Row : Capital
Region : North America
Change History
Update the following table as necessary when this document is changed:
Trigger
Perform this procedure when you wish to unlock WBS Element planning.
Prerequisites
WBS Element has a Planning Element indicator and a user status of PMRL.
WBS Element planning is locked and has a System Status of PLLK..
Menu Path
Use the following menu path(s) to begin this transaction:
Select Logistics Project System Project Special Maintenance Functions
Work Breakdown Structure (WBS) CJ02 - Change to go to the Change Project:
Initial Screen.
Transaction Code
CJ02
Helpful Hints
None
Procedure
1. Start the transaction using the menu path or transaction code CJ02.
2. Click
3. Click
4. Click
5. Click
6. Click
7. Double-click
Change Project: Initial Screen
Project def. R Enter Project definition number or Press F4 to select from the
list.
Example: A.08888
10. Click scroll to the right to check the status of the WBS element(s) you wish to unlock. The
WBS should have a Planning Element indicator and have a user status of PMRL with the
system status of REL PLLK.
11. Click to the left of the WBS Element(s) that you would like to unlock planning for.
Change Project: WBS Element Overview
14. Click until you reach the SAP Easy Access screen.
SAP Easy Access
Result
You have unlocked planning for a WBS Element.
Comments
None