GTS, PTS & Technical Data Sheet of Pakaldul H.E.project
GTS, PTS & Technical Data Sheet of Pakaldul H.E.project
GTS, PTS & Technical Data Sheet of Pakaldul H.E.project
(A Joint Venture of NHPC Ltd., JKSPDC Ltd. & PTC India Ltd.)
Volume – 4
Section IIIA, IIB, IIIC & IIID- General Technical Specifications
(GTS),Particular Technical Specifications (PTS),Technical Dta Sheets
(TDS) & Model Quality Assurance Plan (MQAP)
For
HM Works: Design,Procurement,Manufacture,Inspection,Shop Assembly, Testing,
Painting, Transportation, Site Storage & Site Erection, Testing &
Commissioning including provision for all labour, Plant & material for
the above ,handing over to Owner ,supply of necessary Spares for 5
years trouble free operation
JUNE 2017
2.0 Standards
2.1 Standards for General Applications 10
2.2 Standards for Design and Testing 11
2.3 Material Standard 13
2.3.1 Substitute Material 16
2.3.2 Sub-Contractors/Vendors
2.4 Permissible Stresses 17
2.4.1 Permissible Stresses for Spillway Gates, Adit gates & Intake 17
Gates
2.4.2 Permissible Stresses for Embedded parts 18
2.4.3 Permissible Stresses for Surface spillway stoplog, Tunnel 18
spillway, Bulkhead gate, Intake bulkhead gate, Tail race tunnel
gate
2.4.4 Permissible Stresses for Rope drum Hoist Equipment 19
.
2.4.5 Permissible Stresses for Hoist Bridge, Hoist Support, 19
Trestles & Hand Railing (Clearly above Water)
2.4.6 Permissible Stresses for Trash racks 19
2.4.7 Permissible Stresses for Hydraulic cylinder and their
Components
i
Pakal Dul H E Project
ii
Pakal Dul H E Project
iii
Pakal Dul H E Project
6.0 Installation
6.1 Installation of Gates and Bulkheads 64
6.2 Installation of Frame, Guide and Tracks 64
6.3 Placing Concrete in Blockout 65
6.4 Hoist &Crane 65
6.5 Installation of Pressure shaft steel liners/ Tunnel Spillway steel
liners
6.5.1 General 65
6.5.2 Erection/ Laying Procedure 66
6.6 Seals 67
6.7 Drives and Gears 68
6.8 Lubrication, Lubricants and Oils 68
6.9 Oil piping 69
6.9.1 Pipe Supports and Hangers 69
6.10 Mechanical Instruments 69
6.11 Hydraulic servomotor Systems 70
iv
Pakal Dul H E Project
10.0 Measurement
10.1 General 98
10.2 Steel liner 98
10.2.1 Weight of straight ferrule 98
10.2.2 Weight of Bend section 99
v
Pakal Dul H E Project
Annexure-A
vi
Pakal Dul H E Project
1 General Description
1.1 Introduction
The project is proposed on river Marusudar, a major tributary of river Chenab,
in Kishtwar district, Jammu and Kashmir. The dam is envisaged near
Drangdhuran village and power house is proposed near Trimuli village. The
proposed dam site is located at about 23 km upstream of the confluence of
Marusudar river with Chenab river near Bhandarkut village. Drangdhuran
village is connected by a 13.5 km long road to the nearest town Patimahal.
1
GTS
Pakal Dul H E Project
2
GTS
Pakal Dul H E Project
Two numbers of radial gate for clear opening size of 6.20m wide x 7.00m high
complete in all respect with skin plate, stiffeners, bracings, arms, girders,
trunnion assemblies, trunnion brackets, anchorage system for trunnions, seal
assemblies, guide roller assemblies, dogging device, lifting attachment and
other miscellaneous fittings i.e. walkways, hand railings, ladders etc. as
specified complete in all respect.
Two sets of first stage and 2nd stage embedded parts complete with
embedments for first stage, lintel beam, sill beam, seal seats, wall plates,
embedments for trunnion brackets to fix in the concrete beam, embedments for
hoist supporting structure, dogging devices , groove embedded frame at deck
level suitable for removable/ fixed steel groove cover with removable steel
groove cover.
Two sets of double acting hydraulic cylinders of sufficient capacity but not less
than 900T (2 X 450T per gate for pulling and 2 x 100 T per gate for pushing),
with spherical self lubricating plain bearings on either trunnion ends, hoist
supporting structure including anchorage system, and other associated
components required necessary for the erection and commissioning etc.
Two independent units of hydraulic power pack for the two numbers of gates
each comprising two motors( One standby), two pumps (One standby), control
panel, piping, hydraulic oil for first filling, pressure gauges, flow control valves,
direction control valves etc. with controls, manual controls, limit switches and
other fittings. Each power pack shall be standby for the adjacent unit for which
inter linking shall be made.
Two sets of double acting hydraulic cylinders and requisite power pack of
sufficient capacity but not less than 500T (1 x 500T per gate) alongwith power
packs for partial movement of eccentric trunnion pin, with spherical self
lubricating plain bearings on trunnion ends, hoist supporting structure including
anchorage system, and other associated components required necessary for
the erection and commissioning etc.
One No. portable oil filter unit for filtration, dehydration and degasification of
hydraulic oil.
Provision shall be made for supply of one number gasoline engine operated
portable power pack capable of operating one radial gate at 25% of the rated
operating speed.
Two sets of 1200mm dia air vent pipes for each tunnel spillway for aeration
requirements downstream of the tunnel spillway radial gates sill area. (This air
vent pipe shall be provided as per model studies recommendation.)
One electrically operated gantry crane of adequate capacity (but not less than
40T) with appropriate gears, pinion, reducers, motors, brakes, limit switches,
rope drums, wire ropes, lifting attachments, sheaves, crane rails and
embedments, end stoppers, fixtures, cable reeling/ trailing cable for all supply
arrangement, operator’s cabin, ladders, hand railings, walkways etc. for
installation and maintenance purposes of hydraulic hoists and tunnel spillway
gates.
3
GTS
Pakal Dul H E Project
One wheeled type Bulkhead gate, for clear opening size of 6.20m wide x 7.0m
high comprising of skin plate, vertical stiffeners, horizontal girders, end vertical
girders, seal assemblies, filling in valves in top unit, lifting attachment, side
guide shoe assemblies, bumpers etc.
Two sets of first stage embedded part inserts, corner angles, groove
embedded frame at deck level suitable for removable/ fixed steel groove cover
etc.
Two sets of second stage embedded parts complete with wheel tracks, sill
beam, Lintel beam, side seal seats and bases, groove and lintel liner, side
guides, dogging devices, groove covers and receiving frames, anchors with
double nuts and washers removable steel groove cover etc.
One electrically operated gantry crane of adequate capacity (but not less than
230T), shall be provided with appropriate gears, pinion, reducers, motors,
brakes, limit switches, rope drums, wire ropes, lifting attachments, sheaves,
crane rails and embedments, end stoppers, fixtures, cable reeling/ trailing cable
for all supply arrangement, operator’s cabin, ladders, hand railings, walkways
etc. The bulkhead gate shall be directly attached to Gantry crane.
1.3.2 Surface Spillway Radial Gates, Flap Gates, Hydraulic Hoists, stoplog
Gates & Gantry Crane.
i) Gate & Hydraulic Hoists
Two No. crest type radial gate for clear opening size of 12.0m wide x 16.00m
high complete in all respect with skin plate, stiffeners, bracings, arms, girders,
trunnion assemblies, trunnion brackets, shields, flow breakers, post tensioned
anchorage system for supporting trunnion beams, seal assemblies, guide roller
assemblies, dogging device, lifting attachment and other miscellaneous fittings
i.e. walkways, hand railings, ladders etc. as specified complete in all respect.
Two sets of first stage and 2nd stage embedded parts complete with
embedments for first stage, lintel beam, sill beam, seal seats, wall plates,
embedments for steel trunnion beam/yoke girder for fixing the gate trunnion,
fabricated radial pier guide members, trunnion bearing foundation plates, post
tensioned trunnion anchor rods, sleeves, nut, frames/supports, embedments for
hoist supporting structure, dogging devices groove embedded frame at deck
level suitable for removable/ fixed steel groove cover with removable steel
groove cover etc.
4
GTS
Pakal Dul H E Project
Two pairs of hydraulic cylinders of sufficient capacity but not less than 200T
(100T each), with spherical self lubricating plain bearings on either trunnion
ends, hoist supporting structure including anchorage system, and other
associated components required necessary for the erection and commissioning
etc.
Two independent units of hydraulic power pack for the two numbers of gates
each comprising two motors( One standby), two pumps (One standby), control
panel, piping, hydraulic oil for first filling, pressure gauges, flow control valves,
direction control valves etc. with controls, manual controls, limit switches and
other fittings. Each power pack shall be standby for the adjacent unit for which
inter linking shall be made.
Provision shall be made for supply of one number gasoline engine operated
portable power pack capable of operating one radial gate at 25% of the rated
operating speed.
Two sets of 8.00m x 2.00m size flap gate in the skin plate body of above radial
gates complete with skin plate, stiffeners, girders, seal assemblies, guides,
lifting attachment complete in all respect.
Two pairs of double acting hydraulic cylinders of sufficient capacity but not less
than 100T each with spherical self lubricating plain bearings/bushings on either
ends, gate position indicators and other associated components required
necessary for the erection and commissioning etc.
Two independent units of hydraulic power pack & Control system for the flap
gates to be operated individually including motor, pump, control panel, piping,
pressure gauges, flow control valves, direction control valves etc. with controls,
manual controls, limit switches, lightings and other fittings. Each power pack
shall be standby for the adjacent unit for which inter linking shall be made.
One number oil purifier of capacity 15-17 lts/hr complete with all accessories,
equipments, instruments etc. for radial gate shall be provided to purify the
hydraulic oil used in servomotor. The hydraulic oil purifier shall be
electrostatic liquid cleaner type and able to purify the suspended particle
more than 5 µm. Unit shall be supplied along with paper and other
consumable required for 5 years of successful operation of machine.
One number of Low vacuum dehydration and degasification unit for Radial
Gates shall be provided to remove moisture and dissolved gases from the
used hydraulic oil in servomotor. The capacity of the vapouriser shall not be
less than 50 lts and capacity of vacuum pump shall not be less then 50
lts/min.
Two sets of first stage embedded parts insert, corner angles groove embedded
frame at deck level suitable for removable/ fixed steel groove cover etc.
5
GTS
Pakal Dul H E Project
Two sets of second stage embedded parts complete with slide tracks, sill
beam, lintel beam, side seal seats and bases, groove liner, removable steel
groove cover, side guides, dogging devices, anchors with nuts and washers
etc.
Two sets of storage structure including its embedded parts comprising, side
guides, dogging arrangement and removable steel groove covers suitable to
cover for stop log units.
One lifting beam with automatically engaging and disengaging hooks, lifting
lugs and sheaves, side frames with guide rollers, pilot tubes, probe mechanism/
arrangement to ensure proper seating of lifting beam with stop log units.
One electrically operated gantry crane 100T capacity, having Long travel and
Cross travel arrangement provided with appropriate gears, pinion, reducers,
motors, brakes, limit switches, rope drums, wire ropes, lifting attachments,
sheaves, crane rails and embedments, end stoppers, fixtures, cable reeling/
trailing cable for all supply arrangement, operator’s cabin, ladders, hand
railings, walkways, lighting etc.
1.3.3 Intake Gates and Hoists, Intake Bulkhead Gates & Hoists
Three sets of first stage embedded parts and corner angles, bonnet body etc.
and groove embedded frame at deck level suitable for removable/ fixed steel
groove cover etc.
Three sets of second stage embedded parts complete with wheel tracks, sill
beam, lintel beam, side seal seats and bases, groove liners, removable steel
groove cover, side guides, suitable dogging arrangements to hold the gates in
open position, bonnet body, cylinder supports etc. 2nd stage anchorages with
nuts and washers etc.
Two sets of double acting hydraulic hoist of sufficient capacity but not less than
(350T pulling/305T pushing each), with spherical self lubricating plain
bearings and other associated components required necessary for the erection
and commissioning etc.
Two independent units of hydraulic power pack for the two numbers of gates
each comprising two motors( One standby), two pumps (One standby), control
panel, piping, hydraulic oil for first filling, pressure gauges, flow control valves,
direction control valves etc. with controls, manual controls, limit switches and
other fittings. Each power pack shall be standby for the adjacent unit for which
inter linking shall be made.
Provision shall be made for supply of one number gasoline engine operated
portable power pack capable of operating one Intake gate at 25% of the rated
operating speed.
6
GTS
Pakal Dul H E Project
One electrically operated gantry crane of adequate capacity (but not less than
30T) having long travel and cross travel arrangements with appropriate gears,
pinion, reducers, motors, brakes, limit switches, rope drums, wire ropes, lifting
attachments, sheaves, crane rails to cover all 3 (three) Intakes, end stoppers,
fixtures, including embedments, cable reeling/ trailing cable for all supply
arrangement, operator’s cabin, ladders, hand railings, walkways etc. for
installation and maintenance purposes of hydraulic hoists and Intake gates.
Three sets of first stage embedded parts and corner angles, groove embedded
frame at deck level suitable for removable/ fixed steel groove cover.
Three sets of second stage embedded parts complete with wheel track
assemblies, sill beam, lintel beam, side seal seats and bases, groove liners,
side guides, suitable dogging arrangements to hold the gates in open position,
2nd stage anchorages with double nuts and washers removable steel groove
cover etc.
One nos. electrically operated gantry crane of adequate capacity but not less
than 165MT for operation of gate under balance head condition having long
travel arrangement provided with appropriate gears, pinion, reducers, motors,
brakes, limit switches, wire ropes, rope drums, lifting attachments, sheaves,
crane rails and embedment, end stoppers, fixtures, cable reeling/ trailing cable
for all supply arrangement, operator’s cabin, ladders, hand railings, walkways
etc.
(iii) Model study of complete intake gate and trash rack arrangement to
determine the hydrodynamic forces on each Intake bulkhead gate/ Intake
gate and aeration requirement of Intake Gate and Bulkhead Gate.
One set of first stage inserts and embedded parts suitable for trash rack
covering complete opening of intake structures 88.50m (wide) x 19.50m
(Vertical Height), (consisting of an intermediate pier at the center line of intake
and 0.5 m bearing for trash rack at each end) in all respect in accordance with
these specifications.
