FGD & Ash Handling Maintenance Manual
FGD & Ash Handling Maintenance Manual
FGD & Ash Handling Maintenance Manual
OWNER: CONSULTANT:
VIETNAM ELECTRICITY POWER ENGINEERING CONSULTING
VINH TAN THERMAL POWER MANAGEMENT BOARD J.S.C 2 (PECC2)
EPC
CONTRACTOR: SHANGHAI ELECTRIC GROUP CO.,LTD.
COMPILE:
CHD POWER PLANT OPERATION CO.,LTD.
PROJECT: DESIGN STAGE:
VINH TAN 2 2×622MW THERMAL POWER PLANT Detail Design
Contents
1. Overview ....................................................................................................................................................... 1
1.1 Main engine device model .................................................................................................................. 1
1.2 Overview ............................................................................................................................................. 1
1.3 Flue gas system ................................................................................................................................... 2
1.4 SO2 absorption system......................................................................................................................... 2
1.5 Seawater supply system....................................................................................................................... 3
1.6 Seawater recovery system ................................................................................................................... 3
1.7 Other auxiliary systems ....................................................................................................................... 3
2. Equipment specifications ................................................................................................................................. 4
2.1 Flue gas desulfurization (FGD) system performance .......................................................................... 4
2.2 Equipment specifications .................................................................................................................... 5
3. Maintenance and overhaul of flue gas desulfurization (FGD) system devices ................................................ 6
3.1 Overhaul and maintenance items of all levels ..................................................................................... 7
3.2 Main equipment maintenance process and quality requirement.........................................................11
4. Dirt catcher equipment maintenance and overhauling ................................................................................... 17
4.1 Electric precipitator equipment overview ............................................................................................ 17
4.2 Equipment specification .................................................................................................................... 17
4.3 Safety tips (precautions) .................................................................................................................... 19
4.4 Maintenance items............................................................................................................................. 20
4.5 Equipment parts maintenance methods and precautions ................................................................... 21
4.6 Acceptance, test run, test and summary ............................................................................................ 24
4.7 General fault and handling methods during electric precipitator operation ...................................... 25
5. Pneumatic ash conveying equipment maintenance and overhauling ............................................................. 30
5.1 Overview ........................................................................................................................................... 30
5.2 Equipment specifications .................................................................................................................. 30
5.3 System layout .................................................................................................................................... 31
5.4 Pneumatic ash conveying system maintenance technology and quality standard ............................. 32
5.5 Ordinary maintenance and fault shooting.......................................................................................... 35
6. Equipment maintenance and overhaul of ash silo unloading system ............................................................. 36
6.1 Overview ........................................................................................................................................... 36
6.2 Main equipment specification ........................................................................................................... 36
6.3 Overhaul technology and quality standard of ash silo unloading system .......................................... 40
6.4 Daily maintenance and troubleshooting ............................................................................................ 45
Maintenance Manual on Ash Handling & Flue Gas Desulfurization
I
Vietnam Vinh Tan Phase II 2×622MW Coal Fired Power Generation Unit
1. Overview
pipeline.
1.5 Seawater supply system
The desulfurization absorber drains water with condenser circulating cooling water, after pressurized
with seawater booster pump and directly supplies to desulfurization absorption tower. The reacted seawater is
discharged to seawater recovery system. Another part of condenser outlet circulating cooling water leads out
to seawater recovery system through drainage pipeline, mixed with desulfurized seawater in the seawater
recovery system. After the desulfurized draining water reaches the target, it is discharged into the sea from
circulating water outlet through open drainage channel of the power plant.
1.6 Seawater recovery system
1.6.1 Seawater recovery system includes aeration basin and aeration fan. The aeration basin is divided into
water distribution zone, aeration zone, emission zone and bypass zone.
1.6.2 A large quantity of fresh seawater from unit circulating water system siphon well enters water
distribution zone of aeration basin for water distribution, wherein, most of the seawater enters aeration zone
front-end, mixed with directly accessible desulfurized seawater, and a small part of fresh water is directly
discharged into emission zone through bypass zone. The mixed seawater is aerated during forward flow
process in aeration zone, and the aeration fan blows a large quantity of air through aeration diffusion device
(aerator) so as to create a large quantity of fine bubbles to make dissolved oxygen in seawater within aeration
basin saturated and oxidize labile sulfite into stable sulfate ion, and the carbonate CO32- and bicarbonate
HCO3- in seawater can react with H+ discharged from absorption tower to release CO2 through aeration so as
to meet the requirements on seawater emission standard and finally discharge back to the sea. The
desulfurized seawater realizes seawater PH value≥6.5, COD discharge value ≤6mg/l and dissolved oxygen
DO>3mg/l through aeration & oxidation to accomplish no-pollution discharge. .
1.7 Other auxiliary systems
1.7.1 FGD device GGH bypass baffle valve is equipped with electric actuator, and other valves (air valves)
under automatic control and remote operation are equipped with pneumatic actuator. The instrument
compressed air is supplied by main engine.
1.7.2 Adopt steam for heat exchanger component purging medium of flue gas heat exchanger. The steam
source is supplied by boiler purging steam system for main steam and auxiliary steam. The closed chilled
water system for desulfurization island leads from main engine closed chilled water, used for the cooling of
booster fan motor bearing and oil stations.
1.7.3 The desulfurization island is installed with independent process water system, with two-way water
source respectively from industrial water and industrial wastewater, and normal industrial wastewater
makeup water is used as flushing water for GGH and absorption tower demister.
2. Equipment specifications
Equipment Maintenance
Main process points Quality requirements
name contents
2) 2) Impeller rotating flutter 2) It should meet factory’s requirements
and static balance inspection and 3) There are no corrosion, pit and so on.
measure unbalance weight.
1) 3) Inspect blade apex
clearance, degree of balance and
so on.
1)Inspect surfaces of main axle
1) There are no crack and other defects and journal
and journal.
Inspect and adjust should have no groove.
2) Inspect main axle straightness
main axle. 2) Straightness is 0.05 mm and cylindricity
and journal cylindricity
tolerance is 0.04 mm.
tolerance.
1) Inspect oil pump and coupler
1) Cooling water system various pipes and gates
and change bearing and shaft
have no leakage.
seal rubber ring.
2) Fuel system various pipe line joints have no
2) Clear fuel tank bottom dirt
Lube oil station leakage phenomenon.
and change fuel.
maintenance 3) Water pressure is 0.5Mpa and there is no
3) Oil cooler water pressure leak
leakage when oil cooler operates for 30 minutes.
finding.
