Cash Flow Forecasting Global 1st Edition PGguidance 2013 PDF
Cash Flow Forecasting Global 1st Edition PGguidance 2013 PDF
Cash Flow Forecasting Global 1st Edition PGguidance 2013 PDF
This guidance note summarises what cash flow forecasting is, how to
produce a useful forecast and how to use the forecast to assess Cash flow forecasting
progress on site and assist both employers and contractors to analyse
1st edition, guidance note
actual expenditure against forecast expenditure.
Guidance is given on the cash flow of construction contracts (project
cash flows) and not specifically for the cash flows of companies
(organisational cash flow), although many principles do overlap.
Guidance is given under the following headings which map to the
Assessment of Professional Competence (APC):
General Principles (Level 1: Knowing)
Practical Application (Level 2: Doing)
Practical Considerations (Level 3: Doing/Advising)
rics.org/standards rics.org/standards
Cash flow forecasting
Introduction 2
1.5.1 S-Curve 8
2.2 Identifying the employers brief for the cash flow forecast 9
2.12 Currency 12
2.13 Variations 12
2.19 The need for regular adjustments to reflect progress and events on site 14
3.6 Effect of claims and loss and expense and liquidated damages 18
3.9.1 Traditional versus Design and build and cost reimbursable/target costs 19
Lead author
James Garner (Gleeds Cost Management Limited)
Contributor
David Benge (Gleeds Cost Management Limited)
Working Group
Chair: Andrew Smith (Laing ORourke)
This guidance note generally gives guidance on The quantity surveyor is expected to fulfil the
the cash flow of construction contracts (project following duties, notwithstanding the detailed terms
cash flows) and not specifically for the cash flows of any appointment or contractual obligation:
of companies (organisational cash flow), although
there are many principles that do overlap. Take an initial brief from the employer to
understand their requirements for a cash
Cash flow is the lifeblood of the construction flow forecast.
industry and relates to the incoming or outgoing of
Produce an initial cash flow forecast at the
money to or from a company over a given period
feasibility stage to give the employer an
(usually monthly). Within construction contracts
understanding of their likely obligations.
a cash flow forecast is generally used to inform
the employer so that they know what and when Update the cash flow forecast throughout the
their monetary commitments under the contract design, tendering and contract period.
will be. They can be in the form of long-term or Monitor actual payments against the cash flow
short-term forecasts and these forecasts should forecast and explain any discrepancies.
be constantly updated and revised as better, more
accurate information becomes available or when
variations to the model occur (i.e. non-expenditure
of provisional sums, claims, extension of times).
The cash flow forecast can also be used internally Some of the key details to review are the overdraft
by contractors to monitor their own progress (or level, the frequency that the business is using the
subcontractors progress) or used to assess the overdraft facility and the potential effect if the bank
movement of any float within the programme. removed the overdraft facility. It is also important to
review the companys largest clients and analyse
It takes on extra significance for NEC contracts, the effect of a reduction or omission of business
as the programme and activity schedules are from one or more of these. It is a simple equation
specifically referenced within the contract that must be reviewed is the business bringing
conditions. Therefore, cash flow forecasts that are in as much money (revenue) as it is spending
produced in accordance with these documents, (expenditure)?
can be used by the project manager to assess
any compensation events, early warnings or 1.1.5 Stakeholder management
programme revisions before accepting them. There are very often third parties or stakeholders
While cash flow forecasts can be used to monitor who have a vested interested in the cash flow of
progress on site, both the preparation of the a company or construction contract and often
cash flow forecasts and the valuation have to be for very different reasons. Funders will want to
accurate to ensure comparisons are valid. It goes know that a business is sound and solvent before
without saying that the further along the design and agreeing to loans. Shareholders will be interested
tender process the project is the more detailed and in company performance and ensuring that their
accurate the cash flow forecast will become. annual dividends are as high as possible. This
may impact a companys ability to make decisions
rio t
es rac
lia fect
pe trac
pe ility
wo itati
d
Fe on
b
rio
Co
cil
C
e-
Fa
Pr
Most contracts include a mechanism for either If the project includes materials from other
pre-determined parts of the building to be handed countries then this may affect the contractors
over early (sectional completion) or for previously outward cash flow to the suppliers and
undefined areas to be handed over with the subcontractors, principally if the contracts with
contractors consent if they are completed earlier these subcontractors and suppliers are dependent
than planned (partial possession). If sectional on the exchange rate.
completion is used then it will be relatively
straightforward to factor this information into 2.13 Variations
the cash flow forecast, as dates will be included
against each of the sections within the contract.
Each of these sections will have their own unique Most contracts have a means for allowing
completion dates and retention amounts and variations to the contract, which will change the
periods. This means each section will have its own amount due to the contractor. The cash flow
unique S-curve. The easiest way to deal with this is forecast should therefore make some attempt to
to produce a separate cash flow for each section, include for likely spend on variations. The identified
based on its unique information, and merge them risk allowance can be used for this exercise. If
together to give an overall cash flow. a priced risk register has been produced for the
project then the value of this should be included
The time lag between completed sections will have
in the cash flow. However, if the risk allowance is
an effect on the profile of the overall cash flow. If
all sections complete within a few weeks of each based on a percentage then this should also be
other then it will not have a significant impact on included in the forecast.
the overall development cash flow. If a section As well as having an effect on the price of the
completes significantly earlier than others (i.e. say contract, a variation may also affect the programme
a school has a block finished 12 months earlier than
of the contract. In fact, a variation may have no
the rest of the school), then this will clearly have a
effect on the contract value but could increase the
rather more marked impact.
programme. If the risk allowance is included within
Different sectional completion elements may also the forecast then the employer should be made
have individual retention releases (relative to their aware that the programme effects of any variations
value) and this should be incorporated into the cash are not factored in, as they will be unknown.
flow forecast.
