SAP PS Overview (Tutorialspoint)

Project System is one of the key modules of SAP to perform project and portfolio management.
It helps you to manage the project life cycle starting from structuring to planning, execution,
until the project completion. Project system is closely integrated with other SAP modules like
logistics, material management, Sales and Distribution, Plant Maintenance, and Production
planning module.

It enables organizations to manage all SAP projects- large and small-scale projects efficiently.
The Project Manager has a task to ensure that these projects are executed within budget and
time and to ensure that resources are allocated to the project as per the requirement.

Before a project is initiated, it is required that project goal is clearly defined and the activities be
structured.

The integration between SAP Project System PS with SAP ERP R/3 application modules allows
you to design, plan, and execute the projects as part of your normal project procedure. Hence,
Project System module has the constant data access to all the departments involved in the
project.

Classification of Projects
As per budget, projects can be categorized in the following categories

External Financed Projects This includes the projects which are sponsored by clients and are
executed to meet the client requirements. These projects are called customer projects and project goal
is aligned to meet the customer demand.

Internal Financed Projects This includes project related to capital investment or overhead cost
projects.

You can also categorize projects according to the list of activities and project structure or on the
basis of individual activities

Using Work breakdown structure WBS.

Using individual activities as per work packages.


In Project System, Work Breakdown structure and network diagram can be used to structure the
project either in hierarchical order or in using network techniques. You can define key
milestones and documents that allow you to monitor the progress of project and helps you to
define key interest of individuals.

Project Structure can be defined either manually or based on templates. You can also create the
Project structures using sales documents automatically.

In the following diagram, you can see the sample project structure that is created hierarchically
using Work Breakdown structure.

Project System Process Flow


In Project System, each process has a defined set of tasks to be performed. These tasks are
known as process flow in Project Lifecycle.

When a project request is received, a project is created and it has to undergo the following steps
in project process flow/lifecycle.

Following are the key steps involved in Project process flow

Create Templates/WBS

Create Project

Project Planning

Budgeting and Release

Project Implementation

Project Completion

Here is a diagrammatic representation of the process flow of SAP PS

SAP PS - Integration with ERP Modules


Project system is closely integrated with other SAP modules like logistics, material
management, Sales and Distribution, Plant Maintenance, and Production planning module.

The integration between SAP Project System PS with SAP ERP R/3 application modules allows
you to design, plan, and execute the projects as part of your normal project procedure. Hence,
Project System module has the constant data access to all the departments involved in the
project.

SAP PS system is tightly integrated with the following modules

Finance and Controlling Module To plan the costs and revenue in the project system as per the
financial planning requirements.

Material Management MM To manage procurement and inventory functions occurring in project


lifecycle.

Sales and Distribution Module To manage the sales process in project lifecycle- includes
quotations for customer projects. This includes billing, selling, and shipping of goods and services
required in project lifecycle.

Production Planning To perform activities like material requirement planning MRP, Bills of
material BOM, material requisition as per MRP, capacity planning, and other production planning
tasks in project lifecycle.

Other R/3 modules Other modules like plant maintenance, budget management, investment, etc.

In the following diagram, you can see SAP Project System is integrated with SAP R/3 modules
during project lifecycle.
Organization Structure and Elements
When a project is initiated, it starts with the definition and classification of the project structure,
which is required to align it with the existing enterprise structure in an organization.

Project System has no organizational structures of its own and we have to incorporate the
structure to enterprise structure by assigning organization elements in different ERP R/3
modules. These organization elements allow Project system to maintain and get the data
correctly.

An Organization structure consists of various elements that have to be created as part of


structuring of project. Following are the organization elements

Company Code
In SAP FI, a company can comprise of multiple codes, however it acts as a single unit for which
financial statements are available. Company code is smallest unit in an organization for which
financial statements (profit-loss statement, etc.) can be generated.

To create, edit and delete a company code, follow the steps given below
Step 1 Expand Enterprise Structure Definition Financial Accounting Edit, Copy,
Delete, check company code.

Step 2 A new window will open. You can create new company code by selecting both the
options.

The option Copy, delete, and check company code allows you to copy all configuration and
tables automatically.

Step 3 If you select Edit company code, you will get the following window
Step 4 Click New Entries and update the code details.

Step 5 You can click the Address button and update the fields as shown below. Once Address
field is updated, click the Save button.
Creating a Business Area
Business Areas are used to differentiate transactions that comes from different line of business
in a company.

Example
There is a big company XYZ, which runs multiple business. Let us say it has three different
domains like manufacturing, marketing and sales.
Now you have two options

First is to create different company codes

The other option is to create each of these business lines into business areas.