4) Oil station outlet working pressure is no lower
4) Clear fuel filters strainer
than 2.5Mpa.
element and magnetic filter.
1) Impeller surface should have no corrosion,
1) 1) Inspect impeller surface. deformation and crack and impeller surface is
Overhaul impeller
2) 2) Inspect sealing fin clean.
and sealing fin.
deformability. 2) Sealing fin has no obvious deformation and
change it if there is serious gas leakage part.
1) Inspect sealing air pipe
1) There are no sundries, corrosion and leakage in
corrosion and connector
Overhaul sealing the pipe and pipe is clear.
connection and drain pipe.
air device. 2) Sealing fan can make sure wind pressure and
2) Inspect and overhaul sealing
rotating wind pressure.
fan device.
1) Inspect whether bearing has
mechanical damage. 1) Bearing has no corrosion and crack.
Overhaul bearing.
2) Inspect whether bearing block 2) Bearing block has no crack and it is well fixed.
has displacement or crack.
Inspect whether worm gear,
Damper Worm gear and worm are intact and have no
Overhaul worm worm and box body have
corrosion and lube oil does not go bad and oil
gear case. mechanical damage and change
level is normal.
lube oil.
Overhaul baffle Inspect whether baffle Baffle connecting rod should have no curve and
connecting connecting rod has deformation deformation, firm connection, can open and close
Equipment Maintenance
Main process points Quality requirements
name contents
mechanism. or curve. First inspect each flexibly and it reaches full closing in 00 and full
rotating and then install opening in 900 .
transmission connecting rod and
inspect whole baffle.
1) Inspect and change shaft seal 1) Shaft seal should be intact and have no
Baffle shaft seal packing. corrosion and leakage.
maintenance 2) Inspect and adjust oil seal 2) Shaft seal press cover should be clean and have
press cover. no crack.
1) Inspect baffle body action 1) Inspect baffle action is smooth and has no
situation. obstruction, abnormal sound and noise and action
Baffle body
2) Inspect baffle body and is in place.
maintenance
sealing fin abrasion and 2) Inspect baffle is in tight closure and has no
corrosion situation. leakage and no breakage.
1) Surface and weld joint are neat and have no
1) Impeller and blade surface
crack.
inspection.
2) Impeller and main axle connecting key must not
2) Main axle journal and
have loose sense and key top clearance is
installation inspection.
Inspect impeller 0.3-0.5mm.
3) Impeller rotating flutter and
and main axle 3) Impeller, main axle fixed ring and tightened
static balance degree inspection.
maintenance. ring must not have loose sense.
4) Impeller, main axle fixed ring
4) Macro axis levelness error is no more than
and tightened ring inspection.
0.04mm/m.
5) Mule and impeller clearance
5) Mule and impeller are joined: axial clearance is
inspection.
3-5mm.
1) Wind shell, support surface and weld joint are
neat and have no crack.
1) Wind shell and support
Aeration fan Chassis mule 2) Mule installation is firm and mule seal ring has
inspection.
maintenance. no deformation.
2) Mule inspection.
3) Mule and impeller clearance meet factory’s
requirements.
1) Inspect baffle and actuator 1) Baffle should keep switch working well and
Inlet baffle opening. switch angle indicates correctly.
maintenance. 2) Inspect and change baffle 2) Baffle and part installation are intact and shaft
shaft seal packing. seal is precise.
Equipment Maintenance
Main process points Quality requirements
name contents
1) Inspect oil pump and coupler
1) Cooling water system various pipes and gates
and change bearing and shaft
have no leakage.
seal rubber ring.
2) Fuel system various pipe line joints have no
3) Fuel tank bottom dirt
Lube oil station leakage phenomenon.
clearance and change fuel.
maintenance. 3) Water pressure is 0.5Mpa and there is no
3) Oil cooler water pressure leak
leakage when oil cooler operates for 30 minutes.
finding.
4) Oil station outlet working pressure is normal
4) Clear fuel filters strainer
and filter differential pressure is normal.
element and magnetic filter.
Scaling, soot formation and
There is no large area scaling, soot formation or
deposition inspection and
blockage and no dust is locally accumulated.
clearance.
Tower internal
1) Mend corrosion and abrasion 1) Undergo erosion resistant treatment after
parts maintenance.
support. finishing repairing support.
2) Packing inspection and 2) Packing top is neat and has no sundries and
clearance. filling amount meets design requirements
Tower wall and
erosion resistant
Tower wall leakage inspection. Undergo handling and adopt erosion resistant
coating
measures for leakage parts according to location.
maintenance.
Inlet and outlet Tower wall lining erosion resistance coating
Tower wall erosion resistant
Absorption flue, tower wall should not have crack, bubbling, peeling off and
coating inspection and flaw
tower and tower internal other phenomena. Repair damaged erosion
detection.
part maintenance. resistance coating.
1) Inspect pipe flange and
1) Flange and connecting pieces are intact and
Seawater pipe connecting pieces.
have no leakage.
inspection. 2) Pipe internal inspection and
2) There are no sundries in the pipe.
clearance.
1) Nozzle inspection is
Spray nozzle 1) Nozzle installation is firm and has no blockage.
unblocked.
maintenance. 2) Spray effect is good.
2) Nozzle spray test.
1) Defogger inspection and 1) There is no breakage and falling and defogger
Defog components mending. components’ installation is intact.
maintenance. 2) Supporting framework 2) Supporting framework is intact and there is no
inspection and mending. fracture and damage.
Impeller and axle
Inspect shaking degree. Shaking degree is ≤0.05 ㎜.
sleeve
Seawater
1) Inspect coupler. 1) Coupler and middle nipple should be complete
booster pump
Inspect coupler. 2) Inspect the joint between and have no crack and no deformation, whose
coupler and journal. surface is bright and clean, and coupler and axle
Equipment Maintenance
Main process points Quality requirements
name contents
3) Inspect coupler bolt. firmly join and have no loose.
2) Connecting bolt should have no curve and
deformation; bolt is intact; gasket, spring cushion
and nut should be complete.
3) Coupler and axle joint is H7/K6.
4) Joint among keys must not have loose sense and
key top clearance is 0.3-0.5mm.
Various parts surfaces should be neat, bright and
All parts Surface inspection. clean, no damage and no defect and castings have
no crack, bubble and other defects.
