Review Questions
Lesson Topics
Production Scheduling (1) Problems are
Resource Allocation Problems when outputs are fixed
and when outputs and inputs occur at different periods
in time. The simplest problems consider only two time
periods.
Production Scheduling Problems with
Dynamic Inventory (4) help managers find an
efficient low-cost production schedule for one or more
products over several time periods (weeks or months).
Workforce Assignment (1) Problems are
Resource Allocation Problems when labor is a
resource with a flexible allocation; some labor can be
assigned to more than one work center.
Make or Buy (2) Problems are Linear
Programming Profit Maximization problems when
outputs are fixed and when inputs can be either made
or bought. Make or Buy Problems help minimize cost.
Product Mix (1) Problems are Resource Allocation
Problems when outputs have different physical
characteristics. Product Mix Problems thus determine
production levels that meet demand requirements.
Blending Problems with Weight Constraints
(1) help production managers blend resources to
produce goods of a specific weight at minimum cost.
Review Questions
Production Scheduling
Question. Greenville Cabinets received a contract to
produce speaker cabinets for a major speaker
manufacturer. The contract calls for the production of
3300 bookshelf speakers and 4100 floor speakers
over the next two months, with the following delivery schedule:
Model
Bookshelf
Floor
Month 1
2200
1000
Month 2
1100
3100
Greenville estimates that the production time for each bookshelf model is
0.7 hour and the production time for each floor model is 1 hour. The raw
material costs are $10 for each bookshelf model and $12 for each floor
model. Labor costs are $22 per hour using regular production time and $33
using overtime. Greenville has up to 1900 hours of regular production time
available each month and up to 500 additional hours of overtime available
each month. If production for either cabinet exceeds demand in month 1,
the cabinets can be stored at a cost of $5 per cabinet. For each product,
Greenville Cabinets must determine the number of units that should be
manufactured each month on regular time and on overtime to minimize
total production and storage costs.
Formulate a linear program for finding the optimal production schedule for
Greenville Cabinets. Formulate the problem, but you need not solve for the
optimum.
Review Questions
Answer to Question:
Decision variables: Regular time labor
Model
Month 1
Month 2
Bookshelf
B1R
B2R
Floor
F1R
F2R
Model
Month 1
Month 2
Bookshelf
B1O
B2O
Floor
F1O
F2O
Model
Regular
Overtime
Bookshelf
.7 (22) =
15.40
.7 (33) =
23.10
Floor
1 (22) = 22
1 (33) = 33
Objective function
Review Questions
5 IB + 5 IF
or
5 IB + 5 IF
s.t.
.7 B1R + 1 F1R
< 1900
.7 B2R + 1 F2R
< 1900
.7B1O + 1 F1O
< 500
Overtime: month 1
.7B2O + 1 F2O
< 500
Overtime: month 2
B1R + B1O - IB
= 2200
Bookshelf: month 1
IB + B2R + B2O
= 1100
Bookshelf: month 2
F1R + F1O - IF
= 1000
Floor: month 1
IF + F2R + F2O
= 3100
Floor: month 2
Review Questions
(hours)
Model
Production Costs
Manufacturing
Assembly
Current Inventory
Mens
$120
2.0
1.5
20
Womens
$90
1.6
1.0
30
Last month the company used a total of 1000 hours of labor. The
companys labor relations policy will not allow the combined total hours of
labor (manufacturing plus assembly) to increase or decrease by more than
100 hours from month to month. In addition, the company charges monthly
inventory at a rate of 2% of the production cost based on the inventory
levels at the end of the month. The company would like to have at least 25
units of each model in inventory at the end of the two months.
a) Establish a production schedule that minimizes production and
inventory costs and satisfies the labor-smoothing, demand, and
inventory requirements. What inventories will be maintained and what
are the monthly labor requirements?
b) If the company changed the constraints so that the monthly labor
increases and decreases could not exceed 50 hours, what would
happen to the production schedule? How much will the cost
increase? What would you recommend?
Review Questions
Answer to Question:
a. Let
x11 = amount of men's model in month 1
x21 = amount of women's model in month 1
x12 = amount of men's model in month 2
x22 = amount of women's model in month 2
s11 = inventory of men's model at end of month 1
s21 = inventory of women's model at end of month 1
s12 = inventory of men's model at end of month 2
s22 = inventory of women's model at end of month
The model formulation for part (a) is given.
Min 120x11 + 90x21 + 120x12 + 90x22 + 2.4s11 + 1.8s21 + 2.4s12 + 1.8s22
s.t.
