Performance of Contract
Performance of Contract
Performance of Contract
Introspection on professional
performance of contracts
R. Ramakrishnan
The performance by client, contractor and consultant/ aim for an amicable settlement. Disputes could be
engineer in construction projects need introspection settled through negotiation or arbitration innovatively.
for ensuring better professionalism with the aim of Arbitration process should be facilitated timely and the
completion of the project in time, with economy and awards accepted, not challenged. Awards challenged
quality. With respect to quantum and time, quality in the court may take a very long time for justice.
consciousness is vaning. The vision and mission should 'Where there is a will, there is a way' is an apt quote
be, to have fair conditions of a contract, reasonable for projects.
rates, each adhering to the reciprocal responsibilities
and perform professionally. The client, contractor Scope
and engineer should work in mutual cooperation,
There is a surge of activities in construction Industry
coordination and trust as a team.
now. The construction industry is next only to the
In private enterprises, where the private entrepreneur agriculture industry in terms of employment is also
apart from taking all risks has to finance, design, unorganised with many players and employs manpower
construct and maintain, the mind set has to be more of more than 30 million.
facilitative and innovative so that every effort could
be made to resolve the bottlenecks and complete the The scope of the project should be critically examined
project early for yielding the fruits to both employer and from all angles. Depending on the type of project
entrepreneur/contractor. Coordination and cooperation and complexity, consultants could be engaged for
of different government departments may be involved investigations, drafting designs, specifications and
in this process. Leadership skills along with the art engineering. Then prepare the estimates realistically
of managing conflicts accommodatively and ethical keeping in view the escalation for the period and decide
approach should be used in achieving the goal. on the method of funding. Necessary approval from
the environment department and relevant authorities
In case of differences of opinion, every effort should should be obtained in time so that the same does not
be made to appreciate the other person's view and become a deterrent in starting the work.
Tendering 1969 have not borne any fruits. The tender conditions
are normally one-sided leaning towards the employer
Type of contract
and not fair. In internationally aided projects, the
Depending upon the nature of work, the type of contract aiding agency insists on adoption of FIDIC (Federation
should be decided. Each has it own advantages and Internationale des Ingenieurs-Conseils / International
disadvantages and has to be dovetailed with the nature Federation of Consulting Engineers) conditions, which
of work and complexity. are relatively balanced. Of late, there is a tendency
in some organisations to adopt conditions similar to
Item rate contract might be simpler to prepare FIDIC.
with key drawings, but in operation it may be
cumbersome as the payment is related to the In fact CIDC (Construction Industry Development
quantum of work done, involving a large number Council), the apex trade body for the construction
volumes of measurements in big projects. industry and sponsored by the Planning Commission,
has brought out new model tender conditions for
Lump sum contract can be resorted to when adoption. It is hoped that at least in the future, we
detailed drawings and specifications can be shall have uniform tender conditions that is fair to both
prepared with payment stages, as well as parties.
variations. Variations during site execution should
cause no surprise and should be expected. Interest for delay in payments
It is high time that the tender conditions contain shorter
Cost plus contract is entered into when the
period for payment of bills after submission by the
scope is undecided and is open ended such as in
contractor or else interest liability should be included.
research projects. Clear understanding regarding
After all the contractor is in a commercial transaction
scope and time is essential.
with profit motive and without periodical payment of
dues, the progress of work suffers causing delay and
Turnkey contract can be resorted for complex
escalation. FIDIC provides for this, but everybody is
projects where different special items/services are
afraid to include the clause, as it is an avoidable cost and
taken up by the main contractor either by himself
the onus of taking responsibility comes in.
or as a joint venture for design, drawing, execution,
testing etc. The investigation responsibilities and
variations has to be made foolproof so that the Time period
scope of disputes is minimised. This is easily said Adequate time period should be provided for execution,
than done and hence the need for minuteness keeping in view the monsoons, site availability for doing
in investigation, detailing, design and scope the work, utility shifting by other departments/agents,
requirements. etc. This should be further related the to the requisite
equipment/labour and methodology of work. In a
B.O.T. privatisation type of contract is used civil engineering contract time is of the essence of the
when the funds are limited or not available contract, but has no meaning, with so many bottlenecks
but the development is essential. In this case, and breaches affecting the time schedule. The penalty for
major responsibilities of designing, financing, delay should be reasonable and not abnormal.
construction and maintenance is shifted to
the entrepreneur, with suitable provision for Bonus
recouping the cost of financing and making profit
Every contract contains a clause for levy of penalty
in the form of toll or other income.
for delay. Similar clause is hardly found for payment
of bonus or incentive for early completion. This will
Balanced tender conditions infuse some motivation to complete early and moreover
The Contract Act is more than 100 years old and the asset is available early for use with less escalation.
