARAMETER BY
FUZZY LOGIC
VOLTAGE
MEASUREMENT
CURRENT
I:Current
ACTIVE POWER
RA:Arc Resistance
Z:Impedance
VA: Arc Voltage
Control Strategy PLC PROCESS
by INFORMATION
Fuzzy logic
Usually, the positions of electrodes are controlled by considering only the impedance. However, in
this system, we consider many factors such as electric currents, power voltages, arc resistances, input
electric powers in order to control the electrodes appropriately according to Fuzzy Logic. More input
of electric power can be achieved by the proper control of electrodes.
The principle is derived from Fig. 2.2-11 showing the relation between the power and the current of
the arc and the input side circuit, and the power factor of the arc current at an identical voltage. As
electric current increases (up to some 50 kA), the power factor is lowered but the input power
increases. Therefore we can put the power into the arc more efficiently by increasing the arc current.
16
Tap/630 V Power Curve
Figure 2.2-11 Arcing power, Circuit input, and Phase factor at same input voltage 6
When this control technology is applied, it is necessary to review not only the renewal of control
system but also the controllability of the hardware related to electrode control.
17
Conventional Air Combustion Oxygen Combustion
Gas volume
25%
A conventional burner generates the flame by combustion of fuels with the air to preheat a ladle. On
the other hand, the oxygen/fuel burner is supplied with nitrogen-free oxygen instead of air for
combustion (the Figure shows the case using 100% of oxygen), and the amount of waste gas is
reduced to about 25% after combustion. Therefore, the flame temperature becomes higher and high
efficiency preheating is attainable due to the increase in heat transfer efficiency, the reduction in
waste gas amount and the reduction in sensible heat of waste gases.
Figure 2.2-13 shows a comparison of the temperature changes in the ladle preheated with a
conventional burner and the oxygen/fuel burner, while both of them use natural gas as a fuel.
1600
1400
1000
Difference heating capability
800
600
0
0 50 100 150 200 250 300
Heating Time (min)
Figure 2.2-13 Comparison of Ladle inside temperature between conventional burner and
oxygen/fuel burner 7
In Fig. 2.2-13, blue lines indicate the temperature changes by a conventional burner, red lines by the
oxygen/fuel burner, and the two lines in each color indicate the inside surface temperature and the
18
outer shell temperature, respectively. Figure 2.2-13 shows that the flame temperature rises faster by
the use of the oxygen/fuel burner, and that it is possible to preheat the ladle in a shorter period.
Therefore, large energy saving can be achieved due to improvement of heat transfer efficiency and
shortened period of preheating according to the higher flame temperature.
However, we have to take heed of the oxygen usage in this technology. The technology needs the
supply of oxygen as a matter of course. At a steel mill which holds its in-house oxygen plant and is
capable to produce and supply oxygen, economic effects can be easily realized because the usage cost
of oxygen is lower than the benefits from the energy saving. On the other hand, some EAF plants
purchase liquid oxygen and utilize the vaporized oxygen. In this case, the application of this
technology may not be economically possible because the cost of liquid oxygen is generally high and
the economic effect becomes smaller.
No.13 is the energy saving technology effective in preheating combustion air at RHF, and there are
three types of the technologies according to the desired temperature level of preheating air (Tair):
13.1 Integrated System for Regenerative Burner: suitable for Tair is higher than 1000 ℃(the
principle is the same as No.9-1),
13.2 Heat Exchanger using Cr-Si-Al heat resistant steel: suitable for Tair is around 600 ℃,
13.3 Commonly used Heat Exchanger suitable for Tair is around 400 ℃.
No.14 is the technology for reducing fuel consumption rate due to the reduction of heat loss through
the furnace walls by utilizing ceramic fibers with low thermal conductivity and high adiabaticity
for inside wall materials of the furnace.
No.15 is the technology for reducing the fuel consumption of RHF due to the introduction of
combustion control system for RHF. The system enables us to attain optimal combustion in
accordance with the heating conditions (such as heat pattern control, oxygen content control in
waste gas, and furnace pressure control, and so on).
No.16 is the technology for reutilizing heat of combustion waste gas from RHF which is used for
supplying hot water for cooling air with an absorption refrigerator.
“No.13.1 – Integrated System for Regenerative Burner at Preheating temperature ≧1000 ℃”
is the technology which is well known as regenerative burner system, and developed and commonly
used in Japan. It is also the technology which is recommended in this study, and the details are
described below:
19
combustion air.
Figure 2.2-14 Relation between preheated air temperature and fuel saving (in case of furnace
temperature 1350 deg.C)8
An usually equipped heat exchanger preheats air to a temperature of around 400 ℃ as shown in
Fit.2.2-14. On the other hand, the heat exchanger with high thermostability can preheat air up to a
temperature of 650 ℃. Furthermore, the regenerative burner used in this technology can preheat air
to a temperature close to that of the furnace temperature and large energy saving can be achieved.
When the furnace temperature is 1350 ℃ as shown in Fig. 2.2-14, we can save some 30% of the
energy consumption by the regenerative burner compared to an usual heat exchanger, and some 15%
compared to even a heat-resistant one. However, the reduction of energy consumption changes
depending on the furnace temperature, and we can replace not all the burners but just the ones
subjected to higher combustion load into regenerative burners from the economical point of view.
Therefore, we need to estimate the energy savings as well as the profitability for each of the cases.
Figure 2.2-15 shows an overview of the regenerative burner system.
Fuel Fuel
Burner B Burner A
1350℃
1350℃
Ceramic
Ceramic Billets
Billets 1250℃
1250℃ Regenerator
Regenerator B A
Exhaust gas
Switch valve 200 deg.C
Air
20
A regenerative burner has a structure in combination of a combustion unit (burner) with a thermal
storage unit (regenerator), and the burners are basically used in pairs.
While one burner (Burner B in the figure) is working with fuel and air having passed through the
ceramic regenerator B, the exhaust gas is induced to the ceramic regenerator A on the other side
(Burner A in the figure) and its sensible heat is stored there. After heat storage is completed at the
ceramic regenerator A, the burner A is switched to combustion and the ceramic regenerator B is
switched to heat storage. By this operation, the combustion air is always heated passing through the
regenerator and kept at a high temperature (that is, the waste heat is recovered).
The regenerative burner system can recover around 85% of waste heat, and the application of the
system is promoted widely in Japan not only to heating furnaces and heat treatment furnaces for steel
products, but also to ladle drying, aluminum melting furnaces, gas treatment, and so on.
The minimum unit of application is one pair (two burners) to RHF but several pairs are usually
equipped to a furnace. The application to RHF has the following merits besides high thermal
efficiency:
・ the maximum local flame temperature is possible to be lowered due to forced gas circulation in the
furnace and the NOx concentration decreases,
・ the average temperature in the furnace is possible to be raised and the operation of higher
productivity and flexibility can be achieved,
・ homogeneous distribution of temperature can be attained in the furnace due to alternate combustion
and forced gas circulation in the furnace,
・ zone heat control becomes easy as gas flow is small in the direction of a furnace length,
・ fluctuation or variation of excess air ratio does not affect much on the thermal efficiency, and so
on.
In addition to them, a regenerative burner can be applied not just to a new RHF, but to an existing
one by revamping it.
No.17 is the inverter control technology for changing the rotation speed of an electric motor such as a
fan and a pump, and saves electric power by controlling some kinds of flow rates, pumping head
and damper opening in accordance with the EAF operation.
No.18 is the supervisory and management control system for the optimization of energy consumption
in EAF steel mill, and is utilized to avoid overall energy loss of the whole steel mill.
The applicable positions for each of the energy saving technologies, No.1 – 18, as mentioned above
are illustrated with the indication by the numbers in Fig. 2.2-16 of the process of EAF steel mill.
The quantitative effects on the energy savings and CO2 emissions reduction by these technologies
are rearranged in Fig. 2.2-18. In the figure, the following data are used for the conversion of electric
power saving and heat saving into CO2 emissions.
21
Figure 2.2-17 CO2 Emission Factor
CO2 Remarks
IEA statistics, 2013 edition
Emission Vietnam world
(average of '09-'11) *3
Factor *2
Vietnam India Japan
t-CO2/MWh 0.564 *1 0.415 0.904 0.444 0.504
t-CO2/GJ 0.095 *2 0.095
*1 http://pub.iges.or.jp/modules/envirolib/view.php?docid=2137
(20141031_iges_er_sheet_gridef_JP.xls)
*2 Data collection user guide_v6. - World Steel Association
*3 CO2 Emissions from Fuel Combustion Highlights (2013 Edition), IEA
22
Figure 2.2-16 Technologies positive list for steel making plant with EAF
(The number of each title corresponds to the number of Figure 2.2-6)
23
Figure 2.2-18 Presumed effect (power saving, CO2 reduction) of each technology from Technologies positive list
Effect of Technologies Introduction Technologies Reference
Energy Savings
Miscellaneous
CO2
EPA-BACT
India TCL
EU-BAT
SOACT
No. Title of Technology
NEDO
Reduction (Fuel)
ver.2
Co-benefits
kg-CO2/t GJ/t kWh/t
of product of product of product
Steelmaking
1 Hot DRI/HBI Charging to the EAF 84.6 >150 ○
2 Scrap Preheating (ex. Ecological and Economical Arc Furnace) 84.6 150 1. reduction of DXN, Dust, Noise ○
3 Transformer efficiency—ultra-high power transformers 8.5 15 ○
4 Aluminium Alloy Conductor Arm for Supporting Electrode 1.6~3.3 3~6 *1
≦5% 1.electrode consumption -(40-60)%
5 DC Electro Arc Furnace 5~10.1 ○ ○
9~18 2. reduction of flicker -(50-60)%, noise
6 Oxy-fuel Burners/Lancing (together with enough capacity of direct suction type dust collector) 10.1~20.2 0.14 18~36 ○ ○
13.6 1. 15-25% reduction of CaO(kg/t)
7 Eccentric Bottom Tapping (EBT) on existing furnace 3.9~14 ○
(7~25) 2. shorter tap-to-tap times
8 Waste Heat Recovery from EAF 81.7 0.86 ○
9 Ladle Preheating
9.1 -Regenerative Burner Total System 20.0 0.21 or 51% ○
9.2 -Oxygen/fuel Burner Total System ≧50% 1. life extension of refractory *2
1. electrode consumption -25%
10 Electrode Position Control for Power Optimization 10.4~16.9 0.11 30 ○ ○
2. Productivity: +(9-12)%
11 Control and Automation for EAF Optimization
11.1 - by pattern presetting
11.2 - by using Off-gas Analysis 19.7 35 ○ ○ *3
11.3 - Automatic Scrap Meltdown Timing Judgment System by Acoustic Spectrum Analysis for AC EAF 1.6~3.3 3-6 1. skill free *4
11.4 - Optimum Regulation System with multi-variable control using Fuzzy logic 10 *6
0.04~0.05
12 Carbon and Oxygen Injection System for foamy slag practice 2.8~3.9 5~7 ○ ○
or 2.5~3%
Reheating Furnace
13 Combustion Air Preheating for reheating furnace
45%(S),
13.1 - Preheating temperature ≧1000℃ by Regenerative Burner Total System 16.1~19.9 1. reduction of NOx ○ ○ ○
0.17-0.21(N)
13.2 - Preheating temperature 600℃ by Recuperator using high heat resistance steel 10.7~13.3 30% ○
20% (S)
13.3 - Preheating temperature 400℃ by Recuperator 7.1~8.8 ○ ○
0.7(E)
14 Thermal insulation by Ceramic Fiber on inner wall of reheating furnace 15.2 2-5%, 0.16 ○ ○
15 Process Control for Reheating Furnace 19.9~79.8 0.21~0.84 ○
16 Air Conditioning by Hot Water Absorption Chiller utilizing Waste Heat 1.5 2.6 *5
Miscellaneous
17 Inverter (VVVF; Variable Voltage Variable Frequency) Drive for Motors 42% ○ ○ ○ ○
18 Energy Monitoring and Management Systems for Steel Plant with EAF 0.5% ○ ○ ○
Remarks;
*1: NIKKO Industry CO.,LTD, and "Tekko-Binran" (Handbook of Iron and Steel) Vol.5, No.6, p.224
*2: CHUGAI RO Industry CO.,LTD, and http://www.klchem.co.jp/blog/2013/08/post_2094.php
*3: Iron Steel Technol Conf Proc, vol.1, 2006, pp.509-518
*4: Daido Steel
*5: estimated by JFE Techno-Research Corp. from data supplied from EBARA Refri. Equip. & Systems Co., Ltd.
*6: NIKKO Industry CO.,LTD
24
3. T HE R EVIEWS ON THE S PECIFIC P ROJECT P LANNING FOR
C OMMERCIALIZATION
Upon commencement of the field surveys, we requested the government of Vietnam (Heavy
Industry Dept., Ministry of Industry and Trade (hereinafter referred to as MOIT) to select the
steelworks which are willing to accept the study of the project on energy diagnosis and technology
introduction to EAF mills in Vietnam, and two companies were the candidates. Both of the companies
desired to receive energy diagnosis and study of the project, and we finally determined field surveys
on both of the companies. Hereinafter, the companies are referred to as A-Company and B-Company,
respectively.
These 2 companies locate in the north area in Vietnam. One is a steelworks with its long history, the
other is a comparatively new one which was established after 2000, and then they are contrast
steelworks to each other.
In surveying both the companies, we implemented field surveys and presentations according to the
schedule below:
1st visit (Sep. 2014), Preliminary field surveys on both EAF steelworks
Contents: Presentation of the project purpose (including introduction of JCM scheme),
Understanding of the actual conditions (plant tours and operation observations)
Discussion of the issues on energy, and refinement of applicable technology
2nd visit (Nov. 2014), Technical study of both EAF steelworks
Contents: Energy diagnoses of the electric furnaces and the RHF
Diagnoses of each of the processes on energy saving, and study of feasibilities of the
technology
Collection and estimation of data to evaluate energy saving
3rd Visit (Jan. 2015): Seminar
Presentation of the diagnosis results, the estimation of profitability for each technology,
and explanation of JCM
As for both of the EAF steelworks in Vietnam, we refined the equipment and the technology
applicable to them through actual condition surveys on the steelworks, and discussions with the
officers of the steelworks during our 1st visit. During the 2nd visit, we practically implemented
surveys and diagnoses, and during the 3rd visit, we held a seminar to present the results from the
surveys and the diagnoses and to focus on the profitability of the application of the technologies.
During the 2nd visit and diagnosis, we were accompanied by people from engineering firms
specializing in EAFs and RHFs in iron and steel making process, they also implemented diagnosis
and study based on applicability of the technologies to estimate the cost for the applicable
technologies and to do trial calculations of the merits together with us.
25
During the 1st and 2nd visits, we also explained to the relevant ministries and agencies to JCM in
Vietnam, the contents and activities of the project, and the details of JCM, which will be described
late in Chapter 5.
The contents of these three times of visits are described below.
