LO305 Basic Data for Process Manufacturing

LO305

Release 630 29.08.2003

LO305 Basic Data for Process Manufacturing...............................................................................................................0-1


Copyright....................................................................................................................................................................0-2
Process Industry (PP - PI).......................................................................................................................................0-3
Prerequisites...........................................................................................................................................................0-4
Target Group...........................................................................................................................................................0-5
Introduction................................................................................................................................................................1-1
Course Goals (I).....................................................................................................................................................1-2
Course Goals (II)....................................................................................................................................................1-3
Course Objectives...................................................................................................................................................1-4
Course Content 1....................................................................................................................................................1-5
Course Content 2....................................................................................................................................................1-6
Overview Diagram 1..............................................................................................................................................1-7
Main Business Scenario.........................................................................................................................................1-8
PP-PI Overview..........................................................................................................................................................2-1
PP-PI Overview: Unit Objectives...........................................................................................................................2-2
Overview Diagram 2..............................................................................................................................................2-3
PP-PI - Integration with the R/3 System................................................................................................................2-4
Application Areas of PP-PI....................................................................................................................................2-5
Positioning of PP-PI in the Enterprise Model........................................................................................................2-6
Functions of PP-PI..................................................................................................................................................2-7
Data Flow in PP-PI.................................................................................................................................................2-8
PP-PI Overview: Summary....................................................................................................................................2-9
Exercise Data........................................................................................................................................................2-10
Exercises...............................................................................................................................................................2-13
Solutions...............................................................................................................................................................2-15
Master Data: Overview..............................................................................................................................................3-1
Master Data: Unit Objectives.................................................................................................................................3-2
Overview Diagram 3..............................................................................................................................................3-3
Master Data: Business Scenario.............................................................................................................................3-4
Master Data Overview............................................................................................................................................3-5
Material..................................................................................................................................................................3-6
Batch.......................................................................................................................................................................3-7
Resource.................................................................................................................................................................3-8
Production Version.................................................................................................................................................3-9
Master Recipe.......................................................................................................................................................3-10
Bill of Material - Definition..................................................................................................................................3-11
BOM Categories...................................................................................................................................................3-12
Master Data: Unit Summary.................................................................................................................................3-13

Materials.....................................................................................................................................................................4-1
Materials: Unit Objectives......................................................................................................................................4-2
Overview Diagram 4..............................................................................................................................................4-3
Materials: Business Scenario..................................................................................................................................4-4
Material Master Records: Definition......................................................................................................................4-5
Material Master Records: Views............................................................................................................................4-6
Material Type..........................................................................................................................................................4-7
Control Using Material Type..................................................................................................................................4-8
Industry Sectors and Material Types......................................................................................................................4-9
Field Selection: Influencing Factors.....................................................................................................................4-10
Field Selection: Influencing Factors - Field Reference........................................................................................4-11
Field Selection: Field Selection Group (Example)...............................................................................................4-12
Field Selection: Field Selection Groups and Field References............................................................................4-13
Field Selection: Link Rules..................................................................................................................................4-14
Customized Material Master................................................................................................................................4-15
Creating a Customized Material Master...............................................................................................................4-16
Influencing Factors for Screen Sequences...........................................................................................................4-17
Screens for Material Master Maintenance............................................................................................................4-18
Materials: Summary.............................................................................................................................................4-19
Exercises...............................................................................................................................................................4-20
Solutions...............................................................................................................................................................4-26
R/3 Classification System..........................................................................................................................................5-1
R/3 Classification System: Unit Objectives...........................................................................................................5-2
Overview Diagram 5..............................................................................................................................................5-3
R/3 Classification System: Business Scenario.......................................................................................................5-4
Classification..........................................................................................................................................................5-5
Classification in the R/3 System............................................................................................................................5-6
R/3 Classification System......................................................................................................................................5-7
R/3 Classification System: Example......................................................................................................................5-8
Class Types.............................................................................................................................................................5-9
Creating Classes...................................................................................................................................................5-10
Classifying Objects...............................................................................................................................................5-11
Classifying Objects for Process Manufacturing...................................................................................................5-12
Example : Classification of Resources.................................................................................................................5-13
R/3 Classification System: Summary...................................................................................................................5-14
Exercises...............................................................................................................................................................5-15
Solutions...............................................................................................................................................................5-19
Batches.......................................................................................................................................................................6-1
Batches : Unit Objectives.......................................................................................................................................6-2

Overview Diagram 6..............................................................................................................................................6-3


Batches : Business Scenario...................................................................................................................................6-4
Material and Batch.................................................................................................................................................6-5
Batch Management in the Logistics Process..........................................................................................................6-6
Levels of Uniqueness of a Batch............................................................................................................................6-7
Changing Batch Levels...........................................................................................................................................6-8
Converting Batch Numbers....................................................................................................................................6-9
Classification of a Material and a Batch - Characteristic Inheritance..................................................................6-10
Creating Classes for Batches I..............................................................................................................................6-11
Creating Classes for Batches II............................................................................................................................6-12
The Batch Where-Used List at Several Production Levels..................................................................................6-13
Batch-Specific Material Unit of Measure.............................................................................................................6-14
Batch-Specific Units of Measure as an Attribute of a Batch................................................................................6-15
Integration of Batch-Specific Units of Measure...................................................................................................6-16
Physical Quantity and Active Ingredient Quantity...............................................................................................6-17
The Central Unit of Measure for Active Ingredients............................................................................................6-18
Relation of Units of Measure...............................................................................................................................6-19
Percentage and User-defined Calculation............................................................................................................6-20
Active Ingredient Characteristics.........................................................................................................................6-21
Linking Master Data I..........................................................................................................................................6-22
Linking Master Data II.........................................................................................................................................6-23
Maintaining Units of Measurement in the Material Master.................................................................................6-24
Batches : Unit Summary.......................................................................................................................................6-25
Exercises...............................................................................................................................................................6-26
Solutions...............................................................................................................................................................6-31
Resources: Customizing.............................................................................................................................................7-1
Resources: Customizing: Unit Objectives..............................................................................................................7-2
Overview Diagram 7..............................................................................................................................................7-3
Resources: Customizing: Business Scenario..........................................................................................................7-4
Resources in the Company.....................................................................................................................................7-5
Resource Master Record........................................................................................................................................7-6
Functions of the Resource Category......................................................................................................................7-7
Field Selection........................................................................................................................................................7-8
Capacity and Available Capacity............................................................................................................................7-9
Capacity Categories for a Resource.....................................................................................................................7-10
Formulas in the Resource.....................................................................................................................................7-11
Example of a Formula..........................................................................................................................................7-12
Customizing a Default Resource..........................................................................................................................7-13
Resources: Customizing: Unit Summary.............................................................................................................7-14

Exercises...............................................................................................................................................................7-15
Solutions...............................................................................................................................................................7-22
Resources: Functions..................................................................................................................................................8-1
Resources: Functions: Unit Objectives..................................................................................................................8-2
Overview Diagram 8..............................................................................................................................................8-3
Resources: Functions: Business Scenario..............................................................................................................8-4
Resource Data I......................................................................................................................................................8-5
Resource Data II.....................................................................................................................................................8-6
Resource Management Views................................................................................................................................8-7
Cost Center / Activity Type / Resource..................................................................................................................8-8
Creating a Resource................................................................................................................................................8-9
Resource Network................................................................................................................................................8-10
Classification of Resources..................................................................................................................................8-11
Available Capacity of a Resource.........................................................................................................................8-12
Maintaining Avail. Capacity Using Shift Sequences............................................................................................8-13
Assignments to the Personnel System (HR).........................................................................................................8-14
Reporting Functions for Resources......................................................................................................................8-15
Resources: Functions: Unit Summary..................................................................................................................8-16
Exercises...............................................................................................................................................................8-17
Solutions...............................................................................................................................................................8-29
Production Version.....................................................................................................................................................9-1
Production Version: Unit Objectives......................................................................................................................9-2
Overview Diagram 9..............................................................................................................................................9-3
Production Version: Business Scenario..................................................................................................................9-4
Production Version: Definition...............................................................................................................................9-5
Production Version: Mass Processing (I)...............................................................................................................9-6
Production Version: Mass Processing (II)..............................................................................................................9-7
Recipe Editing........................................................................................................................................................9-8
Consistency Check.................................................................................................................................................9-9
Approval...............................................................................................................................................................9-10
Production Version: Unit Summary......................................................................................................................9-11
Exercises...............................................................................................................................................................9-12
Solutions...............................................................................................................................................................9-16
Master Recipes: Operations and Phases...................................................................................................................10-1
Master Recipes, Operations, and Phases:Unit Objectives....................................................................................10-2
Overview Diagram 10..........................................................................................................................................10-3
Master Recipes, Operations, and Phases: Business Scenario...............................................................................10-4
Elements of a Master Recipe................................................................................................................................10-5
Structure of a Master Recipe (I)...........................................................................................................................10-6

Structure of a Master Recipe (II)..........................................................................................................................10-7


Functions of a Master Recipe...............................................................................................................................10-8
Non-Manufacturing Recipes................................................................................................................................10-9
Profile for the Recipe..........................................................................................................................................10-10
Recipe-Plant Assignment....................................................................................................................................10-11
Copying Recipes from Other Plants...................................................................................................................10-12
Reporting............................................................................................................................................................10-13
Recipe Header Data............................................................................................................................................10-14
Operations and Phases........................................................................................................................................10-15
Assignment of Primary and Secondary Resources.............................................................................................10-16
Standard and Default Values from the Resource................................................................................................10-17
Relationships......................................................................................................................................................10-18
Relationships Between Master Recipes..............................................................................................................10-19
Scheduling in the Master Recipe........................................................................................................................10-20
Phase Duration...................................................................................................................................................10-21
Classification of Operations and Resources.......................................................................................................10-22
Checking the Recipe / Consistency Log.............................................................................................................10-23
Master Recipes, Operations, and Phases:Unit Summary...................................................................................10-24
Exercises.............................................................................................................................................................10-25
Solutions.............................................................................................................................................................10-34
Master Recipes: Materials........................................................................................................................................11-1
Master Recipes, Materials: Unit Objectives.........................................................................................................11-2
Overview Diagram 11...........................................................................................................................................11-3
Master Recipes, Materials: Business Scenario.....................................................................................................11-4
Typical Material Flow in the Process Industry.....................................................................................................11-5
Material-Recipe Assignment (I)...........................................................................................................................11-6
Bill of Material - Definition..................................................................................................................................11-7
Material-Recipe Assignment (II)..........................................................................................................................11-8
Bill of Material - Example....................................................................................................................................11-9
BOM Item Categories.........................................................................................................................................11-10
Material List........................................................................................................................................................11-11
Classification of BOM Components...................................................................................................................11-12
Material Quantity Calculation I..........................................................................................................................11-13
Material Quantity Calculation II.........................................................................................................................11-14
Material Quantity Calculation - Example...........................................................................................................11-15
Material Quantity Calculation - Process (I)........................................................................................................11-16
Material Quantity Calculation - Process (II)......................................................................................................11-17
Material Quantity Calculation Screen................................................................................................................11-18
Product Quantity Calculation.............................................................................................................................11-19

Component Quantity Calculation (I)..................................................................................................................11-20


Calculation Using Active Ingredient Quantities of Batches...............................................................................11-21
Calculation Using Physical Batch Quantities.....................................................................................................11-22
Component Quantity Calculation (II).................................................................................................................11-23
Master Recipes, Materials: Unit Summary.........................................................................................................11-24
Master Recipes, Materials: Exercises................................................................................................................11-25
Solutions.............................................................................................................................................................11-38
Master Recipes: Control View..................................................................................................................................12-1
Master Recipes, Control View: Unit Objectives..................................................................................................12-2
Overview Diagram 12..........................................................................................................................................12-3
Master Recipes, Control View: Business Scenario..............................................................................................12-4
Process Management............................................................................................................................................12-5
Creating and Downloading Control Recipes........................................................................................................12-6
Process Instructions and Control Recipes............................................................................................................12-7
Planning View and Control View.........................................................................................................................12-8
PI Sheet.................................................................................................................................................................12-9
PI Sheet: Structure..............................................................................................................................................12-10
Process Instruction Maintenance........................................................................................................................12-11
Displaying Generated Process Instructions........................................................................................................12-12
PI Sheet Simulation in the Master Recipe..........................................................................................................12-13
Master Recipes, Control View: Unit Summary..................................................................................................12-14
Exercises.............................................................................................................................................................12-15
Solutions.............................................................................................................................................................12-21
Aspects of Co-Product Manufacturing.....................................................................................................................13-1
Aspects of Co-Product Manufacturing: Unit Objectives......................................................................................13-2
Overview Diagram 13..........................................................................................................................................13-3
Aspects of Co-Product Manufacturing:Business Scenario...................................................................................13-4
Typical Material Flow for the Manufacture of Co-Products................................................................................13-5
Material Master....................................................................................................................................................13-6
BOMS for the Manufacture of Co-Products........................................................................................................13-7
Material Costing: Objectives................................................................................................................................13-8
Executing a Material Cost Estimate.....................................................................................................................13-9
Aspects of Co-Product Manufacturing: Unit Summary.....................................................................................13-10
Exercises.............................................................................................................................................................13-11
Solutions.............................................................................................................................................................13-18
Aspects of Quality Inspection During Production...................................................................................................14-1
Aspects of Quality Inspection During Production: Unit Objectives....................................................................14-2
Overview Diagram 14..........................................................................................................................................14-3
Aspects of Quality Inspection During Production: Business Scenario................................................................14-4

Integration with Quality Management..................................................................................................................14-5


Inspection Lot.......................................................................................................................................................14-6
In-Process Inspection - Inspection Lot.................................................................................................................14-7
Assignment of Production Resource / Tool to Inspection Characteristics...........................................................14-8
Inspection Points, Partial Lots, and Batches........................................................................................................14-9
Specification of Batches Produced.....................................................................................................................14-10
Creating a Material Specification.......................................................................................................................14-11
In-Process Inspection - Example........................................................................................................................14-12
Aspects of Quality Inspection During Production: Unit Summary....................................................................14-13
In-Process Quality Inspection: Exercises..........................................................................................................14-14
Solutions.............................................................................................................................................................14-20
Engineering Change Management, Recipe Approval..............................................................................................15-1
Engineering Change Management, Recipe Approval: Unit Objectives...............................................................15-2
Overview Diagram 15..........................................................................................................................................15-3
Engineering Change Management, Recipe Approval: Business Scenario...........................................................15-4
Objects Linked to Engineering Change Management..........................................................................................15-5
Why Use Engineering Change Management for Changes?.................................................................................15-6
Engineering Change Management: With and Without History............................................................................15-7
Change Master Record (Change Number)...........................................................................................................15-8
Structure of a Change Master Record..................................................................................................................15-9
Change Documentation......................................................................................................................................15-10
Engineering Change Mgmt - Validity Period of Recipe Objects........................................................................15-11
Engineering Change Request / Order.................................................................................................................15-12
Structure of an Engineering Change Request.....................................................................................................15-13
Comparison of Change Master Records and Engineering Change Requests / Orders.......................................15-14
Changing Master Recipes...................................................................................................................................15-15
System Status Network Object...........................................................................................................................15-16
System Status Network for Engineering Change Requests / Orders..................................................................15-17
Recipe Approval (General Procedure)................................................................................................................15-18
Recipe Approval (Statuses I)..............................................................................................................................15-19
Recipe Approval (Statuses II).............................................................................................................................15-20
Digital Signature (I)............................................................................................................................................15-21
Digital Signature (II)..........................................................................................................................................15-22
Activating the Digital Signature.........................................................................................................................15-23
Engineering Change Management, Recipe Approval: Unit Summary...............................................................15-24
Exercises.............................................................................................................................................................15-25
Solutions.............................................................................................................................................................15-35
Summary and Conclusion........................................................................................................................................16-1
Summary and Conclusion: Unit Objectives.........................................................................................................16-2

Overview Diagram 16..........................................................................................................................................16-3


Summary and Conclusion: Business Scenario.....................................................................................................16-4
Functions of PP-PI................................................................................................................................................16-5
Data Flow in PP-PI...............................................................................................................................................16-6
Life Cycle of a Process Order..............................................................................................................................16-7
Order Processing - Further Information...............................................................................................................16-8
Process Management - Further Information.........................................................................................................16-9
QM and Batches - Further Information..............................................................................................................16-10
Summary: Exercises...........................................................................................................................................16-11
Solutions.............................................................................................................................................................16-15

0
LO305 Basic Data for Process Manufacturing

LO305
Basic Data for
Process
Manufacturing

SAP AG 2001

R/3 System
Release 4.6C
March 2001
5004 2382

0.2
Copyright

Copyright 2002 SAP AG. All rights reserved.


No part of this publication may be reproduced or transmitted in
any form or for any purpose without the express permission of
SAP AG. The information contained herein may be changed
without prior notice.

SAP AG 2002

Notes on Trademarks:
Some software products marketed by SAP AG and its distributors contain proprietary software
components of other software vendors.
Microsoft, WINDOWS, NT, EXCEL, Word, PowerPoint, and SQL Server are registered
trademarks of Microsoft Corporation.
IBM, DB2, OS/2, DB2/6000, Parallel Sysplex, MVS/ESA, RS/6000, AIX, S/390, AS/400,
OS/390, and OS/400 are registered trademarks of IBM Corporation.
ORACLE is a registered trademark of ORACLE Corporation.
INFORMIX-OnLine for SAP and INFORMIX Dynamic ServerTM are registered trademarks
of Informix Software Incorporated.
UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group.
HTML, DHTML, XML, and XHTML are trademarks or registered trademarks of W3C , World Wide
Web Consortium, Massachusetts Institute of Technology.
JAVA is a registered trademark of Sun Microsystems, Inc.
JAVASCRIPT is a registered trademark of Sun Microsystems, Inc., used under license for technology
developed and implemented by Netscape.
SAP, SAP Logo, R/2, RIVA, R/3, ABAP, SAP ArchiveLink, SAP Business Workflow, WebFlow, SAP
EarlyWatch, BAPI, SAPPHIRE, Management Cockpit, mySAP.com Logo, and mySAP.com are
trademarks or registered trademarks of SAP AG in Germany and several other countries all over the

world. All other products mentioned are trademarks or registered trademarks of their respective
companies.

0.3
Process Industry (PP - PI)
Level 3

Level 2

5 days
LO210
Production
Planning
2 days

3 days
LO320
Process Flow
Scheduler

5 days
LO305
Master Data for
Process
Manufacturing

5 days
LO310
Detail Functions of
Process Orders

Capacity Planning

3 days
LO315
Process
Management

2 days
LO930
Logistics Info
System (LIS)

Classification

5 days
LO990
Variant
Configuration Part 1

2 days
LO935
Logistics Info
Planning

3 days
LO955
Batch
Management

3 days
LO991
Variant
Configuration Part 2

LO235
KANBAN
LO060 5 days
Process
Manufacturing

LO985

SAP AG 1999

3 days

LO230

5 days

2 days
LO275
Special Features
of LIS
in Production

0.4
Prerequisites

LO060 - Planning & Control for Process Manufacturing

SAP AG 1999

0.5
Target Group

Audience
Members of project teams who are responsible for the
introduction of material masters (including batch master records),
resources, and master recipes (including BOMs) into
the R/3 System.

Duration: 5 days

SAP AG 1999

Note:
This training material is not intended to be used as self-study material but rather to complement the
trainers explanations. It therefore includes space for noting down additional information.

1
Introduction

Contents
Course goals
Course objectives
Course content
Course overview diagram
Main business scenario
Introduction to course

SAP AG 1999

(C) SAP AG

LO305

1.2
Course Goals (I)

This course will prepare you to maintain the basic data


required for process manufacturing.
This includes:
Material master and batches
Resources
Production versions
Master recipes
Material BOMs

SAP AG 1999

(C) SAP AG

LO305

1.3
Course Goals (II)

Furthermore, you will be introduced to the following


special aspects of process manufacturing:
Using engineering change management to edit a
master recipe that requires approval
Visually reproducing the manufacture of coproducts and costing of the materials involved
Planning a quality inspection during production
Preparing master data for active ingredient
management

SAP AG 1999

(C) SAP AG

LO305

1.4
Course Objectives

At the conclusion of this course, you will be able to:


Make the most important system settings

regarding the material master, resources, and


master recipes with material lists
Describe the effects of these system settings

on process manufacturing
Use engineering change management for recipe

approval
Visually reproduce the manufacture of co-

products
Perform a quality inspection in the system

during production

SAP AG 1999

(C) SAP AG

LO305

1.5
Course Content 1

Preface

Unit 1

Introduction

Unit 9

Production Versions

Unit 2

PP-PI Overview

Unit 10

Unit 3

Master Data: Overview

Master Recipes,
Operations and Phases

Unit 4

Materials

Unit 11

Master Recipes,
Materials

Unit 5

R/3 Classification System

Unit 12

Unit 6

Batches

Master Recipes,
Control View

Unit 7

Resources: Customizing

Unit 13

Unit 8

Resources: Functions

Aspects of Co-Product
Manufacturing

SAP AG 1999

(C) SAP AG

LO305

1.6
Course Content 2

Unit 14

Aspects of Quality Inspection Unit 16


During Production

Unit 15

Engineering Change
Management, Recipe
Approval, and Further
Functions

Summary and
Conclusion

SAP AG 1999

(C) SAP AG

LO305

1.7
Overview Diagram 1
1

Introduction

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes: Operations and

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

1.8
Main Business Scenario

As a member of a project team in a company,

you are responsible for creating the basic data


in the R/3 System.
The company is a process manufacturing

enterprise with chemical and pharmaceutical


divisions. It produces detergent, fertilizer, and
headache tablets.
The basic data that you will define covers

materials, batches, classes, resources, and


production versions with master recipes and
material BOMs.

SAP AG 1999

(C) SAP AG

LO305

2
PP-PI Overview

Contents:
Integration of PP-PI with the R/3 System
Application areas
Functions for representing process manufacturing in the

R/3 System

SAP AG 1999

(C) SAP AG

LO305

2.2
PP-PI Overview: Unit Objectives

At the conclusion of this unit, you will be able to:


Describe how PP-PI is integrated in the R/3

System
Tell which application areas exist for

PP-PI
Name the functions PP-PI contains

SAP AG 1999

(C) SAP AG

LO305

2.3
Overview Diagram 2
1

Introduction

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Engineering Change Management,

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes: Operations and

Aspects of Quality Inspection

Recipe Approval

SAP AG 1999

(C) SAP AG

LO305

2.4
PP-PI - Integration with the R/3 System

PP - SOP

Sales & Operation Planning

PP - MPS

Master Prod. Scheduling

Introduction
SD

PP - MRP

Material Rqmts Planning

PP

MM

CO

R/3

PP - CRP

Capacity Rqmts Planning


Shop Floor Control

AM

Client / Server
ABAP/4

QM

PP - SFC

FI

WF

PM
HR

PP - PI

PS

IS

Process Industries

PP - PC

Product Costing

.
.
.

SAP AG 1999

The R/3 System contains integrated application software that is based on an open three-level
client/server architecture. It covers the entire range of business functionality a company requires. The
systems efficiency is achieved through an integration of different application components that represent
a network of business functions. This guarantees a consistent execution of all business processes in every
area of a company. All components work on the basis of real-time processing.
With its PP-PI component, SAP offers a set of functions that meet the requirements of production
planning and control in process industries.
The PP-PI component is a fully integrated production planning and control system designed for
process industries. Since it is an integral part of the R/3 production planning component PP, it is linked
to other PP subcomponents such as Sales & Operations Planning (PP-SOP), Material Requirements
Planning (PP-MRP), Capacity Requirements Planning (PP-CRP), and Shop Floor Control (PP-SFC).
In addition, PP and PP-PI are fully embedded in the logistics chain, consisting of the R/3 components
Sales and Distribution (SD), Materials Management (MM), Production Planning (PP), and Quality
Management (QM).
Furthermore, PP-PI is linked to applications of other business areas such as the Human Resources
System (HR) and Controlling (CO).

(C) SAP AG

LO305

2.5
Application Areas of PP-PI

Process manufacturing

Batch manufacturing

Co-products / byby-products
Co
Fully and partially automated lines

Lines with variable usages

Variable production parameters

Quality assurance

Batch and production records


Target markets:

Chemical industry

Pharmaceutical industry

Food industry

Process-oriented electronics
industry

SAP AG 1999

PP-PI is designed for the batch-oriented process manufacturing company that uses integrated
planning for its production processes. Ideally, PP-PI is used in companies of the chemical and
pharmaceutical industry, the food, beverages, and tobacco industry as well as the process-oriented
electronics industry.
PP-PI meets the following typical requirements of such companies:
The production process is carried out in batches, that is, non-reproducible units that are
characterized by certain specifications. In addition, many materials entering the manufacturing
process are managed in batches with varying specifications.
During the different manufacturing steps, products, co-products, by-products, and remaining
materials are produced. If several planned materials are manufactured during one production run,
they are called co-products.
Information is exchanged between the process planning and the process control levels. Production
is carried out in automated or partially automated lines. Part of the manufacturing instructions must
therefore be displayed in natural language to be read by a process operator, whereas part of them
must be prepared for an automatic process control system.
The usage of the production lines is variable and process control is carried out using variable
parameters that differ from batch to batch.
To ensure the quality of the product, a constant coordination with quality assurance is
indispensable.

(C) SAP AG

LO305

It must be possible to archive and evaluate the planning data and actual data of the manufacturing
process for each batch.

(C) SAP AG

LO305

2.6
Positioning of PP-PI in the Enterprise Model

SD
Company management level

Production management level

FI

CO

AM

Business applications

MM

PP

PP-PI

QM

Production planning - process industries

PCS
Process control systems

Process control level

SAP AG 1999

The graphic shows the hierarchical structuring of information of an individual company. The following
levels exist:
Company management level
Production management level
Process management level
PP-PI is situated at the production management level between the upper-level business applications and
the lower-level process control systems.
PP-PI is designed to close the information gap between business applications and process control.

(C) SAP AG

LO305

2.7
Functions of PP-PI

Production planning
Master data
Material

Quality
management

Process
planning/
orders
Process
management

Process control
LIMS
Laboratory system (autom.)
PCS
information syst.

Process data
documentation/
evaluation

Resource
Master recipe

PI sheet
(manual)

PI sheet

SAP AG 1999

PP-PI comprises the following functional areas :


Resource management: The PI-specific master data of resources describes all means of production
and persons involved in the production process.
Master recipe management: The PI-specific master data of master recipes describes the
manufacture of one or more materials in one production run without relating to a particular order.
Master recipes are the basis for process orders.
Process planning comprises the planning of process orders. Process orders are created on the basis
of master recipes. They describe and monitor the actual production process.
Process management coordinates the transfer of data between PP-PI and the process control level.
It can be used in fully automated, partially automated, and manually operated plants.
Process data documentation and evaluation enables a detailed documentation and evaluation of
all planned and actual values of a process.
PP-PI is integrated with, for example:
R/3 Quality Management. Via a special interface, external laboratory information systems
(LIMS) can be linked to R/3 QM.
The higher-level planning components of R/3. Production requirements for PP-PI are created in R/3
Material Requirements Planning. Via a special interface, you can also transfer requirements
from an R/2 System or an external planning system to PP-PI.
The master data and functions of R/3 Materials Management (such as material, inventory
management).

(C) SAP AG

LO305

(C) SAP AG

LO305

2.8
Data Flow in PP-PI

Production reqmts

Materials
Material master
Bill of material
Resources
Proc. units
Personnel

PP

Planned order

PP-PI

Process order

Master recipe
Manually

MM
Process data documentation & evaluation

Process management

QM
Process
messages

Automatic control
Manual control (PI sheet)

Control recipe:
proc. instructions

Process control
system

Process
control level

SAP AG 1999

A production process is triggered by production requirements. Production requirements are created in


material requirements planning in the form of planned orders. Planned orders define the basic dates and
planned production quantities.
During process planning, planned orders are converted into process orders. The basic dates and
production quantities are copied from the planned order. The actual production dates are calculated using
the basic dates. You can also create a process order manually.
A process order provides a detailed description of the actual production of one or more materials in one
production run. It is the main control instrument in production, describing and monitoring all planned
and actual data relating to production.
A master recipe is used as the basis for a process order. It defines, for example, the planned resources
and material components.
After a process order has been released for production, the process instructions maintained in the order
are bundled into control recipes by process management. The control recipes are either transferred to a
process control system via a specific interface or are displayed online in the form of a process
instruction sheet (PI sheet) that can be read and maintained by process operators.
Process management in turn receives process messages from the process control level and transfers
them to various destinations. For instance, it is possible to record confirmations for the process order,
transfer actual values of the process to functions for process data documentation and evaluation, post
material consumptions or production yields as goods movements and transfer quality data to Quality
Management results recording.

(C) SAP AG

LO305

10

(C) SAP AG

LO305

11

2.9
PP-PI Overview: Summary

The PP-PI component covers the requirements of

production planning and production control in


process industries.
The application area of PP-PI is the batch-oriented,

process manufacturing enterprise.


The process order describes in detail the concrete

production of a material in one production run.


The source for the order is the master recipe.
Process management coordinates the data

exchange between PP-PI and the process control


level.

SAP AG 1999

(C) SAP AG

LO305

12

2.10Exercise Data
Key to the symbols in the exercises and solutions:
Exercises
Solutions
Unit Objectives
Business Scenario
Tips & Tricks
Warning

Data Used in Exercises


Data

Data in Training
System

Data in IDES
System

Plant

1100

1100

Master recipes

T-DET100

T-DET100

T-RC1##

T-RC100

T-TAB##

N-2100

T-ICE##

T-ICE00

COLORS

COLORS

T-JUI100

T-JUI100

T-DTM1##

T-DTM100

T-DTR1##

T-DTR100

Resources
(C) SAP AG

LO305

13

T-DTR2##

T-DTR200

T-DTR3##

T-DTR300

T-DTA1##

T-DTA100

T-DTG1##

T-DTG100

T-IC1##

T-IC100

T-JM100

T-JM100

Secondary resource

T-DTT1##

T-DTT100

Material, ROH

T-RD1##

T-RD100

T-RD2##

T-RD200

T-RD4##

T-RD400

T-RD5##

T-RD500

T-RF1##

T-RF100

T-RF2##

T-RF200

T-RF3##

T-RF300

T-RJ1##

T-RJ100

T-RJ2##

T-RJ200

T-RJ3##

T-RJ300

T-RI5##

T-IC-R2006

Material, PIPE

T-RD3##

T-RD300

Material, HALB

T-FF3##

T-FF300

T-Hat2##

N-2100

T-FD1##

T-FD100

T-FF1##

T-FF100

T-FJ1##

T-FJ100

Material, FERT

(C) SAP AG

LO305

14

Characteristics

Classes

M100

M100

M200

M200

M700

M700

M800

M800

M900

M900

023_14

023_14

023_15

023_15

023_20

023_20

023_21

023_21

## = 01 - 20

(C) SAP AG

LO305

15

2.11Exercises
Unit: PP-PI Overview: Overview PP-PI
Topic: Logging on to the System/ Menu Paths

At the conclusion of these exercises, you will be able to:


Log on to the system
Find the menu paths for process industries
Create a user menu
You are a member of your company's project team and are responsible for
creating the basic data in the R/3 System.
Your company is a process manufacturing enterprise with chemical and
pharmaceutical divisions. It produces detergent, fertilizer, and headache
tablets.
The basic data that you will define includes materials, batches, classes,
resources, and master recipes.
1-1

Logging on to the system


1-1-1 Log on to the PC
USER:
PASSWORD:
1-1-2 Log on to the R/3 System
CLIENT:
USER:
PASSWORD: INIT
LANGUAGE: EN

1-2

Overview of the menu paths for process industries in the SAP menu
Familiarize yourself with the menu paths in the SAP menu.
Familiarize yourself in particular with the master data that can be selected and
maintained in Production Process

(C) SAP AG

LO305

16

1-3

Creating a role (user role)


Create your own role by selectively copying the role LO305_EN and giving it the
name LO305_## with the description Role for LO305 group ## . Do not copy the user
that is already assigned.
Add the SAP homepage to your role. The web address is www.sap.com.
Move your web address so that it is below Customizing in your role menu.
Assign your user ID to the role.
Save your role.
Open a second session and select the menu for your activity group. In this session, the
changes are effective.
Compare the structure of your user menu with that of the SAP standard menu.
Close the first session.
Your user menu was specifically created for this course and
contains all transactions you need to do the exercises. The
structure of the user menu can be adjusted at any time to
meet your individual needs. For this reason, the menu paths
in the solutions refer to the SAP menu, not to the individual
user menu.

