Automation of Power Distribution Using Scada
Automation of Power Distribution Using Scada
Automation of Power Distribution Using Scada
1
2
AUTOMATION OF POWER DISTRIBUTION USING SCADA
ABSTRACT
3
AUTOMATION OF POWER DISTRIBUTION USING SCADA
INTRODUCTION
Traditionally, the protective system comprising of relays and circuit breaker were
almost independent control systems for tap changer control, voltage control, data logging, and
data monitoring and routine operations. Before 1985, the protective functions were segregated
from control functions.
In modern automatic SCADA systems, the functions are interlinked by means of digital
processing devices and power line carrier/radio communication links. Every power/substation
has a control room the relay and protection panels and control panels and man machine
interface (MMI) installed in the control room.
With the development of programmable digital systems i.e, microprocessor based SCADA
systems, the entire supervisory functions, control functions, protective functions can be
combined. The main function of distribution SCADA is to control and supervision of
distribution of power to various consumers with minimum outage and minimum loss.
4
AUTOMATION OF POWER DISTRIBUTION USING SCADA
Due to lack of information at the base station (33kv substation)on the loading and health
status of the 11kv/415v transformer with associated feeders is one of the primary causes of
inefficient power distribution. Due to absence of monitoring, overloading occurs which
results in low voltage at the customer end and increases the risk of frequent breakdown of
transformers and feeders. In fact, the transformer breakdown rate in India is as high around
20% in contrast to less than 2% in some advanced countries.
In the event of a fault in any feeder section downward stream, The circuit breaker at
the 33kv substation trips (opens).As a result there is a blackout over a large section of the
distribution network. If the fault feeder segment could be precisely identified, it would be
possible to substantially reduce the blackout area, by re-routing the power to the healthy
feeder segments through the operation of switches placed at strategic location in various
feeder segments.
Currently the scope of Power System Automation in India has been limited to
SCADA system automation up to the transmission level. However as the fig.1 given below
indicate, the substations contribute only 1% of the outages.
5
AUTOMATION OF POWER DISTRIBUTION USING SCADA
Fig.1
Hence the need for protection of the system beyond the substation becomes very
important. As such the fledgling field of DAS in India will become extremely critical in the
coming years.
IDAS
DG
6
AUTOMATION OF POWER DISTRIBUTION USING SCADA
SCADA:
SCADA is an acronym for supervisory control and data acquisition system.
It consists of one or more computers with appropriate applications software (Master
Stations) connected by communications system (wire, radio, power line carrier or fiber
optics) to a number of remote terminal units (RTUs) placed at various locations to collect
data and for remote control and to perform intelligent autonomous (local) control of a
system and report results back to the remote master(s).The required control actions are
then conveyed back to the process. The concept of SCADA forms the basis of the DA
system.
SCADA Process classified into 3 parts.
Input:
Analog: Continuous Electrical Signals
Ex. Active Power (MW), Reactive Power (MVAR), Voltage (KV), Frequency (Hz).etc..
Digital: Switching Signals High (1) or Low (0) Signal
Ex. Breaker Close (high) or Open (low), Isolator Closed (high) or Open (low).
Process:
The signals are converted into digital format
Implement protocol between Master and Slave
It operates with Real Time Operating System (RTO)
Output:
The results are exposed with user friendly environment
Through displays can be possible to control the substation and generating station.
1. HARDWARE COMPONENTS:
The components of a SCADA system are field instrumentation, remote
stations, Communication Network (CN) and Central Monitoring Station (CMS).
a) Field instrumentation:
Field instrumentation generally comprises sensors, transmitters and actuators that
are directly interfaced to the plant or equipment and generate the analog and digital
signals that will be monitor by the remote station. Signals are also conditioned to make
sure they are compatible with the inputs/outputs of the Remote Terminal Unit (RTU) or a
Programmable Logic Controller (PLC) at the remote Station. It also refers to the devices
that are connected to the equipment or machines being controlled and monitored by the
8
AUTOMATION OF POWER DISTRIBUTION USING SCADA
SCADA system. These are sensors for monitoring certain parameters and actuators for
controlling certain modules of the system.
