Procedure For Power Receiving - pg2-13
Procedure For Power Receiving - pg2-13
Procedure For Power Receiving - pg2-13
Doc. No
Rev. No.
Page
TABLE OF CONTENTS
1.
PURPOSE
2.
EXTENT
3.
4.
PREREQUISITES
5.
6.
7.
REFERENCE DOCUMENTS
KP-00+++-CY712-G0019
1
of 18
Doc. No
Rev. No.
Page
1.
KP-00+++-CY712-G0019
1
of 18
PURPOSE
The purpose of this document is to establish the power energizing procedure to be performed
prior to initial operation of the electrical systems of KHABAT THERMAL POWER PLANT UNIT 1
& 2 according to the following schedules,
1) 132KV AIS Power Receiving : Jul. 2, 15 (Official Completion of Power Receiving)
2) Power Plant Energizing : Sep. 1, 15
2.
EXTENT
Power receiving shall be carried out after completion of site test of the following equipment in
accordance with each test procedure.
1) 132KV AIS
-
2) POWER PLANT
-
Generator Step-up Transformer and Protection Panel (OLTC : temp power supply)
Unit Auxiliary Transformer and Protection Panel (OLTC : temp power supply)
15.75KV IPB
6 kV SWGR
6 kV Cables between Unit Auxiliary TR and 6kV SWGR
6 kV Outgoing feeders from 6kV SWGR to Service TR
400V LV Switchgear
400V Essential Power Switchgear
220V DC Battery Charger, Battery & DC Distribution Panel
230V UPS System & Essential Power Distribution Panel
Grounding system
Fire Fighting & Alarm system (if not, temporary installation)
HVAC System (if not, temporary installation)
Lighting System (temporary power supply)
Doc. No
Rev. No.
Page
KP-00+++-CY712-G0019
1
of 18
A.
B.
3.
4.
All individual feeder breakers of 6 kV switchgear, 400V switchgear, 400V MCCs and LV dist
boards shall be tagged out in accordance with single line diagram prior to initial energizing.
All checks and tests specified in site test plan or commissioning procedure submitted by
manufacturer shall be performed prior to energizing the equipment.
Provide warning barriers around the equipment to be energized first for the protection of plant
personnel.
Ensure that circuit breakers and disconnecting switches are open and SF6 pressure correct.
Check all panels and electrical equipment are connected to earth.
Check the lighting and HVAC are available (if not, temporary installation).
PREREQUISITES
a)
b)
c)
d)
e)
f)
g)
h)
The main and auxiliary power systems have been turned over to the commissioning team and
the commissioning engineers are to be aware of the electrical distribution system of the plant.
All the factory test report and operation manuals are to be available for review.
All the test equipment shall be prepared to fulfill the complete test and commissioning
400V AC power supplies are available for energizing the 220V DC system and 230V UPS
System. (Temporary power supply).
For 132KV AIS energizing, 132KV Substation should be installed completely, also all preenergizing tests should be done.
Coordinate with MOE for power energizing of 132kV AIS Breaker.
Earthing switches of 132kV AIS, 15.75KV GCB and 6KV switchgear are on correct position
(closed for pre-energizing checks, opened for energizing)
Ensure that all circuit breakers are in power off position initially
All protective relays have been set as per Protective Relay Setting Table prepared.
The Contractor will be responsible for all the safety measure necessary to the taken before, during and
after the commissioning tests. The works will be carried out in accordance with the PLANT HSE PLAN.
Doc. No
Rev. No.
Page
KP-00+++-CY712-G0019
1
of 18
Reference Drawing
- Single line diagram
- Schematic diagram
- Vendor drawing
5.1.1
220V/48V DC system
1) Complete the pre-energizing checks of 220V/48V DC systems as per the test plan and
procedure of manufacturer.
- Battery charger unit (DC 220V, 48V)
- DC 220V & DC 48V switchboard
- Battery bank (DC 220V, 48V)
5.1.2
2)
-
5.2
Reference Drawing
- Single line diagram
- Schematic diagram
5.2.1
Doc. No
Rev. No.
Page
KP-00+++-CY712-G0019
1
of 18
- Vendor drawing
5.2.2 Prerequisites
1)
-
2)
132KV Protection relay panels, Control Panels, Metering Panels, Common Signal Panels,
SCADA Panels, ECS and Telecom Panels
Verify that the factory test data is available for review
Verify all equipment are installed correctly
Verify all equipment are grounded properly.
Verify all protection relay settings are correct and tests completed
Verify all function test completed
Verify all interlock, inter-trip test completed
Verify all indications are correct
Verify all communication are correct with MOE
Perform pre-energizing checks in accordance with field test plan and procedure.
3)
-
Doc. No
Rev. No.
Page
6.
KP-00+++-CY712-G0019
1
of 18
220V DC system
1) Complete the pre-energizing checks of 220V DC systems as per the test plan and
procedure of manufacturer
- Battery charger unit (220V DC)
- DC 220V switchboard
- Battery bank (220V DC)
6.1.2
Doc. No
Rev. No.
KP-00+++-CY712-G0019
Page
6.2
6.2.1
1
of 18
4) 6KV Switchgear
Check and verify open position of ES Q10 of Incomer
Check and verify open position of ES Q10 of busbar
Doc. No
Rev. No.
KP-00+++-CY712-G0019
Page
1
of 18
6.3.2 Prerequisites
Perform inspections and tests as outlined in manufacturer's field test plan and procedure.
Perform functional tests of the breaker control circuits to verity proper operation of the
switchgear protection circuitry
Verify proper operation of the incoming breaker and switchgear bus earthing switch and
interlocks
Verify the control switch operation to open and close all breakers
Check the contact and the tightness of earth connectors on framework.
6.3.3 Initial energizing 6kV switchgear
Check and verify the open position of incoming breaker of 6 kV switchgear
Check and verify the open position of all feeder breakers to station service transformer
Check and verify the open position of all outgoing breakers (except station service TR) with
LOTO
Verity the open position of switchgear bus earthing switch
Check correct connection of 6kV power from Transformers.
Energize 6 kV switchgear by closing the incomer breaker at local
Verity the voltage and phase rotation of 6kV switchgear and record the result on the checklist
6.4 TEST AND ENERGIZING OF STATION SERVICE TRANSFORMERS
6.4.1 Reference Drawing
1) Single line diagram
2) Vendor drawing
6.4.2 Prerequisites
Doc. No
Rev. No.
Page
KP-00+++-CY712-G0019
1
of 18
2) 6KV Switchgear
Verity the control switch operates to open and close all breakers.
Perform inspections and pre-energizing tests of the 6KV switchgears as per manufacturer's
field test plan and procedure.
Verify outgoing feeder ES open
3) 400V Switchgear
Verify incoming CB open
Verify all outgoing feeder breakers open
field
Prerequisites
Doc. No
Rev. No.
Page
KP-00+++-CY712-G0019
1
of 18
1) 400V Switchgear
Check outgoing feeder breaker open
2)
MCC
Check incoming breaker open
Check all outgoing feeder breakers open and LOTO
Perform inspections and pre-energizing tests of the 400V MCCs as per manufacturer's field
test plan and procedure
Reference Documents
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
Doc. No
Rev. No.
Page
Attachment
KP-00+++-CY712-G0019
1
of 18
Attachment #1