26
3.1 T H E R E V I E W ON THE SPECIFIC PROJECT PLANNING FOR A-C O M P A N Y
To A-Company, the 1st and 2nd visits were made by the members and on the schedule shown in Fig.
3.1-1.
3.1.1 O V E R V I E W OF A-C O M P AN Y
Figure 3.1-2 shows an overview of A-Company steelworks.
Main Facilities
Blast Furnaces,
Sintering Plant,
Coke Making Sinter Cokes ovens
BF
27
A-Company is a steelworks holding blast furnaces and coke ovens along the river, and behind them
an extensive site on which sintering furnaces and an electric furnace plant stand.
Its steelmaking process is an electric furnace one, and both scraps and hot metal from the blast
furnace are its iron sources. There are two units of EAFs as steelmaking equipment and two lines of
RHF and a rolling machine as rolling equipment in the plant, and the steelworks holds coke ovens,
sintering furnaces and blast furnaces in its upstream process. The steelworks is characterized by its
operation at the EAFs, where about a half of the iron source is hot metal from the blast furnaces and
the remainder relies on scraps.
The steelmaking plant holds two units of EAFs, the large scale No.2 EAF mainly produces molten
steel. Both of them are made in Chine and considerably old facilities.
Molten steel is treated at a ladle furnace (LF) and it is cast at a 4-strand continuous casting machine.
The cast products are transferred into RHF. There are two units of RHFs, one is the old and
Chinese-made No.1 RHF, and the other is the No.2 RHF which commenced operation in 1996.
A-Company intends that billets are supplied to No.2 RHF by hot charging from the steelmaking plant.
About 80 - 85% of the billets are supplied to the RHF at a temperature of 500 - 600℃, and the hot
charging is put into good practice (hot charging is not in operation at No.1 RHF).
Oil (Fuel Oil, F.O) is used as a fuel for both of No.1 and No.2 RHFs, however, we could not confirm
any information on type and property of the oil. No.1 RHF is a Chinese-made and old facility;
nevertheless, it is maintained sufficiently and kept in good condition. No.2 RHF is also kept up in
good condition.
This rolling process produces steel bars as finished products, which are shipped.
Meanwhile, the steelworks plans on expanding its annual production to about 1 million tons per year
in the future. The steelworks currently holds two blast furnaces, and a new blast furnace is under
construction. In line with this, the steelworks plans to construct a steelmaking plant as well as a
sintering plant and a coke oven. In addition, construction of new RHF is almost completed. It seems
that the steelworks enters a period of transition to some kind of integrated steelworks.
28
・ RHF capacity: 50 ton/h (walking hearth type)
・ Hot charging ratio: 80 – 85% (at an assumed temperature of 500 – 600℃)
・ Fuel: Oil (details unknown)
・ Fuel consumption rate: 24 l/t-steel (210,000 kcal/t-steel, when hot charged)
31 l/t-steel (273,000 kcal/t-steel, when cold charged)
Where the energy conversion factor is assumed as 8,800 kcal/l, supposing that Oil is fuel oil
A (JIS K2205 Class).
・ Furnace temperature: 1150℃
It is a very conventional RHF, however, the fuel consumption rate is lower compared to an average
RHF because of its intention of hot charging.
On the 1st visit, we presented the technology in Japan, took a tour of the whole steelworks, and had a
discussion focused on issues A-Company has with energy saving.
Based on the discussion with officials of A-Company and the current situations witnessed through
plant tour, following technologies are the issues for study of the technologies.
(1) Study of energy saving technologies for EAF:
oxygen lances, burners, coal injection, and reduction in electric power consumption rate by
application of the technologies such as the optimal control for an EAF.
(2) Study of fuel consumption reduction for RHF:
diagnosis of the current operation and reduction in fuel usage by introduction of the
regenerative burners.
29
(3) Utilization of gases in the whole steelworks:
gas balancing in the whole steelworks and effective utilization of B gas.
Based on the premise of study of the above items, we implemented surveys and study, and specified
technologies to introduce on the 2nd visit. The above item (3) is not likely linked to a practical project
at this moment. However, we considered it subject to the study because it is important to save energy
at the steelworks in future.
(1) S T U D Y O F E N E R G Y S A V I N G T E C H N O L O G I E S F O R T H E EAF:
On the study of technologies, we followed through such steps as witnessing the operation at the plant,
identifying issues, and studying appropriate technologies to introduce. We show the approximate
merits by introduction of the technologies below; nevertheless, further study in detail is required.
30
③ Timing of Hot
SC① 10t SC③ 5t
metal charge
HM 20t SC② 10t
Tap V(V)
509V 509V Charge: SC 25t,HM 20t
500
⇒Tap:42t
Power consumption: 241kWh/t
Oxygen consumption:55Nm3/t
450
442V ② Tap change
442V 442V
428V
400
Time (min) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62
Total (kWh) 600 4511 7093 8244 10142
Oxygen PON Tap
16min
Cutting Tap change De-C Tap change Decarburization Tap change
① Oxygen supply
31
Figure 3.1-6 Current fluctuation of each electrode
Finding 3: As shown as "③Timing of Hot metal charge" in Fig. 3.1-5, hot metal is charged just after
charging of scraps, which may cause to solidify the charged hot metal.
Finding 4: As shown in Fig. 3.1-4, flames are blown out of the furnace throughout the whole period of
operation. This leads to the loss of energy, causes damage to the peripheral equipment, and worsens
the surrounding work environment.
Based on the above issues, we recommend the introduction of appropriate technologies.
③ Recommended improvement
The Finding 1, 4 require a common measure to solve.
As for the facility concerning the Finding 4, first we confirmed that the EAF is not equipped with
any precipitator called “Dust Collector” which is indicated in Fig. 3.1-7 by the eclipse in red and is
usually installed on EAF. Therefore, flammable materials generated in the furnace are all emitted out
of the furnace, and they are to be collected into the dust collector equipped onto the ceiling over the
top of the EAF.
Suction
Dust
collector
Slag Door
Consequently, the pressure is always positive in the furnace, such materials as gas and dust that are
generated in the furnace will be all emitted out of the furnace, and they are to react with the air to
32
undergo combustion. In this case, there are the following points at issue:
・ Loss of energy is caused due to the combustion outside the furnace, of non-reacting materials in
the furnace.
・ Repairs cost will increase because of greater deterioration of the peripheral equipment such as a
furnace lid, electrode holders, and so on, due to the outside combustion.
・ Building dust collector can not sufficiently collect such materials as dust that is generated in the
furnace, which leads to worsening the surrounding environment.
Considering the above issues, we conclude that installation of the “Dust Collector” is the first and
direct measure to energy saving and environmental improvement.
Meanwhile, as for the Finding 1, because hot metal (usually including more than 4 % of carbon) is
used for the operation of the EAF, oxygen is required to lower the carbon content in the hot metal;
nevertheless, the sole source of oxygen supply is currently the oxygen from the oxygen lance which is
inserted through the slag opening. There is no “Dust Collector”, which causes the loss of energy; the
scrap melting rate is limited by the rate of oxygen supply and the power consumption rate will be
worsened by the elongation of operation period.
The measures to the above are as follows:、
・ Installing a “Dust Collector” with a sufficient capacity,
・ Progressing in promotion of scrap melting and positive supply of oxygen
As for the latter regarding oxygen supply, we can recommend application of the technology, “No.6
Oxy-fuel Burners/Lancing (in combination with direct-suction-type Dust Collector with
sufficient capacity)” in the Positive List. Furthermore, the energy efficiency can be more improved
by adoption of a door burner which is one of the associated technologies for the Oxy-fuel
Burners/Lancing technology.
Currently, oxygen is supplied into the melt in the EAF only by the lance at slag opening. By
installation of Oxy-fuel Burners/Lancing in combination with a door burner, it is possible to prevent
the furnace from infiltration of outside air and to supply oxygen efficiently. Therefore, the technology
can attain power saving and shorter operation time.
As mentioned above, we can recommend application of “Oxy-fuel Burner System + Introduction of
Direct Suction Type Dust Collector” technology to solve the Finding 1. In such a case, we expect that
the power consumption rate can be reduced by 25kwh/ ton-steel.
However, as stated above, an auxiliary fuel is required to use a burner. The auxiliary fuel can be
considered to rely on the C gas which is generated out of the coke ovens and is excessive in the
steelworks. As the steelmaking process utilizes hot metal, any burning function is required only at the
beginning of the scrap melting period, and therefore it requires an equivalent amount of an auxiliary
fuel to 5 Nm3/t-steel of natural gas. When C gas is used, the required amount is 11.1 Nm3/t-steel.
From the viewpoint of CO2 emissions reduction, if we can confirm that necessary and sufficient C
gas is currently emitted to the air for the EAF to require, there is no more cost of C gas and no more
emissions of CO2, however, the more study will be necessary to make it clear in future.
As for the Finding 2, it is necessary for the control system to improve. As a measure to it, we can
33
recommend application of “No.11 Control and Automation for EAF Optimization” in the
Technologies Positive List. Renewal of the control system enables us to change the voltage setting
without turning off the electric power. In addition, the new “Optimal Power Regulation System”
mentioned above enables us to efficiently input the electric power. The estimated power saving will
be 10 kWh/t-steel by adoption of these systems.
Finally, as for the Finding 3, it is the point at issue that hot metal is charged just after scraps are
charged and they are cut with an oxygen jet. As shown in Fig. 3.1-8 which is the iron carbon (Fe-C)
binary phase diagram, when hot metal includes about 4% of carbon, its solidification point is 1147℃.
When hot metal is charged into a furnace which has been already charged with scraps, the hot metal is
cooled by the scraps in the furnace and it may be solidified. Therefore, a desirable operation shall be
as follows: Charge scraps into the furnace. Melt the scraps. Bore the scraps. Charge hot metal into the
furnace after scrap is bored. By prevention of hot metal from solidifying in the furnace, it leads to
avoiding electrode breakage and hot metal splash.
Fe-C diagram
[C] = 4%
1147℃
34
Figure 3.1-9 Effect for proposed technologies to A-Company EAF
Electric Power
Items Effect Saving
kWh/t-steel
Electric Power Saving
Oxy-fuel Burner System Other merit
+ 1. Increase of productivity 15
Introduction of Direct 2. Saving of Operational expenses 15% +
Suction Type Dust (Electricity / Electrode / Refractory / 10
Collector Alloy / etc.)
3. Improvement of Environment & Safety
Electrode Regulation Electric Power Saving
and Automation Control Other merit 10
for EAF Optimization 1. Increase of productivity
total 35
(2) S T U D Y O F F U E L C O N S U M P T I O N R E D U C T I O N F O R T H E RHF:
On the study of technologies, we witnessed the operation at the plant, identified issues, diagnosed
the RHF and studied appropriate technologies to introduce. The observation was conducted only of
the No.2 RHF.
35
Figure 3.1-11 Operation condition at the observation
We found that some data are not indicated on the monitor as shown in Fig. 3.1-11. Troubles of
instruments were the main cause of this problem. We consider it important to promote operational
control by grasping the accurate values in future.
Hot charging was in practice during the observation, the furnace temperature averaged 1150℃ and
the production rate was 43 t-steel/h. We could not obtain the actual usage of “Oil” and the calorific
value of it, and then it was impossible for us to estimate the fuel consumption rate exactly.
As stated above, hot charging was conducted during the witness, which is of high value. The
charging billets were faintly lit, and the temperature was supposed to be 500 – 600℃. It seemed that
the furnace is well insulated and we can suppose that the furnace refractory is in good condition.
② Issues on the operation
On witnessing the operation, we were also requested to diagnose the temperature of preheated air
which is some 350℃ in spite of the specified value of 400℃. Therefore we conducted the study
taking it into account.
However, as noted above, there are a lot of inaccessible operational values. It is important to
organize these values (including maintenance of measuring equipment) and to control them in order
to promote operational control in future.
The following findings are identified through the observation of the furnace and its associated
equipment.
Finding 1: Inspection of the heat exchanger
Finding 2: Air fuel ratio (Air/Fuel) appropriate control
Finding 3: Furnace pressure appropriate control
However, these findings were checked just visually, and it is necessary to confirm and correct them
through inspections, and so on in future.
36
Finding 4: Study of applying regenerative burners.
As for fuel reduction, we estimated introduction of ” No.13.1 – Integrated System for
Regenerative Burner at Preheating temperature ≧1000 ℃” in the Positive List, so-called
regenerative burners. However, we noted that it is necessary in installation of regenerative burners to
plan for revamping the facilities in consideration of utilizing surplus gas at the time of the capacity
extension in the future.
Summarizing the above issues, the Finding 1 to 3 is on improvement of the operations and the
Finding 4 is on study of new technology application.
③ Recommended improvement
As for the issue 1, we studied the heat exchangers focusing on insufficient preheating of air. There
was found such a point as shown in Fig. 3.1-12, and we proposed the necessity of inspection. First of
all, there is a possibility of waste gas leakage because we observed smoke emission from the top of
the heat exchanger. Second, the inlet temperature of the waste gas is low (suspicious of any leakage
of waste gas, and so on). Finally, it is necessary to check the leakage through bypass damper of
combustion air.
Leakage inside ?
Leakage in duct ?
Bypass damper
37
usage because we observed the condition of combustion in the furnace changing with the alternation
of furnace load during the operation. In addition, we also presumed it because the fuel usage is not
indicated. If the flow rate of air is excessive, the flow rate of waste gas increases and the heat loss of
waste gas increases. On the contrary, when it is deficient, incomplete combustion of fuel causes the
loss of energy.
As for the Finding 3, although the furnace pressure is indicated, it is not controlled at all. We also
observed blow off of gas out of and suction of it into the furnace. The blow off of gas leads to the loss
of heat, and the suction of it cools the furnace and also leads to the loss of energy.
Our recommendation on the Finding 1-3 is all the improvement of the current operation. First of all,
it is required to maintain measuring equipment (sensors) and preserve the control functions with
accurate measuring apparatus as premised. Moreover, as we recommended, measured result during
operation should be recorded accurately and managed exactly, and after that it is necessary to advance
to the step of building an energy management system in order to keep operation in normal condition.
As for the Finding 4 on introduction of regenerative burners, we recommended the two ways of
replacement of the burners, the full replacement and the partial replacement, considering the furnace
layout as shown below, operation, and so on, as well as from an economical point of view. Figure
3.1-14 illustrates a schematic drawing for partial replacement of burners.
Zone3 & 4
Burner : 10
The furnace currently consists of the preheating zone 1 (equipped with 2 burners), the heating zone 2
(with 4 burners) and soaking zones 3 & 4 (with 5 burners, respectively) (as indicated in blue in the
figure). The plan of partial burner replacement suggests that a total of 6 burners at the preheating zone
and the heating zone will be replaced by 2 pairs of regenerative burners (as indicated in red). At the
same time, the new burners will be increased in capacity. The soaking zone will be untouched. The
plan aims at enhancement of energy saving effects by supplying more fuel through large-sized
regenerative burners.
Figure 3.1-15 shows the comparison of effects obtained by the full replacement and the partial one.
