A Risk-Based Shutdown Inspection and Maintenance Interval Estimation Considering Human Error
A Risk-Based Shutdown Inspection and Maintenance Interval Estimation Considering Human Error
A Risk-Based Shutdown Inspection and Maintenance Interval Estimation Considering Human Error
a r t i c l e
i n f o
a b s t r a c t
Article history:
This paper presents a risk-based methodology to estimate shutdown inspection and main-
unit. The methodology presented in this paper addresses to identify the number of shut-
2015
down intervals required to achieve a target reliability over a goal period. The proposed
methodology is the extension of the previously published work by the authors to deter-
mine the shutdown interval considering the systems desired availability. The proposed
work is novel in the sense that a concept of human error during shutdown inspection and
Keywords:
maintenance is introduced while modeling the system failure. Selection of critical equip-
System reliability
ment is the most important aspect in obtaining the shutdown interval to minimize overall
operational risk. In order to achieve this, a risk criticality matrix is proposed to select the
maintenance
critical equipment for shutdown inspection and maintenance. Probability of human error
induced during shutdown inspection and maintenance is estimated using Success Likeli-
hood methodology (SLIM). The proposed methodology is composed of three steps namely,
Failure probability
Consequence
ering human error and nally a risk-based shutdown inspection and maintenance interval
Failure model
estimation. The proposed methodology is applied to a gas chilling and liquefaction unit of
a hydrocarbon processing facility. The methodology is used to ensure the practicality of the
proposed formulation to the real industry. The proposed methodology can be applied to any
plant (process or non-process) such as those for LNG processing, petrochemicals, reneries
or manufacturing plants. The key elements for the success of the proposed methodology are
the identication and selection of critical equipment, breakdown of activities to estimate
human error probability and plant-specic data for modeling system failures.
2015 The Institution of Chemical Engineers. Published by Elsevier B.V. All rights reserved.
1.
Introduction:
Due to continuous production demands, processing facilities are getting not only bigger and bigger but also more
complex in nature. The increase in complexity and size is
inviting maintenance and reliability engineers to put more
emphasis on system inspection and maintenance optimization to minimize unplanned downtime, overall cost and risk
10
2.
Past studies
researchers have introduced concept of imperfect maintenance. Nguyen and Murthy (1981) introduced the concept of
imperfect maintenance considering that the failure characteristic of the system is different (worse) from that of correctively
maintained system to minimize the mean cost rate. Block et al.
(1985) extended Brown and Proschan model and proposed an
age-dependent repairable model considering a probability of
p(t) a complete repair or with probability q(t) = 1 p(t) is a minimal repair, where, t is the age of the equipment in use at
the failure time. Ben-Daya and Alghamdi (2000) presented two
sequential preventive maintenance model considering age
reduction model, an extension of Nakagawas model, while
in the second model, PM intervals are dened such that the
integrated hazard rate over each interval is the same for all
intervals. Levitin and Lisnianski (1999) have used Genetic Algorithm to generalize a preventive maintenance optimization
to multi-state system considering the effective age of equipment. Nakagawa et al. (2012) considered system damages due
to shock (a shock number N) and a damage level k and proposed a preventive model considering imperfect maintenance.
Rangan and Grace (1989) extended Brown and Proschan model
to develop a replacement policy for a deteriorating system
with imperfect maintenance. Li and Shaked (2003) extended
Brown and Proschan (1983) imperfect maintenance approach
to model preventive maintenance and obtained stochastic
maintenance comparisons for the number of failures under
different policies via a point process approach. Malik (1979)
introduced the concept of improvement factor assuming that
maintenance action changes the system time of the failure
rate curve and the failure rate post maintenance lies between
as good as new and as bad as old. Brown and Proschan (1983)
reported that some possible causes for imperfect, worse or
worst maintenance due to the maintenance performer, such
as repair the wrong part, only partially repair the faulty part,
repair the faulty part but damage the adjacent part, are the
true contributor. Nakagawa and Yasui (1987) reported that
hidden failures which are not detected during the maintenance, human errors such as wrong adjustment and further
damage done during maintenance and replacement with
faulty parts. Dhillon (1986) reported that operation, assembly design, inspection, installation and maintenance are all
prone to human errors. These errors are due to poorly written
maintenance procedures, complex maintenance tasks, harsh
environment, fatigue, outdated maintenance manual, inadequate training and experience. Dhillon and Liu (2006) reported
that reasons for the occurrence of human errors including
inadequate lightning in the work area, inadequate training
or skills of the manpower involved, poor equipment design,
high noise level, an inadequate work layout, improper tools
and poorly written equipment maintenance and operating
procedure. They further classied human errors into six categories: (1) operating error (2) assembly error (3) design error
(4) inspection error (5) installation error and (6) maintenance
error. Dhillon and Yang (1995) cited that failure of repairable
system can occur not only due to hardware failure but also
due to operating human error or maintenance error. Factors
such as temperature, dust, fatigue, incomplete or inappropriate maintenance tools, errors in inventory and personal
problems may be the contributor for these errors. Noroozi et al.