Axle surface has no crack, corrosion, groove mark
Axle Inspect flexibility. and other undesirable phenomena and axle shaking
degree is ≤0.05mm.
Impeller Inspect gourd ladle skewness. Gourd ladle skewness is ≤0.05 ㎜.
Seal ring and Radial clearance is 0.35-0.45mm, axial clearance
impeller Inspect fit clearance. is 1.5-2.0mm and tightening force is 0.03-0.05mm.
1) Mechanical seal shaft sleeve has no crack and
sgraffito phenomena and fit clearance with axle is
≤0.07mm.
2) Mechanical seal working compression amount
is 50%-70% of total compression amount.
Inspect and change mechanical
Mechanical seal 3) Mechanical seal has no eccentric wear, crack
seal.
and other phenomena; moving ring spring and
supporting framework are good and have no jam;
moving and static ring surfaces are bright and
clean, which have no crack, scratch, rusty spot or
groove.
Pump body sealing Surface is neat, bright and clean, has no defect,
Inspect joint surface integrity.
flange. intact and has no leakage.
1) Axial clearance is 2.5-5mm and radial clearance
between impeller inlet and pump shell is 0.70mm.
Impeller and pump 1) Installation clearance
2) Rotor disc flexibly move and has no jamming.
shell inspection.
3) Radial shaking degree is ≤0.10mm at impeller
seal ring.
1) Coupler excircle deviation is ≤0.1mm; coupler
end face deviation is ≤0.06mm.
Calibrate coupler Coupler calibration and
2) Foot pads are no more than 3 pieces.
center. connection.
3) Water pump vibration value meets factory’s
requirements.
4.2.1 Auxiliary equipment specifications (it is the data of one precipitator if no specified mark.)
Equipment Parameter Quantity
Rectifier transformer Model: GGAj-2.0A/72KV 8 sets
AC input: rated voltage: 400V (effective value)
rated current: 540A (effective value)
Frequency: 50/60Hz
DC output: rated voltage: 72KV (average value)
rated current: 2.0A (average value)
HP isolating switch Model: FTTB 8 sets
Rated voltage: 72KV
Rated current: 3A
Cathode vibration Reducer model: XLED63-595-0.37KW 8 sets
Reducer form: cycloidal-pin wheel reducer
Motor model: Y27124
Rotating speed: 1440r/min
Power: 0.37KW
Rated voltage: 400V
Frequency: 50Hz
Rated current: 1.14A
and flue.
4.4.5 Inspect air deflector, air flow distributor and back plate.
4.4.6 Inspect dust hopper heating device and top insulator compartment heating device.
4.4.7 Inspect dust hopper gasification wind device.
4.5 Equipment parts maintenance methods and precautions
4.5.1 Remove ash in the internal of electric field.
1 Inspection before ash removal:
Inspect anode plate and cathode line soot formation situation, analyze soot formation causes and
make technical records.
Inspect air flow distributor and trough plate soot formation situation, analyze soot formation causes
and make technical records.
Inspect polar plate deviation situation and inter-electrode distance macroscopic inspection.
2 Ash removals:
Electric field inner top and insulating sleeve protective barrel.
Anode plate and cathode large and small framework and polar line.
Vibrating part.
Inlet air deflector, air flow distributor, trough plate and back plate
Inlet and outlet flue, outlet air flow distributor, trough plate and dust hopper.
Remove ashes in the following order: from top to down and from inlet to outlet, and do not drop
ash removal instruments.
Inner electric field and dust hopper.
When possible, dry it with hot wind after flushing ashes with water.
4.5.2 Anode plate device maintenance
1 Inspect anode plate deformation, abrasion and its hanger structure situation.
2 The datum of each electric field is anode plate row whose middle part is relatively flat and the
homopolar distance is measured with polar distance pallet tools. Spacing measurement should be at the outlet
and inlet position of each row of polar plate. The measurement is along three points of up, middle and down
on the polar plate height, and each large and small repair measurement should be at the same position and
make the records.
3 When the homopolar distance exceeds the manufacturers’ specifications, adjust the deformative polar
plate. For the deformative polar plates on running, which have been early found and which cannot be
eliminated with adjustment methods, prepare for unroofing before maintenance and change the whole row of
polar plate on maintenance.
4 When dies holder deviates, limit it according to requirements and leave activity gap in accordance with
design specifications.
5 Inspect polar plate sinking situation and if it sinks inspect polar plate punch holder fixed pin or
concave and convex sets.
6 Inspect die holder (polar plate) trip rod deformative situation, bearing anvil head abrasive situation,
whether rivets or bolts for fixing are loose, inspect vibrating center and adjust it if necessary (it goes after
anode plate row and gear device maintenance).
7 Inspect anode plate belt and fixed screw should not be loose.
4.5.3 Cathode large and small framework device maintenance
1 Insulator compartment and insulating sleeve protective barrel maintenance
Inspect bearing insulator crosstie deformative and horizontal situation; inspect results of bearing
insulators insulating sleeve according to electric maintenance; when needing to change it, mechanical parts
are coordinated to make fixing measurements of cathode large framework. When electric changes insulating
sleeves, pay attention to plugging around insulating pipe bottom with asbestos rope to avoid leaking wind.
Inspect protective barrel corrosion and concentricity. When changing protective barrel, after
making firm fixation measurements between large framework and inwall, boom bolt exposed length and
relative position size, loose boom top large bolt, remove boom and penetrate protective barrel. Boom takes its
place, find protective barrel center and concentricity according to boom center and fix protective barrel.
Demolish large framework temporary fixation measurements, calibrate this large framework height and
horizontal position and pay attention to insulator crosstie levelness.
2 Cathode large and small framework maintenance
Overhaul large framework levelness and verticality and shell body inner wall relative size should
comply with the design requirements.
Inspect large framework deformation situation.
If large framework horizontal direction needs to adjust, conduct it with changing insulator,
insulating sleeve or protective barrel; if adjusting it along, adjust it after jacking it with lifting jack.
Inspect up down small framework connecting structure and small framework fixing clamps and
first adjust it if framework tube locally deforms.
Each up down framework measures cathode small framework homopolar distance at two points,
which the same as anode plate row. When it exceeds specifications and has deviation, adjust it with fixation
clamp for trimming.
When adjusting cathode small framework, conduct it along with measuring heteropolar distance,
finally make sure heteropolar distance is within prescribed limit and adjust cathode small framework based
on anode.
3 Cathode lines maintenance
Inspect polar line and small framework connecting plate snap or screw dropping situation.