20 + x11 - s11 = 150
or
x11 - s11 = 130
Satisfy Demand
[1]
30 + x21 - s21 = 125
or
x21 - s21 = 95
Satisfy Demand
Satisfy Demand
Satisfy Demand
[2]
[3]
[4]
s12
> 25
Ending Inventory
s22
> 25
Ending Inventory
[5]
[6]
Labor Hours: Mens = 2.0 + 1.5 = 3.5
Womens = 1.6 + 1.0 = 2.6
3.5 x11 + 2.6 x21 > 900
3.5 x11 + 2.6 x21 < 1100
[7]
[8]
3.5 x11 + 2.6 x21 - 3.5 x12 - 2.6 x22 < 100
Review Questions
-3.5 x11 - 2.6 x21 + 3.5 x12 + 2.6 x22 < 100
[10]
Month 2
The optimal solution is to produce 193 of the men's model in month 1, 162
of the men's model in month 2, 95 units of the women's model in month 1,
and 175 of the women's model in month 2. Total Cost = $67,156
Inventory Schedule
Month 1
Month 2
63 Men's
25 Men's
0 Women's
25 Women's
Labor Levels
Previous month
Month 1
Month 2
1000.00 hours
922.25 hours
1022.25 hours
Review Questions
Review Questions
10
Review Questions
Review Questions
Review Questions
Answer to Question:
The decision variables are the production quantities for the 3 months,
labeled P1 through P3. To keep quantities small, all quantities are in
hundreds of baseballs.
The objective function and constraints are easier to understand if we add
variables I1 through I3 to be the corresponding end-of-month inventories
(after meeting demand). For example, I3 is the number of baseballs left
over at the end of month 3.
Minimize the total production and holding costs:
Min 12 P1 + 13 P2 + 14 P3 + 2 I1 + 3 I2 + 4 I3.
The following constraints define inventories:
P1 I1 = 120-20 (productioninventory = net demand)
P2 + I1I2 = 130 (production-net inventory = demand)
P3 + I2I3 = 30 (production-net inventory = demand)
There are obvious constraints are on production and inventory storage
capacities: Pj 120 and Ij 20 for each month j (j = 1, , 3).
Finally, production and inventory storage are assumed non-negative.
12
13
Review Questions
Review Questions
What is the net cost of producing 2 more baseballs in month 2 and 1 less
baseball in month 3? Using the 100% rule, those changes are within the
range of feasibility, so the dual prices for constraints 2 and 3 apply.
Net cost = $14 x 2 + $14 x (-1) = $14.
14
15
Review Questions
Review Questions
16
Review Questions
Answer to Question:
The decision variables are the production quantities for the 3 months,
labeled P1 through P3.
The objective function and constraints are easier to understand if variables
I1 through I3 are end-of-month inventories (after meeting demand). For
example, I2 is the number of baseballs left over at the end of month 2.
Minimize the total production and holding costs:
Min 12.55 P1 + 12.70 P2 + 12.80 P3
+ 0.6275 I1 + 0.635 I2 + 0.64 I3.
The following constraints define inventories:
P1 I1 = 13000-2000 (productioninventory = net demand)
P2 + I1I2 = 3000 (production-net inventory = demand)
P3 + I2I3 = 13000 (production-net inventory = demand)
There are constraints are on production and inventory storage capacities:
Pj 12000 and Ij 2000 for each month j (j = 1, 2, 3).
Finally, assume production and inventory storage are non-negative.
17
Review Questions
Workforce Assignment
Question.
National Wing Company (NWC) is gearing up for the
new B-48 contract. NWC has agreed to supply 20
wings in April, 24 in May, and 30 in June. Wings can
be freely stored from one month to the next.
Currently, NWC has 90 fully-qualified workers. A fully qualified worker
can either be placed in production or can train new recruits. A new recruit
can be trained to be an apprentice in one month. After another month, the
apprentice becomes a fully-qualified worker. Each trainer can train three
recruits. At the end of June, NWC wishes to have at least 140 fully-qualified
workers.
The production rate and salary per employee type is listed below.
Type of
Production Rate
Wage
Employee
(Wings/Month)
Per Month
Production
.4
$3,000
Trainer
.3
$3,300
Apprentice
.2
$2,600
Recruit
.1
$2,200
Formulate a linear programming model to minimize cost. Formulate the
problem, but you need not solve for the optimum.
Tip: Your written answer should define the decision variables, and
formulate the objective and constraints.
