2014-0021 Construction Method Statement

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

Construction

Method Statement
Scout Moor Wind Farm
Expansion Erection of a
Temporary Meteorological
Mast

Scout Moor Wind Farm


Expansion Limited
January 2014
Contents

1 Introduction 1

2 Mast Specification 2

3 Commissioning 3

4 Avoidance of Adverse Impacts to Ecological Receptors 11

5 De-Commissioning 12

TA reference: PEEM2100

Date of issue: 20 January 2014

1 New York Street


Manchester
M1 4HD

T: 0161 233 7676


1 Introduction
1.1 This Construction Method Statement has been prepared on behalf of Scout Moor Wind
Farm Expansion Limited (SMWFE), previously known as Peel Wind Farms (Scout Moor)
Limited. SMWFE is a joint venture company formed by Peel and United Utilities. This
application provides detailed information in relation to the proposed erection of a
temporary meteorological mast (met mast) on land to the north of Scout Moor Windfarm.

1.2 The existing Scout Moor windfarm comprises 26 no. wind turbines and associated
ancillary infrastructure. Each turbine stands to a height of 100 metres to blade tip.

1.3 In the autumn of 2011, Peel Wind Farm (Scout Moor) Limited announced that it was
investigating the potential to expand the wind farm through the erection of additional
turbines. Because the expansion proposals would constitute a Nationally Significant
Infrastructure Project (NSIP) it would be promoted through the submission of an
application for a Development Consent Order to the Planning Inspectorate.

1.4 The proposed met mast is required in order to assist SMWFE in obtaining a better
understanding of the prevailing wind regime in the potential location of the additional
turbines and the information will, in turn, assist the iterative design process for the
expansion proposal.

1.5 The proposed met mast will be erected for a period of 36 months.

1.6 Details of the proposed mast location are provided at Table 1 below.

Mast Location

382256, 420340

Latitude: 53 40 45.185 N

Longitude: 2 16 12.373 W

Table 1: Proposed Met Mast Locations

1
2 Mast Specification
2.1 The proposed mast is an 80 metre high Nexgen H1 meteorological mast.

2.2 The mast will be delivered in sections and assembled on site. For the height proposed
there will be:

8 no. 2.7m long, 25.4cm diameter tubes


12 no 3.0m long, 22.0cm diameter tubes
7 no. 3.0m long, 20.0cm diameter tubes
1 no. 1.5m long, 20.0cm diameter tube

2.3 The general arrangement of the mast is shown on drawing 1-MA-80-001. Instruments will
be mounted on booms at heights of 30mAGL, 50mAGL, 75mAGL and 78mAGL. The
orientation of the booms is typically 180 and 270.

2
3 Commissioning
3.1 This Chapter details the processes that will be undertaken to commission the met mast
on site. Photographs of the erection of a similar met mast are provided for context.

Stage 1: Siting

3.2 Peat is a valuable natural resource supporting key habitats and represents an important
store of sequestrated carbon. The location of the met masts has been carefully selected
by SMWFE in order to avoid areas of deep peat, i.e. those areas with an organic-rich
upper horizon deeper than 0.5 metres. The proposed location has also been chosen as it
is outside of any area designated for biodiversity or geodiversity interest.

3.3 Using a compass, GPS and tape measure, the site will be marked out with pegs showing
anchor positions and base plate. Clearance from power lines, buildings, public walkways
etc. will be ensured. Wherever possible the mast will be laid out uphill, with the side
anchors on level ground and with the prevailing wind coming from the direction of the lift
anchor.

3.4 The mast anchoring configuration is detailed at Table 2 below.

Anchor Distance from Mast


Guys Load Required
Centre (metres)

34 36 1, 2, 3 1,500 kg

49 51 4, 5, 6, 7 3,900 kg

23m lift anchor 1&1to1 > 5,000 kg

7m rear lift anchor N/A > 3,000 kg

There must be a 35m and 50m anchor on all four sides of the mast. In addition to this there must
be a 23m lift anchor and 7m rear anchor. Only guy set 1 and the 1 to 1 can be connected to the
lift anchor, all other guys must connect to the outer anchors as specified.

Table 2: Mast Anchoring Configuration

Ground Conditions

3.5 Damage to the moorland vegetation and soils would be prevented by adhering to the
following methods:

Wet ground would be avoided. Unavoidable movement of machinery over wet ground
would require the laying down in advance of >15mm plywood boards.