38
Figure 3.1-15 Comparison of effect for all burner replacement and partial burner replacement
Large effect will be obtained by the full replacement of burners because among the four zones, the
most burners are equipped in the soaking zone which will be also revamped in this case. However, the
investment cost will increase much more, and it is necessary to study the application considering its
profitability. In addition, there remains a room for more precise study of merits because we have
much lack of data for study.
Meanwhile, we studied gas balance associated with the capacity augmentation of A-Company in the
future.
When the expansion is completed, more by-product will be generated and some of the surplus gas
can be utilized as fuel in the RHF. “Oil” is currently used at the RHF, however, large energy saving
can be achieved by utilizing the surplus gas. We studied the gas balance in the whole steelworks and
the feasibility of surplus gas utilization to RHF. The result is described below.
④ Utilization of gases in the whole steelworks
On studying the gas balance, we obtained those data first. In addition, we also used various empirical
values for the estimation because we could not receive enough data on the generation or usage of
by-product gases in the steelworks.
Figure 3.1-16 shows the current gas balance and the future one after theaugmentation.
1,400,000 1,400,000
1,200,000 1,200,000
0 0
Production
Consumption
Production
Consumption
Consumption
Production
Consumption
Production
Consumption
Consumption
BFG
COG
BFG
COG
BFG
COG
BFG
COG
OIL
OIL
Figure 3.1-16 presumed results of present gas balance and future gas balance after augmentation
Each of the abscissas indicates from the left side, the generation of C gas from the coke ovens, the
consumption of C gas, the generation of B gas from the blast furnaces, the consumption of B gas, and
39
the usage of Oil by the RHF at the right end. The figure on the left hand side shows the estimations of
the current gas balance, and the one on the right hand side shows those of the gas balance after the
augmentation.
In addition, Fig. 3.1-7 shows the property of B gas and C gas used for the above estimations.
B gas is considerably excessive at the current gas balance, while C gas is not very much excessive.
After the augmentation, the excess of B gas will be remarkably increased, and C gas will become
some excessive. The usage of Oil will be also increased due to the augmentation. It seems possible to
change the RHF fuel “Oil” to surplus gas because B gas is more excessive calorimetrically. However,
it will be impossible to operate the RHF only with B gas, because 2,000 to 2,500 kcal/Nm3 of the gas
is necessary for securing the furnace temperature and calorie of B gas is as low as around 750
kcal/m3N. Therefore, the RHF will require 2,000 to 2,500 kcal/m3N of M gas which is made by
mixing B gas with C gas. It is because C gas has a calorie of around 4,500 kcal/m3N. The calorie
content of C gas should be higher than 75% in M gas in order that the calorific value of M gas
becomes higher than 2,000 kcal/m3N. If the production is extended in the same condition as of now, it
is presumed possible to change a part of the furnace fuel, however difficult to change all of the
furnace fuel because the excess of C gas will not reach 75% of Oil usage by the RHF.
On the other hand, the steelworks holds the processes of an integrated steelworks including a blast
furnace and a coke oven; therefore, there is a room in such other facilities for introducing energy
saving equipment, which may bring out more C gas than planned augmentation.
Figure 3.1-18 shows typical energy saving technologies at an integrated steelworks.
9
World Encyclopedia 2nd edition
40
:Considered technologies
Power・Slag
: other energy saving technologies
・Efficient power generation
Energy: power station, utility supply ・Efficient air separator
・Energy audit
Coke Blast ・Power saving
Oven Power Furnace BOF
Gas Steam Gas Gas
By-product Gas
Power, Air, Steam, etc.
・Combustion
Control
(Δ15%)
Coke Making
Furnace rolling
・CDQ
BF BOF Rolling mills
・High efficiency
ignition burner
・BOF gas recovery
(Δ50%)
Sinter Hot Stove OG ・Regenerative
•Combustion Control burner
•Heat Exchanger (Δ15%)
・Off gas boiler
・Product cooler •TRT
(Δ15%)
heat recovery
Figure 3.1-18 Major energy saving technologies for integrated steel plant
Figure 3.1-19 shows the future gas balance after the augmentation with the application of the
technologies which are relatively easy to introduce (as indicated in red letters within a red frame
together with its energy saving ratio) among these technologies.
1,400,000
LDG
1,200,000
Residual
1,000,000 Steam Boiler
Melting shop
800,000 Blast Furnace
Cokes Oven
600,000 Sinter
COG
400,000
200,000
0
roduction
ption
roduction
ption
ption
+LDG
+LDG
G
G
G
G
O
F
onsum
onsum
onsum
IL
O
F
B
C
O
B
C
BFG
BFG
P
P
C
Figure 3.1-19 Gas balance in the case of introducing some of the major energy saving
technologies to the steel plant
By introduction of the energy saving technologies, the excess of B gas will be increased and that of
C gas will be also increased. It will be possible to change all the RHF fuel into by-product gas (B gas,
C gas and in addition recovered gas from steel converter: LD gas) because the excess calorie of C gas
41
will become almost 75% of Oil calorie. Introduction of energy saving facilities leads to increase in the
excess of by-product gas and it becomes possible to exclude “Oil” from the RHF due to conversion of
all the RHF fuel into by-product gas. This fuel conversion is considered to be the most efficient in
energy saving. Moreover, if a power facility is installed and it generates electric power using an
excess of by-product (including LD gas in the figure) after the fuel conversion of the RHF, the more
energy saving can be attained. A power facility with the generation efficiency of 30% will enable to
produce the power of 230 GWh/y.
As described above, the promotion of energy saving in the whole steelworks can achieve the fuel
conversion of “Oil” into surplus gas at the RHF(s). As far as installation of regenerative burners is
concerned, we presume that energy saving can be more efficiently attained due to avoiding duplicate
investment by simultaneous installation of regenerative burners at the time of the fuel conversion into
surplus gas.
⑤ Summary on recommended technologies
We recommended the following regarding the RHF.
・ Inspection and maintenance of heat exchanger,
・ Proper control of combustion and furnace pressure by restoring and normalizing measuring
equipment and controller,
・ Reduction of energy consumption by installation of regenerative burners.
Among them, we picked out regenerative burner “No.13.1 – Integrated System for Regenerative
Burner at Preheating temperature ≧1000 ℃” for the technology subject to the project study.
As for the installation of regenerative burners,
・ Study of the two ways of replacement, one is the full replacement which means that all the
existing burners are replaced into regenerative burners, and the other is the partial replacement
which means that not all but a part of the existing burners are replaced into regenerative burners,
・ Study of the future balance of surplus gas at the time of planned augmentation of A-Company,
and the fuel conversion of “Oil” of the RHF into by-product gas.
As for the latter regarding the fuel conversion, we presumed that it will be possible to change all the
RHF fuel “Oil” into surplus gas due to its excessive generation by introduction of appropriate
technologies to the currently existing facilities and/or the future planned facilities.
Although the fuel conversion of RHF will have a larger effect on energy saving, we recommended
the application of regenerative burners to the current RHF using “Oil” as fuel in this study.
42
3.2 T H E R E V I E W ON THE SPECIFIC PROJECT PLANNING FOR B-C O M P A N Y
To B-Company, the 1st and 2nd visits were made by the members and on the schedule shown in
Figure 3.2-1.
3.2.1 O V E R V I E W O F B-C O M P A N Y
Figure 3.2-2 shows the overview of B-Company steel plant.
Main Facilities
Reheating Furnace
Capacity: 50ton/h
250,000ton/y
43
B-Company is the typical steelworks with EAF. B-Company possesses 1 EAF and 1 RHF, and EAF
operates with 100% scrap as a raw material. The capacity of EAF exceeds that of RHF, and
operations are matched with RHF capacity. The special feature of this steel company is that EAF and
RHF are far by car for approximately 2 hours, and the transportation of billets must rely on land
transportation.
We describe the overviews of the EAF, Ladle preheater, and RHF which become the focus of this
study. These values below rely on the documents of B-Company and the interviews with the officers.
EAF:
・ Type of scrap charging system: Consteel®10 type
・ Tapping weight: approximately 70 t-steel
・ Specific power consumption: 345 kwh/ t-steel
・ Specific oxygen consumption: 39 m3N/ t-steel
・ Specific coal consumption: 24 kg/t-steel
This EAF has the special scrap charging system, so called Consteel®. Consteel® feeds scrap
continually from the side wall of the furnace, and at the same time as the waste gas from EAF passes
through the scarp passage, scrap is preheated before charging to the furnace. The power consumption
of EAF is comparatively low because of this continuous feeding and preheating of scrap. The oxygen
consumption is reasonable but the coal consumption is relatively high.
Ladle Preheater
・ Preheater:Vertical type ladle preheater: 2sets, Horizontal type ladle preheater: 2sets
・ Fuel; Coal gasification gas from coal gasification plant
・ Specific fuel consumption: 7 kg-Coal/t-steel(360kg/h)
・ Average preheating time: 40~50 minutes
This ladle preheater has the special feature that it uses coal gasification gas from coal gasification
plant.
RHF:
・ Heating Capacity: 50 t-steel/h (Walking hearth type)
・ Hot charge ratio: 0% (all cold charge)
・ Fuel: coal gasification gas from coal gasification plant
・ Fuel consumption rate: 71 kg-coal/t-steel
・ Furnace temperature: 1,170 deg.C
This RHF is the typical type furnace except that it uses coal as a fuel. This RHF used oil as a fuel
previously, but converted to coal from economical reason.
3.2.2 S PE C I F I C A T I O N O F I S SU E S O N E N E R G Y S A V I N G T O S T U D Y
On the 1st visit, we presented the technology in Japan. After plan tour, and had a discussion focused
10
http://www.tenovagroup.com/consteel_system.php?id_prodotto=8
44
on issues B-Company has with energy saving. Because B-Company has EAF and RHF at different
place, meetings were held at each plant.
(1) S T U D Y O F E N E R G Y S A V I N G T E C H N O L O G I E S F O R EAF
On 2nd visit, we followed the same step as A-Company after witnessing the operation and identifying
issues, and studying appropriate technologies to introduce.
45
Figure 3.2-4 Site view of EAF
82.4
80 l
70.6 e tota
arg
Scrap Charge
Scrap Charge Ch
ap
60 700 7ton 55.6 Sc r
(t) 1575℃
44.1
1565℃
(t)
46
Finding 1: Fig 3.2-6 shows the current fluctuation of each electrode 10 minutes after operation started.
(The graph starts at this timing which corresponds to 0 second). The current fluctuation of No.1
electrode is the biggest, and that of No.3 is the most stable. 30 minutes after operation started (1200
seconds in graph), current fluctuation of all electrodes becomes stable. This imbalance of electrode is
one finding.
(A)
(second)
Finding 2: Fig 3.2-6 indicates that current fluctuations of all electrodes are big. This big current
fluctuation may lead to low power input efficiency.
③ Recommended improvement
The current imbalance of Finding 1 is caused by the following phenomenon. The situation in the
furnace is presumed in Figure 3.2-7 from the understanding of Figure 3.2-6.
EBT
Molten Steel Circulation
Scrap
47
Scrap is fed from the right side of this Figure. Because of that, non-melted scrap remains at the right
side of the furnace. Non melted scrap causes the high current fluctuation of No.1 and No.3 electrode.
Meanwhile, Carbon injection is supplied from the slag opening in order to foam slag. However,
foamed slag instantaneously flows out through the slag opening. AS slag flows out of the furnace
soon, it is hard for the foaming slag to cover all inside the furnace, which explains the high carbon
consumption rate.
According to this presumption, the followings are proposed as shown in Figure 3.2-8
Molten steel
Circulation
Figure 3.2-8 proposed technology to the current imbalance among each electrode
Installment of oxy-fuel burner at the back side of No.1 and No.3 electrode eliminates the non-melted
scrap. Installment of carbon injection near No.1 electrode can easily cover all inside the furnace than
the present position with smaller amount of coal injection. Both improvements reduce the electric
power consumption of EAF. Further improvement is expected by installing door burner, which melts
the scrap more efficiently. As stated above, “No.6 Oxy-fuel Burners/Lancing (together with
enough capacity of Direct Suction Type Dust Collector) “ in the positive list, and application of
door burner associated with the technology of Oxy-fuel Burners/Lancing, enables more energy
efficient operation. Application of this technology improves the electric power consumption by 20
kwh/t-steel. At the same time, carbon injection consumption is saved to 10 kg/t-steel. In order to
apply this technology, auxiliary fuels are required, and this plant must procure fuels from outside. Oil
or coal is the candidate, but coal is hard to ignite, so Oil is the 1st priority.
As for the Finding 2, “No.11 Control and Automation for EAF Optimization” in the positive list is
proposed. Introduction of new Optimum Power Regulation System enables efficient power input and
reduces the electric power consumption rate by 10 kwh/ t-steel.
④ Summary on recommended technologies
The following technologies are recommended through witnessing the operation.
・ “No.6 Oxy-fuel Burners/Lancing (together with enough capacity of Direct Suction Type
Dust Collector) “
48
・ “No.11 Control and Automation for EAF Optimization”
Figure 3.2-9 describes the effect of each proposal.
(2) S T U D Y O F F U E L C O N S U M P T I O N R E D U C T I O N F O R L A D L E F U R N A C E
Figure 3.2-10 shows the diagram of the supply of fuel from gasification plant to ladle preheater. Coal
gasification gas from gasification plant preheats the ladles.
Coal Gasification
Gas
① Observation of operation
Gasification plant is the coal bed type. Air is fed from lower part of the plant, combusts coal partially,
and the plant produces gasification gas. Feeding air is controlled according to the demand of fuel gas,
and at the same time coal is fed into the plant to keep the outlet gas temperature at 300 deg.C. The
calorific value of the gas is approximately 1,300 kcal/m3N, and is supplied to ladle preheater without
any cooling of the gas.
The preheating time of ladle is determined by the time cycle of ladles. Figure 3.2-11 shows this time
49
cycle.
EAF
LF Ladle#1
1hr Ladle#2
CC
Ladle#3
Pre-heater
Ladles must stay at continuous casting (CC) during its operation, because CC is casting the molten
metal. This time cycle generates 40~50 minutes of waiting time from the relation between the timing
required for EAF and the time required for CC. During this waiting time, ladle preheater works for the
purpose of minimizing the temperature drop of molten steel from EAF to CC.
② Findings of operation
Present ladle inside temperature after preheating is approximately 800 deg.C. Calorific value of coal
gasification gas is relatively low of 1,300 kcal/m3N. This low calorie gas cannot give the high
temperature flame, which hampers the high temperature preheating of the ladle.
③ Recommended improvement
“No.9.2 Ladle Preheating: Oxygen burner Total system” in the positive list provides the higher
flame temperature, and realizes high temperature preheating of the ladle.
On the other hand, there is a possibility to improve energy saving in another way. Figure 3.3-11
explains the reason why the 40~50 minutes of waiting time generates. Another method of energy
saving is achieved by shortening the EAF operation time. If the operation time of EAF became
enough shorter than the current condition, the number of the ladle would decrease from 3 to 2 shown
in Figure 3.2- 12. In this case, there will be little waiting time.
