PURPOSE
SCOPE OF WORKS
STEP OF WORKS
QC INSPECTION
ATTACHMENT
1. PURPOSE
The purpose of this Work Method Statement for Drywall Partition of Building is to outline and describe in detail
the procedure such as setting and lay-out plan on actual location, installation of drywall and all other related
activity. Inform all concerned supervisor including workers the value and importance of this activity prior to
implementation. This activity should be performed with strict compliance and implementation of Safety
Requirements & Procedure and project specifications to complete the Drywall Partition Works.
2. SCOPE OF WORKS
The scope of this Work Method Statement covers all the works in any Project
Especially for Central Control Rooms in substation building and general building Drywall Partition as follows:
6 Doorways
The head is formed with U channel, bent back and screw fixed with Wafer Head Jack point screws to the studs.
For doors weighing up to 50kg, fully boxed C studs are used for the frame openings inserted with treated timber
of 38mm thickness, cut to the size of stud.
3.
7 Boarding
All boards should be offered up to the frame with the face of the board outwards and secured with drywall
screws at 300mm on centers. Fixing centers should be reduced to 200mm at corners.
Boarding should commence at one end and work across the partition. At head, foot and abutments, board
edges should be added on to continuous beads of sealant. Board joints in multiple layers should be staggered
both vertically and horizontally by at least 600mm.
3.