18
Review Questions
Answer to Question:
Pi = number of producers in month i (where i = 1, 2, 3 for April, May, June)
Ti = number of trainers in month i (where i = 1, 2 for April, May)
Ai = number of apprentices in month i (where i = 2, 3 for May, June)
Ri = number of recruits in month i (where i = 1, 2 for April, May)
Define the objective function to minimize total wage cost for producers,
trainers, apprentices, and recruits for April, May, and June:
Min 3000P1 + 3300T1 + 2200R1 + 3000P2 + 3300T2
+ 2600A2+2200R2 + 3000P3 + 2600A3
Define the constraint that total production in Month 1 (April) must equal or
exceed contract for Month 1:
(1) .4P1 + .3T1 +.1R1 > 20
Define the constraint that total production in Months 1-2 (April, May) must
equal or exceed total contracts for Months 1-2:
(2) .4P1 + .3T1 + .1R1 + .4P2 + .3T2 + .2A2 + .1R2 > 44
Define the constraint that total production in Months 1-3 (April, May, June)
must equal or exceed total contracts for Months 1-3:
(3) .4P1+.3T1+.1R1+.4P2+.3T2+.2A2+.1R2+.4P3+.2A3 > 74
Define the constraint that the number of producers and trainers in a month
(fully qualified workers) must not exceed the initial supply of 100, plus any
apprentices employed in a previous month:
(4) P1 + T1 < 90
(5) P2 + T2 < 90
(6) P3 + T3 < 90 + A2
Define the constraint that the number of apprentices in a month must not
exceed the number of recruits in the previous month:
(7) A2 - R1 < 0; (8) A3 - R2 < 0
19
Review Questions
Define the constraint that each trainer can train three recruits:
(9) 3T1 - R1 > 0; (10) 3T2 - R2 > 0
Define the constraint that at the end of June, there are to be at least 140
fully-qualified workers (50 more than you started with):
(11) 90 + A2 + A3 > 140
20
Review Questions
Make or Buy
Question. Danchuk Manufacturing produces a
variety of classic automobiles, including a 1955 Chevy
and a 1955 Thunderbird. Each car consists of three
components that can be manufactured by Danchuk: a
body, an interior, and an engine. Both cars use the same interior and
engine, but different bodies.
Danchuks sales forecast indicates that 400 Chevys and 600 Thunderbirds
will be needed to satisfy demand during the next year. Because only 2000
hours of in-house manufacturing time is available, Danchuk is considering
purchasing some, or all, of the components from outside suppliers. If
Denchuk manufactures a component in-house, it incurs a variable
manufacturing cost. The following table shows the manufacturing time per
component, the manufacturing cost per component, and the cost to
purchase each of the components from an outside supplier:
Manufacturing
Time per Unit
(hours)
3
Manufacturing
Cost per Unit
(thousands of
dollars)
4
Purchase Cost
per Unit
(thousands of
dollars)
5
Thunderbird
Body
Interior
Engine
1
2
1
4
2
5
Component
Chevy Body
Formulate a linear program for Denchuk to minimize total cost to meet the
sales forecasts. Formulate the program, but you need not solve for the
optimum.
Tip: Your written answer should define the decision variables and formulate
the objective and constraints.
21
Review Questions
Answer to Question:
Continuous (non-integer) variables are used for the number of units made:
CB = the number of Chevy Bodies to make
TB = the number of Thunderbird Bodies to make
IN = the number of Interiors to make
E = the number of Engines to make
Continuous variables are also used for the number of units purchased:
CBP = the number of Chevy Bodies to purchase
TBP = the number of Thunderbird Bodies to purchase
INP = the number of Interiors to purchase
EP = the number of Engines to purchase
Objective: Minimize Total Cost
4CB + 2TB + 1IN + 4E (production costs)
+5CBP + 3TBP + 2INP + 5EP (purchase costs)
Input Constraints:
3CB + 2TB + 1IN + 2E < 2000 (In-house hours)
Sales Constraints:
CB + CBP = 400 (manufactured or purchased bodies used for Chevys)
TB + TBP = 600 (manufactured or purchased bodies used for
Thunderbirds)
IN + INP = 1000 (manufactured or purchased interiors used for both
Chevys and Thunderbirds)
E + EP = 1000 (manufactured or purchased engines used for both Chevys
and Thunderbirds)
22
Review Questions
Make or Buy
Question. Danchuk Manufacturing produces a
variety of classic automobiles, including a 1955 Chevy
and a 1955 Thunderbird. Each car consists of three
components that can be manufactured by Danchuk: a
body, an interior, and an engine. Both cars use the same interior and
engine, but different bodies.
Danchuks sales forecast indicates that 500 Chevys and 300 Thunderbirds
will be needed to satisfy demand during the next year. Because only 3000
hours of in-house manufacturing time is available, Danchuk is considering
purchasing some, or all, of the components from outside suppliers. If
Denchuk manufactures a component in-house, it incurs a variable
manufacturing cost. The following table shows the manufacturing time per
component, the manufacturing cost per component, and the cost to
purchase each of the components from an outside supplier:
Manufacturing
Time per Unit
(hours)
4
Manufacturing
Cost per Unit
(thousands of
dollars)
7
Purchase Cost
per Unit
(thousands of
dollars)
9
Thunderbird
Body
Interior
Engine
5
9
3
9
4
11
Component
Chevy Body
Formulate a linear program for Denchuk to minimize total cost to meet the
sales forecasts. Formulate the program, but you need not solve for the
optimum.