(C) SAP AG

LO305

17

2.12Solutions
Unit: PP-PI Overview
Topic: Logging on to the System/Menu Paths

1-1

Logging on to the System

1-2

Overview of the Menu Paths for Process Industries


Master Data: Material master
Production Versions
Resources
Master Recipes
Engineering Change Management
Production Resources / Tools

1-3

Choose Create role.


Enter role LO305 DE.
Choose Copy role
from role:

LO305_DE to role:

LO305_##

Choose Copy selectively.


X

Personalization

Choose Continue.
Choose Change.
Description: Role for LO305 group ##
Choose the Menu tab page.
Choose Other.
X

Web address or file

Choose Continue.
Text: For example, SAP Homepage
Web address or file: www.sap.com
Choose Continue.
(C) SAP AG

LO305

18

Select the Web address and use the Move down button to move it to another position.

(C) SAP AG

LO305

19

User tab page


User ID: PI-##
Save
Choose Create a new session.
Choose User menu.
In the first session, choose System -> Delete mode.

(C) SAP AG

LO305

20

3
Master Data: Overview

Contents:
Material
Batch
Resource
Production version
Master recipe with material BOM

SAP AG 1999

(C) SAP AG

LO305

3.2
Master Data: Unit Objectives

At the conclusion of this unit, you will be able to:


Distinguish between the definitions of material

and batch
Define resources
Explain what a production version is
Define the components of a master recipe along

with its material BOM

SAP AG 1999

(C) SAP AG

LO305

3.3
Overview Diagram 3
1

Introduction

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes: Operations and

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

3.4
Master Data: Business Scenario

Before you start maintaining master data in the

R/3 System, get an overview of the R/3


terminology and the following PP-PI basic data
objects:
Material and batch
Resource
Production version
Master recipe with material BOM

SAP AG 1999

(C) SAP AG

LO305

3.5
Master Data Overview

Batch
Batch

Material
Batch
Batch

Batch
Batch

Resource

..
.
Production version

Master recipe

Material BOM

SAP AG 1999

Master data is data in the R/3 System that remains unchanged over an extended period of time. It
contains information that is used in the same manner for similar objects.
The material is the central master record in Logistics. In general, SAP defines a material as a substance
or commodity that is bought or sold on a commercial basis, or is used, consumed or created in
production.
A batch is a subset of a material with unique specifications. The batches of one material are managed
separately in stock. With regard to the production process, a batch is a quantity of a material produced in
a given production run. This quantity, therefore, represents a non-reproducible unit with unique
specifications.
The PI-specific master data of the resource describes all means of production and persons involved in
the production process.
A production version determines which alternative BOM is used together with which master recipe.
The PI-specific master data of master recipes describes the manufacture of one or more materials in one
production run without relating to a particular order.
Material BOMs are used to represent the structure of products that a company manufactures.

(C) SAP AG

LO305

3.6
Material

Material

Material
Substance or commodity that is bought or sold on a
commercial basis, or is used, consumed, or created in
production. A material can also be a service.

SAP AG 1999

A material master record contains data of a descriptive nature (such as size, dimension, weight) and data
with a control function (such as material type).
In addition to this data, which can be maintained by the user, the material master record also contains
data that is automatically updated by the system (such as stock levels).
An alphanumeric material number identifies a material master record in the system. This material
number is unique at the client level.
Depending on its function or usage, master record data is assigned to different organizational levels
(such as plant, storage location, sales organization).
A material master record comprises different views. A view groups all data on a material created by a
particular department (such as Purchasing, MRP, Work scheduling) in the master record.
Depending on their usage and requirements, material master records are grouped into material types.

(C) SAP AG

LO305

3.7
Batch
Batch
Batch

Batch
Batch

Material
Batch
Batch

..
.

Batch
Batch

Subset of the total quantity of a material held in stock. This


subset is managed separately from other subsets of the same
material.
Quantity of a material produced during a given production run.
A batch represents a non-reproducible, homogeneous unit with
unique specifications.

SAP AG 1999

In a process manufacturing company, production is usually executed in batches. In addition, many


materials entering the process are managed separately in batch stocks with different specifications.
In the R/3 System, batch master records depend on the corresponding material master record. Batches
are created for a material.
In general, the data of a material master record is valid for all batches assigned to it. In contrast, a batch
master record contains data that uniquely identifies a batch and characterizes it as a non-reproducible
unit.
A batch master record is identified by an alphanumeric batch number. In accordance with the structure of
your plant or company and your operational requirements, you can choose whether you want the batch
number to be unique in combination with a material and a plant, in combination with a material number,
or at client level.

(C) SAP AG

LO305

3.8
Resource

Processing
unit

Waste disposal
facility

Labor

Resources

Transport
Energy

Means of production and persons in the production process that have capacities
assigned to them. Resources are subdivided into resource categories.

SAP AG 1999

Resources are the main planning instruments of production planning and control. The data you maintain
for a resource is, for example, used for:
Scheduling process orders
Capacity requirements planning
Product and order costing
Resources are grouped in resource categories on the basis of their usage and function. You can define
your own resource categories in Customizing.

(C) SAP AG

LO305

3.9
Production Version

Production version
A production version determines which alternative BOM is
used together with which master recipe to produce a
material or create a master plan for a material.
More than one production version for different validity
periods and lot-size ranges can be assigned to a material.

SAP AG 1999

Production versions are used both in discrete manufacturing and process manufacturing.

Production versions are used in Sales & Operations Planning (SOP), material requirements planning
(MRP), process order creation, and product costing to select the most suitable task list or recipe and the
corresponding material list.

(C) SAP AG

LO305

3.10
Master Recipe
Proc. planning

Proc. control

EBF/ISA(S88)/NAMUR
Steps in the
prod. process

Control
information

Master
recipe
Quality
inspec. data

Resources

Materials

Process order Control recipe

SAP AG 1999

A master recipe defines the following data that is required for the manufacturing of materials without
relating to a particular order: processing steps, resources, material components, data for quality
inspection during production, and control information for the process control level.
Master recipes have a planning and a control view. The planning view comprises the planning of
operations, materials, resources, and inspection characteristics, realizing links to the R/3 application
components PP, MM, SD, WM, and QM. The control view contains information required for
communicating with the process control level.
The master recipe is the basis for creating process orders. A process order describes an actual production
process. It contains all the information specified during process planning, such as the production date
and quantities to be produced.
A control recipe contains all the information necessary for the execution of a process order by a certain
process control system or a line operator. Control recipes are generated from the process instructions in a
process order and sent to the corresponding destination in process control. Process instructions are
defined in the master recipe the process order is based on.
Three organizations have defined the data that must be included in the standard recipe maintenance of
the PP-PI module:
The European Batch Forum (EBF)
The Instrument Society of America (ISA; with standards S88)
NAMUR (Norms working committee for measuring and control techniques in the
chemical industry).

(C) SAP AG

LO305

10

(C) SAP AG

LO305

11

3.11
Bill of Material - Definition
Bill of material
Material
(to be produced)
Material
component 10
Material
component 20
Material
component 30
Material
component 40

Bill of material

A complete, fully structured list of the components that


make up a product or assembly. The list contains the object
number of each component together with the quantity and
unit of measure.

SAP AG 1999

Bills of material (BOMs) contain important basic data used in many different organizational areas.
BOM data is, for instance, important for:
Material requirements planning
Material staging during production
Product costing

(C) SAP AG

LO305

12

3.12
BOM Categories

Material

Material BOM

Sales order BOM

WBS BOM

Equipment BOM

Funct. loc. BOM

Document

Doc. structure

SAP AG 1999

BOM categories are used to represent different objects.

Material BOMs are used to represent the structure of products that a company manufactures.

Sales order BOMs are used to represent the specific bill of material used to manufacture a product for a
specific sales order.

Work breakdown structure BOMs (WBS BOMs) are used to enter components in the project system.

A document may consist of several different documents such as a program, drawings, manuals, and
photos. Document structures are used to represent this. They are created for a single document
information record and are maintained in the R/3 document management system.

Equipment BOMs are used in Plant Maintenance to describe the structure of a piece of equipment and
to assign spares to the piece of equipment for maintenance purposes.

Functional location BOMs are used in Plant Maintenance to tie equipment to a particular location
within a facility.

(C) SAP AG

LO305

13

3.13
Master Data: Unit Summary

The most important master data in PP-PI are material,

resource, and master recipe.


A batch is a subset of a total quantity of a material

with unique specifications.


Resources are means of production and persons

involved in the production process that have


capacities assigned to them.
Production versions serve to assign a master recipe

to a material BOM.
A master recipe defines processing steps, resources,

material components, QM data, and control


information required for the manufacturing of
materials without relating to a particular order.

SAP AG 1999

(C) SAP AG

LO305

14

4
Materials

Contents:
Material Master Record: Definition
Material Type
Field Selection
User-Defined Material Master Record
Creating Material Master Records

SAP AG 1999

(C) SAP AG

LO305

4.2
Materials: Unit Objectives

At the conclusion of this unit, you will be able to:


Define the term "material master"
Create a material type
Make field selection settings
Make user-specific configurations
Create material master records

SAP AG 1999

(C) SAP AG

LO305

4.3
Overview Diagram 4
1

Introduction

PP-PI Overview

10 and Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes: Operations

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

4.4
Materials: Business Scenario

Your company is going to put a new

detergent on the market.


You are responsible for the definition of the

material masters that are required for the new


product:
Raw materials
Finished product

SAP AG 1999

(C) SAP AG

LO305

4.5
Material Master Records: Definition

Material
Substance or commodity that is bought or sold on a
commercial basis, or is used, consumed, or created
in production. A material can also be a service.

Material master record


Data record containing all data required for
managing a material;
the data is arranged according to various criteria.

SAP AG 2001

Materials are created as material master records and identified using a material number.
A material master record contains data of a descriptive nature (such as size, dimension, weight) and data
with a control function (such as material type).
In addition to this data, which can be maintained by the user, the material master record also contains
data that is automatically updated by the system (such as stock levels).
An alphanumeric material number identifies a material master record in the system. This material
number is unique at the client level.
Depending on its function or usage, master record data is assigned to different organizational levels
(such as plant, storage location, sales organization).
A material master record comprises different views. A view groups all data on a material created by a
particular department (such as Purchasing, MRP, Work scheduling) in the master record.

(C) SAP AG

LO305

4.6
Material Master Records: Views

Purchasing

Sales

Basic data

Quality
management

MRP

Work
scheduling

St

Plant / Storage
location stock
A

XX

XX

Material
master record

Forecasting

Accounting

Classification

Storage

Warehouse
management

SAP AG 1999

Each department of a company needs to maintain different information on a material. Therefore, the
material master record comprises different views.
A view groups all data on a material created by a particular department (such as Purchasing, MRP, Work
scheduling) in the master record.
In accordance with their different usages, the materials of a company are grouped together in material
types. The material type controls, for example, which views of a material master record can be accessed.
Master record data is assigned to different organizational levels of the R/3 System. When maintaining
specific views, you must therefore enter the organizational units (such as plant, storage location, and
purchasing organization) for which you want to maintain the data.
For each user, you can specify which views of the material master record may be maintained or
displayed.

(C) SAP AG

LO305

4.7
Material Type

Material type
Term for the subdivision of materials into different
groups such as raw materials, semi-finished products,
finished products, configurable materials, process
materials, intra materials.
The material type controls, for instance, the material's
procurement type, screen sequence and field
selection, inventory management type, and account
determination in financial accounting.

SAP AG 1999

Within a company, different materials are used for different purposes. Material master records must
therefore meet different requirements with regard to views to be maintained and control of certain
business transactions. To achieve this, materials are assigned to different material types in the R/3
System.

(C) SAP AG

LO305

4.8
Control Using Material Type

Procurement type
Material

Views for material maintenance


Number assignment (check external numbers Y/N)
Type of inventory management (quantity/value)
Assignment of account categories and references

Mat. type

Field selection and screen sequence


General indicator

(pricing for pipeline,


process, configurable)

Costing control
Item category group in SD
Authorization group

SAP AG 1999

You specify a material type for each material. It is part of the general data of a material.
The material type defines the following:
Which procurement type is set, that is, whether external or internal orders are possible
Which views can be maintained by which user departments
Whether material numbers can be checked against a number range
Whether stock quantities and stock values can be updated
Which material accounts are assigned
The field selection and screen sequence in material master maintenance
Costing control for a material
The determination of item category groups for sales documents
Control of data access via authorization groups

(C) SAP AG

LO305

4.9
Industry Sectors and Material Types

SAP R/3 Material Types

ROH - Raw materials

HALB - Semi-finished products

FERT - Finished products

KMAT - Configurable materials

HAWA - Trading goods

INTR - Intra materials

PROC - Process materials

VERP - Packaging materials

Raw materials
Raw materials

Semi-finished products

Finished products

Miscellaneous

Semi-finished products

Finished products

Miscellaneous

.
.

SAP AG 1999

The material types ROH (for raw materials), HALB (for semi-finished products), FERT (for finished
products) and KMAT (for configurable materials) are generally used in production.
The material types PROC and INTR are specifically used in process industries:
The material type PROC (process material) can be used to represent the manufacture of co-products
that is not initiated by material requirements planning.
The material type INTR (intra material) describes materials that exist only temporarily in a process.
The industry sector determines to which branch of industry the material is assigned.
The industry sector determines which fields are required fields in material master data maintenance.

(C) SAP AG

LO305

4.10
Field Selection: Influencing Factors

Transaction

..................

Material type

Procurement
indicator
?

..................
..................

Field selection
Plant

Industry sector

SAP / user

SAP AG 1999

(C) SAP AG

LO305

10

4.11
Field Selection: Influencing Factors - Field
Reference
Influencing factor

Field reference

Examples
HALB

Material
Material type
type HALB
HALB

Z01

Material type PI01

1100

Plant 1100

Industry sector C

Transaction MM02

MM02

Procurement indicators E / F

E/F

SAP

SAP1
SAPR

User

KB

SAP AG 2001

Each influencing factor is assigned its own field reference for field selection.
You can define field references for the material type, plant, and industry sector.
The field references for the other influencing factors are predefined.

(C) SAP AG

LO305

11

4.12
Field Selection: Field Selection Group (Example)

Field name
Field selection
group
015

MARA-FERTH

1:n

Field name
MARA-FORMT

Field name
MARA-KZUMW

SAP AG 1999

The material master fields are grouped in field selection groups.

(C) SAP AG

LO305

12

4.13
Field Selection: Field Selection Groups and Field
References
Field selection
group 1

Field selection
group 2

MARA-MEINS

MARA-MATKL

T006A-MSHT

Field selection (field sel. grp 1)


Field ref. Hide

Field selection (field sel. grp 2)


Field ref. Hide

PROC

P
PROC

ROH

ROH

SAP1

SAP1

Displ. Reqd. Opt.

(and so on)

Disp. Reqd.Opt.

SAP AG 2001

All field selection groups are assigned to all field references.


The field options (hide, display, required entry, optional entry) are defined for each field selection group
and field reference.

(C) SAP AG

LO305

13

4.14
Field Selection: Link Rules
Examples

Link rules

Field sel. Field sel. Field sel.


grp 1
grp 2
grp 3

Industry sector

Transaction

Procurement
indicator

SAP / user

.
+

Material type
Plant

for field selection groups

SAP AG 1999

Field references of several influencing factors (such as the material type or plant) determine the field
selection.
The field references define the field options (hide, show, required entry, optional entry) for the
indvidual field selection groups.
All field option entries valid for each operation are linked together per field selection group.
The link rules shown in this graphic determine the result of the field selection for a field selection
group.
In order of priority, the signs mean the following:
- Hide
* Show
+ Required entry
. Optional entry

(C) SAP AG

LO305

14

4.15
Customized Material Master
You can structure the material master according to
the requirements of your company:

You can remove screens that you do not need from the
screen sequence.

You can create your own screens by adding or


deleting screen modules.

You can influence individual fields in the screen


modules.
Screen
modules

Screens

Screen
sequences

Basic data

Basic data
Sales
Purchasing

SAP AG 1999

Customized material master screens support sufficient data maintenance by creating entry dialogs
specific to your company's data requirements.
The material master is a set of logical screens organized in a specific sequence when more that one view
is selected. This organization of logical screens is referred to as a screen sequence.
Each logical screen consists of several programmed sets of material master fields. In the R/3 System,
these sets are referred to as screen modules or subscreens. The fields assigned to each screen module
cannot be changed in Customizing.
In Customizing for the Material Master you can:
Maintain screen sequences
Maintain logical screens
Maintain the order of logical screens in a screen sequence
Determine which screen modules are displayed on which logical screens
Assign field selection influencing factors to a screen sequence
Assign a user or group of users to a screen sequence
Enter default values for the organizational level, the industry sector, and the logical screens for a user
or a group of users

(C) SAP AG

LO305

15

4.16
Creating a Customized Material Master

Copy standard screen sequence (such as "01)


Use your own name range for screen sequence => Y*, Z*
Delete, extend, or change logical screens in the new sequence
a) Use standard screen modules (recommendation)
b) Use field selection to show/hide fields

Logical
screen

c) Program and integrate user-specific screen modules


d) Define the sequence of screen modules in the logical screen

Define sequence of logical screens in the screen sequence


Link the new screen sequence to influencing factors

SAP AG 1999

Note:
When you create your own logical screens, it is a good idea to use the standard screen modules that
already exist.
You need your own screen modules if you require non-standard field groupings or new fields.
To create your own screen modules, copy the standard program SAPLMGD1 into your own function
group (for instructions, see IMG). Then you can create the subscreens you require in the new function
group.
Append structures are defined in the Data Dictionary so that you can integrate your own fields.
You can only integrate fields from user-specific tables and user-specific subsreen containers in the
SAPLMGMM program by using modifications.
You must use Customizing to create your own material master dialogs.

(C) SAP AG

LO305

16

4.17
Influencing Factors for Screen Sequences

Combinations of screen
references:

Influencing factors:
Transaction

Screen ref. transaction

01

01

User

Screen ref. user

Material type

Screen ref. material type

Industry sector

Screen ref. industry sector

01

Y1

Screen sequence

TEMPLATE

*
*

SAP AG 1999

You can create a screen reference for user, material type, and industry sector.
The screen references for transactions are predefined.
The screen sequence becomes valid for the appropriate user, material types, and industry sectors when
you assign the screen references to this screen sequence.
In the example in the graphic, the screen sequence 01 is valid for all users who are assigned to the
"Template" reference, irrespective of industry sector and material type.

(C) SAP AG

LO305

17

4.18
Screens for Material Master Maintenance

Material

St
A

Purchas- Work
ing scheduling

MRP

Forecasting

Sales

Accounting

Texts

Document
data

Units of
measure

Administrative Consumption
data

SAP AG 1999

To maintain a material, you enter the material number on the initial screen. You then select the
organizational levels and views of the main data screens.
The data screens on the main level are displayed in a standard sequence. However, you can jump from
screen to screen and thus interrupt the standard sequence.
To reach the additional data screens, choose the menu option Extras from within the corresponding view.

(C) SAP AG

LO305

18

4.19
Materials: Summary

The material master is the central master record

for logistics.
The material is identified using the material

number.
Maintenance takes place in individual material

views.
The material type groups materials and controls

how they are processed.


Material types that are commonly used in PP-PI

are: ROH, HALB, FERT.

SAP AG 1999

(C) SAP AG

LO305

19

4.20Exercises
Unit: Materials
Topic: Material Master Records

At the conclusion of these exercises, you will be able to:


Make system settings for materials
Create material master records

Your company is going to put a new detergent on the market.


You are responsible for the definition of the material masters that are
required for the new product:
Raw materials
Finished product

1-1

Settings for material types


In the IMG (implementation guide/Customizing), display the material types that are
defined for finished products, semi-finished products, and raw materials.
1-1-1 Write down the settings for the parameters in the table below.

Parameters

Finished
Products

Semi-finished
Products

Raw
Materials

Material type
Are internal orders allowed?
Are external orders allowed?
Which of the following fields are
selected in the User departments
area?
Sales?
Costing?
Purchasing?
MRP?
(C) SAP AG

LO305

20

Parameters

Finished
Products

Semi-finished
Products

Raw
Materials

Work scheduling?
Which price control is set?
Does a quantity update take place
for the material type?
1-1-2 What does the External no. assignment w/o check indicator specify?
______________________________________________________
______________________________________________________
______________________________________________________
1-1-3 What does the With qty structure indicator specify?
______________________________________________________
______________________________________________________

1-2

Creating a new material type


Copy the material type for the semi-finished product HALB.
Enter a new material type PI## (## = group number).
The description of the material type is "PI Group ##".
Set the following parameters for the new material type:

External and internal orders are allowed.

Externally assigned material numbers are checked against a number range.

Product costing with a quantity structure (BOM, routing)

For materials of this material type, the following areas may be maintained:
Work scheduling

Classification

MRP

Storage

Basic data

Plant and storage location stock

Costing

(C) SAP AG

In all plants (valuation areas), quantities and values are to be updated for
materials of this material type.

All materials of this material type (not changeable) are to be valuated according to
the moving average price.

LO305

21

1-3

Account assignment is to take place according to account category reference


0008, the same as for material type HALB.

Save the material type.

Field selection settings for the material type


The material type PI## is used for semi-finished products that are copied from an
external system.
Make the following material fields a required entry for material type PI##:
Old material number
Cross-plant material status

(MARA-BISMT)
(MARA-MSTAE)

1-3-1 To which field selection groups are these fields assigned?


______

______

1-3-2 Is the content of this field copied (proposed) when you create using a reference
material?
__________
1-3-3 Which other field belongs to these groups ?

______

1-3-4 Copy field reference Z## and specify that these fields are required fields.
Copy the field reference for the semi-finished product HALB.
Save your settings.
1.3.5

Assign the field reference Z## to your material type PI##.

1.3.6

Test your settings by creating material T-PI## with material type PI-## (only
the Basic data 1 + 2 views). Notice which views the system displays.
Notice that the fields previously processed are now required entries.
You can make any entry in the old material number fields of this material. Use
material status 01 with today as the valid from date. Cancel without saving.

1-4

Creating a customized material master


Set up a user-specific screen sequence Y# or Z# (free number) for material master
maintenance.
Use screen sequence 21 "Std ind.(short) tab" as a template for your screen sequence
Y# or Z# "Screen sequence: PI Gr.##".

(C) SAP AG

LO305

22

1-4-1 From data screen 08 (basic data 2), copy the screen module environment
(2010) to data screen 07 (basic data 1). Then delete data screen 08 and name
data screen 07 "basic data".
1-4-2

Control your screen sequence Y# or Z# in a way that the following sequence


appears:
Screen 1
Screen 2
Screen 3
Screen 4
Screen 5

Basic data
MRP 1 - 4
Work scheduling
General plant data/storage
Classification

The rest of the sequence after these screens remains the same.
1.4.3

The screen sequence is to be valid for your user PI-##. Define a screen
reference for your user and create a new screen sequence control (for all
material types and branches).

1.4.4

Open a second session and check your settings by displaying material master
record T-RD2##.
Reverse your changes from exercise 1-4-3 for the rest of the exercises.

1-5

Default settings for industries and organizational levels


To make entering data easier, define default data for the branch (chemicals) and
organizational level (1100 as the default plant and source plant) before you create the
material master records. Define the default settings in a way that the industry and
organizational fields only appear when you need them.

1-6

Creating material master records


1-6-1 Raw materials
Create the following material with the material type raw material by copying:
Material

Material
type

Copy from

T-RD1##

Raw
materials

T-RD100

In the Select View(s) dialog box, select all of the views except Warehouse
management 1 and 2.
On the Basic Data 1 screen, check the following description for your material:
Material
(C) SAP AG

Material description
LO305

23

T-RD1##

Sulfuric acid

Go through all of the data screens and save the material master record when you
reach the last data screen.
The material mentioned above is a raw material that will be
needed to produce the product.

1-6-2 Finished product


Create material T-FD1## with the material type finished product by copying
material T-FD100:
Material

Material type

Copy from

T-FD1##

Finished product T-FD100

In the Select View(s) dialog box, select all of the views.


On the Basic Data 1 screen, check the following description for your finished
product:
Material

Material description

T-FD1##

Detergent, group ##

Go through all of the screens and save the material master record when you
reach the last data screen.
In this course, you will create a master recipe for the production
of finished product T-FD1##.

(C) SAP AG

LO305

24

1-7

Displaying the material master record:


Display the following materials.
What type of materials are they and which material categories are assigned to them?
Material

Industry Material
sector
type

Material description

T-RD2##
T-RD3##
T-RD4##
T-RD5##
These materials will be used for the production of the finished
product T-FD1## along with the raw material in exercise 1-6-1.

(C) SAP AG

LO305

25

4.21Solutions
Unit: Materials
Topic: Material Master Records

1-1

Settings for material types


SAP standard menu Tools AcceleratedSAP Customizing Project
Management [SAP Reference-IMG] Logistics - General Material Master
Basic Settings Material Types Define Attributes of Material Types
Display
1-1-1 Solution table
Double-click the material type.

Parameters

Finished
Products

Semi-finished
Products

Raw
Materials

Material type

FERT

HALB

ROH

Are internal orders allowed?

Yes

Yes

No

Are external orders allowed?

Allowed with
warning

Yes

Yes

Sales?

Yes

Yes

No

Costing?

Yes

Yes

Yes

Purchasing?

Yes

Yes

Yes

MRP?

Yes

Yes

Yes

Work scheduling?

Yes

Yes

No

Standard price

Standard price

Moving average
price/periodic
unit price

By valuation
area

In all valuation
areas

In all valuation
areas

Which of the following fields are


selected in the User departments
area?

Which price control is set?

Does a quantity update take place


for the material type?

(C) SAP AG

LO305

26

1-1-2 What does the External no. assignment w/o check indicator specify?
Choose the F1 help for the field.
If the indicator is set, the material number can be entered manually and it is
not compared with the number range for the material type. If the indicator is
not set, the number entered is compared with the external number range if
external numbers are allowed for this material type.
1-1-3 What does the With qty structure indicator specify?
Choose the F1 help for the field.
This field is used to specify whether product costing is carried out with or
without a quantity structure (BOM and routing).
1-2

Creating a new material type


Tools AcceleratedSAP Customizing Project Management SAP
Reference IMG Logistics - General Material Master Basic
Settings Material Types Define Attributes of Material Types Copy
as ... PI## PI Gruppe ##
Make the settings as described.

1-3

Setting the required fields


You first determine the number of the field selection group.
Tools AcceleratedSAP Customizing Project Management SAP Reference
IMG Logistics - General Material Master Field Selection Assign Fields
to Field Selection Groups
1-3-1 Field selection groups
Go to Position cursor
MARA-BISMT:
MARA-MSTAE:

11
155

1-3-2 Detail screen for field names: Since the Propose field content indicator is set,
the contents of the fields are copied when they are created.

(C) SAP AG

LO305

27

1-3-3 Tools AcceleratedSAP Customizing Project Management SAP


Reference IMG Logistics - General Material Master Field Selection
Maintain Field Selection for Data Screens
Enter field selection group 11 in the appropriate field and choose Enter. No
other fields belong to field selection group 11.
Repeat the procedure for field selection group 155. The fields MARA-MSTAE
and MARA-MSTDE belong to group 155.
Choose Details.
1-3-4 Copy field reference Z## and specify that these fields are required fields.
Copy the field reference for the semi-finished product HALB.
Select the line HALB and copy it to Z## (Edit Copy as). Call up the field
groups 11 and 155 in the field reference Z## you just copied. Change the field
option to a required entry.
Save your settings.
1-3-5 Assign field reference Z## to your material type PI##.
Tools AcceleratedSAP Customizing Project Management SAP
Reference IMG Logistics - General Material Master Basic Settings
Material Types Define Attributes of Material Types
Select material type PI## and choose Goto Details.
Field reference Z## instead of Halb.
Save your settings.
1-4

Copy the screen sequence 21 by choosing Edit Copy as....


SAP standard menu Tools AcceleratedSAP Customizing Project
Management [SAP Reference-IMG] Logistics - General Material Master
Configuring the Material Master-> Define Structure of Data Screens for Each
Screen Sequence
Save the screen sequence.

(C) SAP AG

LO305

28

1-4-1 Select your screen sequence and double-click the entry Data screen in the
dialog structure.
Select data screen 08 Basic Data 2 and double-click the entry Subscreens in
the dialog structure.
Choose View data screen. Notice the simulation of the logical screen. Choose
Cancel. Select the subscreen with Screen number 2010 and choose View
subscreen. You now see the Environment screen module .
Go back to the Change view "data screen": Overview screen by doubleclicking Data screens in the dialog structure.
Select data screen 07 Basic data 1 and double-click the entry Subscreens in
the dialog structure.
Add the screen module (subscreen) Environment to this data screen by
overwriting screen number 0001 (=empty screen module) with the number
2010. Choose View data screen. The Environment screen module is now
copied to the Basic data 1 data screen. Choose Cancel. Double-click the
entry data screens in the dialog structure. Select data screen 08 basic data
and choose Edit -> Delete. Change the screen description and the alternative
screen description of data screen 07 to Basic data. Save your changes.
1-4-2 SAP standard menu Tools AcceleratedSAP Customizing Project
Management [SAP Reference-IMG] Logistics - General Material
Master Configuring the Material Master-> Maintain Order of Main and
Additional Screens.
Select the screen sequence and choose Goto->Details.
For the data screens MRP 1-4, Work scheduling and General plant data/storage,
enter ascending numbers in this sequence that are between the numbers of the
data screens Basic data and Classification in the column for sequential
numbers. Example :
MRP 1 Current No.: 11
MRP 2 Current No.: 12
MRP 3 Current No.: 13 etc.
Choose Sort main screens. The screens are put in a new order. Save your
changes.
1-4-3 SAP standard menu Tools AcceleratedSAP Customizing Project
Management [SAP Reference-IMG] Logistics - General Material
Master Configuring the Material Master-> Assign Screen Sequence to
User/Material Type/Transaction/Industry Sector
Double-click User screen reference in the dialog structure and then New
entries. Enter your user name PI-## in the first column and your screen
sequence number Y# or Z# in the second column.
Save your entries.
It is not necessary to define the screen sequence control before the
user. It is only a selection criteria for controlling the screen
sequence. The assignment of one entry to different users allows
you to group the users.
(C) SAP AG

LO305

29

Double-click Screen sequence control in the dialog structure and then New
entries. Enter the following and then save:

SRef:trans.

SRef:user

SRef: matl type

SRef: industry

SSq

01

Y# or. Z#

Y# or Z#

1-4-4 Testing the settings:


Open a second session:
SAP standard menu Logistics Production Process Master Data
Material Master Material Display Display current
Display material master T-RD2##. Notice the sequence of the views in view
selection.
Choose the Basic data view. The Environment screen module appears.
Reversing changes made in exercise 1-4-3:
In the Change View Screen Sequence Control: Overview view, delete your
entry in the Control Screen Sequence table. Choose Edit Delete. Save after
deleting and check your settings by displaying material master T-RD2## again.
1-5

Default settings for industry sectors and organizational levels


SAP standard menu Logistics Production - Process Master Data
Material Master Material Create general Immediately
Enter a material type, such as "raw material" and a branch such as "chemical
industry".
Choose Defaults Industry sector. Choose "Chemical industry". Select the Hide
industry sector on initial screen indicator.
Choose Defaults Organizational levels. Enter plant 1100, source plant 1100.
Select the Org.levels/profiles only on request indicator.
You can also maintain the user settings in Customizing by choosing:
SAP standard menu Tools AcceleratedSAP Customizing
Project Management [SAP Reference-IMG] Logistics General Material Master Configuring the Material Master->
Maintain User Settings

1-6

Creating material master records


1-6-1 Raw materials

(C) SAP AG

LO305

30

Material Master : Material -> Create (general) -> Immediately


Select all in the view selection.
1-6-2 Finished product
Material Master / Material -> Create (general) -> Immediately
Select all in the view selection.