Inspect polar line discharge point dust, electric corrosion and “dropping sting” situation.
When polar line in middle location of framework cannot be trimmed or changed, which influences
spacing, cut it.
When cutting polar lines, pay attention not to damaging nearby polar lines.
4.5.4 Vibrating device
Inspect vibrating anvil and sleeve intact, no fracture and breakage.
Inspect vibrating anvil uplifted height and make records.
4.5.5 Air deflector, air flow distributor and back plate
1 Air deflector:
Inspect abrasive situation.
Inspect welding fixation situation.
Inspect guide direction, angle and air flow distributor distance, which meet the requirements of
manufacturers.
2 Air flow distributors:
Inspect connecting fixing clamp splint, loose dropping and screw abrasive situation and spot weld
when changing new screws.
Fixed angle steel inspection should not swing; inspect upper hang air flow distributor U-steel and
screw corrosive situation.
Inspect distribution plate tapping abrasive situation and distribution plate glancing flatness; when
tapping is abrasive, change it and adjust it when deforming.
Distribution plate bottom and inlet gland inner wall spacing should conform to design
requirements.
3 Back plate;
Inspect back plate soot formation, abrasive deformation and corrosive situation on the top two sides
and bottom of electric field. Spacing to polar plate conforms to design requirements.
Inspect dust hopper back plate deformation situation and mobile back plate should be flexible.
4.5.6 Shell body, dust hopper, outlet and inlet gland, man hole door and flue
1 Shell body and dust hopper
Inspect inner wall corrosion situation.
Inspect dust hopper and inner shell body support abrasion and fixation situation.
Dust hopper flange joint surface wind leakage situation inspection and leaking stoppage.
When there are convex collapse and deformation on the inner wallboard of shell body, adjust it to
keep straight and avoid causing vortex.
Soot formation and corrosive situation inspection on top seal plate of electric field.
Grey-headed outer steam heating device ring-shape pipe corrosive and leaking inspection and valve
and drain valve maintenance.
2 Outlet and inlet gland:
Inner wall abrasion and corrosion situation inspection.
Inner wall and support corrosion and abrasion inspection.
Shell outlet and inlet flue flange joint surface air leakage inspection and handling.
Concave collapse mending and reinforcement.
3 Man hole door maintenance:
Through the maintenance, switch is flexible and jackscrew and handle are repaired.
Man hole door joint surface is firm and does not leak wind; sealing packing is changed and
trimmed.
Inner wall corrosion situation inspection.
When man hole door and HP electric supply device have latching, coordinate electrical
maintenance and conduct it.
4 Defogger top cap and insulator compartment box body;
Deformation top cap trimming.
When boxing up, joint surface fills sealing gasket.
Rainwater catch basin and sewer pipe maintenance.
Inspect insulator compartment inner wall stringency and handle it if there are bulges.
5 Flue maintenance is the same as that of outlet and inlet gland maintenance and inspect expansion joint
abrasive and corrosion and flange joint surface stringency.
6 After overhauling, whole electric precipitator including insulator compartment insulation should trim,
which conforms to design requirements and mop it.
7 Electric field internal aisle maintenance
4.5.7 Local tiding
1 Stairs, platform and handrail trimming and mopping.
2 Signboards trimming and completion.
3 Ash groove clearance and trench covers are spread in order.
4 After maintenance, clear local sundries and detachable parts, useful parts are conserved according to
requirements and are piled neatly.
4.6 Acceptance, test run, test and summary
4.6.1 Quality acceptance
Do quality inspection and acceptance for ensuring maintenance quality. Quality inspection combines
maintainer self-checking, mutual inspection and inspection personnel checking; after inspection personnel
finish each maintenance, according to quality standard, first after self-check is qualified and make technical
records and then send it to inspection personnel acceptance.
4.6.2 Test run and test
1 After electric precipitator maintenance and before test run, inspection personnel should do disclosure
to operating crew the following items: main maintenance items, equipment system improved transaction and
changing information, residual defects after maintenance and so on. During test run and test, relative
maintenance operating crew together inspect equipment technical conditions and operating situations.
2 On the condition of finishing LP electric maintenance and power transmission, after vibrating device
maintenance and finishing completion formalities, conduct test run and vibrating center verification.
3 After finishing electric field internal work and clearing sundries in dust hopper, conduct ash conveying
device test run.
4 Change more than 1/3 of air flow distributors, air deflector and parts concentrated, but if it is less than
1/3, conduct air flow distribution test.
5 Do HP and LP electric equipment protection, faults warning and signal monitoring test.
6 Do insulation sleeve and dust hopper heating device tests.
7 If necessary, do electric precipitator body and outlet and inlet gland leakage test.
8 After overhauling, conduct electric precipitator dust collection efficiency measurement under rated
load.
9 After electric precipitator overhauling and small repair, do cold no-load VA boosters tests.
4.6.3 Maintenance summary
1 After electric precipitator overhauling, organize relative personnel conscientiously summarize
experience, affirm achievements, discover disparity and continuously improve maintenance quality and
technological level.
2 After maintenance for one week, finish maintenance summary report (including equipment technical
records and test reports).
3 Equipment technical records are the important link of straightening equipment management and
technical management, so reserve them as technical files.
4.7 General fault and handling methods during electric precipitator operation
General fault and handling method during electric precipitator operation
No. Fault phenomena Main causes Handling methods
Control cabinet air 1.Defogger has foreign matter causing second 1. Clear foreign matter.
switches trip or trip level short circuit. 2. Cut off break line and take out cast.
1
again after 2.Discharge electrode fracture or internal parts 3. Repair level indicator and exclude soot
switching on. falling causing short circuit. formation.
5.1 Overview
Vinh Tan II-phase unit adopts positive pressure concentrated phase pneumatic ash conveying system to
convey the dust collected by precipitator. In which, one boiler is a unit. Each boiler is equipped with two sets
of double-room four electric field electrostatic precipitators and every boiler electrostatic precipitator is set up
with 32 dust hoppers. Each boiler economizer is set up with 8 dust hoppers. Each boiler air preheater is set up
with 8 dust hoppers. Each precipitator dust hopper is set up with a manual isolating valve, a feed valve, an
expansion joint (only No. 1 and 2 electric fields are set up with ash conveyer)and an ash conveyer (fluidizing
transporter). Two boiler fly ash conveying systems are set up with 3 φ 15m ash silo. Ashes under No.1 boiler
electrostatic precipitator, economizer and air preheater are conveyed to No.3 ash silo and No.2 ash silo
(public ash silo) through positive pressure concentrated phase pneumatic ash conveying system and switching
operation is allowed. Ashes of No.2 boiler electrostatic precipitator, economizer and air preheater are
conveyed to No.1 ash silo and No.2 ash silo (public ash silo) through positive pressure concentrated phase
pneumatic ash conveying system and switching operation is allowed.