3
No heavy tracked vehicles would be used unless on metalled roads and existing stone
tracks.
Only low ground pressure vehicles and machines would be used.
Vehicles and machines would be confined to designated service tracks and work
areas and movement kept to an absolute minimum to complete the work.
There would be no slewing of vehicles that can form ruts and damage the vegetation
and soil.
There would be no change to the shape and form of the ground surface that could
alter site hydrology.
No bare ground would be left following works where not already present.

3.6 Suitable vehicles (e.g. 44 Land Rover or equivalent) to gain access to the mast location
and plant and equipment will be used as needed to complete the work efficiently and
safely.

Underground Services

3.7 The site plan will be checked and local land management contacted (or other
knowledgeable source) for any known underground services.

3.8 CAT scan will be used to check for underground cables or pipe work in the vicinity of
anchor locations.

Stage 2: Installation of Ground Anchors and Load Testing

3.9 The exact method of ground anchoring is typically determined by the ground conditions
encountered on site. In this instance the ground consists of a shallow layer of peat
(<10cm) which overlays soil. Nevertheless, efforts will be made to minimise the number of
machine traverses over the ground.

Installation of dead-man anchors

3.10 A trench is dug at the anchor position using a small backhoe or excavator, approximately
0.5m wide by 2.4m long by 2m deep, resulting in removal of approximately 2.4m of
material. A small sloping trench is cut in front of the anchor to allow the anchor rod to sit
at an angle of 45 to the mast centre. The dead man is made from a tanalised timber
gate post approximately 250mm round by 2m long, through the middle of which is passed
a 2.5m long 24mm dia. galvanised anchor rod. The anchor rod is terminated on the
underside of the timber using a 175mm 175mm 8mm steel washer plate and nut. The
timber is then lowered into the hole with the eye of the anchor rod above ground. The
following measures would be employed to reduce damage / disturbance to the ground:

The turf/vegetation will be cut with a spade or the blade of the bucket, held vertically to
cut down, and not at an angle. The cut turf should fit the bucket. It is anticipated that
would be a need to only remove 2 or 3 turves at each anchor point.
Turves would be cut to the depth of the roots (probably about 200-300mm although
this will be assessed on site at each of the anchor points).

4
Turves would be extracted intact and carefully placed in the order they were extracted
on a geotextile (or heavy duty plastic sheet) in a location that is convenient for the
works but where they will not be damaged by other activities. They will not be placed
on top of each other. Turves from one anchor point will not be mixed with those from
another.
If there is organic-rich soil beneath the cut turf, this would be extracted in as complete
a form as possible i.e. as bricks or box-shapes, and placed carefully to avoid them
breaking, and stored on geotextile.
The lower mineral soil horizons and substrate would be excavated and stored
separately on geotextile.
Following the completion of the trench and the installation of the anchor, the trench
would be backfilled initially with the mineral soil and tampered down every 300mm
with the back of the excavator bucket to get even compaction and support for the
anchors. This would be followed by the infilling of any remaining organic-rich material.
The turves would be replaced in the same order as they were extracted to maintain
the integrity of the vegetation community, and gently compressed but not compacted,
so they are not significantly proud of the of the adjacent ground surface.
Any excess soil would be removed from site. However, the majority of the soil would
be used to infill excavation trenches and it is not thought that there would be a
significant amount of material to be removed.

3.11 The hole is backfilled with the soil and tamped down every 300mm with the bucket to get
even compaction.

Load Testing

3.12 In order to test the holding capacity of the anchor the rod is pulled using the backhoe or
excavator at an angle of approximately 45 to the mast centre. A load cell is placed in
between the anchor and the machine in order to measure the holding capacity. In all
except very weak ground a dead man anchor will provide extremely good holding
characteristics. If the ground is very weak such as in peat then the hole dug will need to
be backfilled with other material, and or the amount of buried timber will need to be
increased. A typical dead man anchor layout is demonstrated at Figure 1 below; whilst a
photograph of an example anchor point excavation is provided at Figure 2.

Figure 1: Typical dead man anchor Figure 1: Example anchor point


layout excavation (dug in soft sand)

5
Stage 3: Mast Assembly

3.13 The tubes that make up the mast exceed 25 kg and will be lifted carefully by at least 2
people. The mast and guys are assembled in the horizontal position on level ground to
avoid undue flexing of the mast tower sections.

Figure 2: Mast assembly on level ground

Stage 4: Gin-Pole Assembly

3.14 The gin-pole will be assembled and erected. A winch load will be applied to the lifting
cable and the mast raised off the ground. The security of winch anchor under load will be
checked, and mast lifting points checked before commencing the mast erection.