The remote station is installed at the remote plant with equipment being
monitored and controlled by the central host computer. This can be a RTU or PLC. Field
instrumentation, connected to the plant or equipment being monitored and controlled, is
interfaced to the remote station to allow process manipulation at a remote site. It is also
used to gather data from the equipment and transfer it to the central SCADA system.
9
AUTOMATION OF POWER DISTRIBUTION USING SCADA
10
AUTOMATION OF POWER DISTRIBUTION USING SCADA
c) Communication Network:
Simplified Installation
Immunity from EM interface
Reliability and high Bandwidth
Availability of Direct Metallic Contacts for devices in the same region
Two way communication unlike that provided by radio.
Break in a fiber cable will not cause a loss of data.
11
AUTOMATION OF POWER DISTRIBUTION USING SCADA
Each I/O point of the remote units can be displayed with corresponding graphical
representation and the present I/O reading. Set-up parameters such as trip values, limits,
etc. are entered on this program and downloaded to the corresponding remote units for
updating of their operating parameters.
Modem Modem
Communication Backbone
There are two typical network configurations for the SCADA systems. They are
the point-to-point and the point-to-multipoint configurations. The point-to-point
configuration is the simplest one device is designated as the master unit to several slave
units. The master is usually the main host and is located in the control room, while the
slaves are the remote units. Each slave is assigned a unique address or identification
12
AUTOMATION OF POWER DISTRIBUTION USING SCADA
number set-up for a telemetry system. Here data is exchanged between two stations. One
station can be set up as the master and the other as the slave.
SOFTWARE COMPONENTS:
b) Control:
This is done by Engineering Analysis Software. Users are allocated to groups,
which have defined read/write access privileges to the process parameters in the system
and often also to specific product functionality. The allocated users can have the access
to the devices, which are to be controlled. Control can be single or group, open or closed
loop control. The execution of control can be executed at selective places, can be
immediately executed, can be executed at required time etc.
13
AUTOMATION OF POWER DISTRIBUTION USING SCADA
SCADA systems can be made use to have GUI system. GUI system can be used
to have maps, graphical representation of the required area. Using SCADA these maps
can be layered, zoomed, scrolled and planned.
APPLICATION PROGRAMS:
The various application programs that can be implemented using SCADA systems
are clearly explained here. The following are the applications that can be used for remote
monitoring, control, safety, efficient utilization of resources etc.
c) Load Balancing:
This function distributes the system total load among the available transformers
and the feeders in proportion to their capacities. As explained above, there was a need to
replace the existing switches with remotely controllable switches in order to reconfigure
the network for load balancing.
15
AUTOMATION OF POWER DISTRIBUTION USING SCADA
e) Remote metering:
The function of remote metering is to read data from the meters and to provide
information to the operator of the consumption patterns of the high-value HV customers.
Its main feature is to provide a multiple tariff to the customers to encourage them to shift
their loads from peak times to off-peak times. This function also provides meter-
tampering detection.
g) Energy accounting:
This function helps in arriving at the system's load patterns, which helps in
planning expansion. It also helps in detecting abnormal energy consumption patterns of
the consumers and identifying high-loss areas. Processing the data obtained by the
remote metering function and the data obtained from the substation does this.
IMPLEMENTATION:
SCADA system to automate power for Hyderabad & Secunderabad and
streamline APCPDCL electrical distribution network .APCPDCL (Andhra Pradesh
Central Power Distribution Company Ltd) commissioned a state of the art SCADA
(Supervisory Control & Data Acquisition) system supplied by ABB India to monitor and
control the power distribution network for the twin cities of Hyderabad and
Secunderabad.
The system offers operational advantages by integrating distribution automation
functionalities like Automatic / Remote meter reading, Load balancing, trouble call
management etc. to facilitate effective distribution management.
16
AUTOMATION OF POWER DISTRIBUTION USING SCADA
CONCLUSION:
17