SAP PS (Tutorialspoint)
SAP PS (Tutorialspoint)
SAP PS (Tutorialspoint)
Project System is one of the key modules of SAP to perform project and portfolio management.
It helps you to manage the project life cycle starting from structuring to planning, execution,
until the project completion. Project system is closely integrated with other SAP modules like
logistics, material management, Sales and Distribution, Plant Maintenance, and Production
planning module.
It enables organizations to manage all SAP projects- large and small-scale projects efficiently.
The Project Manager has a task to ensure that these projects are executed within budget and
time and to ensure that resources are allocated to the project as per the requirement.
Before a project is initiated, it is required that project goal is clearly defined and the activities be
structured.
The integration between SAP Project System PS with SAP ERP R/3 application modules allows
you to design, plan, and execute the projects as part of your normal project procedure. Hence,
Project System module has the constant data access to all the departments involved in the
project.
Classification of Projects
As per budget, projects can be categorized in the following categories
External Financed Projects This includes the projects which are sponsored by clients and are
executed to meet the client requirements. These projects are called customer projects and project goal
is aligned to meet the customer demand.
Internal Financed Projects This includes project related to capital investment or overhead cost
projects.
You can also categorize projects according to the list of activities and project structure or on the
basis of individual activities
Project Structure can be defined either manually or based on templates. You can also create the
Project structures using sales documents automatically.
In the following diagram, you can see the sample project structure that is created hierarchically
using Work Breakdown structure.
When a project request is received, a project is created and it has to undergo the following steps
in project process flow/lifecycle.
Create Templates/WBS
Create Project
Project Planning
Project Implementation
Project Completion
The integration between SAP Project System PS with SAP ERP R/3 application modules allows
you to design, plan, and execute the projects as part of your normal project procedure. Hence,
Project System module has the constant data access to all the departments involved in the
project.
Finance and Controlling Module To plan the costs and revenue in the project system as per the
financial planning requirements.
Sales and Distribution Module To manage the sales process in project lifecycle- includes
quotations for customer projects. This includes billing, selling, and shipping of goods and services
required in project lifecycle.
Production Planning To perform activities like material requirement planning MRP, Bills of
material BOM, material requisition as per MRP, capacity planning, and other production planning
tasks in project lifecycle.
Other R/3 modules Other modules like plant maintenance, budget management, investment, etc.
In the following diagram, you can see SAP Project System is integrated with SAP R/3 modules
during project lifecycle.
Organization Structure and Elements
When a project is initiated, it starts with the definition and classification of the project structure,
which is required to align it with the existing enterprise structure in an organization.
Project System has no organizational structures of its own and we have to incorporate the
structure to enterprise structure by assigning organization elements in different ERP R/3
modules. These organization elements allow Project system to maintain and get the data
correctly.
Company Code
In SAP FI, a company can comprise of multiple codes, however it acts as a single unit for which
financial statements are available. Company code is smallest unit in an organization for which
financial statements (profit-loss statement, etc.) can be generated.
To create, edit and delete a company code, follow the steps given below
Step 1 Expand Enterprise Structure Definition Financial Accounting Edit, Copy,
Delete, check company code.
Step 2 A new window will open. You can create new company code by selecting both the
options.
The option Copy, delete, and check company code allows you to copy all configuration and
tables automatically.
Step 3 If you select Edit company code, you will get the following window
Step 4 Click New Entries and update the code details.
Step 5 You can click the Address button and update the fields as shown below. Once Address
field is updated, click the Save button.
Creating a Business Area
Business Areas are used to differentiate transactions that comes from different line of business
in a company.
Example
There is a big company XYZ, which runs multiple business. Let us say it has three different
domains like manufacturing, marketing and sales.
Now you have two options
The other option is to create each of these business lines into business areas.
You can use these business areas if other the company codes require the same areas.
It is easy to configure if you use Business Area because you just need to attach to the company code
and the other details in business area will get attach itself.
By using Business areas in controlling, you can create profit and loss statements, balance sheets, etc.
for business areas. Therefore, this is used for management accounting in few companies.
Step 2 To create a Controlling area, click New Entries. Enter the following details
Name of Controlling Area
Company Code
Currency settings
Defining Plant
Plant is an organizational unit within a company where activities take place. A plant will
produce goods and makes goods available for the company.