The function of ash conveying system is to automatically complete collecting, conveying of ashes under
electrostatic precipitator, boiler economizer and air preheater and pipeline purging, blowing, display the ash
level of ash silo 1, ash silo 2 and ash silo 3, realize the high and low material level alarm of ash silo 1, ash
silo 2 and ash silo 3, realize the remote start-stop control and fault alarm of bag-type precipitators of ash silos
(ash silo 1, ash silo 2 and ash silo 3) so as to complete the function of the whole set of ash conveying system.
The system adopts automatic program control and remote manual operation and local manual operation
can be realized.
5.2 Equipment specifications
5.2.1 Pneumatic ash conveying system performance (one boiler)
Item Unit Value
System output t/h 165
No.1 electric field dust hopper of electrostatic
t/h 122
precipitator
No.2 electric field dust hopper of electrostatic
t/h 24(Normal)/122(No.1 electric field quits)
precipitator
No.3 electric field dust hopper of electrostatic
t/h 4. 8(Normal)/24(Quit)
precipitator
No.4 electric field dust hopper of electrostatic
t/h 1.2
precipitator
Dust hopper of economizer t/h 8
Dust hopper of air preheater t/h 5
3
Average air consumption for system operation Nm /min 43.2(Designed coal BMCR)/65. 5(Designed output)
enter B side pipeline of No.1 electric field and form mixed ash with No.1 electric field ash for common
conveying;
No.1 electric field of electric precipitator is divided into A side and B side, which adopts 4 delivery
pumps respectively to convey electric ash to ash silo through pipeline in series; it can switch to another ash
silo;
No.2 electric field of electric precipitator is divided into A side and B side, which adopts 4 delivery
pumps respectively to convey ash to ash silo by combining with corresponding side of No.1 electric field into
one pipeline; it can be switched to another ash silo; No.1 and No.2 electric fields are set up with 2 pipelines;
No.3 and No.4 electric field of electric precipitator respectively adopts 8 delivery pumps in series to
convey ash to ash silo by using one pipeline; it can be switched to another ash silo; No.3 and No.4 electric
fields are set up with 1 pipeline.
Every boiler delivery is set up with 3 ash pipes.
5.4 Pneumatic ash conveying system maintenance technology and quality standard
5.4.1 Pipe and pipe accessory maintenance
Ash conveying pipe is on violently abrasive state for long time and bears 0.2-0.4Mpa pressure during the
operation. When some part of pipes has wearing and leakage phenomenon, contact operation staff and stop
this unit operation; when medium in the pipe reduces to normal pressure, maintenance staff inspect abrasive
situation of leakage place; if it can be welded up, adopt iron plate supplement welding; if it cannot be welded
because of thin pipe wall, temporarily handle it with putting clamp. Make records of pipe abrasive situation
(including expansion joint and elbow), and make relative changing in schedule maintenance.
Feed dome valve is the most important key part of pneumatic ash conveying system. Spool is made of
wear resistant casted steel material, whose surface conducts hardening treatment; make use of its smooth and
hard surface and make sure good firm contact of rubber seal ring for reliable sealing. Rubber seal ring is
made of specially formulated rubber, which has the features of corrosion resisting, wear resistant, aging
resistance and so on.
Feed valve spool is a spherical dome. During feed valve is on opening and closing process, there is a
1mm clearance between spool and valve body sealing lip, which makes it movement without contact and
whose purpose is not produce friction between spool and valve body. Feed valve pneumatic actuators are full
sealed cylinder structures and directly drives feed valve rotating, which effectively avoids ash entering into
them and producing abrasion and leakage and other problems. When feed valve is in sealing state and after
rubber seal ring inflates, it tightly presses on spherical dome spool forming a very reliably seal band; because
seal ring is soft seal, it can contain particles, which makes it in seal ring and close to spool surface, limits
particles moving and reduces abrasion to some content.
Because seal ring material is rubber, it is easy to be aged and damaged on high temperature and abrasive
state, please periodically change it after using a certain time. When changing seal ring, loose bolts between
flange and main valve body, take down flange, take out seal ring and aluminum alloy bushing ring, change
new seal ring, reload seal ring and bushing ring into main valve body and tighten again flange, main valve
bolt. In addition, simple maintenance and change seal ring easily.
5.4.2 Change expansion seal ring
1 Switch off gas source and power source and drain residual air pressure of system and parts.
2 After withdrawing dome valve withdraw concave bolts fixing terminal disc and valve body.
3 Record the direction of top disc-seal ring expansion connector relative valve body and withdraw top
disc parts from valve body. Top disc parts include expansion seal ring, inner ring and backing ring and pay
attention to top disc washer number and size, because it will influence spacing of spherical parts and seal
rings.
4 Withdraw expansion seal ring from inner ring.
5 Change abrasive or scratched expansion seal ring;
6 Reinstall in reverse order of withdrawing, use new top disc-valve body washer and make sure new
washer thickness is the same as that of changed one.
5.4.3 Change dome or axle
1 Withdraw dome valve and put it on dry and clean ground;
2 Remove cylinder and make sure spherical parts have been firmly clamped to avoid occurring out of
control movement when withdrawing cylinder;
3 Withdraw fixing spherical parts and drive/pivot axle bolt;
4 Withdraw spherical parts and put them on clean and dry ground;
5 Withdraw axles from valve bodies and inspect whether they are abrasive and damaged;
6 If changing axle, change shaft seal;
7 Make sure axle clean and no burr, and then reinstall in reverse order of withdrawing and make sure
drive axle is matched with valve bottom cylinder support.
5.4.4 Change bearing
1 Withdraw dome valve top disc and axle acceding to the above methods;
2 Withdraw sealing ring fixing ring and shaft seal to inner valve body.
3 With circular seat and bearing fixture smaller than bearing outer diameter, push bearing out of valve
body until into inner valve.