Benefits of using Business Areas in this case

You can use these business areas if other the company codes require the same areas.

It is easy to configure if you use Business Area because you just need to attach to the company code
and the other details in business area will get attach itself.

By using Business areas in controlling, you can create profit and loss statements, balance sheets, etc.
for business areas. Therefore, this is used for management accounting in few companies.

Note Business areas are used in Controlling as compared to Finance Accounting.

Create new Business Area in SAP FI


Step 1 Expand Enterprise Structure as Definition Financial Accounting Define
Business Area.

Step 2 A new window will open. Click New Entries.


Step 3 Enter the 4-digit Business Area code and save the configuration.

Creating a Controlling Area


Controlling Area in an organization is defined as an organizational structure and is cost
accounting, Cost centers, profit centers are used to define the Controlling area.

Step 1 To maintain a Controlling area, use T-Code: OKKP or go to Controlling General


Controlling Maintain Controlling Area Maintain Controlling Area.

Step 2 To create a Controlling area, click New Entries. Enter the following details
Name of Controlling Area

Company Code

Currency settings

Cost Center standard hierarchy

Defining Plant
Plant is an organizational unit within a company where activities take place. A plant will
produce goods and makes goods available for the company.

The following steps will take you through the procedure of creating Plant

Step 1 Go to IMG Enterprise Structure Definition Logistic General. Click


the Define, Copy, Delete check plant icon or use T-Code: OX10.
Step 2 Select Define Plant to create a new plant.

Step 3 Click New Entries.


Step 4 Fill in all necessary details like plant name, along with detailed information like
Language, House no., city, country, region, postal code.

Step 5 Click the save icon. A new plant will be created.

Creating a Storage Location


Storage location is an organizational unit, which actually differentiates between different
material stocks in a Plant. Storage location is a place where stock is kept physically. Plant can
be consisting of multiple storage location. All data is stored at storage location level for a
particular storage location.

The following steps will take you through the procedure of creating Storage location

Step 1 To Create Storage Location, IMG Enterprise Structure Definition Materials


Management. Click the Maintain Storage Location option or use the T-Code: OX09
Step 2 Enter the name of plant for which you want to create storage location.

Step 3 Click New Entries.


Enter the name of storage location along with the description of storage location.

Click the save icon after filling required information. A new Storage Location will be created.

SAP PS - Currencies
In SAP PS system, you can manage all the currency dependent data in the Project System using
the following different currencies.

Controlling Area Currency


In this currency type, you define work breakdown structure (WBS), networks, activities, and
orders in one controlling area. As the same controlling area is used, currency in a project system
is also uniform.

Object currency
In Project System, it is possible to assign any object currency to different objects in the system.

WBS element

Project definition

Network header

Network activity

Note When a company code is assigned to a controlling area and company code contains
multiple currencies, you cannot allocate object currency in PS. In such a case, system
automatically takes the local currency of company code.
Transaction currency
In this case, the costs and revenues from different business transactions are recorded as per
currency of the business transaction.

Example

You can take the currency of PO in which it is raised in the system. In PS system, each amount
is recorded in the database in all three currencies and you use the currency translation rates in
the PS implementation.

Note You can use Information system to view the reports in any currency including the above
mentioned currency types and Project System translates the values in report as per the latest
conversion values.

SAP PS - What is a Project?


A Project is defined as a temporary endeavor to create a product or to provide a service.

Projects have the following characteristics

Projects have a defined goal, which is agreed between the company and customer and is defined in
Project Charter.

Projects are complex, unique, and definitive in scope and involves a high certain risk to execute and
complete on time.

Projects have a defined quality requirements.

Projects have definitive cost, duration and resources to work on the project.

Projects are defined as a part of the internal processes of a company. To execute the tasks in a
project, you have to get an organizational form that is specific to the project and which is shared
by all the departments involved.

You should define the project goal clearly to carry out project in its entirety and the activities to
be carried out must be structured.

You can define project structure

As per the organization structure.

As per the defined processes.


Work Breakdown Structure
This is the first step in project planning to define work breakdown structure to divide the
activities into tasks. The type of tasks and activities to be defined vary as per project complexity
and type of project- customer based or internal project.

In SAP Project system, you define the activities and people in the project in form of Work
breakdown structure WBS.

Project Planning also involves the sequence of tasks to be performed and which tasks are
dependent on each other and which tasks can be further divided in to smaller tasks. In SAP
Project system, sequence of tasks are defined in the form of Network in project planning.

Maintain PS Types
A Project type is used to group or classify the projects as required. For example, banking
projects capital projects or IT development projects.