The following steps will take you through the procedure of creating Plant
The following steps will take you through the procedure of creating Storage location
Click the save icon after filling required information. A new Storage Location will be created.
SAP PS - Currencies
In SAP PS system, you can manage all the currency dependent data in the Project System using
the following different currencies.
Object currency
In Project System, it is possible to assign any object currency to different objects in the system.
WBS element
Project definition
Network header
Network activity
Note When a company code is assigned to a controlling area and company code contains
multiple currencies, you cannot allocate object currency in PS. In such a case, system
automatically takes the local currency of company code.
Transaction currency
In this case, the costs and revenues from different business transactions are recorded as per
currency of the business transaction.
Example
You can take the currency of PO in which it is raised in the system. In PS system, each amount
is recorded in the database in all three currencies and you use the currency translation rates in
the PS implementation.
Note You can use Information system to view the reports in any currency including the above
mentioned currency types and Project System translates the values in report as per the latest
conversion values.
Projects have a defined goal, which is agreed between the company and customer and is defined in
Project Charter.
Projects are complex, unique, and definitive in scope and involves a high certain risk to execute and
complete on time.
Projects have definitive cost, duration and resources to work on the project.
Projects are defined as a part of the internal processes of a company. To execute the tasks in a
project, you have to get an organizational form that is specific to the project and which is shared
by all the departments involved.
You should define the project goal clearly to carry out project in its entirety and the activities to
be carried out must be structured.
In SAP Project system, you define the activities and people in the project in form of Work
breakdown structure WBS.
Project Planning also involves the sequence of tasks to be performed and which tasks are
dependent on each other and which tasks can be further divided in to smaller tasks. In SAP
Project system, sequence of tasks are defined in the form of Network in project planning.
Maintain PS Types
A Project type is used to group or classify the projects as required. For example, banking
projects capital projects or IT development projects.
A Project type is also used for reporting, building authorization and for creating hierarchies and
network in project planning. It can also be used for developing customer requirements, i.e., use
of BADI for WBS settlement rule determination based on project type as a parameter.
By defining PS type for PS texts in SAP system, this helps you to attach the text in project
builder and this text can be used in projects.
Step 1 Go to SPRO IMG Project System Documents Define PS types for PS texts
or use T-code: OPS3
Step 2 The PS Text Type screen appears. Click New Entries to define new text types as per
the business requirement.
Text Type Enter the text that defines PS text type in system.
Simulation version You can select checkbox to define changes in simulation version
Step 4 Once you enter the details, click the save button at the top.
Length of key for project coding and an indicator to specify if a project should have this length or it
can be shorter.
Automatic Number assignment This is used to update symbol that you want to assign
automatically to project object and WBS.
PL Project Length
SL Structure Length
Step 3 To save the configuration, click the save button at the top.
Step 1 You can use T-code: OK02 or go to SPRO IMG Project Systems Structure
Operative Structure Work breakdown structure WBS user status Create Status
profile.
Step 2 A new screen Change status profile overview will open. You can use other options to
copy an existing profile, to delete a profile or to view details.
Step 3 In the next window, enter status profile Id to identify the profile in SAP system.
Enter the text of profile, Maintenance Language: Enter language key like EN. Press ENTER to
continue.
Step 4 Once you press ENTER, status profile you have created will be shown in the list of
status profile. Double-click on status profile.
Step 6 After entering these details, click Object types at the top.
The Allowed Object types screen appears with various options.
Step 7 Once you enter all the details, click the save button at the top.
Step 2 To create new selection profile, click New Entries on Status Selection
Overview screen.
Step 3 In the next window, you have to enter 7-digit alphanumeric id that identifies the
selection profile and text description of selection profile. Enter the status profile Id that you
have created.
Step 4 You can also perform Search option to select the Status profile.
Status Update status from drop down, If status is user status, you can select X from the drop down.
Step 8 To exclude selected condition in the report, enter
Note that the values in the project profile is used to maintain the functions of certain areas of the
Project System and should only be changed without considering all the factors. You should not
change the keys related to costing sheet or the results analysis key as these can change existing
system.
You must maintain the following information under project profile section
Basic data
Time scheduling
Costs/revenues/finances
Organizational data
A standard R/3 System contains the predefined project profile that has the most important
control parameters.
Proj.prof. Enter the unique ID that identifies project profile in SAP system.
