Project Closeout Management
Project Closeout Management
Project Closeout Management
Introduction
Nobody gets excited about project closeout management. That isnt to say that nobody
wants to complete their projects, or that people dont want to judge how successful projects
have been. Its just that the associated routine (or process) and paperwork never seem as
important as the myriad of other things that a project manager and her team must do as a
project, or a stage of one, is being closed. The work has been done, the customer has what
he wants, and everybodys mind is moving on to the next project or challenge.
Project managers, project sponsors, and project team members alike will readily
acknowledge the importance of project closeout management. The logic is unassailable. If
adequate product records are not kept, whole-life costs of the product are likely to increase.
If there is no deep and thorough understanding of where reality has diverged from plans,
there is little hope of making better plans next time. If time is not taken to reflect on the
lessons of the past, the likelihood is that similar mistakes will be made in the future. If project
relationships are not brought to a satisfactory closure, unresolved issues and resentments
may smoulder beneath the surface, ready at any time to erupt with unpleasant
consequences. And yet none of these arguments is enough to change peoples attitudes
toward and responses to project closeout management.
This paper will review the following:
9
Steps that organizations can take to improve the practice of project closeout
management.
Harvesting
the benefits
Finishing
the work
Handing over
the product
Gaining
acceptance for
the product
Reviewing how
it all went
Doubt his or her ability to deliver the benefits from the product or service on
which the business case was built, and there will no longer be anyone else
with whom to share the blame.
Be receiving adverse comments from end users who were never convinced of
the merits of the project in the first place.
Have come to realize in the course of the project that what they really want
isnt the product or service that the project has delivered, and as long as no
acceptance has been signed, it might be possible to improve the match.
So planning for project acceptance needs to start much earlier in the life of the project
ideally during project initiation.
The criteria by which benefits of the product or service will be measured or assessed
are clear.
The post-implementation review has a somewhat different focus. Its purpose is to establish
the extent to which the product of the project is delivering the anticipated benefits. The
review is likely to be based on a comparison between actual operating benefits being
harvested and those predicted in the business case for the project. The focus is on the
product in operation and the impact on benefits of decisions made during the establishment
and execution of the project.
Similar to the lessons-learned review, the results should be communicated widely to the
appropriate audience.
Ending relationships
The seventh and final element of project closeout management is ending relationships, or
disbanding the project team. As tasks come to an end, resources can be released in an
orderly fashion. In the case of people who work for the same organization as the project
manager, they can return to their own line or functional department in order to take on other
tasks. In the case of contractors and suppliers, it is important that contracts are closed to
prevent unnecessary work being charged to the project after it has formally ended.
Two aspects of saying goodbye are importantcelebrating and providing feedback. At some
time when the memories of the project are still fresh in the minds of the project team, some
form of celebration such as a party can help team members move on from the past to their
future assignments with a sense of closure regarding the completed project. This is an
important social dynamic.
The second aspect is equally important, and just as often ignoredpeople need to
understand their own contribution to the projects results. Appraisals with each team member
are the means by which a persons own perception of their contribution can be checked
against that of the project manager. In an organization where much of the work is carried out
in projects, this can be the only feedback available to the persons line or functional manager
on which development plans and career opportunities can be assessed.
Executives,
managers, or
sponsors
Customer or
Sponsor
Project being
closed
Project or stage
Project being
started
Closeout
activities
Lessons
learned
Startup
activities
New project or
stage
Members of
other live
projects
Project team
Project closeout management carried out well will give people the chance to learn lessons
while they are still fresh in the memory and while the context is well understood.
Conversely, the lack of effective project closeout management can lead to the demotivation
of team members, who can easily feel that their contribution was not valued, and that the
organization has no interest in learning from their experience.
While survey after survey points to the high social and economic cost of project failures,
project closeout management becomes the focal point for understanding the particular
circumstances that led to success and/or failure on each specific project. Yet, in spite of this,
project closeout management remains one of the least well executed of project management
activities.3
How can this be? As a philosopher once said, Those who cannot remember the past are
condemned to repeat it.4 What prevents organizations from applying common sense in such
an important area? The next section will examine possible answers to this question.
Getting paid, or getting closure, drives all closeout actions. Unresolved issues and
incomplete tasks that frustrate customers and users drag on while the project
manager hopes they will eventually go away.