Figure 3.2-12 Time schedule of ladle at the time of saving EAF operation time
In this case ladles can receive molten steel just after they leave CC. No preheating of ladles is
required because there is little time for the ladles to wait.
This measurement is not proposed here because it requires other improvements. However from the
energy saving point of view, this time schedule must be always considered.
50
④ Summary on recommended technologies
The followings are proposed according to the study above.
Figure 3.2-13 describes the study results.
Original O2 burner
burner
Burner capacity 2250Mcal/h 1000Mcal/h
→
Fuel consumption 7.0kg/ton 45~55% 3.5kg/ton
Coal Gasification gas (80~100%O2) 1890m3/h down 840m3/h
This technology saves fuel consumption by approximately 50%. Although this technology requires
oxygen, B-Company has oxygen plant in its site. It enables to provide cheaper oxygen, which makes
this technology more feasible.
(3) S T U D Y O F F U E L C O N S U M P T I O N R E D U C T I O N F O R RHF
RHF of B-Company uses coal gasification gas as a fuel shown in Figure 3.2-14. The principle of
coal gasification is the same as that of ladle preheater. However the size of the gasification plant is
much larger because of the amount of the energy consumed. Figure 3.2-15 shows the process of
gasification. This process produces coal gasification gas by feeding air and combusting coal partially,
cooling the gas, increasing the pressure, separating drain, and then this gas is supplied to RHF. The
gas produced has the calorific value of 1,350kcal/m3N.
Reheating Furnace
Capacity: 50ton/h
Coal Gasification 250,000ton/y
Gas
Coal pressure
Gasification Cooling To RHF
Increase
plant
Figure 3.2-15 Coal gasification process
51
Through operation observation at the site, applicable technologies were studied and specifying
operation findings
① Observation of operation
Figure 3.2-16 summarizes the operation condition at observation.
Material condition
Size (mm) 130 x 130 x 12000
Charging temperature (℃) 20
Production rate (t/h) 50
We found that some data are not indicated on the monitor as shown in Fig. 3.2-16. Troubles of
instruments were the main cause of this problem. We consider it important to promote operational
control by grasping the accurate values in future.
At observation, RHF operated at furnace temperature of 1,168 deg.C, and at 50 t-steel/h. Specific
fuel consumption was not clear at this moment because of the uncertainness of coal and gas
consumption
② Issues on the operation
There are many uncertainness of the operation condition, it is recommended to maintain the
instruments and manage these values.
Through this observation, the following findings appeared.
Finding 1: Inspection of the thermometer of heat exchanger
Finding 2: Air fuel ratio (Air/Fuel) appropriate control
Finding 3: Furnace pressure appropriate control
These findings include presumption, and check and correction will be necessary
Finding 4: Study of applying regenerative burners
“No.13-1 Preheating temperature ≧1000℃ by Regenerative Burner Total System” in
positive list is effective for the energy saving and restoration of furnace capability, so this technology
was studied.
③ Proposals for improvement
52
Finding 1 is related to the temperature measurement of the heat exchanger. In figure 3.2-16.
pre-heated air temperature indicated higher value than that of waste gas outlet temperature. It was
hard to believe considering that the heat exchanger is parallel-flow type. And to convert the heat
exchanger from parallel flow type to counter flow type was also proposed as same as that of
A-Company.
Finding 2 suggested that combustion condition inside the furnace was altering according to the load
change by visual observation. Air/Fuel ratio control was not executed because of non gas flow
measurements. We recommend the same countermeasures as A-Company.
Finding 3 suggests that furnace pressure was basically positive, but there was no indication of
furnace pressure and no furnace pressure control. The effect of Finding 3 is the same as that of
A-Company.
Findings 1~3 are the proposals to operation improvement. We recommended the same
countermeasures as A-Company too.
Finding 4 studied the installment of regenerative burner system. we recommended the two ways of
replacement of the burners, the full replacement and the partial replacement as same as in the case of
A-Company. This RHF is almost same as that of A-Company except that the fuel is coal gasification
gas. Figure 3.2-17 shows the plan about regenerative burner system with partial burners’ replacement,
and this is same as that of A-Company.
Zone3 & 4
Burner : 10
Figure 3.2-18 describes this effect. These values are also the same as A-Company.
53
Figure 3.2-18 Comparison of effect for all burner replacement and partial burner replacement
Energy saving rate of all burners’ replacement is bigger, but the investment becomes much bigger
because this replacement includes zone 3 & 4 which possesses many burners. On the other hand, the
investment of partial burners’ replacement is lower although the energy saving rate is low. The
selection depends on economical situation. However, more precise study is desirable in order to
clarify energy saving effect.
To the problem that the furnace capacity does not reach its specification, enlargement of burner
capacity is required. Another cause of this problem is the low calorific value of the gas which is
approximately 1,350kcal/m3N. This low calorific value gas may hamper the increase of furnace
temperature. Because regenerative burner system recovers high temperature combustion air, it
increases the furnace temperature, and at the same time it enlarges the burner capacity.
④ Summary on recommended technologies
Proposals for RHF are
・ Recommendation for check of thermometer of heat exchanger
・ Proper control of combustion and furnace pressure by restoring and normalizing measuring
equipment and controller,
・ Reduction of energy consumption by installation of regenerative burners.
“No.13-1 Preheating temperature ≧1000℃ by Regenerative Burner Total System” is the
candidate of the JCM project.
Both regenerative burner system with all burners’ replacement and partial burners’ replacement
are studied. This technology has not only energy saving effect but also restoration of furnace
capability, which is expected to contribute operation improvement.
54
3.3 E S T I M A T I O N O F E N E R G Y S A V I N G AND CO2 R E D U C T I O N R AT E , AND
ECONOMICAL EVALUATION
Energy Saving rate and CO2 Reduction rate of each Technology are estimated, and at the same time
each technology is economically evaluated. Engineering makers cooperated together to estimate the
investment and merit of each technology.
Figure 2.2-1 describes the premise condition for economical evaluation. In Vietnam, deprecation
period of facilities is generally 10 years, interest rate from city banks are 10%, and their loan period is
6 years. VAT is 10%, which assumes to apply only for domestic procurement.
CO2 Emission Factor is shown again in Fig. 3.3-2 as mentioned before.
3.3.1 E S T I M A T I O N O F E N E R G Y S A V I N G A N D CO2 R E D U C T I O N R A T E , A N D
E C O N O M I C A L E V A L U A T I O N F O R A-C O M P A N Y
The following 4 technologies are studied.
Technologies for EAF
1. Direct Suction Dust Collector & Installment of Oxy-fuel burner system
Introduction of Oxy-fuel burner system with direct suction collector
2. Electrode Regulation and Automation Control for EAF Optimization
Introduction of new electrode Regulation system for EAF
Technologies for RHF
3. Regenerative Burner Total System :Replacement of all burners
4. Regenerative Burner Total System :Replacement of partial burners
55
Regenerative Burner Total System with either replacement of all burners or replacement of
partial burners
Fig 3.3-2 indicates the energy cost in economical evaluation. These values are based on the hearing
from B-Company.
Economical evaluation describes one more case in which NEDO’s scheme of 201411 is available.
NEDO’s scheme is to entrust the Japanese portion of the facility to the Japanese Company, and after 1
year depreciation (remaining book value 10%) out of 4 years depreciation period, NEDO sells this
Japanese portion of the facility to the Japanese Company after 1 year. Pay back years using this
NEDO’s scheme is evaluated.
(1) E S T I M A T I O N O F E N E R G Y S A V I N G R A T E A N D CO2 R E D U C T I O N R A T E
11 NEDO : http://www.nedo.go.jp/koubo/EX2_100021.html
56
Introduction of new electrode Regulation system can upgrade control of power input to EAF, and
save electric power. This effect is reduction of 10 kwh/t-steel, which leads to cost reduction of
electricity.
Technologies for RHF
3. Regenerative Burner Total System :Replacement of all burners
4. Regenerative Burner Total System :Replacement of partial burners
Regenerative Burner Total System with either all burners’ replacement or partial burners’
replacement
Regenerative Burner Total System generates profit of fuel reduction to RHF. In A-Company case,
oil is the targeted fuel of energy saving.
Fig. 3.3-3 shows the evaluation results.
Energy Saving
▲ 23,435 22,511 32,368 21,578
(GJ/y)
*1)
If C gas is assumed to be free of carbon, the result is 5,326t-steel/y & 56,068 GJ/y
CO2 reduction and energy saving of Direct Suction Dust Collector & Installment of Oxy-fuel burner
system has conversely minus effect, because CO2 from C gas is bigger than CO2 reduction from
electric power. If enough amount of C gas is confirmed to be vented to the air, C gas becomes free of
carbon. In this case, big CO2 reduction and energy saving has appeared, which is written in the note
of the figure 3.3-3. It is important to confirm how much C gas is vented in order for this technology to
become JCM.
(2) E S T I M A T I O N O F E C O N O M I C A L C O N D I T I O N
57
Fig 3.3-4 describes trial calculations of pay back years and Internal Return Rate (IRR: 10yers) on the
basis of the investment cost estimated by engineering makers. At the same time, it also includes the
case in which NEDO’s scheme is available. In order to calculate NEDO’s case, Japanese portion of
the investment is shown together.
Investment
US$ 3,000,000 600,000 4,300,000 2,100,000
VND 66,423,380,000 12,942,948,000 93,676,188,000 45,748,836,000
Japanese
63.3 90.0 80.0 80.0
portion(%)
Pay Back
8.1 2.7 8.7 6.1
(years)
IRR (%) 4.6 35.5 2.8 10.8
In the case of Application of NEDO Scheme
Pay Back
6.3 2.3 6.2 4.3
(years)
Considering that loan period in Vietnam is generally 6 years, Electrode Regulation and Automation
Control for EAF Optimization is the most feasible out of 4 candidates, which is most likely to become
JCM project. About RHF, regenerative burner system with partial replacement of burners has the
possibility of the project if this project could use the NEDO’s scheme. However, regenerative burner
system with all replacement of burners would not become feasible even though it could use the
NEDO scheme. Although regenerative burner system with partial replacement of burners with
NEDO’s scheme seems to be feasible, conversion of fuel from Oil to by-product gas is the first
priority for energy saving of RHF in A-Company.
3.3.2 E S T I M A T I O N O F E N E R G Y S A V I N G A N D CO2 R E D U C T I O N R A T E , A N D
E C O N O M I C A L E V A L U A T I O N F O R B-C O M P A N Y
The following 7 technologies are studied.
Technologies for EAF
58
1. Installment of Oxy-fuel burner system with oil as a fuel
2. Installment of Oxy-fuel burner system with coal as a fuel
Introduction of Oxy-fuel burner system
2 cases are studied for this technology. One is using oil as a fuel, and another is using coal as a fuel.
3. Electrode Regulation and Automation Control for EAF Optimization
4. Electrode Regulation and Automation Control for EAF Optimization with hardware
Introduction of new electrode Regulation system for EAF
B-Company demands us to study not only for improvement of only control system but also
improvement of control system together with its related hardware. The hardware has the possibility
not to work as the improved control system instructs, and therefore more precise study is required to
become real project. Final investment cost will exist between these 2 investment costs.
Technologies for Ladle Preheater and RHF
5. Ladle Preheater
Introduction of Oxy fuel burner to ladle preheater
6. Regenerative Burner Total System :Replacement of all burners
7. Regenerative Burner Total System :Replacement of partial burners
Regenerative Burner Total System with either replacement of all burners or replacement of partial
burners
Figure 3.3-5 shows the energy cost for this evaluation.
The evaluation of economical condition also includes the NEDO’s case as described before.
(1) E S T I M AT I O N O F E N E R G Y S AV I N G R AT E AN D CO2 R E D U C T I O N R AT E
59
foaming is reduced by 15 kg-coal/steel.
The related value of Oil and coal is shown in Figure 3.3-6
The energy saving and CO2 reduction rate are evaluated by using the above mentioned value.
3. Electrode Regulation and Automation Control for EAF Optimization
4. Electrode Regulation and Automation Control for EAF Optimization with hardware
Introduction of new electrode Regulation system for EAF
Introduction of electrode Regulation system upgrades the electrode control to reduce the electric
power consumption by 10 kwh/ t-steel, which generates cost merit.
Technologies for Ladle Preheater and RHF
5. Ladle Preheater
Introduction of Oxy fuel burner to ladle preheater
Oxy fuel burner can realize 45~55 % reduction of a fuel. Merit of this technology is evaluated by
assuming that supplied oxygen has 80 % concentration and the energy saving ratio is 40% from
conservative point of view. Although this technology requires oxygen plant, this steel plant possesses
the oxygen plant. The electric power consumption of this oxygen plant for consumed oxygen is 1.57
kwh/m3N-O2. This value is used for economical evaluations.
The coal consumed for the gasification gas is the same one as used for EAF, and same value is
applied. Ladle preheater has the possibility of improving coal consumption rate by improving time
cycle of the ladle. The time cycle of ladle must be watched。
6. Regenerative Burner Total System :Replacement of all burners
7. Regenerative Burner Total System :Replacement of partial burners
Regenerative Burner Total System with either replacement of all burners or replacement of partial
burners
The application of regenerative burner total system has the same effect as the case in A-Company,
which realize the reduction of coal,
Figure 3.3-7 indicates the evaluation result of the technologies for EAF, and Fig 3.3-8 shows the
evaluation result of technologies for Ladle Preheater and RHF.
60
Figure 3.3-7 Evaluation of CO2 reduction and energy saving rate for EAF
Electrical Arc Furnace
Electrode
Installment of Installment of Electrode
Regulation and
Oxy-fuel Oxy-fuel burner Regulation and
Automation
Technology burner system system Automation
Control for EAF
with oil as a with coal as a Control for EAF
Optimization
fuel fuel Optimization
with hardware
Electric power Saving of EAF Electric power Saving of EAF 10kwh/
25kwh/t-steel t-steel
Merit: (Requires Consumption of Control system only, and Control
5l-kg/t-steel for oil, system with hardware
15kg-coal/tos-s for coal
CO2 Reduction
4,484 2,848 1,424 1,424
(t-steel /y)
Energy Saving
40,020 29,979 14,990 14,990
(GJ/y)
Figure 3.3-8 Evaluation of CO2 reduction and energy saving rate for heating technology
Heating Technology
Ladle Preheater Regenerative burner : Regenerative burner :
Technology with oxygen/fuel Replacement of all Replacement of partial
burner burners burners
CO2 Reduction
2,238 8,156 5,437
(t-CO2 /y)
Energy Saving
20,294 80,590 53,727
(GJ/y)
(2) E S T I M A T I O N O F E C O N O M I C A L C O N D I T I O N
Fig 3.3-9 describes trial calculations of pay back years and Internal Return Rate (IRR; 10years) for
EAF, and Fig 3.3-10 describes those for Ladle Preheater and RHF on the basis of the investment cost
and merit estimated together with engineering makers. At the same time, it also includes the case
when NEDO’s scheme is available. In order to calculate NEDO’s case, Japanese portion of the
investment is shown together.