1-7

Displaying the material master record:


Material

Industry
sector

Material type Material description

T-RD2##

ROH

Lauryl Alcohol

T-RD3##

PIPE

Water

T-RD4##

ROH

1-Butanol

T-RD5##

ROH

Sodium hydroxide

Material master menu / Material -> Display -> Display Current


Choose Information on material.

(C) SAP AG

LO305

31

5
R/3 Classification System

Contents:
Creating characteristics and classes in the R/3 classification
system
Classifying objects
Classifying objects for process manufacturing

SAP AG 1999

(C) SAP AG

LO305

5.2
R/3 Classification System: Unit Objectives

At the conclusion of this unit, you will be able to:


Describe the advantages of classification
Create classes, characteristics, and objects
Classify objects
Define the functions of the class types

SAP AG 1999

(C) SAP AG

LO305

5.3
Overview Diagram 5
1

Introduction

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes: Operations and

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

5.4
R/3 Classification System: Business Scenario

Classification is required in your company for the

selection of materials and resources for production.


You are responsible for the classification of raw

materials and finished products.


You will define a class with the appropriate

characteristics to select a suitable reaction vessel for


detergent production.

SAP AG 1999

(C) SAP AG

LO305

5.5
Classification

Classification = Object Assignment + Value Assignment


Batch
CH-01

Assignment

Material
-CL100
T
Material Class
Class TT-CL100
Acids:
Acids:
Solids:
Solids:
Freezing
Freezing Point:
Point:
Values

Classification

Value
Value Assignment
Assignment
Acids:
Acids:
Solids:
Solids:
Freezing
Freezing Point:
Point:

Ph
Ph 77
68
68 %
%
3.20F
3.20F

SAP AG 1999

In classification, you assign objects to classes and use the characteristics of the class to describe the
objects.
You can then use the classification system to search for the objects.
You can use the settings in characteristics maintenance to specify, for example, that entries are required
or default values are used in classification.

(C) SAP AG

LO305

5.6
Classification in the R/3 System

Classification enables you to:

Describe objects using characteristics


Group similar objects in classes

You can use the find object function to determine


whether:

An object exists

Similar objects exist

No objects exist

SAP AG 1999

The classification system is a cross-application basic function.


The purpose of a classification system is to describe objects using characteristics and to group or classify
similar objects based on a criteria that is defined.
You can search for objects using the classes and the characteristics defined for the classes. In this way,
you ensure that objects that are similar or identical regarding their characteristics can be found as soon as
possible.
Any basic data elements of the R/3 System can be classified (materials, batches, recipes, operations,
resources, documents, ...)
Classes can be structured in single-level or multi-level class hierarchies.

(C) SAP AG

LO305

5.7
R/3 Classification System

Class

Object

A class is used to group


objects that have identical or
similar attributes.

An object is a classifiable unit


(such as resource, material,
batch, and so on).

Characteristic

Characteristic Value
A characteristic value is a value
assigned to a characteristic
of an object (such as 1000 l, 130
CP).

A characteristic is used to store


information on the attributes of an
object (such as volume, viscosity).

SAP AG 1999

Characteristics that are defined individually are assigned to classes.


A characteristic describes a detail of the classified object.
After assigning an object to a class, the object characteristics can be assigned values.
Objects can be assigned to several classes.

(C) SAP AG

LO305

5.8
R/3 Classification System: Example

Class Type 001 (Material Classes)


Class 270 (Oils)

Oil-001

Class Types
Class

Oil-002

Oil-003

Object

Viscosity
120 cP

Viscosity
130 cP

Viscosity
140 cP

Characteristic
Char. Value

SAP AG 1999

You can search for objects using the classification system.


Two steps are required to find a certain object:
Find the class in which the object is classified
Search for the object in the class
During the search, the characteristics are used as search criteria. They are assigned values, and these
values are compared with the values of the objects that are in the class.

(C) SAP AG

LO305

5.9
Class Types

001
Mat. classes

019
Work ctr cl.

023
Batches

Class types

Objects
Material

Resource

Operation/recipe

SAP AG 1999

Classes are always assigned to a class type.


A class type is a top-level unit of control for classes. The class type is used to define, for example:
Which objects can be classified in a class
Whether objects of different object types can be classified in the same class
The standard system contains settings for some object types (for example, materials, vendors,
documents, and so on) and class types so that you can begin creating a classification system for these
objects immediately. You can also include other class types in the classification system.

(C) SAP AG

LO305

5.10
Creating Classes

Assign characteristics
to the class

Create
characteristics

Create class
for class type

SAP AG 1999

You can set up your own classification system in the following way:
Define the properties of an object:
You use characteristics to define the properties of an object. You create characteristics centrally in
the R/3 System.
Create classes
You need classes to classify objects. These classes must first be created. Characteristics are assigned
to the classes.
Up to 999 characteristics can be assigned to a class. The system checks the characteristic values by
comparing them to the allowed value range.

(C) SAP AG

LO305

10

5.11
Classifying Objects

Object
Specify char. values
Assign characteristics
to the class

Create
characteristics

Create class
for class type

SAP AG 1999

The assignment of objects:


After the classes required for classification have been created, the objects of these classes can be
assigned. The objects are described using the characteristics contained in the classes. In this way,
the data required to use the classification system is available. The system can then be used to find
objects with specific properties.

(C) SAP AG

LO305

11

5.12
Classifying Objects for Process Manufacturing

Resources
Class Type "Work Center Class"'

Operations: Master Recipe


Materials / Batches
Class Type "Batch"

BOM Items

SAP AG 1999

In PP-PI, different objects can be classified, for example, within a master recipe. In this way, resources
(for resource selection which takes place later) as well individual operations of a recipe, for example, can
be assigned to a class.

(C) SAP AG

LO305

12

5.13
Example : Classification of Resources

Class type: 019 "Work center class"


Class: Reaction vessel
Class: Heating vessel
Class: Mixing vessel

...

...
HV-03

HV-02
Object:
MV-02
Heating vesselCharacteristics
Object:
U/min
200C
Characteristics
Mixing vessel Characteristics
Volume
Characteristics
U/min
300C 250 l
RK-01 Characteristics
U/min
200C
Volume
Max. temp.
300C 150 l
Characteristics
U/min Volume
200C 250 l
Volume 200 l
200 l
U/min Volume
150
Volume 300 l
MV-03

...
RE-03
RE-02
Object:
Reaction vessel
Characteristics
RE-01 Characteristics
Coating
Graphite
Volume PVC 350 l
Coating
Characteristics
Volum
Coating
Enamel 250 l
Volume
300 l

...

SAP AG 1999

Classes are always assigned to a class type.


A class type is a top-level unit of control for classes. The class type is used to define, for example:
Which objects can be classified in a class
Whether objects of different object types (such as materials and batches) can be classified in the
same class

There are predefined class types in the standard system such as the class type work center class, for
classifying resources, or class type batch, for classifying materials and batches.

(C) SAP AG

LO305

13

5.14
R/3 Classification System: Summary

Creating a class:
Create characteristics
Create class for class type
Assign characteristics to the class

Any objects in the R/3 System, such as resources,

operations, or MRP components, can be assigned


to a class.
The top-level class type for the class controls, for

example, which objects can be classified in the


class and whether a multi-classification is allowed.

SAP AG 1999

(C) SAP AG

LO305

14

5.15Exercises
Unit: R/3 Classification System
Topic: Characteristics and Classes

At the conclusion of these exercises, you will be able to:


Display and create characteristics
Display and create classes

Classification is required in the company for the selection of materials


and resources for production.
You are responsible for the classification of raw materials and finished
products.
Furthermore, you are to define a class with the appropriate characteristics
to select a suitable reaction vessel for detergent production.
1-1

R/3 classification system


1-1-1 Display the characteristics M100 and M200
Logistics -> Central functions -> Classification Master Data ->
Characteristics. Choose Display.
Write down the description and formatting details for these characteristics.
Characteristic

Description

Data type

Unit of
measurement

M100
M200
Which status do the characteristics have?
________________
What value assignments have been defined for the characteristics?
________________
Is a value assignment for a classified object required?
________________
(C) SAP AG

LO305

15

Are interval values allowed for the value assignment?


________________
Are you allowed to enter negative values?
________________
To which class types is the usage of the characteristics restricted?
Restrictions tab
________________
________________
________________
Within which value range are you allowed to assign a value to a characteristic?
Values tab
Characteristic

Allowed values

M100
M200
Are you allowed to assign values that have not been defined as allowed values?
________________
Display the indicators for one of the characteristics on the Additional data tab.
Additional data tab
Use the F1 help to find out more about the functions of these indicators.
1-1-2 Display the class 023_14 of the class type 023 Batch.
Which description does this class have?
_______________
Which status does this class have?
________________
Which characteristics are assigned to this class?

(C) SAP AG

LO305

16

Characteristics tab
________________
________________
During the course, the class 023_14 will be used for
classification of the raw materials used in the production.

1-1-3 Creating characteristics


In this exercise, you will first create the characteristics M3## and M6## in the
R/3 classification system. These characteristics will then serve as a basis for
class REAC_## that is also to be created for reaction vessels.
1-1-3-1

Create characteristic M3##:

Description

Surface coating

Data type

Character format

No. of char.

Value assignment

Single-value

A value assignment for the characteristic is required.


Restrict the possible characteristic values to the following:
Characteristic value

Description

Glass coated

Polyethylene coated

Stainless steel
Restrict the usage of the characteristics to the class type 019 Work
center class.
Save characteristic M3##.

(C) SAP AG

LO305

17

1-1-3-2

Create characteristic M6##:

Description

Revolutions per minute,


group ##

Data type

Numeric format

No. of char.

Decimal places

Unit

No entry

Value assignment

Multiple values

A value assignment for the characteristic is not required.


Interval values are allowed.
Enter a possible value range of 0 500.
Specify that the allowed values are displayed during value
assignment.
Restrict the usage of the characteristics to the class type 019 Work
center class.
Save the characteristic M6##.
1-1-4 Creating a class
Create the class REAC_## of the class type 019 Work center class.
Enter "Reaction vessel" as the description and assign the characteristics M3##
and M6##.
Save your class.
During the course, the class REAC_## will be used for the classification
of resources (reaction vessel). A resource selection based on previously
defined characteristic values will follow at a later time.

(C) SAP AG

LO305

18

5.16Solutions
Unit: R/3 Classification System
Topic: Characteristics and Classes

1-1

R/3 Classification System


1-1-1 Display the characteristics M100 and M200.
Logistics -> Central Functions -> Classification System Master Data ->
Characteristics (Display)
Characteri
stic

Description

Data type

Unit of
measureme
nt

M100

Concentration

Numeric format

M200

Density

Numeric format

g/ccm

Which status do the characteristics have?


Released
What value assignments have been defined for the characteristics?
Single-value
Is a value assignment for a classified object required?
no
Are interval values allowed for the value assignment?
yes
Are you allowed to enter negative values?
no
(C) SAP AG

LO305

19

To which class types is the usage of the characteristics restricted?


Choose the Restrictions tab.
001 = Material class
022 = Batch (at plant level)
023 = Batch (at client or material level)
Within which value range are you allowed to assign a value to a characteristic?
Values tab
Characteristic

Allowed values

M100

2.0 - 98.0 %

M200

0.5000 -2.0000 g/ccm

Are you allowed to assign values that have not been defined as allowed values?
No
Additional data tab
The indicators are listed under "Procedure for value assignment" and "User
entries handling".
1-1-2 Display the class 023_14 of class type 023 Batch.
Logistics -> Central Functions -> Classification System Master Data ->
Class Management
(Display)
Which description does this class have?
Detergent production

(C) SAP AG

LO305

20

Which status does this class have?


Released

Which characteristics are assigned to this class?


Characteristics tab
M100 Concentration
M200 Density
1-1-3 Creating characteristics
Logistics -> Central Functions -> Classification System Master Data ->
Characteristics Management
(Create)
same as part 1-1-1
1.1.4

Creating a class
Logistics -> Central Functions -> Classification System Master Data ->
Class Management
(Create)
same as part 1-1-2

(C) SAP AG

LO305

21

6
Batches

Contents:
Material and Batch
Batch Management in the Logistics Process
Levels of Uniqueness of a Batch
Classification of a Material and a Batch - Characteristic
Inheritance
Batch-Specific Material Unit of Measure
Active Ingredient / Product Quantity Management

SAP AG 1999

(C) SAP AG

LO305

6.2
Batches : Unit Objectives

At the conclusion of this unit, you will be able to:


Define the term "batch"
Describe how you can use batches in logistics
Use the levels of uniqueness for batches
Have batches inherit the characteristics of the top-

level materials
Make basic settings for active ingredient

management

SAP AG 1999

(C) SAP AG

LO305

6.3
Overview Diagram 6
1

Introduction

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes: Operations and

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

6.4
Batches : Business Scenario

Since the production is to be handled in

batches, you will define, as the person


responsible for the basic data, the finished
product as subject to be handled in batches.
A raw material is also to be handled in batches.

You will define a batch master record for this


raw material.
You will then be able to make a posting of stock

for the raw material.


You will also check the settings for active

ingredient management.

SAP AG 1999

(C) SAP AG

LO305

6.5
Material and Batch
Material Y-300
Yellow paint

Batch mgmt reqmt

Batch B1

Viscosity:
170 -178 cP
Covering property: 95.0 - 98 %
Wavelength:
580 -620 nm

Batch C2

Batch C3

Origin:

Origin:

Origin:

Process order 60000114

Process order 60000146

Process order 60000210

Specifications:

Specifications:

Specifications:

Viscosity:
Covering prop.:
Wavelength:

175 cP
97.0 %
589 nm

Viscosity:
Covering prop.:
Wavelength:

174 cP
97.0 %
605 nm

Viscosity:
Covering prop.:
Wavelength:

170 cP
96.0 %
595 nm

SAP AG 1999

In the R/3 System, batch master records depend on the corresponding material master records. Batches
are created for a material.
In general, the data of a material master record is valid for all batches assigned to it. In contrast, a batch
master record contains data that uniquely identifies a batch and characterizes it as a non-reproducible
unit.
If a material is to be produced in batches and is subject to inventory management, you must set the
Batch management indicator in one of the material master views of Purchasing, Work Scheduling, or
Storage.
You either create a batch master record directly during master data maintenance or the system creates it
in the background during the first goods movement.

(C) SAP AG

LO305

6.6
Batch Management in the Logistics Process

Procurement

Production
Warehouse mgmt

Sales
Warehouse mgmt

A
B

Purchase
order

Batch
assignment

Warehouse

Process/
production
order

Warehouse

Sales
order

Batch
assignment

Batch determination

Batch determination

SAP AG 1999

R/3 batch management is used in all areas of logistics. A batch can be followed through the whole
logistics chain, from the entry of the raw materials to the production of the finished product, and all the
way to sales and delivery to the customer.
You can assign a batch to a material at various points in the logistics process by creating a batch master
record. For example, if the subset of a material that is subject to being handled in batches leaves a
production process with certain specifications, it is posted to stock with a batch number and can then be
clearly identified.
If you need a batch with certain specifications in the logistics process, you can find suitable batches from
the system in the stock using the batch determination function. In the production area, batch
determination is carried out in a process order to find and withdraw suitable material components for the
product to be produced.

(C) SAP AG

LO305

6.7
Levels of Uniqueness of a Batch

Unique batch number


At client level

Material Y-300
Batch 1

In combination with a
material number

Material Y-300
Plant 1

In combination with a plant


and material

Plant 2

Material P-300
Batch 2

Batch 1

Material P-300
Plant 1

Plant 2

Batch 1

Batch 1

Material Y-300

Material P-300

Plant 1

Plant 2

Plant 1

Plant 2

Batch 1

Batch 1

Batch 1

Batch 1

SAP AG 1999

A material master record is identified by an alphanumeric material number. This material number is
unique at the client level.
A batch master record is identified by an alphanumeric batch number. You can choose the level at which
you want the batch number to be unique in accordance with the structure of your plant and company and
your operational requirements.

(C) SAP AG

LO305

6.8
Changing Batch Levels

Client level

Material level

Plant level

SAP AG 1999

You can select the validity of the batch in Customizing. Three batch levels are available. The default
setting in the standard system is the plant level.
You can change to a higher level at any time. However, if you want to change to a lower level, the
system only lets you change from the client level to the material level. You cannot change to the plant
level. This is due to the organization of the batch data, which must be converted each time you change
the batch level.

(C) SAP AG

LO305

6.9
Converting Batch Numbers
Plant level

Plant level

Batch
C1

Plant 01
4712

C4
B2

C4

C1
B3

B2

C3

Batch
C3

B1

B3

4712

C4
B1

Material

Plant 02

Material

B2

Reorganization program

Batch

C1 C3 C4 B1 B2 B3
4712

Material level

Material

Material level

SAP AG 1999

If the batch number was unique at the plant level up to now, and you want to change the validity so that
it is unique only at the material level, you must convert the batch numbers when you make this change.
Up to now, you could issue the same batch number for one material number in each plant. The batches
did not need to be identical, since they were completely independent of each other. In this example, we
assume that the batch specifications are completely different.
When converting existing batch data, the system checks whether identical batch numbers exist. If all
batch numbers are unique at the new level (that is, the material level), the batch number can be converted
directly. If they are not unique, the system writes a log containing all batch numbers that cannot be
converted. You have to decide which batch numbers remain valid and which have to be posted to new
batches together with their stock. If you want the system to delete batches, you must set the deletion flag
and start a batch reorganization run.
You can use the conversion tool to display the current state of conversion. The system repeats the checks
again and again to find out if the existing batch numbers are unique at the new level. Use the test mode.
If the numbers are unique, you can carry out conversion.
At the new batch level, the batch number is unique for each material and is no longer additionally
distinguished by the plant.

(C) SAP AG

LO305

6.10
Classification of a Material and a Batch Characteristic Inheritance

Class type "Batch"


Class 023_08
Color
Characteristics

Viscosity:
100 - 200 cP
Covering property:
0 - 100 %
Wavelength:
400 - 800 nm

Material Y-300
Yellow color

Viscosity:
170 -178 cP
Covering property: 95.0 - 98 %
Wavelength:
580 -620 nm

SAP AG 1999

C
h
a
r.
I
n
h
e
r
i
t
a
n
c
e

Batch B1

Viscosity:
174 cP
Covering property: 97.5 %
Wavelength:
589 nm

When defining the specifications for batch master records, the higher-level material master records are
assigned to classes belonging to class type batch. In these classes, all material and batch attributes are
stored as characteristics.
When you create a batch for a material, the batch is automatically assigned to the same class of class
type batch used to classify the material. This ensures that the same characteristics are used for the
material and the batch. In the R/3 System, this is called characteristic inheritance.
Class type batch specifies a hierarchical relationship between the object types "material" and "batch".
The batch inherits the material's characteristics. The specifications for the individual batches are stored
as characteristic values.
You can define value ranges or fixed values for a characteristic of a class. These specify a maximum
value range that applies to all objects assigned to this class, in this case materials and batches.
In the material master record, you can further restrict the values preset by the characteristics. These
restrictions are inherited by the batch of the material. You can then only assign values to the
characteristics of the batch that lie within the range specified for the material.

(C) SAP AG

LO305

10

6.11
Creating Classes for Batches I

Viscosity
Color
Epoxy no.
Volatile portion

Classification system

5000 - 12000
0-5
23 - 25
0.00 - 0.50

Create characteristics.

Class X

Create a class.
Use the class type for batches.

Class Type "Batch"

Characteristics

Class X

Viscosity
Color
Epoxy no.
Volatile portion

Assign characteristics to
the class.

SAP AG 1999

The classification system must be set up such that the specifications of a material and its batches can be
stored as classification data.
First, you define the properties that you want to specify the material and the batches.
These properties are stored in the classification system as characteristics.
You now create the classes that you want to use for the material and the batches. You can create a
selection of various classes for this purpose. Later, you can only assign one class to the material and the
batch. You thus do not set up multiple classification.
You have to assign class type 022 or 023, as these have been set up in the standard system
specifically for batches. The applicable class type depends on the batch level you have selected.
If you have specified plant level as the validity range of the batch in Customizing, you must select
class type 022 in the standard system. Otherwise, class type 023 is valid. The system automatically
suggests the correct class type.
In the last step, you assign the characteristics to the class. When doing so, you can restrict the value
ranges even further.

(C) SAP AG

LO305

11

6.12
Creating Classes for Batches II

Materials management

Class Type "Batch"


Class X

Classify your material with


the batch class.

Material
Epoxy resin Y

Viscosity
Color
Epoxy no.
Volatile portion

5000 - 8000
0-5
23 - 25
0.00 - 0.50

Post a batch to the material.

Batch
Epoxy resin Y1

Viscosity
Color
Epoxy no.
Volatile portion

Assign allowed characteristic


values to your batch.

7250
1-3
23 - 25
0.30

SAP AG 1999

In Materials Management, you create the material master record and batch master record. You must
classify the material to be able to use the entire functionality of batch management.
You assign the batch class in the classification view of the material master.
You can restrict all value ranges of batch characteristics.
When you create a batch for this material, the system automatically copies the classification data of the
material and proposes the value ranges of the characteristics.
The system checks whether the characteristic values you entered lie within the value range if you have
defined the characteristics accordingly. For the system to be able to do so, you may not set the
Additional values indicator.

(C) SAP AG

LO305

12

6.13
The Batch Where-Used List at Several Production
Levels

Top
down

Customer A

Customer B

Customer order

Customer C

Customer order

Customer order

F1

F2

Production order

Production
Production order
order

H1

H2

Production order

Production order
R1

R2
F=Finished prod.
H=Semi-fin. prod.
R=Raw material

Purchase
order
Vendor

Bottom
up

SAP AG 1999

The batch where-used list follows the path of a batch using inventory management. Each batch receives
its document journal from the first posting to stock to the withdrawal from stock. Additionally, each link
between batches is documented at every production level all the way to the customer order and the batch
split.
The path of a batch is only registered when an inventory posting has taken place. The numbers of the
reference documents, such as the production order and the customer order, are recorded along with the
material document.
The display variations "top down" and "bottom up" describe the view direction using the "family tree" of
the batch.
The batch where-used list can also be processed graphically.

(C) SAP AG

LO305

13

6.14
Batch-Specific Material Unit of Measure

BatchBatch-specific material unit


An alternative unit of measure of a material, for which
you can define the conversion ratio into the base unit
of measure on a batch-specific basis.
Batch-specific material units of measure are:

Proportion unit

Product unit

Proportion and product units for batch-specific


materials can be used in all processes in the logistics
chain.

SAP AG 1999

Proportion unit:
Unit of measure in which you can enter proportions of the base unit of a material. The total or physical
quantity can consist of several proportions.

Product unit
Unit of measure which describes the total quantity of a material as an alternative to the base unit of
measure.

You use batch-specific units of measure when the ratio for conversion from the unit of measure into the
base unit of measure can differ from batch to batch.

While the conversion ratio for the alternative units of measure is fixed in the base unit of measure in the
material, for the proportion unit and the product unit you define the following:
-The planned conversion ratio in the material
-The actual conversion ratio in the batch

As long as the batch is not known, the system uses the planned conversion ratio from the material when
converting to the base quantity. As soon as the batch is known, the system uses the actual conversion
ratio from the batch.

(C) SAP AG

LO305

14

6.15
Batch-Specific Units of Measure as an Attribute of
a Batch

Batch-specific
unit 1 PC
equals 110 KG

Contains 0.7
liters active
ingredient / liter
A
Batch

Expires on
12/31/99

Melting point at
45 C

SAP AG 1999

The specification contains the description of the batch. It may also contain measured values and quality
characteristics, plus details concerning the usability of the batch and whether it is locked. Important date
specifications may also be included, such as the expiration date, the last goods receipt date, and so on.
The active ingredient proportion is one of the criteria that should be used to differentiate between
batches of the same material. For this reason it is integrated into the batch specification.
Likewise, the conversion factor between alternative units of measure and base units of measure in a
batch forms a characteristic, which can be valuated differently from batch to batch.

(C) SAP AG

LO305

15

6.16
Integration of Batch-Specific Units of Measure

Batch Management
Batch-Specific
Unit of Measure
Classification

SAP AG 1999

In the R/3 System, batch-specific units of measure (active ingredient management and product units) are
handled in Batch Management.
The active ingredient potency of a batch is stored in the batch's specification along with the batchspecific ratio between the alternative unit of measure and the base unit of measure.
Batch Management uses those features found in the classification system. The characteristic values in
the batch classification form the specification.
To use batch-specific units of measure, you must have Batch Management set up, the class system must
be in use, and the material concerned must be able to be handled in batches.

(C) SAP AG

LO305

16

6.17
Physical Quantity and Active Ingredient Quantity

Full quantity:
500 l

Full quantity: 500 l

90% a.i.

50% a.i.

Full quantity:
500 l

92% a.i.

SAP AG 2001

If active ingredients are not suitable for storage on their own, they are stored together with carrier
materials. A combination of a carrier material and an active ingredient is called a physical quantity or a
weighed quantity. The terms mixed quantity and telquel quantity are also common.
The situation is similar if materials contain impurities of varying degrees.
The amount of active ingredient in a material is its active ingredient quantity.
The potency (of active ingredient) varies within a material to a certain degree.
A material can contain more than one different active ingredient.

(C) SAP AG

LO305

17

6.18
The Central Unit of Measure for Active Ingredients

BOM

Proportion
Unit
Sales

Inventory
Management
Purchasing

C B
A

SAP AG 1999

The proportion unit can be seen as a core element which is found throughout the applications and is used
to reproduce the active ingredient potency of a material.
The conversion between the proportion unit and the base unit of measure is continuously maintained in
the background and can be displayed by each of the respective applications.
The physical quantity is measured in base units of measure, whereas the active ingredient is measured in
proportion units.
In Logistics you may enter the active ingredient quantity instead of the physical quantity.

(C) SAP AG

LO305

18

6.19
Relation of Units of Measure

Proportion unit
Liter of fruit

Ratio
Liter of active
ingredient per
liter

LF

=
Base unit of
measure
Liter

LIL

SAP AG 2001

The base unit of measure is the leading unit of measure for a material containing active ingredients. You
post the materials in this unit. If an entry is made in proportion units, the system converts this to base
units of measure before posting.
The proportion unit is based on the active ingredient. If a material contains more than one active
ingredient, separate proportion units must be defined for each active ingredient so that they can be
clearly distinguished.
You store a ratio to convert quantities between the proportion unit and the base unit of measure. This
constitutes a separate unit of measurement.
In this example, the active ingredient "fruit" is measured in liters. LIL was defined as the proportion unit
for the purpose of measuring an active ingredient.
The liters of fruit are based on one liter of the physical quantity.
The ratio is recorded in the unit of measurement LIL.

(C) SAP AG

LO305

19

6.20
Percentage and User-defined Calculation

User-defined
calculation

Percentage
calculation

Characteristic
units of
measure
measure the active
ingredient proportion
in relation to the base
unit of measure

LIL
LF / L

SAP AG 2001

If the active ingredient proportion for a batch is known, the active ingredient quantity can be calculated
from the base quantity. The relation between the potency of the active ingredient and the base quantity is
stored in Customizing, and assigned to a characteristic unit of measurement.
If the relation is measured by percentage, the conversion is specified by definition.
If the relation is user-defined, any formula can be stored that describes the relationship between the
proportion unit and base unit of measure.

(C) SAP AG

LO305

20

6.21
Active Ingredient Characteristics

Which active ingredient ?

Fruit

Data type: numeric

LF

What is the ratio?


Value assignment: singlevalue

LIL=
(%) L

SAP AG 1999

The characteristic description specifies the active ingredient on which the data is based and a unique
assignment is made. For this reason, you should define one characteristic for each active ingredient.
The relationship between active ingredient potency and physical quantity must be entered as a unit of
measurement when you create the characteristic.
The characteristic must be numerical and a single value.

(C) SAP AG

LO305

21

6.22
Linking Master Data I

Char. potency
(act. ingred.)
xy

Batch 1
Batch 2

A
Batch 3

Batch class

Transfers
specification

Material

SAP AG 1999

The potency of the active ingredient in a material forms part of its specification.
If the potency is not constant, the different specified material inventories should be managed separately.
This is carried out by the Batch Management component of the R/3 System. Each batch bears its own
characteristic values.
Batch specifications are stored in the classification system as characteristics. The ratio between the
active ingredient and the base quantity is linked to a characteristic, and potency of active ingredient is
stored as its characteristic value. In this way, the ratio becomes the characteristic unit of measurement.
The active ingredient characteristic contains the information about the active ingredient concerned and
the ratio of the proportion of physical quantity to the base unit of measure.
The ratio between the potency of active ingredient and the physical quantity is stored in one batch
characteristic and thus becomes part of the specification.
The material transfers the information to its batches.

(C) SAP AG

LO305

22

6.23
Linking Master Data II

Material Master
View
S = Subs.

Char. potency
(act. ingred.)

Ratio LIL
(%)

Unit of
measurement
LIL (%)

Batch class

LF <=> L

SAP AG 1999

Active ingredient characteristics are assigned the special view 'S' within the batch class.
Characteristics with this view are recognized when you maintain the material master. The information
for conversion between active ingredient and physical quantity is transferred to the material master.

(C) SAP AG

LO305

23

6.24
Maintaining Units of Measurement in the Material
Master

View:
Proportion/product unit
Characteristic Plnd value Unit of meas. Prop. unit

Fruit
potency

0.75
(75)

LF

LIL (%)

Material

LF <=> L
X
75

Prop. unit <=>


LF

<=>

Base unit

100

Liter

SAP AG 1999

After the classification view has been maintained, the system establishes whether any active ingredient
characteristics are present.
You must complete the information in the Proportion/Product Unit view. The system requires a planned
value for the active ingredient proportion.
The planned value specifies the expected mixing ratio between active ingredient and physical quantity in
the characteristic unit of measurement.
If the actual proportion of active ingredient in a batch is not known for a particular business
transaction, the system uses the planned value from the material master.
The planned value for the conversion between active ingredient and physical quantity is transferred
to the units of measure table automatically.

(C) SAP AG

LO305

24

6.25
Batches : Unit Summary

A batch is a subset of a material with unique

specifications.
The level of the uniqueness of a batch can be

changed.
A batch that has been created for a material

automatically belongs to the same class or has the


same characteristics (characteristic inheritance).
A batch-specific material unit of measure is

required for active ingredient management.

SAP AG 1999

(C) SAP AG

LO305

25

6.26Exercises
Unit: Batches

At the conclusion of these exercises, you will be able to:


Classify batches
Describe characteristic inheritance
Make settings for active ingredient management
Since the production is to take place in batches, define the finished
product as a material to be handled in batches.
A raw material is also to be handled in batches. A batch master record is
to be defined for this raw material.
Quantities are to be posted stock.
To be able to carry out active ingredient management at a later time,
maintain the required settings.
1-1

Material to be handled in batches


Check whether the Batch management indicator is set for both the finished product TFD1## and its raw material T-RD1##.
Select view(s):

General Plant Data/storage 1

Organizational level:Plant 1100


Check whether the availability check for batches (CH) is set for the raw material TRD1## in the MRP 3 view.
1-2

Classification of materials in the class type Batch


1-2-1 Classify your finished product T-FD1## in class 023_15 Detergent of class type
023 Batch.
Select view(s):Classification
Class type: 023 Batch

(C) SAP AG

LO305

26

Assign the following characteristic values:


Density:

1.10 -1.20 g/ccm

Save your entry.