One set of vertical trash racks and fabricated in 88 numbers of panels each of
size 3.05m wide x 6.5m high comprising of trash bars, framing members,
vertical support members, panels for all three Intakes complete in all respect in
accordance with these specifications.
One set of 500mm dia. and three sets of 400mm dia. electrically operated
Knife edge gate valves to regulate flow through environment release pipes
including supports, dismantling joints etc. (The pipes are not in HM Contractor’s
scope).
7
GTS
Pakal Dul H E Project
Four number hinged type adit gate suitable for opening size of 3.0m wide x
3.0m high comprising of skin plate, stiffeners, girders, sealing and bearing
members, connecting hinge members and suitable piping and valves (
minimum 250 mm Ø) for dewatering purpose and pressure gauge for
measuring HRT water pressure. These gates are proposed for adit plugs at
adit-1 , adit-1A, adit-2 and adit-2A.
Four sets of fabricated embedded parts for gate opening of 3.0m x 3.0m
consisting of track cum sealing frames, embedments required for fixing hinges
and locking bolts etc. complete in all respects including first stage anchors.
Four No. fixed wheel type Tail race gates for opening size 5.5 m wide x 5.5
m high including skin plate, vertical stiffeners, horizontal girders, bottom lip,
end vertical girders, wheel assemblies, guide rollers assemblies, top, side and
bottom seals, lifting attachments, dogging arrangement etc suitable for 2nd
stage embedded parts.
Four sets of first stage embedded parts and corner angles, etc. and groove
embedded frame at deck level suitable for removable/ fixed steel groove
cover.
Four sets of second stage embedded parts complete with wheel tracks, sill
beam, lintel beam, side seal seats and bases, groove liners, removable steel
groove cover, side guides, suitable dogging arrangements, etc. 2nd stage
anchorages with nuts and washers etc.
Four sets of electrically operated fixed rope drum hoists of capacity not less
than 85 MT, including wire ropes, drums, shafts, couplings, gearing
arrangement, brakes, motors, gate position indicator, limit switches, control
panels, cables and wiring with fixing plates and covers, manual operating
arrangements etc.
8
GTS
Pakal Dul H E Project
ii) Gate position indication and monitoring of tunnel spillway gates, surface
spillway gates and gate position indication of Intake gates and tail race
gates.
v) Two sets of water level measuring and indication Equipment along with
necessary alarms at dam area.
vi) Two sets of water level measuring system to indicate balance head
condition of intake gates.
vii) Four sets of water level measuring system to indicate balance head
condition of Tail race gates.
9
GTS
Pakal Dul H E Project
1.3.11 Spares
Mandatory spare parts for gates, hoists and cranes, remote control system, DG
set etc. as per list. Additional spares recommended by bidder for 5 years
trouble free operation.
Tools and equipment including special tools required for repair and
maintenance as per list enclosed.
Ten (10) sets of operation and maintenance manual containing drawings, all
catalogue and brochures for plants and machinery, handling procedures for
assemblies & sub assemblies of all equipment covered under this specification.
2.0 Standards
Latest Indian Standards for design, testing, workmanship, material and Works
have been selected mostly in these specifications as a basis of reference.
When IEC or ISO Recommendations or other Standards are referred to, the
edition shall be current at the time of issue of Tender Documents, together
with any amendments issued to that date.
• BS : British standard.
10
GTS
Pakal Dul H E Project
• EN : European Standard
S. No Description Standard
1. Recommendation of structural design of
fixed wheel gates. IS: 4622
11
GTS
Pakal Dul H E Project
23. Code of practice for plain & reinforced concrete. IS: 456
12
GTS
Pakal Dul H E Project
Standards other than those stipulated in the Bid documents shall be acceptable
after scrutiny provided they ensure equal or higher quality than those specified
in the specifications. The contractor shall submit for approval the detailed
standards, which he proposes to use.
If these specifications conflict in any way with any of the above standards or
codes, these specifications and drawings shall take precedence.
All material used for the fabrication of the equipment shall conform to relevant
Indian standard or equivalent International standard as DIN, ASTM, or BS
unless otherwise specified.
13
GTS
Pakal Dul H E Project
viii. Ballast if any Cast Iron/ Structural IS: 210/ IS: 2062
steel
ix. Lifting hooks (for lifting beam) Forged steel IS: 2004 Cl. IV
b Seal Bronze/rubber
seating on stainless
c Stem Corrosion resistant IS 1570 (Part-V)
steel
xii Piping Mild Steel IS: 2062
14
GTS
Pakal Dul H E Project
15
GTS
Pakal Dul H E Project
16
GTS
Pakal Dul H E Project
The bidder shall include details of proposed sub contractors including vendors
for items of supply or services, it proposes to sublet or procure bought out
items. The capabilities of sub contractors and vendors shall be evaluated for
acceptability based on previous references/ experience / credentials etc. to be
furnished by the bidder along with tender. A list of approved vendors along with
qualification criteria is given in annexure A.
2.4.1 Permissible Stresses for Spillway Gates, Adit gates and Intake Gates
a) Structural steel
b) Bearing stresses
c) Wheel
d) Wheel pin
17
GTS
Pakal Dul H E Project
e) Corrosion allowance of 1.5 mm for the skin plate of gate except for Tunnel
Spillway radial gate is to be considered.
a) Structural steel
b) Bearing stresses
2.4.3 Permissible Stresses for surface spillway stop log, tunnel spillway
bulkhead gate, Intake bulkhead gate, Tailrace tunnel gates.
Structural steel
i) Direct compression and compression 0.55 Y.P.
in bending
ii) Direct tension & tension in bending 0.55 Y.P.
b) Bearing stresses
c) Wheel
18
GTS
Pakal Dul H E Project
d) Wheel pin
a) Drum
b) Gears
c) Shafts
iv) Allowable stress for shafts with keys will be 75% of above value.
2.4.5 Permissible Stresses for Hoist Bridge, Hoist Support, Trestles & Hand
Railing (Clearly above Water)
As per IS 800, if not specified otherwise except hydraulic hoist support structure
where the permissible stresses shall be taken as per clause 2.4.1 of GTS
(Permissible Stresses for Gates).
2.4.6 Permissible stresses for Trash racks
The permissible stresses for trash racks shall be as specified in IS: 11388.
19
GTS
Pakal Dul H E Project
20
GTS
Pakal Dul H E Project
shall be delivered by the Contractor to the Engineer within the periods, and in
a number and quality as specified in the General and Special Conditions.
The Engineer reserves the right to request the Contractor additional
documents as may be required for proper understanding and definition of
constructional, operational, co-ordination or other matters.
The contractor shall inform the owner about the software to be used for
analysis and design. The diskettes / CD of such software shall be
provided to the owner at no cost to the owner.
The Contractor shall co-operate with other Contractors in the exchange of
drawings, dimensions, data and all other information required to ensure
proper co-ordination of the work. All documents to be supplied shall be
submitted in accordance with the agreed programme so that any comment
and change requested by the Engineer can be taken into account before
starting of the manufacturing in the workshop and/or erection or installation at
the Site.
If the Contractor fails to submit such documents, then the later execution of
changes requested by the Engineer and the resulting additional cost and/or
delays shall be the Contractor's liability. The Contractor shall not be released
of his responsibility and guarantee after drawings and computations have
been approved by the Engineer.
The preparation of drawings, computations or other technical documents shall
not be subcontracted by the Contractor without the written authorisation of the
Engineer. In such a case of subcontracting the Contractor shall be fully
responsible for such drawings, computations and other technical documents
as if they were done by himself.
If required for proper understanding of the documents, additional
descriptions/explanations shall be given on these documents or on separate
sheets. All symbols, marks, abbreviations, etc., appearing on any document
shall clearly be explained by a legend on the same document or on an
attached sheet.
Each device appearing on any document (drawing, diagram, list, etc.) shall
clearly be designated. The abbreviation mark used for an individual device
shall be identical throughout the complete documentation so as to avoid
confusion. All documents shall have a uniform title-block as outlined in the
specification. Beginning with the very first submittal to the Engineer, the
Contractor's drawings shall bear a serial number corresponding to a drawing
classification plan of the owner.
Any comment given by the Engineer on "I" type drawing shall have the same
effect as if it were given on "A" type drawing.
21
GTS
Pakal Dul H E Project
Diagrams
• The circuit diagrams shall show the power circuits in all phases with the
main apparatus as well as the pilot circuits (measuring and control
circuits). It shall show in full the functioning of part or all installations,
works or circuits with all required technical information. This shall show
all technical blocks control cubicle, cable details, cable tracks etc.
• Electrical wiring diagrams of hoist, hydraulic circuit, piping / cable lay out
drawings, performance curves, specifications and catalogue numbers of
all motor control centres, control panels, motors and accessories.
22
GTS
Pakal Dul H E Project
The Engineer in-charge shall have the right to ask the contractor to make any
change in the designs and drawings, which may be necessary in the opinion of
the Engineer in-charge to make the equipment conform to the provisions and
intent of those specifications without additional cost to the purchaser.
The Contractor shall carry out and be responsible for the design of works.
Design shall be prepared by qualified designers who are engineers or other
professionals and have experience and capability necessary for the design.
The contractor undertakes that the designers shall be available to attend
discussions with the Engineers at all reasonable times until the date of
relevant Defect notification period.
The Contractor shall prepare all Contractors’ Documents, and shall also
prepare any other documents necessary to instruct the Contractor’s
Personnel. The Employer’s Personnel shall have the right to inspect the
preparation of all these documents, wherever they are being prepared.
Any approval or consent, or any review shall not relieve the Contractor from
any obligation or responsibility therein contract.
3.3 Submissions
23
GTS
Pakal Dul H E Project
Design
Radial Gates
Hydraulic Hoists
Power Pack
24
GTS
Pakal Dul H E Project
Hydraulic Hoists
Design Criteria, Design of Cylinder (Radial & Cylinder heads end connections
Flap gate), Stem, Rod end clevis, Head end (fasteners), piston, threads and
clevis/attachment, Fully extended/fully connections among various mating
collapsed length of cylinder assembly, components, Details & specification
Kinematic details in form of line of sealing and bearing
diagram/sketches/data of gate & hoist components, position indicators,
establishing & describing working stroke, total Details of all other components.
stroke, reserve stroke on both ends.
Detail design of all Pressure Shaft A complete list of all technical data,
Liner/ Structural analysis/ FEM analysis/
software used etc.
Penstock, their specials (like Bends,
manholes, transitions, bifurcations
thrust collar etc) and liner thickness
including stiffeners, if any, and
respective welding details.
All details of equipment and materials required for design /fabrication and/or
assembly and drawings to be cross-referenced to all other documents
25
GTS
Pakal Dul H E Project
Detailed design of all Tunnel Liner/ A complete list of all technical data,
their specials (like transitions etc) and liner Structural analysis/ FEM analysis/
thickness including stiffeners, if any, and software used etc.
respective welding details.
All details of equipment and materials required for design /fabrication and/or
assembly and drawings to be cross-referenced to all other documents
Selection of Knife edge gate valves. A complete list of all technical data.
Adit Gates
Design Criteria, Design/ End carriage, Rails and attachments, Pulleys/ sheaves
Selection of Rope drum, & attachments, buffer/bumper, overload/slack rope
Reduction gearing, mechanism, limit switches, power supply arrangement,
Shafts, Wire rope and storm/parking clamps/anchors, Turn buckles, cabin,
attachments, Motors, Walkway, ladders, handrails, grating/ chequered
Brakes, Wheels, hoist plate/hatch covers, hydraulic actuators, hydraulic
Supporting structure/ control system other components, rope clamps,
Gantry frame structure. couplings, Plummer blocks.
Trash rack
For approval For review/Information
Bar, Horizontal Embedded frame, Guides, other details
members
Connections (weld/bolt)
Lifting beam
26
GTS
Pakal Dul H E Project
Drawings
27
GTS
Pakal Dul H E Project
Lifting beam
General assembly drawing of lifting beam Probe mechanism, all types of sub-
assembly drawings, detailed
drawings of all components etc.
Trash rack
28
GTS
Pakal Dul H E Project
DG SET
Adit Gates
Instrumentation System
29
GTS
Pakal Dul H E Project
The Contractor shall provide certain types of drawings and other technical
data to the Engineer for approval, such as the following to the extent
applicable:
(1) Drawing List: A complete list of all drawings and technical data.
(3) Detail Drawings: All penstock and liner thicknesses shall be clearly
defined, including stiffener dimensions, if any, and respective welding
details shall be shown. All details of equipment and materials required
for fabrication and/or assembly shall be clearly defined. These drawings
are to be cross-referenced to all other drawings.
(4) A QA/QC plan as per ASME Section VIII, Division 2, or equal, shall be
submitted. This plan shall also cover subcontract monitoring. The
QA/QC plan shall ensure weld trace-ability to the welder (such that code
stamping of welder identification on the weld will not be required, e.g.
through the use of a weld map) both for field and shop weld.
The plan shall address frequency and scope of fabrication, shop audits
and job site erection audits. Also the plan shall define the procedure to
be used to ensure that test coupon welding is representative of the
actual procedure being executed.
(6) Material certification shall be submitted to the Engineer with all test
results for approval. This also includes welding consumables and
miscellaneous materials.
(7) All deviations from the Specifications and/or Drawings shall be clearly
noted and submitted to the Engineer for approval.
The Contractor shall provide a certificate with the following information for
each steel liner (penstock pipe) section:
30
GTS
Pakal Dul H E Project
Each certificate shall show in sketch form the sequence of the welds, the
position of the radiographs and repair locations. A sample certificate (with
hypothetical entries) shall be submitted to the Engineer for review prior
to liner shipments.
The motor lists shall be prepared and shall contain at least the following
information/data:
• Description
• Rated capacity
• Service factor (ratio between motor output and power requirement of the
driven machine)
• Rated speed
• Rated voltage
• Rated current
31
GTS
Pakal Dul H E Project
• Duty (continuous/intermittent/start-up)
• Denomination of feeder
• Motor protection
The motor starter lists shall include all starters, thyristors and contactors used
for motors and contain the following technical information as a minimum:
• Type and current rating of the back-up fuses/MCBs for the main and
control circuits
32
GTS
Pakal Dul H E Project
The Cable Lists shall include for each individual cable the following as a
minimum:
• Cable type
• Rated voltage
• Overall diameter
• Cable routing
• Interconnecting wiring
• This list shall indicate all measurements, local as well as remote, and
shall contain at least:
These lists shall indicate all alarms and shall contain at least:
33
GTS
Pakal Dul H E Project
This list shall indicate all control actuators and control valves and shall
contain at least:
• Item/code number
• Manufacturer
• Place of manufacture
• Place of test
• Date of test
• Standards applied
• Certification
• Remarks
Lists of Tools and Appliances shall detail for all tools and appliances included
in the scope of supply:
34
GTS
Pakal Dul H E Project
- Description
- Quantity
- Weight
Spare part lists shall detail for all parts included in the scope of supply:
• Description
• Quantity
• Weight
This list shall contain the used Works identification numbers in alphanumeric
order and for each of them a description (the defined Works denomination, for
example as written on the Works label) and the location (short definition of
outdoor area and level elevation or building/room with elevation and room
number).
