Instruction No. 5.1 Charges For Supply:: Section - V Tariffs
Instruction No. 5.1 Charges For Supply:: Section - V Tariffs
Instruction No. 5.1 Charges For Supply:: Section - V Tariffs
SECTION V
TARIFFS
********
4. Extension in Load.
i) Extension in load by single Rs.350/- per kW
phase (for extension part
in NDS only)
ii) Extension in load by three Rs.750/- per kW
phase in NDS (for extension part
only)
iii) Extension in load bringing the Rs.500/- per kW
total load Upto 70 kW (Both for (for extension part
Bulk and L.T. Industrial Supply) only)
iv) Extension in load bringing the Rs.750/- per kW
total load Above 70 kW. (Both (for extension part
for Bulk and H.T. Industrial only)
supply
33
NOTE :
Where there is a change of category from L.T. (upto 70
kW) to HT (above 70 kW), the charges would be levied on
the additional kVA demand, calculated as under (as an
example):
Existing sanctioned load 40 kW
Applied Load 150 kW with Contract 140 kVA
demand of 140-(40/0.90)=95.55
Additional Demand kVA
NOTES :
i) The line service charges on the original load, if already
being levied, shall continue.
ii) While assessing the connected load for working out this
charge both general and industrial loads shall be taken into
account.
iii) Load exceeding 70 kW shall be catered on 11 KV and
above. The above limit shall be applicable both for new and
extension cases after taking into account the existing load.
iv) An increase in the connected load without increase in
Contract Demand shall not call for payment of service
connection charges. However, consumers seeking
extension in Contract Demand within the sanctioned
connected load shall be required to pay service connection
charges on kVA basis on the incremental contract demand.
NOTES:
i) Upto 70 kW: The Advance Consumption deposit may be
accepted in two equal installments, first installment along
with the application and the 2nd installment at the time of
compliance demand notice.
ii) Above 70 kW: The Advance Consumption Deposit may be
recovered in two installments. First installment being
1/3rd(but not less than the first installment for 70 kW) and
(remaining) or 2/3rd at the time of compliance of demand
notice.
6. Capacitor Service Charges For A.P. For
(per month) Consumers Industrial
Capacitor Size Consumers
a) Capacitors upto 2 KVAR Rs. 2/- Rs. 4/-
b) Capacitors of 3 KVAR Rs. 7/- Rs. 14/-
c) Capacitors of 4 KVAR Rs. 9/- Rs. 18/-
d) Capacitors of 5 KVAR Rs. 12/- Rs. 24/-
e) Capacitors of 7 KVAR Rs. 20/- Rs. 40/-
35
GENERAL NOTES:
i) Wherever in the above schedule, a rate is
expressed as a rate per month or as a monthly
rate, it means a proportionate charge if the period
of charge is less than one month.
ii) In case where disconnection and connection takes
place in the same month, a full months charge
shall be recovered.
iii) In case a consumer elects to pay the cost of the
service line, the amount payable by him shall be
the estimated cost of service line (excluding the
cost of 30 meters) and equipment and of installing
the same.
iv) In case of temporary general and industrial supply,
if the service line and meter are provided and
installed by the Licensee, the consumer shall be
charged four times the relevant charges provided
above for each period of 30 days or less.
Concession of first 30 meters of free service line is
not to be allowed.
********
INSTRUCTION NO. 5.15
Levy of surcharge:
The surcharge is leviable on all types of dues raised through
energy bills including energy charges recoverable under the schedule
of tariff and the amount recoverable under the schedule of general and
miscellaneous charges (excepting the amount of Electricity Duty and
M. Tax) in case the payment is not made within the due date.
********
INSTRUCTION NO. 5.17
Example-1
Suppose a domestic supply consumer deposits Rs.10,000/- in
advance as on 1.4.2003 and his due date for making the bimonthly
payment of energy bill is 15th May, 15th July and so on. The rate of
incentive declared by DHBVNL for the year 2003-04 is 4.5% per
annum.
Example-2
Suppose a Industrial supply consumer deposits Rs.10,000/- in
advance as on 1.4.2003 and his due date for making the bimonthly
payment of energy bill is 15th April, 15th May and so on. The rate of
incentive declared by DHBVNL for the year 2003-04 is 4.5% per
annum.
********
INSTRUCTION NO. 5.26