Field Inspection Testing Electrical Equipment
Field Inspection Testing Electrical Equipment
Field Inspection Testing Electrical Equipment
Procedure
Document
Table of Contents
1.0 PURPOSE
This specification covers the procedures for field inspection and pre-commissioning of
electrical equipment and installations for Betara Complex Development Project.
The requirements contained in the latest editions of the following publications shall form a part
of this specification in the manner and to the extent specified herein.
- Indonesian Law
- Statutory Regulation
- American National Standard Institute (ANSI)
- American Petroleum Institute (API)
- International Electro Technical Commission (IEC)
- National Electrical Manufacturers Association (NEMA)
- National Electrical Code (NEC) NFPA 70
- PCIs Specification:
- BCD03-01-00-46-CRT-001-1 (Electrical Design Criteria)
- BCD03-01-00-46-SPC-013-1 (Specification Electrical Installation)
(1) Any underground circuit is energized until tests show otherwise or until it is
grounded.
(2) Wiring is incorrect.
(3) Motors are connected to run in reverse.
(4) Phases are different across a bus-tie breaker.
(5) Everything needs checking.
3. Unauthorized personnel must be kept away from test work. Rope off the area if
necessary. Provide warning signs. Plan ahead and think before acting. One good
way to avoid trouble is to write down the sequence before proceeding with a complex
or hazardous inspection or test.
1. Transformers
a. Remember that certain test equipment such as megger and dielectric test sets can
cause painful, if not lethal, shocks. Be careful when working with transformers; low
voltages applied to the secondary windings can produce lethal voltages at the
primary terminals.
a. When working on any one circuit, be sure to positively identify the specific source
breaker(s) and then lock it open and tag it. In the case of draw-out type gear,
remove the breaker from its operating position. Make sure that personnel working
on the equipment are familiar with the test procedures. Make sure they observe
that the breaker is locked open.
3. Cables
a. Establish that the circuit is dead by testing it with a high voltage detector (glow-
stick), or in the case of low voltage use a voltage tester.
b. Make sure that the glow-stick, voltmeter, or voltage tester is in working order, by
checking it against a live cable or test device both before and after the circuit check.
c. In addition to these tests, the source circuit breaker should be opened and tagged.
Only after these precautions have been taken, the testing and checking of circuits
can be started.
d. When a long cable is impressed with voltage and a megger is used during tests, the
cable can still give a painful kick after the source is removed. Before allowing
personnel to work on the cable, the cable must be discharged by connecting an
insulated wire to earth.
4. Motors
a. Before any work is done on a motor, ensure that the motor controller has been
disconnected and tagged out. If possible, the motor feeder should be connected to
earth.
4.1 Purpose
The inspection and tests described in this procedure shall be carried out at the
appropriate time both during and after the installation or erection of the electrical facilities.
At the beginning of the electrical inspection and tests, the check sheets (Appendix l) shall
be filled in by the inspection engineer.
4.2 Transformer
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet, appendix-1. Check & inspection
result, general information of transformers shall be filled in this check sheet.
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet, appendix-1. Check & inspection
result, general information of switchgear and MCC shall be filled in this check sheet.
1. 13.8kV and 4.16kV Switchgear and MCC
7. MCCB, Contactor, Fuses, Etc. correctly sized and identified as per Single Line
Diagram.
8. Padlocking facilities correct.
9. Ammeter and current transformer correctly installed.
10. Check internal for cleanliness.
11. Check manual operation of selector switch, MCB, push button, etc.
12. Incoming cables correctly installed, terminated and supported.
13. Unused cable entry sealed.
14. All internal cabling and wiring neat, correct and undamaged.
15. Heater correctly installed.
16. The relays and measuring instruments are checked and tested. The rating and
range are checked in accordance with setting data if the ratings of current and
potential transformers are adequate. All blocking materials are removed. Adjust
the relays and devices to the correct duty point per setting data
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet, appendix-1. Check & inspection
result, general information of electric motor shall be filled in this check sheet.
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet, appendix-1. Check & inspection
result, general information of cables shall be filled in this check sheet.
1. The cable trench is clean and free from any foreign objects.
2. The size and installation are in accordance with the approved drawings.
3. The cable tray is correctly and rigidly installed.
4. The circuit indication and terminal numbering are correct and firm.
5. The cable end bells, oil or compound levels are satisfactory and there is no leakage.
6. The cable end seals are complete and tight.
7. The cable glands are complete and tight.
8. The cable is protected against mechanical damage.
9. The underground cable joints are complete and meet the specifications.
10. The grounding connections are completed.
11. The cable terminations and connections are correct and tight.
12. The cable route markers are correct.
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet, appendix-1. Check & inspection
result, general information of grounding system shall be filled in this check sheet.