4 From the outside of valve, push changed bearing to inner valve body and at the same time precisely
calibrate oil hole;
5 Reinstall axle and make sure axle clean and no burr until shaft bushing sticks out and withstand
bearing cage;
make sure 90 degree rotating piston gear and small gear meshed in correct tooth. Gear rotates in clockwise
order when piston gathers. Inspect cylinder and make sure cylinder top correctly indicates closure or opening
position:
12 Install in the reverse order of withdrawing cylinder. Pay attention to making sure cylinder and valve
are at opening or closure position at the same time.
5.5 Ordinary maintenance and fault shooting
5.5.1 Feed dome valve
Periodically inspect whether dome valve pressure table indication value is within normal pressure range,
cylinder action is flexible and seal ring is abrasive and loses effectiveness (whether pressure switch has much
soot formation).
5.5.2 Balanced valve
Periodically inspect whether valve action is flexible and valve sealing loses effectiveness.
5.5.3 Pressure reducing valve
Inspect whether pressure reducing valve has gas leakage and water leakage phenomenon and in time
clean spool.
5.5.4 Check valve
Periodically inspect whether spool and seal ring are abrasive and in time change them.
5.5.5 Blowing plug valve
Periodically inspect whether blowing plug valve closure is in place and sealing is normal.
6.1 Overview
Vinh Tan II-phase unit is set up with 3 flat base concrete ash silos, which are used to collect the ashes
from two sets of boiler precipitator, economizer and air preheater dust hoppers. Every fly ash silo is set up
with silo-top exhaust air filter with 100% capacity and every ash silo is set up with a set of precipitator on the
top, which can 100% handle the air amount that enters into ash silo to satisfy the delivery air amount of all
the ashes by every boiler that enter one ash silo, ash replacement air amount, air volume entering into ash silo
by ash silo gasified air and the exhaust air volume of ash silo lower dry ash unloader. Silo top is set up with
vacuum pressure relief valve, three ash silos are set up with three sets of vacuum pressure relief valves. Ash
silo is set up with gasified blower and heater and every ash silo is installed with gasified groove at the bottom
to prevent the ash in dust hopper from damping and bonding.
Every ash silo is set up with 3 ash discharging ports, discharging hopper gasification plate to prevent
the ash in dust hopper from damping and bonding. Three ash silos are installed 5 sets of wet-type
discharging system and 4 sets of dry-type discharging system to exhaust ash.
6.3 Overhaul technology and quality standard of ash silo unloading system
6.3.1 Maintenance technology and quality standard for wet blender
Overhaul item Overhaul technology Quality standard
Preparations Principals of overhaul shall deal with working
Qualified filling.
before overhaul sheet
Measurement 1. Measure the axial and radial clearance.
Remove the screws on protective cover
before overhaul 2. Record the shim number and thickness.
Remove gland Remove the shaft sealing cover screw, remove the Replace the damaged land screw.
retainer plate packing, and loose the gland with a copper bar.
Remove the screw Remove the screws on bearing cover.
Measure the thickness of pad.
bearing body Check for the abrasion conditions.
Remove the Lift the main shat to check the abrasion
connection screw conditions of the impeller Replace the impeller if its abrasion is greater than 2/3
of short shaft and Remove the flange screws of short shaft and main Check the abrasion conditions of the impeller.
main shaft shaft to check the abrasion conditions
Lift out main
Lift out the gear part of main shaft and bearing
shaft and bearing Measure and record.
body
body
1. Remove the auxiliary gear set with wheel
There is no defect, like pitting, peeling, crack and
puller.
corrosion on the internal and external balls of the
Remove the gear, 2. Remove the retaining screw of bearing
bearing.
bearing body and body to remove it.
The maximum radial clearance between bearing outer
bearing 3. Loosen the lock net of rigid bearing.
ring and its body is 0.04mm, otherwise, replace the
4. Clean up the parts and check the abrasion
bearing body.
condition.
7.1 Overview
Vinh Tan Phase II slag discharging system adopts water-cooling type submerged scraper conveyor
scheme. For boiler B-MCR working condition by using designed coal quality, the slag discharging quantity is
21.11t/h. Boiler deslagging device is arranged as follows: water seal groove is under water seal plug board
and slag receiving well is under water seal grove, hydraulic shut-off valve is under slag well, submerged
scraper conveyor is under hydraulic shut-off valve and submerged scraper conveyor is arranged on the
ground. For normal operation, hydraulic shut-off valve’s door panel is inserted in the water channel of
submerged chain conveyor to keep the seal of boiler. Water seal groove, transition slag well, shut-off valve,
submerged scraper conveyor and relevant ancillary facilities shall satisfy the seal requirement for boiler’s
operation. Make-up water of submerged chain conveyor is supplied by water supply pump under buffer tank.
Every boiler shall be set up with 2 water supply pumps, one for delivery and one for standby. Water seal
groove, transition slag well, hydraulic shut-off valve, submerged scraper conveyor and ancillary facilities
shall be arranged at the bottom of hearth; elongated submerged scraper conveyor shall operate continuously;
head of submerged scraper conveyor, electric three-links, slag silo (two for each boiler) shall be arranged
outside boiler room. Every boiler slag silo is set up with 2 sewage discharging pumps, one for delivery and
one for standby. Submerged chain conveyor overflow water flows to the boiler room overflow water pool and
delivered to high-efficiency concentrator and buffer tank through overflow water pump. Every unit is set up
with high-efficiency concentrator and buffer tank. Two high-efficiency concentrators and buffer tanks are
installed in ash silo area together. Every concentrator and buffer tank is set up with 2 sets of stuff discharging
pump at the bottom, one for delivery and one for standby.
7.2 Main equipment specification
7.2.1 Equipment performance
Item Unit Value
Normal output of submerged chain conveyor t/h 21
Maximum output of submerged chain
t/h 84
conveyor
Scraper speed (normal speed) m/min 1
Scraper speed (maximum speed) m/min 3
Chain speed m/min 1-3
Noise at 1m away from equipment when
dB(A) 85
equipment is operating
Suspended solid content of concentrator
ppm
overflow
Suspended solid content of buffer tank
ppm <100
overflow
of plugged hole drill or reamer broaching, but the expanding rate shall not exceed the 5% of the track
diameter. After fastening. Bolt shall show 2~3 button of the nut.
2 Main driving wheel assembly overhaul
1) Gear inspection
The large and small driving gear shall be complete and the tooth shall be smooth without burr.
Replace the tooth if the abrasion reaches the 1/4 of the original thickness. The tooth contact side shall be over
90%. The jointing force of gear and shaft shall be 0.03 mm~0.04mm. The clearance between the tooth top
and bottom shall be 0.40mm. The tooth meshing clearance is 0.15 mm~0.30mm. During disassembly, use
special tool to jacking of pinching-out on the special frame, to avoid damage the shaft and its journal.