3.0 M 10 M
Periodic
2.5 M
8M
Cumulative
2.0 M
6M
Periodic 1.5 M Cumulative
4M
1.0 M
2M
0.5 M
0M 0M
May
Aug
Mar
Sep
Apr
Oct
Jun
Feb
Jan
Jul
(e) materials off site not taken into account when As a construction development progresses so
producing cash flow forecast should the cash flow forecast. It would be unwise
(f) the inclusion of variations to rely on a forecast carried out at the beginning of
a project throughout the development, particularly
(g) contractor purposely accelerating the works to
if important changes have been made to the
complete earlier (and therefore expending less
design, value or programme (see Figure 7).
preliminaries)
Figure 7: Diagram showing the relationship
(h) the sign of a distressed contractor (or
between the stage of the project and the
subcontractor) or supplier, and
information used in the production of the
(i) cash flow not being accurate in the first place. cash flow forecast
Variations / compensation
Construction events
Claims
Final account Final account
It is essential that the actual payments are analysed delay damages). However, both of these factors
against the forecast and adjustments made to the can have an acute effect on the accuracy of the
forecast as necessary. If a payment has been made forecast.
which differs to the forecast then it would seem
unreasonable to expect the employer to rely on 3.6.1 Claims for loss and expense from
the cash flow forecast for the following payment contractor
without updating it to show the current actual Claims for loss and expense will be made against
situation. an event listed in the contract and will usually also
involve an extension of the contract period. As
3.5 Risk factors inherent in soon as it becomes apparent that a claim may be
construction cash flow forecasting made by the contractor, the employer should be
made aware that the accuracy of the cash flow
The following list gives an indication of the sort of forecast may be compromised. An assessment of
items, which should be considered as potential the likely settlement of the claim should be made
risks to the accuracy of the cash flow forecasts. and the cash flow updated accordingly. This may
This is by no means a definitive list and indeed a involve producing a best-case and worst-case
major risk is the fact that every project is different assessment so that the employer understands their
and comes with its own set of circumstances. potential liability.
While cash flow forecasts are valuable tools they The timing of the claim is also important and will
also come with inherent risks, which must be often depend on the economic circumstances
considered. of the time. It is not uncommon for claims to be
Perhaps the biggest danger comes from the agreed upon many months after the end of the
reliance on a cash flow forecast without proper contract period. In this circumstance the cash
understanding on how it was produced and the flow forecast should be updated regularly so as
limitations of the data that informed it and a failure to inform the client of any slippage in the likely
to adjust the assumptions as circumstances payment of claims. This is also significant as an
change; for example: additional payment may be due to the contractor
some time after practical completion.
(a) effect of changes in design specification may
change sequencing of works, value of works or 3.6.2 Liquidated damages
overall programme of works
If a contractor is late delivering a project through
(b) effect of inflation the value of money may be
no fault of the employer then most construction
different at the time of payment to the time of
contracts will include a provision for the employer
production
to claim liquidated damages from the contractor.
(c) effect of interest and exchange rate This will have the effect of reducing the employers
particularly where supplies or labour are being liability to the contractor but employers should be
sourced from overseas advised not to forecast the benefit of liquidated
(d) complexities of the building the more damages until they have been formally agreed with
complicated and bespoke the building the less the contractor. As liquidated damages are meant to
accuracy that can be placed in the forecast. be a genuine pre-estimate of likely loss then there
should be no real saving to the employer, simply
(e) estimating error, and
a transfer of liability from one source to another.
(f) changes in sequence to mitigate delays. This will affect the construction cash flow but not
necessarily the overall cash flow position.
3.6 Effect of claims and loss and
The cash flow forecast can be used to help paint
expense and liquidated damages a picture when assessing the legitimacy of a
contractors claim. It should be noted that a claim
At the early stages most cash flow forecasts would should be based on determining a series of issues
not pre-empt a claim from the contractor for loss which were out of the contractors control and
and expense, or a reduction of the contract sum that are so defined in the relevant clauses of the
due to the deduction of liquidated damages (or particular form of contract. It is unlikely that an
t
ntrac
accumulation of lots of mini cash flows for each
n co
io
project (this is slightly different in management
truct
contracting and other packaged based routes
cons
es
rvic
d se
s an
where the contractual link is still with the main/ io nal
fee
fess
Pro
management contractor only).
rs f
ee When using an S-curve formula ensure that the
age
st ruct
ion
Man basis of the formula is understood so that an
Con
s explanation of the basis of the S-curve can be
ice
e
rks
am
rv
Se communicated to a client.
Fr
wo
pe
nd
es
lo
+E
ish
ou
ve
ing
Consider cyclical events that will delay payment
En
Fin
Gr
FF
Pil
Time
throughout a construction contract (i.e.
The various overlapping cash flows within a
construction management procurement route Christmas and Easter).
The likely expenditure of risk allowances should
be considered, perhaps by allocating dates to
the project risk register.
Any assumptions and exclusions and any
relevant notes that affects the readers
understanding of the cash flow forecast should
be clearly included.
The information used to produce the forecast
should be included.
This guidance note summarises what cash flow forecasting is, how to
produce a useful forecast and how to use the forecast to assess Cash flow forecasting
progress on site and assist both employers and contractors to analyse
1st edition, guidance note
actual expenditure against forecast expenditure.
Guidance is given on the cash flow of construction contracts (project
cash flows) and not specifically for the cash flows of companies
(organisational cash flow), although many principles do overlap.
Guidance is given under the following headings which map to the
Assessment of Professional Competence (APC):
General Principles (Level 1: Knowing)
Practical Application (Level 2: Doing)
Practical Considerations (Level 3: Doing/Advising)
rics.org/standards rics.org/standards