1. The grounding joints are complete and tight. The underground joints should be spot-
checked before they are backfill.
2. The size of the cables and installation comply with the approved drawings.
3. The installation of the electrodes is satisfactory.
4. Check the protective measures that have been taken against mechanical damage to
the system.
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet, appendix-1. Check & inspection
result, general information of lighting system shall be filled in this check sheet.
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet (Hold), appendix-1. Check &
inspection result, general information of electrical monitoring system shall be filled in this
check sheet.
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet, appendix-1. Check & inspection
result, general information of UPS / Battery Charger and Batteries shall be filled in this
check sheet.
The following general items shall be checked, inspected, and tested. Detail requirements
for inspection and testing should refer to the check sheet, appendix-1. Check & inspection
result, general information of Distribution Panel shall be filled in this check sheet.
4.12Telecommunication Systems
The inspection and testing for the communication systems shall be carried out in
accordance with the manufacturers recommended procedures and manuals.
The installation of cathodic protection system shall be checked and tested in accordance
with the manufacturers recommended procedures and manuals.
4.15Miscellaneous
For the miscellaneous electrical equipment or installation that not specified on the above,
the detail inspection and testing should refer to the check sheet on appendix-1.
Figure - 1
MEASURING RESISTANCE BETWEEN CONDUCTOR AND EARTH
3. Voltage shall be applied until the pointer remains steady. Insulation resistance of
HV motor shall be measured after 15 sec., 30 sec., 1 min., 10 min. to calculated the
polarization index.
Figure - 2
MEASURING RESISTANCE BETWEEN CONDUCTORS
5.2 High Voltage Test (This test shall be carried out by Vendor recommendation).
Figure - 3
HIGH VOLTAGE TEST
Figure - 4
MEASURING GROUNDING RESISTANCE
Before backfilling the grounding wiring, make a visual check of the underground
connections. Measure the electrical continuity by use of a circuit tester, according to the
following sequence:
1. Apply the circuit tester to all of the grounding electrodes, as shown in Figure 5 (1st
step).
2. Apply the circuit tester between grounding electrode and the nearest connected
equipment, as shown in Figure 5 (2nd step).
3. Apply the circuit tester between adjacent connected equipment, as shown in Figure 5
(3rd step).
4. Using the same procedure, check the resistance between all connected equipment and
grounding electrodes.
5. Complete an grounding continuity test data sheet for every test.
Figure - 5
CHECKING GROUNDING CONTINUITY
Figure - 6
CHECKING ELECTRICAL CONTINUITY
1. The test shall be applied to all bus bars bolted connection that are assembled at site
and complete bus bar.
2. Resistance of the connected parts shall be measured by low- resistance test set.
The test shall be applied for power transformers in accordance with the following
procedure:
1. Connect primary terminal "C" and secondary terminal "C", as shown in Figure 7.
2. Connect a temporary test power source to the primary side of the transformer and
switch it on.
Figure - 7
TESTING POLARITY OF POWER TRANSFORMER
This test shall be applied to electrical insulation oil in accordance with applicable standard.
Two samples shall be taken from the insulating oil. Each sample shall be tested
according to the following procedure:
Figure - 8
DIELECTRIC STRENGTH TEST
The testing vessel and electrodes shall be cleaned, dried, and then rinsed with a little
of the insulating oil that is to be tested.
Each current transformer shall be individually tested to verify that the primary and
secondary polarity markings are correct. A low voltage battery is used, via a single-
pole push-button switch to energize the primary winding.
When polarity are as shown below, on closing the push-button, the d.c. ammeter
should give a positive flick and on opening, a negative flick.
Figure - 9
TEST CIRCUIT
a. This check is usually carried out during the primary injection test. The circuit shall
be as shown in figure 10.
b. Current is passed through the primary conductors and is measured on the test set
ammeter (A1).
c. The secondary current is measured on the ammeter (A2) and the ratio of the
reading on A1 to that on A2 should approximate to the ratio marked on the
switchgear to be applied with Primary Injection Test.
d. Connect injection leads on the primary circuit of CT using primary junction device.
e. Check the secondary terminals by a temporary wire.
f. Confirm other CT secondary loop is complete, if not, short the CT secondary
terminals by a temporary wire.
g. Inject the current as same value of CT primary (as possible) and confirm the CT
ratio measuring the CTs secondary current.
h. Record the test results and complete the test report.