(2014, 2013) used Human Error Assessment and Reduction
Technique for evaluating human error risk assessment and
applied to pre- and post-maintenance procedure of a process
facility and has also applied Success Likelihood method (SLIM)
to perform human factors analysis in pre- and post-pump
11
3.
A risk-based inspection and
maintenance modeling considering human
error
Although several studies have been published on inspection
and maintenance interval modeling and optimization in the
literature as discussed above, a majority of these works deals
with addressing the individual equipment. Consideration of
shutdown inspection and maintenance modeling is found to
be limited. Hameed et al. (2014) and Khan and Hameed (2014)
has proposed a risk-based shutdown interval modeling for
continuous operating facilities. These modelings are based on
the assumption of the perfect maintenance. In reality, majority of the time inspection and maintenance does not meet the
perfect conditions and fall short. The result of imperfectness
is induced due to the contribution of human errors. Errors
induced during inspection and maintenance may be realized
immediately and result in the premature failure of the equipment or system or in some cases may lie dormant with the
equipment or system for some period of time, until a combination of other factor accelerate the degradation mechanism and
lead to a failure. Sometime these have resulted in serious accidents in process industries. The proposed model is developed
considering the human error which may be induced during the
shutdown inspection and maintenance and is the extension of
Hameed et al. (2014) and Khan and Hameed (2014). The objective of this paper is to integrate human errors in the system
failure model and to interlink this with the operational risk.
Higher the probability of failure of inducing the human error
in inspection and maintenance, the degradation or the system failure probability will be more impacted. The proposed
12
Fig. 1 Risk-based inspection and maintenance interval optimization model considering human error.
shutdown inspection and maintenance methodology is broken down in three modules and shown in Fig. 1. Assumption
in developing the model as well as detail of each module is
described below.
3.1.
A group of equipment which cannot be inspected or maintained without taking the plant into non-operational mode
(shutdown).
Failure as a time-dependent process.
Material, labor, specialist and production cost are available.
The degree of imperfectness is assumed to be a number
between 0 and 1 due to human error while performing
inspection and maintenance.
Sufcient manpower and equipment are available to execute the planned job.
Inspection and maintenance durations are non-negligible.
3.2.
Module 1: equipment selection considering
criticality of operation
A processing facility consists of a large number of interacting systems or equipment. When these system or equipment
13
3.3.1.
Frequent
Probable
Occasional
Remote
Extremely unlikely
>0.1
0.0010.01
0.00010.01
0.000010.0001
<0.000001
(1)
3.3.
Module 2: component/system failure modeling
considering human error
Failure characteristics of the component or system are one of
the most important parameters used to analyze and model the
system failure or behavior. Since failure of a system is a probability, the rule of probability theory may be applied to compute
the system failure probability from knowledge of component
or system characteristics.
Rsys (t) =
n
R (i ) R
i=0
t
n
i
(2)
i=0
where,
(1) t >
n
i
i=0
14
tup
td
TSD2
tup
TSDn
TSD3
td
tup
td
tup
Td
Rjk Wj
(3)
(4)
td
15
Fsys (t) = 1
n
R (i ) R
i=0
p=
m
(1 HEPk )
(5)
k=1
Rsys (t) =
n
R (i ) R
i=0
t
n
i
i=0
n
(1 p)
(6)
i=1
3.4.
Module IIIrisk-based shutdown interval
estimation
Too frequent inspection and maintenance of equipment or
system will increase not only the loss in revenue but also the
overall operational risk exposure due to possible human error
introduction in the system. On the other hand, an optimal
inspection and maintenance interval will not only help to have
better utilization of the inspection and maintenance resources
but also reduce the risk of increased failure. It is necessary to
express the probability of failure for a piece of equipment or a
system as a function of time for risk-based shutdown inspection and maintenance interval estimation. In order to develop
a risk-based shutdown inspection and maintenance interval,
system failure probability considering human error and consequences are required to generate the overall risk exposure
and are discussed below.
