H130 76-10526-Detail Design: Drainage - Level 2 Part 1

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Key Plan

A
BL
QI
Notes

150mm SWP RISER


TO BELOW

150mm SWP
RISER TO BELOW

E
RWO RWO

A ISSUED FOR TENDER FV BM* AH* 08.03.15

No Revision
Job Project
Drawn Manager Director Date

D FD WITH FUNNEL
WITH 100mm SWP FOR Note: * indicates signatures on original issue of drawing or last revision of drawing
WATER TANK FLUSHING Conditions of Use. This document may only be used by GHD's client (and any other
person who GHD has agreed can use this document) for the purpose for which it was
prepared and must not be used by any other person or for any other purpose.

100mm VP FROM BELOW


WITH VENT COWL Master Developper / Owner

150mm VP FROM BELOW


WITH VENT COWL Abu Dhabi Airports Company PJSC
Planning & Development
PO Box 94449, Abu Dhabi, U.A.E
100mm VP FROM BELOW T: +971 (0) 2 505 5000
WITH VENT COWL F: +971 (0) 2 575 8300

C
100mm VP FROM BELOW
WITH VENT COWL Lead Consultant

GHD GLOBAL PTY LTD


3rd Floor, Guardian Tower, Danet Community
PO Box 45921 Abu Dhabi United Arab Emirates
T 971 2 6968700 F 971 2 4472915
E [email protected] W www.ghd.com

B Specialist Consultant

Fire Life Safety, Planning


and Regulatory Specialist
150mm SWP
RISER TO BELOW

Specialist Consultant

RWO RWO
Third Party
A Operational Advisor

150mm SWP
RISER TO BELOW
1 3 4 5 6 Client
ADAC
Project
MIDFIELD TERMINAL FIRE
2
STATION
Title
DRAINAGE - LEVEL 2 PART 1
SCALE 1 : 100 DRAINAGE SERVICES LEVEL 2
HIGH LEVEL PART 1
Scale 1 : 100 DO NOT SCALE
Drawn F. VILLETE Designer P. MOHD.
Drafting Design
Check Check
Approved
(Project Director)
Date
This Drawing must not be used for Construction unless signed as Approved
Original Size
Drawing No:
A1
DETAIL DESIGN 76-10526- H130 Rev: A
Plot Date: 7/03/2015 10:26:59 PM Cad File No: C:\Users\fvillete\Documents\76-10526_Midfield Fire Station MEP-Central_fvillete.rvt