The jointing force of wheel roll and shaft is 0.03 mm~0.04mm, and the locating pin hole on hub
shall be free of deviation (decentration) which may make the locating pin cannot plug in or out. The
allowable skewed error of the keyway axis and shaft hole axis on hub is 0.03mm.
The connection of big gear ring and hub adopts clearance connection and the connecting clearance
is 0.5mm.
The connection jointing side of big gear ring and hub shall be clean and polished; the connecting
clearance is 0.5mm.
For the large and small gear rings, the axial moving is ≤1mm, and radial moving is≤0.5mm.
For the large and small gear rings, there shall be no phenomenon, such as broken tooth, tooth
surface fatigue pitting, tooth surface wear and the plastic deformation of gear tooth.
When to plug the lug boss of baffle fully into large gear ring, the jointing side of lug boss with large
gear ring, and lug boss with hub shall ensure that it could contact evenly when turns to any angle relatively.
2) Bearing body overhaul
The bearing cover on bearing base and the glove of the bearing seat shall be cleaned up and the
through shall be free of mechanical damage, burr and the trench. There shall be no crack on bearing cover
and base, and the groove connects with lug boss.
The radial connecting of the outer bearing ring and cover is a radial clearance of 0.1mm~0.15mm.
The clearance between bearing and bearing housing end cover is 0.0mm~0.05mm.
Bearing housing oil path should be smooth, and the injected calcium base fat quantity should better
be 10~15 cups.
The felt ring in transparent cover shall not be broken and damaged. The felt ring head joint shall be
cut into inclined joint lapped by 30~45 degree. There shall be no oil immersion phenomenon on felt ring.
After each major overhaul, in principal, the felt ring shall be replaced. The felt ring dimension shall conform
to the requirements and the connection clearance of the inner felt ring circle and shaft diameter shall be
0.10mm.
3) Overhaul of shaft
Curvature of shaft shall not be more than 0.10mm. There shall be no crack and groove mark, and
shaft shoulder, journal and key slot shall be smooth and clean, and no burr. The ovality and conicity of
journal shall be less than 0.06mm and degree of finish shall be ▽5.
Tightening force of bearing and shaft shall be 0.02mm~0.04mm.
There shall not be ring rib layer deeper than 0.5mm and crack on the surface of shaft sleeve, and
tightening force of shaft sleeve shall be 0.03mm~0.05mm, with no defect of wear and partial grinding at
both ends of shaft sleeve.
Cylindricity of roller shall be 0.2mm, with no longitudinal or lateral layer after wear deep as
0.5mm~1mm on the surface, and there shall not be defects such as porous sand hole and crack around crater
on both sides of roller, otherwise repair welding and polishing shall be needed.
4) Overhaul of chain wheel
Suitable tightening force of hub and shaft shall be 0.03mm~0.04mm, the permissible deviation of
deflection between axis of key slot and shaft hole on the hub shall be 0.03mm.
Chain wheel and hub cooperate through clearance, with the fit clearance of 0.5mm.
Fitting interface between chain wheel and hub and screw hole on big gear ring shall be cleaned up
and grazed; with the fit clearance of 0.5mm.
Axial moving between chain wheel and hub shall not be more than 1mm, while radial moving shall
not be more than 0.5mm.
Gear teeth symmetry shall be synchronized when assembling two pairs of chain wheels. Both sides
of clearance between vertical slot and standing chain ring shall be 3 mm~5mm respectively, while length of
flute between two contiguous vertical slots shall be about 10 mm~20mm longer than horizontal chain ring.
3 Overhaul of flight chain assembly
1) Overhaul of flight
There shall be no crack at the joint between the flight and connector assembly on both ends of it.
Both sides of connector assembly shall be parallel and thickness uniform and no bend. Connector assembly
shall be over four fifths thickness of original. The bolt with 2~3 buttons exposed after being locked shall be
sealed or soldered by opening pin.
Non-parallelism of side on both sides of flight shall not be more than 0.4mm; Wear of side to
shovel slag shall not be more than 15mm; Centre distance of axis pin on both sides shall not be over 0.5mm.
Two contiguous flights shall parallel to each other, each one shall be vertical to chains on both sides,
angle between bevel and horizontal plane shall not be bigger than 15 degree, and opening direction of slot
scraping shall coincide to moving direction.
2) Overhaul of chain
Size deviation of unilateral chain’s overall length shall not be over 8mm; deviation per meter of
corresponding chain shall not be over 1mm. When replacing chains, both sides shall be replaced in the
meantime and corresponding chains shall be the same in length.
Wear of chain ring and connector shall not be over 1/3 of ring diameter. There shall not be crack
around weld area of chain ring.
Straight pin in connector shall be unbroken, with no straight pin lost. Serration shall be unbroken,
with no damage and rust phenomenon.
Deviation of two chains’ centre distance shall not be bigger than 0.5mm. Keep good mesh between
chain and chain wheel, with tension side of both sides of chain aboard and loose side infra.
4 Overhaul of guide pulley up and down
There are two top pulleys in extrorsely structure; there are bottom pulleys, bottom pulley of head are
installed symmetrically at both sides, bottom pulley of tail is concave tooth structure, supported by thru-shaft.
1) Overhaul of guide pulley up and down
Curvature of shaft shall not be more than 0.10mm. There shall be no crack and groove mark, and
shaft shoulder, journal and key slot shall be smooth and clean, and no burr. The ovality and conicity of
journal shall be less than 0.06mm and degree of finish shall be ▽5.
There shall be smooth and no burr in vertical slot of guide pulley, and clearance of both sides
between vertical slot and vertical chain ring shall be 3mm~5mm respectively.
Felt ring in transparent cover shall not be broken and damaged, joint of felt ring attachment shall be
cut to inclined joint of 30~45 degree, and no extraction phenomenon on felt ring. Felt ring shall be replaced
in principle after every heavy repair. Size of felt ring shall meet the requirement, and fitting clearance
between circle and shaft diameter in felt ring shall be 0.1mm.
Boss for transparent cover and blank cap on both sides of guide pulleys shall insert into guide
pulley entirely and be uniformly combined with outer ring of bear, outer side of transparent cover and blank
cap and interface between chain wheel and hub shall guarantee uniform contact. Oil-way of guide pulley
shall be smooth.