61
Figure 3.3-9 Economical Evaluation of each technology for EAF
Electrical Arc Furnace
Electrode
Installment of Installment of Electrode
Regulation and
Oxy-fuel burner Oxy-fuel burner Regulation and
Automation
Technology system system Automation Control
Control for EAF
with oil as a with coal as a for EAF
Optimization
fuel fuel Optimization
with hardware
Investment
US$ 2,000,000 2,000,000 800,000 2,200,000
VND 43,997,480,000 43,997,480,000 17,257,264,000 47,457,476,000
Japanese
70.0 70.0 90.0 90.0
portion(%)
Pay Back
No return 9.6 7.2 27.6
(years)
IRR (%) - 0.8 7.4 ▲ 17.3
In the case of Application of NEDO Scheme
Pay Back
No return 7.1 4.9 14.3
(years)
Pay Back
2.2 12.3 8.8
(years)
Installment of Oxy-fuel burner system with oil as a fuel cannot recover the investment because Oil
price is much higher compared with the price of electricity. Even though in case of coal, this
62
technology cannot give good pay back years. It is because the price of electricity is relatively
inexpensive compared with the price of oil and coal. In future, if the price of electricity is raised
compared with the price of oil and coal, the technology might become feasible.
Considering that loan period in Vietnam is 6 years, Ladle Preheater is the most feasible
technology because it has shortest pay back years. Electrode regulation system is the second
candidate of the feasible projects from the pay back years. However, in case of this technology,
it is necessary to ascertain a remodeling range about the hardware, and further study is expected.
On the other hand, although regenerative burner system with partial burners’ replacement has better
pay back years than that of all burners’ replacement, it still has long pay back years than loan period.
NEDO’s scheme is not enough assistance to shorten pay back years even for regenerative burner
system with partial burners’ replacement. However regenerative burner system has the effect of
restoring and reinforcing furnace capacity, it is worth studying considering these conditions.
As a result of economical evaluations on these 2 companies, each technology locates at the following
state in the steel industry in Vietnam.
Installment of Oxy-fuel burner system is aiming at reducing electric power consumption, but it is
hard to apply because the price of electric power is cheap compared with the price of fuels and CO2
factor of electric power in Vietnam is low. In future increase of CO2 factor and the price of electric
power may assist to be able to incorporate this technology.
Technologies of reducing fuels are also hard to incorporate because the price of energy is still cheap
in Vietnam. Especially regenerative burner system is hard to apply as its installment costs much and
requires time to install when it is applied to existing facilities. Regenerative burner system with partial
burners’ replacement can shorten pay back years and make economical situation better, but it is still
hard to adopt. In the case of newly construction or reinforcement of RHF, the cost of installing
regenerative burner system becomes much cheaper, which makes regenerative burner system more
feasible.
3.4 F I N A N T I A L S C H EM E IN V I ET N A M
In order to study and seek efficictnt financing scheme to lead to the realization of this study, the
study and hearing of the aid package of finance situation in Vietnam is investigated.
As a result, government financial agencies like Vietnam Development Bank (VDB) and city banks
do not have preferential scheme for introduction of energy saving equipment or new technologies at
present, and any special preferential scheme for steel industry.
On the other hand, Vietnamese government starts to regulate the introduction or import of
equipments and facilities which are cheap but outdated, and basically takes a stance of introducing
efficient equipments and technologies and developing high value-added steel products. However,
fund support to promote these measures is not enough at present.
However these days, concrete aid package begins like special tax measures, fund aid etc.
63
Special tax measures to enterprises which perform new investment project like energy saving
activities and production of high value-added steel will start soon. For example, “National
Technology Innovation Fund” is available from 2016, which is related to Ministry of Science and
Technology. Such financial aids have just been embodied
Whether these new aid packages are applicable to actual energy saving project or not, is not clear,
because they have just started or will start in near future.
Accordingly economical evaluations of each technology detailed before is estimated on the basis of
general city bank loan conditions.
Fig 3.4-1 shows interest rate, loan period, etc on the basis of hearings to banks in Vietnam.
64
Fig 3.4-1 Reference: Interest rate and loan period of city banks in Vietnam
65
4. JCM METHODOLOGY
JCM methodologies are built up for the technologies which are economically feasible in this study.
These methodologies follow to the methodology development guidelines agreed in the second joint
committee between Japan and Viet Nam. Effort is made to make methodologies as concise and
intelligibly as possible.
This study propose 3 methodologies, which correspond to the technologies of the positive list
described in 2.2,
(1) Energy Saving by Introduction of Optimum Power Regulation System at Electric Arc Furnace
(2) Ladle Preheating Oxygen/Fuel Burner
(3) Introduction of Regenerative Burner to the Reheating furnace for Semi-processed Steel
66
4.1 J O I N T C R E D I T I N G M E C H AN I S M M E T H O D O L O G Y O F “E N E R G Y S A V I N G B Y
INTRODUCTION OF OPTIMUM POWER REGULATION SYSTEM AT ELECTRIC ARC
FURNACE”
At electric arc furnace (EAF), the steel scrap is melted to molten steel with electricity through the
electrodes. The key technology of the “JCM Methodology” is the optimum power regulation system
which controls the position of electrodes and the tap voltage. The introduction of the system is
expected to save electricity and reduce CO2 emission.
Date of completion
67
A. Title of the methodology
Energy Saving by Introduction of Optimum Power Regulation System at Electric Arc Furnace
Version number: 1.0
Terms Definitions
Billet Semi-processed steel which have square or circle cross
section. The products are manufactured by continuous
casting.
Electric Arc Furnace (EAF) The furnace which melts steel scrap to molten steel with
electricity through the electrodes. The molten steel is
simultaneously refined by oxygen blowing in the furnace.
Continuous Casting machine The machine which continuously solidifies molten steel into
(CC) the billets.
Ladle furnace (LF) The furnace which is placed between EAF and CC, if
necessary. The main purpose of introduction of the ladle
furnace is reduction of S content in the molten steel.
Hot pig iron The molten iron produced by blast furnace. Temperature of
the hot pig iron is around 1500 degrees Celsius after tapping
from blast furnace. The main content of the hot pig iron is
iron (Fe). The hot pig iron contains around 4% carbon.
Cold pig iron Solidified “Hot pig iron”.
Tap temperature Temperature of the molten steel. The tap temperature is
measured at EAF before tapping molten steel from EAF to
the ladle.
Items Summary
GHG emission reduction The Optimum Power Regulation System is introduced into the
measures established EAF. The system improves the electricity efficiency,
so that the project reduces CO2 emission that originated from
electricity and fossil fuel.
68
Scrap
Electricity
Electricity Oxygen
Steam Plant Other Process
D. Eligibility criteria
This methodology is applicable to projects that satisfy all of the following criteria.
Criterion 1 The project of improving energy efficiency at electric furnace process by
introducing the electric furnace electrodes control system into an existing electric
furnace.
Criterion 2 Electrode control system, which is based on the impedance, is used before the
69
project.
Criterion 3 Electrode control system, which is based on multi-variable information, is
introduced at the project.
Criterion 4 All molten steel, which are produced at EAF, are casted to billets.
Criterion 5 The tap temperature difference between of the reference and of the project is
within 10 degrees Celsius.
Reference emissions
Emission sources GHG types
Electricity, which is consumed at the EAF CO2
Carbon of the cold pig iron, which is consumed at the EAF CO2
Carbon of the hot pig iron, which is consumed at the EAF CO2
EAF coal, which is consumed at the EAF CO2
Natural gas, which is consumed at the EAF CO2
Heavy oil, which is consumed at the EAF CO2
Electricity, which is consumed at the oxygen plant CO2
Steam, which is consumed at the oxygen plant CO2
Project emissions
Emission sources GHG types
Electricity, which is consumed at the EAF CO2
Carbon of the cold pig iron, which is consumed at the EAF CO2
Carbon of the hot pig iron, which is consumed at the EAF CO2
EAF coal, which is consumed at the EAF CO2
Natural gas, which is consumed at the EAF CO2
Heavy oil, which is consumed at the EAF CO2
Electricity, which is consumed at the oxygen plant CO2
Steam, which is consumed at the oxygen plant CO2
The reference data measurement period, which is more than three months, should be provided
before the project. The consumption of electricity, fossil fuels (coal, natural gas, heavy oil) and
oxygen at the EAF, also the production of billets are measured. The CO2 emission factors are of
70
the project period. The yearly production of billets during the project is used when the reference
values are converted to the yearly amounts. The carbon contents of the cold pig iron and the hot
pig iron are fixed 4 mass %, because these contents do not vary significantly.
Where,
REy : Reference emissions in year y [t-CO2/y]
REelec : CO2 emission from electricity, which is consumed at the EAF during the
reference period [t-CO2]
REcm : CO2 emission from carbon of the cold pig iron, which is consumed at the EAF
during the reference period [t-CO2]
REhm : CO2 emission from carbon of the hot pig iron, which is consumed at the EAF
during the reference period [t-CO2]
REcoal : CO2 emission from EAF coal, which is consumed at the EAF during the
reference period [t-CO2]
REng : CO2 emission from natural gas, which is consumed at the EAF during the
reference period [t-CO2]
REoil : CO2 emission from heavy oil, which is consumed at the EAF during the
reference period [t-CO2]
REo2 : CO2 emission from oxygen, which is consumed at the EAF during the
reference period [t-CO2]
WRPbillet : Production of billets during the reference period [t-billet]
WPbillet,y: Yearly production of billets during the project [t-billet/y]
71
REhm = WRhm × 0.04 × (44/12)
Where,
WRhm : Consumption of hot pig iron at the EAF during the reference period [t]
72
Where,
PEy : Project emissions in year y [t-CO2/y]
PEelec : CO2 emission from electricity, which is consumed at the EAF during the
project [t-CO2/ y]
PEcm : CO2 emission from carbon of the cold pig iron, which is consumed at the EAF
during the project [t-CO2/ y]
PEhm : CO2 emission from carbon of the hot pig iron, which is consumed at the EAF
during the project [t-CO2/ y]
PEcoal : CO2 emission from EAF coal, which is consumed at the EAF during the
project [t-CO2/ y]
PEng : CO2 emission from natural gas, which is consumed at the EAF during the
project [t-CO2/ y]
PEoil : CO2 emission from heavy oil, which is consumed at the EAF during the project
[t-CO2/ y]
PEo2 : CO2 emission from oxygen, which is consumed at the EAF during the project
[t-CO2/ y]
73
PEng = QPng, y × EFng
Where,
QPng, y : Consumption of natural gas at the EAF during the project [km3N/ y]
EFng : CO2 emission factor for the natural gas [t-CO2/km3N]
Emission reductions are calculated as the difference between the reference emissions and
project emissions, as follows.
74
EFelec CO2 emission factor for The combined margin(CM) emission factor in Viet
the Viet Nam grid system Nam from "IGES CDM project data base"
(http://www.iges.or.jp/en/cdm/report.html)
EFcoal CO2 emission factor for 1) The data is calculated from the carbon content of
the EAF coal the coal, which is measured by chemical analysis.
2) The data is sourced from "CO2 EMISSIONS
DATA COLLECTION, User Guide, Version 6"
(worldsteel).
(unless instructed by the Joint Committee)
EFng CO2 emission factor for 1) The data is calculated from the carbon content of
the natural gas the natural gas, which is measured by chemical
analysis.
2) The data is sourced from "CO2 EMISSIONS
DATA COLLECTION, User Guide, Version 6"
(worldsteel).
(unless instructed by the Joint Committee)
EFoil CO2 emission factor for 1) The data is calculated from the carbon content of
the heavy oil the heavy oil, which is measured by chemical
analysis.
2) The data is sourced from "CO2 EMISSIONS
DATA COLLECTION, User Guide, Version 6"
(worldsteel).
(unless instructed by the Joint Committee)
EFsteam CO2 emission factor for 1) The data is sourced from "CO2 EMISSIONS
the steam DATA COLLECTION, User Guide, Version 6"
(worldsteel).
(unless instructed by the Joint Committee)
As an example, JCM Methodology Spreadsheets (Input sheet, Calculation process sheet) are shown in
Figure 4.1-1 and Figure 4.1-2.
75
Figure 4.1-1 Input sheet
JCM_VN_F_PMS_ver01.0
Joint Crediting Mechanism Proposed Methodology Spreadsheet Form (input sheet) [Attachment to Proposed Methodology Form]
at the start
Consumption of electricity at
(2) Epeaf, y 97,500 MWh/ y C Monitored data - Measuring the Watt-hour meter equipped to the EAF and the end
the EAF
of the period
at every
Consumption of cold pig iron - Measuring the weight of the charged cold pig iron
(3) WPcm, y 12,500 t/ y C Monitored data charge to
at the EAF - Integration of the weights
EAF
at every
Consumption of molten pig - Measuring the weight of the charged molten pig iron
(4) WPhm, y 0 t/ y C Monitored data charge to
iron at the EAF - Integration of the weights
EAF
Consumption of EAF coal at - Reading the delivery amount of the EAF coal described at every
(5) WPcoal, y 6,250 t/ y C Monitored data
the EAF in the invoice delivery
at the start
Consumption of natural gas - Measuring the integrating flowmeter equipped to the
(6) QPng, y 0 km3N/ y C Monitored data and the end
at the EAF EAF
of the period
Consumption of heavy oil at - Reading the delivery amount of the oil described in the at every
(7) QPoil, y 0 m3/ y C Monitored data
the EAF invoice delivery
at the start
Consumption of oxygen at - Measuring the integrating flowmeter equipped to the
(8) QPo2, y 10,000 km3N/ y C Monitored data and the end
the EAF EAF
of the period
at the start
Consumption of electricity at - Measuring the Watt-hour meter equipped to the oxygen
(9) EPo2, y 8,750 MWh/ y C Monitored data and the end
the oxygen plant plant
of the period
at the start
Consumption of steam at the - Measuring the integrating flowmeter equipped to the
45 WPsteam, y 1,563 t/ y C Monitored data and the end
oxygen plant oxygen plant
of the period
at the start
Consumption of oxygen at - Measuring the integrating flowmeter equipped to the
(11) QPo22, y 2,500 km3N/ y C Monitored data and the end
the other plant other plant
of the period
76
Table 2: Project-specific parameters to be fixed ex ante
(a) (b) (c) (d) (e) (f)
Estimated
Parameters Description of data Units Source of data Other comments
Values
CO2 emission factor for the Viet Nam grid The combined margin(CM) emission factor in Viet Nam from "IGES CDM project data
EFelec 0.564 t-CO2/MWh
system base"(http://www.iges.or.jp/en/cdm/report.html)
1) The data is calculated from the carbon content of the coal, which is measured by
chemical analysis.
EFcoal CO2 emission factor for the EAF coal 3.257 t-CO2/t 2) The data is sourced from "CO2 EMISSIONS DATA COLLECTION, User Guide,
Version 6"(worldsteel).
