AirportInfrastructure PDF
AirportInfrastructure PDF
AirportInfrastructure PDF
Infrastructure
Contents
3
9
27
New Bengaluru
International Airport
39
43
51
Airport Mosaic
55
Mumbai International
Airport Ltd (MIAL)
A World-class Airport for Mumbai will also be
ready in 4 years. L&T has been entrusted with
View of the Passenger Terminal Building as seen from the Air Traffic Control Tower
10
Aerotropolis
A Jet Airways flight parked on the apron during the trial run operations
11
12
Resources
Total Man hours (workmen)
3200 Nos.
78 Nos.
6 Nos.
Major Quantities
Concrete
64,500 Cum
Formwork
2,28,500 sq.m
Structural steel
4,400 tons
Rebar
9,500 tons
Roofing
42,500 sq.m
Flooring
97,000 sq.m
Cladding
52,000 sq.m
Glazing
29,500 sq.m
False Ceiling
64,000 sq.m
13
Passenger Terminal Building showing the beautiful temple leaf pattern roof,
circular columns, check-in counters, etc.
Berhad, the Andhra Pradesh government, and the
Airports Authority of India.
Equipped to handle 7.2 million passengers in 2008,
the airport (without any expansion) is expected to
handle 12 million passengers by 2010, subsequently
scaling up to 40 million in the final phase. The
corresponding figures for cargo handling is expected
to touch 1.0 million tonnes from its present 1.0 lakh
ton capacity.
The airport is South Asias first A-380 aircraft
compatible and has Indias longest runway at 4,260
metres.
The passenger terminal building having an area
of 1.17 million sq. ft. is capable of handling twelve
million passengers per annum. It is provided with
42 stands consisting of 12 contact boarding bridges
and 30 remote stands. There are 130 check in
counters with common user terminal equipment
(CUTE), 16 self-check-in- kiosks, 46 immigration
14
Airport Village
For the first time in the country an "Airport village"
has been created between the terminal building
and the public land side at level D. This consists
of a shopping arcade with a wide variety of stalls
and food courts to serve as a place for people to
"meet and greet." Those not using the airport can
also drop in here for shopping.
This apart, there is a uniquely designed retail area
inside the terminal building based on the walkthrough concept that enables customers to move
from one shop to another without having to walk
in and out of shops. Moreover, plans are afoot for
L&Ts Contribution
L&T secured two major contracts, against
international competitive bidding at GMR Hyderabad
International Airport, for the construction of:
15
Design Principle
The basic design of the passenger terminal building
is simple, attractive and loose-fit. The fluid design
is such that sequences of spaces are provided to
facilitate easy and comfortable movement and
orientation. This spaciously designed PTB ensures
rapid transit between its Domestic and International
concourses. In fact it has everything that gives one
the out-of-the-ordinary feeling. The roof, designed
as a Temple Leaf Structure, enables the natural
light to filter through. Built with modular construction
technique, the passenger terminal building has 16
skylights and this reflects the distinct Indian culture.
L&T fabricated and erected the 75m long 3m high
trusses for the erection of 40,000 sq.m Kalzip roof.
Kalzip Roofing
Another salient feature of the Passenger terminal
building is the Kalzip roof.
ATC tower
The tower structure is of 75m height with conical
shape. ECC encountered many difficulties in arriving
at the shape on ground due to the complexity in
design both architectural and structural.
The RC shaft of the tower structure up to 54m height
part was completed using Climbing formwork. The
conical portion of the tower commences from 5m
level and tapers outside from there till it reach 75m
level. The construction imposed several challenges
an working at such a height.
16
First in India
Airport village, a new concept introduced for the
first time in India, is the place for retail, restaurants,
supermarkets outside the passenger terminal
building in level D. The 40,000-odd sq.ft. covered
village with free entry is also the place where visitors
can meet, greet and see off passengers.
Access Roads
Incoming vehicles in to the airport can find its way
in to 3 different levels as per ones requirement.
Passengers reaching the spacious car park at the
ground level can take both the ramp or the elevators
and reach either level D to pick up the passengers
or go for a shopping spree at the airport village.
From here one can reach the departure lounge in
level F through elevators.
17
Scope of Works
The scope of works involved detailed design,
working drawings, shop drawings, construction,
production, assembling, installation, testing,
commissioning and integration of all works for
the airside and landside facilities. In brief this
involved:
18
Landside works
Main access roads 8.4 km
Traffic loop in front of terminal building including
upper and lower traffic forecourts.
Parking areas inside the traffic loop 2 lakh
sq.m
Road systems to other airport facilities
Connectivity road from NH7 to Airport main
access road
Storm water drains for landside roads and
other areas
Utility corridor and trenches connecting various
buildings and facilities
All utilities on the landside and airside
D G emergency power station
Construction also included some of the other
major Buildings, such as:
Cargo terminal
Crash and fire rescue (CFR) stations
Ground handling equipment and maintenance
facilities
Water treatment plant and Sewage treatment
plant
Engineering building for airline operators
Building for ground handlers Menzes & Air
India - SATs
Miscellaneous buildings such as substations,
pumping station and gate houses.