A Project type is also used for reporting, building authorization and for creating hierarchies and
network in project planning. It can also be used for developing customer requirements, i.e., use
of BADI for WBS settlement rule determination based on project type as a parameter.

By defining PS type for PS texts in SAP system, this helps you to attach the text in project
builder and this text can be used in projects.

Defining PS type in PS Texts


To define PS type in PS texts, follow the steps given below

Step 1 Go to SPRO IMG Project System Documents Define PS types for PS texts
or use T-code: OPS3
Step 2 The PS Text Type screen appears. Click New Entries to define new text types as per
the business requirement.

Step 3 In the next window, enter the following fields

Type Enter the 2-digit unique ID to define PS type in system.

Text Type Enter the text that defines PS text type in system.

Description Enter the text of PS type.

Simulation version You can select checkbox to define changes in simulation version
Step 4 Once you enter the details, click the save button at the top.

SAP PS - Defining Special Characters


You can define various special characters in the project. These characters define how a project
is coded for editing.

You can define different parameters for

Editing the project number.

Length of key for project coding and an indicator to specify if a project should have this length or it
can be shorter.

Structure length to specify length must be equal to no of characters.

Entry tool field for fast entry of WBS element.

Special character helps WBS number to be separated with special charterers.

Automatic Number assignment This is used to update symbol that you want to assign
automatically to project object and WBS.

To define special characters, use T-Code: OPSK

Step 1 Go to SPRO IMG Project System Structure Operative Structure work


breakdown structure Project coding mask Define special characters for project.
Step 2 On special characters overview screen, enter the following details

PL Project Length

SL Structure Length

Entry Tool To fast enter WBS element

Special Character WBS to be separated with special characters

EDIT To create project with coding rules

ANO To assign symbol automatically to project


Note SAP recommends avoiding these special characters *, +, ? and % as these special
characters are used for specific functions in the system.

Step 3 To save the configuration, click the save button at the top.

SAP PS - Status Profile


A status profile contains the individual user statuses and the business transaction rules defined
for those statuses. You can define multiple limit number of user status profiles that can be
maintained in SAP system.

To create a status profile in SAP system

Step 1 You can use T-code: OK02 or go to SPRO IMG Project Systems Structure
Operative Structure Work breakdown structure WBS user status Create Status
profile.
Step 2 A new screen Change status profile overview will open. You can use other options to
copy an existing profile, to delete a profile or to view details.

Step 3 In the next window, enter status profile Id to identify the profile in SAP system.

Enter the text of profile, Maintenance Language: Enter language key like EN. Press ENTER to
continue.
Step 4 Once you press ENTER, status profile you have created will be shown in the list of
status profile. Double-click on status profile.

Step 5 In the next window, enter the following details

Stat Status number form lowest to highest

Status Update unique status id

Short text description text

Initial Status To set the status of profile for project

Lowest Update the lowest status number

Highest Update highest status number

Position To determine status to be displayed

Step 6 After entering these details, click Object types at the top.
The Allowed Object types screen appears with various options.
Step 7 Once you enter all the details, click the save button at the top.

SAP PS - Selection Profile


A Selection profile in SAP Project system is used when you have large number of selection
objects repeatedly with same selection condition. Selection conditions are used using topdown
approach.

To configure selection profile, follow the given steps


Step 1 Go to SAP Easy access SPRO IMG Project Systems Structure Operative
Structure Milestones Define Selection profiles or use T-code: BS42.

Step 2 To create new selection profile, click New Entries on Status Selection
Overview screen.

Step 3 In the next window, you have to enter 7-digit alphanumeric id that identifies the
selection profile and text description of selection profile. Enter the status profile Id that you
have created.
Step 4 You can also perform Search option to select the Status profile.

Step 5 Next, go to Selection conditions screen on the left side.


Step 6 Once you double-click, click the New Entries button at the top.

Step 7 In the next window, enter the following details

Usr For user status

StatusProf This is optional field to update user status profile.

Status Update status from drop down, If status is user status, you can select X from the drop down.
Step 8 To exclude selected condition in the report, enter

State To show if profile is active


Step 9 Once you enter all the details, click the save button at the top.

SAP PS - Project Profile


A Project profile is defined to maintain default values and control parameters like planning
methods for costs. The information entered in project profile is copied to project in project
definition or also in the project elements. This information can be changed at later stage.

Note that the values in the project profile is used to maintain the functions of certain areas of the
Project System and should only be changed without considering all the factors. You should not
change the keys related to costing sheet or the results analysis key as these can change existing
system.