1-2-2 Classify your raw material T-RD1## (Sulfuric acid) in the class 023_14
Detergent of the class type 023 Batch.
Assign the following characteristic values:
Concentration 40 60 %
Density

1.30 -1.50 g/ccm

Save your entries.

1-3

Characteristic inheritance
1-3-1 Create the batch master record CH_1 for material T-RD1##.
To which class is the batch assigned?
________________
Classification tab
Within which value range can the characteristics be assigned values? Why?
______________________________
______________________________
Assign the following characteristic values:
Concentration 50 %
Density

(C) SAP AG

1.39 g/ccm

LO305

27

Save the batch master record.


1-3-2 Post a goods receipt of 500,000 L of batch CH_1 of material T-RD1## in
storage location 0002 of plant 1100.
Use movement type 501.
Save the goods receipt and then check the stock for material T-RD1##.
1-3-3 Post another goods receipt (movement type 501) for batch CH_2 of material TRD1## in storage location 0002 of plant 1100.
The system creates the batch master record in the background. Before posting
the goods receipt, the system displays the characteristics of the new batch CH_2
for value assignment.
Assign the following characteristic values:
Concentration 40 %
Density

1.30 g/ccm

Post your goods receipt.

1-4

Settings for active ingredient management


You have two materials, fruit premix T-RJ1## and lemon juice T-RJ2##, which contain
the active ingredients fruit and acid. You want to change the logistic management for
the materials. You want to be able to work with the material quantity and with the
active ingredient quantity for the materials. Active ingredient management will allow
you to do this. You need two batch-specific material units of measure (proportion
units).
1-4-1 Check whether the required units of measure are maintained. What are the
descriptions for the following units of measurement?
LF = _________________________________
LS = _________________________________
1-4-2

(C) SAP AG

Make sure that the use of batch-specific units of measure is activated!

LO305

28

1-4-3 To which base unit of measure are the batch-specific units of measure LF and
LS referenced?
______________________________________________________
1-4-4 Notice the definition of the characteristic unit of measurement % for the
proportion calculation.
Notice that in the case of proportion calculation in percent, the unit of
measurement is defined in connection with the batch-specific units of measure
and base units of measure.
Now notice the definition of the characteristic unit of measurement LIL.
What are the batch-specific units of measure and the base unit of measure
from which it is calculated?
LIL

__________________________________________________

1-4-5 Display the material master records for the materials fruit juice T-FJ1##, fruit
premix T-RJ1##, and lemon juice T-RJ2##. Which data is maintained in their
classification views?
Char. values: Char. values:
Material: Class:

Fruit content Acid content

T-FJ1##
T-RJ1##
T-RJ2##
1-4-6 Check whether the organizational area S is maintained in the basic data and in
the characteristics for the classes found under 1-4-5. Display the material
master of the raw material T-RJ1##.
1-4-7 What are the characteristic names that belong to the characteristic descriptions
fruit content and acid content?
Fruit content = ____________________________
Acid content = ____________________________

(C) SAP AG

LO305

29

1-4-8 Check whether the characteristics mentioned in 1-4-7 have the following
settings:
The status is released.
The data type is numeric.
The value assignment is a single value and no negative values are allowed.
Which unit of measurement is maintained for these two characteristics?
_______________________________
1-4-9 What is the planned value defined for the fruit content on the
Proportion/prod. unit tab in the additional data for material T-RJ1##?
___________________________________
Look at the Units of measure tab.

(C) SAP AG

LO305

30

6.27Solutions
Unit: Batches

1-1

Material to be handled in batches


Material -> Display -> Display current
Select view(s):

General plant data/storage 1

Organizational levels:

1-2

Plant 1100

Classification of materials in the class type Batch


1-2-1 Classify your finished product T-FD1## in class 023_15 Detergent of class type
023 Batch.
Material Change Immediately
Select view(s):

Classification

Class type:

023 Batch

Assign characteristic values to class.


1-2-2 Classify your raw material T-RD1## (Sulfuric acid) in the class 023_14
Detergent of the class type 023 Batch.
same as in 1-2-1

(C) SAP AG

LO305

31

1-3

Characteristic inheritance
1-3-1 Create the batch master record CH_1 for material T-RD1##.
SAP standard menu ->Logistics->production-Process->Master Data/ Material
master menu / Batch -> Create
Classification tab
To which class is the batch assigned?
023_14
Within which value range can the characteristics be assigned values? Why?
40 60 %
1.3 -1.5 g/ccm
The value range of the characteristics was defined in classification Part 1-2-2.
1-3-2 Goods receipt for batch created
Goods receipt:
SAP standard menu Logistics Materials Management Inventory
Management Goods Movement Goods Receipt Other
Post goods receipt (save)
Check stock:
SAP Menu Logistics Production -Process Master Data Material
Master Other Stock Overview
1-3-3 Goods receipt for batch not created
Goods receipt:
SAP Menu Logistics Materials Management Inventory
Management Goods Movement Goods Receipt Other
Assign characteristic values to class.
Post goods receipt (save)

(C) SAP AG

LO305

32

1-4

Settings for active ingredient management:


1-4-1

Tools AcceleratedSAP Customizing Project Management SAP


Reference IMG General Settings Check Units of Measurement.
Choose Units of measurement (no dimension).
LF = L fruit
LS = L acid (= L Sure)

1-4-2 Tools AcceleratedSAP Customizing Project Management SAP


Reference IMG Logistics - General Batch Management Batch
Specific Material Units of Measure Activate Batch-Specific Material Units
of Measure
1-4-3

Tools AcceleratedSAP Customizing Project Management SAP


Reference IMG Logistics - General Batch Management BatchSpecific Material Unit of Measure Edit Batch-Specific Material Unit of
Measure
Both batch-specific units of measure reference a liter.

1-4-4

Tools AcceleratedSAP Customizing Project Management SAP


Reference IMG Logistics - General Batch Management BatchSpecific Material Unit of Measure Calculate Proportional Factors
Define Percentage Calculation
Tools AcceleratedSAP Customizing Project Management SAP
Reference IMG Logistics - General Batch Management BatchSpecific Material Units of Measure Calculate Proportional Factors
Define Calculation of Proportion Quantity from Base Quantity
LIL

= Liter of active ingredient / liter

1-4-5 SAP Standard Menu Logistics Production - Process Master Data


Material Master Material Display Display Current

(C) SAP AG

LO305

33

Display the Classification view for each of the materials.


Char. values: Char. values:
Material: Class:

Fruit content Acid content

T-FJ1##

023_20

35 40 %

2 2.2 %

T-RJ1##

023_20

80 100 %

35%

T-RJ2##

023_21

40 80 %

1-4-6 SAP Standard Menu Logistics Production - Process Master Data


Material Master Material Display Display Current
Raw material T-RJ1##
View: Classification
Position cursor on the class entry and choose Environment Display master
data
Basic data and Characteristics tabs
Both the class and the characteristics are maintained for application view S.
1-4-7

SAP Standard Menu Logistics Production - Process Master Data


Material Master Material Display Display Current
View: Classification
Position cursor on the class entry and choose Environment Display master
data. Choose the Characteristics tab.
Fruit content = ______M800______________________
Acid content = ______M900_________________

1-4-8

SAP Standard Menu Logistics Production - Process Master Data


Material Master Material Display Display Current
View: Classification
Position cursor on the class entry and choose Environment Display master
data
Characteristics tab
Double-click Characteristics.

(C) SAP AG

LO305

34

The characteristics M800 and M900 are both released, numeric, and singlevalue. Negative values are not allowed, and they are assigned to a class type
batch. For both characteristics, the unit of measure % (percent) is maintained.
1-4-9 SAP standard menu Logistics Production - Process Master Data
Material Master Material Display Display Current
Select Basic data view 1, choose Additional data, and then choose the
Proportion/prod. unit tab.
The planned value for the fruit content is 85 %. The conversion ratio is entered
on the Units of measure tab.
As long as the batch is not known, the system uses the planned
conversion ratio from the material when converting to the base
quantity. As soon as the batch is known, the system uses the actual
conversion ratio from the batch.

(C) SAP AG

LO305

35

7
Resources: Customizing

Contents:
General data for resources
Planning data
Data for capacity requirements planning
Costing data
Default capacity

SAP AG 1999

(C) SAP AG

LO305

7.2
Resources: Customizing: Unit Objectives

At the conclusion of this unit, you will be able to:


Make user-specific settings for the resource
master record
Maintain general data for resources
Define formulas for resources
Create a default capacity
Prepare for the creation of a default resource

SAP AG 1999

(C) SAP AG

LO305

7.3
Overview Diagram 7
1

Introduction

PP-PI Overview

10 Operations and Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes:

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

7.4
Resources: Customizing: Business Scenario

Your company wants to reorganize the resources


used for detergent production.
You are responsible for setting up and maintaining
the resources. You will make preparations for the
creation of a default resource in Customizing.
You will also define an available capacity for the
corresponding capacity category.

SAP AG 1999

(C) SAP AG

LO305

7.5
Resources in the Company

Processing unit

Waste disposal
facility

Labor

Resources

Transport

Energy

Means of production and persons in the production process that have capacities
assigned to them. Resources are subdivided into resource categories.

SAP AG 1999

Resources are the main planning instruments of production planning and control. The data you maintain
for a resource is, for example, used for:
Scheduling process orders
Capacity requirements planning
Product and order costing
Resources are grouped in resource categories on the basis of their usage and function. You can define
your own resource categories in Customizing.

(C) SAP AG

LO305

7.6
Resource Master Record
Plant
Resource
Basic data

Resource description

Default values

Capacities

Scheduling

Costing

General data
Resource category
Person responsible

Standard value maintenance

Descrpts.

Admin. data

Classification

Subsystems

SAP AG 1999

The data in the resource is used, for example, for:

Basic data

When creating a resource, you enter general basic data before you maintain specific data such as
standard values, capacity data, or scheduling data.

Simplification of operation maintenance

Various default values can be maintained in the resource for operations.

Scheduling

Formulas for calculating operation duration can be maintained here.

Costing

Formulas for calculating the operation costs are maintained in the resource. In addition, a resource
is assigned to a cost center.

(C) SAP AG

Capacity requirements planning


LO305

Formulas for calculating capacity requirements of an operation can be maintained here.

(C) SAP AG

LO305

7.7
Functions of the Resource Category

Usage

Default resource

Recipes

Basic data

Routings for
plant maintenance

Scheduling

.
.
.

.
.
.

Resource
category

Control of field and screen selection

SAP AG 1999

Resources are grouped in resource categories on the basis of their usage and function.
You can define your own resource categories in Customizing.
Resource categories have the following functions:
Each resource category is assigned one or more task list types in Customizing. A task list
application groups one or more task list types. This assignment specifies the task list types for
which a resource of a certain category can be used. Task list types are, for instance, master recipes,
maintenance task lists, inspection plans. In PP-PI, the task list type "master recipes" is used.
In Customizing, you can maintain a default resource for each resource category and plant. When
you create a resource, the data maintained for the default resource is transferred to this resource as
default values.
In Customizing, you can define the screen sequence and field selection for resource maintenance
for each resource category.

(C) SAP AG

LO305

7.8
Field Selection

Input in modifiable
field (for all
resource types)

Modifiable field

Input in influencing
field (enter resource
type)

Input

Req. Disp.

Hide

HiLi

Field 1
Field 2
Field 3
Field 5
Field 6
Field 7

SAP AG 1999

In Customizing for Resources, you can use field modification to influence the attributes of individual
fields shown on the resource maintenance screens. You can specify how specific data fields are
displayed. You have the following options for data fields:

Input field

Required input field

Display field

The field is hidden.

The field is highlighted.

You can decide whether the fields are to be modifiable or influencing for each screen group.

(C) SAP AG

LO305

7.9
Capacity and Available Capacity

Class
A

PHQU
VAR = DV *

BAQU

Capacities

Capacity
A capacity refers to the ability to perform a specific task.

SAP AG 1999

A capacity refers to the ability to perform a specific task. Together with the available capacity and
capacity loads collected for them, capacities are the central planning unit for capacity requirements
planning.
You can assign any number of capacities of different capacity categories to one resource. You can
maintain variable availability in time for each capacity. The available capacity is the ability of a capacity
to perform a specific task in a certain period of time.
The available capacity is determined using work start and finish times, break times, rate of capacity
utilization, and the number of individual capacities.

(C) SAP AG

LO305

10

7.10
Capacity Categories for a Resource

Energy

Resource
Processing unit 1

Machine
Personnel

Resource
Processing unit 2

Pooled
capacity
Steam

Available capacity

SAP AG 1999

The ability of a resource to perform a specific task is limited in time. In the R/3 System, this limited
availability is expressed by capacities.
Available capacities form the basis of scheduling for process orders and are required for capacity
planning and shop floor control. Formulas are assigned to resources in order to calculate execution times
and capacity requirements of operations.
You can assign any number of capacities of different capacity categories to one resource. However, per
capacity category, you can only assign exactly one capacity.
A capacity category is a description that classifies capacities and can be defined by the user in
Customizing. Capacity categories are, for example, machine capacities, labor capacities, and energy.
You create the available capacity that is to apply to only one specific resource as a resource capacity in
the resource itself. Capacities that are used by several capacities, such as a common steam reservoir or
the clean-out team, are created as pooled capacities and assigned to the resources.

(C) SAP AG

LO305

11

7.11
Formulas in the Resource

Resource

Execution times
Formulas

Capacity requirements
Production costs

SAP AG 1999

To calculate costs, execution times, and capacity requirements of phases carried out at a resource,
enter a formula key that refers to a suitable formula on the corresponding screens of the resource.

(C) SAP AG

LO305

12

7.12
Example of a Formula

General operation
values

Operation quantity

Formula constant

Resource output

Standard values

Formula

Base quantity

Duration
Base output

Total time =

Operation qty
Base quantity

Base output
Res. output

X Duration

SAP AG 2001

Formulas and formula parameters are defined in Customizing.


Formula parameters that you can use include standard values, constants defined in the resource (for
example, resource output) as well as general operation values in master recipes or process orders (for
example, operation quantity).

(C) SAP AG

LO305

13

7.13
Customizing a Default Resource

Define default
resource
Define
formula
parameter
1.3

1.2

1.1

Define
default capacity

Define area of
responsibility
for cap. req. planning

Create capacity category

Define
standard
value key

Define
formula key

Define control key

2.4

Define task list usage

2.3

Define person
responsible for resources

2.2

Define resource category

2.1

SAP AG 1999

When you define a default resource in Customizing, you can maintain the following data:
Capacity category, area of responsiblility for capacity requirements planning, default capacities
Resource category, person responsible for resources
Task list usage, control key
Formula parameter, standard value key, formula key
The default resources defined in Customizing can be used as a basis for creating new resources in PP-PI.
The previously defined default resources are copied when you go through the individual resource
screens.
For each resource category, you can define exactly one default resource in Customizing.

(C) SAP AG

LO305

14

7.14
Resources: Customizing: Unit Summary

You are now able to:


Make settings for the field selection in the
resource master record
Explain the structure and use of the formulas for
the resource
Make the Customizing settings required to create
a default resource

SAP AG 1999

(C) SAP AG

LO305

15

7.15Exercises
Unit: Resources - Customizing

At the conclusion of these exercises, you will be able to:


Make general Customizing settings for resources
Define default capacities
Maintain formula parameters and formulas
Your company wants to reorganize the resources used for detergent
production.
You are responsible for setting up and maintaining the resources. You are
also responsible for creating a default resource in Customizing.
The available capacity for the resource must also be defined.
1-1

Resource data overview


To get a general overview of the screens and fields of a resource, look through those
for resource T-IC1## for plant 1100. Write down the corresponding entries in the tables
below.
Use F1 to find out more about the meaning and functions of individual data fields. Use
F4 to have the possible entry values displayed for each data field.
1-1-1 Basic data tab
Description
Resource category
Person responsible
Task list usage
Standard value key
Parameters assigned

(C) SAP AG

LO305

16

1-1-2 Default values tab


Control key
Unit of measure of standard
values
1-1-3 Capacities tab
Capacity category
Formula key
(Formula assigned for capacity requirements determination)
1-1-4 Scheduling tab
Capacity category
Duration of internal
processing
(Formula assigned for calculating the phase duration)
1-1-5 Costing tab
Validity
Controlling area
Cost center
Activity type
Formula key
(Formula assigned for activity cost calculation)
From the resource menu, go to the SAP Library. Familiarize yourself with the
information available on resources in the R/3 documentation.
Choose Default resource in the index to display information about the function
of a default resource.

(C) SAP AG

LO305

17

1-2

General data and task list data for resources


In this exercise, you will become familiar with the most important Customizing
settings for resources. IMG texts are available for the individual Customizing activities,
which you can display if you need help making Customizing settings. Furthermore,
you can use the F1 and F4 help.
Tools -> Accelerated SAP -> Customizing ->Project management -> SAP Reference
IMG -> Production Planning for Process Industries -> Master Data -> Resource ->
(..)
1-2-1 Defining a resource category
Define the resource category RE## "Processing unit gr##".
(...) -> Resource -> General Data -> Define Resource Category (Work Center
Category)
Copy the field selection and the screen sequence of the existing resource
category 0008.
Specify that change documents are to be written for the resources of the
category RE##.
Assign the task list usage for recipes to resource category RE##.
1-2-2 Defining a person responsible for a resource
Define the person responsible R## "Person responsible for resource group##"
for plant 1100.
(...) -> General Data -> Determine Person Responsible
1-2-3 Defining a task list usage
Define the task list usages O## "Recipe & Order group##" and C## "Recipe
until release group##".
(...) -> General Data -> Define Task List Usage
Assign both task list usages to the task list type Master recipe.

(C) SAP AG

LO305

18

Indicate that a resource with a task list usage of C## can only be used until
phase release, operation release, or order release.
1-2-4 Defining a control key
Define control key K1## "Cost., Sched., Cap. Grp.##" and K2## "Cost., Sched.,
Cap., QM Grp.##'".
(...) -> Resource -> Master Recipe -> Data for Operations and Phases ->
Define Control Key
Set the Scheduling indicator, Det. Cap. Reqmnts indicator, and Cost indicator
for both control keys.
For control key K2##, also set the Insp. char. required indicator.
Confirmations for the phases with this control key are possible, but not
required.
1-2-5 Defining the field selection
Which field groups of the basic data screen group are defined as required
entries for resource category 0008?
(...) -> Resource -> General Data -> Define Field Selection
_______________________ and

1-3

_______________________

Data on capacity requirements planning


Tools -> Accelerated SAP -> Customizing ->Project management -> SAP Reference
IMG -> Production Planning for Process Industries -> Master Data -> Resource ->
(..)
1-3-1 Creating capacity categories
Create the capacity category M## "Processing unit##" and P## "Personnel
Group##".
(...) -> Capacity Requirements Planning -> Define Capacity Categories
Define capacity category P## as personnel capacity. Which function is made
possible by setting the CapCatPers indicator?

(C) SAP AG

LO305

19

______________________________________________
______________________________________________
Save your entries.
1-3-2

Defining an area of responsibility for capacity requirements planning.


Define the responsible capacity requirements planner group C## "Cap. planner
grp.##".
(...) -> Capacity Requirements Planning -> Determine Capacity Planner

1-3-3 Defining default capacities


Define default capacities for the capacity categories M## and P## in plant 1100.
(...) -> Capacity Requirements Planning -> Define Default Capacity
Define the following default values for both capacity categories:
Capacity planner group

C##

Factory calendar ID

01

Base unit of measure

Standard avail. capacity

Start: 00:00:00
Finish:

Capacity utilization

100

No. of indiv. cap.

24:00:00

The capacity categories are to be relevant for finite scheduling. This means that
the available capacity is taken into account during capacity requirements
planning.

(C) SAP AG

LO305

20

1-4

Creating formulas for resources


Tools -> Accelerated SAP -> Customizing ->Project management -> SAP Reference
IMG -> Production Planning for Process Industries -> Master Data -> Resource ->
(..)
1-4-1 Defining formula parameters
Define the following formula parameters:
(...) -> General Data -> Standard Value -> Define Parameters
Param

Origin

Short
keyword and
keyword

Dim.

Std value

Std
value
unit.

DF##

Fixed time

TIME

DV##

Var. dur.

TIME

Field
name

BAQU##

Base quantity

BMSCH

PHQU##

Phase qty

MGVRG

The parameters DF## and DV## are the standard values for
the operation.
The parameters BAQU## and PHQU## are general
operation values for the recipe or process order. The
operation values are transferred to the formula parameters by
way of their field names.
1-4-2 Defining a standard value key
Define the standard value key SK## "Fixed and variable time gr##" and assign
the standard values DF## and DV## to it.
(...) -> General Data -> Standard Value -> Define Standard Value Keys
Also set the Generate indicator. You use this indicator to control whether a
coding (ABAP command) is generated for a standard value key.
1-4-3 Defining formula keys
Define the following formulas:
(C) SAP AG

LO305

21

(...) -> Capacity Requirements Planning -> Resource (Work Center)


Formulas -> Define Formulas for Resources (Work Centers)
or
(...) -> Costing -> Resource (Work Center) Formulas -> Define Formulas for
Resource (Work Center)
Formula

Description

Formula definition

FIX##

Fixed duration

DF##

VAR##

Duration, qty-dep.

DV## * PHQU## / BAQU##

DUR##

Total duration

DF## +DV## * PHQU## / BAQU##

Be sure to put a space between each parameter and the adjacent operator. Set
the Generate indicator for each one.
Also allow the use of the formula for costing, capacity requirements
determination, and scheduling.

(C) SAP AG

LO305

22

7.16Solutions
Unit: Resources - Customizing

1-1

Resource data overview


Resources menu: Resource -> Display
1-1-1 Basic data tab
Description

Mixing tank

Resource category

0008

Person responsible

I##

Task list usage

PI2

Standard value key

SAP8

Parameters assigned

Fixed time

1-1-2 Default values tab


Control key

PI01

Unit of measure of
standard values

min.

1-1-3 Capacities tab


Capacity category assigned

008

Formula key

SAPL61

1-1-4 Scheduling tab

(C) SAP AG

LO305

23

Capacity category assigned

008

Formula key

SAPL61

1-1-5 Costing tab

1-2

Validity

01.01.1998 12.31.9999

Controlling area

1000

Cost center

4271

Activity type

1420

Formula key

SAPL61

General data and task list data for resources


1-2-1 to 1-2-4
Enter the Customizing settings as described in the exercise.
1-2-5 Defining the field selection
Position the cursor on the screen group Basic data. Choose Influencing and
enter 0008 (resource category processing unit) as the influencing value.
Choose Enter.
The following are required fields:
Usage

1-3

and

Person responsible

Data on capacity requirements planning


1-3-1 Creating capacity categories
(...) Resource -> Capacity requirements planning -> Define Capacity
Categories
Define capacity category P## as a personnel capacity. Which function is made
possible by setting the CapCatPers indicator?
You set this indicator to specify that persons can be assigned to this capacity
category as single capacities.
1-3-2 to 1-3-3
Enter the Customizing settings as described in the exercise.

(C) SAP AG

LO305

24

(C) SAP AG

LO305

25

1-4

Creating formulas for resources


1-4-1 to 1-4-3
Enter the Customizing settings as described in the exercise.

(C) SAP AG

LO305

26

8
Resources: Functions

Contents:
Resource management
Cost center assignment
Available capacity
Resource network
Classification
Evaluation options

SAP AG 1999

(C) SAP AG

LO305

8.2
Resources: Functions: Unit Objectives

At the conclusion of this unit, you will be able to:


Create a default resource and resource master
record
Maintain available capacities
Create resource networks
Define selection criteria for a system-aided
resource selection
Execute evaluations

SAP AG 1999

(C) SAP AG

LO305

8.3
Overview Diagram 8
1

Introduction

PP-PI Overview

10 Operations and Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes:

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

8.4
Resources: Functions: Business Scenario

You will create the master records for resources


that are used for detergent production in your
company.
You will also allow the resources to be selected
just before production begins.

SAP AG 1999

(C) SAP AG

LO305

8.5
Resource Data I

General data

Default values
for operations in
master recipe
Costing data

Name and description


Person responsible
Task list usage
Standard value key

Basic data

Default values

Control key
Standard text key
Wage data

Cost center
assignment

Cost center
Activity types
Formula key

SAP AG 1999

You can find resource-related data on several screens. This graphic shows some of the most important
resource data.
On the Basic Data screen, you define a person or group of persons responsible for the maintenance of
the master data of this resource. By defining the task list usage, you also specify the task list types (such
as master recipe, equipment task list, or inspection plans) in which the resource can be used and whether
the resource can be used in orders.
By entering a standard value key, a resource is assigned standard values for operations in master
recipes or process orders to be executed at this resource. A standard value is a planned value used to
carry out an operation, such as the execution time. Standard values are used in costing, scheduling, and
capacity requirements planning to calculate costs, execution times, and capacity requirements.
You can enter default values for the operation to be executed at a resource. When you maintain the
operations in the master recipe or process order, the system copies or references this information. You
can, for instance, propose a control key. A control key specifies how an operation is to be processed
from a business point of view.
By assigning a cost center to a resource, you link the resource to cost accounting and can now carry out
product and order costing. You can define the specific output of a resource by assigning activity types
which are defined for the cost center.

(C) SAP AG

LO305

8.6
Resource Data II

Capacity data

Scheduling
data

HR data /
Qualifications

Capacity

Available capacity
Formula key

Scheduling

Scheduling basis
Formula key

Assignments

Persons
Positions
Qualifications

SAP AG 1999

Available capacities of resources are the basis for scheduling process orders. They are also required for
capacity requirements planning and shop floor control.
In order to calculate the execution time of an operation during process order scheduling, the available
capacity of exactly one of several possible resource capacities is defined as the basis for scheduling.
To calculate costs, execution times, and capacity requirements of phases carried out at a resource, enter a
formula key that refers to a suitable formula in the corresponding screens.

(C) SAP AG

LO305

8.7
Resource Management Views
Resource
network
Classification

Personnel

Class
A

Formulas
VAR = DV *

Capacities

PHQU
BAQU

Cost center
assignment

SAP AG 1999

Resources are used in the operations of the recipes and the process orders.
With the resource, you can
Determine which processing units, persons, or other resources are to be used in the operations and
phases of the recipe.
Specify costs, capacity requirements, and dates for the operations and phases.
Persons are assigned to the resource to determine which employees are to work at this resource.
Costs, execution times, and the capacity requirements of the resource can be calculated from standard
values using formulas.
Activity types that are linked to a cost center are assigned to a resource via the cost center. You can
calculate in-house costs of an operation by assigning the resource to a cost center.

(C) SAP AG

LO305

8.8
Cost Center / Activity Type / Resource
Resource

Cost Center
Formula

Activity types

F1
F2
.
.
.
(max. 6)

A
B

Charge rates
USD 10/h
USD 20/h

.
.

Example :

Formula F1
Operation qty

Base quantity

Standard

Base output

Rate for
activity type A
x Duration = Total time

Res. output

values

USD 10/h

Total time x Charge rate = COSTS

Operation

values
Resource constant

SAP AG 2001

The costs incurred due to the use of a resource in a phase must be calculated in production and order
costing. For this, you must maintain costing data in the resource.
The link to cost accounting is created by assigning a cost center to a resource.
For a specified validity period, you can assign a resource to one cost center only.
The specific output of a resource is defined by assigning activity types specified in the cost centers to
the resource. Each activity type is valued with specific charge rates.
The output (= total time) of a resource is calculated with the help of formulas. A formula is assigned to
each activity type.
Finally, the costs are calculated using the output (= total time) of a resource and the corresponding
charge rates.

(C) SAP AG

LO305

8.9
Creating a Resource

Manually

Copy

Default
resource

Resource 1

Customizing

PP-PI

Resource 1a

Resource 1b

Resource 1c

SAP AG 1999

You can create a resource for a resource category in PP-PI in the following ways:
Manually
By using a predefined default value in Customizing
By copying a resource that already exists

(C) SAP AG

LO305

8.10
Resource Network

Charge

Reaction

Discharge

R1
B1

R2

R3

B2

E1

SAP AG 1999

You can often use processing units in a specified sequence only. To represent this sequence in the
system, you can create predecessor/successor relationships between resources in the form of resource
networks.
During process planning, these networks are used to determine possible sequences in which a resource
can be used to manufacture a batch.
If several similar resources are available in a network, it makes sense to decide on the resource to be
used at the time of production and not before. To do this, you can define a resource that is to be used for
planning purposes only. This resource represents several equivalent resources.
You can restrict the usage of resources defined for planning reasons only with the task list usage of
the resource. In Customizing, you can set the Until release indicator for a task list usage. If a resource
has been assigned to a process order whose usage is restricted in this way, the order cannot be released.
Before releasing the order, you must replace the planning resource with a suitable individual resource.
You can use the function of resource selection to do so.

(C) SAP AG

LO305

10

8.11
Classification of Resources

Class type: 019 "Work center class"


Class: Mixing vessel

Object:
Reaction vessel
Reactor - 01

Object:

...

Oper. 10 "Stirring"
(Mst. rec. "Colors")

Characteristics
U/min 150 - 300
Temp. 80 - 120C

Characteristics

Fits ?
Resource selection
in the process order

U/min
Temp.

170
85C

SAP AG 1999

You can add specific resource attributes to the resource data by classifying the resource with classes of
class type 019 work center class. The resource attributes are stored as characteristics of a class and are
assigned specific values in the resources.
Apart from resources, you can also classify operations of master recipes in classes of class type 019.
This allows you to store specifications for a resource in an operation.
The characteristic values of classified operations represent the selection criteria for system-aided
resource selection in the process order. This allows you to select a suitable resource just before
production begins. The resource network must be taken into account for resource selection.

(C) SAP AG

LO305

11

8.12
Available Capacity of a Resource

Avail. cap. maint.


outside of the
resource

Resource
Avail. cap. maint.
outside of the
resource
Pooled capacity
"Clean"Clean-out labor"
CapCat 009
"Labor"

CapCat 010
"Transport unit"

Reference

Reference CapTRANS

"Clean-out labor"
CapCat 009
Labor
CapCat 008
Process. unit

or
copy

CapCat 010
"Transport unit"

Avail. cap. maint.


in the resource

Customizing: Default capacity


Default values per
capacity category and plant

SAP AG 1999

You can maintain and assign the capacity of a resource while processing the resource, provided the
capacity data can be maintained for the resource category.
The capacity overview is the starting point for capacity maintenance from the resource.
Different available capacities of a capacity category are identified using the version number. The version
of the available capacity that appears in the screen header as the active version is used during capacity
requirements planning and scheduling.
When creating an available capacity, you can copy or reference capacities of different origins.

(C) SAP AG

LO305

12

8.13
Maintaining Avail. Capacity Using Shift Sequences

Day 1

Day 2

...

Day 7

Shift
Shift definition
definition
Shift 1

Shift 1

Shift 1

Work start
...

Work finish

Shift sequence

Breaks
Shift 2

Shift 2

Shift 3

Shift 3

Shift 2

Resources /
Work centers

SAP AG 1999

You can use shift sequences to reduce the time and effort needed to maintain an available capacity.
In a shift definition, you define the work start and finish times as well as duration of breaks, which are
valid for several resources.
In a shift sequence, you maintain the sequence of certain shift definitions for several resources.
You define shift sequences in Customizing.

(C) SAP AG

LO305

13

8.14
Assignments to the Personnel System (HR)

Resource
Resource
Master data

Capacities

Process order
Operation:
Reaction
Resources:
Vessel
Volume 10 m3
Line operator
2 years experience

Line operator
2 yr

Resource network

1 yr

Human resources

Shift schedule

SAP AG 1999

You can only maintain assignments of personnel, qualifications, and position when the HR system is
being used.