The operation and maintenance manual shall be prepared and provided by the
contractor and shall contain following information in sufficient detail to enable
35
GTS
Pakal Dul H E Project
the employer to maintain dismantle, reassemble, adjust and operate the works
with all its works and installation.
The manuals shall include a separate and complete section describing the
following:
• Maintenance instructions.
• As built drawings.
• Spare parts.
The manuals shall describe and illustrate the procedure for assembling,
adjusting, operating and dismantling of each component and control system.
The maintenance of each component shall be described, including the
recommended frequency of inspection and lubrication.
Three (3) copies of the manuals shall be submitted in English in draft for
approval of Engineer- in-charge within 3 months after the final approval of the
equipment. Ten (10) suitably bound copies shall be provided to
Engineer-in-charge along with soft copies on good quality compact disc (two
sets) suitable for editing and printing of the text & drawings not later than 30
days after receipt of approval.
Manufacturer shall ensure that his installation supervisor has a copy of all
approved drawings and the manuals in his site office.
The Contractor shall monthly submit four (4) copies of the progress reports in
a format acceptable to the Engineer, detailing the progress of the work during
the preceding period. The report shall contain (but not be limited to) the
following information:
36
GTS
Pakal Dul H E Project
During erection the Contractor shall, before the tenth (10th) day of each
calendar month, submit four (4) copies of the monthly progress reports in a
format acceptable to the Engineer, detailing the progress of the work during
the preceding month. The report shall contain but are not be limited to the
following information:
37
GTS
Pakal Dul H E Project
Certificate the spare parts shall be checked and tested at the Site by the
Contractor in presence of the Engineer.
Acceptance of any spare parts will not take place before the Contractor has
submitted the complete final detailed list of all spare parts and tools.
All spare parts shall be protected against corrosion and shall be marked with
identification labels in the Ruling Language. The identification shall be in
accordance with the agreed Works Identification System.
All spare parts, tools and materials shall be delivered in marked boxes of
sufficient sturdy construction to withstand long term storage.
The required Mandatory spare parts are listed separately in the Particular
Technical Specifications. The price for each listed special spare part shall be
quoted individually in the Price List; the total price shall be included in the
Total Tender Price.
If any additional spare parts are recommended by the tenderer, these shall be
stated in quantity and description in the Technical Data Sheets for each item.
The prices for that may be indicated in separate price schedule. This may not
be treated as the part of tender price schedule.
The scope of work shall include all special tools, as well as all special devices
including lifting devices, ropes, etc. necessary for total assembly and
disassembly of all parts of the supplied Works.
Tools and tackles required for maintenance of the specified equipment shall
be quoted individually in the price list. The total price shall be included in the
total tender price.
If any additional tools and tackles are recommended by the tenderer, these
shall be stated in the quantity and description in the Technical data Sheets for
each item.
Orders for recommended tools and tackles shall be optional to Employer, for
a period of three years after the date of Contract award.
38
GTS
Pakal Dul H E Project
Specifications are valid for all parts of the Works except where they are varied
by additional and/or special requirements, specified in the Particular
Technical Specifications.
The parts of the Works shall be designed and arranged so that they can be
easily inspected, cleaned, erected and dismantled without involving large
scale dismantling of other parts of the Works. They shall be designed, and
manufactured in accordance with the latest recognised rules of workmanship
and modern engineering practice.
All parts of the Works shall be suitable in every respect for continuous
operation at maximum output under the climatic conditions and operating
conditions prevailing at the Site.
For individual items of the Works, materials and design are to be selected
which are best suited for the operating conditions to which the parts in
question will be subjected. Only such design and types of Works shall be
offered which has confirmed its reliability in long-term continuous operation.
Innovations cannot be accepted for the main Tender but can be offered as an
alternative proposal.
All live, moving and rotating parts shall be adequately secured in order to
avoid danger to the operating staff. All electrical components shall be earthed
as per the latest practice.
39
GTS
Pakal Dul H E Project
Suitable lifting eyes and backing-out bolts shall be provided where required or
where they will be useful for erection and dismantling.
Pockets and depressions likely to hold water shall be avoided, and if not
avoidable they shall be properly drained. Parts of the Works principally
intended for standby purposes shall be protected from corrosion by careful
choice of material and if necessary, by additional means these should not
reduce their continuous standby readiness.
All design details and layout matters shall be discussed in periodic meetings
with the Engineer. The first design meeting between the Contractor and the
Engineer shall take place within 28 days after the Date of Commencement.
Further design meetings shall take place as agreed between the participants
until the design work is completed.
After designs and drawings are completed and approved, the manufacturer
shall supply 4 prints of all the design and 8 prints of drawings. However,
prior to completion of contract manufacturer shall supply 6 prints of all
approved “As Built Drawings” plus soft copy on good quality compact
disc (two sets) suitable for editing and printing along with 2(two) good
quality polyester film transparencies suitable for micro filming.
The Works shall be designed for the worst possible combination of the
following loading conditions:
• Other loads
40
GTS
Pakal Dul H E Project
The full reservoir level, maximum water level, sill elevation and design criteria
are described in particular specification required for the design.
The basic wind load of 600 N/m.sq. shall be applied on the vertical
projected area of exposed equipment, multiplied by the form factors for
the different type of structures in accordance with IS:875.
The wind load for the stability check of gantry crane, etc. shall be 600
N/m sq. while operating and 1500 N/m sq. when out of service.
Other Loads
Load on the foot path, balcony floor, platform/ groove cover: 5000N/m2.
COMBINATION OF LOADS
2. Occasional load case- considers the loads which occur less frequently,
such as:
b. Wind loads
c. Temperature effects
b. Seismic effects
The following design clearance shall be submitted to the Engineer In-charge for
approval: -
• Clearance between end of main Roller housing (side of gate) and gate
guide.
41
GTS
Pakal Dul H E Project
All components shall be fabricated in accordance with IS: 4622, IS: 4623, IS:
5620 & IS: 9349 except as noted below: -
• The machined sealing surface of the sill and lintel beams and side guides
shall be straight within 0.5 mm and level within 1.0mm over the whole
length with a straight edge.
• The roller path below the lintel shall be straight within 0.4 mm in any 3 m
length and within 0.8 mm over the whole length and shall not deviate from
a vertical line in any direction by more than 1.0 mm. Roller path faces for
the same gate shall be in the same plane within 1.0 mm
• The roller path above the lintel shall not deviate from a vertical line in
any direction by more than 2 mm and shall be straight within 2 mm over
the full length.
• The side roller paths shall be straight within 1.0mm in any 3 m length
and within 2mm over the full length. The side roller path shall not
deviate from a vertical line in any direction by more than 2mm
• The distance between the side roller paths and the main roller paths
shall not vary by more than 3mm.
• Radial run out of assembled roller shall not exceed 0.025mm of total
indicator reading measured at the roller tread.
• Wheel treads, seal bases (top and side), bearing faces and seal faces
(side and top) on an assembled gate should be in a true plane.
42
GTS
Pakal Dul H E Project
• Seals
• Fasteners
• Valves
• Thermometers
• Pressure gauges
• Flow meters
• Auxiliary relays
• Contactors, fuses
• Control devices
All instrument scales shall be written in the Ruling Language of the Contract.
43
GTS
Pakal Dul H E Project
For general requirements concerning the quality of materials and Works refer
to the General Conditions of contract.
All materials shall comply with the latest IS standards, or other Standards
specified unless otherwise specified. All drawings and /or material lists shall
show IS Standard. The materials and workmanship throughout shall be the
best of their respective kind and free from defects. The design of all equipment
shall be such that installation, replacements and general maintenance may be
undertaken with the minimum of time and expense. All fitted joints shall be
machined and castings shall be spot faced for nuts. All components shall be
built in accordance with approved drawings only. No patching plugging or other
such means of overcoming defects, discrepancies or errors shall be done
without written permission of Engineer-in-charge.
Similar parts shall be made to gauge where possible, to ensure that such parts
are interchangeable one with the other.
Dimensions shown on the drawings shall be adhered to closely and the work
shall in all cases be of high grade and carefully performed to the satisfaction of
the Engineer-in-Charge. The contractor shall warrant all materials and
workmanship furnished by him to be free from injurious defects. He shall
replace free of cost any defective materials or workmanship discovered during
erection or in guarantee period and shall pay the actual cost of the correction
on the field of any errors for which he is responsible.
The Contractor shall supervise the leveling and adjustment of all parts of the
equipment on the foundations and after each item is set up and the
Engineer's approval obtained, grouting or concreting will be carried out by the
civil works contractor's and verified by the Contractor. The Contractor shall be
responsible for ensuring that such work is carried out to his satisfaction and
that levels and adjustments made by him are not disturbed by the grouting
operation. The Contractor shall be responsible for ensuring that the positions,
levels and dimensions of the Works are correct according to the drawings
notwithstanding that he may have been assisted by the Engineer in setting
out the said position, levels and dimensions.
44
GTS
Pakal Dul H E Project
5.7.1 General
Each important part to be delivered under this Contract shall be equipped with
permanent identification plates in readily visible locations. Whether a part
shall be considered as important in this respect shall be decided by the
Engineer.
All equipment shall be provided by a securely fastened name plate showing the
maker's name, model, serial numbers, year of manufacture, main
characteristics data of the respective equipment and further relevant
information specified in the applicable standards or necessary for the proper
identification of the equipment involved.
45
GTS
Pakal Dul H E Project
5.8 Fabrication
Care shall be taken that the side seals of gate bear evenly and with uniform
pressure throughout their length on the side seal seats embedded in the faces
of the piers and that the bottom seals bear evenly on the bottom seal seat (sill)
embedded in crest. The roller axle supports and lifting connection shall be
accurately line bored so that the axis of all such holes be perpendicular to the
vertical centre line of the gate and shall lie in a common plane which shall be
parallel to the finished surface for the seal bases. The wheel pins shall be
finished to required surface finish. The sealing faces for the vertical seals,
bearing bars and lintel seal shall be finished to required surface finish. The bolt
holes for guide rollers shall be accurately bored only after the gate has been
completely field assembled and position of guide rollers located in stop logs /
gates.
46
GTS
Pakal Dul H E Project
plane surface for the track. The faces of the seal seats shall be finished so as
to lie in one plane within permitted tolerances. The crowns of the track shall lie
in a true vertical plane. The splice length for embedded parts such as seal
seats, track paths, guides etc. shall generally not be less than 6.0m.
All structures, parts of the gate frames shall be straight and free from twist.
Trunnion pedestal shall be stress relieved. The rest beam supporting the
trunnion bearings shall be securely fastened to anchor bolts embedded in the
piers. All the connections in the trunnion pedestal are heavily stressed under
load and special precaution should therefore be taken to ensure that such joints
are without flaw. The bottom sill beam, wall plates, liners etc. shall be fabricated
of steel plates/ structural sections and shall be provided with suitable
anchorages for rigid connection to the spillway crest, breast wall and the piers.
5.8.3 Fabrication of steel works
47
GTS
Pakal Dul H E Project
Accuracy of reamed and drilled holes: Holes shall be drilled and reamed so
accurately after assembly that not less than 85 per cent of any group of
continuous holes in the same plane shall show no off-set greater than 0.8mm
between adjacent thickness of metal.
The fabrication of the steel liners for pressure shaft shall be in accordance with
the specification, drawing and the corresponding approved design and
fabrication drawings and latest version of Indian Standard for unfired pressure
vessels (IS: 2825) or the equivalent standards specified under this Chapter. In
case of any difference between the above the specification shall govern.
Plates to be welded shall be cut to size and shaped by machining and/or flame
cutting. Where the plate thickness does not exceed 25mm, cold shearing may
be used provided that the sheared edge is cut back by machining or chipping
for a distance one quarter of the plate thickness but in no case less than 3mm.
48
GTS
Pakal Dul H E Project
b) Plate cutting may include plasma arc, oxy-acetylene gas with or without flux
injection or equivalent fusion cutting process. Any material damaged in the
process of cutting plates to size or forming welding grooves shall be
removed by machining, grinding or chipping back to sound metal. Surfaces
which have been flamecut shall be cut back by machine grinding so as to
remove all burnt metal, notches, slag and scale but slight discoloration of
machine flame cut edges on mild steel shall not be regarded as detrimental.
After the edges of the plates have been prepared for welding they shall be
given a thorough visual examination for flaws, cracks, laminations, slag
inclusion or other defects. When plates are flame cut, the edges should be
examined after this operation. Edges which have been flame cut by hand
shall be cut back by machining or chipping for a distance of one quarter of
plate thickness but in no case less than 3mm.
Rust, scale, painting, oil slag etc. from the flame cutting or other
contamination of the fusion pieces shall be removed before welding is
commenced. The surfaces to be welded shall be free from foreign material
such as grease, oil or marking paint for a distance of at least 25mm from the
welding edges. Irregularities in fusion faces, which are likely to affect the
quality of welding, shall be removed before welding is commenced. All plate
edges after cutting and before carrying out further work upon them shall be
examined for lamination and also to make certain that marks have not been
caused by shearing. Plates for shell sections shall be formed to required
shape by a process that does not impair the quality of the material. However,
correction of curvature by blows will not be permitted. Cold-formed plates
material shall not be subjected to a deformation of more than five percent,
unless suitable heat treatment is carried out after such forming. Heat
treatment shall, however, be carried out even when the deformation is less
than 5 per cent if there is pronounced risk of brittleness through aging. The
deformation expressed as a percentage is obtained from the formula:
Deformation = t x 100
D
Where t = thickness of plate
Cold forming shall not be undertaken when the temperature of the metal is
less than 0°C. If the forming or bending operation takes place in hot
condition, no subsequent heat treatment is required, if the final shaping
process terminates within the correct temperature limits for the particular
material.
Where two plates at a welded joint differ in thickness the thicker plates shall be
trimmed to a smooth taper as per para 6.3.5 IS 2825 -1969.