has not been updated. Even after nearly 60 years of Though traditionally Indian contracts are not completed
independence, there are no uniform tender conditions in time, introduction of bonus clause for flyovers in
even amongst state or central government, leave alone Mumbai, N.H.A.I. road development works, etc. have
public sector and private firms. The efforts of the resulted in early completion of the projects. FIDIC
Planning Commission to bring out a modal contract in contract has provisions for bonus clause.
of completing the project. The parties in a contract mobilisation of material, men and equipment. Periodical
therefore are not competitors in any way, but rather progress reports should be submitted by the contractor/
joint partners contributing their separate talents and consultant. Periodical reviews be it weekly/monthly/
efforts to produce the outcome agreed in the contract. In quarterly should be proactively made at different levels,
spite of this accepted premise, conflicts do arise. Many to assess the progress achieved with respect to the
of them can be traced to personal differences, desire planned schedule. This would help in taking remedial
for credit or one-upmanship regardless of what might action in case of lag. Pragmatic approach with empathy
be good judgment and acceptable conduct. The most would help to motivate all parties and lead to progress
effective and simplistic approach is the observance of even with odds. Methods that would enable to make up
good business ethics by all the parties concerned. the loss of time should be ascertained and resorted to
compensate/avert the delays anticipated/accrued.
The elements of satisfactory contractual relations are
dependent basically upon the following characteristics Cooperative discussion rather than authoritative
and qualities that should apply to the parties of the direction would ensure better results and relations. If
contract. there are some costs involved in accelerating the work,
the decision to incur the cost or accept the delay should
Good reputation be deliberated and decided. Quality should not be
sacrificed for the sake of quantity and time. Quality and
Financial capability
time consciousness should be inculcated especially with
Proven competence respect to men, machinery and material.
Whenever changes, variations or hindrances are Conduct progress review meetings periodically
involved, bring out the facts promptly and furnish to identify bottlenecks and suggest alternative
details of cost and new rates. measures so as to adhere to the schedule.
Provide details as required by the engineer to Examine in detail the extension requirement
determine the extension of time as well as the caused due to the fault of the client/engineer/
cost. contractor and approve the same.
Appreciate and cooperate with the engineer and Avoid and reduce variations/changes in design
client to ensure that the dispute/claims are sorted during execution as the same causes work
out amicably in spirit of give and take. disruption and delay.
In case the disputes are referred to arbitration, Clarify ambiguities in drawings/specifications/
cooperate with the client and arbitrator in arbitral BOQ (bill of quantities).
proceedings/conciliation proceedings to settle the
issue amicably. Assess correctly the claims/variations and certify
the same in coordination with the contractor and
Do not make false or hefty claims.
employer.
Cooperate with the consultant to enable decision
on claims. When a decision under dispute resolution clause
is sought, the decision should be given promptly
Do not challenge the arbitral award, if it was not as a quasi arbitrator after detailed examination of
favorable. Awards challenged in the court take the full facts, in accordance with the contract and
lot of time, even decades, for justice. circumstances of the case. He may also coordinate
discussions between the parties for a quick
Mutual cooperation rather than confrontation, decision but he should not get influenced by the
flexibility rather than rigidity, trust and faith, client or contractor while giving his decision.
should be the golden ethos, for ethical and
professional performance. Cooperate, coordinate and act in a fair manner
to gain the confidence of both client and the
It should also be noted that goodwill earned will contractor.
lead to a lasting bond and mutual appreciation.
In other words, the consultant/engineer functions as a
catalyst and facilitator in the whole exercise of contract
Role of engineer management. He is a bridge between the client and
The engineer could be an employee/consultant of contractor, enabling proper and adequate performance.
the client or a separate consultant employed for the Hence, he plays a very crucial role in the success or failure
purpose. The engineer should perform duties diligently of a contract/project. Unprofessional behaviour can put
with technical soundness and contractual fairness in the project in jeopardy causing financial burden either
coordination with the client and contractor such that the to the client or contractor unnecessarily. Introduction
progress of work is facilitated. He should of a new consultant in the middle of the project phase
does create problems. Hence, there is a need to select
Give drawings/designs for execution in advance at the outset consultant who is properly qualified and
for planning the procurement of materials and experienced for the work. These are a few pointers for
men for project execution. the client and consultant to appreciate and abide.
quantum of work and the high speed of execution, thus ensure success of the scheme. In such projects, the
quality requirements, have been overlooked. There may art of managing loss or profit gains more importance
be records to prove that everything is done perfectly as the entrepreneur has taken up the work with profit
well. But, the reality is different. It is hence essential motive. Central government and planning commission
that professional commitment in maintaining requisite are trying to address these critical issues in their model
quality should be in adhered to by the contractor, concession agreements. But, amicable solutions are still
consultant and client. not easy to achieve.