(C) SAP AG

LO305

14

8.15
Reporting Functions for Resources

Which resources
exist in a plant?

Resources

Which capacities
are assigned?

Which hierarchy does


the resource
belong to?

Which cost centers


are assigned to them?

Which recipes use the


resource?

SAP AG 1999

Different reporting functions are available for the resources of your company. They provide information
on, for example:
Which resources are available?
Which cost centers are they assigned to?
Which capacities have been defined for the resources, or which resources use a capacity?
To which resource hierarchies have the resources been assigned?
Which recipes use the resources?
In addition, you can use the Logistics Information System to carry out resource evaluations.

(C) SAP AG

LO305

15

8.16
Resources: Functions: Unit Summary

You are now able to:


Copy and reference available capacities
Prepare for a system-aided resource selection by
creating a resource network and using resource
classification
Create a resource based on a default resource and
by copying another resource

SAP AG 1999

(C) SAP AG

LO305

16

8.17Exercises
Unit: Resources - Functions

At the conclusion of these exercises, you will be able to:


Create a default resource
Create, copy, and classify resources
Create resource networks, maintain available capacities, and assign
cost centers
The resources required to produce detergent in your plant must be
maintained in the system. Resource selection is to take place just before
production starts. You will therefore classify the resources and include
them in a resource network.
After entering the data in the system, you will use various reports for the
resources.
1-1

Creating a Resource
Create some resources using the Customizing settings you made in the previous unit.
1-1-1 Defining a default resource
Define a default resource for resource category RE## in plant 1100.
Tools -> Accelerated SAP -> Customizing ->Project Management -> SAP
Reference IMG -> Production Planning for Process Industries -> Master
Data -> Resource ->General Data Define Default Resource (Default Work
Center)
Basic data tab

(C) SAP AG

Description

Resource

Person responsible

R##

Usage

O##

Standard value key

SK##

LO305

17

Specify that the system is not to check the standard values.


Default values tab
Control key

K1##

Capacities tab
Capacity category

M##

Other formula

DUR##

Scheduling tab
Capacity category

M##

Other formula

DUR##

Costing tab
Cost center

4250

Activity type

1420

Fixed time
Activity type

1420

Variable time
Formula key

FIX##

Fixed duration
Formula key

VAR##

Duration,qty-dep.
Save your default resource.

(C) SAP AG

LO305

18

1-1-2 Creating a resource based on the default resource


Create resource T-DTM1## of the resource category RE## in plant 1100.
Resources menu / Resource -> Create
When you maintain the resource data, the system suggests values that were
created in Customizing as default values.
Enter Charging vessel grp.## as the resource description on the Basic Data
screen.
Copy the other default values suggested on the Basic Data screen without
changing them.
Look at the other detail screens on:

Default values

Capacities

Scheduling

Costing

Click through the corresponding tabs.


While doing this, pay attention to the messages on the status bar.
The default values will not be copied automatically from the
default resource until you run through the detail screens.

Save your resource.

(C) SAP AG

LO305

19

1-1-3 Creating resources with reference to existing resources


In plant 1100, create the resources in the following table that are of the category
RE## by copying the source T-DTM1##.
Select all the views that are offered for selection on the Copy from screen and
choose Copy.
You only have to maintain the resource description and perhaps the task list
usage on the Basic Data screen. You can then save the resource without going
through further detail screens. All of the data from the screens you selected are
copied from the source.
Create the following resources:
Resource

Description

Task list usage

T-DTR1##

Reaction vessel 1 grp.##

O##

T-DTR2##

Reaction vessel 2 grp.##

O##

T-DTR3##

Reaction vessel 3 grp ##

O##

T-DTA1##

Cooling tank grp ##

O##

T-DTG1##

Group reaction vessel grp ##

C##

In which way is resource T-DTG1## restricted by task list usage C## ?


_____________________________________________
_____________________________________________

1-2

Capacities
1-2-1 Displaying the capacity data of a resource
Display the capacity data of your cooling tank T-DTA1##.
Which capacity category is assigned to it? Why?
_____________________________
_____________________________
Display the capacity header data of the capacity category assigned.
Choose Capacity Header Data.

(C) SAP AG

LO305

20

Where was the header data of this resource capacity originally created?
_____________________________
_____________________________
1-2-2 Creating a pooled capacity with available capacity intervals
Create a pooled capacity POOL-## (personnel pool group##) of the capacity
category P## in plant 1100.
Resources menu / Capacity -> Create
The data that is maintained as the default capacity for each plant and capacity
category in Customizing is automatically copied.
Set the Pooled capacity indicator.
Set the Can be used by several operations indicator.
The standard available capacity has an operation time of 24 hours. An average
of 10 single capacities is available in the standard available capacity, and the
rate of capacity utilization is 100%. Maintain the standard available capacity
accordingly.
Enter the detailed information for the available capacity of your pooled
capacity. Define an available capacity interval for the active version 1 Normal
available capacity according to the following information.
Choose Interval avail. cap.
Choose Insert.

(C) SAP AG

LO305

21

Make the following entries on the Add Interval of Available Capacity screen:
Valid from:

Today

Valid to:

End of this year

Length of cycle:

Number of shifts:

Workdays:

1 (overrides factory calendar)

Specify the following shifts on the Create Capacity: Shifts screen:


Shf

Start

Finish

Breaks

No.

00:00:00

08:00:00

01:00:00

08:00:00

16:00:00

01:00:00

12

16:00:00

24:00:00

01:00:00

10

After defining your shifts, choose F3 Back.


Check the available capacity intervals that are now valid on the Create
Capacity: Interval of Available Capacity screen.
Save your pooled capacity.
1-2-3 Assigning a pooled capacity
Assign your pooled capacity POOL-## of the capacity category P## to your
cooling tank T-DTA1##.
Resource -> Change
Capacities tab
Choose Create capacity.
Check whether the capacity data has been copied correctly to the resource.
Position your cursor on capacity category P20 and choose Capacity Header
Data.
Save the resource.
1-2-4 Referencing a capacity
(C) SAP AG

LO305

22

Assign the capacity category 010 (Transport) to your cooling tank,


T-DTA1##.
Resource -> Change
Capacities tab page
Choose Create capacity.
On the Header Data screen for this capacity category, reference the available
capacity of the capacity TRANS-00 of the capacity category 010.
Choose Capacity Header Data.
Choose Reference avail. cap.
After entering the capacity on the Reference Available Capacity screen, you
reference the available capacity by choosing Continue. You cannot process the
referenced data within the resource. You do have the option of changing the
available capacity data by choosing Copy.
Save your resource.
Display the capacity
TRANS-00 and check the data again.
1-3

Formulas
1-3-1 Formulas in the resource
On which screens in a resource is a formula key used to reference the formulas
that were defined in Customizing? Display, for example, the resource TDTA1## again.
______________________
______________________
______________________
What is calculated with each of the formulas?
______________________
______________________
______________________
1-3-2 Displaying and testing the formula in a resource

(C) SAP AG

LO305

23

You can display the formulas that are assigned to the formula keys on the
resource screens. You can also test the formulas.
Display the formulas defined on the Capacities, Scheduling and Costing screens
for one of your resources and write down the formulas.
__________________________________
__________________________________
__________________________________
Extras -> Formula -> Display
For example, test the formula on the Scheduling screen
Extras -> Formula -> Tests
General operation values: (for example)
Operation qty:

1000 kg

Base quantity:

100 kg

Standard values: (for example)


Duration, fixed:

10 H

Duration, variable: 1 H
Choose Calculate.
Result: Total duration = 20 H

(C) SAP AG

LO305

24

1-3-3 Formula constants of a resource


Assign the formula constant RESPOW (Resource activity) to one of your
resources.
Note: Resource constants can be used as parameters in the formula for costing,
capacity requirements determination, and scheduling. This can be useful for
resources, for example, that have activity-dependent output.
Resource -> Change /
(for example) Choose Scheduling /
Extras -> Formula ->Formula constants
Param.

Values

UN

RESPOW

(for example)
10,000

Which origin must be specified for a formula parameter in Customizing so that


it can be used as a resource constant?
____________________________

1-4

Resource selection requirements


1-4-1 Creating a resource network
Create a resource network NETZ-## in plant 1100 according to the following
graphic.
T-DTR1##
T-DTM1##

T-DTR2##

T-DTA1##

T-DTR3##

(C) SAP AG

LO305

25

Make the following entries on the Header Data screen:


Description

Resource network group ##

Person responsible

R##

Assign the resources of the network shown in the graphic above.


Choose Resource allocation.
Choose the following selection conditions:
Plant:

1100

Resource:

T-DT*

Resource Category: RE##


On the Resource allocations screen, select the resources and go to graphical
maintenance.
Choose Graphic.
Create the resource network shown above in the graphic. Use drag and drop to
position the resources as shown. Choose Connect and draw the links between
the resources. Click in the blank area and go back one screen.
Save your resource network.
1-4-2 Displaying the network relationship of a resource
Display the data of the network resource for the reaction vessel T-DTR2##.
Resource -> Display
Goto -> Network -> Relationships
Goto -> Relationship detail

Header
Graphic

(C) SAP AG

LO305

26

1-4-3 Classification of resources


Classify your reaction vessel in class REAC_## (Reaction vessel) of the class
type 019 (Work center class).
Assign values to the characteristics assigned for the individual reaction vessels
in the following way:

Surface
Rev. per min

T-DTR1##

T-DTR2##

T-DTR3##

(glass)

(polyethylene) (stainless steel)

20 - 80

20 - 40

20 - 60

Save your data.


Classification is carried out for the purpose of system-aided
resource selection in the process order.

1-5

Reporting
Resources / Reporting -> < ... >
1-5-1 Resource list
Display all resources that R## is responsible for in plant 1100. Be sure to
remove any resources that have defaulted onto the selection screen.
Reporting ->Resources list
Note: Double-click one of the resources listed to display the corresponding
resource data.

(C) SAP AG

LO305

27

1-5-2 Cost center assignment


Display the cost center that is assigned to your resources.
Plant:

1100

Work center:

T-DT*##

Reporting -> Cost center assignment


Note: Double-click the objects listed to display data for the resources, cost
centers, and activity categories.
1-5-3 Resource capacities
Display the capacities that are assigned to your resources.
Reporting -> Resource capacity
Plant:

1100

Work center:

T-DT*##

Note: Double-click the capacities listed to display the corresponding capacity


data.
1-5-4 Where-used list
In which master recipe is, for example, the resource T-IC101 from plant 1100
used? Use overview variant: L00000000100.
Reporting -> Where-used list ->Resource
For which resources is the capacity POOL-## from plant 1100 used?
Reporting -> Where-used list ->Capacity

(C) SAP AG

LO305

28

8.18Solutions
Unit: Resources - Functions

1-1

Creating a Resource
1-1-1 Defining default resources
Maintain the data as described for the exercise.
1-1-2 Creating a resource based on the default resource
Maintain the data as described for the exercise.
1-1-3 Creating resources with reference to an existing resource
Maintain the data as described for the exercise.
In which way is resource T-DTG1## restricted by task list usage C##?
The "Until rel." indicator (usage only until release in order) is set. An
operation with this resource in its process order cannot be released. By this
time at the latest, the resource must be replaced by a resource that physically
exists.

1-2

Capacities
1-2-1 Displaying the capacity data of a resource
Which capacity category is assigned to it? Why?
M##. This capacity category was defined in the default resource and was
copied when the resource was created.
Display the capacity header data of the capacity category assigned.

(C) SAP AG

LO305

29

Choose Capacity Header Data.


When was the header data of this resource capacity originally created?
When the default capacity was defined for M## ( in Unit Resources:
Customizing).
1-2-2 Creating a pooled capacity with available capacity intervals
Resources menu: Capacity -> Create
Choose Interval avail. cap.
Choose Insert.
1-2-3 Assigning a pooled capacity
Resource -> Change
Capacities tab
Choose Create capacity.
Check whether the capacity data has been copied correctly to the resource.
Choose Capacity Header Data.
1-2-4 Referencing a capacity
Display and check the capacity TRANS-00
again.

Resources menu/ Capacity ->Display


1-3

(C) SAP AG

Formulas

LO305

30

1-3-1 Formulas in the Resource


On which screens in a resource is a formula key used to reference formulas that
were defined in Customizing?
Capacities
Scheduling
Costing

What is calculated with each of the formulas?


Capacity requirements are determined
Operation time is calculated
Costs based on fixed and variable duration
1-3-2 Displaying and testing the formula in a resource
Display the formulas defined on the Capacities, Scheduling and Cost centers
screens for one of your resources and write down the formulas.
Extras -> Formula -> Display
DUR##:

Duration, Fixed + Duration, Var. * Phase Quantity / Base Quantity

FIX##:

Duration, Fixed

VAR##:

Duration, Var. * Phase Quantity / Base Quantity

For example, test the formula on the Scheduling screen


Extras -> Formula -> Tests
Choose Calculate.
1-3-3 Formula constants of a resource
Resource -> Change /
(C) SAP AG

LO305

31

Choose (for example) Scheduling /


Extras -> Formula ->Formula constants
Which origin must be specified for a formula parameter in Customizing so that
it can be used as a resource constant?
Use the F1 help in the "Param." field on the "Formula constants" screen to
answer this question.
Origin 1 Work center constant

1-4

Resource selection requirements


1-4-1 Creating a resource network
Resources menu / Resource network -> Create
Choose Resource allocation.
Choose Graphic.
1-4-2 Displaying the network relationship of a resource
Resource -> Display
Goto

Network -> Relationships

Relationship detail
Header
Graphic
1-4-3 Classification of resources
Resource Change.
On the Basic data tab, choose Classification.
1-5

(C) SAP AG

Reporting

LO305

32

Resources / Reporting -> < ... >

1-5-1 Resource list

Reporting -> Resource list

1-5-2 Cost center assignment

Reporting -> Cost center assignment

1-5-3 Resource capacities

Reporting -> Resource capacity

1-5-4 Where-used list

Reporting -> Where-used list ->Resource

Reporting -> Where-used list ->Capacity

(C) SAP AG

LO305

33

9
Production Version

Contents:
Mass processing: overview and access to recipe and
BOM maintenance
Recipe editing
Approval
Consistency check

SAP AG 1999

(C) SAP AG

LO305

9.2
Production Version: Unit Objectives

At the conclusion of this unit, you will be able to:


Create, change, check, display, and delete
production versions
Access master recipes and BOMs through
production versions to edit them
Perform consistency checks for production
versions

SAP AG 1999

(C) SAP AG

LO305

9.3
Overview Diagram 9
Production Version

1 Introduction

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

Master Recipes: Operations and

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

9.4
Production Version: Business Scenario

The products in your company are manufactured in


different ways and are therefore managed in
several different production versions.
You are responsible for maintaining production
versions in individual or mass processing.

SAP AG 1999

(C) SAP AG

LO305

9.5
Production Version: Definition

Production version
A production version determines which alternative BOM
is used together with which master recipe to produce a
material or create a master plan for a material.
More than one production version for different validity
period and lot-size ranges can be assigned to a
material.

SAP AG 1999

Production versions are used in discrete manufacturing, repetitive manufacturing, and process
manufacturing.

Production versions are used in sales & operations planning (SOP), material requirements planning
(MRP), process order creation, and product costing to select the most suitable task list or recipe and the
corresponding material list.

A production version comprises the following data: Material number, version ID, lot-size range, and
validity period of the production version, details about whether the production version is locked, the
date of the last consistency check, the assignment of master recipes to the production version, the
assignment of the alternative BOM to the production version, a check status that displays the result of
the last consistency check, the production line if the product is manufactured in discrete manufacturing,
the change number that was used when the production version was last changed, as well as further
administrative data.

When you create process orders that require approval, the system uses the change number to check
whether the production version has been approved.

You can also select a production version without a recipe or BOM. Note, however, that if you do so,
material quantity calculation data is not copied.

(C) SAP AG

LO305

9.6
Production Version: Mass Processing (I)

Selection criteria for worklist creation:


Extended selection:

Selection criteria:

Header data

Plant
Plant

Lot size

Material
Material

Validity

MRP controller

Tas Lists

Key date
date

BOMs

Task list type / group

Repetitive manufacturing

Production line

SAP AG 1999

(C) SAP AG

LO305

9.7
Production Version: Mass Processing (II)

Production Version: Mass Processing


Copy
Assign change
number

Maintain Prod.Version: Detail Screen

Delete

Create

Create

Change

Change

Check consistency

Check consistency

Lock

Lock

SAP AG 1999

(C) SAP AG

LO305

9.8
Recipe Editing

Worklist:
Production version

Task list group

Grp cntr

0002

T-DET100

0003

T-DET100

...

...

...

T-DET100

...

0001

Recipe

Key date (for change status)

Master recipe

Bill of material

Detailed plng grp: T-DET100

Alternative BOM 2

Group counter: 2

Alt. BOM

SAP AG 1999

From mass processing of production versions, you can navigate to the corresponding master recipe and
create, edit, or display the recipe or alternative BOM there. From the production version, you can thus
access all production related master data.

If you have assigned a change number to a production version, this number is also valid for recipe and
BOM editing from the production version. This enables you to use an approval procedure in the same
way for all related objects.

(C) SAP AG

LO305

9.9
Consistency Check
Plant
Material
Prod.version

1100
T-FD100
Recipe group for...
0001

Check
03/05/1999
Date of
last check

Production version
Lock
From lot size
Valid from

Change no.assign.
1 000
01/20/2000

To lot size
Valid to

20 000
12/31/2002

Task lists
Task list group
T-DET100

Check status

Group counter
1

Bill of material
Alternative BOM

BOM usage

Check status

Repetitive manufacturing

SAP AG 1999

You can check whether the data of a production version is consistent with the data of the master recipe
and the data of the alternative BOM assigned to it. You can then be sure that a valid recipe or valid BOM
actually exists within the whole validity period of the production version.
In order for a production version to be consistent, it must fulfill the following requirements:
The lot-size range of the production version must be in the lot-size range of the assigned recipe as
well as of the assigned alternative BOM. This applies to all change statuses of the recipe and
alternative BOM that are in the validity period of the production version.
The assigned recipe and alternative BOM must exist during the whole validity period of the
production version. The deletion flag must not be set for them.
If one of these requirements is not met, an error or warning message is given in the inspection result.

After the check, you can update the date of the last check and check status of the production version. The
recipe, task list, or BOM are then assigned one of the following statuses in the production version:
Last check ok
Last check with warning
Last check with error

(C) SAP AG

LO305

9.10
Approval

Change number

Recipe group TT-DET100


Recipe:

MRP view

Change rule:
With an engineering
change order

Validity period

MaterialMaterial-recipe assignment

Prod.vers. 0001

Recipe

T-FD100 T-FD100

11

Prod.vers. 0001

Maintain

Maintain

Material

Material TT-FD100

Maintain

Production version
Mass processing

SAP AG 1999

Unlike recipe editing with a change master record or engineering change order, you do not create a new
change status for the production version. You only assign the change number to it in the worklist for
production version processing by carrying out the corresponding function. The change number is used to
document or approve changes. If required, you must adjust the validity period of the production version
manually.

You cannot use a change number when you edit production versions in the material master record. In the
standard system therefore you cannot edit production versions whose change rule requires an
engineering change order in the material master record.

A production version is considered approved when the following requirements are met:

The master recipe assigned to the production version has a change rule that requires an
engineering change order with or without a change type.

rule.

The production version has been assigned a change number that complies with this change

The relevant engineering change order has been released. This means you can no longer
use it for changes.
(C) SAP AG

LO305

10

9.11
Production Version: Unit Summary

You can create, change, check, and lock


production versions in detail maintenance.
In addition, you can copy and delete production
versions in mass processing and assign change
numbers.
From the production version, you can access all
production-related data (master recipe and
material BOM).
The consistency check ensures that a master
recipe and BOM exist during the whole validity
period of a production version.

SAP AG 1999

(C) SAP AG

LO305

11

9.12Exercises
Unit: Production Version

At the conclusion of these exercises, you will be able to:


Create and process production versions
Perform consistency checks for production versions

You are responsible for mass maintenance of production versions in your


plant. You will create several production versions for the new detergent TFD1##, since you are planning to produce it on different lines with
different ingredients. You will therefore create production versions for
different lot-size ranges, master recipes, validity periods, and BOM
versions.
1-1

Creating a production version


Create production version 0001 for material T-FD1## in plant 1100 using the following
specifications:
Description of production
version

Detergent 1

Valid from

Today

Valid to

Maximum validity date

From lot size

1000

To lot size

20000

Alternative BOM

BOM usage

Production

Detailed plng grp:

T-DET1##

Group counter:

Task list type:

Master recipe

1-1-1 Which warnings appear after detail maintenance for the production version?
______________________________________________________
(C) SAP AG

LO305

12

______________________________________________________
1-1-2 Use the application help to find out more about the symbol that appears in the
processing status column. What does this symbol stand for?
______________________________________________________
1-2

Copying from production versions


Copy the production versions created and change the copies according to the following
instructions:
1-2-1 Copy production version 0001 to production version 0002 and change the
number of the alternative BOM from 1 to 2.
1-2-2 Copy production version 0002 to production version 0003 and change the valid
from date from today to today + 2 months in detail maintenance. Also change
the number of the alternative BOM from 2 to 3.
1-2-3 Copy production version 0001 to production version 0004 and change the lotsize range from 1000 - 20000 to 20000 - 30000. Also change the group counter
from 1 to 2.
1-2-4 Copy production version 0004 to production version 0005 and change the
number of the alternative BOM from 1 to 2.
Save the production versions.

1.3

Consistency check for production versions /processing status


Perform a consistency check for production version 0003 of material T-FD1##.
1-3-1 Which messages appear in the consistency log?
______________________________________________________
______________________________________________________
1-3-2 How do you recognize that a consistency check has been performed on this
production version?
_____________________________________________________
_____________________________________________________
_____________________________________________________
1-3-3 What is the processing status?
________________________________________________________________
____________________________________________
Save the production versions.

(C) SAP AG

LO305

13

1-3-4 What changes with regard to the processing status after you save?
______________________________________________________

(C) SAP AG

LO305

14

1-4

Production version in the material master


The production version that was created in the previous exercise is defined in the
master data record of the material T-FD1##.
Display the production version for material T-FD1## in the material master.

(C) SAP AG

LO305

15

9.13Solutions
Unit: Production Version

1-1

Creating a production version


SAP Standard Menu Logistics Production -Process Master Data
Production Versions
Enter plant 1100 and material T-FD1## as your selection criteria.
Choose Refresh or press enter.
Choose

Create production version

The Detail Maintenance: Production Version screen appears.


Maintain the data as described for the exercise.
1-1-1 The following warnings appear:
No task list exists
No BOM exists
1-1-2 Help Application help
The symbol means the following:
Newly created or copied production versions
Save your production version.

1-2

Copying from production versions


1-2-1 Copy production version 0001 to production version 0002.
Select production version 0001.
Choose

Copy production version

Enter number 0002 in the Copy/ProdVersion field.

(C) SAP AG

LO305

16

Choose Enter.
On the Production Version: Mass Maintenance screen, enter alternative BOM
2 for production version 0002.
Confirm the No BOM exists warning by choosing Enter.

(C) SAP AG

LO305

17

1-2-2 Copy production version 0002 to production version 0003.


Select production version 0002.
Choose

Copy production version

Enter number 0003 in the Copy/ProdVersion field and choose Enter.


Double-click the entry production version 0003. The Detail Maintenance:
Production Version screen appears. Change the Valid from date and the
alternative BOM as described in the exercise.
Choose Close detail screen.
Confirm the No task list exists, No BOM exists warnings by choosing Enter.
1-2-3 Copy production version 0001 to production version 0004.
Copy production version 0001 as described in 1-2-1.
Change the lot-size range and the group counter as described in the exercise.
Confirm the warnings by choosing Enter.
1-2-4 Copy production version 0004 to production version 0005.
Copy production version 0004 as described in 1-2-1.
Change the alternative BOM number as described in the exercise.
Confirm the warnings by choosing Enter.
Save the production versions.

1-3

Consistency check for production versions /processing status


Select production version 0003.
Choose

Consistency check

The consistency log for production version 0003 appears.


1-3-1 The consistency log contains the following error messages:
Task list does not exist
BOM does not exist
Choose Back.
1-3-2 The current date was entered in the check date column. Additionally, the check
status "Last check with error" (red light) is set.
(C) SAP AG

LO305

18

1-3-3 The processing status shows that the production version data was changed.
Note: The production version is therefore locked for other users until you save.
Save the production versions.
1-3-4 The following results when you save:
The symbol in the Processing status column disappears.
Note: This unlocks the production version.

1-4

Production version in the material master


SAP standard menu Logistics Production -Process Master Data
Material Master Material. Display Display current
Display the MRP 4 view in the material master for material T-FD1##.
Choose ProdVersion.
On the Production Version Overview screen, the production versions just created are
listed.
Select a version and press Detail to call the Production Versions Details screen.
If you enter the material master in the change mode, you can also
create, check, and delete production versions if the production
versions are not for recipes to be approved.

(C) SAP AG

LO305

19

10
Master Recipes: Operations and Phases

Contents:
Elements and structure of a master recipe
Functions of a master recipe
Recipe-plant assignment
Recipe header data
Operations and phases
Resource assignment
Relationships
Scheduling
Classification of operations and resources

SAP AG 1999

(C) SAP AG

LO305

10.2
Master Recipes, Operations, and Phases:
Unit Objectives

At the conclusion of this unit, you will be able to:


Define the elements and structure of a master

recipe
Describe the functions of a master recipe
Make assignments between recipes and plants
Create operations and phases
Assign primary and secondary resources
Create relationships
Classify operations
Carry out scheduling for a master recipe

SAP AG 1999

(C) SAP AG

LO305

10.3
Overview Diagram 10
1 Introduction

9 Production Version

PP-PI Overview

10

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

Master Recipes: Operations


and Phases

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

10.4
Master Recipes, Operations, and Phases:
Business Scenario

The elements and structure of a master recipe that

already exists will be presented.


Your company is going to put a new product on

the market.
The production process is to be described in a

master recipe.
You are responsible for creating a master recipe

with operations and phases based on the


resources used.

SAP AG 1999

(C) SAP AG

LO305

10.5
Elements of a Master Recipe
Proc. planning

Proc. control

EBF/ISA(S88)/NAMUR
Steps in the
prod. process

Control
information

Master
recipe
Quality
inspec. data

Resources

Materials

Process order Control recipe


Master recipe
A recipe that describes the production of one or several materials in a production
process.

SAP AG 1999

A master recipe defines the following data required for the manufacturing of materials without relating
to a particular order
Resources
Material components
Data for in-process quality inspection
Control information for the process control level
Master recipes have a planning and a control view. The planning view comprises the planning of
operations, materials, resources, and inspection characteristics. Therefore, links to the R/3 application
components PP, MM, SD, WM, and QM have been realized. The control view contains information
required for communicating with the process control level.
The master recipe is the basis for the creation of process orders. A process order describes an actual
production process. It contains all information specified during process planning, such as production
date and quantities to be produced.
A control recipe contains all the information necessary for the execution of a process order by a certain
process control system or a process operator. Control recipes are generated from the process instructions
in a process order and transferred to the corresponding destination in process control. Process
instructions are defined in the master recipe on which the process order is based.
Three organizations have defined the data that must be included in the standard recipe maintenance of
the PP-PI application component:
The European Batch Forum (EBF)

(C) SAP AG

LO305

The Instrument Society of America (ISA; with standards S88)


NAMUR (Norms working committee for measuring and control techniques in the
chemical industry).

(C) SAP AG

LO305

10.6
Structure of a Master Recipe (I)

Resource network
Recipe header

Primary resource
Operations

Material (product)

Phases

Process instructions

Proc. instr. characteristics

SAP AG 1999

The recipe header contains data that is valid for the whole recipe. At the header level, a resource
network and the material to be produced is assigned to the recipe.
Operations describe the different steps required during the production process. For a more detailed
description of these steps, operations are subdivided into phases.
Exactly one primary resource at which an operation is to be carried out is assigned to the operation.
This assignment of the primary resource is also valid for all phases that belong to the operation.
Process instructions are structures with which data is transferred from R/3 process planning to process
control. Process instructions are assigned to the phases of a master recipe.

Process instruction characteristics are assigned to process instructions and define the content of the
process instructions together with the corresponding characteristic values..

(C) SAP AG

LO305

10.7
Structure of a Master Recipe (II)

Resource network
Recipe header

Primary resource
Operations

Material (product)

Secondary resources

Phases

Process instructions

Material
components

Proc. instr. characteristics

Inspection characteristics

Relationships

SAP AG 1999

If required, you can assign additional secondary resources to operations and phases.
If materials are added, temporarily created, or withdrawn at certain places in the production process, you
assign them to the corresponding operations and phases as components of a material list.
Inspection characteristics specify which in-process quality inspections are to be carried out. They can
be assigned to operations and phases.
Relationships define the sequence of phases as well as link the start and finish points of phases.

(C) SAP AG

LO305

10.8
Functions of a Master Recipe

Master recipe

Recipe header

Process order

Primary resource
Operations

MRP

Phases

Cost accounting

Process instructions

Proc. instr. characteristics

SAP AG 1999

(C) SAP AG

LO305

10.9
Non-Manufacturing Recipes

Equipment-testing
recipes
Setup recipe
Clean-out recipes
Changeover recipes

SAP AG 1999

Master recipes can also be created for purposes other than the manufacture of materials. Nonmanufacturing master recipes are, for example:
Equipment-testing recipes
Clean-out recipes
Setup or changeover recipes
Equipment-testing recipes contain process instructions that are used to carry out and document periodic
functional testing of a plant line.
Clean-out recipes describe the activities as well as the time, resource, and material requirements that are
necessary to clean out a vessel after a production run.
Changeover recipes describes the activities necessary to transfer a processing unit from an initial state to
a subsequent state.

(C) SAP AG

LO305

10

10.10
Profile for the Recipe

Profile

Default values for recipe maintenance for:

The operation

The relationship

The process instruction

The relationship graphic

Changeability

Default values for quality inspection

SAP AG 1999

When creating a master recipe, you must enter a profile defined in Customizing. To display or change
the default values set in this profile, choose Extras in the master recipe menu.
You can change the values in the profile dialog box. However, these changes are only valid until you exit
the recipe.
In the profile, you can enter default values for the operation, the relationship, the increment of process
instructions and process instruction characteristics as well as for the relationship graphic and how it is
displayed.
Moreover, you can branch to a dialog box displaying QM data and enter default values for quality
inspection.

(C) SAP AG

LO305

11

10.11
Recipe-Plant Assignment

Production
plants

Recipe group Detergent production


Recipe

1100

Description

Plant

1
2

Detergent production 1100


Clean-out
1100

3
4

Detergent production 3100


Clean-out
3100

3100

SAP AG 1999

Master recipes that belong to the same recipe group can be assigned to different plants.
When creating a master recipe, you can enter the plant number in the recipe header.

(C) SAP AG

LO305

12

10.12
Copying Recipes from Other Plants

Plant 1100
Material

BOM
Production version

Material components

Material list
Mat. qty calc.
Recipe
Recipe
Operations / phases

Copy
Plant 3100
Recipe
Operations / phases

SAP AG 1999

You can create a master recipe by copying another master recipe, even if they are from different plants.
The material in the recipe header of the recipe being copied as well as the factory calendar are copied to
the new recipe.
The other recipe objects, such as primary resources, control recipe destinations, process instructions, etc.
are copied to the new recipe if they already exist in the target plant (otherwise error messages appear).
The data on the recipe detail screen of the new recipe is checked. The data must be changed if the entry
does not exist in the target plant or is not the same as the resource data in the target plant.
Caution! The master inspection characteristics are not checked in the target plant. The system also does
not check whether the process instruction characteristics that were copied have been released in the
target plant.
To use the material assignments that have been copied to the new recipe, you must first create a
production version to use the alternative bills of material in the new recipe.