Field Key Select field key from the drop-down list. You can select different field keys for different
projects as shown below
In the new window, select the following
Display Options This determined how the project will be identified in project builder.
All account assessment element This has to be selected if all WBS has to be created using this
profile.
Project summarize master data Select this field to summarize the master data in project. This is
used to perform any reports.
Company Code Enter the company code that belongs to Control area
Business area Enter business area belongs to company code and controlling area
Plant Enter plant code belongs to company code
Click the save button at the top to save the project profile.
You can use the settlement profile to define the following for actual costs
Full Settlement
Can be settled
Not to be settled
As per the settings in the settlement profile, there is a need to settle the costs of an object in full
before that object is achieved in the system.
Step 2 In the next window, select maintain settlement profiles and click Choose.
Step 3 To create a new settlement profile, click New Entries in the Settlement profile
overview window.
Step 4 In the next window, you have to enter the following details
Settlement profile Enter unique ID that identifies the settlement profile in system and description.
Actual Cost/Cost of sales To find the settlement value
Default values Enter allocation structure and default object type field
Enter Receivers
Other parameters Document type, maximum number of dist rls, residence time
Step 5 Once you enter all the fields, click the save button at the top.
SAP PS - Network Profile
You can create network profile in SAP PS to maintain Network and WBS structure and to
define rules for linking networks.
Step 1 Use T-Code: OPUU or go to SAP Easy access, SPRO IMG Project System
Structures Operative structure Network Setting for Network
Network Type Enter the network type from drop down list
MRP Control group Enter the MRP control group associated with planner group
Relationship view Enter the relationship view used for defining rules for linking network
Check WBS account Enter WBS account system determines the WBS.
Reservation Purchase requisition Enter Reservation purchase requisition
Capacity Requirement Select this to calculate capacity requirement once network is saved.
Step 3 Next, go to the Graphic tab to select the details for network graphics like color, display
option, etc.
Step 4 Similarly, go to the Activity tab and enter the details.
In SAP PS system, a network type is used to contain the information for controlling and
managing networks. Network is defined as work order that has a structure in common with
production, maintenance, and inspection orders.
In SAP system, when you define a network, it should also contain a network type maintained
with it.
Order category
CO Partner update
Order Type Enter unique id that identifies the order type in SAP system
o Residence Time 1
o Residence Time 2
Step 2 In the next window for Person Responsible for Work center, click New Entries.
Step 3 In the next screen, you have to enter the following details
Plnt Enter the plant key that you want to assign person for work center.
Pers. Respons In this field, enter the person responsible for work center ID
Person responsible for work center Descriptive name of person responsible for managing work
center.
Step 4 Once you enter all the details, click the save button at the top.
Using Control key in SAP PS system, you can determine the business transactions to be
performed when you perform an activity. An activity can be an internal activity, external
activity or both.
While defining the control key, you have to specify the indicators and keys for different
functions in the control key. You can use SAP standard control keys PS01, PS02 and PS05 for
networks.
Step 1 Use T-code: OPSU or navigate to SPRO IMG Project System Structures
Operative structure Network Setting for network activities Define Control Key.
Step 2 In the next screen, click Activity Control screen New Entries.
Scheduling You can select this option to perform the activity elements according to scheduling
parameters.
Det. Capacity requirements To determine which activity elements have capacity requirement.
Check the option, Print time ticket and enter value 2 to enter confirmation.
Step 5 Click the save button to save configured activity control details.
Project
Network
Activity
Activity Element
Single User
User group
Organizational Group
Display PS Object
Write
Change PS Object
Display PS Object
Change PS Object
Create PS Object
Administration
Delete PS Object
In SAP system, highest possible authorization always applies to a user. If a higher authorization
applies for a user or PS object, the system overwrites the inherited authorization.
Example
Consider user A is assigned to user group 1 that has read authorization for a PS object and the
user has change authorization for PS object. The user gets change authorization in this scenario.
Step 1 Go to the ACL tab page. Select insert line button to enter the new data.
Step 2 In next screen, you have to select the project/network for which you want to delete the
ACL.
Step 3 To display the access control lists, click the Display button.
Step 4 To delete the access control lists, click the Delete button.
Production Planning
Material Management
Using cost function, you can perform fund management and budget allocation. In addition, you
can perform cost planning using the cost function of SAP PS.