Miscellaneous Works
11 km airside/landside boundary wall
Upgradation of 9 km boundary wall to BCAS
spec
Airside fire drill facility
Operations
facilities
and
maintenance
equipment/
Electro-mechanical services
This involved execution of the Fuel Hydrant
System, which included:
11 km of 18 dia piping with 3 layer polyethylene
coating and lining.
58 fuel pit valves.
14 drains and 14 vents.
Entire piping pressure tested with JETAI fuel
@ 30 bar for 24 hrs.
19
230 TR cassette
buildings.
units
for
engineering
16 km of piping.
Security Equipment:
40 external hydrants.
HVAC
Heating, Ventilation and Air conditioning for the
ALS package involved:
20
- 37 lakh Cum
Embankment
- 32 lakh Cum
GSB
WMM/FCR
Asphalt
DLC
PQC
Structural Concrete
Filling
- 560000 Cum
Shutterring
- 275431 sq.m
Concrete
- 140000 Cum
Rebar
- 4300 tons
Structural Stee l
- 1100 tons
Roof Sheeting
- 16000 sq.m
Tile Flooring
- 4880 sq.m
Mandatory Requirement
- This included:
Kotah Flooring
- 2596 sq.m
Painting
- 29000 sq.m
Textured Painting
- 29156 sq.m
False ceiling
- 6664 sq.m
Water Proofing
- 23163 sq.m
Glazing works
- 650 sq.m
Doors
- 390 Nos
Al joinery works
- 4743 sq.m
Masonry
- 17894 Cum
2 Pug mills
3 Stationary Crushers
1 mobile crusher
Excavators at peak
- 30
- 120
Sensor pavers
- 4
- 1
Motor grader
- 10
Rollers
- 25
Manpower
200 Staff including approximately
6000 labourers at peak.
21
Runway
22
365,695 Cum
59,296 Cum
89,088 Cum
16,586 C um
15,722 Cum
6,812 Cum
12,642 Cum
Sreechand Sreedhar
Engineering Co-ordinator
with inputs from
M.R. Choudhary (CM-B&F)
Vijayakumar (CM-BUCC)
Manish Agarwal (CM - R&R)
23
24
centreline
lighting,
edge
lighting
25
26
27
28
Close-up view of shell roof elements and the glass facade at the entrance
to the Passenger Terminal Building
friendly air-traffic. The runway is designed and built
to ICAO standards and it is compatible for B-747
aircrafts.
Of the total 4,000 acres of land, around 2,000
acres are occupied by the runways, terminal
buildings, air traffic control tower, parking bays
and other structures. The remaining land is used
for other related infrastructure including phaseII expansion, extended air cargo terminals and
cold storage including hotels, landscaping and
horticulture facilities.
The air traffic control tower attracts every visitor as
one approaches the airport and this leads you in
to the sprawling transparent passenger terminal
building with its beautiful parking bays, ticketing
counters, reception and spacious visitor lounges
before one enters the departure bays.
29
30
31
Site Preparation
Site preparation involved site grading and clearance
of thick bushes as well as putting up temporary
structures including major earthwork excavation to
the tune of 70,20,000 Cum.
Airside Infrastructure
Building the airside infrastructure involved
construction of a 4000 meter long 60 meter wide
asphalt paved runway including 7.5m shoulders
on either side; 1,80,000 sq.m of allied taxiways;
3,66,000 sq.m of aprons with rigid pavement,
aircraft isolation bay and the civil works for the
airfield lighting. The runway is designed to cater to
B-747 aircraft.
View of the Passenger Terminal Building as seen from the car park
32
he Unique S shaped precast concrete roof element used in the passenger terminal building at
Bangaluru International Airport called for special techniques for fabrication and erection.
Since the project required a large number of roof elements, to begin with a dedicated production yard
had to be established near the terminal building with necessary facilities like casting moulds, handling
equipments like gantries for lifting and placing etc. Precast elements were produced using custombuilt steel moulds with near zero deflection, employing prefabricated reinforcement cage and self
compacting concrete. After pre-stressing, elements were shifted to storage area by high speed long
stroke hydraulic jacks. From storage yard, elements were transported by a special trolley to the terminal
building site for erection after attaining the required strength.
Lifting and placement of each element was carried out by custom built two tier portal gantry cranes.
While the lower gantry facilitated lifting of elements by top level gantry directly from the shifting trolley,
this also enabled shifting the top gantry to next bay after completing the erection in each and every
bay. Similarly, the top gantry equipped with strand jacks, carried out the lifting of element from trolley,
moving it and placing the same in its final position including alignment in one single operation. The most
challenging aspect of erection was the handling of delicate elements, each 24m long and placing them at
a height of 19m with a clearance of only 25mm. To ensure safe & trouble free operations, the entire set of
erection equipment was load tested before commencing the
erection works. Moreover, the entire production and erection
scheme was devised in such a manner, that no element was
over stressed at any stage during the erection operation.