Stiffener rings shall be fabricated in not more than ten circumferential sections
butt welded together and properly fitted and welded to the pipes, so that the
plane of rings will be normal to the axis of the pipe.
49
GTS
Pakal Dul H E Project
Bends and reducers shall be made of short segment of pipe with mitered ends.
Deflection angle between each successive segments shall not be more than
100. The segments shall be made with equal deflection angles except for the
end ones, which shall be of smaller deflection angles than the other segments.
The number of segment along with stiffener rings shall be adequate to take
care of the loads.
Each part of the pressure shaft liner section, curvature of the shell or surface to
which they are attached or its auxiliary parts shall be legibly marked to show
the unit of which it is a part and match marked to show its relative position in
the finished structure to facilitate assembly in the field. To ensure proper
matching of sections at the joints, expanding struts spiders may be used. Each
section shall be marked struts to show top of vertical diameter and the direction
of the flow. Unit marks and match marks shall be made with heavy stamps and
with paints. The contractor shall prepare marking drawings of each Pressure
shaft liner indicating clearly the location of each section and appurtenant parts
in the completed structure and shall furnish to the Corporation such drawings.
If Pressure shaft liner ferrules are transported for a long distance necessary
precaution shall be taken to provide bracing /spider to prevent deformation.
Where the finish is not indicated or specified, the type of finish shall be that
type which is most suitable for the surface to which it applies and shall be
consistent with the class of fit required.
As far as practicable, all work shall be laid out to secure proper matching of
adjoining unfinished surfaces. Where there is a large discrepancy between
adjoining unfinished surfaces, they shall be chipped and ground smooth, or
machined to secure proper alignment.
Unfinished surfaces shall be true to the lines and dimensions shown on the
drawings and shall be chipped or ground free of all projections and rough
spots. Depressions or holes not affecting the strength or usefulness of the
parts shall be filled in a manner approved by the Engineer.
50
GTS
Pakal Dul H E Project
5.10 Fasteners
Bolts, Studs, Nuts and Screws : They shall have standard threads and be of
high quality steel. All standard size bolts, studs, nuts and screws (including
their washers) shall be heavily protected against corrosion or made of stainless
steel if so specified in the technical Specifications. Nuts and bolts heads shall
be hexagonal in shape & truly faced. Nuts & bolts and screws, which might
become loose during operation shall be locked in fastened position by means
approved by the Engineer-in-charge.
All bolts shall have unified threads. Bolts in tension shall have a net section at
root of thread, 15 percent in excess of the net section required in tension.
Field Jointing: All fasteners for field joint shall be supplied 5 per cent in excess
of actual requirements. This should be indicated in the drawings/bill of material.
5.11 Welding
The cut surface shall be free from all visible defects such as lamination, surface
defects caused due to shearing or cutting or flame cutting operations. The
surfaces of plates to be welded shall be free from dust, grease and scale for a
distance of 12mm from the welding edge at the time of welding. Flame cutting
may be used in the preparation of the various members provided the operation
is performed carefully and the edge so cut are cleaned thoroughly after being
cut so as to expose clean metal. Any contour irregularities at points of critical
stress shall be removed by grinding.
When the welding process has been approved by the Engineer, the contractor
shall produce a record drawing to show the approved process. The drawing
shall include details such as the form of edges to be welded, electrodes and
other welding materials, welding sequence etc. Changes in the welding process
after the welding method has been approved shall require the consent of the
Engineer.
51
GTS
Pakal Dul H E Project
Unless otherwise allowed by the Engineer all welded parts to be welded shall
be manufactured of steel produced by open-hearth or electric furnace with
carbon content not more than 0.20 % and a Phosphorous content not more
than 0.05%.
All welding shall be done by the electric arc method or by a process, which will
exclude the atmosphere from the molten metal, except where otherwise
specifically permitted. The welding electrodes shall be heavily coated type
designed for all position welding. In assembling and during welding, the
component parts of built up members shall be held in place by sufficient
number of clamps or other adequate means to keep all parts in proper position.
All shop and field welding performed on the work shall be subject to inspection
by Engineer-in-charge when welding plates, of which one or both exceed
25mm in thickness. Continuous areas of plates around the welding operation
shall be preheated to not less than 700 c and kept at a substantially uniform
temperature throughout the process. The temperature shall be measured by
52
GTS
Pakal Dul H E Project
The welding sequence shall be planned to control and minimise distortion and,
where necessary, shall include stress relief to minimise residual stresses.
Minimum stress-relieving requirements are specified in the appropriate sections
of these specifications.
Stress Relieving
The post weld thermal stress relieving shall be part of approved welding
procedure and shall be carried out in accordance with the relevant provision
ASME boiler and pressure vessel code section VIII division–2 or IS: 2825. The
method statement procedure for conducting thermal stress relieving shall
depend upon the particular structure, grade and composition of steel and
thickness involved. The contractor shall obtain prior approval regarding the
above from Engineer.
53
GTS
Pakal Dul H E Project
If welding work is made under the condition of ambient temperature less than
5˚C, steel materials on weld joints shall also be preheated even though
application of preheating is not required due to the kind and thickness of the
steel materials under normal welding condition.
The relations between the carbon equivalent and the preheating temperature in
cases of manual welding shall be as follows:
Note: Ceq (%)= C+1/6 Mn + 1/24 Si + 1/40 Ni + 1/5 Cr + 1/4 Mo + 1/14 V and
Cu, P, etc., could be added as necessary.
a) After carrying out the complete first pass welding, the same shall be
grinded so as to achieve a U shaped groove in the backing strip, to enable
appropriate welding by 3.15mm electrode
54
GTS
Pakal Dul H E Project
b) After completion of root run & subsequent passes, the weld shall be
subjected to D.P. test for checking of surface defects needing rectification.
c) After completion of full welding again D.P. shall be done for checking of
surface soundness.
The shell sections of the completed Pressure shaft liner/pressure shaft liners
shall be circular within the limits defined hereunder. Measurement shall be
made to the surface of the parent metal and not to a weld, fitting or other raised
part. There shall be no flats or peaks at welded seams and the local departure
from circularity shall be gradual.
a) For plates of thickness 5mm or less than t/6 for a longitudinal seam and
t/4 for circumferential seam subject to a maximum of 1mm.
The individual cylindrical shell shall be reasonably square and straight. The
axis of the pipe sections shall be normal to the axis of the pipe within a
55
GTS
Pakal Dul H E Project
tolerance of 2mm on the radius. The edges of the plates of each course shall
be properly prepared for field welding. Unless otherwise specified the out of
straightness of the shell shall not exceed 0.3 per cent both of the total
cylindrical length any 5m. length (This tolerance may be omitted where the
individual shell length does not exceed 2m).
All field welds, wherever not spot radiographed or such joints which are
inaccessible to radiographic examination shall be subjected to ultrasonic
examination. The circumferential joints of pressure shaft liner not subjected to
radiographic examination shall be tested ultrasonically to 100%. The procedure
for the ultrasonic examination, the acceptance standards for welds etc. shall
conform to the relevant articles of ASME Boiler and pressure vessel code-
Section V.
All weld metal build up shall be examined over the full surface of the deposit by
either liquid penetrant examination or by magnetic particle examination. All
permanent hold down logs or devices welded to the steel Pressure shaft liner
shall be examined by either of the above two methods. Removal of temporary
logs and devices tack welded to the pressure shaft liner shell and subsequent
56
GTS
Pakal Dul H E Project
dressing shall be followed by either of the above two examinations viz. LPE or
MPE of the connection area.
The procedure and acceptance standards for the above methods shall conform
to the relevant articles of ASME boiler and pressure vessel code -Section V.
All primer and painting material shall satisfactorily fulfill the requirements
imposed by the site conditions, as well as the stresses to which the respective
equipment is subjected during operation of the works. Shades of the finished
coatings shall be as approved by the Engineer-in-charge.
Each coat of primer and paint shall be compatible with the previous and
subsequent coats. All pigmented primers and paints which will be used for
primer and painting at the site shall be delivered in original and sealed
containers packed by the manufacturer bearing brand name, colour
designation, storage and handling instructions.
The manufacturer shall supply full details regarding the extent to which
sand-blasting, primer and paintings will be carried out in his workshops (or his
sub-contractors, as the case may be) at the site and after erection. A properly
equipped paint shop shall be set up at the site using a specialist organisation,
experienced and skilled in the preparation and application of protective
coatings at the conditions prevailing at the site.
57
GTS
Pakal Dul H E Project
For removing rust and mill scale from structural steel, plate sheets, piping and
other steel surfaces, as well as from other parts blast cleaning shall be carried
out to clean bare metal. The average surface roughness after sand blasting
shall not exceed 40 microns. Sand blasting shall be performed with corundum
or sand of type approved by engineer-in-charge. Parts which cannot be blast-
cleaned shall be cleaned free from rust and scale by power tool cleaning to the
highest possible degree.
Coal tar painted surface which is directly exposed to Ultra violet rays should be
painted with aliphatic polyurethane having DFT of 75 microns in addition to total
DFT mentioned as below.
Stainless steel and bronze surfaces shall only be cleaned but not painted. All
surfaces of the embedded parts, which are to come in contact with concrete,
shall be cleaned as mentioned above and given two coats of cement latex to
prevent rusting during shipment and while awaiting installation. All finished
surfaces of the gates and stoplogs that will be exposed to atmosphere during
shipment or while awaiting installation shall be given a coat of gasoline
soluble rust preventive compound. For preservation of hydraulic cylinders
during shipment and while awaiting installation these shall be filled minimum
10% with hydraulic oil suited to temperature range for the particular Project,
and 2% VSI or equivalent corrosion inhibitor shall be added prior to dispatch
to site .The grade of oil shall be got approved from owner.
5.12.2.1 Gates, Bulkheads, Embedded parts, Trash Racks and Lifting beam
Perfect cleaning of all surfaces which are not to be covered with concrete shall
be carried out by sand blasting to the requirements of SA 2½ of Swedish
Standard SS 05.5900.
58
GTS
Pakal Dul H E Project
Over the prepared surfaces one coat of inorganic zinc rich primer / 2 coat of
Zinc rich primer by spray (preferably airless spray) should be applied giving a
dry film thickness of 70 ± 5 microns.
Lifting Beams
The following painting system shall be adopted for lifting beams. Over the
prepared surfaces by sand blasting, two coats of priming with zinc rich/Zinc
Phospahte primer conforming to IS 102, each coat giving a dry film thickness of
40 microns shall be applied. The finished paint shall consist of two coats of
alkyd based micaceous iron oxide paint. Each coat of paint shall give a dry film
thickness of 75 microns. The interval between coats shall be 24 hours. The
total DFT of all the coats shall not be less than 210 microns.
Hoists and supporting structure:- The parts after surface preparation shall
be given two coat of inorganic zinc silicate / Zinc phosphate primer paint
conforming to IS: 102 in the shop before dispatch. One further coat of primer
shall be applied after erection. The primer coats shall give a minimum dry film
thickness of 40 microns per coat. The finish paint shall consist of two coats of
alkyd based micaceous iron oxide/ synthetic enamel of thickness 50 micron per
coat or one coat of alkyd based micaceous iron oxide paint of thickness 65
microns followed by two coats of synthetic enamel paint of thickness 25 micron
per coat. The interval between coats of micaceous iron oxide paint or synthetic
enamel paint shall be 24 hours. The total dry film thickness should not be less
than 175 microns.
Power Pack
The outside surface of oil tank shall be given one coat of epoxy zinc rich primer
by spray giving a dry film thickness of 50 microns. Over the primer,
intermediate coat of epoxy polyamine to give a dry film thickness of 60 micron
followed by top coat of glossy polyurethane enamel to give a dry film thickness
of 60 microns. The total DFT of all the coats shall not be less than 170 microns.
59
GTS
Pakal Dul H E Project
The inside surface of oil tank shall be given one coat of epoxy zinc rich primer
of dry film thickness of 50 microns.
60
GTS
Pakal Dul H E Project
Before encasing/laying the Pressure shaft liner pressure shaft liner in concrete
the outside surface of the lower and upper half of the Pressure shaft liner in
area d/s of thrust collar shall be given suitable wrapping of bond breaking
material like lucobit-1218 of thickness 10mm over the painted surface (refer
painting schedule in the table). Remaining part of steel liner embedded in
concrete shall be given two coats of cement latex after clearing. The concrete
encasement shall be poured in the portions shown in the drawings only after
such inspections and approval. However, the embedments of timber supports
in concrete will not be permitted at all. All internal bracings and foreign matter
shall be removed from the inside of the pressure shaft liner after the liner have
been erected and embedded in concrete.
All interior surfaces of the Pressure shaft steel liners shall be protected against
corrosion. The contractor shall furnish prepare and apply all materials for
cleaning, primer coating and painting of the liners. Cleaning, primer coating and
painting shall be performed prior to, during or after installation of the penstocks
subject to the approval of the Engineer-in-charge, provided that the completed
coatings shall in all respects conform to the detailed requirements of these
specifications at the time of final acceptance by the Employer.
Primer and coal tar epoxy: Before the application of Zinc rich primer the surface
shall be cleaned by surface blasting to Sa-2.1/2 quality of Swedish standard or
to any approved equivalent. Over the prepared surfaces, two coats of Zinc rich
primer with epoxy resin, containing 90% zinc on the dry film shall be applied;
each coat providing a dry film thickness of at least 25 microns. This shall be
followed by application of two coats of coal tar epoxy paint; each coat providing
a dry film thickness of 100 microns. The total dry film thickness of all the four
61
GTS
Pakal Dul H E Project
coats shall not be less than 250 microns. Workmen skilled in the trade shall
perform the application of zinc primer and epoxy paint and related operations
under experienced supervision.
For touching up, the same paint shall be used as for the original painting work.
Repaired finish coats shall be of identical appearance with the original and no
difference in the colour shall occur. Severely damaged coatings may be
removed and repainted as per requirement of Engineer.
The dry film thickness shall be measured by approved gauges, and the cost
of two new electronic gauges shall be included in the Tender for the use of
Engineer.
For checks on porosity, the Contractor shall furnish a D.C. variable high-
tension test instrument with built-in pore counter. The test voltage shall not
exceed 2000 V. The tests shall not be performed within 0.5 m distance from
uncovered, corrosion resistance surfaces.
Upon completion of each coat, the painter shall make a detailed inspection of
the painting finish and shall remove from all adjoining works all splattering of
paint material. He shall make good all damage that can be caused by such
cleaning operations.
