TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
Exam.
Level
Programme BCE
Year / Part
III / II
Full Marks
80
Pass Marks
Time
32
3 hrs.
Candidates are required to give their answers in their own words as far as practicable.
Attempt All questions.
The figures in the margin indicate Full Marks.
Assume suitable data if necessary.
6. What is a spur? How do you fix the spacing of spur in a bend? Draw neat sketches of plan
and section of a typical gabion spur.
[1+2+5]
7. a) Design a vertical drop for the data given below:
Full supply discharge u/s and d/s = 1.5 m3/s
Drop height = 1.0 m
FSL u/s and d/s = 106.0 m and 105.0 m respectively
Full supply depth u/s and d/s = 0.80 m
Bed level of u/s and d/s =105.2 and 104.2 respectively
Bed width u/s and d/s = 1.10 m
Top width of crest = 0.50 m
b) With definition sketch, write the procedure to fix design parameters of a Non-modular
outlet.