Yet another significant aspect of this innovative erection
method included the elimination of high capacity lifting
cranes and avoidance of any type of modification to the
main structure. This apart, every major activity was
automated using hi-speed hydraulic jacks resulting in
optimum cycle times and reduced manpower. Using this
technique, a total of 234 elements were erected in a short
span of five months with an average of 2 elements per day.
The complete erection methodology including the design of
enabling structures was done in-house by an expert team
of Construction Method engineers. Meticulous planning
in design of enabling structures coupled with automation
of activities ensured that the fabrication and erection of
roof elements were completed ahead of schedule with
excellent quality standards, setting a new benchmark for
similar works in future.
K. Senthilnathan
Head (EDRC - Transportation & Infras)
33
Construction Marvel
The passenger terminal building (PTB) is an
outstanding example of marvellous construction
by L&T. Having a floor area of 71,000 sq.m and
built in three levels, the PTB is specially created
for a hassle-free flow of passengers. The terminal
building is 218m long, 147m wide and 15.7m high
and at peak, this can handle more than 2700
passengers at a time.
34
Terminal parking
A beautiful car park in front of the terminal building at
the ground level has been developed with aesthetic
landscaping and garden provided with fountains,
etc. for the convenience of passengers and visitors
to the airport.
Ancillary Buildings
The strategically located Air Traffic Control (ATC)
Tower having a height of 65m enables complete
view of Airside Operations for all Phases of the
Airport. It is one of the few Airports which have the
Tower on the landside. In addition to the above
infrastructure, a number of ancillary structures have
been constructed to meet various requirements for
the operation of the airport. This includes:
A three level Administration/Canteen/Security/
Technical Block (5260 sq.m),
35
Mr. K.V. Rangaswami, President (Construction) and Member of the Board L&T (second from right)
along with L&T colleagues after successful completion of trial run of commercial flights at the New
Bengaluru International Airport.
36
Air side view showing an aircraft being docked to a passenger boarding bridge
Maintenance Buildings Civil & Electrical and
Mechanical (2909 sq.m),
Aircraft Rescue and Fire Fighting Building (1457
sq.m),
Ground Support Equipment Building (1984
sq.m),
Other Buildings DG Power House, Main Power
Substation, Compact Stations, Navaid Buildings
(4107 sq.m),
VVIP terminal (282 sq.m),
Watch towers (145 sq.m),
Security cabins (75 sq.m),
Public amenities (326 sq.m)
Landside Infrastructure
A four lane main Access Road
Secondary access road
Access roads to buildings
Car park and bus park departure car dropoff for 100 vehicles Arrival car pick-up for 58
vehicles Car park for 1550 vehicles, Bus bay for
10 vehicles includes Private Taxi Parking.
Traffic Loop in front of terminal building
1.3 km of main access road connecting trumpet
flyover outside the boundary
Civil works for electrical services
37
Future Opportunities
Miscellaneous Works
Trumpet flyover
5 star hotel with 321 rooms, restaurants and a
world class spa.
K. Sridharan
CCD-ECC HQ,
Chennai
38
39
40
41
42
since
October
2003.
The
Radio
Perspective view of the T-3 passenger terminal building under construction at IGIA, New Delhi
43
A section of the existing Terminal Building at the Indira Gandhi International Airport, New Delhi
44
Project Background
45
46
Scope of Works
Phase 1A
Construction of new run way 11R/29L to 4430m x
60m along with a parallel taxiway and connecting
rapid exit taxiways.
Remote Aprons
To be constructed to provide the additional stands
required due to the new runway.
Airfield Ground Lighting and Power Supply
The navigation lights on the runway, taxiway and
the aprons for navigating the aircrafts to the landing
and stands
Satellite Rescue & Fire Fighting
Facility housing airport rescue fire fighting facility
with high speed/foam appliances available all time
to reach any part of aircraft operational surface
within 3 minutes of fire accidents.
Precast Boundary Wall
To secure the runway and taxiway and form the
boundary between airside and landside including.
Storm Water drainage and Sanitary Drains
Phase 1B
Passenger terminal building (T3) catering to
47
The project also forms a glorious example of interdivisional camaraderie where L & T Infotech is
lending its expertise in IT design and converting
user requirements into vendor specifications.
Current Status
- Contact Aprons
- Twin Parallel Taxiway
48
Project Organization
49
Phas 1A - Remote Apron 301 to 305 stands handed over & operational
50
R. Shankar Narayanan
Planing Manager
Chhatrapati Shivaji
International Airport (CSIA)
51
52
Overall view
Interior view of
gate pier
53
GVK
About MIAL
Mumbai International Airport Pvt. Ltd. (MIAL) is a
joint venture between the GVK-SA consortium and
Airports Authority of India. MIAL was awarded the
mandate of modernizing and upgrading Chhatrapati
Shivaji International Airport (CSIA) in April 2006.
54
Airport Mosaic
55
56
and
Terminal building
and control tower at
Puttaparthi Airport
Runway at
Puttaparthi Airport
Indira Gandhi
International Airport,
New Delhi
57
Executed Complete
infrastructure works.
Airfield
and
other
completed
and
58
Indian Airlines
Hangar, Mumbai
59
60