A detailed inspection of all painting work shall be made, and all abraded,
stained, or otherwise disfigured portions shall be touched up satisfactorily or
refinished as required to produce a first-class job throughout and to leave the
entire work clean and acceptable condition.
5.12.6 Galvanising
62
GTS
Pakal Dul H E Project
Unless otherwise specified, any foundations, wall and roof openings and
coverings, concrete floor filling, sleeves in foundations and walls and trenches
with floor plates for cables & hydraulic pipe, will be provided by the Civil
Contractor.
The Contractor will be responsible for the determination and details of all
loads and forces exerted by his equipment and transferred to the foundation.
The Contractor shall show the location and full details of all embedded
components on his drawings and shall be responsible for the completeness
and accuracy of his drawings and the information supplied to others.
Anchorages to be embedded in primary concrete will be installed by the civil
contractor as per Contractor's drawings. The Contractor shall be responsible
for the adequacy and accuracy of the location of all embedded components
supplied by him or by others.
The grouting will be carried out by the civil contractor under the supervision of
the Contractor and the mix and grouting pressure shall be approved by the
Contractor. The Contractor shall satisfy himself that the grouting has been
carried out to his entire satisfaction.
Any steel work which is to be built into the concrete foundations shall not be
painted or coated unless otherwise approved or specified.
63
GTS
Pakal Dul H E Project
All platforms, ladders, guards and handrails necessary for easy and safe
access to Works supplied under the Contract. Handrails shall be of tubular
steel construction.
Safety guards at each point where normal access provision would permit
personnel to come within reach of any moving equipment to be provided
under the Contract.
All covers for pipe and cable trenches, required for completing the floors
around and over Works supplied under the Contract will be supplied and
installed by the civil contractor. Unless otherwise approved, floor plates shall
be of an angular pattern.
Covers and curbing for dismantling hatches in main floors will be provided by
the civil contractor.
6.0 Installation
64
GTS
Pakal Dul H E Project
Placement of concrete in block outs will be done by the Owner and contractor
shall give a detailed programme of fixing and aligning the embedded parts to
the Owner for this purpose. Before placing the concrete in any one lift and
between placements of successive lifts, alignment tolerances shall be checked
and remedial action be taken if any displacement is noticed. The block out (2nd
stage) concrete will conform to the grade M-30 (minimum) unless
otherwise specified on drawings.
For hoist and gantry crane/EOT Crane, the contractor shall prepare a complete
erection procedure which shall describe the sequence of operations to be
carried out, the methods to be used, the measurements to be taken and the
tolerances to be met, in the erection and alignment of the equipment.
6.5 Installation of Pressure shaft steel liners / Tunnel Spillway Steel Liners
6.5.1 General
Before erection is started the Contractor shall supply eight complete sets of
erection schedules, procedures and erection drawings to the Engineer-in-
Charge for approval. The Contractor will be required to lay/erect the Pressure
shaft liner pressure shaft liners in place and do the welding of field joints. All
civil works e.g. excavation, concrete and back-fill as also the anchor and
foundation for supports etc. will be done by the contractors as per the items in
civil works.
The contractor shall complete all preliminary works at site well before the arrival
of pressure shaft liner such as keeping in readiness of electrical winches,
mobile cranes, jig poles, all tools and tackles, welding sets etc. as part of this
contract, and any other work that may be necessary to start erection
immediately after the fabrication. The Contractor shall arrange for such
number of erection equipment, supervision, labour and other arrangements so
as to carry out the work efficiently.
65
GTS
Pakal Dul H E Project
The contractor shall be solely responsible for correctness of laying steel liners.
The checking and approval by the Engineer in charge will not absolve the
contractor from the responsibility of erecting the steel liners in true alignment.
Establishing and maintaining temporary benchmarks and connecting to the
permanent benchmarks by double leveling shall be the responsibility of the
Contractor. No extra payment shall be made to them.
The Contractor shall furnish and install such permanent structures, erection
supports permanent or temporary including holding down straps and internal
bracings as may be required to support the liners securely in place and prevent
distortion during erection, welding and placing of concrete. Cost of all such
structures including erection supports (permanent or temporary) shall be
included in the unit rate of various items. The girth seams shall then be welded
as soon as practicable. After field welding by the electric arc method of girth
seams the joints are to be tested ultrasonically/spot radiography as given under
non-destructive examination, and if any joint is found defective the same shall
be repaired to the satisfaction of Engineer-in-charge. To ensure the matching of
sections at the joints expanding struts or spiders may be used. Tack welds
where used to hold the sections in line, shall be removed so that they may not
become part of the joints. The schedule of installation of pressure shaft liner on
the supports and the field welding and embedments in concrete have to be
carefully synchronized with the works of civil contractor who shall be doing the
concreting of pressure shaft. When the pressure shaft liner has been installed,
with all structural supports, rods, wedges, etc. as may be required to hold the
pipes securely in place while being embedded in concrete, all such work shall
be inspected and approved by the Engineer in charge. It shall be ensured by
the Contractor that the provision of supports (permanent or temporary) and
chairs are sufficient to prevent any misalignment of the pressure shaft due to
buoyancy of wet concrete during concreting.
When erection, welding and inspection of the steel lining have been completed
in accordance with these specifications, the steel lining shall be encased in
concrete. The Contractor shall supply and install sufficient interior bracing's in
addition to that required for welding to maintain the roundness within the
specified tolerances until the encasement is completed. The Contractor shall
supply and install sufficient exterior bracings and anchor bands and bars to
resist the loading due to the placing of concrete.
----
66
GTS
Pakal Dul H E Project
6.6 Seals
Rubber seals shall be of the moulded type only. The materials used for rubber
seals shall be compound of natural rubber, a copolymer of butadiene and
styrene, or a blend of both, and shall contain reinforcing carbon black, zinc
oxide, accelerators, anti-oxidants, vulcanising agents and plasticizers. The
contractor shall provide all seal with adequate temperature and age resistant
properties which will provide, in the moulded form, suitable sealing properties.
All corners shall be remoulded and have a suitable radius on the inside edge.
All joints, both shop and field, shall be located at reasonable distance from the
corners and shall meet the following requirements:
a) All shop joints shall be vulcanised. Joint geometry shall be such as to avoid
feather edges on the sealing surfaces.
c) Vulcanised joints shall not break on tear when bent 180 degrees around a
mandrel of a diameter equal to the maximum cross section thickness of the
seal
e) The joints in the rubber seal shall be vulcanised but joints and at right angle
to the rubber seal. Oblique joints at the corner shall not be permitted in the
rubber seal. Vertically placed strips of rubber seals shall be formed in one
piece and no joints of any sort shall be permitted in them.
Joints shall be water tight and seal materials shall have following physical
properties as determined by tests made in accordance with the relevant
Standards.
Property Limits
67
GTS
Pakal Dul H E Project
Gears shall be designed so that all stresses are within allowable limits when
the maximum loads are being handled. All gears shall be designed and
calculated in accordance with IS Standards or equivalent international
standards, or widely approved methods and to the individual experience of
the manufacturer. On request of the Engineer, the manufacturer shall submit
the calculation of the gears.
Where worm gears are used as a direct drive, they shall have the same load
and time rating as the motors driving them. The gears shall work in oil and the
temperature rise of the oil bath shall not exceed 500C under normal working
conditions at Site. The materials of the mating faces of worm wheel and worm
shall be of a bronze/steel alloy.
Where practicable gear wheels shall be forced fit on the shaft and in addition,
shall be keyed adequately to prevent any relative motion between the wheel
and shaft. Where gears and couplings are secured in position by means of
keys, they shall be easily accessible for tightening or removal. All keyways
shall be machine cut. Couplings and collars shall be the shrouded or
protected-type, free from projections of any kind.
Efficient means of lubrication, suitable for use under Site conditions, shall be
provided for all moving parts.
The contamination of the air, water and soil by lubricants and fuel shall by all
means be avoided by applying an appropriate design and layout of the Works
in conformity with the latest recognized standards for modern engineering
practice.
The number of different lubricants, transformer oils, oils for pressure systems,
etc. used in the items of Works throughout the Works shall be limited to a
minimum in order to facilitate keeping stocks and maintenance.
68
GTS
Pakal Dul H E Project
The Owner reserves the right to request the different Contractors to use
certain types of lubricants, oils etc. The Contractor shall not be entitled to
claim extra payment for this request. All different types of oils, lubricants, etc.,
shall be stated in the Tender and are subject to the written approval of the
Engineer.
Unless otherwise stated in the Particular Technical Specifications, the first oil
or grease filling for bearings, pressure oil systems, transformers, etc.,
including the necessary quantity for flushing and for the first oil change, shall
be included in the Tender Price.
Oil pipes shall not be embedded in concrete. Oil pipes crossing civil
structures shall be routed through sleeves embedded in the concrete.
The piping can either be treated in an acid-bath or being completely filled with
acid. The duration of the treatment shall be approx. 6 hours. After that the
piping shall be neutralised, flushed and corrosion protected for final
installation.
69
GTS
Pakal Dul H E Project
7 Electrical Works
7.1 General
The electrical items of Works of any electrical or mechanical installation to be
provided under this Contract according to the Particular Technical
Specifications shall - if not stated otherwise therein-fulfill the requirements of
this Section.
All components shall be of an approved and reliable design. The highest
extent of uniformity and interchangeability shall be reached. The design shall
facilitate maintenance and repair of the components.
The Works shall be pre-assembled to the highest possible extent in the
Contractor's or Sub-Contractor's workshop, complete with all devices and
wired up to common terminal blocks.
Unless otherwise agreed, ratings of main electrical Works (infeeds, bus-ties)
as selected or proposed by the Contractor, whether originally specified or not,
shall generally include a safety margin of 10% under consideration of the
worst case to be met in service. Prior to approval of such basic characteris-
70
GTS
Pakal Dul H E Project
tics, the Contractor shall submit all relevant information such as consumer
lists, short circuit calculations, de-rating factors etc.
Short-circuit calculations shall be evaluated giving full evidence that every
electrical component can withstand the maximum stresses under fault
conditions, for fault levels and duration's obtained under the worst conditions,
e.g., upon failure of the corresponding main protection device and time
delayed fault clearing by the back-up protection device.
All Works shall be suitable for the prevailing climatic conditions.
Outdoor installations shall be protected against solar radiation by means of
adequate covers, where required.
The Contractor shall ensure that all the supplied Works is insensitive to any
signals emitted by wireless communication equipment.
7.2.1 Board
7.2.1.1 General
The 415 V board switchgear shall be metal enclosed indoor cubicles free floor
standing type.
The bus bars of Main distribution system shall have adequate continuous
current carrying capacity. Bus bar conductors shall be made of copper. All
connections shall be in accordance with the best modern practice.
Phase arrangements shall be R-Y-B from top to bottom, from back to front
and from left to right when facing the front of the equipment. All bus bars shall
be clearly marked by engraved letters.
71
GTS
Pakal Dul H E Project
Adequate provisions must be made for the expansion and contraction of the
bus bars and other bus bar connections with variation in temperature. Bus
bars shall be so arranged that they can be extended in length without
difficulty.
7.2.2.1 General
The air circuit breakers shall be three pole electrically operated with motor
driven stored-energy operating mechanism. The motor for operating the
spring loading device shall be for 220 V D.C. supply. The closing and tripping
coils shall be for 220 V DC.
The operating handle shall be located so that the air circuit breakers can be
operated without opening the compartment door.
A mechanical interlock shall prevent moving of the air circuit breaker from the
connected position, while the breaker is closed, and prevent the access door
being opened unless the circuit breaker is in test or withdrawn position.
7.2.2.2 Contacts
The main circuit breaker contacts shall be of the self-cleaning type, made
from an arc resisting material and provided with auxiliary arcing contacts as a
protection against burning during the operation of the breaker. All contacts
shall be self-aligning, and shall be readily replaceable.
7.2.2.3 Protection
The air circuit breakers shall be equipped with adjustable magnetic short
circuit over current and instantaneous trip mechanism/ relay, with auxiliary
magnetic short circuit contacts for indication of tripped condition. The
protection equipment shall be interchangeable.
7.2.3.1 General
72
GTS
Pakal Dul H E Project
All MCCB shall be of the draw out type, housed in individual metal-enclosed
compartments. Arrangement shall be provided for easy removal and handling
of the units. ON, OFF TRIP position of MCCBs should be indicated.
A mechanical interlock shall prevent moving of the MCCB from the connected
position, while the breaker is closed, and prevent the access door being
opened unless the breaker is in withdrawn position.
7.2.3.2 Contacts
Main and secondary disconnecting contacts shall be silver plated, with spring,
which will ensure high-pressure contact.
Required no. of single core current transformers for each main air circuit
breaker coming from unit auxiliary transformers and Station service
transformers for protection and measuring:
Accuracy class
Over current and E/F: 5P20
7.2.5 Interlocks
The local control panel shall be an Indoor/ outdoor type (degree of protection
of enclosure type IP-55) made of steel sheet of thickness not less than
2.5mm, containing all necessary equipment for the control, protection/safety
and supervisory elements as required and shall be completely painted and
wired. The panel frame structure shall be self-supporting, free standing on
floor or suitable for wall/vertical post mounting.
Cubicles and panels shall be vermin proof. Removable gland plates shall be
supplied and located to provide adequate working clearance for the
termination of cables. Under no circumstances shall the floor/ roof plate be
used as a gland plate. The cables and wiring shall enter from bottom or top as
approved by Engineer.
The cubicles and panels shall be adequately ventilated, if required, by vents
or louvers and shall be so placed as not to detract from the appearance. All
ventilating openings shall be provided with corrosion resistant metal screens
or a suitable filter to prevent entrance of insects or vermin. Space heating
elements with thermostatic control shall be included in each panel.
73
GTS
Pakal Dul H E Project
The controls, indicating lamps, push button, selector switches etc. will be
installed flush mounted on the out side door of the control panel so as to give
clear view of all the indicating lights, measuring instruments, position indicator
so that the gate and hoist can be operated with the cabinet door closed. The
remaining equipment will be installed inside the cabinet being accessible
when the door is opened.
The panel door shall have close fitting, gasketted, hinged, swing off
construction capable of being opened through 180 degree. The doors shall be
provided with integral lock and master key. A mechanical interlock shall be
provided so as to ensure de-energisation of the panel as soon as the door is
opened. Suitable provision may, however, be made to bypass the above
interlock under extraordinary requirements when manual energisation of
panel is necessary under open condition. Panel shall be provided with door
switch operated illumination.