You must maintain the following information under project profile section

Basic data

Time scheduling

Costs/revenues/finances

Organizational data

A standard R/3 System contains the predefined project profile that has the most important
control parameters.

To create a Project profile

Step 1 Use T-code: OPSA or go to SPRO IMG Project Systems Structure


Operative Structures Work Breakdown structure Create Project Profile.
Step 2 To create a new profile, click New Entries on Project Profile Overview screen.

On the New Entries screen, enter the following details

Proj.prof. Enter the unique ID that identifies project profile in SAP system.

Project Type Category to which project belongs.

Field Key Select field key from the drop-down list. You can select different field keys for different
projects as shown below
In the new window, select the following

Display Options This determined how the project will be identified in project builder.

All account assessment element This has to be selected if all WBS has to be created using this
profile.

Project summarize master data Select this field to summarize the master data in project. This is
used to perform any reports.

Project Stock Default is no stock option.


Next, go to Organization tab. You have to enter the following details under the Organization tab

Controlling Area Enter Controlling area belongs to project profile

Company Code Enter the company code that belongs to Control area

Business area Enter business area belongs to company code and controlling area
Plant Enter plant code belongs to company code

Functional area Enter functional area key

Profit Center Enter profit center belongs to controlling area

Project Currency Enter project currency

Click the save button at the top to save the project profile.

SAP PS - Settlement Profile


In a project, you collect cost and revenues temporarily and they have to settle as part of period
end processing. You need a settlement profile stored in project profile or network type, which
determines whether settlement is required, allowed, or blocked.

You can use the settlement profile to define the following for actual costs

Full Settlement

Can be settled

Not to be settled

As per the settings in the settlement profile, there is a need to settle the costs of an object in full
before that object is achieved in the system.

You can maintain a settlement profile in system.


Step 1 Use the T-code: OKO7 or navigate to SPRO IMG Controlling Internal
Orders Actual Postings Settlement Maintain settlement profiles.

Step 2 In the next window, select maintain settlement profiles and click Choose.
Step 3 To create a new settlement profile, click New Entries in the Settlement profile
overview window.

Step 4 In the next window, you have to enter the following details

Settlement profile Enter unique ID that identifies the settlement profile in system and description.
Actual Cost/Cost of sales To find the settlement value

Default values Enter allocation structure and default object type field

Indicator Select % settlement and amount settlement

Enter Receivers

Other parameters Document type, maximum number of dist rls, residence time

Step 5 Once you enter all the fields, click the save button at the top.
SAP PS - Network Profile
You can create network profile in SAP PS to maintain Network and WBS structure and to
define rules for linking networks.

To create network profile, follow the steps given below

Step 1 Use T-Code: OPUU or go to SAP Easy access, SPRO IMG Project System
Structures Operative structure Network Setting for Network

Step 2 In next screen, enter the following details

Network Profile This is unique Id to identify network profile in the system.

Plant Enter plant code and it is default for all activities

Network Type Enter the network type from drop down list

MRP Control group Enter the MRP control group associated with planner group

Relationship view Enter the relationship view used for defining rules for linking network

Comp increment Enter the comp increment

Check WBS account Enter WBS account system determines the WBS.
Reservation Purchase requisition Enter Reservation purchase requisition

Capacity Requirement Select this to calculate capacity requirement once network is saved.

Project summary Master data To summarize master data

Step 3 Next, go to the Graphic tab to select the details for network graphics like color, display
option, etc.
Step 4 Similarly, go to the Activity tab and enter the details.

Click the save button at the top.

SAP PS - Network Type


Network type is defined as an order type with different order categories- Production order,
network order, etc.
These orders represent different business transactions- CO01 / CO11N, IW31, KO01, OPSC
and these order parameters are defined by order categories. All these order types are relevant for
specific applications.

In SAP PS system, a network type is used to contain the information for controlling and
managing networks. Network is defined as work order that has a structure in common with
production, maintenance, and inspection orders.

In SAP system, when you define a network, it should also contain a network type maintained
with it.

Network type in PS system determines

Order category

CO Partner update

To maintain a Network type, follow the steps given below

Step 1 Use T-Code: OPSC or go to SPRO IMG Project System Structures


Operative structure Network Setting for Network Maintain Network Type.
Step 2 In the next screen, click New Entries to create a network type.

Step 3 In the next screen, enter the following details

Order Type Enter unique id that identifies the order type in SAP system

Control Indicator to select classification and to copy data to Controlling

o Residence Time 1

o Residence Time 2

Functional Area To create Profit and Loss account in FI

Settlement profile and other fields as shown below.