(C) SAP AG

LO305

13

10.13
Reporting

Material lists
Structure
Changes
Quantity

Master recipe

Recipe changes:
Which objects were
created, changed, or
deleted for a recipe?

Mass changes
Recipe: Replacing resource
Replacing process instruction
Material list: Replacing material

Recipe list:
Which
texts for
relationships
secondary resources
material components
proc. instructions
PI characteristics
insp. characteristics
are used in a recipe?
Where-used list:
Which recipe uses a
Resource
Process instruction
Material
Document
Class?

SAP AG 2001

You can evaluate the data of your recipe in the following ways:
Evaluations on recipe changes: Documentation of changes made to all objects belonging to a
recipe over a certain period of time.
Where-used list for resources, process instruction categories, materials, documents, and classes.
Evaluations of material lists: Evaluations of the structure and changes carried out for a material
list
Mass changes: Replacing of process instruction categories and resources in master recipes.
Replacing of materials in material lists.

(C) SAP AG

LO305

14

10.14
Recipe Header Data

Recipe header data


Recipe group, recipe counter, plant
Resource network
Usage
Planner group
Status
Charge quantity range
Change rule
Material-recipe assignment
Long text
QM data
Administrative data

SAP AG 1999

Data that is valid for the whole recipe is maintained on the recipe header level.
A recipe is identified by the recipe group and the recipe counter. Recipes are defined on the plant
level. They can be grouped into recipe groups based on criteria defined by the user.
By assigning a resource network, the physical network of the resources is described for the line at
which the process is to take place.
The usage describes the purpose for which the recipe can be used (for example, production,
construction, plant maintenance). The planner group specifies a group of people who are responsible
for the maintenance of the recipe. The status gives information about the processing status of a recipe
(for example, creation phase, released for order, released for costing) and controls which business
operations are allowed or not allowed.
With the charge quantity range, you specify a value range that is allowed for the production quantity
and for which the master recipe may be used as the reference for a process order in production.
The material to be produced using the recipe is assigned to the recipe at the header level.
To give more information, you can create a long text for the recipe header.
On the recipe header detail screen for QM data, you determine whether an in-process inspection is to
take place with or without inspection points.
Administrative data gives information about the validity dates of the recipe, who has created or
changed the recipe, and whether a change was made using a change number.

(C) SAP AG

LO305

15

10.15
Operations and Phases
Operation 10

Charge

Phase 12

Mix

Phase 13

Discharge

Control key

CtrK
CtrK

.
.
.

Reaction

Phase 21

Charge

Phase 22

Heat

Phase 23

Discharge

Operation 30

CtrK

Phase 11

Operation 20

CtrK

Charging

Cooling

Phase 31

Charge

Phase 32

Cool

Phase 33

Discharge

SAP AG 1999

Operations describe the different steps required during the production process. For a more detailed
description of these steps, operations are subdivided into phases.
You must enter a control key for each operation and phase. The control key determines how an
operation or phase is to be processed in functions such as process orders, costing, and capacity
requirements planning.
Control keys are defined in Customizing. You can set a number of indicators specifying, for instance:
Whether scheduling is to be carried out for the phase
Whether capacity load records are to be written for the phase
Whether the phase is costed
Whether a goods receipt is to be posted automatically for the process order when a confirmation is
received
Whether time tickets are to be printed for the operation or phase
Whether inspection characteristics have to be maintained for the operation or phase
Note:
Scheduling, determination of capacity requirements, and costing take place at phase level.
The dates and capacity requirements for operations are derived from the
corresponding phases.

(C) SAP AG

LO305

16

10.16
Assignment of Primary and Secondary Resources

Operation 30

Cooling
Phase 32
Cool and check
quality

Phase 31
Charge

Phase 33
Discharge

Primary resource
Cooling tank
Secondary resource
Line operator

Secondary resource
Transport truck

CtrK

Var.
start

CtrK

Var.
finish

Time

SAP AG 1999

Exactly one primary resource is assigned to an operation. The primary resource is that part of a line or
processing unit at which the operation is carried out. It is committed for the entire duration of the
operation.
The primary resource is also assigned to all phases subordinate to the operation in the hierarchy.
If required, you can assign additional secondary resources to operations and phases. This assignment
can be carried out with a flexible start and finish time, relative to the start or finish of the operation or
phase.
You must assign a control key to each secondary resource. The same business transactions can be
carried out for secondary resources as for operations and phases. Secondary resources can, for example,
be included in scheduling, capacity requirements planning, and costing.

(C) SAP AG

LO305

17

10.17
Standard and Default Values from the Resource

Resource
Standard values
f.ex. duration

Rule for maint.


Mandatory

Recipe operation/phase

Default values

Units for standard values

Control key

Ref.ind.

Standard text key

Ref.ind.

Wage data

Ref.ind.

Activity types

Ref.ind.

SAP AG 1999

When you assign a resource to an operation or phase, you also assign the standard and default values
maintained in the resource.
A standard value is a planned value for the execution of an operation or phase such as the execution
time or operation quantity. Standard values are used in costing, scheduling, and capacity requirements
planning to calculate costs, execution times, and capacity requirements.
Possible standard values for an operation or phase are defined in the corresponding resource. You can
use a rule for maintenance to specify whether a standard value for an operation or phase may be, should
be, or has to be entered. In the resource, you can also maintain default values for the units of measure of
the standard values.
In the resource, you can maintain default values for the operation or phase data "control key" and
"standard text key", for wage data as well as for the activity types to be assigned. These default values
are then either copied into the operation or phase, giving you the possibility to later change them, or they
are referenced into the operation or phase, thus making further changes impossible. In the latter case, a
reference indicator is set for the relevant default value in the resource.
The control key specifies how an operation or phase is processed from a business point of view.
Using the standard text key, you can choose a standard text created previously for the description of an
operation or phase.
The specific output of a resource is defined by assigning activity types to the resource. Each activity
type is valued with a specific charge rate (for example, USD 100/h). This forms the basis for calculating
the costs resulting from activities performed.

(C) SAP AG

LO305

18

10.18
Relationships

Operation 10 Charging
Charge vessel
vessel

Operation 30 Cooling
Cooling tank

Phase 11

Phase 12

Phase 13

Phase 31

Phase 32

Phase 33

Charge

Mix

Discharge

Charge

Cool

Discharge

Phase 21

Phase 22

Phase 23

Charge

Mix

Discharge

Operation 20 Reaction
Reaction vessel

Time

SAP AG 1999

Relationships determine the time-based sequence of phases. Relationships link the start and finish
points of phases. This enables you, for instance, to synchronize phases belonging to different operations.

(C) SAP AG

LO305

19

10.19
Relationships Between Master Recipes

Recipe group "Production"


Recipe 1

Recipe group "Clean-out"


Recipe 1

SAP AG 1999

Phases from different recipes can be linked using relationships.

(C) SAP AG

LO305

20

10.20
Scheduling in the Master Recipe

PhS

PhF

Duration
Float before
production

BS

Ph11

Ph12

Ph13
Ph21

Ph31
Ph22

Ph23

Relationships !

SS

Dates:

Time

Ph32

Ph33

Float after
production

SF

BS:
BF:
SS:
SF:
PhS:
PhE:

BF

Basic start
Basic finish
Scheduled start
Scheduled finish
Phase start
Phase finish

SAP AG 1999

Scheduling a master recipe enables a time-based simulation of the manufacturing process in the planning
phase. During scheduling, the start and finish times of phases are determined. Scheduling takes place at
phase level only. The operation dates are derived from the phase dates.
Starting from the basic start or basic finish dates, scheduling is done either as forward or backward
scheduling. You can enter a planned lot size if the phase duration depends on the quantity to be
processed.
To be able to schedule, you must maintain default values for phases as well as relationships between
phases.
Depending on the scheduling type, the float before production is either added to the basic start date, or
the float after production is subtracted from the basic finish date. In this way you can determine the start
and finish dates of production (scheduled start date, scheduled finish date).
The float before production and float after production are time buffers enabling you to react to
disturbances in the manufacturing process. You can assign them to the material in the MRP view of the
material master record using the scheduling margin key.

(C) SAP AG

LO305

21

10.21
Phase Duration
Resource

Phase

Formula key for


scheduling
Capacity category as a
basis for scheduling
Formula constants

General operation
values
Standard values
Control key
"Scheduling"

Formula

PhS

PhF

PhS
Duration

Phase 11

Phase 12
PhS

PhF

Phase 13
PhF

Operation 10
OS

OF

SAP AG 2001

To calculate the phase duration, you must specify a capacity category as a basis for scheduling and
define a formula in the resource.
The phase duration is determined on the basis of the standard values and additional formula parameters.
When calculating the phase dates, the available capacity is taken into account as the basis for scheduling.
Scheduling takes place via the phases. The operation duration is derived from the phase dates.
The scheduling result can either be displayed in a table or graphically in a Gantt chart.
Due to the relationships, phase dates can have a certain time buffer. Therefore, the earliest and latest start
and finish dates are determined in scheduling.

(C) SAP AG

LO305

22

10.22
Classification of Operations and Resources
Class type 019 "Work center class"
Class "Reaction vessel"
Characteristics:

Stirring speed
Temperature

Attributes - Resource

1000-2000 RPM
80-120 C

Requirements - Operation

Fits ?
Resource selection in
the process order

1200 RPM
85 C

SAP AG 1999

Using classes of class type 019 work center type, you can classify resources as well as operations
contained in master recipes.
You can thus use the characteristics of a class of class type 019 in two ways: first, you can store specific
resource attributes and second, you can define requirements a resource must meet if it is to be used in an
operation of a master recipe.
The characteristic values of classified operations represent the selection criteria for system-aided
resource selection in the process order.

(C) SAP AG

LO305

23

10.23
Checking the Recipe / Consistency Log

Header

Res. netwk

Primary res.

Consistency log
Material

Oper.

Phase
Proc. inst.
PI char.

Sec. res.

Check
Comp.

W
E
I

QM data is
missing

Insp. char.
Relationsh.

SAP AG 1999

If you want to check whether the data for your recipe is complete and consistent, call the Recipe check
function.
After the recipe is checked, warnings, information, and errors are collected for the recipe check in a
consistency log.

(C) SAP AG

LO305

24

10.24
Master Recipes, Operations, and Phases:
Unit Summary

Describe the elements and structure of master

recipes.
Assign recipes of the same group to different

plants.
Copy master recipe between plants.
Assign primary resources.
Define relationships.
Carry out scheduling.
Prepare system-aided resource selection by

classifying operartions.

SAP AG 1999

(C) SAP AG

LO305

25

10.25Exercises
Unit: Master Recipes
Topic: Operations and Phases

At the conclusion of these exercises, you will be able to:


Describe the elements and structure of a master recipe
Create a master recipe
Classify operations
Perform scheduling
The elements and structure of a master recipe that already exists will first
be presented.
Your company is going to put a new detergent on the market.
The production process will be described in a master recipe.
You are responsible for creating a master recipe with operations and
phases based on the resources used.
1-1

Elements and structure of a master recipe


Go to mass maintenance for production versions in plant 1100 for group T-ICE##.
Familiarize yourself with the data in the master recipe for production version 0001 of
material T-FI1##.
1-1-1 Operation overview
Familiarize yourself with the operations, phases, and resources assigned.
1-1-2 Relationships
Display the relationships defined between the phases in the graphic.

(C) SAP AG

LO305

26

1-1-3 Recipe header data


Display the recipe header data.
Which materials are assigned to the recipe as products?
________________________
________________________
________________________
1-1-4 Material list
Familiarize yourself with the material components that are assigned to the
recipe.
Which materials are assigned?
In which quantities are the material components required?
To which operations or phases are the material components assigned?
Material

Quantity

Operation

(5 examples are sufficient)


1-1-5 Process instructions
Display the process instructions maintained for phase 1010.
Which process instruction is assigned?
________________________

(C) SAP AG

LO305

27

1-2

Reporting and changing master recipes


1-2-1

Recipe list
Create a print list for the master recipe T-ICE##.
Master recipe menu / Reporting Recipe -> Recipe list
Task list type:

Plant:
Recipe group:

T-ICE##

Recipe:

Material components are to be displayed for all BOMs.


Program -> Execute
1-2-2 Familiarize yourself with the further reporting functions that are available for
the master recipe.
Master recipe menu / Reporting -> < ... >
1-2-3 Familiarize yourself with the mass changes that are possible for master data.
Master recipe menu / Mass changes -> < ...
1-2-4 Familiarize yourself with the settings you can make in the master recipe
environment.
Master recipe menu / Environment -> < ...

1-3

Creating a master recipe: header data and operations / phases


Go to mass maintenance for the production version for material T-FD1## in plant 1100.
Create a master recipe for production version 0001 based on the following information:
Key date:

today

Profile:

0001

1-3-1 Data for recipe header


1-3-1-1
(C) SAP AG

The Create Master Recipe: Recipe appears. Enter the following data
on the Recipe header tab:
LO305

28

Description of the recipe: Recipe for detergent production, grp ##


Plant:

1100

Status:

4 Released general

Use:

1 Production

Planner group:

001 Planner group PI

Resource network:

NETZ-##

Charge quantity range:

1000 - 20000 l

1-3-1-2

Header text
Create a long text that describes the recipe.
Choose Header text.
Header text:

Recipe for detergent production, grp ##,


exothermic reaction

1-3-1-3

Administrative data
Display the administrative data.
Administrative data tab

1-3-2 Operations and phases


1-3-2-1

Creating operations and phases and assigning primary resources


Create operations and phases for your recipe 1 of the recipe group TDET1## based on the data in the following table. Assign the primary
resource.

(C) SAP AG

LO305

29

Operations tab
Op

Ph

SOp

CRD

100

Resource

Description

T-DTM1##

CHARGING

110

100

DE

Charge

120

100

DE

Mix

130

100

DE

Add water

140

100

DE

Discharge

200

T-DTG1##

REACTION

210

200

DE

Charge

220

200

DE

Add Butanol and


NaOH

230

200

DE

Discharge

300

T-DTA1##

COOLING

310

300

DE

Charge

320

300

DE

Cool

330

300

DE

Discharge

Save your master recipe.


1-3-2-2

Control key
Use the input help (F4) to display detailed information about the
control key K1##.
Which indicators are set?
____________________
____________________
____________________
Based on the indicators that have been set, what happens to a phase
marked with this control key in the process order?
______________________________________
______________________________________
______________________________________
Use field help (F1) to display information about the functions of the
different indicators.

(C) SAP AG

LO305

30

1-3-2-3

Text
Create the following text for operation 200.
Choose Text.
Text: Reaction
Resource selection condition have been defined for the
operation so that a suitable reaction vessel can be selected.

1-3-2-4

Administrative data
Display the administrative data for an operation or a phase.

1-3-2-5

Maintaining standard values


Maintain the standard values for the phases of your recipe using the
information in the following table.
The quantity-dependent durations should each refer to a base
quantity of 1000 L.

Phase

Duration,
fixed

Act.
type

(1st oper.
value)

Duration,
variable

Act. type

(2nd oper.
value)

110

10 min

1420

130

10 min

1420

140

10 min

1420

210

10 min

1420

230

10 min

1420

310

10 min

1420

20 min

1420

120

220

320

30 min

1420

30 min

1420

5h

1420

330
1-3-3 Assigning a secondary resource

Add the secondary resource T-DTT1## (Transport vehicle) for phase 330.
SRes
(C) SAP AG

Resource

Plant
LO305

Description
31

0001
1-3-3-1

T-DTT1##

1100

Discharge into transport unit

Text
Enter the following text for your secondary resource.
Text: Discharge into transport unit:
The transport vehicle must be connected
15 minutes before charging begins.
It cannot be detached until 10 minutes
after charging has ended.

1-3-3-2

Resource dates
Define the earliest and latest dates of your secondary resource based
on the following information.
Offset to start: 15- min.
(Be sure to put a negative sign after 15 to indicate 15 minutes
before)
Offset to finish: 10 min.

1-3-3-3

Administrative data
Display the administrative data for your secondary resource.
Save your recipe.

1-3-4 Relationships
1-3-4-1

Graphic maintenance
Create the relationships between the phases of your recipe as shown
in the following graphic.

(C) SAP AG

LO305

32

Suggestion: Put the phases in the appropriate positions before connecting them.

1-3-4-2

Phase maintenance on the Detail screen


Maintain the last relationship in the corresponding detail screen
for phase 320.
320------330

Rel. type

Phase

Scs
(successor)

Rcp. grp

Rcp. grp.

NF

330

T-DET1##

Normal
sequence
Display the detail information for this relationship.
Choose Details for the relationships created.
Display the administrative data for this relationship.
Administrative data tab
1-3-4-3

Displaying information in graphic maintenance


Go back to the graphic display of the relationships.
Double-click a phase. Which detail screen appears?
____________________
Double-click a line connecting two phases. Which detail screen for
the relationships appears?
____________________
Save your recipe.

1-4

Classifying operations
Classify the operation 200 with the class REAC_## (Reaction vessel).

(C) SAP AG

LO305

33

Assign the following values to the characteristics:


Surface coating

Revolutions per min.

30

Save your master recipe.


The classification of the operation defines the selection
conditions for a system-aided resource selection in the process
order.

1-5

Scheduling
Suggestion: Do the following exercise for different charge quantities.
1-5-1 Scheduling overview
Simulate order scheduling in your master recipe.
Choose Schedule recipe.
Display the result in the scheduling overview.
1-5-2 Gantt chart
Display the scheduling results in the Gantt chart.
Choose Gantt chart.
Select a suitable time unit.

(C) SAP AG

LO305

34

10.26Solutions
Unit: Master Recipes
Topic: Operations and Phases

1-1

Elements and structure of a master recipe


Production Process Master Data Production Versions
Plant:

1100

Planning type:

Group:

T-ICE##

Select production version 0001 of material T-FI1##.


Choose Recipe.
On the Parameter for recipe maintenance screen, choose Display recipe.
1-1-1 Operation overview
1-1-2 Relationships
On the Operations tab, choose Operation graphic
1-1-3 Recipe header data
Recipe header tab
Which materials are assigned to the recipe as products?
Choose Material assignments.
T-FI100
T-FI200
T-FI300
(C) SAP AG

LO305

35

(C) SAP AG

LO305

36

1-1-4 Material list


Materials tab
Material

Quantity

Op

T-RI000

0.1 KG

1010

T-RI100

0.12 KG

1010

T-RI200

0.16 KG

1010

T-RI300

0.02 KG

1010

T-RI400

0.02 KG

1010

1-1-5 Process instructions


Operations tab
Select phase 1010.
Choose Proc. inst.
Which process instruction is assigned?
INSTR

1-2

Reporting and changing master recipes


1-2-1 to 1-2-4
Production Process Master Data Master Recipes
<....> Reporting Recipe Recipe list

Production versions
Recipe Recipe changes
Change documents
Material list <....>
Where-used list
Mass changes
Environment

(C) SAP AG

LO305

37

1-3

Creating a master recipe: header data and operations / phases


Production Process Master Data Production Versions
Select production version 0001 of material T-FD1##.
Choose Recipe.
Parameter for recipe maintenance: edit recipe
1-3-1 Data for recipe header
1-3-1 to 1-3-1-3
Maintain the data as described for the exercise.
1-3-2 Operations and phases
1-3-2-1

Creating operations and phases and assigning primary resources


Operations tab

1-3-2-2

Control key
Use the input help (F4) to display detailed information about the
control key K1##.
In the operation overview, position the cursor on the control key.
F4 help.
In the control key overview, position the cursor on the control key
and choose Detail info.
Which indicators are set?
Scheduling
Det. Cap. Reqmnts
Cost
Based on the indicators that have been set, what happens to a phase
marked with this control key in the process order?
The phase is scheduled

(C) SAP AG

LO305

38

Capacity requirement records are generated


The phase is costed
1-3-2-3

Text
Choose Text.

1-3-2-4

Administrative data
Double-click the operation/phase number.
Administrative data tab

1-3-2-5

Maintaining standard values


On the Operations tab, double-click each phase number.
Standard values tab.

1-3-3 Assigning a secondary resource


On the Operations tab:
Select phase 330.
Choose Secondary resource.
1-3-3-1

Text
On the Secondary resource tab:
Select the secondary resource.
Choose Text

1-3-3-2

Schedule
Double-click the item number of the secondary resource.
Standard values tab

1-3-3-3

Administrative data
Administrative data tab

1-3-4 Relationships
(C) SAP AG

LO305

39

1-3-4-1

Graphic maintenance
In the operation overview (Operations tab), choose Operation
graphic.

(C) SAP AG

LO305

40

1-3-4-2

Phase maintenance on the Detail screen


In the operation overview:
Double-click phase number 320.
Relationships tab.

1-3-4-3

Displaying information in graphic maintenance


Operations tab
Choose Operation graphic.
Double-click a phase. Which detail screen appears?
Standard values of the phase
Double-click a line connecting two phases. Which detail screen
appears for the relationships?
Relationships General Data screen

1-4

Classifying operations
On the Operations tab:
Select operation 200
Choose Resource selection criteria Goto -> Res. sel. criteria.

1-5

Scheduling
1-5-1 Scheduling overview
In the operation overview, choose Schedule recipe.
1-5-2 Gantt chart
Choose Gantt chart.

(C) SAP AG

LO305

41

11
Master Recipes: Materials

Contents:
Material-recipe assignment
Bill of material
Material list
Classification of bill of material items
Material quantity calculation

SAP AG 1999

(C) SAP AG

LO305

11.2
Master Recipes, Materials: Unit Objectives

At the conclusion of this unit, you will be able to:


Describe what the material list and the bill of

material are used for


Create a material list for a master recipe
Classify bill of material components
Define and carry out a material quantity

calculation in the recipe

SAP AG 1999

(C) SAP AG

LO305

11.3
Overview Diagram 11

Introduction

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes: Operations and

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

11.4
Master Recipes, Materials: Business Scenario

Your company is going to put a new product on

the market.
As the person responsible, you will add a

material list and a material quantity calculation


to the the master recipe that has been defined
for the production of the new detergent.

SAP AG 1999

(C) SAP AG

LO305

11.5
Typical Material Flow in the Process Industry
Operation 10 "Charging"

Charge
vessel

Ingredients
Waste

Intra material
Catalyst

Product A
Catalyst
Operation 20 "Reaction"

Product B
Reaction vessel

SAP AG 1999

The graphic shows two examples of operations carried out at the primary resources charge vessel and
reaction vessel and the typical material flow in process manufacturing.
The graphic shows:
Ingredients entering the production process
The temporary appearance of an intermediate product between two processing units which
continues to be processed without leaving the process. Such materials are assigned material type
INTR Intra material.
Waste produced during the manufacturing process.
The use of a catalyst that enters the process at a certain point of time and leaves it again later.
The manufacture of one or more products. If several planned materials are manufactured during one
production run, they are called co-products.

(C) SAP AG

LO305

11.6
Material-Recipe Assignment (I)
Master recipe
Material list
Recipe header

Bill of material
1

Material
(to be produced)

Operation 10

Material
component 10

Operation 20

Material
component 20

Operation 30

Material
component 30
Material
component 40

Phase 31
1 Material-recipe
assignment

SAP AG 1999

The material to be produced is assigned to the master recipe at header level.


The structure of the product, which is the material to be produced along with the corresponding material
components without operation and phase assignments, is defined in PP BOM Management as the bill of
material (BOM). A fixed and unique link between the master recipe and BOM is defined in a production
version. The production version is an attribute of the material to be produced.

The BOM data is used, for example, in material requirements planning and product costing.

(C) SAP AG

LO305

11.7
Bill of Material - Definition
Bill of material
Material
(to be produced)
Material
component 10
Material
component 20
Material
component 30
Material
component 40

Bill of material

A complete, fully structured list of the components that


make up a product or assembly. The list contains the object
number of each component together with the quantity and
unit of measure.

SAP AG 1999

Bills of material (BOMs) contain important basic data used in many different organizational areas.
BOM data is, for instance, important for:
Material requirements planning
Material staging during production
Product costing

(C) SAP AG

LO305

11.8
Material-Recipe Assignment (II)
Master recipe
Material list

Bill of material
Material
(to be produced)

Recipe header
Operation 10

Operation 20

Operation 30

Phase 31

1 Material-recipe

Material
component 10
Material
component 20
Material
component 30
Material
component 40

assignment

2 Material componentoperation/phase
assignment

Material quantity calculation

SAP AG 1999

The material list contains all materials that enter, are temporarily created, and leave the process along
with their planned quantities as components. It also defines the assignment of these material components
to operations or phases of the recipe according to where they appear in the process.
A specific material list component is assigned to exactly one operation or phase. You can assign several
different material components to an operation or phase.
In material quantity calculation, you define formulas to calculate the material quantities to be used or
obtained in a production process, taking into account the mixing ratios of the ingredients, yield ratios of
the products and remaining materials as well as specific material attributes (for example, concentration).

(C) SAP AG

LO305

11.9
Bill of Material - Example

Product
(Co-product)

Y-300 "Yellow paint" Base quantity : 5000 l

Ingredients

Intra material

Catalyst
...

Item 10

300 -110

Water

Item 20

300 -120

Diaminobenzol

Item 30

INTRA_01 Intra material

2000- kg

Item 40

INTRA_01 Intra material

2000 kg

Item 50

CAT_01

Catalyst

50 kg

Item 60

CAT_01

Catalyst

40- kg

Item 170 PA-300

Co-product

BOM header

Paste

BOM items

837 l
1163 kg

500- kg

...

SAP AG 1999

The graphic shows the structure of a bill of material (BOM) for a material.
The product is assigned to the BOM header. A base quantity is defined in the BOM header and the
quantities of the material components entered in the BOM items refer to this base quantity.
BOM items are, for example:
Ingredients, intra materials, catalyts, co-products, waste
Quantities of materials entering the production process are maintained with a positive number, quantities
of materials leaving the process with a number followed by a negative sign. Materials that both enter and
leave the process are assigned two different BOM items with the corresponding signs.
If a BOM item is a co-product, the corresponding indicator must be set for this item. In addition to this,
the co-product assigned to the BOM header as well as the co-products listed as BOM items must be
marked as co-products in their material master records.

(C) SAP AG

LO305

11.10
BOM Item Categories

Item Categories:

When creating a new BOM item, you must assign each component to
an item category.

The item category controls how the individual BOM items are
processed.

Stock item
NonNon-stock item
VariableVariable-size item
Text item
Document item
Intra material

SAP AG 1999

When creating a new BOM item, you must assign each item to an item category. The item category
defines the attributes and functions of an item and controls how the individual BOM items are processed.
A BOM item category specifically designed for the process industry is category M for intra materials.
The item category determines, for example:
Whether you must enter a material number
Whether quantity-based inventory management is to be carried out for this item
Which sign is to be entered for the item quantity
Whether sub-items can be used
What the screen selection and the screen layout of the item detail screens look like
Note that you cannot change the item category once you have created an item. You can only correct a
wrong item category assignment by deleting the item and creating it again.

(C) SAP AG

LO305

10

11.11
Material List
Ph 11
300 -110

Water

837 l

Ph 12
300 -120

Diaminobenzol

1163 kg

INTRA_01 Intra material

2000- kg

INTRA_01 Intra material

2000 kg

CAT_01

Catalyst

50 kg

CAT_01

..
.

Catalyst

40- kg

PA-300

Paste

Ph 13

Ph 22
Ph 31

..
.

500- kg

Ph 21

Ph 23

Ph 32
Ph 33

SAP AG 1999

In the material list, the material components of the BOM are assigned to phases and operations.
The material list is made up of components representing the materials entering and leaving the
production process, as well as temporarily existing materials and their planned quantities. It also defines
the assignment of these material components to operations or phases of the recipe according to their
appearance in the process.
A specific material list component is assigned to exactly one operation or phase. You can assign several
different material components to an operation or phase.

(C) SAP AG

LO305

11

11.12
Classification of BOM Components

Y-300 "Yellow paint"


Class type "Batch"

300 -110 Water


300 -120 Diaminobenzol

BOM item as
classifiable
object

300 - 130 Pyridene


...

Characteristic values
Solubility:
40 - 60 kg/m3
Color purity: light yellow

Class
023_02
"Pyridene"
Characteristics
Solubility
Color purity

Material quantity calculation


Batch determination in the process order

SAP AG 1999

BOM components can be classified with class type batch in the master recipe. You thus store specific
attributes that the planned material components must possess in the form of characteristic values for
individual BOM items.
BOM components are classified for the purpose of material quantity calculation and batch determination.
The characteristic values can be used in the formulas of material quantity calculation.
The characteristic values defined in the process order are used as selection criteria during batch
determination.

(C) SAP AG

LO305

12

11.13
Material Quantity Calculation I

Material quantity calculation


Calculation of the material quantities to be used
or obtained in a production process, taking into
account the mixing ratios of the ingredients, yield
ratios of the products and remaining materials as
well as specific material attributes.

SAP AG 1999

(C) SAP AG

LO305

13

11.14
Material Quantity Calculation II

Ingredients
Raw
material

Catalyst

Solvent

Characteristics
Concentration:
80%

Characteristics
Viscosity:
15.5 cP
Yield
Remaining
material

Catalyst

Product

SAP AG 1999

In material quantity calculation, you define formulas to calculate the material quantities to be used or
obtained in a production process, taking into account the mixing ratios of the ingredients, yield ratios of
the products and remaining materials as well as specific material attributes (for example, concentration).
Formulas for material quantity calculation can consist of:
All quantities of materials in the material list
The characteristics and their values
Quantities assigned to operations or phases

(C) SAP AG

LO305

14

11.15
Material Quantity Calculation - Example
Product: fruit juice

Production version: 0001

Master recipe: fruit juice production


Material list

Bill of material
Fruit juice

Recipe header
MIXING
MIXING OPERATION
OPERATION

Fruit premix

- Charge
Lemon juice

- Mix

Treated
Treated water
water

-- Discharge
Discharge

Sugar

Material quantity calculation

SAP AG 1999

The food division of your company produces fruit juice. At the beginning of the mixing operation, the
individual components fruit premix, lemon juice, treated water, and sugar are charged into the mixer.
The fruit premix and lemon juice are listed in the material BOM and material list in their proportion
units Liter fruit and Liter acid.

(C) SAP AG

LO305

15

11.16
Material Quantity Calculation - Process (I)
Fruit juice (A)

Fruit premix (B)

Quantity: 1000 liter (A1)

Quantity: 350 liter fruit (LF) (B1)

35 % fruit content (A2)

80 - 100 % fruit content (B2)

2 % acid content (A3)

3 - 5 % acid content (B3)


B1 = A1 * A2
Adjust product
quantity?

Recalculate
product quantity

Batch determination:
fruit premix

A1 = (B1n) * A2

Batch 1:

100 LF (B11)

Batch 2:

150 LF (B12)

and so on

Lemon juice (C)


Quantity: 6.875 liter acid (LS) (C1)
40 -80 % acid content (C3)

SAP AG 1999

C1 = A1 * A3 - ((B1n / B2n) * B3n )

You want to use a fruit premix with varying fruit and acid content to produce a fruit juice whose fruit
content is always 35 % and whose acid content is always 2%. The fruit quantity in the fruit premix is
thus calculated as follows:
Fruit quantity of fruit premix = Quantity of fruit juice * 35 %

The fruit premix has limited shelf life, therefore you want to use complete batches, i.e. no batch splits.
The actual fruit quantity in the fruit premix may not equal the planned fruit content, so the product
quantity and all component quantities must be adjusted. You adjust the fruit content of the fruit juice by
mixing water with it. The acid content, on the other hand, is adjusted by adding lemon juice. Different
lemon juice batches also have different acid contents.