All terminals will be of block type. Wiring inside the control panel is made at
least with 650 Volt insulation grade, 1.0 mm2, 1.5 mm2 and 2.5 mm2 Control
cable and required size of power cable. All cables shall be brought at terminal
blocks mounted inside the control panels to facilitate connection with the
external cables. All the metallic parts of the switch- boards and all the earth
wires of the circuits shall be connected with the Earthing bus of not less than
25 sq. mm copper conductors. All control cables and components will be
marked in a systematic manner on drawings on the accordingly tagged cables
and components in the control panel. All necessary auxiliary devices for
connection to limit switch shall also be provided. The control equipment shall
generally meet the requirements of Clause 6.6 of IS: 6938 -1989.
7.4 Standards
The design, manufacture and testing of all Works and installations shall
strictly comply with the latest edition of the relevant IEC publications.
7.6.1 General
All motors shall be of approved manufacture and shall comply with the
requirements of this Chapter. Motors of the same type and size shall be fully
interchangeable and shall comply with Indian standard and to IEC standard
motor dimensions.
74
GTS
Pakal Dul H E Project
The general construction shall be stiff and rigid, no light metal alloy casings
will be accepted. All precautions shall be taken to avoid any type of corrosion.
All motors shall be fitted with approved types of lifting hooks or eye bolts as
suitable.
7.6.2 Rating
The rating of motor other than Hydraulic Hoist motors shall be adequate to
meet the requirement of its associated equipment. The service factor, being
the ratio of the installed motor output to the required power at the shaft of the
driven machine at its expected maximum power demand, shall be applied as
follows:
Up to 5 kW 1.2
7.6.3 Starting
The maximum starting currents (without any tolerance) shall not exceed value
5 times of rated current for motors.
Generally, all motors shall be able to withstand three cold starts per hour,
equally spaced. In addition, each motor shall be capable of enduring two
successive starts with the motor initially at operating temperature under the
same conditions or once every twenty minutes without detrimental heating.
Motors for frequent automatic starting shall have an adequate rating. In the
motor list the Contractor shall state the frequency of starts permitted in
compliance with the motor design.
75
GTS
Pakal Dul H E Project
The insulation of all motors shall be of class F but maintain in operation the
temperature limits of class B materials. It shall be suitable for operation in
damp locations, for occasional contact with corrosive gases and vapours and
for considerable fluctuations in temperature.
The stator winding shall be suitably braced to withstand the forces due to
thyristorised controlled/ direct-on-line starting and transfer conditions as
mentioned before. The winding envelopment and tails shall be non-
hygroscopic. The stator winding shall withstand the maximum fault current for
the period determined by the associated protective devices.
All motors shall be of the totally enclosed fan-cooled type, protection class IP
54 according to IEC Recommendation 144. Cable terminal boxes shall be of
class IP 55.
They shall have a closed internal cooling air circuit recooled by an external
cooling air circuit drawn from the opposite side of the driving end.
Vertical motors shall be provided with a top cover to prevent the ingress of dirt
etc.
7.6.6 Bearings
As far as possible, the motors shall have sealed ball or roller bearings
lubricated for life. All other motors with ratings of about 1 kW and above shall
be equipped with lubricators permitting greasing while the motor is running
and preventing over-lubrication. Additionally, the bearings shall be fitted with
grease nipples permitting the use of a universal grease gun. Vertical motors
shall have appropriate thrust bearings.
76
GTS
Pakal Dul H E Project
The motors shall be provided with a free shaft extension of cylindrical shape
with key and keyway according to IEC Recommendation 72-1 and with the
motor side-coupling which shall be pressed on the motor shaft and be
balanced together with it. A coupling guard shall also be provided.
The terminal leads, terminals, terminal boxes and associated equipment shall
be suitable for terminating the respective type of cables as specified in these
General Technical Specifications and in the Particular Technical
Specifications.
The terminal boxes with the cables installed shall be suitable for connection to
supply systems with the short-circuit current and the fault clearance time
determined by the motor protective devices.
Terminal boxes shall be totally enclosed and designed to prevent the ingress
of moisture and dust. All joints shall be flanged with gaskets of neoprene or
similar material. For motors above 1 kW, the terminal box shall be sealed
from the internal air circuit of the motor.
Depending on the size, the terminal box of L.V. motors shall be fitted either
with an approved cable sealing-end or with a gland plate drilled as required
and provided with suitable fittings for cable fixing and sealing. Such openings
shall be temporarily plugged or sealed during transportation.
Terminal boxes of M.V. motors shall be fitted with an approved cable sealing
end and a pressure relief diaphragm suitably located. For plastic insulated
and sheathed cables filling with compound is not required.
The three neutral ends of the windings of M.V. motors shall be brought out to
a separate terminal box.
For earthing purposes, each motor shall have adequately sized bolts with
washers at the lower part of the frame. In addition, each terminal box shall
contain one earthing screw.
Under all operating conditions, the noise level of motors shall not exceed
85 dB (A).
In order to prevent undue and harmful vibrations, all motors shall be statically
and dynamically balanced. Vibration displacements or velocity shall be
measured in accordance with DIN 45 665 for IEC motor sizes 80 to 315. The
results for all motors shall be within the "R" (reduced) limits.
77
GTS
Pakal Dul H E Project
7.6.10 Tests
Each motor shall be factory tested and shall undergo a test at site. The
following tests shall be performed under full responsibility of the Contractor.
Workshop Tests:
• Measurement of winding resistance
• No-load and short-circuit measurements
• Measurement of starting current and torque
• Efficiency measurement (type test)
• Heat test run
• Dielectric test
• Measurement of insulating resistance
• Over speed test
Site Tests:
• Measurement of insulation resistance
• Measurement of motor vibrations
• Measurement of starting time
Where appropriate, each item of Works shall be equipped with all necessary
auxiliary switches, contactors and devices for indication, protection, metering,
control, interlocking, supervision and other services. All auxiliary switches
shall be wired up to terminal blocks on the fixed portion of the Works.
Control Switches
Control switches for electrically operated circuit breakers shall be of the pistol
grip or discrepancy type. They shall operate clockwise when closing the
circuit breakers and anti-clockwise when opening them. The control switches
shall be so designed as to prevent them from being operated inadvertently,
and where switches of the discrepancy type are used they shall require two
independent movements to effect operation. Control switches shall be so
designed that when released by the operator, they return automatically to the
neutral position after having been turned to the "closed" position and shall at
the same time interrupt the control voltage supply to the operating mechanism
of the circuit breaker.
78
GTS
Pakal Dul H E Project
Heaters shall be equipped with a suitable terminal box. All Works, whether
fitted with a heating device or not, shall be provided with suitable drainage
and be free from pockets in which moisture can collect.
The protection relays shall be equipped with all necessary auxiliaries such as
tripping unit, time relay, external resetting device (hand reset flag with seal-in
operation). The relays shall provide easy access for testing and setting
purposes.
Unless otherwise required for special purposes, protection relays shall remain
in the tripped position until the operator resets the relay manually. The
protection and auxiliary relays shall be grouped and mounted on plug-in
modules or stationary-mounted on swing frame with separate plugs and
sockets to feature easy replacement and testing. The construction shall be
sturdy and such that all parts are easily accessible for adjustment. Relays
installed in switchboards shall be arranged in compartments separated from
the switchgear.
Besides the mechanical-operated flag type indicator, all relays shall have
sufficient contacts and/or auxiliary relay contacts to perform all the tripping,
inter-tripping, interlocking, indication and alarm functions required. Spare
contacts (1 N.O., 1 N.C.) shall be provided for later use. The contacts shall
be silver-plated or of the seal-in type with the main contacts adjustable. The
79
GTS
Pakal Dul H E Project
relay contact rating shall be for the specified standard voltage and for 200%
of the nominal passing current. The relay coil shall be able to operate
properly at voltage variations of -25% to +15%.
ii) 415/230 V A.C supply in the vicinity of Intake for Intake Equipments.
The electric service power provided by the Employer or the other Contractors
shall be as follows:
- 415/230 V, 50 Hz, three-phase system with earthed neutral for feeding
three-phase and single-phase consumers (connected between neutral).
- 230 V, 50 Hz, permanent supply, single phase earthed.
- 48 V, D.C. system, isolated from earth, for the supply of electronic
equipment, telecontrol, telecommunications. etc. wherever necessary
shall be provided by the Contractor.
Supply Tolerances
System 415/230 V 230 V 48 V, D.C.
Limits of the supply
Voltage
a) Steady +5/-10% ± 2% +10/-15%
The Contractor shall supply and install all terminals, control boxes, cables,
conduits, fittings including main distribution system comprising of Air Circuit
Breaker (ACB), Moulded case circuit breaker (MCCB), Current Transformer
(CT), Potential Transformer (PT), bus bars in sufficient capacity along with at
least two nos. of spare MCCBs for operating units supplied by others from
terminal points for the distribution of electric power supply to the electrical
equipment and its controls including lighting to be supplied under this
contract. The power supply cables shall be designed so that the voltage drop
between the terminal points and the respective equipment shall be limited to
within 2.5 % of the rated voltage. In MDS, the provision shall also be made for
automatic changeover from mains to DG so that no time lag may be there.
80
GTS
Pakal Dul H E Project
7.9 Cables
7.9.1 General
The Contractor shall provide the relevant design and engineering of the
relevant cable systems and, in close co-operation with the Civil Contractor,
prepare the cable installation drawings with cable routing, connection
diagrams, and cable lists, details etc.
The power cables and control cables shall be of copper as per Indian
Standards or IEC publications and the power cables shall be of minimum size
16 mm2 and control cables shall be of minimum size 1.5 mm2.
All cables and accessories shall be suitable for installation under site
conditions (e.g. aggressive soil conditions, etc.).
The Contractor shall select the most suitable cable routes and raceways
ensuring a minimum of interference with other installations.
Earth E grey
380 V white
81
GTS
Pakal Dul H E Project
The contractor shall supply and install the lighting fixtures including high
pressure mercury/sodium vapour lamps etc to provide proper illumination
over and under all the hoist equipment/gantry cranes /EOT cranes etc. to
enable the operator and O&M crew to work on the equipment.
All electrical system shall be properly earthed as per the latest ruling practice
for the safety of the equipment, operating staff as well as the system. All
protection devices for the control equipments including grounding system/ pit
wherever required shall be provided by the Contractor.
7.11.1 General
The proposed material of the labels, size, exact label lettering and proposals
for the arrangement of the labels shall be submitted to the Engineer for
approval.
Labels written in the Contract language shall be provided for all instruments,
relays, control switches, push buttons, indication lights, breakers, etc. In case
of instruments, instrument switches and control switches, where the function
is indicated on the device, no label is required. The label shall be fixed close
to the devices in such a way that easy identification is possible. Fixing on the
dial glass of instruments will not be accepted. The wording shall conform to
the wording used in engineering documents.
Each separate construction unit (cubicle, panel, desk, box etc.) shall be
identified by its Works identification number. Cubicles and similar units shall
also bear this identification number on the rear side if rear access is possible.
The overall designation of each unit shall be given in the Contract language
and - if required - also in a selected local language. These labels shall be
made of anodised aluminium with black engraved inscriptions, arranged at
the top section of the units. Manufacturer's trade labels shall - if desired -
appear in the bottom section of the units.
All Works inside cubicles, panels, boxes, etc., shall be properly labelled with
their item number. This number shall be the same as indicated in the
pertaining documents (wiring diagrams, Works list etc.).
82
GTS
Pakal Dul H E Project
Warning labels shall be made of synthetic resin with letters engraved in the
Contract language and in particular cases, where required, in the selected
local language.
The cable identification numbers shall comply with those of the cable list.
All cables in cable pits and at the entry to buildings shall be labelled utilising
the aforementioned type of label.
Works (hoists, machines, transformers etc.) rating plates and other technical
data/informative plates shall either be of the enamelled type or be of stainless
steel suitably protected after engraving with a transparent paint resistant to
aggressive atmosphere and solar radiation.
The locks or padlocks shall be coordinated for the different applications and
shall be supplied with three keys. A key cabinet at the end of each board
(distribution board, MCC, control cubicles etc.) shall be provided for storing
the keys of that board. For all locks supplied there shall be six master keys to
open any lock or padlock supplied. Each key shall have one identification
label fixed above the key hanging hook inside the cabinet.
The cabinet door keys shall be similar and shall be six (6) in number.
8.1 General
The general co-ordination of storage and erection work as well as the civil
engineering work on site will be done by the Engineer.
83
GTS
Pakal Dul H E Project
From the time of manufacturing until commissioning all parts of the plant shall
be protected against damage of any kind. Parts, which are damaged during
transport, shall be replaced at the Contractor's expense.
The Contractor shall provide the Engineer with complete packing lists of each
performed shipment.
8.2 Packing
After the workshop assembly and shop inspection and tests including witness
inspection by the Engineer or his authorised representative wherever
specified and prior to dismantling for shipment to the Site, all items shall be
carefully marked to facilitate site erection. Wherever applicable, these
markings shall be punched or painted so they are clearly visible.
Dismantling shall be done into convenient sections, so that the weights and
sizes are suitable for transport to Site and for handling on the Site under the
special conditions of the Project.
All individual pieces shall be marked with the correct designation shown on
the Contractor's detailed drawings and other documents (packing lists, spare
part lists, in Operating and Maintenance Instructions etc.).
Marking shall be done preferably by punching the marks into the metal before
painting, galvanising etc., and shall be clearly legible after painting,
galvanising etc. In labelling, the Contractor shall endeavour to use as few
designations as possible, and each part of identical size and detail shall have
the same designation, regardless of its final position in the plant.
All parts of the Works shall be packed at the place of manufacture. The
packing shall be suitable for shipment by sea and for all special
requirements/limitations of the transportation to Site. Where necessary,
double packing shall be used in order to prevent damage and corrosion
during transportation, unloading, reloading or during intermediate
storage.
The Engineer reserves the right to inspect and approve the packing before
the items are dispatched but the Contractor shall be entirely responsible for
ensuring that the packing is suitable for transit and such inspection will not
exonerate the Contractor from any loss or damage due to faulty packing.
8.3 Marking
The Contractor shall mark all containers with the implementing document
number pertinent to the shipment. Each shipping container shall also be
clearly marked on at least two sides as follows:
- Consignee :
- Contract No. :
- Port of destination :
84
GTS
Pakal Dul H E Project
- Description of Works :
8.4 Storage
The Contractor shall inform himself fully as to all relevant transport facilities
and requirements, loading gauges and other limitations and shall ensure that
the equipment as prepared for transport shall conform to such limitations. The
Contractor shall also be responsible for obtaining any permit from the railway
or highway authorities that may be required for the transport of loads
exceeding the normal gauges.