3.4.1.
(7)
t
n
i=0
i
n
(1 p)
(8)
i=1
3.4.2.
16
Due to heat ux
Due to Overpressure
Due to heat ux
Due to overpressure
(ECAL)x = (PDHF)x AD
ECAL = PDOP EZ AD
(ECHHL)x = (PIHF)x PD CF
ECHHL = PDOP EZ PD CF
ECPL = SDT PL SP
Cp(i) = Clp tp ,
CI (i) = ClI ti + CIe ti ,
Cm (i) = Clm tm + Csp ,
Cts(i) = Clts tts ,
ECSI&M(i) = Cp(i) + CI(i) + Cm(i) + Cts(i) .
ECT = Max (ECAL+ECHHL)i +
n
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
ECSI&M+ECPL,
i=1
3.4.3.
Risk estimation
Since the risk is a combination of probability and consequence, one needs to consider all possible consequences,
including safety and health, operational and non-operational
consequences. In this paper, risk is estimated in terms of ($)
value due to all possible combination and can be written as:
n
n
ECSI&M
4.1.
Module 1: equipment selection considering
criticality of operation
SDi=1
ECPL
(20)
SDi=1
4.
The application of RBSIM to a LNG
processing facility
Snmez et al. (2013) reported that energy plays a fundamental role in both manufacturing and services, and natural gas is
rapidly becoming a key energy source worldwide. Since the last
few decades, liqueed natural gas (LNG) plants are increasing in number due to the growing demand for natural gas to
17
4.2.
Module 2: integrating human error in reliability
modeling
A functional block diagram is developed for the selected
critical equipment and is shown in Fig. 8. System failure
probability is calculated using the block diagram from the
Shape parameter ()
282,000
4.38
450,000
2.0
18
E01
E02
E03
E04
E05
Internal PSF
Stressors
Training
Experience
Knowledge of performance standards
Stress (mentally or bodily)
Work memory
Physical condition
E06
Rank
Training
Experience
Time pressure
Work memory
Work environment
5
4
3
2
1
Weight
0.20
0.25
0.20
0.15
0.20
Task description
HEP
0.001594
1.47E-05
0.00029
0.00029
1.47E-05
1.47E-05
1.47E-05
0.000359
0.010839
1.47E-05
1.47E-05
1.47E-05
1.47E-05
0.010839
5.07E-06
0.010839
1.47E-05
1.47E-05
1.47E-05
19
E01
E02
E03
E04
E05
E06
4.3.
Module IIIrisk-based shutdown inspection and
maintenance interval
Module III of the proposed methodology consists of estimating system failure probability, all possible consequences due to
process unit shutdown and nally developing a risk prole to
nd the optimal shutdown inspection and maintenance intervals. Since system failure probability is the function of time,
it is modeled here using Weibull distribution. To calculate the
system failure probability, the Weibull distribution parameters of the equipment are used as discussed in Module II, thus
the system failure probability function can be written using
Eq. (8). Considered gas chilling and liquefaction unit is used
to process hydrocarbons and operates at higher pressure and
cryogenic temperature conditions, the consequences of failure will be very high. Failure scenario considered to estimate
the asset damage and human health loss for these equipment
is the release of hydrocarbon which upon nding an ignition
source may result in explosion which could generate shock
waves. Calculated shock waves are then transformed in to
probability of damage due to shock wave for various effected
zones. This shock wave may cause serious asset damage as
well as human injury or fatality. In this particular scenario,
estimated consequence is based on a radius of 200 m and is
listed in Table 8. It is important to note that the loss of life
or injury suffered by the people is hard to estimate in dollar value; however, the cost associated with the compensation
and corporate liability needs to be taken into account in consequence analysis. In this regard, published note from Judycki
(1994) of the US Department of Transportation and the Federal
Highway Administration published relating the injury scale
(in terms of severity) to the comprehensive costs in policereported crashes is used. In this paper, the production loss
estimated using Eq. (13) for 10 days of shutdown is considered.
Plant-specic data and eld engineer supports to estimate
number of manhour, labor and equipment cost is considered
to estimate economic consequence of each shutdown inspection and maintenance interval.