Step 4 Click the save button at the top.

SAP PS - Person Responsible for Work Center


In SAP Project System, you can define the person responsible for Work Center. To define a
responsible person, you need to enter person responsible Id and descriptive name of the person
responsible for managing the work center.
To specify a person responsible for work center, navigate to the following path in SAP Easy
access.

Step 1 SPRO IMG Project System Structures Operative structure Network


Work Center Specify person responsible for work center

Step 2 In the next window for Person Responsible for Work center, click New Entries.

Step 3 In the next screen, you have to enter the following details

Plnt Enter the plant key that you want to assign person for work center.

Pers. Respons In this field, enter the person responsible for work center ID
Person responsible for work center Descriptive name of person responsible for managing work
center.

Step 4 Once you enter all the details, click the save button at the top.

SAP PS - Maintain Activity Control Key


In SAP Project system, you can create control key to perform the different activities and activity
elements.

Using Control key in SAP PS system, you can determine the business transactions to be
performed when you perform an activity. An activity can be an internal activity, external
activity or both.

While defining the control key, you have to specify the indicators and keys for different
functions in the control key. You can use SAP standard control keys PS01, PS02 and PS05 for
networks.

To maintain control key, follow the steps given below

Step 1 Use T-code: OPSU or navigate to SPRO IMG Project System Structures
Operative structure Network Setting for network activities Define Control Key.
Step 2 In the next screen, click Activity Control screen New Entries.

Step 3 In the new window, maintain the following fields

Crtl four digit alphanumeric ID identifies control key

Description Enter the detailed text of control key

Step 4 Under the Indicator tab, select the following fields


Indicator You can update the following option under Indicator field.

Scheduling You can select this option to perform the activity elements according to scheduling
parameters.

Det. Capacity requirements To determine which activity elements have capacity requirement.

General Costs account To use control key by general costs.

Cost To determine cost with activities.

Check the option, Print time ticket and enter value 2 to enter confirmation.

Step 5 Click the save button to save configured activity control details.

SAP PS - Access Control List


In SAP Project system, you use access control list to assign authorizations for specific Project
system objects. The Access control list function should be activated in project profile or
network profile.
Authorization can be assigned for the following PS objects

Project

Work Breakdown structure

Network

Activity

Activity Element

You have the following different authorization types available

Single User

User group

Organizational Group

In SAP PS system, you can assign different types of authorizations.

Authorization Allowed activity

Read Display PS Object

Display PS Object
Write
Change PS Object

Display PS Object

Change PS Object

Create PS Object
Administration
Delete PS Object

Create access control lists

Edit access control lists


Delete access control lists

No Authorization No activity allowed

In SAP system, highest possible authorization always applies to a user. If a higher authorization
applies for a user or PS object, the system overwrites the inherited authorization.

Example
Consider user A is assigned to user group 1 that has read authorization for a PS object and the
user has change authorization for PS object. The user gets change authorization in this scenario.

Creating Access Control List


To create an access control list, navigate to the PS object for which you want to assign
authorizations.

Step 1 Go to the ACL tab page. Select insert line button to enter the new data.

Step 2 Click Save to save the entry.

Deleting Access control list for a project or a network


Step 1 To delete access control list for a project, use T-code: CNACLD

Step 2 In next screen, you have to select the project/network for which you want to delete the
ACL.

Step 3 To display the access control lists, click the Display button.
Step 4 To delete the access control lists, click the Delete button.

SAP PS - Cost Component


In SAP PS, you can use the Cost component to plan, monitor, and control project cost for
projects. This component is integrated with different components in SAP ERP system

Finance Accounting and Controlling

Production Planning

Material Management

Using cost function, you can perform fund management and budget allocation. In addition, you
can perform cost planning using the cost function of SAP PS.
Cost planning
Cost planning means the costs that is expected to incur in connection with your project as it is
executed. Cost planning is used for different goals as per the project stages

At the Initial Planning Stage, you define cost planning as the base for an initial cost estimate.

At the Approval stage, you define it for the budget allocation.

At the time of project execution, it is used to control cost variances and monitor costing.

In addition, you can perform automatic cost planning to integrate project costs with enterprise
controlling.

SAP PS Create Costing Variant


In SAP PS system, you use Costing variants to manage the criteria for the costing. Costing
variants are used to define the pricing strategy in the system for costing and how overhead
should be determined.

A Costing variant contains the following components

Costing type Costing type is used to define the object - like a network, or a project for which you
have to create the costing.

Valuation variant In SAP system, you use valuation variant to maintain valuation bases for
materials and activity types managed in the costing.