The Contractor shall provide means for all unloading and reloading for all
consignments of the plant, during transport to Site. Unloading on the Site will
be provided for by the Contractor. Consignments shall be unloaded
immediately on arrival at Site. The Contractor is required to take the
necessary steps in order to provide the carriage, special supporting structures
for heavy loads etc.
The contractor shall develop necessary storage facility for proper and safe
storage of all the materials. The warehouses shall be waterproof, well
ventilated and of designated floor etc.
If large parts are stored in the open air, they shall be provided with weather
resistant and fire-resistant covers. Electrical parts which are not packed in
heavy duty polyethylene foil and those so packed but whose packing has
been damaged shall be kept in suitable places from the moment of storage to
the moment of installation.
All insulation materials which will be taken from the warehouse for installation
and which are stored temporarily in the station shall be protected from
weather or humidity.
9.1 General
85
GTS
Pakal Dul H E Project
Three (3) sets of all test records, test certificates, performance curves, tables
etc. of all inspections and tests, whether or not attended by the Engineer shall
be supplied soonest after performance of each inspection or test. After
completion of all testing two (2) sets of the above-mentioned documents
shall be supplied properly bound in books.
Contractors name
Project title
Date
Inspection and testing of equipment shall include all inspections, tests, checks
etc., whether mechanical, hydraulic or electrical, as required to ensure that
the equipment supplied meets the requirements of the Specifications.
• Dimensional checks
• Balancing tests
• Electrical tests
• Functional tests
• Performance tests
• Type tests
• Acceptance test
86
GTS
Pakal Dul H E Project
The contractor shall be responsible to carry out and keep record of all
inspection/tests during manufacture through his quality assurance group. This
shall be supplemented by third party inspection by reputed Firms well versed
in carrying out inspection activity in accordance with the approved Quality
Assurance Plans namely Lloyds / Bureau Veritas for all components under
fabrication at manufacturer’s/sub contractor’s works. In addition Owner’s
inspection representatives shall get associated for specific inspections as
specified in the approved quality assurance plan.
When placing orders for major material and equipment with sub suppliers, the
Contractor shall send unpriced copies of such orders in triplicate to the
Engineer.
Arrangements shall be made for expediting the shop inspection by having all
shop assemblies or pieces covering a single shipment ready at one time. Any
painting work as well as transport to the site of the Works shall not be started
before the approval of the Engineer has been obtained.
87
GTS
Pakal Dul H E Project
Free and unrestricted access to the Contractor's factory and shops (including
those of his Subcontractors) shall be granted to the Engineer, and upon
reasonable notice by the Engineer or others nominated by him if deemed
necessary by the same for additional witnessing of assembly work or
inspections and tests.
• Chemical analysis
Strength etc.)
88
GTS
Pakal Dul H E Project
Certified mill test reports of plates will be acceptable when these comply with
the requirement for "Reports of Inspections and Tests" as stated in the
Special Conditions. Test specimen and samples for analysis shall be plainly
marked to indicate the materials they represent.
Castings and forgings shall be tested in the rough state in order to detect
flaws in time thus avoiding delays. Magnetic particle inspection of important
castings shall cover the whole surface of the casting. After partial machining
further tests can be conducted. Important castings and forgings like Gate
wheels, hoist drum, gears, crane wheels etc. shall be ultrasonically tested. The
acceptable limit for ultrasonic testing of castings shall be level I of SA-603 of
ASME Section-5 and that of forgings shall be as per SA 388 of ASME
Section-5.Load tests on crane hooks, steel wire ropes, chains, etc. shall be
considered as material tests.
The dimensions, especially clearances and fits (ISO 286), which are essential
for operation and efficiency shall be carefully checked in an approved
manner, as for example:
In addition to the quality and production control tests, the following shop
assembly work and tests shall be made to check measurements, fitting and
functioning.
Works to be furnished shall be shop assembled to a status sufficient to prove
that the design and workmanship have been executed in accordance with the
Specifications, that the delivery is complete, and that no work remains to be
done at Site, which reasonably can or should be done in the shop.
The metal work shall be shop-assembled to ensure that all parts are properly
fitted and that the dimensional and tolerance requirements shown on the
drawings have been obtained. All holes for field connections of parts
furnished under these specifications shall be drilled or reamed as noted on
the drawings, with the embedments so assembled. Members to be shop-
bolted shall have all parts well pinned up and drawn together with bolts before
bolting is commenced.
To commence the shop assembly of radial gates the 2 gate arms shall be
supported in their relative position at the same elevation properly spaced
centre to centre and so that the machined pin holes have a common
horizontal axis. With the arms in the position the gate leaf shall be erected
between them. The vertical lift gates shall be assembled in a vertical or
89
GTS
Pakal Dul H E Project
horizontal position and holes for field connections carefully drilled or reamed.
Connections, which have to be dissembled for shipment, shall be made by
the use of erection pins, one size less in diameter than the designed size of
temporary machine bolts.
The Hoist / crane shall be completely assembled in the shop to ensure that all
parts are properly fitted. Surfaces of metal, which will be in contact, shall be
cleaned before the parts are assembled. The parts shall be adjusted to line
and fit and shall be well pinned and bolted so that the surfaces are in close
contact before reaming, drilling, bolting or welding is commenced. The field
connections shall be fitted and checked in the shop to assure proper fit during
field erection.
Where applicable each item of the works shall be assembled completely prior
to painting.
All parts shall be properly match marked, identified and doweled where
practicable, to facilitate correct and quick field assembly and alignment.
Where necessary, suitable dowels shall be provided for insertion after field
assembly and drilling. The holes for any fitted bolt shall be accurately reamed.
During workshop assembly all instruments, control devices and piping shall
be fitted.
Before final machining, each of the hydraulic hoist cylinder shall be subjected to
a hydrostatic pressure of one and a half time pump capacity or 30 N/mm2,
whichever is more. The test pressure shall be held on each cylinder for a
sufficient length of time to permit inspection of all joints. Any leakage in joints
may be repaired by rewelding at the discretion of and, in a manner acceptable
to the purchaser. The purchaser, at his discretion may require additional stress
90
GTS
Pakal Dul H E Project
relieving and radiographic examination of the hoist cylinder that have been
repaired by rewelding. All test heads and other equipment required for testing
shall be furnished by the Contractor free of cost and will remain his property
after the completion of the tests.
Before testing the Contractor shall submit a notice containing full information
on the tests with detailed tables or graphs on the latest edition of the
characteristic values of the Works to be tested and on the test facilities and
equipment.
Operational tests of lifting equipment and other machinery shall include tests
under following condition
(i) No load
(ii) 5% of rated load
(iii) 125 % of rated load
unless otherwise specified. The deflection test shall be carried out with the
safe working load at rest.
The following tests shall be carried out at shop as well as at site after erection.
i) After erection but before the hoist/crane is connected to the supply, the
insulation of the electrical equipment shall be tested by a suitable
instrument and any defects revealed shall be rectified. The voltage
required for the insulation resistance test shall be d. c. voltage not less
than twice the rated voltage.
ii) Any reading less than 0.5 mega ohm obtained with an insulation
resistance tester of the un-regulated type shall be disregarded and the
wiring under test shall be sub-divided until a reading higher than 0.5
mega ohm is obtained. Failure to obtain a higher reading shows an
unsatisfactory state of insulation. If an installation has been sub-divided
for test purposes, each sub-division shall meet the requirement.
91
GTS
Pakal Dul H E Project
ii) The correctness of all circuits and interlocks and sequence of operation.
The measurement shall not be taken on the first application of the load.
92
GTS
Pakal Dul H E Project
In all cases, where the Contractor provides for test whether at his premises of
work or of any sub Contractor the Contractor except where otherwise
specified shall provide free of charges, such labour, material electricity, fuel,
water, stores, apparatus and instruments as may reasonably be demanded to
carry out efficiently such tests of the plant in accordance with the contract and
shall give facilities to the Engineer-in-Charge or his authorized representative
to accomplish such testing. If special tests other than those specified in the
contract are required, the Corporation shall pay them for as "Variations".
When the tests have been satisfactorily completed at the Contractor's/Sub
Contractor’s premises or works the Engineer-in-charge shall issue a
certificate to that effect and no plant shall be transported before such
certificate has been issued. The satisfactory completion of these tests or the
issue of the certificate shall not bind the Engineer-in-charge to accept the
plant so passed for dispatch, should it on further tests be found not to comply
with the specifications.
Wherever possible all tests shall be carried out before dispatch. Should
however, it is necessary for the final tests as to performance and guarantees
to be held over until the plant is erected at site they shall be carried out in the
presence of Contractor's representative within one month of the completion of
erection. In all such cases except where otherwise specified, the Contractor
shall provide free of charge all the facilities, equipment and material as may
be required from time to time and as may reasonably be demanded for
efficiently carrying out such tests of the pressure shaft liner, material, or
workmanship in accordance with the contract. Should the results of test not
come within the margin specified, then test shall, if required, be repeated
within one month from the date of the steel lining being ready for re-test and
Contractor shall repay to the Engineer-in-charge all reasonable expense to
which he may be put by such tests.
9.3 Site Inspection and Tests
Unless otherwise specified, all costs for testing at site and of the works and
charges associated with it shall be borne by the Contractor. This includes the
measuring devices (properly calibrated) and any pertinent accessories, which
shall be made available by the Contractor for the entire duration of the tests.
The Contractor shall delegate his experts to supervise the tests at site.
The tests, checks, examinations at site shall comprise but not be limited to:
• Tightness tests
• Dielectric tests
93
GTS
Pakal Dul H E Project
• Running tests
• Reliability tests
All such tests and checks shall be performed in the presence of the
Employer's Representative. If not satisfied with the performance of the tests
and checks the Owner’s Representative shall have the liberty to ask for
additional tests or repetition of same.
The testing at Site shall be complete in every respect to prove the successful
performance and operation of all the works and Works supplied and erected
under the Contract.
For the procedure of inspections and test at site, notice to the Engineer,
reports, commissioning, trial runs and trial operation, and acceptance tests
refer to General Conditions.
After the contractor has notified the Owner’s Representative and received his
agreement that the equipment is ready for the commissioning tests, the
Contractor shall start with the Tests as stipulated in the Conditions of
Contracts.
94
GTS
Pakal Dul H E Project
• Inspection of lifting beam for proper matching with all units of stoplogs.
• Inspection of hoist/ Crane for exact location of hook/ pulley block over
the lifting point of the gate and for proper matching and connections.
General
After completion of various phases of works final checking of the entire work
shall be done, by the contractor to ensure that all the equipments erection
and wiring etc. have been done strictly according to the specification drawings
and as approved by the Engineer-in-charge. All the works shall be thoroughly
inspected keeping in view the following main points:
• All routine and pre-commissioning tests and any other special tests
required to be conducted at site on each and every equipment as per
relevant standards and manufacturers instructions and
recommendations.
Proper record shall be maintained for all visual inspections, settings and
checks carried out.
The functional tests on hydraulic hoist shall be carried out by the hydraulic
hoist manufacturer's representative.
95
GTS
Pakal Dul H E Project
• Checking of fluid tank and piping for completion as per drawings as well
as for cleanliness before filling the hydraulic fluid.
The dry testing of the gate and hoist shall be carried out generally in
accordance with Cl. 8.1, 8.2, 8.3 and 8.4 of IS 7718- 1991. The gate & hoist
shall be functionally operated, fully closed, fully opened and it shall be
ensured that there is no obstruction during the operation, the movements are
smooth without any jerks and no undue effort is required for operation.
Contact between gate seals and seal seats shall be checked and pre-
compression ensured by viewing the contact surface against a light source.
The operation of the hoist shall be smooth without any undue noise/
excessive friction and without excessive vibrations in the gate, hoist and
supporting structure. The operation of hydraulic hoist shall be without any
increase in oil pressure beyond design limits and motor current shall be within
design value.
IMPORTANT: Any 'Dry' testing movements should have Rubber seals & seal
faces lubricated with WATER (Do not use grease/ oil). For Metal-to-Metal
sealing/ bearing surfaces grease be used.
96
GTS
Pakal Dul H E Project
During the trial operation period the Contractor may request any minor
adjustments, which do not in any way, interfere with or prevent the use of the
equipment by the Owner’s or result in reducing the output or decreasing the
efficiency.
During the trial run the Contractor shall make familiar the Owner’s personnel
with the properties, the operation and maintenance of the Works and its
auxiliaries to such extent that thereafter the duties can be assigned to the
Owner’s trained personnel.
9.3.2 Acceptance
The taking-over testing of any part or section of the Permanent Works which
can operate as an independent unit, shall be performed in accordance with
the standards and regulations laid down in the "Particular Technical
Specifications" and following the test procedure agreed upon between
Engineer and Contractor.
97
GTS
Pakal Dul H E Project
If any test for the verification of the guaranteed data could not be performed
for operational reasons beyond the Contractor's responsibility, this part of the
acceptance shall be stated in the "Protocol of Acceptance" and be postponed
for a mutually agreed period.
10.0 Measurement
10.1 General
For the purpose of measurements of gates/ pressure shaft liner etc., linear
dimension such as length, breadth, diameter and thickness shall be in
millimetres. The dimension shall be taken for only finished item. For example,
in case of machined item, dimension shall be measured after final machining.
Weight shall be calculated in Kilograms. Rounding off will be only in weight up
to third decimal places in tonnes.
Payment for each item shall be made at unit rate per tonne (1000 kg) of steel
as finally laid and accepted. For gates/ pressure shaft liner, measurement of
linear dimensions including the welds/ the holes less than 300mm (maximum
dimension of hole) shall be considered as continuous dimension. The steel
density shall be considered to be as 7850 kg/m3 for calculation of weights.
The weight calculation shall be made on the basis of theoretical volume thus
arrived. For the variation in thickness relevant code may be referred for the
tolerances.
For the purpose of calculating the weight of the straight portion finished
lengths as laid in position shall be measured and then weight calculated on
98
GTS
Pakal Dul H E Project
For the bend, the length along central axis of the curve shall be measured
and weight calculated there from.
For the purpose of calculating the weight of the stiffener rings etc. the
thickness, inner and outer diameter of the ring etc. shall be measured. The
outer dia of the pressure shaft liner at a particular section shall be the inner
dia of the ring and the outer dia shall be equal to the inner dia plus the height
of the stiffener.