The product quantity in the order is determined by the available fruit quantity in the fruit premix. The
system must calculate the fruit juice quantity as follows:
Fruit juice quantity = Fruit quantity of fruit premix / Fruit content of fruit juice

To obtain the intended acid content of the fruit juice, you must balance variations in the percent of acid
content of the fruit premix by adjusting the lemon juice quantity. This adjustment is not in proportion to
the product quantity:
Acid quantity of lemon juice = Acid quantity of fruit juice - Acid quantity of fruit premix

(C) SAP AG

LO305

16

11.17
Material Quantity Calculation - Process (II)
Batch determination:
lemon juice
Batch 1:

5 LS (C11)

Batch 2:

1.9 LS (C12)

Add to obtain product quantity:


Treated water (D)
Quantity: 545 L (D1)
D1 = A1 - (B1n / B2n) - (C1n / C3n)

Sugar (E)
Quantity: 10 kilograms (E1)
E1 = A1 / 100
(to exactly 100 g)

SAP AG 1999

After batch determination has been carried out for the lemon juice, the actual acid quantity in the lemon
juice and the actual fruit quantity in the fruit premix are known. The batch-specific quantity proportions
of fruit and acid can be used to calculate the physical quantities of the fruit premix and lemon juice.
Treated water is added to obtain the product quantity. The amount of water required depends on the
product quantity and the physical quantities of the fruit premix and lemon juice:
Quantity of water = Quantity of fruit juice - Quantity of fruit premix - Quantity of lemon juice.
When adding water, the quantity added is always rounded up to full liters.
Sugar is added to improve the taste of the fruit juice. The sugar dissolves completely. The amount of
sugar added is to be approximately 1% of the product quantity. It is to be added in 100 gram portions.

(C) SAP AG

LO305

17

11.18
Material Quantity Calculation Screen
Formula definition

[001,001] * ([001,002] / 100)


003,001 003T-RJ100:gquantity

Components/operations
-

001
Quantity

002
Fruit content

003
Acid cont..

1000 L

35 %

2%

80 %

3%

001 MT

T-FJ100

002 OP

Charge

1000 L

003 MT

T-RJ100

350 LF

004 MT

T-RJ200

Select formula
Key
MT = Material text
OP = Operation

Insert formula

Calculate prod. qty

Column number

[ 003 , 001 ]
Line number

SAP AG 1999

The numbers in brackets define a "cell" consisting of line and column numbers (see key)
The detail functions of material quantity calculation are:
Select formula
This function selects the cell on which you have positioned the cursor and enters it in the formula
section of the screen.
Insert in formula
This function copies the coordinates of the line and column in the formula section, for example,
[003,001].
Save formula
This function saves formulas but does not transfer the values into the material list.
Save formula and copy result This function saves all formulas and copies the values to the
material list and bill of material.
Formula overview This function contains the quantities and value fields plus the
corresponding formulas. References used in the formulas are replaced by the value and the
description of the field to which they refer.
Calculate product qty The system calculates the product quantity and subsequently updates all
component, operation, phase, and scrap quantities for which formulas have been defined.

(C) SAP AG

LO305

18

11.19
Product Quantity Calculation
Material
quantities

Total quantity Fruit content Acid content

ID

Material

Un

Fruit juice

1000

35 %

2%

Fruit premix

LF

350

80 %

3%

Lemon juice

LS

6.875

Water

545

Sugar

...

Material
characteristics

40 %

KG
10
Qty (1) = Qty (4) / Fruit content (1)
1000 = CSUM (4) / (fruit content (1) / 100)

SAP AG 1999

The material, phase, and operation quantities for a recipe can be linked to each other in formulas.
Material characteristics can also be entered in the formulas.
The formulas are used to calculate the relevant quantities when creating a process order.
If a material or characteristic quantity is changed, dependent quantities can be recalculated.
The product quantity in the order is determined by the available fruit quantity in the fruit premix. The
system calculates the fruit juice quantity as follows:
Quantity of fruit juice = Quantity of fruit premix / Fruit proportion of fruit juice.
To calculate the actual fruit quantity of the fruit premix, the system must add the fruit quantities of the
batches selected in the order.
Adding batch quantities or characteristic values - CSUM
This function adds the batch quantities or the values in the characteristic column you specified for all
batches of a material item. As long as no batches have been assigned to the material item, the function
returns the quantity of the material item or the characteristic value of the material item.
The formula for material quantity calculation looks as follows:
CSUM(004) / ( [001,002] / 100 )

(C) SAP AG

LO305

19

11.20
Component Quantity Calculation (I)
Material
quantities

Total quantity Fruit content Acid content

ID

Material

Un

Fruit juice

1000

35 %

2%

Fruit premix

LF

350

80 %

3%

Lemon juice

LS

6.875

Water

545

Sugar

KG

10

...

Material
characteristics

40 %

Qty (4) = Qty (1) * Fruit content (1)


350
=
Qty (1) *(fruit content (1) / 100)

SAP AG 1999

The fruit quantity of the fruit premix can be calculated using a percentage calculation.
The formula for material quantity calculation looks as follows:
[001,001] * ( [001,002] / 100 )

(C) SAP AG

LO305

20

11.21
Calculation Using Active Ingredient Quantities of
Batches
Material
quantities

USERUSER-EXIT

Material
characteristics

Total quantity Fruit content Acid content

ID

Material

Un

Fruit juice

1000

35 %

2%

Fruit premix

LF

350

80 %

3%

Lemon juice

LS

6.875

Water

545

Sugar

KG

10

40 %

...

Qty (5) = Qty (1) * Acid content (1) - Phys. qty (4) * Acid content (4)
6.875 =Qty (1) * (Acid con. (1) / 100) - - ( (Qty (4) / Fruit content (4)) * Acid content (4))

SAP AG 1999

To obtain the intended acid content of the fruit juice, you must balance variations in the percent of acid
content of the fruit premix by adjusting the lemon juice quantity. This adjustment is not in proportion to
the product quantity:
Acid quantity of lemon juice = Acid quantity of fruit juice - Acid quantity of fruit premix
The acid quantity of the fruit juice is calculated by multiplying the product quantity with the acid content
of the fruit juice.
The acid quantity in the fruit premix is calculated by multiplying its physical quantity with its acid
content. The physical quantity is calculated by dividing the fruit quantity by the fruit content. The
following calculation must therefore be carried out for each batch of the fruit premix:
Fruit quantity of fruit premix / Fruit content of fruit premix * Acid content of fruit premix. Afterwards,
the results for the acid quantities of the fruit premix are added.
A user exit is required for this complex calculation.
An SAP enhancement (user exit) for material quantity calculation can be used to enhance standard
functionality. The following are just some of the features offered by this SAP enhancement:
Enhancement of input data through the inclusion of additional fields and columns
Calculation of values that cannot be calculated in the standard system
The formula for material quantity calculation is: [001,001] * ([001,003] / 100) - CPSM (004;005)

(C) SAP AG

LO305

21

11.22
Calculation Using Physical Batch Quantities
Material
quantities

Material
characteristics

Total quantity Fruit content Acid content

ID

Material

Un

Fruit juice

1000

35 %

2%

Fruit premix

LF

350

80 %

3%

Lemon juice

LS

6.875

Water

545

Sugar

KG

10

40 %

...

Qty (6) = Qty (1) - Phys. Qty (4) - Phys. Qty (5)
545 = Qty (1) - CQSM (Qty (4) / Fruit content (4)) - CQSM (Qty (5) / Acid content (5))

SAP AG 1999

Treated water is added to obtain the product quantity. The amount of water required depends on the
product quantity and the physical quantities of the fruit premix and lemon juice:
Quantity of water = Quantity of fruit juice - Quantity of fruit premix - Quantity of lemon juice.
The quantity of water added is always rounded up to full liters:
Adding weighted batch quantities of characteristic values: Quotient sum - CQSM. For each batch
of a material item, this function divides the batch quantities by the value in the characteristic column you
specified or the value of the first characteristic column by that of the second column. It then adds the
results. The system interprets the characteristic value as a percentage if its unit of measure contains a
percent sign (%).

As long as no batches have been assigned to the material item, the function divides the quantity of the
material item by the corresponding characteristic value or the first characteristic value of the material
item by that of the second value.

You may need this function, for example, to calculate the total of the physical batch quantities from the
active ingredient quantities of batches based on the active ingredient concentration.

The formula for material quantity calculation looks as follows:


[001,001] - CQSM(004;002) - CQSM(005;003)

(C) SAP AG

LO305

22

11.23
Component Quantity Calculation (II)
Material
quantities

Material
characteristics

Total quantity Fruit content Acid content

ID

Material

Un

Fruit juice

1000

35 %

2%

Fruit premix

LF

350

80 %

3%

Lemon juice

LS

6.875

Water

545

Sugar

KG

10

40 %

...
Qty (7) = Qty (1) / 100 (to exactly 100 grams)
10 =
Qty (1)
DIV 10 / 10

SAP AG 1999

Sugar is added to improve the taste of the fruit juice. The sugar dissolves completely. The amount of
sugar added is to be approximately 1% of the product quantity. It is to be added in 100 kilogram
portions.
The quantity of sugar can be determined using a percentage calculation. The result is always to be
rounded to 100 kilograms. The following basic function is used:
DIV - Division using integers; not intended for negative numbers. Example: 1015 DIV 10 = 101
The formula for material quantity calculation is as follows:
[001,001] DIV 10 / 10
It returns results with no more than one decimal place.

(C) SAP AG

LO305

23

11.24
Master Recipes, Materials: Unit Summary

The material to be produced is assigned to the

recipe at the recipe header level.


The material list shows the assignment of the BOM

components to phases.
BOM components are classified so that a system-

aided batch determination can later be carried out.


Using material quantity calculation, you can

calculate the material quantities required or


obtained in a production process by considering
the mixing ratios of the ingredients and yield
ratios of the products.

SAP AG 1999

(C) SAP AG

LO305

24

11.25Master Recipes, Materials: Exercises


Unit: Master Recipes
Topic: Materials

At the conclusion of these exercises, you will be able to:


Carry out material-recipe assignment
Create a material list
Check a production version
Classify bill of material components
Set up material quantity calculation
Your company is going to put a new product on the market.
As the person responsible, you will add to a material list and prepare a
BOM component for system-aided batch determination in the master
recipe for the new detergent.

1-1

Material-recipe assignment
Your master recipe T-DET1## describes the production of the material T-FD1##.
Check the material assignment in the recipe header.
How was this material assignment determined?
____________________________________________________________

1-2

Creating a BOM and material list for the product assigned


Create the BOM and material list for the assigned material.
Go to the material overview (Materials tab) of your recipe.

(C) SAP AG

LO305

25

1-2-1 Bill of material for material T-FD1##


The initial screen for BOM maintenance appears. After entering the data, you
can assign the required material components in the BOM. Enter the following
data:
Item

Item cat.

Component

Quantity

0010

T-RD1##

975 liters

0020

T-RD2##

400 liters

0030

T-RD3##

1225 liters

0040

T-RD4##

1000 liters

0050

T-RD5##

1400 liters

Enter 5000 L as a base quantity in the BOM header.


Choose Header.
1-2-2 Material list for material T-FD1##
Choose Back. The overview screen for the material list appears. Assign the
material components to the phases of your recipe based on the following table.
Component

Phase

T-RD1##

110

T-RD2##

110

T-RD3##

130

T-RD4##

220

T-RD5##

220

Save your recipe.

(C) SAP AG

LO305

26

1-3

Checking the production version


Perform a consistency check for production version 0001 of material T-FD1##.
Which messages appear in the consistency log?
____________________________________________________________
____________________________________________________________
What is the new check status for the production version?
____________________________________________________________

1-4

Classifying BOM components


1-4-1 In your master recipe T-DET1## for material T-FD1##, classify the BOM
component T-RD1##.
You must classify the BOM components so you can carry
out system-aided batch determination in the process
order.

To which class of class type 023 Batch is the BOM item assigned? Why?
__________________________________
__________________________________
Define the following values for the class characteristics as batch selection
conditions:
Concentration

40 50 %

Density

1.3000 - 1.4000 g/ccm

Save your master recipe.

(C) SAP AG

LO305

27

1-5

Material quantity calculation


To carry out material quantity calculation, you will create a production version and a
master recipe for fruit juice production in your company.
The corresponding material master records are already available in the system. The
master record for the fruit juice mixing line still needs to be created.
1-5-1 Creating a resource
Create resource master record T-JM1## of the resource category RE##. The
description is "fruit mixing line".
Check the default values offered for the resource.
Fruit juice production only takes place in a two-shift plant.
Assign grouping 01 (for shift definitions and shift sequences) to your resource
in the header data of the assigned capacity category. Choose Intervals and shifts
and insert a new interval with shift sequence.
Choose the interval from today to today + 1 year and the shirt sequence M2.
Assign the fruit mixing line to the cost center for the production of food. Use
the F4 help to find the cost center key.
Save the resource.
1-5-2

Checking the material master records


In addition to the materials considered in Unit 6 Batches: Settings for Active
Ingredient Management, which are fruit juice T-FJ1##, fruit premix T-RJ1##
and lemon juice T-RJ2##, treated water and sugar are also to be added to the
master recipe for fruit juice production.
The material numbers to be used are:
Treated water
Sugar

(C) SAP AG

= T-RI5##
= T-RJ3##

LO305

28

1-5-3

Creating production versions


Create a production version 0001 in plant 1100 for fruit juice T-FJ1##.
The lot size covers the range of 1000 to 20000 L. The production version is
valid from today.
The master recipe for production version 0001 is maintained with group counter
1 for recipe group T-JUI1##. The corresponding alternative BOM number 1 is
used in production.

1-5-4

Creating master recipes


Create master recipe 1 in recipe group T-JUI1## with the following data
(profile: PI01) for the production version:

Description of the recipe: Fruit juice production, grp ##


Plant:

1100

Status:

4 Released general

Use:

1 Production

Planner group:

001 Planner group PI

Charge quantity range:

1000 - 20000 liters

1-5-4-1

Text for recipe header


Create a text for the header that describes the recipe.
Choose Header text.
Header text:

Fruit juice production, grp ##

Base recipe for fruit juice production at the fruit juice mixing line.

(C) SAP AG

LO305

29

1-5-4-2

Operations and phases


Create the following operations and phases for the recipe:

Op

Ph

SOp

CRD

100

Resource
T-JM1##

Description
Mix

110

100

SP

Charge

120

100

SP

Mix

130

100

SP

Discharge

1-5-4-3

Material BOM
Create the following material BOM for the recipe:

Item:

ICt

Material component

Quantity

Unit of
measure

10

Fruit premix T-RJ1##

350

LF

20

Lemon juice T-RJ2##

7.65

LS

30

Treated water T-RI5##

570

40

Sugar T-RJ3##

10

KG

Maintain the following data in the BOM header:


BOM text: Fruit juice
Base quantity: 1000 L
1-5-4-4

Material list
Assign all of the materials listed above to phase 110.
Save the master recipe.

(C) SAP AG

LO305

30

1-5-5 Material quantity calculation


Maintain the required formulas in the material quantity calculation for master
recipe T-JUI1##. Save the material quantity calculation without copying the
results to the material list (and then to the BOM).
To produce fruit juice, we will begin with a fruit premix which has varying fruit
and acid content. The fruit premix has a limited shelf life so complete batches
must be used. Since the fruit content of the final product must be 35%, the
quantity of fruit juice produced may have to be adjusted. Lemon juice is used
to balance the variations of acid content in the fruit premix and to maintain a
2% acid content in the final product. Treated water is added (rounded up to full
liters) to obtain the quantity of fruit juice . Finally, sugar is added (in 100 gram
portions) to improve the taste. The sugar content is approximately 1% of the
total product quantity.
The components fruit premix B and lemon juice C both consist of their active
ingredients fruit and acid, as well as their carrier material water. The physical
quantity will refer to the sum of the active ingredient quantity and the carrier
material quantity.
To do the following exercise, refer to the slides Material Quantity
Calculation - Process (I) and (II).

1-5-5-1

Product Quantity Calculation


The total quantity of fruit juice A1 is calculated by dividing the fruit
quantity in the batches of fruit premix B1n by the fruit content of
fruit juice A2 (which is 35%).
What is the calculation formula for the total quantity of the fruit
juice (also the product quantity in this case)?
_____________________________________________
Familiarize yourself with the functions available in the application
help for material quantity calculation.

What is the formula that is to be entered in the cell [001,001]?


_____________________________________________
What result appears in the Quantity column for product T-FJ1##
after you enter the formula above?
_____________________________________________
(C) SAP AG

LO305

31

How does this result change when you recalculate the product
quantity for the fruit premix after batch determination in the process
order?
_____________________________________________
_____________________________________________

(C) SAP AG

LO305

32

1-5-5-2

Calculating the fruit quantity B1 in the fruit premix


The fruit premix has varying fruit and acid content. You need to use
a quantity that will always produce a fruit juice with 35% fruit
content and 2% acid content. The fruit premix B component is listed
in the material list in its proportion unit LF (liter of fruit) which
equals fruit quantity B1. It is calculated by multiplying the total
quantity of fruit juice A1 by its fruit content in percent A2.
What is the calculation formula for the fruit quantity?
_____________________________________________
What formula must be entered in the cell [004,001]?
_____________________________________________
What result appears in the Quantity column for material T-RJ1##
after you enter the formula above?
_____________________________________________

1-5-5-3

Calculating the acid quantity C1 in the lemon juice


In the product fruit juice, a certain acid quantity must be obtained (=
2 % of the total quantity of the fruit juice), which is a combination
of the acid quantity in the fruit premix and the acid quantity C1 in
the lemon juice.
What is the formula for calculating the acid quantity in the fruit
juice?
Acid quantity in the fruit juice = _____________________
The acid quantity in the fruit juice is calculated from the total
quantity of fruit juice A1 and the acid content of the fruit juice in
percent A3.
To obtain the desired acid quantity in the fruit juice, the acid
quantity contained in the lemon juice must be added to the acid
quantity contained in the fruit premix batches.
The fruit premix is listed in the material list in its proportion unit LF
and therefore also in its fruit quantity. Which calculation is required
to be able to convert the fruit quantities B1n to the physical
quantities of the fruit premix batches (unit of measure: liters)?
Physical quantity =

___________________________

The physical quantity must be multiplied by the acid content B3n to


obtain the acid quantity of the fruit premix in the batches. For this
reason, a USER-EXIT is used to enter the quotient of acid content
and fruit content of the individual batches in the 5th column
"Intermediate results".
(C) SAP AG

LO305

33

Intermediate results = B3n / B2n


The acid quantity of the fruit premix is calculated from the product
of the fruit quantity B1n and intermediate result in the 5th column.
What is the formula that is to be entered in the cell [005,001]?
_____________________________________________
What result appears in the Quantity column for material T-RJ2##
after you enter the formula above?
_____________________________________________
1-5-5-4

Calculating the component quantity of treated water D1


After the fruit premix and lemon juice have been charged, water is
added until the required product quantity is reached.
The total quantity of water is calculated by subtracting the two
physical quantities of fruit premix and lemon juice from the total
quantity of fruit juice.
What is the calculation formula for the total quantity of water?
_____________________________________________
What is the formula that is to be entered in the cell [006,001]?
_____________________________________________
What result appears in the Quantity column for material T-RI5##
after you enter the formula above?
_____________________________________________
Change the formula so that the result is rounded down to the next
whole liter.
What is the formula in cell [006,001]?
_____________________________________________
Use the same function to round the product quantity down to the
next whole liter!
What is the formula in cell [001,001]?
_____________________________________________

1-5-5-5

Calculating the component quantity sugar E1


The sugar completely dissolves in the fruit juice. A sugar content of
1% of the product quantity ensures the best taste for the fruit juice.
100 grams of sugar should always be added to the fruit juice mixture

(C) SAP AG

LO305

34

per 10 liters of fruit juice. The sugar quantity is always weighed on


the fruit juice mixing line to exactly 100 grams.
Which of the three formulas gives the correct result?
a) [001,001] DIV 100
b) [001,001] DIV 10 / 10
c) [001,001] / 10 DIV 10
_____________________________________________
Maintain the correct formula for calculating the sugar quantity.
Save the formula without copying the result to the BOM.
1-5-5-6

Formula test for different quantities of fruit premix


The fruit premix component is the starting point for all further
material quantity calculations in this example. Use different active
ingredient quantities of the fruit premix to check the function of the
formula entered. Choose the formula for the component quantity of
the fruit premix and overwrite it with the following values:
a) T-RJ1##: Quantity= 352

(C) SAP AG

LO305

(LF)

35

Enter the new values of the other quantities:


Material

Quantity

Fruit juice
Lemon juice
Treated water
Sugar
Recalculate the product quantity to adjust it. What are the new
quantities?
Material

Quantity

Fruit juice
Lemon juice
Treated water
Sugar
Which value has not changed, even though it is dependent on the
product quantity?
_____________________________________________
Cancel material quantity calculation without saving.
b) T-RJ1##: Quantity= 370

(LF)

Enter the new values of the other quantities in the table below:
Material

Quantity

Fruit juice
Lemon juice
Treated water
Sugar
Recalculate the product quantity to adjust it. What are the new
quantities?
Material

Quantity

Fruit juice
(C) SAP AG

LO305

36

Lemon juice
Treated water
Sugar
Cancel material quantity calculation without saving.

(C) SAP AG

LO305

37

11.26Solutions
Unit: Master Recipes
Topic: Materials

1-1

Material-recipe assignment
Use the production version transaction to access your recipe T-DET1##.
In the recipe:
Recipe header tab
Choose Material assignments.
Material assignment resulted from the creation of production version 0001 for material
T-FD1##.

1-2

Creating a BOM and material list for the product assigned


1-2-1 Bill of material for material T-FD1##
You are on the Material assignments tab.
Recipes tab
Choose Materials.
On the Create Material BOM: Initial Screen, choose Enter.
Enter the material components.
To enter the base quantity, choose Header,
1-2-2 Material list for material T-FD1##
in the BOM header:
F3 (Back)
Materials tab
Choose Create assignment.

1-3

Checking the production version


Task list exists (no warnings or errors)
BOM exists (no warnings or errors)

(C) SAP AG

LO305

38

Last check ok (green light)

(C) SAP AG

LO305

39

1-4

Classification of BOM Components


1-4-1 In your master recipe T-DET1## for material T-FD1##, classify the BOM
component T-RD1##.
Production versions
Select: Production version 0001
Choose Recipe.
Materials tab
Choose Bill of material.
Select: T-RD1##
Extras Batch classification.
To which class of class type 0023 Batch is the BOM item assigned? Why?
023_14 This class was used in the unit Batches to classify the raw material
T-RD1##.
The BOM item inherits the classification from the material master.

1-5

Material quantity calculation


1-5-1 Create resource
SAP standard menu Logistics Production -Process Master Data
Resources Resource Create.
Resource Category:
Description:

RE##

Fruit mixing line

When you maintain the resource data, the system suggests values that were
created in Customizing as default values.
Copy the default values without changing them.
Capacities screen:
Choose Capacity Header Data.
Enter grouping 01 for shift definitions and shift sequences.
Choose Intervals and shifts.
Choose Insert intervals.
Valid from:
(C) SAP AG

<today>

Valid until:< today + 1 year >


LO305

40

Shift sequence:

M2 < ENTER >

Costing screen:
Position the cursor on the Cost center field.
F4 help:

Cost center short text: *Food*

Cost center:

4271

Food Production

Save the resource.


1-5-2 Checking the material master records
Treated water = T-RI5##
Sugar

= T-RJ3##

1-5-3 Creating production versions


SAP standard menu Logistics Production -Process Master Data
Production Versions
Selection conditions:
Plant: 1100
Material: T-FJ1##
Choose Create production version.
Detail maintenance:
Material:

T-FJ1##

Production version:

0001

From lot size: 1000

To lot size:20000

Valid from:

fruit juice production

<today>

Detailed planning:
Task list type: Master recipe
Task list group:

T-JUI1## Group counter 1

Alternative BOM 1

BOM usage

Ignore warnings.
Close the detail screen.
1-5-4 Creating master recipes
Select production version 0001.
Choose Recipe.
Final date: < today >
(C) SAP AG

LO305

41

Profile:

PI01

Maintain the data as described for the exercise.


1-5-4-1

Text for recipe header


Recipe header tab
Maintain the data as described for the exercise.

1-5-4-2

Operations and phases


Operations tab
Maintain the data as described for the exercise.

1-5-4-3

Material BOM
Materials tab
Screen: Create Material BOM: Initial Screen
Choose Enter.
Screen: Item Overview: General

Item:

ICt

Material component

Quantity

Unit of
measure

10

T-RJ1##

350

LF

20

T-RJ2##

7.65

LS

30

T-RI5##

570

40

T-RJ3##

10

KG

Choose Header (or F6).


BOM text: Fruit juice
Base quantity: 1000
Choose Back.
1-5-4-4

Material list
Materials tab
Select all materials.
Choose Create assignment.
Assign to operation/phase:

110

Save the master recipe.


(C) SAP AG

LO305

42

(C) SAP AG

LO305

43

1-5-5 Material quantity calculation


1-5-5-1

Product quantity calculation formula:


A1 = (B1n) / A2
Formula definition in cell [001,001]:
CSUM(004) / ( [001,002] / 100 )
Result: 1000
This result changes immediately when the active ingredient quantity
of the batch found for the process order is not equal to the active
ingredient quantity planned. The product quantity adjusts itself to
the active ingredient quantity found.

1-5-5-2

Fruit quantity calculation formula:


B1 = A1 * A2
Formula definition in cell [004,001]:
[001,001] * ([001,002] / 100)
Result: 350

1-5-5-3

Acid quantity calculation formula:


Acid quantity in the fruit juice = A1 * A3
Physical quantity calculation formula
Physical quantity = (B1n / B2n)
Formula definition in cell [005,001]:
[001,001] * ([001,003] / 100) CPSM (004;005)
Result: 6,875

1-5-5-4

Water quantity calculation formula:


D1 = A1 - (B1n / B2n) - (C1n / C3n)
Formula definition in cell [006,001]:
[001,001] - CQSM(004;002) - CQSM(005;003)
Result: 545,31
Formula definition in cell [006,001]:
ROUND ([001,001] CQSM(004;002) CQSM(005;003))
Formula definition in cell [001,001]:
ROUND (CSUM(004) / ([001,002] / 100))

(C) SAP AG

LO305

44

1-5-5-5

Sugar quantity calculation formula:


Correct result: Formula b

1-5-5-6

Formula test
a) T-RJ1##: Quantity= 352

(LF)

Material

Quantity

Fruit juice

1000

Lemon juice

6.8

Treated water

543

Sugar

10
Recalculated product quantity:

Material

Quantity

Fruit juice

1006

Lemon juice

6.92

Treated water

549

Sugar

10
The sugar quantity has not changed. It is not increased by 100
grams until the product quantity is increased by 10 liters. Cancel
without saving.
b) T-RJ1##: Quantity= 370

(C) SAP AG

(LF)

Material

Quantity

Fruit juice

1000

Lemon juice

6.125

Treated water

522

Sugar

10

LO305

45

Recalculated product quantity:

(C) SAP AG

Material

Quantity

Fruit juice

1057

Lemon juice

7.265

Treated water

576

Sugar

10.5

LO305

46

12
Master Recipes: Control View

Contents:
Process management
Process instructions and control recipe destinations
Control recipe creation
PI sheet simulation

SAP AG 1999

(C) SAP AG

LO305

12.2
Master Recipes, Control View: Unit Objectives

At the conclusion of this unit, you will be able to:


Define the tasks of process management
Create and send control recipes
Define and simulate a PI sheet

SAP AG 1999

(C) SAP AG

LO305

12.3
Overview Diagram 12
1 Introduction

9 Production Version

PP-PI Overview

10 and Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

Master Recipes: Operations

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

12.4
Master Recipes, Control View: Business Scenario

The process manufacturing of the product will

be controlled by process operators. As the


person responsible, you will define a
corresponding PI sheet in your master recipe.

SAP AG 1999

(C) SAP AG

LO305

12.5
Process Management
Process
planning

Process
management

Process
order

Control
recipe

Process
control

Execution

Proces
control
system

Process
messages
Further
message
dest.

PI sheet

R/3 or
external system

SAP AG 1999

Process management is the interface between PP-PI and the systems involved in process control. Due to
its flexible structure, it can be linked to fully automated, partially automated, and manually operated
lines. Process management comprises the following functions:
Receiving control recipes with process instructions from released process orders
Transferring control recipes to the corresponding process operators or process control systems
Translating process instructions into natural language so that they can be displayed and maintained
on the screen by the process operator
Receiving, checking, and transferring process messages with actual process data
Manual entry of process messages

(C) SAP AG

LO305

12.6
Creating and Downloading Control Recipes
Process management
Manually operated
Charge

Reaction

Automated
DisDischarge Text
Charge

ReacReaction

DisDischarge

PI sheet
Process control
system

Process
order

Operation 10
Phase 11 Phase 12

Phase 13

Operation 20
Phase 21

Phase 22

Control recipe destination:


Process control system
PI sheet

Phase 23

SAP AG 1999

Using control recipe destinations, you specify the process operators or process control systems that are
to carry out the process instructions of an order in the process order.
You assign control recipe destinations to the phases of the process order. This assignment is independent
of the subdivision of operations into phases. This means that you can assign different destinations to
phases of the same operation if this makes sense from the point of view of process control.
Process management creates one control recipe for each control recipe destination of a process order. A
control recipe can only be created if all the phases involved are released. Once a control recipe has been
created, you can no longer change the process instructions of the corresponding phases in the order.

(C) SAP AG

LO305

12.7
Process Instructions and Control Recipes
Master recipe
Oper. 100

Ph 110
CRD A1
Proc.instructions

Ph 120
CRD A1
Proc.instructions

Ph 120
CRD A1
Proc.instructions

Ph 130
CRD P1
Proc.instructions

Ph 130
CRD P1
Proc.instructions
Oper. 200

Ph 210
CRD P1
Proc.instructions

Ph 210
CRD P1
Proc.instructions

Ph 220
CRD P1
Proc.instructions

Ph 220
CRD P1
Proc.instructions

Ph 230
CRD P2
Proc.instructions

Ph 230
CRD P2
Proc.instructions

Oper. 300

Oper. 100

Ph 110
CRD A1
Proc.instructions

Oper. 200

..
.

Process order

SAP AG 1999

Oper. 300

Ctrl recipe 1

Dest. A1
Ctrl recipe 2

Dest. P1

Ctrl recipe 3

Dest. P2

..
.

Process instructions are structures with which data or requests from R/3 process planning are copied to
process control. Process instructions are assigned to the phases of a master recipe or process order.
Each phase must have a control recipe destination assigned to it. A control recipe destination indicates a
process control system, a process operator, or a group of process operators to which the process
instructions that have been created for the phase are to be transferred.
To execute an actual production process, a process order is created on the basis of a master recipe.
Together with the control recipe destinations and process instructions, the operation and phase structure
is copied from the master recipe.
Once a process order has been released for production, the process instructions to be sent to the same
control recipe destination are grouped in a control recipe and transferred to process control. Exactly one
control recipe is created for each control recipe destination.

(C) SAP AG

LO305

12.8
Planning View and Control View

Example
Ph110

Ph120

FILL

MIX

Op. 100

Recipe structure
Ph130

Ph 110

EMPTY

Op. 100

Ph 210 Ph 220

FILL

Ph 120
Ph 130

Ph 230

REACT EMPTY

Op. 200

Ph 310 Ph 320

FILL

Ph 330

COOL EMPTY

Ph 210
Op. 200

Ph 220

Ph 310

Ctrl recipe 2

Control recipe 2/
Control recipe
destination P1

Ph 230

Op. 300

Ctrl recipe 1

Control recipe 1/
Control recipe
destination A1

Ctrl recipe 3

Op. 300

Ph 320

Control recipe 3/
Control recipe destination P2

Ph 330

Planning view

Control view

SAP AG 1999

Master recipes have a planning and a control view. The planning view comprises the planning of
operations, materials, resources, and inspection characteristics.
In the planning view, phases are combined into operations. Phases are hierarchically subordinate to
operations.
The control view contains information in the form of process instructions. This is required for
communication with the process control level.
In the control view, phases are combined for a control recipe destination. Phases of a recipe that are
combined for a control recipe destination do not need to belong to the same operation.
The graphic shows an example of an operation/phase structure, with two phases of different operations
being processed in parallel. The parallel filling and emptying phases are monitored by the same process
control system or process operator.