(unless instructed by the Joint Committee)
1) The data is calculated from the carbon content of the natural gas, which is measured
by chemical analysis.
EFng CO2 emission factor for the natural gas 2.014 t-CO2/km3N2) The data is sourced from "CO2 EMISSIONS DATA COLLECTION, User Guide,
Version 6"(worldsteel).
(unless instructed by the Joint Committee)
1) The data is calculated from the carbon content of the heavy oil, which is measured by
chemical analysis.
EFoil CO2 emission factor for the heavy oil 2.907 t-CO2/m3 2) The data is sourced from "CO2 EMISSIONS DATA COLLECTION, User Guide,
Version 6"(worldsteel).
(unless instructed by the Joint Committee)
The data is sourced from "CO2 EMISSIONS DATA COLLECTION, User Guide, Version
EFsteam CO2 emission factor for the steam 0.195 t-CO2/t 6"(worldsteel).
(unless instructed by the Joint Committee)
Monitored data.
- Counting the number of the produced billets divided into each billet size.
Production of billets during the reference - Having data of the weight per a billet of each billet size by direct mesuaring or by
WRbillet 50,000 t-billet
period calculating using billet size and dencity.
- Calculating "Pbillet,ref" from the number of the produced billets and the weight per a
billet of each billet size
Monitored data.
Consumption of cold pig iron at the EAF
WRcm 2,500 t - Measuring the weight of the charged cold pig iron
during the reference period
- Integration of the weights
Monitored data.
Consumption of molten pig iron at the EAF
WRhm 0t - Measuring the weight of the charged molten pig iron
during the reference period
- Integration of the weights
[Monitoring option]
Option A Based on public data which is measured by entities other than the project participants (Data used: publicly recognized data such as statistical data and specifications)
Option B Based on the amount of transaction which is measured directly using measuring equipments (Data used: commercial evidence such as invoices)
Option C Based on the actual measurement using measuring equipments (Data used: measured values)
77
Figure 4.1-2 Calculation process sheet
JCM_VN_F_PMS_ver01.0
Joint Crediting Mechanism Proposed Methodology Spreadsheet Form (Calculation Process Sheet)
[Attachment to Proposed Methodology Form]
78
4.2 M E T H O D O L O G Y OF L A D L E P R E H E A T I N G O X Y G EN /F U E L B U R N E R
This methodology describes that retrofitting an existing burner into an oxygen/fuel burner can
improve fuel efficiency, resulting in reduction of CO2 emissions during ladle preheating.
Date of completion
79
A. Title of the methodology
Oxygen/Fuel Burner System for Rapid Ladle Preheating in Elevated Temperature Application
Version number: 1.0
Terms Definitions
Coal Gasification Furnace Furnace to produce mixed gas from coal and air.
(CGF)
Coal Gas (CG) Mixed gas produced from coal in CGF. which consists
primarily of carbon monoxide (CO), hydrogen (H2), carbon
dioxide (CO2), methane (CH4), nitrogen (N2) and moisture
(H2O).
Ladle (LD) Vessel or container of molten steel
Oxygen/fuel Burner total Burners designed to fire coal gas mixed with oxygen in high
system for Ladle preheating temperature applications.
Electric Arc Furnace (EAF) A furnace that heats and melts steel scraps by means of an
electric arc charging between electrodes. The steel melt is
refined by blowing oxygen into melt.
Ladle Furnace (LF) Facility to refine and reheat molten steel in ladle to targeted
steel compositions and temperature after Electric Arc
Furnace.
Continuous Caster (CC) Facility to solidify molten steel into a semi-finished product,
billet, for subsequent rolling in hot rolling mills. (Continuous
Caster can also produce bloom, or slab, larger section than
billet.)
Billet Semis which rectangular or round steel bar in an intermediate
stage of manufacture. Bar, rod, wire, and etc. can be
produced from steel billets.
80
consumption in EAF by decreasing tapping temperature is expected as a result from preheating
temperature increase (ex. from 900 deg C. to 1400 deg C.) of ladle inner refractory. If an operation to
decrease tapping temperature is not applied in EAF, reduction of electricity consumption in LF is
expected by decreasing amount of temperature rising up to targeting temperature of steel melt in LF.
These co-benefits mentioned above strongly affect by operational conditions in EAF and LF, and it is
also difficult to quantitatively evaluate the co-benefits.
Therefore, a methodology in a boudary shown in figure below is focussed hereafter.
Items Summary
GHG emission reduction Reduction of fuel and electricity consumption in CGF by
measures efficiency improvement of ladle preheating through an
introduction of “Oxygen/fuel Burner System for Rapid Ladle
Preheating in Elevated Temperature Application.”
gas/oil flow
Coal steel flow
4-1.Power
Gasification CC 10.Billet
1.Coal Furnace (CGF)
2.Natural gas
LD
3.Heavy oil
Oxygen/fuel
4-2.Power
Oxygen Burner LF
6.O2
Production system
7.Power Plant (OPP) for Ladle 9.Steel
LD
Boundary temperature
8.Steam 5.O2 EAF before tapping
Calculation of reference Calculated using CO2 emission originated from fuel and
emissions electricity consumed at ladle preheating furnace (LPF) before an
introduction of “Oxygen/Fuel Burner System for Rapid Ladle
Preheating in Elevated Temperature Application.”
Calculation of project Calculated from CO2 originated from oxygen, fuel, steam, and
emissions electricity consumed at LPF after introduction of “Oxygen/Fuel
Burner System for Rapid Ladle Preheating in Elevated
Temperature Application.”
Monitoring parameters 1) Coal consumed in CGF produced as a fuel for LPF
2) Natural gas consumed for LPF
3) Heavy oil consumed for LPF
4) Electricity consumed at CGF and LPF
81
5) Oxygen consumed in oxygen production plant (OPP) for
ladle preheating
6) Oxygen consumed in OPP for other plant except for LPF
7) Electricity consumed in OPP
8) Steam consumed in OPP
9) Steel temperature before tapping from EAF
10) Production of billet
D. Eligibility criteria
This methodology is applicable to projects that satisfy all of the following criteria.
Criterion 1 Proposed methodology is applied to improve efficiency of preheating ladle by
retrofitting an existing burner into an “Oxygen/Fuel Burner System for Rapid
Ladle Preheating in Elevated Temperature Application” in billet production route
of EAF-LF-CC.
Criterion 2 At the beginning of project, existing burners for preheating ladle have been
already operated, and “Oxygen/fuel Burner System for Rapid Ladle Preheating
in Elevated Temperature Application” has not been introduced.
Criterion 3 Easily possible to be certificated by analyzing actual data that efficiency of
preheating ladle can be improved by an introduction of “Oxygen/fuel Burner
System for Rapid Ladle Preheating in Elevated Temperature Application.”
Criterion 4 A fuel to preheat ladle should be one of coal gasification gas, natural gas, or
heavy oil.
Criterion 5 Difference of tapping temperature of molten steel in EAF between reference and
project should be within ten degree centigrade.
Reference emissions
Emission sources GHG types
CO2 originated from electricity consumed at CGF and LPF CO2
CO2 originated from coal consumed in CGF as a fuel at LPF CO2
CO2 originated from natural gas consumed as a fuel at LPF CO2
CO2 originated from heavy oil consumed as a fuel at LPF CO2
Reference emissions
Emission sources GHG types
CO2 originated from electricity consumed at CGF and LPF CO2
82
CO2 originated from coal consumed in CGF as a fuel at LPF CO2
CO2 originated from natural gas consumed as a fuel at LPF CO2
CO2 originated from heavy oil consumed as a fuel at LPF CO2
CO2 originated from electricity and steam consumed at OPP CO2
1. Reference CO2 emissions can be converted and summarized following data measured during
at least three months. In this case, CO2 emission factors of coal, natural gas, heavy oil,
electricity, and steam at the time of project year can be applied.
1) Elecricity consumed at CGF and LPF
2) Fuel consumed at LPF
2. CO2 emissions due to billet manufacturing can be strongly influenced by not only electricity
efficiency of plant facilities but also fuel consumption at LPF and production amount of billet.
4. Reference CO2 emissions of electricity consumed for ladle preheating are calculated by using
reference electricity consumption compensated with project production amount of billet.
83
REcoal = WRcoal × EFcoal (t-CO2)
where,
WRcoal : Reference coal consumed for CGF(dry t-coal)
EFcoal : CO2 emission factor of consumed coal(t-CO2/dry t-coal)
ER = ERcgf + ERld
where,
ERcgf:Reference elecricity consumed at CGF (MWh)
ERld:Reference elecricity consumed at LPF (MWh)
84
PEsteam:Project CO2 emissions originated from steam consumed in OPP(t-CO2/y)
85
WPsteam,y:Steam consumed for production of oxygen used at LPF( t-steam/y)
EFsteam :CO2 emission factor of steam(t-CO2/ t-steam)
86
EFoil CO2 emission factor of heavy oil due 1. Actual value
to the project 2. Value in “CO2 EMISSIONS DATA
COLLECTION, User Guide, Version 6”
published from worldsteel
EFelec CO2 emission factor of grid electricity 1. Value (CM) in ”IGES CDM Project
due to the project database”
http://www.iges.or.jp/en/cdm/report.html
published from IGES
EFsteam CO2 emission factor of steam utilized 1. Actual value
for producing oxygen due to the 2. Value in “CO2 EMISSIONS DATA
project. COLLECTION, User Guide, Version 6”
published from worldsteel
EFo2 CO2 emission factor of oxygen due to 1. Actual value
the project 2. Value in “CO2 EMISSIONS DATA
COLLECTION, User Guide, Version 6”
published from worldsteel
UOP Electricity consumption for production 1. Actual value
of 1 km3N oxygen (electricity 2.Calculating as EFo2 / EFelec
consumed for production of steam
used for producing oxygen is not
included)
87
Figure 4.2-1 An example of JCM spreadsheet “PMS(input)”
Table 1: Parameters to be monitored ex post
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
Monitoring Estimated Monitoring Source of Measurement methods and Other
Parameters Description of data Units Monitoring frequency
point No. Values option data procedures comments
Project consumption of coal in coal - Measuring the weight of the charged
Monitored
1 WPcoal,y gasification furnace(CGF) for ladle 1,020 drt t-coal/y C coal at every charge to LPF
data
preheating furnace(LPF) - Integration of the weights
Project consumption of natural gas Monitored - Measuring the integrating natural gas at the start and the end of
2 QPng,y 0 km3N-ng/y C
for LPF data flowmeter equipped to LPF the period
Project consumption of heavy oil for Monitored - Measuring the integrating oil flowmeter at the start and the end of
3 QPoil,y 0 m3-oil/y C
LPF data equipped to LPF the period
Project consumption of elecricity for Monitored - Measuring the Watt-hour meter
4-1 EPcgf,y 200 MWh/y C at every charge to CGF
CGF data equipped to CGF
Project consumption of elecricity for Monitored - Measuring the Watt-hour meter
4-2 EPld,y 400 MWh/y C at every charge to LPF
LPF data equipped to LPF
Project consumption of oxygen
Monitored - Measuring the integrating O2 at the start and the end of
5 QOld,y produced in oxygen production 300 km3N-o2/y C
data flowmeter equipped to LPF the period
plant(OPP) for LPF
Project consumption of purchase Monitored - Measuring the integrating O2 at the start and the end of
5 QOp,ld,y 0 km3N-o2/y C
oxygen for LPF data flowmeter equipped to LPF the period
Project consumption of oxygen - Measuring the integrating O2
Monitored at the start and the end of
6 QOother,y produced in OPP for other plant 10,212 km3N-o2/y C flowmeter equipped to the other plant
data the period
except for LPF except for LPF
Project consumption of elecricity for Monitored - Measuring the Watt-hour meter
7 EPo2 plant,y 2,064 MWh/y C at every charge to OPP
OPP data equipped to OPP
Project consumption of steam for Monitored - Measuring the integrating steam at the start and the end of
8 WSy 1,314 t-steam/y C
OPP data flowmeter equipped to OPP the period
Project average tapping Monitored - Measuring molten steel tempareture in
9 TPtap,y 1,600 deg C. C at every charge from EAF
temperature of molten steel in EAF data EAF before tapping from EAF
- Counting the number of the produced
billets divided into each billet size.
- Having data of the weight per a billet
of each billet size by direct mesuaring or
Monitored at the start and the end of
10 WPbillet,y Project production of billet 220,000 t-billet/y C by calculating using billet size and
data the period
dencity.
- Calculating "Pbillet,ref" from the
number of the produced billets and the
weight per a billet of each billet size
Table 2: Project-specific parameters to be fixed ex ante
(a) (b) (c) (d) (e) (f)
Estimated
Parameters Description of data Units Source of data Other comments
Values
The data is sourced from "CO2 EMISSIONS DATA COLLECTION,
EFcoal CO2 emission factor of coal 3.257 t-CO2/dry t-coal User Guide, Version 6"(worldsteel) unless instructed by the Joint
Committee.
The combined margin(CM) emission factor in Viet Nam from
EFelec CO2 emission factor of grid electricity 0.564 t-CO2/MWh "IGES CDM project data
base"(http://www.iges.or.jp/en/cdm/report.html)
The data is sourced from "CO2 EMISSIONS DATA COLLECTION,
EFo2 CO2 emission factor of oxygen 0.355 t-CO2/km3N-o2 User Guide, Version 6"(worldsteel) unless instructed by the Joint
Committee.
The data is sourced from "CO2 EMISSIONS DATA COLLECTION,
EFng CO2 emission factor of natural gas 2.014 t-CO2/km3N User Guide, Version 6"(worldsteel) unless instructed by the Joint
Committee.
The data is sourced from "CO2 EMISSIONS DATA COLLECTION,
EFoil CO2 emission factor of heavy oil 2.907 t-CO2/m3 User Guide, Version 6"(worldsteel) unless instructed by the Joint
Committee.
The data is sourced from "CO2 EMISSIONS DATA COLLECTION,
EFsteam CO2 emission factor of steam 0.195 t-CO2/t-steam User Guide, Version 6"(worldsteel) unless instructed by the Joint
Committee.
Monitored data.
- Counting the number of the produced billets divided into each
billet size.
WRbillet Reference production of billet 250,000 t-billet - Having data of the weight per a billet of each billet size by direct
mesuaring or by calculating using billet size and dencity.