10.3 Gate\Hoist
10.4 Miscellaneous
Where ever the gate items\penstock are embedded, structural steel supports
required to hold them in position and which are finally embedded in concrete
shall be deemed to be included in the unit prices of various items mentioned.
No separate payment shall be made for such supports or any other type of
temporary or permanent supports. The unit price accepted for the various
items shall be considered to include cost of all materials, transport, plant and
equipment, labour, tools and tackles, fabrication, erection, non-destructive
tests (both at shop and field), surface preparation, painting, protective
coating, wrapping, machining, supervision, Supply, installation, testing and
commissioning of equipments, etc. complete as required for all the operations
specified herein above in addition to those specifically so provided or
otherwise so specifically directed for particular item of work.
99
GTS
Pakal Dul H E Project
ANNEXURE - A
LIST OF APPROVED SUB-CONTRACTORS/ VENDORS
100
GTS
Pakal Dul H E Project
101
GTS
Pakal Dul H E Project
102
GTS
Pakal Dul H E Project
103
GTS
Pakal Dul H E Project
104
GTS
Pakal Dul H E Project
vii). Valve knife-edge plate and valve seat shall be of stainless steel with
precision buffed for tight shut off. Valve body shall be of carbon steel
conforming to IS: 2062 Grade-B. Body lining shall also be stainless steel.
A silt guard ring of stainless steel shall be provided.
viii). Test Pressure: The valves shall be tested for a test pressure of 1.5
times the maximum operating pressure.
The control for valve operation shall be located in valve chamber. Suitable
limit switches shall be inbuilt in the device to stop the movement of operation
to both extreme travels of the valves. Overload relays shall also be provided
in the electrical circuit to check the overloading of the device.
The steel pressure shaft liners shall be designed, fabricated and installed as
per general layout drawing no. NHPK-3KT3-45-GA-004-00. However, the
final layout and details shall be decided at the time of detail design. The
various items involved in the scope of work mentioned herein shall generally
consist of the following but not necessarily be restricted to:
64
Pakal Dul H E Project
4. Upper steel lined vertical Bend (4 set) of mean radius 15.0m and
internal diameter 3.9 meter.
12. 4 sets of Thrust collars at suitable locations on the u/s of MIV, details to
be finalised during detailed design. No grout holes shall be provided in
the reach downstream of the thrust collar.
13. Valve house and Butterfly valves including welding with pressure shaft
liners shall be in scope of other contractor.
Work by others: -
65
Pakal Dul H E Project
otherwise specified. Automatic welding would be preferred for the
fabrication at site. Suitable equipment for doing such type of work is a pre-
requisite for a tender being considered. The fabricator must, have in his
shop, satisfactory facility for plate bending edge preparation and end milling
of members as advised by Engineer-in-charge. Fabrication of steel work
shall be at fabricators shop to be set up by the contractor in the project
areas. Shop fabrication of heavy parts and other specials, requiring
precision finishing such as bends shall be done in regular workshop. The
contractor shall arrange at his own cost the transport of such materials from
site as well as fabricated materials from his shop to the project site. Any loss
or damage in transit on account of this shall be to the contractor’s account.
10.3 Layout
The contractor shall complete all preliminary works at site well before the
arrival of pressure shaft liner such as keeping in readiness of electrical
winches, mobile cranes, jig poles, all tools and tackles, welding sets etc. as
part of this contract, and any other work that may be necessary to start
erection immediately after the fabrication. The Contractor shall arrange for
such number of erection equipment, supervision, labour and other
arrangements so as to carry out the work efficiently.
The item wise specifications are intended for the general description of
quality, workmanship etc. desired for the items covered in the general
technical specification and scope of work. Specifications are not however,
intended to cover all the minute details and the work shall be executed in
accordance with the spirit of the tender specifications. In the absence of
specifications for any particular item of work it shall be executed as per
relevant IS code (latest revision) IS: 2825 i.e. Indian Standard Code for
Unfired Pressure vessels. In case neither of the above mentioned
specification and code are available for any particular item of work, the work
shall be executed as per section VIII ASME Unfired Pressure Vessel code
and ASTM Standards or as directed by the Engineer-in-charge. These
specifications shall be read in conjunction with the description of the items in
the schedule of items.
Objectives
66
Pakal Dul H E Project
The Steel lining of Pressure shaft shall be designed with the following
objectives:
a) Normal Condition
• Internal water pressure corresponding to maximum surge in the upstream
surge shaft i.e.EL.1741.50m or static head along with maximum normal
water hammer pressure at turbine inlet whichever is higher.
b) Intermittent condition
• Intermittent condition includes those during filling and draining of penstock.
• Internal water pressure corresponding to maximum surge in the upstream
surge shaft i.e EL 1741.5m with pressure rise during normal water hammer
at turbine inlet. The internal pressure shall be assumed to be linearly varying
between surge shaft and turbine inlet for the above water head.
• External water pressure either corresponding to normal reservoir level i.e
EL.1700.0m or the ground level vertically above the penstock i.e. invert level
which ever is less.
• Load included due to temperature variation of water from 6°C to 14°C
(Tentative & shall be confirmed during detail design).
67
Pakal Dul H E Project
• Poisons effect associated with radial expansion of liner under internal water
pressure.
c) Emergency condition
• This condition includes partial gate closure in critical time of penstock
(2L/seconds) at maximum rate, and the cushioning stroke being inoperative
in one unit.
d) Exceptional condition
• The dynamic pressure rise due to needle slam on loss of oil pressure or
mechanical failure. As the needles are hydraulically balanced at mid-point
turbine flow cut off shall be taken as instantaneous.
g) Miter Bend
Deflection angle between each successive segment shall not be more
than10°.Bends shall be designed with consideration given to the
concentration of hoop tension stresses along the inside of the bend.
Following formula shall be used to check the stresses.
j) Handling Consideration
• Minimum handling thickness shall be provided for the rigidity of the structure
during fabrication and handling during erection:
t o = (R+0.25)/200
where t o = minimum handling thickness in m, and
R =radius of penstock in m.
68
Pakal Dul H E Project
10.6 Submittals
The Contractor shall submit design & drawings and other technical data to the
Engineer for approval, as detailed in General Technical Specifications.
10.7 Materials
(1) All materials incorporated in the Work shall be of first-class quality, free
from defects and imperfections and, where shown, of the classifications
and grades designated. Materials not specifically designated herein shall
be suitable for the purpose intended and shall, as far as practicable,
comply with the latest specifications of the American Society for Testing
Materials (ASTM) and the ASME Boiler and Pressure Vessel Code
Section VIII, Division 2 or equivalent European Standard.
(2) Plate material for liners and pressure shafts shall be ASTM A517Gr. F or
approved equal.
(3) Material certification and testing shall be as per ASTM A20 manual and
ASME Boiler and Pressure Vessel Code Section VIII, Division 2 and with
supplementary requirements as in the following paragraphs of ASTM
A20:
(4) Steel Tubes Certification: The Contractor shall provide a certificate for
each steel pipe section as stipulated in this clause.
(5) Steel material of the same quality (ASTM A517Gr. F) or equal shall be
purchased from one manufacturer only.
(5) All material used, fabricated and welded to the liners and penstocks,
which are not particularly specified above, shall be compatible in respect
to chemical, mechanical and welding properties as defined by ASME
Code.
69
Pakal Dul H E Project
(6) Welding consumables shall be as per AWS Filler Metal specifications as
recommended by the steel manufacturer. Only "Low hydrogen welding
consumables" shall be used for welding. Consumables shall be baked
when necessary as recommended by the consumable manufacturer to
moisture levels required by the steel manufacturer. FCAW electrodes
and SAW flux electrode combinations shall be certified by the
manufacturer to meet the diffusible hydrogen limits given below.
Diffusible hydrogen shall be determined in accordance with AWS A 4.3-
86.
(7) Temporary and embedded supports for securing liners and penstocks
during concreting shall be of good quality and suitable for the intended
purpose. In addition, the same precautions shall be exercised when any
attachment is welded to the steel liners.
Loads arising during installation and concreting of the liners, due to self
weight of shell weight of shell between support and due to buoyancy forces
resulting when concrete is placed around the liners.
The gate, embedded parts and associated components shall be designed for
Reservoir water level of EL.1700.00m at normal allowable stresses as given
in General Technical Specifications. The gate and all related components
shall be checked for head corresponding to maximum surge level of
70
SURGE SHAFT -2 CONCRETE M20
650 THK
STEEL LINER
196131 Ø
560 00
97 29
9585 11142 1195
1 15
18
7
SURGE SHAFT -1
161840 THRUST COLLAR
(INDICATIVE) C
SECTION
A
11142 11951 D
2703
STEEL LINER 15 SECTION
18
3695
5
7
VALVE HOUSE, (101.5MX8MX18.8M)
4
THRUST COLLAR
6000
CONCRETE M20
1134
650 THK
2126
5
PRESSURE SHAFT ERECTION GALLERY
(LOWER),7M DIA D SHAPE
5
D PRESSURE SHAFT ERECTION GALLERY (UPPER),
7M DIA D SHAPE
6000
3500
Ø
THRUST COLLAR
0
3900 (105MX10MX19M)
MAIN INLET VALVE
1875
B
CR ETE
CON
0
ILL
CKF
) BA
ICAL
4081
TYP
HK.(
3900
T
650
5
B
SECTION
(STIFFENERS NOT SHOWN)
2900
A
SECTION
LINE
6000 Ø
LINE
C
3900 Ø
LINE
5525
2B
LINE
2A
0
1B
USE
1A
DRG. NO. NHPK - 3KT3 - 45 - GA - 004 - 00
W E R HO 51M)
PO 0.2MX NOMENCLATURE OF THE
X2
( 166M PRESSURE SHAFT LINES IS INDICATIVE ONLY.
MANIFOLD
ERECTION GALLERY
3900
PRESSURE SHAFT (UPPER)
6000 Ø
DN. SURGE
EL 1548.00 EL 1542.00
EL 1544.70
EL 1538.60
00
1 50 MANHOLE
56097 9585 161840 11142 21265 R
7200
35000
B
TURNING POINT
TURNING POINT
TURNING POINT
SECTION (STIFFENERS NOT SHOWN)
NOTES :-
1. ALL DIMENSIONS ARE IN MILLIMETERS AND ELEVATIONS IN
METERS.
B 2. MATERIAL OF STEEL LINER SHALL CONFORM TO
ASTM A 517 GR F. OR EQUIVALENT.
PRESSURE SHAFT LINER 3. EXTRA LENGTH OF 3.9M Ø OF 200MM(APPROX.) (4 Nos.) FOR
(LINE 1 A) JOINING HORIZONTAL PORTION OF PRESSURE SHAFT U/S &
3900 D/S OF EACH BUTTERFLY VALVE IN THE VALVE HOUSE.
PRESSURE SHAFT 4. DETAILS OF ANCHOR RINGS/THRUST RINGS AT SUITABLE
(STEEL LINED) LOCATIONS ON THE U/S OF MIV SHALL BE FINALIZED BY
CONTRACTOR DURING DETAIL DESIGN .
5. GROUTING HOLE TO BE PROVIDED IN LINER . HOLES SHALL
BE PLUGGED WITH THREADED STEEL PLUGS AND WELDING.
NO GROUT HOLES SHALL BE PROVIDED IN THE
DOWNSTREAM OF THE THRUST COLLAR.
6.EXTRA LENGTH OF 3.9M Ø OF 300MM (APPROX.) FOR
VALVE HOUSE JOINING EACH HORIZONTAL PORTION OF THE PENSTOCK TO
[8.0M.(W)X20.3M.(H)] REDUCER CONE OF MIV SUPPLIED BY OTHERS IN THE
POWER HOUSE.
SURGE SHAFT 1 7.WELDING ELECTRODE SHALL BE USED OF REPUTED MAKE
LIKE ESAB,D&H ,ADVANI.
STEEL TRANSITION 8.PAINITNG SHALL BE DONE AS PER SPECIFICATION.
MANIFOLD
9. NO SITE PAINTING IS ENVISAGED IN STEEL LINERS ( FROM
VALVE HOUSE TO THRUST COLLAR).
PRESSURE SHAFT 10.DOWNSTREAM OF THRUST COLLAR SHALL BE WRAPPED
DN. SURGE WITH BOND BREAKING MATERIAL.
6000 Ø
00
56097 9585 161840 11142 119511518711345
7200
50
2900
R1
TURNING POINT
TURNING POINT
TURNING POINT
DRG. NO. NHPK - 3KT3 - 45 - GA - 004 - 00
1400
EL 1247.50
MIV CAVERN
THRUST COLLAR CHENAB VALLEY POWER PROJECTS (P) LTD.
PRESSURE SHAFT LINER (A Joint Venture of NHPC, JKSPDC & PTC(I) Ltd.)
PRESSURE SHAFT
(LINE 1 B) ERECTION GALLERY
ikdy nqy ¼æaX|qju½ tYk fo|qr ifj;kstuk
(LOWER) PAKAL DUL (DRANGDHURAN) H.E. PROJECT
500 THK.
BACKFILL CONCRTE
PRESSURE SHAFT
ERECTION GALLERY
3900 Ø
3900
VALVE HOUSE
[8.0M.(W)X20.3M.(H)] 15000 (UPPER)
SURGE SHAFT 2
EL 1542.00
STEEL TRANSITION
MANIFOLD
00
1 50 MANHOLE
PRESSURE SHAFT R
35000
6000 Ø
DN. SURGE
EL 1548.00
A
EL 1538.60 SECTION
(STIFFENERS NOT
A
SHOWN)
TURNING POINT
3900 F
PRESSURE SHAFT
(STEEL LINED)
PRESSURE SHAFT LINER
(LINE 2 A)
7200
7200
6000 Ø
FLOW
VALVE HOUSE
[8.0M.(W)X20.3M.(H)]
SURGE SHAFT 2
10000 7200
STEEL TRANSITION
MANIFOLD
SECTION F
6000 Ø
00
11142 15187
50
196131
7200
2900
R1
27035
TURNING POINT
11951
DRG. NO. NHPK - 3KT3 - 45 - GA - 004 - 00
1400
EL 1247.50
MIV CAVERN
THRUST COLLAR CHENAB VALLEY POWER PROJECTS (P) LTD.
PRESSURE SHAFT LINER (A Joint Venture of NHPC, JKSPDC & PTC(I) Ltd.)