Figure 10
MEASURE CT RATIO (PRIMARY INJECTION)
a. The voltage transformer polarity can be checked with the test described for the
current transformers.
b. Care must be taken to connect the battery supply to the primary winding, with the
polarity ammeter connected to the secondary winding.
With the switchgear control power energized, each circuit breaker position shall be
checked, and then checked again in the operating position, according to the following
procedure:
1. Close the circuit breaker and trip it from the control switch and remote control panel.
2. Mechanically trip each electrically operated circuit breaker.
3. Test the lockout device in the closing circuit for proper operation by simulating
conditions in which a lockout would occur.
4. Complete a sequence test data sheet for every test.
1. Using a relay tester with a third harmonic filter, set the relay in accordance with
the Relay Setting List.
2. Connect one relay unit to the relay tester.
3. The minimum pickup current input to the relay and the calibration of the relay
shall be tested as follows:
a. Rotate the armature disk by hand to the midpoint of its full travel. Mark a
red target line between the disk and a stationary part.
b. Increase the input current to the set tap value and monitor the armature
disk to determine when it starts to rotate.
c. If the disk does not start rotating at the set tap current, increase the current
slightly.
d. Check that when the disk stops, the red lines coincide. If not, adjust the
tension in the spring accordingly.
4. Operational Test.
a. Set the input current at 300% of the set tap value.
b. Set the cycle counter and input the 300% current through the relay coil.
Measure the duration of operation.
c. Repeat the procedure with a 600% tap current.
5. Complete the Relay Setting List for every item of test data.
1. The procedure for this test shall be the same as that for the insulation resistance test.
2. For motors and generators rated below 1,100 kW, take readings at 30 and 60 second
intervals to determine the dielectric absorption ratio.
3. For motors and generators of l,l00kW and larger, take readings at one minute and 10
minute intervals to determine the polarization index.
5. Depending on the type of test, complete a dielectric absorption ratio data sheet or a
polarization index data sheet, for every test.
After satisfactory insulation resistance values have been obtained, the lighting circuit shall
be tested according to the following procedure:
1. Turn off all the branch circuit switches in the lighting panel.
2. Energize the distribution circuit up to the lighting panel.
3. Check the voltage between all phases, and between each phase and the neutral
conductor, at the buses to the lighting panel.
4. Turn on one branch circuit switch and check that the illuminated lighting is in
accordance with the lighting drawing.
5. Check all the branch circuits one by one, using the same procedure.
6. Complete a lighting circuit test data sheet and an illumination level data sheet for every
test.
1. Before energizing the electrical panel by permanent power, phase rotation and polarity
shall be checked by using the temporary low voltage power.
2. Complete a phase rotation and polarity test data sheet for every test.
All tests and inspections of the motor, such as visual inspections, insulation resistance
measurements, and sequence checks, shall be completed before making a motor no-
load run test. Other checks to be performed are as follows:
1. Check that the motor can be easily turned over by hand.
2. Ensure that the coupling is correctly aligned and the motor is fixed to its foundation.
3. Using the starter, rotate each motor to check that it rotates in the direction indicated
by the rotation arrow. If not, reverse the connection leads at the starter, or at the
motor if necessary.
Run the motor uncoupled until the motor tempera-ture reaches the saturation point.
4. Check the vibration, noise, and bearing tempera-ture. Use a thermometer to check
and record the bearing temperature. Do not try and determine the temperature by
feeling the bearing housing. Defective bearings will be discovered by their being
noisy or by their overheating.
5. Complete a motor uncoupled run test data sheet for every test.
Note: Motors with special construction or fractional capacity shall be individually
discussed and decided before the test.
This section defines the acceptance criteria of site test, which shall be used for evaluation of
measured values. The acceptance value of each test item shall be referred to a list as follows:
No. Description of Test Test Equipment & Tolls Test Voltage & Min Acceptance
Duration Value
1 Grounding Resistance
Measurement
2 Power Transformer
No. Description of Test Test Equipment & Tolls Test Voltage & Min Acceptance
Duration Value
3.4 HV Test (Apply HV above 1 AC Dielectric Test Set 4.16KV x 1.5 (10
KV) mnt)
* 4.16KV Circuit Tester & Battery
4 Cables
No. Description of Test Test Equipment & Tolls Test Voltage & Min Acceptance
Duration Value
5 Electrical Motor
6 Lighting