- Calculating "Pbillet,ref" from the number of the produced billets
and the weight per a billet of each billet size
Monitored data,
WRcoal Reference consumption of coal for CGF 1,700 dry t-coal
- Measuring the weight of the charged coal
Monitored data,
QRng Reference consumption of natural gas for LPF 0 km3N-ng
- Measuring the integrating natural gas flowmeter equipped to LPF
Monitored data,
QRoil Reference consumption of heavy oil for LPF 0 m3-oil
- Measuring the integrating heavy oil flowmeter equipped to LPF
Monitored data,
ERcgf Reference consumption of elecricity for CGF 200 MWh
- Measuring the Watt-hour meter equipped to CGF
Monitored data,
ERld Reference consumption of elecricity for LPF 400 MWh
- Measuring the Watt-hour meter equipped to LPF
Monitored data,
ERld Reference elecricity consumed at LPF 400 MWh
- Measuring the Watt-hour meter equipped to LPF
Reference average tapping temperature of molten Monitored data,
TRtap,y 1,600 deg C.
steel in EAF - Measuring molten steel tempareture in EAF before tapping
Table3: Ex-ante estimation of CO2 emission reductions
CO2 emission reductions Units
1,502 t-CO2/y
[Monitoring option]
Option A Based on public data which is measured by entities other than the project participants (Data used: publicly recognized data such as statistical data and specifications)
Option B Based on the amount of transaction which is measured directly using measuring equipments (Data used: commercial evidence such as invoices)
Option C Based on the actual measurement using measuring equipments (Data used: measured values)
88
Figure 4.2-2 An example of JCM spreadsheet “PMS(calc_process)”
1. Calculations for emission reductions Fuel type Value Units Parameter
Emission reductions during the period of year y 1,502 t-CO2/y ERy
2. Selected default values, etc.
CO2 emission factor of coal ----- 3.257 t-CO2/dry t-coal EFcoal
CO2 emission factor of electricity ----- 0.564 t-CO2/MWh EFelec
CO2 emission factor of oxygen ----- 0.355 t-CO2/km3N-o2 EFo2
CO2 emission factor of natural gas ----- 2.014 t-CO2/km3N EFng
CO2 emission factor of heavy oil ----- 2.907 t-CO2/m3 EFoil
CO2 emission factor of steam ----- 0.195 t-CO2/t-steam EFsteam
Electricity equivalent value of oxygen ----- 0.629 MWh/km3N-o2 UOP
3. Calculations for reference emissions
Reference emissions during the period of year y 5,170 t-CO2/y REy
CO2 emissions by reheating ladle fossil fuel 5,537 t-CO2 REcoal
CO2 emissions from coal 5,537 t-CO2 REcoal
CO2 emissions from natural gas 0.0 t-CO2 REng
CO2 emissions from heavy oil 0.0 t-CO2 REoil
CO2 emissions by electricity consumption electricity 338 t-CO2 REelec
4. Calculations of the project emissions
Project emissions during the period of year y 3,668 t-CO2/y PEy
CO2 emissions by reheating ladle fossil fuel 3,322 t-CO2/y PEcoal
CO2 emissions from coal 3,322 t-CO2/y PEcoal
CO2 emissions from natural gas 0 t-CO2/y PEng
CO2 emissions from heavy oil 0 t-CO2/y PEoil
CO2 emissions by electricity consumption electricity 338 t-CO2/y PEelec
Electricity consumption for oxygen used at
59 MWh/y EPld o2,y
ladle preheating
CO2 emissions by steam consumption steam 7 t-CO2/y PEsteam
Steam consumption for production of
38 t-steam/y WPsteam.y
oxygen used at ladle preheating
89
4.3 J O I N T C R E D I T I N G M E C H A N I S M M E T H O D O L O G Y O F “I N T R O D U C T I O N O F
REGENERATIVE BURNER TO THE REHEATING FURNACE FOR SEMI-PROCESSED
STEEL”
The old burners, which are attached to the reheating furnace are replaced to the regenerative burners
in the process of producing steel bars by rolling the heated billets. The burner combustion exhaust gas
is discharged to the outside of the system at high temperatures until introduction of the project.
However, after introduction of the project, heat loss to the outside of the system is significantly
reduced. Therefore, the consumption of fossil fuel for the burners and relating CO2 emission are
reduced.
Date of completion
90
A. Title of the methodology
Terms Definitions
Billet Semi-processed steel which have square or circle cross
section. The products are manufactured by continuous
casting.
Reheating furnace (RHF) The furnace which reheats the semi-processed steel like
billets. The fossil fuel such as natural gas, coal gas and heavy
oil is used for the burner of the RHF.
Semi-processed steel Billet slab etc. These are rolled into sheets, steel bars etc.
Items Summary
GHG emission reduction The old burners, which are attached to the reheating furnace are
measures replaced to the regenerative burners in the process of producing
steel bars by rolling the heated billets. The energy efficiency of
the burner fuel is improved. Therefore, the consumption of
fossil fuel for the burners and relating CO2 emission are
reduced.
Billet
Reheating
Natural Gas
Furnace Heated Billet
Heavy Oil (RHF)
Electricity
Coal gas
Coal Coal
Gasification
Electricity
Plant
91
Calculation of reference The reference data measurement period should be provided
emissions before the project. The reference emissions are calculated from
the quantities of electricity, fossil fuel etc. at the RHF or at the
coal gasification plant during the reference period and their CO2
emission factors.
Calculation of project The project emissions are calculated from electricity, fossil fuel
emissions etc. at the RHF, coal gasification plant and CO2 emission
factors during the project period.
Monitoring parameters 1) Supply of billets
2) Consumption of natural gas at the RHF
3) Consumption of heavy oil at the RHF
4) Consumption of electricity at the RHF
5) Consumption of coal at the coal gasification plant
6) Consumption of electricity at the coal gasification plant
D. Eligibility criteria
This methodology is applicable to projects that satisfy all of the following criteria.
Criterion 1 The project of reducing consumption of fossil fuel by improving the energy
efficiency at RHF for billet.
Criterion 2 The burners of the RHF are not regenerative type before the project.
Criterion 3 The burners of introducing to the RHF are regenerative type.
Criterion 4 The burner fuel is natural gas, heavy oil, or coal gas.
Reference emissions
Emission sources GHG types
Natural gas, which is consumed at the RHF CO2
Heavy oil, which is consumed at the RHF CO2
Electricity, which is consumed at the RHF CO2
Coal, which is consumed at the coal gasification plant CO2
Electricity, which is consumed at the coal gasification plant CO2
Project emissions
Emission sources GHG types
Natural gas, which is consumed at the RHF CO2
92
Heavy oil, which is consumed at the RHF CO2
Electricity, which is consumed at the RHF CO2
Coal, which is consumed at the coal gasification plant CO2
Electricity, which is consumed at the coal gasification plant CO2
The reference data measurement period should be provided before the project. The
consumption of electricity and fossil fuels (coal, natural gas, heavy oil) at the RHF and the coal
gasification plant, also the supply of billets to the RHF are measured. The CO2 emission factors
are of the project period. The yearly supply of billets to the RHF during the project is used
when the reference values are converted to the yearly amounts.
Where,
REy : Reference emissions in year y [t-CO2/y]
REng : CO2 emission from natural gas, which is consumed at the RHF during the
reference period [t-CO2]
REoil : CO2 emission from heavy oil, which is consumed at the RHF during the
reference period [t-CO2]
REelec : CO2 emission from electricity, which is consumed at the RHF during the
reference period [t-CO2]
REcoal : CO2 emission from coal, which is consumed at the coal gasification plant
during the reference period [t-CO2]
REelec2 : CO2 emission from electricity, which is consumed at the coal gasification plant
during the reference period [t-CO2]
WRSbillet : Supply of billets to the RHF during the reference period [t-billet]
WRSbillet,y : Yearly supply of billets to the RHF during the project [t-billet/y]
93
EFng : CO2 emission factor for the natural gas [t-CO2/km3N]
94
during the project [t-CO2/ y]
PEelec2 : CO2 emission from electricity, which is consumed at the coal gasification plant
during the project [t-CO2/ y]
Emission reductions are calculated as the difference between the reference emissions and
project emissions, as follows.
95
DPRy = REy - PEy
Where,
DPRy :GHG emission reductions in year [t-CO2/y]
As an example, JCM Methodology Spreadsheets (Input sheet, Calculation process sheet) are shown in
Figure 4.3-1 and Figure 4.3-2.
96
Figure 4.3-1 Input sheet
JCM_VN_F_PMS_ver01.0
Joint Crediting Mechanism Proposed Methodology Spreadsheet Form (input sheet) [Attachment to Proposed Methodology Form]
Consumption of heavy oil at - Reading the delivery amount of the oil described in the at every
(3) QPoil, y 2,250 m3/ y C Monitored data
the RHF invoice delivery
at the start
Consumption of electricity at
(4) EPrhf, y 2,500 MWh/ y C Monitored data - Measuring the Watt-hour meter equipped to the RHF and the end
the RHF
of the period
Consumption of coal at the - Reading the delivery amount of the coal described in the at every
(5) WPcoal, y 0 t/ y C Monitored data
coal gasification plant invoice delivery
at the start
Consumption of electricity at - Measuring the Watt-hour meter equipped to the coal
(6) EPcgf, y 0 MWh/ y C Monitored data and the end
the coal gasification plant gasification plant
of the period
CO2 emission factor for the Viet Nam grid The combined margin(CM) emission factor in Viet Nam from "IGES CDM project data
EFelec 0.564 t-CO2/MWh
system base"(http://www.iges.or.jp/en/cdm/report.html)
1) The data is calculated from the carbon content of the steam coal, which is measured
by chemical analysis.
EFcoal CO2 emission factor for the coal 2.461 t-CO2/t 2) The data is sourced from "CO2 EMISSIONS DATA COLLECTION, User Guide,
Version 6"(worldsteel). The factor of steam coal is the first choice in the 2nd case.
(unless instructed by the Joint Committee)
Monitored data.
- Counting the number of the supplied billets divided into each billet size.
Supply of billets to the RHF during the - Having data of the weight per a billet of each billet size by direct mesuaring or by
WRSbillet 50,000 t-billet
reference period calculating using billet size and dencity.
- Calculating "Sbillet, ref" from the number of the supplied billets and the weight per a
billet of each billet size
[Monitoring option]
Option A Based on public data which is measured by entities other than the project participants (Data used: publicly recognized data such as statistical data and specifications)
Option B Based on the amount of transaction which is measured directly using measuring equipments (Data used: commercial evidence such as invoices)
Option C Based on the actual measurement using measuring equipments (Data used: measured values)
97
Figure 4.3-2 Calculation process sheet
JCM_VN_F_PMS_ver01.0
Joint Crediting Mechanism Proposed Methodology Spreadsheet Form (Calculation Process Sheet)
[Attachment to Proposed Methodology Form]
98
5. R EPORTING OF E NERGY S AVING T ECHNOLOGIES TO
V IETNAM
Seminar in Hanoi was held in January 2015, in order to widely dissement JCM scheme and to report
the study results of this project, to government officials related to JCM and concerned personnel in
steel industry in Vietnam.
At the same time, during 1st or 2nd visit to Vietnam, we visited government departments related to
JCM and explained JCM scheme and activities of this project
This chapter shows the meeting with government departments, and Seminar in Hanoi.
During 1st or 2nd visit to Vietnam, JFE group visited government officials related to JCM, and
explained JCM scheme and activities of this project. The followings show the departments which JFE
group visited, and attendance at the meeting
(1) MOIT(Ministry Of Industry and Trade)General Directorate of Energy
Date: Sep. 15th ,2014
Attendance:
Mr. Pham Thanh Tung: Director of International Cooperation Department
Mr. Nguyen Van Long: Deputy Director General Science Technology and Energy Efficiency
Department
Visitors:Sogo:JFE Steel Corporation, Sawa, Shimizu: JFE Techno-Research Corporation
(2) MOIT Heavy Industry Department
Date: Sep. 16th ,2014
Attendance:
Mr. Bui Quang Chuyen: Deputy Director General of Heavy Industry Department
Mr. Tran Van Long: Official of Heavy Industry Department
Visitors:Sogo:JFE Steel Corporation, Sawa, Shimizu: JFE Techno-Research Corporation
(3) MOIT Department of Science and Technology
Date: Sep. 16th ,2014
Attendance:
Mr. Le Viet Cuong:
Mr. Pham Truong Son: (Official)
Mr. Do Xuan Dong: (Official)
Visitors:Sogo:JFE Steel Corporation, Sawa, Shimizu: JFE Techno-Research Corporation
(4) MONRE (Ministry Of Natural Resources & Environment) International Cooperation
Department
99
Mr. Nguyen Xuan Bao Tam: (Deputy Director General)
Visitors:Sogo:JFE Steel Corporation, Sawa, Shimizu: JFE Techno-Research Corporation
(5) D MONRE Division of Science, Technology and International Corporation, Department of
Meteorology, Hydrology and Climate Change
Date: Nov.18th ,2014
Attendance:
Mr. LE NGOC TUAN: ( Director)
Visitor:Sogo:JFE Steel Corporation
5.2 S E M I N A R IN HANOI
Seminar was held at Hanoi in January with inviting government departments related to JCM and
concerned personnel in steel industry . At the Seminar, the results of this study were presented, which
includeed enegy diagnosis of each company, introduction of Japanese suitable technologies to each
company as a result of this study, and economcal evaluation of these technologies. JCM scheme was
also introduced in this Seminar.
100
technology is suitable to big furnaces.
Question -3
Q: There is an explanation about slag door and door burner. In this meaning what is the suitable
operation of EAF?
A: Furnace pressure ±0 is ideal operation which aims at no air infiltration and no energy loss toward
outside of the furnace. Slag door helps this operation, and door burner gives more efficient
operation.
Question -4
Q: How much is proper hot metal ratio to EAF? Are there any operations using hot metal in Japan?
A: Proper hot metal ratio depends on the cost of iron sources, so it differs from site to site. And
operation using hot metal is very rare in Japan.
There are all technical questions. After finishing the Seminar, there were still some more technical
questions.
101
Figure 5.2-1 AGENDA for Seminar
20 JANUARY 2015
Agenda
9:00 – 9:10 Introduction Kazumasa Sogo
(JFE Steel Corporation)
Coffee Break
10:35– 11:15 “Summary of Result Activity of Masuto SHIMIZU
B-Company in 2014” (JFE Techno-Research Corporation)
Pocedure
102
6. E CONOMICAL A NALYSIS FOR C OMMERCIALIZATION
Production capacity in the Vietnam steel industry is a mixture of facilities in operation for a long
time and newer ones introduced in line with the market opening since 2000. We confirmed through
the study that there is still a room for introduction of Japan’s newest technology because it is not fully
applied to even newer facilities yet.
The spread of the newest technology depends largely on its profitability and, as described in the
sub-sections “economic evaluation”, it may be hardly accomplished without any financial assistance
such as a subsidy at this point. However, we expect that the profitability will be improved as energy
price increases in the future.
Here, we analyzed the economic effectiveness due to the spread of the technology in consideration
of the future increase in energy price.
As described in Chapter 2, it is expected that energy price will increase in Vietnam in the future.
Here, we estimate the profitability on the assumption that electricity price rises by 30% and fuel price
15% in 2020. Furthermore, for a sensitivity analysis, we also estimate another case where electricity
price rises by 50% and fuel price 25%. The results are shown in Figure 6.1-1, 6.1-2 and 6.1-3. The
calculations are performed by assuming that investment amounts are same and without considering
any subsidies. The current economic evaluations as mentioned above are represented in the upper
rows of each of the figures.