Example
You determine the price to be considered in accounting view in material master record.

Costing variants are used to maintain unit costing in the general costs activity. To create costing
variant in SAP system, follow the steps given below

Step 1 Navigate to SPRO IMG Project System Costs Planned Costs Manual
cost planning in WBS Unit Costing Create Costing Variant or useT-Code: OKKT.
Step 2 To create new costing variants, click New Entries on costing variant screen.

Step 3 In the next screen, enter the following details.

Costing Variant Enter four-digit alphanumeric unique ID to identify costing variant in SAP.

Control Under control tab, enter appropriate options for costing variants.
Step 4 Go to the Misc tab and enter the appropriate option for cost element for unit
accounting.

Click the save button to save the configured cost variant.


SAP PS - Execution Service Profile
In SAP PS system, you can define execution service profile. Follow the steps given below to
navigate

Step 1 Go to SPRO IMG Project System Costs Planned Costs Easy Cost
Planning and Execution Services Execution Services Define Execution Service.

Step 2 In the next window, click New Entries in the Execution Profile overview.
Step 3 In the new window, enter the following details

Execution Profile Enter 4-digit alphanumeric code to identify execution profile in SAP system.

Name Text of execution profile.

To save the data, click the save button at the top.

Step 4 Next go to Execution Service on the left pane. Select execution profile and double-
click on Execution Service icon in the left pane.

Step 5 On the Execution overview screen, click the New Entries button.
Step 6 In the next screen, enter the services from the drop-down list as per the business
requirements. Press ENTER.

Step 7 The next step is to assign Execution profile to project option to update execution
profile to project profile.
To save the Execution service profile, click the save button at the top.

SAP PS - Budget Management


Budget is defined as the approved cost for a project and it is different from the cost plan. The
Budget is the approved cost from management for expected development of order cost for a
given time period. Different budget types exist in a Project system.

Original Budget
In Project system, original budget is defined as the allocated cost assigned for a development
order. You can update the budget using the budget update options.

Budget update is known as the unexpected events that occur. Current budget is calculated from
the following factors

Original Budget

Supplements (added)

Transfers (addition/subtraction)

Returns (Subtraction)

SAP PS Budget Profile


You can define the budget profile for projects in SAP system.

To create a budget profile


Step 1 Use T-code: OPS9 or navigate to SPRO IMG Project System Cost Budget
Maintain budget profiles in SAP

Step 2 A new screen Budget Profile for Projects overview will appear. Click New Entries.

Step 3 In the new window, enter the following details

Profile Enter the unique ID that identify the budget profile

Text Enter the text description

Time Frame Enter the number of years for budget. It has three options: Past, Future and Start

Total Values This is used to select budget as over value


Annual Values Maintaining budget for yearly basis

Investment Management Program type budget for an investment program

Other fields like Availability Control, Currency translation and budgeting currency.

Once you enter all the fields, click the save button at the top.

SAP PS - Number Ranges for Budgeting


Number range is defined for all budget documents that the system creates when there is a
change in budget. You define your own number range for all budget documents created for
allocation, supplement, transfer, release, etc.
You can maintain the number range for budgeting in SAP system using T-code: OK11

Step 1 You can navigate to SPRO IMG Project System Cost Budget Create
number ranges for budgeting.

Step 2 On number range budgeting screen, you have the following options

Intervals to display all budgeting number range that has been created earlier

Status To modify the number range

Intervals To maintain new number range for budgeting as per business requirement
Step 3 Click the Intervals button and click insert interval button.

Step 4 In the next window, enter the following details.

No 2 digit unique ID for number ranges

From Number Starting number of interval

To Number Last number of intervals

Current number Default number will be 0

Ext To assign the number manually

Once you create the number range, click the Save button.

Defining Tolerance Limit


You can define the tolerance limit for a budget in SAP system.

Step 1 SPRO IMG Project System Cost Budget Define Tolerance Limits
Click New Entries to define Tolerance limits.

Step 2 In the next window, enter the following details. Once you define the tolerance limit,
click the save button at the top.

SAP PS - Revenues and Earnings


In SAP custom projects, you need to compare costs and revenues to get details on project
results.

The following points should be considered

You copy plan values from the sales order to the relevant WBS element.
In SAP system, project values are copied to Controlling automatically.

For period end closing, you copy the results analysis to Profitability Analysis.

Revenue Planning is one of the key aspects of Revenue and earnings. Revenue planning defines
the revenue you expect when a project is executed.

In SAP Project system, you can use the following planning methods

Manual Revenue Planning You can perform manual revenue planning based on Work breakdown
structure or by revenue element.

