HaGun Gantry Crane + Method of Works Install Stator Generator+Strand Jack + 03JuLy14 PDF
HaGun Gantry Crane + Method of Works Install Stator Generator+Strand Jack + 03JuLy14 PDF
HaGun Gantry Crane + Method of Works Install Stator Generator+Strand Jack + 03JuLy14 PDF
Prepared by
Review by
Approved by
Rigging Engineer
SITE MANAGER
Rev. No.
Effective Date:
03 July 2014
Distribution
Master
: Rigging
Origin
: Client
Copies
: CONST. DEPT
BRIEF OF REVISION
APPROVED BY:
SITE MANAGER
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
2 of 23
REVISI:
-
TABLE OF CONTENT
TABLE OF CONTENT .......................................................................................................... 2
1.
GENERAL...................................................................................................................... 3
2.
PURPOSE ..................................................................................................................... 3
3.
4.
RESPONSIBILITY ......................................................................................................... 4
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Document No:
Esco-RIG-HG-001
APPROVED BY:
SITE MANAGER
Date:
03 July 2014
Pages:
3 of 23
REVISI:
-
1. GENERAL
This procedure provides information for the erection of Stator Generator PLTU
KALTIM TELUK BALIKPAPAN 2X110MW Teluk Balikpapan Kalimantan Timur
Project.
2. PURPOSE
This Procedure is to make sure that all people involve in the erection, assembly
and welding of Stator Generator activity understand and familiar to do the work
with quality control system for getting quality result as per client specification
and requirement, drawing, standard and code.
3. GENERAL NOTE
3.1. Inspection
As per the works required inspection, carry out inspection under attendance
of Superintendent / Engineer and as surreally record is result.
3.2. Safety
3.2.1. A safety officer presents all times Safety Briefing.
3.2.2. Job Safety Analysis (JSA) must be carried out for all crane lifts and all
other tasks that have potential risk to personnel of equipment.
3.2.3. Install scaffolding where necessary to install bolt in each beam and
member connection.
3.2.4. Pre lift study before any lifting activity.
3.2.5. Lift briefing and Safety briefing before any lift; assign responsibility to
all personnel involved. (Signalman, Rigger to crane driver, etc.)
3.2.6. Ensure all equipment required for installation is on hand and in
position before lift i.e. Chain blocks, Lever blocks, Podgy, Drifts,
Hammer, and Spanners. Etc.
3.2.7. Tag lines must be used to control lift.
3.2.8. Ground conditions must be ready before activities.
3.2.9. Set up safety rope around lifting area of Stator Generator area and
put notice board entered KEEP OFF EXCEPT PERSONEL
CONCERNED.
3.2.10. Lifting equipment should be in certification and tagged.
3.2.11. Crane and other machinery shall be inspected and certified.
3.3. Lifting
All conditions adapted to the Method of Works Install. Prior to
commencement of lifting works, assuredly carry out check of lifting
equipment.
APPROVED BY:
SITE MANAGER
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
4 of 23
REVISI:
-
Document No:
Esco-RIG-HG-001
APPROVED BY:
SITE MANAGER
Date:
03 July 2014
Pages:
5 of 23
REVISI:
-
The Packing List should indicate the quantity of the material and equipment
supplied and its specification as described in the erection drawing. This will
also indicate the size and the total weight of the component and the method
of storage. Also the packing number and material coding is very essential.
5.4. Storage Area and Warehouse
Upon a thorough check on the drawing and the packing list, the quantity of
materials and equipment is already known, including the method of storing,
the size of the storage area and the warehouse can be identifies.
5.5. Resources
Identification of resources is integral part of planning and scheduling is the
most essential part of the basic requirement in undertaking Structure Turbine
House in particular and in all jobs in general. Resources means, the
materials, labor and equipment needed to perform Structure Turbine House
Project.
6. PREPARATION WORK
6.1. Checking of Stator Generator Erection Drawings
This has to be done by the Chief Construction, Field Engineer,
Superintendent and Supervisor to determine the correct resources needed to
perform the job.
6.2. Checking of Client Supplied Material and Equipment
Checking and inspection of the materials and equipment including the spare
parts is to be done by the material control. He will make sure that all
materials, equipment and spare parts received from PT Adhi Karya, conform
to the quantity and the specifications started in the packing list or shipping.
6.3. Checking of Erection Materials, Equipment, Tools and Machinery
In the early stage of planning, these resources had been already identified.
The schedule of mobilization as on planned schedule made by the Chief
Construction and Engineer.
Checking of Labor
Labor requirement for every stage of erection job is prepared by the Chief
Engineer and his erection team, which is in accordance to their planning.
APPROVED BY:
SITE MANAGER
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
6 of 23
REVISI:
-
7. ORGANIZATION CHART
ORGANIZATION CHART
Stator Generator
By Stand Jack and Skidding Roller
PLTU KALTIM TELUK BALIKPAPAN 2X110MW
Teluk Balikpapan Kalimantan Timur
APPROVED BY:
SITE MANAGER
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
7 of 23
REVISI:
-
Document No:
Esco-RIG-HG-001
APPROVED BY:
SITE MANAGER
Date:
03 July 2014
Pages:
8 of 23
Inspection Quality
by QC & Safety
YES
ERECTION ACTIVITY
METHOD OF
STATEMENT
FINISH
NO
REVISI:
-
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
APPROVED BY:
SITE MANAGER
Pages:
9 of 23
Quality Inspection
by QC
Vendor Aproval
Inspection Quality
by QC & Safety
FINISH
Repair
REVISI:
-
APPROVED BY:
SITE MANAGER
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
10 of 23
REVISI:
-
: 4 unit
: 4 unit
: 1 unit
Figure 1
APPROVED BY:
SITE MANAGER
Figure 2
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
11 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 3
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
12 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 4
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
13 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 5
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
14 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 6
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
15 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 7
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
16 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 8
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
17 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 9
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
18 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 10
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
19 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 11
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
20 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 12
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
21 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
Figure 13
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
22 of 23
REVISI:
-
APPROVED BY:
SITE MANAGER
2. Skidding
Figure 14
Document No:
Esco-RIG-HG-001
Date:
03 July 2014
Pages:
23 of 23
REVISI:
-