103
Figure 6.1-2 Economical Evaluation of each technology to EAF in B-Company
Electrical Arc Furnace
Installment of Electrode
Installment of Electrode
Oxy-fuel Regulation and
Oxy-fuel burner Regulation and
burner Automation
Technology system Automation
system Control for EAF
with coal as a Control for EAF
with oil as a Optimization
fuel Optimization
fuel with hardware
Present condition
Pay Back years No return 9.6 7.2 27.6
IRR (%) - 0.8 7.4 ▲ 17.3
In the case that Electric power price +30%, and fuel price +15%
Pay Back years No return 7.1 5.3 18.6
IRR (%) - 8.0 15.5 ▲ 11.3
In the case that Electric power price +50%, and fuel price +25%
Pay Back years No return 6.0 4.4 15.3
IRR (%) - 12.3 20.4 ▲ 8.0
Because the loan period is generally about six years in Vietnam and the valid payout period is aimed
at not more than six years, the evaluations for each technology are given as follows.
For EAF technology, we evaluate that it is difficult to apply the technologies using auxiliary fuel
with burners newly installed (e.g. Direct Suction Dust Collector and Installment of Oxy-fuel burner
104
system to A-Company; Installment of Oxy-fuel burner system with oil as a fuel or Installment of
Oxy-fuel burner system with coal as a fuel to B-Company) from the view point of profitability.
There remains the possibility of applying them only if electricity price rise greatly exceeds fuel price
rise, nevertheless we can not expect this at present.
The profitability of the electrode control technology (e.g. Electrode Regulation and Automation
Control for EAF Optimization to both A-Company and B-Company) will be more improved as
electricity price rises because the technology contributes only to reducing power consumption. As
mentioned above, however, there remains some possibility that we can not achieve our purpose. We
should study more in case that the hardware needs revamping simultaneously.
The utilization of the oxygen/fuel burner for preheating ladles (e.g. Ladle Preheater to B-Company)
is sufficiently profitable technology. This is, as mentioned above, successfully applicable at the
moment when a steelworks holds its in-house oxygen plant.
The applicability of regenerative burners to RHFs (e.g. Regenerative burner to both A-Company
and B-Company) depends much on fuel price, and it will be difficult to replace all the existent
burners even if electricity price is raised by 50% and fuel price 25%. If partial replacement of burners
is applied to a RHF with oil or natural gas used, it will become profitable when fuel price rises in the
future. However, if coal is used as a fuel at RHF as in B-Company, partial replacement will be
less profitable because the price of coal is lower than that of oil or natural gas. Therefore it is less
possible in such a case to adopt the technology in terms of energy saving. There will be a chance of
the installation when a new furnace is set up or an existent one is revamped for reinforcement.
According to these points of view and the results of sensitivity analysis, we forecast the reduction of
CO2 emissions in the future by using the predicted values.
The Vietnamese government has set numerical targets for steel and iron production as of 2025 as
follows.12
・ Expand the total steel production to 38 – 39 million tons,
・ Expand the pig iron production to 20 million tons by 2025.
The Vietnam’s demand for steel is expected to grow in future as the economy is likely developing
and construction of blast furnaces is currently progressing. Based on the numerical targets above, we
assumed that EAF will produce 18.5 million tons per year of crude steel and reheat furnaces will treat
38.5 million tons of semi-finished steel in Vietnam as of 2025. We assume each of the adoption rates
for the technologies as follows.
・ Oxy-fuel burner system for EAF: this technology will be unlikely spread widely because its
profitability is based on the premise of the price difference between electricity and fuel, while
12
Feasibility Study project for the BOCM (FY2012) “Study for applying effective Japanese excellent
energy saving and CO2 Reduction technologies to newly planned Integrated Steel Works in Viet Nam (Policy
proposal and project development Study)” ReportMarch,15th,2013 JFE Steel Corporation JFE
Techno-Research Corporation
105
energy prices are expected to rise in future. Moreover, this does not necessarily reduce CO2
emissions. Therefore we exclude this from the applicable technologies.
・ Electrode Control Technology for EAF: this technology is expected to spread in accordance
with development in the operational skills, while there are still old-fashioned facilities in
Vietnam and the operational skills are immature yet. Moreover, this will improve the
profitability as electricity price rises. Therefore, this is expected to spread in future and we
assume that its adoption rate will be about 50% as of 2025.
・ Oxygen/fuel Burner for Ladle Preheating: this technology is most probable to spread at present,
and we need to make the technology more known to the steelmakers. As described above, the
profitability changes depending on whether a steelwork holds its in-house oxygen plant. We
expect that many steelworks will hold their own oxygen plants in future because it is
economically advantageous for them to do so. Therefore, we assume that 50% of all the
steelworks will hold their in-house oxygen plants and that 50% of them (i.e. 25% of all the
steelworks) will adopt this technology as of 2025. Furthermore, we have the utilization of
regenerative burner for ladle preheating as an applicable technology for a steelworks without its
in-house oxygen plant, and we can also expect the combined spread of these technologies.
・ Regenerative Burner Technology for RHF: this technology is still insufficient in its profitability
when it is applied by revamping the existent facility, even if fuel price rises. Higher rise in fuel
price could give profitability to partial application of this technology, nevertheless full
application would be difficult in such a case. However, we are expecting that there will be new
installment, improvement and reinforcement of steel facilities by 2025, and the application of
regenerative burner can have sufficient profitability at this timing. Therefore, we assume that the
adoption rate will be 50%.
Based on the premises and the assumptions described above, the reduction of CO2 emissions as of
2025 is summarized in Fig. 6.1-4.
Figure 6.1-4 Forecast of dissemination of technologies and CO2 reduction rate at 2025
Electrode Regulation Ladle Preheater
Reheating Furnace
Technology and Automation Control with oxygen/fuel
Regenerative burner
for EAF Optimization burner
Disementation 18.5 mil t-steel/y 18.5 mil t-steel/y 38.5 mil t-steel/y
Ratio in Vietnam x 50% x 50% x 50% x 50%
(mil t-steel/y) =9.25 =4.63 =19.25
CO2 Reduction
5.64 4.9 10.5
ratio
(10kwh/ t-steel) *1) *2)
(kg-CO2/t-steel)
CO2 Reduction
52,170 22,600 202,120
(t-CO2/y)
106
*1) Adopt half of the value of B-Company with replacement of all burners (the value is approximately
double in case of use of coal gasification gas)
*2) Adopt the value of A-Company (he value is approximately double in case of use of coal
gasification gas)
As explained above, we can expect much reduction of CO2 emissions by introducing these
technologies from now on.
107
7. S UMMERY
Energy saving technologies study about contrastive 2 companies was executed this fiscal year. One
has a long history of steel making, and another started its operation after 2000. Although they are
contrastive, the followings are recognized
1. Steel making technologies of both companies are still immature,.
2. There is much room to introduce new technologies. At the same time, it is hard to find the base
and capability which brings up technical knowledge and skills.
3. There are still not many concerns about Japanese technologies, and in many places, technologies
from China have been adopted because of economical priority.
At the same time, from this study, there are few chances for Japanese technoloties to be introduced
to Vietnam steel Indsustry from the economical point of view, because Japanese technologies costs
pretty high and the energy costs in Vietnam are low. These situations lead to the followings
propossals.
108
However, Japanese technologies are better than those from other countries, and it can offer higher
effect. It is very important to break economical barrier for Japanese technologies, and effective use of
JCM scheme can support to show superiority. Track record of Japanese technologies is important,
and application of feasible technologies should be taken first priority even though it has small
investment and small effect.
In the future, energy prices in Vietnam are expected to increase, and for that moment, Japan must
prepare for such situation.
3.Future Development of Understanding and practical use of JCM
It is not exaggeration that steel industry in Vietnam has no information about JCM. At the same
time, some government officials have opinions that it is hard to understand JCM because Ministry of
Economy Trade, and Industry and Ministry of the Environment have different JCM scheme.
Therefore more simple explanation is desirable.
Another big issue in the steel industry in Vietnam is that enough data collection systems are not
established. This leads to the concern whether appropriate MRV system is plausible or not, in order
to promote JCM. System of Management cycle, that is cycle of Plan-Do-Check-Action, is not
popular in Vietnam, and Introduction of Management cycle is also recommended to promote JCM.
4.Barriers to promote Energy Saving Action
Some barriers to introduce energy saving action rise from study and discussion with 2 companies,
from meeting with government officials, and from the situation mentioned above. Based on these
understandings, barriers are wrapped up in the following table.
It is a pleasure to consider these barriers at intergovernmental meeting on JCM consultation.
109
● Insufficient System sharing technical information between steel
companies which is popular in Japan.
Lack of information ● Insufficient information about EPC which is all ordered to
foreign companies because of lack of ability of the domestic
facilities maker and construction supplier
Competition
Common ● The competition about quality and the energy saving (energy
environment among
items in intensity) is not common
companies
rising
● A high interest rate on the occasion of financing under the
nations High interest rate
influence of inflation
● many equipments from overseas from the performance and
quality point of view, because of insufficient ability of the
High facility cost domestic facilities maker
● Higher estimate for the equipment because of a currency risk
and the credit risk of the individual company
● Even some government-affiliated cannot understand JCM
Handling of JCM because of different support scheme in Ministry of Economy,
Trade and Industry, and Ministry of the Environment
● Not much aid package to the energy saving, and insufficient
understanding for the need of energy saving target and the
Energy saving policy regulation
Government ● Little policy about the spread of so-called management cycle
such as Plan-Do-Check-Action
● Hard environment of enhancing energy saving because of low
Uncertainty of energy energy price (The present price of power is kept in a low level
prices not directly to reflect its cost)
● These lead to a high business-related energy consumption and
low energy saving investment
This study indicates much room to introduce Japanese superior technologies to steel industry in
Vietnam. However, environment does not reach to the stage to introduce Japanese technologies from
the economical point of view. In this situation, JCM scheme may support to make some technologies
economical and feasible. Whether these technologies are applied or not, highly depends on the
judgment of targeted company.
On the other hand, in the case that the projects are accepted by these companies, they require more
precise study like check of data and its reliability, estimation of volume of site work, check of data
110
about MRV.
Inexpensive equipment, uptake of various merits etc must be studied in order to improve
economical situation.
At the same time, management cycle, that is Plan-Do-Check-Action, must be radicated for
achieving the embodiment of technologies.
During this study, we were able to visit 2 steel companies and many government officials to study
energy saving technologies. We would like to express our sincere greatness for those who welcomed
us during this study for their great help and kindness at the end.
111
A N N E X 1 C O M M E N T AR Y O N T E C H N O L O G I ES P O S I T I VE L I S T
Figure Annex1-2 No.2: Scrap Preheating (ex. Ecological and Economical Arc Furnace)
(From http:/www.steelplantech.co.jp)
112
Figure Annex1-3 No.4: Aluminum Alloy Conductor Arm for Supporting Electrode
(From NIKKO Industry CO.,LTD)
Graphite hearth
<DC furnace> electrode
Electric room
DC reactor
(DCL)
trans
Transformer
station
High-frequency
filter
Figure Annex1-4 No.5: DC Electro Arc Furnace
(From NEDO Handbook)
113
Figure Annex1-5 No.6: Oxy-fuel Burners/Lancing (or Super Sonic Burner )
(From NIKKO Industry CO.,LTD)
To application
system
Steam drum
Accumulator
Super
heater
From application
WHRB steam drum system
Boiler
Circulation
pump
Condensate
pomp
Cooling water
Heat
Circulation
Exchanger
pump Boiling feed Deaerator Make-up
Water pump water
114
Waste gas Waste gas 170deg.C
Waste gas 4-way selector Valve
COG
920 Mcal/h Heat Storage material
(ceramic honeycomb)
Air 20deg.C Air
COG
1000deg.C 600 Mcal/h
1000deg.C
Figure Annex1-7 No.9.1: Regenerative Burner Total System for Ladle Preheating
(From NEDO Handbook、Photo. from CHUGAI RO CO.,LTD)
Figure Annex1-8 No.9.2: Oxygen Burner Total System for Ladle Preheating
(From CHUGAI RO CO.,LTD)
115
EAF Process Optimization by Off-gas Analysis
Data collection
Meltdown signal
Current Scrap data presetting
transformer Current
Voltage
Touch panel
inverter
Microphone
Sound
signal
Signals from
EAF
EAF Control Panel
116
Carbon Electrode HYBRID
Jet Burner
① Focused O2 Frame
(Mach = 2)
D: Temperature homogenization
by bath stirring on tapping
molten steel
Figure Annex1-11 No.12: Carbon and Oxygen Injection System for foamy slag practice
(From NIKKO Industry CO.,LTD)
No heat
Recovery base condition
Fuel: By-product gas
Furnace Temperature: 1350 deg.C
Fuel usage quantity (%)
Δ20%
Conventional Recuperator
Δ30%
High temperature heat exchanger
Δ45%
Regenerative burner
Figure Annex1-12 No.13: Comparison of fuel usage quantities versus pre-heating air
temperature
(From SOACT)
117
Preheating temperature >1000℃ by Regenerative Burner Total System
Fuel Fuel
Burner B
Burner A
Ceramic Air
Ceramic
Regenerator B Exhaust gas
Switch valve Regenerator
200 deg.C
A
Regenerative burners, using temperature resistant ceramic heat media, can recover approximately 85%
of waste heat from high temperature exhaust gas from reheating furnaces or ladle preheating by directly
introducing high temperature exhaust gas into heat media and alternate switching between heat storage
and preheating of combustion air.
This high performance burner technology achieves superior fuel gas saving and compact reheating
furnace equipment.
It is desirable to install this system when new furnace is introduced, because the cost will be saved
compared to modification of furnaces.
Reheating Furnace
(continuous)
Reheating Furnace
(batch)
Field test project Ladle
Energy conservation ratio (%)
In case of Reheating
Furnace
10 -20% Reduction
118
Temperature and pressure Control in furnace,
,O2 Control in Fuel gas and Change to ceramic fiber inner wall
O2 meter Furnace Furnace manometer
No.14 Thermal insulation by thermometer
Damper
Combustion control system (DCS)
Fuel
Figure Annex1-15 No.15: Process Control for Reheating Furnace + No.14 Thermal
insulation by Ceramic Fiber on inner wall
(From NEDO Handbook)
Figure Annex1-16 No.16: Air Conditioning by Hot Water Absorption Chiller utilizing Waste
Heat
(From revised figure supplied by EBARA Refri. Equip. & Systems Co., Ltd.)
119
Required electric power (%) (1) Delivery side damper control
Airflow (%)
Figure Annex1-17 No.17: Inverter (VVVF; Variable Voltage Variable Frequency) Drive for
Motors
(From NEDO Handbook)
Check
Data Acquisition Management
& Monitoring System System
Power, Carbon, Oxygen, etc. Fuel, Temperature , etc.
Production Scheduling
Plan
Figure Annex1-18 No.18: Energy Monitoring and Management Systems for Steel Plant with
EAF
120