There shall not be crack and gas hole during grand of guide pulley and body welding.
Structure of carrier roller is basically the same with guide pulley, so overhaul is the same as above.
Carrier rollers on the body distribute every one meter generally.
5 Overhaul of tension roller’s assembly
1) Overhaul of chain pulley
Gear teeth symmetry shall be synchronized when assembling two pairs of chain wheels, and it shall
be smooth and no burr in vertical slot, and both sides of clearance between vertical slot and standing chain
ring shall be 3 mm~5mm respectively, while length of flute between two contiguous vertical slots shall be
shaft shoulder, journal and key slot shall be smooth and clean, and no burr. The ovality and conicity of
journal shall be less than 0.06mm and degree of finish shall be ▽5.
6) Overhaul of chain wheel
Gear teeth symmetry shall be synchronized when assembling two pairs of chain wheels, and it shall
be smooth and no burr in vertical slot, and both sides of clearance between vertical slot and standing chain
ring shall be 3 mm~5mm respectively, while length of flute between two contiguous vertical slots shall be
about 10 mm~20mm longer than horizontal chain ring.
Felt ring in transparent cover shall not be broken and damaged, joint of felt ring attachment shall be
cut to inclined joint of 30~45 degree, and no extraction phenomenon on felt ring. Felt ring shall be replaced
in principle after every heavy repair. Size of felt ring shall meet the requirement, and fitting clearance
between circle and shaft diameter in felt ring shall be 0.1mm.
There shall not be ring rib layer deeper than 0.5mm and crack on the surface of shaft sleeve, and
tightening force of shaft sleeve shall be 0.03mm~0.05mm, with no defect of abrasion and partial grinding at
both ends of shaft sleeve that will cause axial distance of bear to be greater than allowable value. End face
with boss of shaft sleeve and interface between inner ring of bear shall guarantee uniform contact.
Boss of transparent cover on both sides of chain wheel shall insert into chain wheel entirely and be
uniformly combined with outer ring of bear, outer side of transparent cover and interface between chain
wheel and hub shall guarantee: the degree for uniform contact with any relatively view.
Assembly interface between transparent cover’s outer side and hub and screw hole on chain wheel
shall be cleaned up and grazed. There shall not be groove mark on surface of the circle in chain wheel.
Suitable clearance between transparent cover on both sides and shaft shall be 0.5mm~1mm.
Retaining ring shall cling to inner ring of bear, and height of snap ring is 1/2 to 2/3 the thickness of
bear’s inner ring generally.
Tension roller shall adjust chains to no over-lap.
7.3.2.3 Pilot run of submerged chain conveyor
1 Contact with operation to return switching sequences after finishing work, and contact with power
supply after inspection.
2 Dynamo shall supply power to test rotation direction after assembling submerged chain conveyor.
After confirming rotation direction and when rotation direction of no-load running dynamo matches, cut off
the power to connect the coupling bolt or install drive belt.
3 Test run each bear and rotation part, and rotation shall be flexible and no clamping stagnation.
4 Working temperature of bear shall be stable, rolling bear shall be lower than 80 degree and rolling
sounds normal.
5 Vibration shall be less than 0.05mm generally; With no chain skipping.
6 End working sheet and hand over operation after test run.
7.4 Daily maintenance and troubleshooting
7.4.1 Submerged conveyor fault cause and troubleshooting
No. Fault Cause Troubleshooting
1 Uneven tension force on both
1 Adjust the tensioning device
sides
1 Off the chain 2 Align the driving shaft again
2 Driving shaft skew
3 Replace the chain
3 Chain abrasion
1 Scraper broken 1 Shutdown inspection and troubleshooting
2 Chain scission
2 Scraper deformation 2 Replace the deformed scraper
1 Restart after inspection and troubleshooting
1 Over-current protection action
3 Main shaft stalling 2 Replace insurance pin after inspection and
2 Insurance pin broken
troubleshooting
1 Driving, tension, and guide
1 Readjust
wheel are not in a vertical plane
2 Readjust tensioning
4 Chain running deviation 2 Uneven tension force
3 Find the corresponding section and
3 The chain length deviation is
exchange the left and right
too big
1 Dirty oil filter net
1 If the fault above occurs, never start the
Hydraulic driving device fault 2 Low fuel tank oil level
5 hydraulic driving device
alarm 3 High oil temperature
2 Shutdown for processing
4 Low pressure of oil pump
1 Submerged conveyor water
temperature exceeds the limit 1 Check the hydrating situation, judge it is
value water inlet valve fault or temperature switch
2 Submerged conveyor speed fault
switch fault. The submerged 2 Determine whether broken chain occurs or
Submerged conveyor fault
6 conveyor starts, but speed disk not
alarm
does not move 3 Jog backward move, restart if checked to be
3 High load or chain block in normal
submerged conveyor 4 If the situation is normal, shutdown for
4 Tension device high-high level processing immediately
alarm
8. Appendix:
Processing method:
Put in the small cover in both sides, heat the bearing to 100℃ (not exceed 110℃) with bearing heater
and put it onto shaft.
Push the bearing in position quickly.
Clean up new bearing and wipe it up with white sand strip.
Add lubricating oil unto bearing housing.
8.2.3.4 Motor assembly
1 Inspection before assembly.
Quality standard:
Clean up the motor rotor and stator, after finish inspection, each part works normally and the device
shows true color.
Bearing testing and assembly conform to the standard.
Motor stator insulation and winding DC resistance measurement conform to the requirements of the
standard, (fill in Table 2).
Table 3~6
Technical requirements:
The coupling wheel disassembling must use heating method, and heating temperature shall not to exceed
250℃.
Bearing installation uses the hot pack method and its temperature shall not exceed 110℃, during heating,
adopt oil or electric heating, but forbid direct heating of flame.
After the motor assembly, fasten the screw tightly, and manual jigger is flexible.
2 Motor assembly
Get through the rotor, pay attention to the rotor air gap, don't touch the wound coil and iron core.
Assemble the end cover of both side of motor and the small cover of bearing housing.
Install recidivating load side fan and fan cover.
Reassemble the coupling wheel.
3 The motor is in place and connect the external connection wire.
Lift motor to be in position.
Check that motor outgoing line is firm, wiring according to the signs, and fasten the screw.
Connect the case grounding line.
8.2.3.5 Motor trail operation
1 Contact the operation to measure the motor insulation resistance and power on.
2 Free load operation and make records.
8.2.3.6 Finishing work