Automatic update Revenue plan You can perform automatic update of revenue planning based on
Work breakdown structure or in sales order.

To update revenue plan data from sales order

Step 1 Navigate to Project System Revenues and Earnings Planned Revenues


Automatic Plan Revenue Calculation Specify Revenue Plan Update from Sales Document.

You record the data using the following


Value and revenue element from the condition.

Expected billing date from the billing plan or schedule line.

SAP PS - Dates
The Dates component in Project System is used to plan and check the dates in project. The use
of date scheduling is to determine phases in a project and duration of the phases, critical paths,
and events in project schedule.

In Work breakdown structures WBS and Network, you enter the dates and these dates can be
changed during full project lifecycle.

Maintaining Dates in Projects


When you define a project in system, you enter the start and the finish dates of the projects.
When you create Work Breakdown structure, you start planning dates for WBS. The dates are
calculated for full part of part of project for activities using the scheduling function.

SAP PS - WBS Scheduling Parameters


In SAP Project system, you can schedule a project or part of the project with all the activities
that are assigned to project. You can use WBS element basic dates as basic dates to schedule the
activities.

When a network contains few activities that are not assigned to same WBS, they are treated as
external networks in system in project scheduling.

Step 1 To define parameters for WBS scheduling, you can use T-code: OPTQ or you can
navigate to SPRO IMG Project System Dates Data Planning in WBS Define
Parameter for WBS Scheduling.
Step 2 In the next screen, click New Entries.

Step 3 In the next window, you have to enter the following field

Scheduling Type To define type of scheduling.

Possible options are as shown in the screenshot given below.


Step 4 In the new screenshot, enter the following details as

Start in Past Enter number of past days when scheduling starts in past.

Scheduling Method Select the scheduling method.

Reduction To enter reduction lead time and reduction type and

Other fields as per business requirement.

Step 5 When you enter all the details, next is to save the configuration.
SAP PS - Material
This component is used to plan and manage material requirement in project and to manage the
material flow in the project. Material requirement planning in project comes from Material
management and Production Planning and Control.

Procurement of Material using MRP


MRP run or planning run is an engine, which is used to fill the demand and supply gap. Issues
& Receipts are called MRP elements. Issues include PIRs, Dependent Requirements, Order
Reservations, Sales Orders, Issuing Stock Transfer Orders, etc. Receipts include Production
Orders, Purchase Requisitions, Purchase Orders, Open Production Orders, Receiving Stock
Transfer Order, Schedule lines, etc.

MRP Parameters
MRP parameters are required to run material requirement planning to meet Planned
Independent Requirement (PIR) and to use the Routing information.

Different MRP parameters can be used.

Processing Key
NetChange In this run system consider those material which has undergone some changes from the
previous MRP run.

NetChange in planning horizon This run considers the requirement in predefined planning
horizon and not like net change, which check the future requirements. In this run, the system
considers only those material, which have undergone some changes from their last MRP run.

Regenerative Planning In this run, the system considers all the material irrespective of changes. It
is time consuming and not common in Production planning.

Scheduling
Basic Scheduling It only calculates the basic dates for orders in MRP run and in house production
time for material master in use.

Lead time Scheduling In this MRP, production dates are defined by lead-time scheduling for
planned orders.

Running Material Requirement Planning for all Products


Step 1 Use T-code: MD01 or go to Logistics Production MRP Planning Total
Planning Online

Step 2 To run MRP with Net Change in planning horizon, enter the following details.

Enter the manufacturing Plant for which you want to take MRP run.

Enter Processing key as NETCH.

Enter Input 2 in Create Purchase req. shows purchase requisition in opening period.

Enter 2 for schedule lines shows.

Enter 1 in MRP List and system will create MRP list similar to stock /requirement list for later
analysis of previous MRP run.

Enter Planning mode 3 as we will delete and recreate all planning data for all materials.

Enter Scheduling indicator 2 shows MRP will do lead time scheduling and consider routing times to
calculate planned order dates.
Step 3 Click the tick mark at the top as shown in the screen shot given below.

Step 4 If you are sure on MRP run, click the tick mark.

System will take some time to run the MRP and do the calculations. You can see material
requirement and what parameters have been considered during the run.
MRP run for a single material
To perform MRP run for a single material

Step 1 Use T-Code: MD02 or go to Logistics Production MRP Planning Single


item Multilevel.
This is used to plan individual item planning. Enter material number and Plant.

Processing key, NETCH (Net Change for total horizon)

Create purchase req. 2

Delivery schedules 2

Create MRP list 1

Planning mode 3

Scheduling 2

Click the Tick mark.