Stage 5: Mast Test Lift

3.15 Before any instrumentation is attached to the mast a dry lift will be carried out to allow
the tube joints to settle and correct any misalignments in the shape of the mast. Once the
full weight of the mast has been taken by the lift anchors the mast is lowered to a working
height. Only then can personnel approach the mast to install instrumentation.

Figure 3: Test lift of mast (with no instrument attached)

6
Stage 6: Instrumentation

3.16 Instrumentation is attached as well as signal cables, data logger, and grounding
conductors. All components are tested prior to lifting.

Stage 7: Rear Guy Replacement

3.17 Before lifting the mast, the rear guys are uncoiled and run through the rear anchor. The
end of the guys are terminated in a loop secured by at least two rope grips, a shackle and
rope extension are connected to the loops to allow control of the mast as it approaches
mast vertical.

Bird Deflectors

3.18 Bird deflectors are fitted to the outer guy wires at specified intervals (typically every five
meters) whilst cables are on the ground.

Figure 4: Bird deflector attached to guy wire

Stage 8: Mast Erection

3.19 The area under the mast will be cleared of personnel, equipment, and vehicles. The area
will remain clear throughout the lifting procedure. The mast will then be raised.

Zones of Safety

3.20 The safety zone for site visitors and inexperienced crew members during the erection of
the mast is beyond the topple distance from the mast base (topple distance comprising
height of mast + 10m).

3.21 Personnel approved by the site manager as competent and experienced in the process of
lowering / raising tilt-up masts are required to work nearer to the mast, in an area of
acceptable risk. This is beyond the gin pole radius (15m) whilst the mast is on the floor,
and outside of the quadrilateral boundary lift anchor to side anchor to mast layout tip to
side anchor and back to lift anchor whilst the mast is being raised / lowered.

7
3.22 If there is any reason for personnel to approach closer to the mast than the boundaries
described above, the mast raising / lowering process must halt and approval agreed with
site manager or the winch operator.

Stage 9: Guy Wire Tension, Side Guys

3.23 It is very important that the correct tension of the side guys is maintained throughout the
lifting process. The side guys hold the mast in the correct alignment while lifting.
Personnel will be stationed at the side anchors to monitor this. The geometry of the site
can cause tension in the guys to change as the mast is lifted. Too much tension may
cause the tower to buckle, or guys to fail. Too little tension will allow the mast to bend or
sway.

3.24 The guys can be adjusted using the rope grips. This must be done one at a time.
Winching must stop while adjustments are made.

Whipping

3.25 The gin stay wires and side guy wires will be continuously monitored to ensure that
excessive tension does not develop. Guy failure during installation will therefore only be
evident on the lift guys. Previous (and rare) experience has shown that guy failure occurs
during the initial stage of the lift when the load is greatest, and that the guys do not travel
beyond the quadrilateral boundary described in the zones of safety above.

Stage 10: Rear Guys

3.26 To support the rear of the mast as it approaches the vertical position, tension must be
applied to the rear guys. This is achieved by means of ropes attached to the end of
alternate rear guy wires. In this way, the mast can be controlled by personnel stationed at
the side anchors.

3.27 Once the mast is vertical, it is held in place by tension in these ropes, while the rear guys
are secured one at a time to the rear anchors. Careful observation of the rear guys has to
be maintained at all times, to ensure free progress of the mast. Any snags or loops must
be immediately rectified.

3.28 Due to the large weight of the gin pole it is necessary to control the rear guy attached to
guy plate 1 with a Tirfor winch (TU8). The guy is run through a turning block on the rear
anchor and run out to the side anchor where the Tirfor is positioned. Tension is applied to
the rear guy using the Tirfor once the mast reaches 450 of tilt, and continuously up to
900. The load on the Tirfor must be enough to maintain the correct shape of the mast and
gin pole as the mast approaches vertical (this is in the region of 600kg). Good
coordination between the winch operator and the Tirfor operator is essential.

8
3.29 It may also be required to control the tension in rear guy 3 using a Tirfor depending on
the site conditions/discretion of the supervisor.

Mast Height 80m

Rear guys to be held with rope (minimum requirement) 1+3+5+7

Stage 11: Final Guy Attachment

3.30 Once all the rear guys have been secured, the remaining guys still attached to the Gin-
pole can be transferred to their respective anchor point.

3.31 Some tension must be maintained at all times on these guys as they are transferred.
Each guy must be firmly attached to the ground anchor before the next guy is removed
from the Gin-Pole.