Cost planning
Cost planning means the costs that is expected to incur in connection with your project as it is
executed. Cost planning is used for different goals as per the project stages
At the Initial Planning Stage, you define cost planning as the base for an initial cost estimate.
At the time of project execution, it is used to control cost variances and monitor costing.
In addition, you can perform automatic cost planning to integrate project costs with enterprise
controlling.
Costing type Costing type is used to define the object - like a network, or a project for which you
have to create the costing.
Valuation variant In SAP system, you use valuation variant to maintain valuation bases for
materials and activity types managed in the costing.
Example
You determine the price to be considered in accounting view in material master record.
Costing variants are used to maintain unit costing in the general costs activity. To create costing
variant in SAP system, follow the steps given below
Step 1 Navigate to SPRO IMG Project System Costs Planned Costs Manual
cost planning in WBS Unit Costing Create Costing Variant or useT-Code: OKKT.
Step 2 To create new costing variants, click New Entries on costing variant screen.
Costing Variant Enter four-digit alphanumeric unique ID to identify costing variant in SAP.
Control Under control tab, enter appropriate options for costing variants.
Step 4 Go to the Misc tab and enter the appropriate option for cost element for unit
accounting.
Step 1 Go to SPRO IMG Project System Costs Planned Costs Easy Cost
Planning and Execution Services Execution Services Define Execution Service.
Step 2 In the next window, click New Entries in the Execution Profile overview.
Step 3 In the new window, enter the following details
Execution Profile Enter 4-digit alphanumeric code to identify execution profile in SAP system.
Step 4 Next go to Execution Service on the left pane. Select execution profile and double-
click on Execution Service icon in the left pane.
Step 5 On the Execution overview screen, click the New Entries button.
Step 6 In the next screen, enter the services from the drop-down list as per the business
requirements. Press ENTER.
Step 7 The next step is to assign Execution profile to project option to update execution
profile to project profile.
To save the Execution service profile, click the save button at the top.
Original Budget
In Project system, original budget is defined as the allocated cost assigned for a development
order. You can update the budget using the budget update options.
Budget update is known as the unexpected events that occur. Current budget is calculated from
the following factors
Original Budget
Supplements (added)
Transfers (addition/subtraction)
Returns (Subtraction)
Step 2 A new screen Budget Profile for Projects overview will appear. Click New Entries.
Time Frame Enter the number of years for budget. It has three options: Past, Future and Start
Other fields like Availability Control, Currency translation and budgeting currency.
Once you enter all the fields, click the save button at the top.
Step 1 You can navigate to SPRO IMG Project System Cost Budget Create
number ranges for budgeting.
Step 2 On number range budgeting screen, you have the following options
Intervals to display all budgeting number range that has been created earlier
Intervals To maintain new number range for budgeting as per business requirement
Step 3 Click the Intervals button and click insert interval button.
Once you create the number range, click the Save button.
Step 1 SPRO IMG Project System Cost Budget Define Tolerance Limits
Click New Entries to define Tolerance limits.
Step 2 In the next window, enter the following details. Once you define the tolerance limit,
click the save button at the top.
You copy plan values from the sales order to the relevant WBS element.
In SAP system, project values are copied to Controlling automatically.
For period end closing, you copy the results analysis to Profitability Analysis.
Revenue Planning is one of the key aspects of Revenue and earnings. Revenue planning defines
the revenue you expect when a project is executed.
In SAP Project system, you can use the following planning methods
Manual Revenue Planning You can perform manual revenue planning based on Work breakdown
structure or by revenue element.
Automatic update Revenue plan You can perform automatic update of revenue planning based on
Work breakdown structure or in sales order.
SAP PS - Dates
The Dates component in Project System is used to plan and check the dates in project. The use
of date scheduling is to determine phases in a project and duration of the phases, critical paths,
and events in project schedule.
In Work breakdown structures WBS and Network, you enter the dates and these dates can be
changed during full project lifecycle.
When a network contains few activities that are not assigned to same WBS, they are treated as
external networks in system in project scheduling.
Step 1 To define parameters for WBS scheduling, you can use T-code: OPTQ or you can
navigate to SPRO IMG Project System Dates Data Planning in WBS Define
Parameter for WBS Scheduling.
Step 2 In the next screen, click New Entries.
Step 3 In the next window, you have to enter the following field
Start in Past Enter number of past days when scheduling starts in past.
Step 5 When you enter all the details, next is to save the configuration.