SAP PS - Versions
In SAP system, version is defined as state of a project at certain point in time. Project versions
are used in Earned value analysis and for project evaluation.

Functions
A Project version can be used for the following purpose

To perform the statistical evaluation.

To document the state of project.

To perform comparison and analysis of project progress.

To perform milestone trend analysis to analyze the dates in a project and comparing them with
planned data in the project.

Types of Versions
There are different project version-types available in Project System. They are

Project Versions To compare project status at specific time period.

Plan Versions This is sued to store different cost plans for a project.

Selection Versions This is used to perform background processing and to save the project data
matching certain selection criteria.

In the table given below, you can see the different features in a project that the above versions
support in a SAP system.
Plan Project Select Simulation
Function
Version Version Version Version

Add to version Yes Yes No Yes

Compare versions Yes Yes No Yes

Limit selection Yes Yes No

Contains Summarized cost


Yes Yes Yes Yes
data

SAP PS - Project Information System


In SAP system, a Project Information System is used to monitor and control the project master
data. It allows you to analyze each project, part of projects, or multiple projects.

Analyzing includes creating different overview reports and advance level reports with various
degrees of detail. These reports meet the metrics required as part of project management data.

Key functions
The key functions are

The data from Project Information System can be transferred to Business warehouse in SAP system.

A BW system in SAP gathers information from the various areas in your business and changes them
to usable reports for Project Managers.

Using Project Information system, you can run standard reports in system or can create own reports to
meet specific tasks and information.

These reports can be displayed directly and available in Project Information system or you can run
them as background jobs.

Analyzing report includes considering various fields and functions of project.


Example
You can send the reports via email, put them on shared drive or take a print out of the reports to
distribute the hard copy.

You can use the report templates to provide different degree of details, summarize data and
historical data with key values. Historical data includes information from the following
processes

Controlling

Project Progress

Project Resource

Material Requirement and planning

Types of Reports
You can use following type of reports using Project Information System.

Technical Reports
Project Information System in SAP PS allows you to manage and control your project
technically.

This allows you to select all the objects or particular objects in the system- WBS, Networks, PS
texts and material etc. to check their present status and their use in project network hierarchy.
This allows you to see the status of project based on different objects.

Using Project Information System, you can monitor the data elated to current project as well as
data in archive to see historical data and lesson learnt.

You can enter the values in filters to create structure list which can be used to view graphics or
to move data to different project management tools.

Commercial Reports
You can view various commercial reports related to project progress in SAP PS system.

Cost Element Report to view cost and revenues to summarize line items.

To monitor full value flow in the project, you can use Cost/Revenue and Payment hierarchy reports.
Payment hierarchy reports contains data related to drill down.
To display actual, plan, commitment, and budget values you can use Line Item Reports.

In the following table, you can see few cost element and hierarchical reports under Project
Information System and their respective information.

Information Report Type

Debits and credits by object Cost Elements

Credit from settlement Cost Elements

Statistical key figures Cost Elements

Detailed actual, plan, and commitment values by object Cost Elements

Budgeting and cost planning Hierarchy Report

Incoming Orders Hierarchy Report

Open Orders Hierarchy Report

Resource Reports
Project Information System provides you various reports on resource utilization and capacity
management.

Capacity Requirements

Capacity Load with Variable View

Workforce Planning

Capacity Load with Work Center View

To view these reports, SPRO IMG Project System Information System Resources
To access all the reports, you can scroll to Project System in SAP Easy access menu. Under
Project System you have Information System.

To view these reports, go to SPRO IMG Project System Information System

You can also access various inventory and material management reports in Project Information
System.

Purchase orders

Outline agreements

Missing parts
Pegged requirements

Stock/Requirements list

SAP PS - Consultant Responsibilities


A SAP PS Consultant must have all required Project System functional and Configuration
knowledge in SAP ECC system.

The Consultant should have relevant experience in the following areas

SAP PS Implementation Experience: End-to-end Implementation experience in different domains -


Banking, Manufacture, Civil or any other Industry.

Good configuration knowledge of PS structures: WBS, Network, Milestones, Cost Planning,


Budgeting, Material Requirement planning, Project quotation, Time sheets, Goods issues, and other
project management activities in SAP PS.

Must have completed at least two end-to-end implementations.

Experience on complete PS module cycle from project creation to settlement.

Integration knowledge with CO, FI and MM, SD and PP.

Must be proficient in handling Issues/support functions.

Conducts user requirements gathering, blueprinting and documentation designs. Follow best practices
and SAP functionality in system.