3.32 Attention must be given to supporting the Gin-Pole weight as the last guy is removed.
This is done by means of a cable grabber and chain hoist. The tension in the last guy is
relieved using the chain hoist and the shackle is then removed. The gin pole can then be
lowered in a safe manner to the ground ready for dismantling. An additional chain hoist is
needed to support the middle gin pole support wire during lowering.

Stage 12: Secure Guys

3.33 The mast is straightened by adjusting the guys one at a time. Once upright and straight,
final security of the guys can be completed.

3.34 Apply security rope grips, three grips to each guy, and carry out final inspection of anchor
points, tighten all fixings, and lock shackles.

3.35 After all guy adjustments have been made, it will be necessary to replace any faulty rope
grips and re-torque all nuts. Ensure at least three wire rope grips are used on each guy,
with the saddles on the live part of the rope, and the U-bolt pressing on the less heavily
loaded tail of the rope. Each rope grip is double checked before leaving the site.

Figure 5: Rope Clipping

9
Stage 13: Instrument Check

3.36 Final tests of instruments and logger are undertaken and then padlocks are fitted as
required.

Figure 6: Instruments being checked and secured

10
4 Avoidance of Adverse Impacts to Ecological Receptors
4.1 The moorland contains a number of important habitats which support valued species of
plants and wildlife.

4.2 Every precaution will be taken to avoid harm and / or damage to vegetation and faunal
species that are known to or may be potentially present.

4.3 This will be achieved by adopting the following.

Avoiding potential disturbance to ground-nesting birds by completing all works,


including decommissioning, outside the bird breeding season (March September). In
the event of works being required within the bird-breeding season a detailed ground
search for nests would be carried out by a suitably experienced ecologist. If a nest is
found no works likely to disrupt breeding would be permitted. Mitigation and avoidance
measures would be recommended as appropriate, which may involve cordoning off
areas until the nests are no longer active.
Immediately prior to the installation of the masts, a walkover survey would be carried
out by a suitably experienced ecologist to carry out a final check for any signs of
species of interest such as badger setts. This could be carried out in conjunction with
the siting of the mast where pegs are put in the ground to identify the working areas
and/or in conjunction with the breeding bird check if works are timed between March
and September,
It is anticipated that any excavations for the dead man anchors will be backfilled as
specified within the same day. However if this is not possible, the excavated area
would be covered overnight to reduce the risk of any nocturnal species such as
badgers becoming trapped.
Existing records of white-clawed crayfish have been provided showing this species to
be present within Dearden Brook on site. The watercourse itself if approximately 100m
south of met mast 1. Whilst no direct impacts will occur as a result of the mast
installation, operation or decommissioning, indirect impacts such as effects from the
access route to/from the mast may occur. Therefore the access route will specifically
avoid any watercourse crossings (except where they already exist). In addition, efforts
will be made to reduce sediment entering watercourses such as avoiding work during
periods of heavy rainfall and micrositing of any anchor points as relevant.
The access to / from the mast locations will follow existing tracks or routes where
possible.
If any species are encountered during the works, such as reptiles, these will be
removed to a suitable safe location as relevant by a qualified ecologist.

11
5 De-Commissioning
5.1 At the end of the period of planning approval, the mast will be removed entirely from the
site. This will be achieved by lowering the mast to the ground and removing all
instrumentation. The tubular sections that comprise the main body of the mast will then
be disassembled and the guy wires removed.

5.2 The methods adopted to safeguard wildlife and the soil resource as part of the installation
would also be followed for decommissioning.

5.3 In summary:

Decommissioning would be targeted outside the bird breeding season. In the event of
this not being possible a detailed search for active nests and any other species that
may represent a constraint would be carried out in advance of works by a suitably
experienced ecologist.
No heavy tracked vehicles would be used and only low ground pressure vehicles.
Works would be confined to service tracks and work areas with no unnecessary
trafficking over vegetation and all movement kept to an absolute minimum.
Intact turves would be cut around the anchors and set aside on geotextile and saved
separately from mineral soil.
The material surrounding the anchor would be removed and / or de-compacted in
order to extract the anchor.
Mineral soil would be returned to the trench and compacted with the excavator bucket.
Turves would be returned to their original position and gently compressed so they are
slightly (about 400mm) above the surrounding ground level to allow for minor
subsidence to avoid a depression in the surface.

12
We are a leading planning consultancy
operating in key development sectors
from offices across the United Kingdom.

Belfast Glasgow
Birmingham Leeds
Bristol London
Cardiff Manchester
Edinburgh Southampton

You might also like