Tip: Your written answer should define the decision variables and formulate
the objective and constraints.
23
Review Questions
Answer to Question:
Continuous (non-integer) variables are used for the number of units made:
CB = the number of Chevy Bodies to make
TB = the number of Thunderbird Bodies to make
IN = the number of Interiors to make
E = the number of Engines to make
Continuous variables are also used for the number of units purchased:
CBP = the number of Chevy Bodies to purchase
TBP = the number of Thunderbird Bodies to purchase
INP = the number of Interiors to purchase
EP = the number of Engines to purchase
Objective: Minimize Total Cost
7CB + 4TB + 3IN + 9E (production costs)
+9CBP + 5TBP + 4INP + 11EP (purchase costs)
Input Constraints:
4CB + 3TB + 5IN + 9E < 3000 (In-house hours)
Sales Constraints:
CB + CBP = 500 (manufactured or purchased bodies used for Chevys)
TB + TBP = 300 (manufactured or purchased bodies used for
Thunderbirds)
IN + INP = 800 (manufactured or purchased interiors used for both Chevys
and Thunderbirds)
E + EP = 800 (manufactured or purchased engines used for both Chevys
and Thunderbirds)
24
Review Questions
Product Mix
Question. Island Water Sports is a business that
provides rental equipment and instruction for a variety
of water sports in a resort town. On one particular
morning, a decision must be made of how many
Wildlife Raft Trips and how many Group Sailing Lessons should be
scheduled. Each Wildlife Raft Trip requires one captain and one crew
person, and can accommodate six passengers. The revenue per raft trip is
$120. Ten rafts are available, and 30 people are on the list for reservations
this morning. Each Group Sailing Lesson requires one captain and two
crew people for instruction. Two boats are needed for each group. Four
students form each group. There are 12 sailboats available, and 20 people
are on the list for sailing instruction this morning. The revenue per group
sailing lesson is $160. The company has 12 captains and 18 crew
available this morning. The company would like to maximize the number of
customers served while generating at least $180 in revenue and honoring
all reservations. Formulate and use the Management Scientist to solve the
appropriate linear programming problem.
25
Review Questions
Answer to Question:
The following description of constraints also mentions assumptions that fill
in information left out of the verbal description of the problem. Let
R = the number of Wildlife Raft Trips to schedule
S = the number of Group Sailing Lessons to schedule
Max 6R + 4S
s.t. R + S < 12 (captain constraint, assuming captains not used do not
affect the objective function or other constraints. Idle captains do no
alternative work)
R + 2S < 18 (crew constraint, assuming crew not used do not affect the
objective function or other constraints. Idle crew do no alternative work)
6R > 30 (6R is the number of raft customers assuming you have all the
paying customers you have room for)
4S > 20 (4S is the number of sailing customers assuming you have all the
paying customers you have room for)
120R + 160S > 180
R < 10 (raft constraint, assuming 1 raft per trip (you cannot do two trips
per day) and rafts not used do not affect the objective function or other
constraints. Idle rafts have no alternative purpose, and depreciate as much
as rafts used)
2S < 12 (sailboat constraint, assuming boats not used do not affect the
objective function or other constraints. Idle boats have no alternative
purpose, and depreciate as much as boats used)
R,S >0
26
27
Review Questions
Review Questions
Units/lb
Units/lb
12
.75
Monosodium glutamate
16
10
14
.90
10
15
.80
10
.70
Wheat
Maltodextrin
Units/lb
Cost/lb
28
Review Questions
Answer to Question:
Define the decision variables:
xj = the pounds of Ingredient j (j = 1,2,3,4) used in 3-ounce mixture
Define the objective: Minimize the total cost for an 3-ounce mixture:
Min .75x1 + .90x2 + .80x3 + .70x4
Constrain the total weight of the mix to 3-ounces (3/16 pounds):
(1) x1 + x2 + x3 + x4 = 3/16
Constrain the total amount of Sodium in the mix to be at least 6 units:
(2) 9x1 + 16x2 + 8x3 + 10x4 > 6
Constrain the total amount of Dietary Fiber in the mix to be at least 5 units:
(3) 12x1 + 10x2 + 10x3 + 8x4 > 5
Constrain the total amount of Iron in the mix to be at least 5 units:
(4) 14x2 + 15x3 + 7x4 > 5