Acceptance becomes acrimonious; with the project team doing the minimum they
have to in order to get the signature, the acceptance certificate (or its equivalent)
being signed grudgingly, and relationships are ultimately soured or severed.
Companies feel that they dont have time to complete post-project reviews correctly.
The project team is busy on the next urgent project, and there just never seems to
be the time to fit the meeting into a crowded schedule.
The task of completing project records is assigned such a low priority that drawings
are never completely finished, archives are never closed off, and so on.
Lessons learned may be noted, recorded, and even filed, but they arent learned.
Sometimes a politically correct story about the project gains acceptance in corporate
folklore.
Why it should be this way becomes understandable when the following formidable array of
barriers to effective project closeout management is considered:
9
Completing records is a distraction. There are already too many important activities
that obviously add value and clamour for attention.
Closeout activities cost money, and in the final stages, it is easy to see that money
can be saved simply by not doing them. If the project lost money or cost more than
expected, why should good money be thrown after bad? If the project went well,
there probably isnt much to be dealt with, anyway.
There is a widespread myth that learning is a personal activity, and so the lessons to
be learned from the project will be available to the organization informally through
the experience of the project manager and project team members.
While most project organizations pay lip service to the importance of project closeout
management, there are rarely any tangible or emotional/psychological rewards given
to people who pay particular attention to this aspect of project management. The
folly of asking for x while rewarding y may be acknowledged, but instances of it
abound.
While many organizations acknowledge the importance of projects and their success,
they frequently underestimate the extent of the difference necessary between
thinking about on the one hand projects and on the other hand either operations
(repetitive processes) or tasks (simple activities). As a result there is often
insufficient attention paid to the unique difficulties of creating organizational learning
in a project environment, where circumstances guarantee that every experience
contains unique elements.
View project closeout as two different sets of activities: one connected with
completing all the tasks and handing over the product or service, and the other to do
with ensuring that both individuals and the sponsoring organisation have learned
what there is to learn from the experience. This second set of activities (learning
from experience) is what knowledge management (KM) is all about in a project
setting. This second set of activities neednt wait until the end of a project it is
possible to hold after action reviews at any stage during the projects life.
Recognise that learning from experience calls for the transfer of knowledge not of
information as such it requires real contact between real people, in an
atmosphere of mutual interest and trust. Knowledge has a large tacit element and is
applied selectively. In other words, when people possess high know-how, they are
very careful to apply what they know only when it is appropriate to do so, and the
greater the degree of mastery of the subject, the greater the finesse they display in
applying their knowledge. This has major implications for how KM is implemented
in a project context.
None of these three items are simple but there is a growing body of evidence3 that project
closeout management is one of the keys to the continuous improvement of project
management practice the highest level of maturity in Harold Kerzners project
management maturity model.7
Notes
1
The material in this paper is dawn largely from Chapter 12 of Joan Knutsons Project Management for Business
Professionals: A Comprehensive Guide, John Wiley and Sons, New York, 2001, which was written by Terry CookeDavies, and is reproduced with permission.
See, for example, such popular and widely-read books as Cleland, David I. and King, William R. 1988. Project
nd
Management Handbook, 2 Edition, Wiley, New York or Kerzner, Harold. 1998. Project Management. A systems
th
approach to planning, scheduling and controlling. 6 Edition. Van Nostrand Reinhold. New York
See Cooke-Davies, Terence, Towards Improved Project Management Practice, Ph.D. Thesis, Leeds Metropolitan
University, 2000.
Widely attributed to George Santayana (1863 1952). For example www.stanford.edu/~miballar/ accessed on 7 April
2001.
This characteristic has been deduced from several studies, most notably Lynn Crawfords comprehensive study of The
Developmental Competence of Project Managers, kindly made available to the author by Dr. Crawford at a number of
workshops organised by the authors company.
For a more detailed discussion of the link between project management success, project success and corporate success,
see the authors paper, The real success factors on projects elsewhere in these conference proceedings.
See Kerzner, Harold. 2000. Applied Project Management. Wiley. New York and Kerzner, Harold. 2001. Strategic Planning
for Project Management Using a Project Management Maturity Model. Wiley. New York.
th