SAP PS - Material
This component is used to plan and manage material requirement in project and to manage the
material flow in the project. Material requirement planning in project comes from Material
management and Production Planning and Control.
MRP Parameters
MRP parameters are required to run material requirement planning to meet Planned
Independent Requirement (PIR) and to use the Routing information.
Processing Key
NetChange In this run system consider those material which has undergone some changes from the
previous MRP run.
NetChange in planning horizon This run considers the requirement in predefined planning
horizon and not like net change, which check the future requirements. In this run, the system
considers only those material, which have undergone some changes from their last MRP run.
Regenerative Planning In this run, the system considers all the material irrespective of changes. It
is time consuming and not common in Production planning.
Scheduling
Basic Scheduling It only calculates the basic dates for orders in MRP run and in house production
time for material master in use.
Lead time Scheduling In this MRP, production dates are defined by lead-time scheduling for
planned orders.
Step 2 To run MRP with Net Change in planning horizon, enter the following details.
Enter the manufacturing Plant for which you want to take MRP run.
Enter Input 2 in Create Purchase req. shows purchase requisition in opening period.
Enter 1 in MRP List and system will create MRP list similar to stock /requirement list for later
analysis of previous MRP run.
Enter Planning mode 3 as we will delete and recreate all planning data for all materials.
Enter Scheduling indicator 2 shows MRP will do lead time scheduling and consider routing times to
calculate planned order dates.
Step 3 Click the tick mark at the top as shown in the screen shot given below.
Step 4 If you are sure on MRP run, click the tick mark.
System will take some time to run the MRP and do the calculations. You can see material
requirement and what parameters have been considered during the run.
MRP run for a single material
To perform MRP run for a single material
Delivery schedules 2
Planning mode 3
Scheduling 2
Functions
A Project version can be used for the following purpose
To perform milestone trend analysis to analyze the dates in a project and comparing them with
planned data in the project.
Types of Versions
There are different project version-types available in Project System. They are
Plan Versions This is sued to store different cost plans for a project.
Selection Versions This is used to perform background processing and to save the project data
matching certain selection criteria.
In the table given below, you can see the different features in a project that the above versions
support in a SAP system.
Plan Project Select Simulation
Function
Version Version Version Version
Analyzing includes creating different overview reports and advance level reports with various
degrees of detail. These reports meet the metrics required as part of project management data.
Key functions
The key functions are
The data from Project Information System can be transferred to Business warehouse in SAP system.
A BW system in SAP gathers information from the various areas in your business and changes them
to usable reports for Project Managers.
Using Project Information system, you can run standard reports in system or can create own reports to
meet specific tasks and information.
These reports can be displayed directly and available in Project Information system or you can run
them as background jobs.
You can use the report templates to provide different degree of details, summarize data and
historical data with key values. Historical data includes information from the following
processes
Controlling
Project Progress
Project Resource
Types of Reports
You can use following type of reports using Project Information System.
Technical Reports
Project Information System in SAP PS allows you to manage and control your project
technically.
This allows you to select all the objects or particular objects in the system- WBS, Networks, PS
texts and material etc. to check their present status and their use in project network hierarchy.
This allows you to see the status of project based on different objects.
Using Project Information System, you can monitor the data elated to current project as well as
data in archive to see historical data and lesson learnt.
You can enter the values in filters to create structure list which can be used to view graphics or
to move data to different project management tools.
Commercial Reports
You can view various commercial reports related to project progress in SAP PS system.
Cost Element Report to view cost and revenues to summarize line items.
To monitor full value flow in the project, you can use Cost/Revenue and Payment hierarchy reports.
Payment hierarchy reports contains data related to drill down.
To display actual, plan, commitment, and budget values you can use Line Item Reports.
In the following table, you can see few cost element and hierarchical reports under Project
Information System and their respective information.
Resource Reports
Project Information System provides you various reports on resource utilization and capacity
management.
Capacity Requirements
Workforce Planning
To view these reports, SPRO IMG Project System Information System Resources
To access all the reports, you can scroll to Project System in SAP Easy access menu. Under
Project System you have Information System.
You can also access various inventory and material management reports in Project Information
System.
Purchase orders
Outline agreements
Missing parts
Pegged requirements
Stock/Requirements list
Conducts user requirements gathering, blueprinting and documentation designs. Follow best practices
and SAP functionality in system.