The total calculated consequence along with Eq. (20) is used
to generate the expected risk prole to determine the total
number of shutdown intervals. Fig. 9 show the obtained risk
prole to achieve optimal shutdown inspection and maintenance interval, which would enable a level of 95.0% system
reliability for a desired goal time while meeting the risk
exposure to the lowest level. The shutdown inspection and
maintenance interval is obtained from Fig. 9. A sensitivity
analysis is performed to study the effect of the number of
shutdown days on the shutdown interval model. The results
are plotted in Fig. 10. It is evident from Fig. 10 that operational risk prole is increasing or decreasing with the increase
or decrease of shutdown duration, due to the impact of production losses; however, the number of shutdown required
5.
Conclusion
Shutdown inspection and maintenance activities are performed to increase the availability and reliability of facility by
selecting the critical equipment to optimize the overall risk
prole. Risk assessment integrates the system failure probability and consequences. A risk-based shutdown inspection
and maintenance helps to select the critical equipment and
systems which cannot be inspected or maintained without
20
References
Alsyouf, I., 2007. The role of maintenance in improving
companies, productivity and protability. Int. J. Prod. Econ.
105 (1), 7078.
API, 2009. Risk Based Inspection; Recommended Practice 580,
Second ed. American Petroleum Institute, Washington, D.C.,
USA.
Backlund, F., Hanu, J., 2002. Can we make maintenance decision
on risk analysis? J. Qual. Maint. Eng. 8 (1), 7791.
Ben-Daya, M., Alghamdi, A.S., 2000. On an imperfect preventive
maintenance model. Int. J. Qual. Reliab. Manag. 17 (06),
661670.
Bertolini, M., Bevilacqua, M., Ciarapica, F.E., Giacchetta, G., 2009.
Development of risk-based inspection and maintenance
procedures for an oil renery. J. Loss Prev. Process Ind. 22,
244253.
Block, H.W., Borges, W.S., Savits, T.H., 1985. Age dependent
minimal repair. J. Appl. Probab. 22 (2), 370385.
Brown, M., Proschan, F., 1983. Imperfect repair. J. Appl. Probab. 20,
851859.
Dey, K.P., Ogunlana, S.O., Gupta, S.S., Tabucanon, M.T., 1998. A
risk-based maintenance model for cross-country pipelines.
Cost Eng. 40 (4), 2431.
21
Sarkar, A., Behra, D.K., 2012. Int. J. Adv. Res. Eng. Appl. Sci. 1 (2),
2038.
Snmez, E., Kekre, S., Scheller-Wolf, A., Secomandi, N., 2013.
Strategic analysis of technology and capacity investments in
the liqueed natural gas industry. Eur. J. Oper. Res. 226 (1),
100114.
Swain A.D., Guttmann H. E., (1983); Handbook of Human
Reliability Analysis with Emphasis on Nuclear Power Plant
Applications; NUREC/CR-1278, U.S. Nuclear Regulatory
Commission, August 1983, with Addendum #1 to
NUREC/CR-1278, August 1983, September 1, 1985, by A. D.
Swain.
Toriizuka, Takashi, 2001. Application of performance shaping
factor (PSF) for work improvement in industrial plant
maintenance tasks. Int. J. Ind. Ergon. 28 (2001), 225236.
Tan, J.S., Kramer, M.A., 1997. A general framework for preventive
maintenance optimization in chemical process operations.
Comput. Chem. Eng. 21 (12), 14511469.
Vatn, J., Hokstand, P., Bodsberg, L., 1996. An overall model for
maintenance optimization. Reliab. Eng. Syst. Saf. 51,
241257.
Vaurio, J.K., 1995. Optimization of test and maintenance intervals
based on risk and cost. Reliab. Eng. Syst. Saf. 49, 2336.
Wang, Y., Cheng, G., Hu, H., Wu, W., 2012. Development of a
risk-based maintenance strategy using FMEA for a continuous
catalytic reforming plant. J. Loss Prev. Process Ind. 25,
958965.
Wilson, L., McCutcheon, D., 2003. Industrial Safety and Risk
Management. The University of Alberta Press, Edmonton,
Alberta, Canada.
Zhaoyang, T., Jianfeng, L., Zongzhi, W., Jianhu, z., Weifeng, H.,
2011. An evaluation of maintenance strategy using risk based
inspection. Saf. Sci. 49, 852860.