(C) SAP AG

LO305

12.9
PI Sheet

Control recipe

Operation 100
CRD 01
Proc.oper.

Phase 110

PI sheet

Proc. instr. 10

Instruction 1:

PI char. 10

Read
temperature

PI char. 20

Master recipe

Process
order

Temp:

SAP AG 1999

The control recipe destination can either be an automatic process control system or a process operator in
a production line that is manually operated (either totally or partially).
If a control recipe is sent to a process operator, the process instructions are prepared for display in
natural language and interactive processing on the screen.

(C) SAP AG

LO305

12.10
PI Sheet: Structure
PI Sheet

Header

PI sheet 1000000449
Process order: 1234

Received
Comment sheet
Material: XYZ Test
material

Operating group: W01

Control
information

Phase 10 / Instruction 10
Heat solvent.
Start agitator.
Add material ABC.

Additional
information

Note:

Due to an error...
Temp.: ______ C
Rot. speed:_____
Quantity:_______kg
Signature:_____

Note:

Phase 10 / Instruction 20
Check material quality.
Record material quantity.
Stop heating and slow
down agitator.

Record insp. results


Call mat. qty calculation
Quantity: ____ kg
Rot. speed: ______
Signature: ____

Phase 10 / Instruction 30
Start cooling and record
time and temperature
every hour.

Input values

Time
10:00
11:01

Total quantity: ?___

Comments

Input values

Insp. results
recording
Function call
Signature for
proc. step
Formula result

Temperature
175.0
168.3

SAP AG 1999

The R/3 PI sheet contains the following elements:


A header with general data such as order number, material number, and operating group
Texts containing control information and instructions for the process operator
Additional information that can be called up using the corresponding pushbutton
Comments maintained by the operators, which can be displayed using the corresponding
pushbutton
Input fields (individually or in tables) for the actual process data to be reported
Fields for formula results to be calculated by the system
The Record inspection results pushbutton, which you can use to jump to the QM function for
recording inspection results
Pushbuttons to call R/3 function modules in order to start a dialog (for example, order
confirmation) or retrieve data from internal or external applications (such as R/3 Document
Management)

(C) SAP AG

LO305

10

12.11
Process Instruction Maintenance

Master Recipe / Process Order


Phase
Process instruction view
Process instructions
Alternative
maintenance
Process instruction
characteristics view

PI
assistant

SAP AG 1999

You can use the PI assistant to maintain process instructions and process instruction categories.
The PI assistant displays special selection views for each process instruction type. No knowledge of
process instruction characteristics or their use is required to work with the PI assistant. When you exit
the PI assistant, the characteristic overviews of the process instructions are created.
You can use the PI assistant to:
Define PI categories in Customizing
Define process instructions in the master recipe or process order

(C) SAP AG

LO305

11

12.12
Displaying Generated Process Instructions
Control recipe dest. 10 Operating group 10
Address
GROUP 10
Type
1 Control recipe transfer to R/3
PI sheet
Digit. signature
Required

Recipe
Op. 10

InstCat

Ph. 11

CRD A1
OPTEXT

Item
Description
Sequence
Scope of gen.
Filters
03
01
00

SEQDEF 05
01
05

At the start of an operation


Only one proc. instruction
No filter
At the start of a phase
For all predecessors
No filter

SAP AG 1999

You can display information on the process instructions that are automatically generated for the recipe
from the operation overview of the master recipe.
The system displays the following information for each control recipe destination assigned to the phases:
The header data of the destination (for example, address, type, type of signature)
The settings for the automatically generated process instructions (for example, process instruction
category, item, scope of generation)

(C) SAP AG

LO305

12

12.13
PI Sheet Simulation in the Master Recipe

PP

Production requirements

Master recipe

Process management

Simulation

Process
messages

Control recipe:
proc.instructions

Process control
system
PI sheet

PP-PI

Process order

Process
control level

SAP AG 1999

The effects process instructions and their characteristics have on the layout and structure of the PI sheet
become visible only after the control recipe has been created. To check the PI sheet beforehand, you can
simulate a PI sheet in the master recipe.
From within the master recipe, you can simulate a PI sheet or parts of a PI sheet in the following ways:
For a control recipe destination
For selected phases
For selected process instructions

(C) SAP AG

LO305

13

12.14
Master Recipes, Control View: Unit Summary

Process instructions that have been assigned to


phases are combined in control recipes.
One control recipe is created for each control
recipe destination.
The control recipes are sent to the corresponding
control recipe destinations.
A control recipe can be created to appear on the
screen as a PI sheet for a process operator.
You can simulate a PI sheet from the master recipe.

SAP AG 1999

(C) SAP AG

LO305

14

12.15Exercises
Unit: Master Recipes
Topic: Control View

At the conclusion of these exercises, you will better understand:


Control recipe destinations
Process instructions
PI sheets
The process manufacturing of the product will be controlled by process
operators.
As the person responsible, define a corresponding PI sheet in your master
recipe.

1-1

Control recipe destinations and process instructions


Display the operation overview for recipe 1 of the recipe group COLORS.
1-1-1 Control recipe destination
Which control recipe destinations have been assigned to the phases of the
recipe?
Input help F4 in the Destination field
CRD Description of control recipe destinations
____

__________________________________

____

__________________________________

1-1-2 Process instructions


Which process instruction categories are assigned to phase 1010?
To which process instruction types do they belong?
(C) SAP AG

LO305

15

In the operation overview:


Choose Proc. inst for phase 1010
Input help F4 for Type field.

(C) SAP AG

LO305

16

ProcInstCat Type
__________

___________________________

__________

___________________________

__________

___________________________

Which process instruction types have been defined in the R/3 System?
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________

Display the administrative data for a process instruction.


Choose Process instruction details and then the Admin. Data tab.
1-1-3 Process instruction characteristics
Which process instruction characteristics are assigned to the process instruction
INSTR?
Choose Process instruction details.
______________________________
______________________________
The characteristics PPPI_INSTRUCTION and PPPI_NOTE are each assigned a
long text. Display the long texts.
Display the administrative data for a process instruction characteristic.
Choose Details for process instruction characteristic and then the
Administrative data tab.
1-1-4 Simulating a PI sheet
Display the PI sheet for the phases with control recipe destination 01 in a
simulation.
(C) SAP AG

LO305

17

Choose Simulate PI sheet.


1-2

Defining a PI sheet in recipe T-DET1##


Create process instructions for your recipe T-DET1## using the information in the
following table. Check and correct the texts and remove the process instruction
characteristics you do not need.
The process instructions required for reporting material
movement and order dates as well as other process instructions
with information on operations, phases, and material components
are all defined as automatically generated process instructions for
the control recipe destination DE (See course LO060).
Note: In this exercise, you only have to define process
instructions for instructions and notes for the line operator.
Process instructions for in-process quality checks will be
explained in a separate unit.

Phase 110:
PI

ProcInstCat

PI Characteristic

10

INSTR

PPPI_INSTRUCTION (control instructions)


Long text (ZT-DET100-1):
Fill the required quantity of raw materials T-RD1##
(sulfuric acid) and T-RD2## (lauryl alcohol) into charging
tank and confirm the filled quantity. Pay attention to the
safety instructions.
PPPI_NOTE (note)
Long text (ZT-DET100-2):
Caution! Corrosive material! Wear protective clothing,
gloves, and protective mask.

Phase 120:
PI

ProcInstCat

PI Characteristic

10

INSTR

PPPI_INSTRUCTION (control instruction)


Long text (ZT-DET100-3):
Turn on agitator. Mix ingredients for 10 min.

Phase 130:
PI

ProcInstCat

PI Characteristic

10

INSTR

PPPI_INSTRUCTION (control instruction)

(C) SAP AG

LO305

18

Long text (ZT-DET100-4):


Add displayed quantity of water to mixture.
Phase 210:
PI

ProcInstCat

PI Characteristic

10

INSTR

PPPI_INSTRUCTION (control instruction)


Long text (ZT-DET100-5):
Transfer material from charging tank to reaction tank. Start
agitator.

Phase 220:
PI

ProcInstCat

PI Characteristic

10

INSTR

PPPI_INSTRUCTION (control instruction)


Long text (ZT-DET100-6):
Carefully add the required raw materials T-RD4## (1
butanol) and T-RD5## (sodium hydroxide) to the reaction
vessel. Confirm consumed quantities. Mix for 10 minutes.
Pay attention to the safety instructions.
PPPI_NOTE
Long text (ZT-DET100-7):
Caution! Wear protective clothing, gloves, and protective
mask.

Phase 310:
PI

ProcInstCat

PI Characteristic

10

INSTR

PPPI_INSTRUCTION (control instruction)


Long text (ZT-DET100-8):
Transfer the contents from the reaction vessel to the
cooling vessel.

Phase 330:
PI

ProcInstCat

PI Characteristic

10

INSTR

PPPI_INSTRUCTION (control instruction)


Long text (ZT-DET100-9):
Fill the product you just produced into the transport vehicle
and confirm the quantity produced. Check if the cooling
vessel is empty and close the valves.
PPPI_NOTE (note)
Long text (ZT-DET100-10):
Wear protective clothing and gloves!

20

(C) SAP AG

DE_PROD

LO305

19

Simulate your PI sheet.


Save your recipe.
For more information, display the process instructions that are
automatically generated in Customizing for the control recipe
destination.
Goto Process management Control recipe dest.

(C) SAP AG

LO305

20

12.16Solutions
Unit: Master Recipes
Topic: Control View

1-1

Control recipe destinations and process instructions


1-1-1 Control recipe destination
Logistics Production - Process Master Data Master Recipe
Recipe and Material List Display
Operations tab.
Use the input help (F4) in the Destination field.
CRD Description of control recipe destinations
01 PI sheet for group 1
A1 PI sheet for group A1
1-1-2 Process instructions
In the operation overview, choose Proc. inst. for phase 1010.
Use the input help (F4) in the Type field.
ProcInstCat Type
INSTR
READ2
SIGN

Process parameter
Process data request
Process data request

Which process instruction types have been defined in the R/3 System?
Universal process instruction category
Process parameter
Process data request
(C) SAP AG

LO305

21

Process message subscription


Process data calculation formula
Inspection results request
Dynamic function call
Sequence definition

(C) SAP AG

LO305

22

Display the administrative data for a process instruction.


Choose Process instruction details and then the Admin. Data tab.
1-1-3 Process instruction characteristics
Which process instruction characteristics are assigned to the process instruction
INSTR?
Choose Details for process instructions.
PPPI_INSTRUCTION
PPPI_NOTE
The characteristics PPPI_INSTRUCTION and PPPI_NOTE are each assigned a
long text. Display the long texts.
Choose Values.
Display the administrative data for a process instruction characteristic.
Choose Details for process instruction characteristics.
Administrative data tab
1-1-4 Simulating a PI sheet
Display the PI sheet for control recipe destination 01.
Operation tab
Select phases.
Choose Simulate proc. inst.

(C) SAP AG

LO305

23

1-2

Defining a PI sheet in recipe T-DET1##


Operations tab
Select phases listed.
Choose Proc. inst.
Enter or select process instructions.
Choose Assistant or Details for process instructions.
Maintain control instructions or notes.
Choose Copy (only if you are maintaining in the assistant).
The control instructions and notes are defined in the system as
standard texts. You can call up these texts in the long text editor
by choosing:
Integrate Text Standard...
Enter text name ZT-DET100-*
Set Expand immediately indicator.
Simulate your PI sheet.
Select all phases in the operation overview..
Choose Simulate proc. inst.

(C) SAP AG

LO305

24

13
Aspects of Co-Product Manufacturing

Contents:
Material Master Maintenance
BOMs for the Manufacture of Co-Products

SAP AG 1999

(C) SAP AG

LO305

13.2
Aspects of Co-Product Manufacturing: Unit
Objectives

At the conclusion of this unit, you will be able to:


Maintain the material master and BOMs for

the manufacture of co-products


Create an apportionment structure for cost

apportionment to co-products
Create a process order for a co-product

SAP AG 1999

(C) SAP AG

LO305

13.3
Overview Diagram 13
1 Introduction

9 Production Version

PP-PI Overview

10 Operations and Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product
Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

Master Recipes:

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

13.4
Aspects of Co-Product Manufacturing:
Business Scenario

Your company also produces fertilizer.


During the production process of the fertilizer,

you want the co-product sulfuric acid to be


produced.
As the person responsible, you will change the

existing master recipe for fertilizer production


regarding the manufacture of a co-product.
You must also make the corresponding changes

to the material master of the co-products.

SAP AG 1999

(C) SAP AG

LO305

13.5
Typical Material Flow for the Manufacture of CoProducts
Operation 10 "Charging"

Charge
vessel

Ingredients
Waste

Intra material
Catalyst

Co-product A
Catalyst
Operation 20 "Reaction"

Co-product B
Reaction vessel

SAP AG 1999

The graphic uses two examples of operations carried out at the primary resources charge vessel and
reaction vessel to show a typical material flow in process manufacturing.
The graphic shows:
Ingredients entering the production process
The temporary appearance of an intermediate product between two processing units which is
processed further without leaving the process. Such materials are assigned material type INTR
Intra material.
Waste produced during the manufacturing process
The use of a catalyst that enters the process at a certain point of time and leaves it again later
The manufacture of one or more products. If several planned materials are manufactured during one
production run, they are called co-products.

(C) SAP AG

LO305

13.6
Material Master
Material YY-300

Co-product

Cost-apportionment to co-products
Apportionment structure Source struct.
0001
0002

..
.

Y-300 and P-300


Y-300 and Z-300

Equivalence

numbers

Material costs

Production costs

..
.

PI
PI

10

Y-300

1
10

P-300
Y-300

P-300

Production version 1
Production version 2

SAP AG 1999

The Co-product indicator must be set in the material master of a material that is to be manufactured as a
co-product.
When manufacturing co-products, the entire costs incurred for the process order are collected at order
header level and distributed to the individual co-products using equivalence numbers.
In the material master record, you define one or more apportionment structures. An apportionment
structure specifies how the order costs are to be distributed to the co-products manufactured in a specific
production process. You can maintain equivalence numbers for each apportionment structure and assign
the apportionment structure to a production version.
When you create a process order, the system uses this data to automatically generate a settlement rule.
This settlement rule is then used to distribute the total costs incurred to the co-products.
A source structure is used to distribute the equivalences in the apportionment structure according to
cost element groups. How the costs are apportioned to the individual co-products can then differ
according to the various cost element groups involved. You define source structures in Customizing.

(C) SAP AG

LO305

13.7
BOMS for the Manufacture of Co-Products

Leading product
Coproduct

Y-300 "Yellow paint"

300 - 100 Water

C = Co-product
+ = Input material
- = Output material

300 - 120 Diaminobenzol +


...
Coproduct

P-300 Paste

...

SAP AG 1999

In PP-PI, the manufacture of co-products can be represented by assigning a co-product as a leading


product to the BOM header. All other co-products appear as BOM items.
The following prerequisites must be met for the manufacture of co-products:
The Co-product indicator must be set in the material master of the co-products.
The Co-product indicator must also be set for BOM items that have co-products assigned to them.
The manufacture of co-products can also be represented using the material type PROC Process
material. A process material is specifically used to represent the manufacture of co-products. A process
material is not a physically existing material but rather it represents a manufacturing process. As a BOM
header for a process material, all co-products of the manufacturing process are listed as BOM items with
manufacture of co-product indicators.
There is no quantity or value update for a process material. This transaction takes place at co-product
level.
A process order can either be created for a co-product or for a process material.

(C) SAP AG

LO305

13.8
Material Costing: Objectives
Quantity
Structure
Material BOMs

Value
Structure
Prices for materials

Master recipe

Prices for activities

Overheads from costing


sheet
Prices for processes

Costing
Costing

Pricing
Pricing

Costing results

$
$
$
$
$
$

400 000
610 000
612 000
660 000
670 000

$
$
$
$
$

Analysis
Analysis

Cost
elements

Itemization
M Material
M Material
E Activity
E Activity
G Overhead
X Process

Valuating
Valuating
Profitability
Profitability analysis
analysis
Controlling
Controlling

SAP AG 1999

Material costing uses data from Logistics, such as the material BOM and the master recipe, as the
quantity structure to calculate costs for material consumption and the activities.

Material costing valuates this quantity structure with:

Prices for materials in the material master

Prices for activities in Cost Center Accounting

Prices for processes in Activity-Based Costing

Overhead on the direct costs for these materials and activities

Overhead for sales and administration costs

You can analyze the results in different ways

The analysis is used, for example, to estimate costs or for reporting

(C) SAP AG

LO305

13.9
Executing a Material Cost Estimate

Costing variant

Costing date from

04/01/2000

Plant

Costing date to

04/30/2000

Material

Quantity structure date

04/01/2000

Lot size

Valuation date

04/01/2000

Cost
Cost Component
Component
Split
Split

Mat

Act.

Itemization
Itemization

Log
Log

Explanation
Explanation

System messages
Information
Warning
Error

OH Process

SAP AG 1999

When you create a cost estimate with a quantity structure, you enter the costing variant, the material, the
plant, and the costing version. If you do not enter a costing lot size, the default value from the material
master record is used. The system determines and valuates the quantity structure automatically.
The dates are proposed from the costing variant and determine the following:
The valuation of the quantity structure (valuation date)
The validity period of the cost estimate (costing date from/to)
The explosion of the quantity structure (explosion date)

(C) SAP AG

LO305

13.10
Aspects of Co-Product Manufacturing:
Unit Summary

The manufacture of co-products is the production

of several materials in one manufacturing run.


In the material master of the co-products to be

produced, the Co-product indicator must be set.


One co-product is assigned to the BOM header as

the leading product. All other co-products appear


as BOM items.
A process order can be created in the BOM item

for the leading product or for a co-product.

SAP AG 1999

(C) SAP AG

LO305

10

13.11Exercises
Unit: Aspects of Co-Product Manufacturing
Topic: Master Data Maintenance

At the conclusion of these exercises, you will be able to:


Set up a material master for co-product manufacturing
Create an apportionment structure
Extend a BOM to include co-product manufacturing

Your company also produces fertilizer.


During the production process of the fertilizer, you want the co-product
sulfuric acid to be produced.
As the person responsible, you will change the existing master recipe for
fertilizer production to reflect the manufacture of a co-product.
You must also make the corresponding changes to the material master of
the co-products.
Scenario: The recipe T-RC1## describes the production of fertilizer. During the production
process, the co-product T-FF3## (sulfuric acid) is to be produced along with the product.

1-1

Overview of master recipe T-RC1##


Familiarize yourself with the data in master recipe 1 of the recipe group T-RC1##.
1-1-1 Operation overview
Familiarize yourself with the operations, phases, and resources assigned.
1-1-2 Recipe header data
Display the recipe header data.
Which material is assigned to the recipe as a product?
________________________

(C) SAP AG

LO305

11

1-1-3 Material list


Familiarize yourself with the material components that are assigned to the
recipe.
Which materials are assigned?
________________________
________________________
________________________

1-2

Material master: Co- product indicator


Set the Co-product indicator for your materials T-FF1## and T-FF3## in the material
master or make sure it is set.
Select view(s): MRP 2
Plant: 1100
For which material type was the co-product T-FF3## created?
Material type: _____________

1-3

Bill of material
Enter the material T-FF3## in the master recipe T-RC1## as a co-product in the bill of
material of the leading product T-FF1##.
Start recipe maintenance on the date of creation (previous exercise) in the material list.
Choose BOM.
Item

ICt

Component

Quantity Un

0040

T-FF3##

7-

Set the Co-product indicator for the new BOM item T-FF3##.
Choose Item
Adjust the base quantity in the BOM header.
Choose Header.
In the material list, assign the co-product T-FF3## to phase 330.
Save your recipe.
(C) SAP AG

LO305

12

1-4

Material master: apportionment structure


For the fertilizer production process, create an apportionment structure for cost
apportionment of the process order costs to the co-products T-FF1## and T-FF3##. Do
this in the material master record of the leading product.
Select view(s): MRP 2
Plant: 1100
Choose Joint production.
Cost Apportionment to Co-Products: Apportionment Structures screen
Assign the source structure to PI so you can directly distribute the production costs to
different cost elements.
Aufteilungsschema

Schema

0001

PI

T-FF1## and T-FF3##

On the Cost Apportionment to Co- Products: Equivalence Numbers screen, you can
assign the groupings of cost categories already defined in the source structure to the
Assignment field and distribute them to the co-products using the equivalence numbers.
Maintain the following equivalence numbers:
Choose Equivalence numbers.
Assignment

Co-product

EqNo

1 "Material costs"

T-FF1##

10

1 "Material costs"

T-FF3##

2 "Production costs"

T-FF1##

2 "Production costs"

T-FF3##

3 "Miscellaneous"

T-FF1##

3 "Miscellaneous"

T-FF3##

Save your material master record.

(C) SAP AG

LO305

13

1-5

Material master: Assigning an apportionment structure to a production version


In the material master record for the product T-FF1##, assign your apportionment
structure 0001 to the corresponding production version.
Select view(s): MRP 4
Plant: 1100
Choose ProdVersion.
Choose Details.

1-6

Source structure in Customizing


In Customizing, display the source structure PI with which the production costs are
directly distributed to the different cost elements.
Determine the source (cost element group) for each assignment in the PI source
structure and write them down in the following table (enter controlling area 1000 if
prompted):
Assignment

Cost element group

Material costs
Production costs
Misc. costs
From the controlling application menu, display the cost element groups above and list
three cost elements for each cost element group:
Cost element group

(C) SAP AG

Cost element

LO305

14

1-7

Creating process orders for the co-products


1-7-1 Create a process order (order type PI01) for the leading product T-FF1## in
production plant 1100.
Create Process Order: Header General Data screen
Total quantity:

(for example) 1000 l

Basic dates: start

(for example) today + 1


week

On the Operation Overview and the Material List screens, check whether the
data from your master recipe has been copied correctly.
Also check whether the apportionment structure for the manufacture of coproducts was copied correctly.
In the order header, choose Header -> Settlement rule
1-7-2 Create a process order (order type PI01) for the co-product T-FF3##.
Total quantity:

(for example) 70 l

Basic dates: start

(for example) today + 1


week

In the order header, the co-product T-FF3## is replaced by the leading BOM
material T-FF1##.
The quantity to be produced for the leading BOM material is calculated from
the target quantity for the co-product.
1-8

Material costing:
Performing material costing with a quantity structure
You want to replan product costs for the fertilizer T-FF1## and the sulfuric acid TFF3##. To do this, you will perform material costing with a quantity structure.
1-8-1 Write down the costing lot size for the fertilizer T-FF1## in the material master:
____________________________________________________________
1-8-2 Create a material costing estimate with quantity structure for the fertilizer TFF1## in plant 1100. Choose the costing variant PPC1 Standard cost estimate (Mat)
and confirm the dates suggested.
1-8-3 Go to the costing data and write down the status and the costing lot size:

(C) SAP AG

LO305

15

___________________________________________
___________________________________________
1-8-4 Write down the following quantity structure data:
Bill of material:
Alternative:
Task list group:
Group counter:
Process:
Production version:
Apportionment structure:
Use the F1 help to find out more about the Process field.
1-8-5 Which costing sheet was used for valuation?
____________________________________________________________
Display the cost in relation to the costing lot size.
Display the itemization for the cost of goods manufactured?
___________________________________________________________
An item category distinguishes costing items according to their cost source. What is the
source of item category A?
____________________________________________________________
Save your material cost estimate.

(C) SAP AG

LO305

16

1-8-7 Create a material cost estimate with a quantity structure for sulfuric acid T-FF3##
in plant 1100 with the costing variant PPC1 for costing lot size 7 L. Compare the data.
What are the differences?
____________________________________________________________
____________________________________________________________
____________________________________________________________

(C) SAP AG

LO305

17

13.12Solutions
Unit: Aspects of Co-Product Manufacturing
Topic: Master Data Maintenance

1-1

Overview of master recipe T-RC1##


Master Data Production Versions
Plant:

1100

Group:

T-RC1##

Select production version.


Choose Recipe.
1-1-1 Operation overview
1-1-2 Recipe header data
Recipe header tab
Which material is assigned to the recipe as a product?
Choose Material assignments.
T-FF1##, Fertilizer, fluid, form A
1-1-3 Material list
Recipes tab
Choose Materials.
Which materials are assigned?
T-RF1##
(C) SAP AG

LO305

18

T-RF3##
T-RF2##

(C) SAP AG

LO305

19

1-2

Material master: Co- product indicator


Master Data Material Master Material -> Change -> Immediately
Select view(s): MRP 2
Plant: 1100
X Co-product
For which material type was the co-product T-FF3## created?
Choose Information on material.
Material type: Semi-finished product

1-3

Bill of material
Master Data Production Versions
Plant: 1100
Group: T-RC1##
Choose Recipes.
Materials tab
Choose Bill of material.
Item
0040

ICt
L

Component
T-FF3##

Quantity

Un

7-

Set the Co-product indicator for the new BOM item T-FF3##.
Choose Item
x Co-product
Adjust the base quantity in the BOM header to 1000 liters.
Choose Header.
(C) SAP AG

LO305

20

1-4

Material master: Apportionment structure


Master Data Material Master Material -> Change -> Immediately
Select view(s): MRP 2
Plant: 1100
Choose Joint production.
Cost Apportionment to Co-Products: Apportionment Structures screen

1-5

Material master: Assigning an apportionment structure to a production version


Master Data Material Master Material -> Change -> Immediately
Select view(s): MRP 4
Plant: 1100
Choose ProdVersion.
Choose Details.
Apportionment structure 0001

1-6

R/3 Customizing IMG Controlling Product Cost Controlling Product Cost


Planning Selected Functions in Material Costing Costing in Joint Production
Define Source Structure
Select PI source structure.
Double-click the Assignment folder.
Select each assignment and double-click the Source folder.
(Controlling area 1000)

(C) SAP AG

Assignment

Cost element group

Material cost

CO PC MAT

Production cost

CO PC PROD

Misc. costs

CO PC MISC

LO305

21

SAP standard menu Accounting Controlling Cost Element Accounting


Master Data Cost Element Group Display
Cost element group:

Cost element (example):

CO PC MAT

400000 Raw material


404000 Spare parts
405000 Packaging

CO PC PROD

620000 Machine costs


629600 Staging
625000 Setup

CO PC MISC

655300 OH Administration
655400 OH sales
416200 Electricity actual
usage

1-7

Creating process orders for the co-products


1-7-1 Create a process order (order type PI01) for the leading product T-FF1##.
Logistics -> Production - Process -> Process Order / Process Order -> Create
-> With material
Also check whether the apportionment structure for the manufacture of coproducts was copied correctly.
In the order header, choose Header -> Settlement rule

(C) SAP AG

LO305

22

1-8

Material costing:
Performing material costing with a quantity structure
1-8-1 Production -Process Master Data Material Master Material.
Display Display current
Material: T-FF1##
Select view(s): Costing 1
Plant: 1100
Costing lot size:

1000

1-8-2 Production - Process Product Cost Planning Material Costing


Costing with Quantity Structure Create
Material: T-FF1##
Plant: 1100
Costing variant: PPC1
Costing version: 1
Choose Enter.
Confirm the proposed dates by choosing Enter again.
1-8-3 Costing data tab
Status: Calculated without errors
Costing lot size:

1000 liters

1-8-4 Quantity Structure tab


Quantity structure data:
Bill of material:

Unique number for each


BOM

Alternative:

Task list group:

T-RC1##

Group counter:

Process:

T-FF100

Production version:

0001

Apportionment structure: 0001


(C) SAP AG

LO305

23

The Process field shows which process is used to cost a co-product.


1-8-5 Valuation tab
The costing sheet COGS, with which overhead costs are calculated, was used for
valuation.

(C) SAP AG

LO305

24

1-8-6 Costing tab


Choose Itemization
The costing item with item category A has the co-product T-FF3## as its cost source.
Save.
1-8-7 Differences to first material cost estimate:
The costing structure is created from the sulfuric acid view. The fertilizer T-FF1##
appears in the individual cost itemization with item category A.

(C) SAP AG

LO305

25

14
Aspects of Quality Inspection During Production

Contents:
Inspection Lot
Specification of Batches Produced
Material Master
Master Recipe
Material Specification

SAP AG 1999

(C) SAP AG

LO305

14.2
Aspects of Quality Inspection During Production:
Unit Objectives

At the conclusion of this unit, you will be able to:


Modify the material master for in-process quality

inspection
Enter master inspection characterisics for the

quality inspection
Prepare the master recipe for the in-process

quality inspection

SAP AG 1999

(C) SAP AG

LO305

14.3
Overview Diagram 14
1

Introduction

PP-PI Overview

10 Operations and Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

Aspects of Quality Inspection


14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes:

Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

14.4
Aspects of Quality Inspection During Production:
Business Scenario

Headache tablets are produced in the

pharmaceutical subdivision of your company.


A master recipe for the production process is

available.
As the person responsible, you will check the

changes in the material master and master


recipe that are specific to QM.

SAP AG 1999

(C) SAP AG

LO305

14.5
Integration with Quality Management

Inspection specifications
Concentration
pH value
Viscosity

Inspection results recording


20 %
7.3
100 cP

R/3 QM insp. lot: insp. char.

R/3 QM insp. lot: char. values

QM-IDI
Ext. labor. information system
(LIMS): analyt. specification

QM-IDI
LIMS: analytical results
50
40
30
20
10

SAP AG 1999

Between the production plant and the laboratory or the quality assurance system, information on product
quality and analysis values can be exchanged. This happens when the R/3 Quality Management
System is used, with or without linking to external LIMS (laboratory information systems).
You define the specifications of a quality inspection in the inspection characteristics of an inspection
lot in R/3 QM. During inspection results recording, the results of the quality inspection are assigned to
the inspection characteristics of the inspection lot.
There is a direct link between PP-PI and R/3 Quality Management. The quality of materials produced
can be checked in an in-process inspection taking place in parallel to the production process. In this
case, the inspection lot is created for the corresponding process order. The inspection characteristics are
created in the operations and phases of the master recipe the process order is based on and are then
transferred to the inspection lot. Inspection results recording takes place when the process order is
carried out. If the product is to be handled in batches, inspection results can be used for batch
specification by automatically copying them to the class characteristics of the batch produced.
You can also check the product quality before a goods receipt after production. In this case, an inspection
lot is created from an inspection plan maintained in R/3 QM.
R/3 QM can be linked to a LIMS using the QM-IDI interface. In this case, inspection specifications are
transferred from R/3 QM to the LIMS, which in turn sends the inspection results back to R/3 QM.

(C) SAP AG

LO305

14.6
Inspection Lot

Goods
movement
Order
(production)

Inspection
lot

Sales
order

Created
by

Inspection

Delivery

11
10

12

9
8

3
7 6 5

Deadline
monitoring

Manually

SAP AG 1999

The functions of quality inspection of the R/3 System are fully integrated into the entire logistics
process. They affect all business activities (such as product planning, production, procurement, and
sales).
A quality inspection can only be carried out if an inspection lot is created. Inspection lots are fully
integrated in the logistics chain, such as the neighboring R/3 tasks of goods receipt, goods issue, and
process order. They document the entire inspection process, from inspection specifications to inspection
results recording, and to the usage decision. They can be created automatically or manually from
different sources of the corresponding application.
In-process inspection takes place parallel to the production process. The inspection lot is either created
manually or automatically from within the process order when the order is released. The inspection
characteristics are maintained for the operations or phases of the master recipe the process order is based
on. They are then transferred to the inspection lot. The inspection results are recorded for the inspection
characteristics of the inspection lot while the process order is carried out.
In other tasks, such as a goods receipt, the inspection lot is created on the basis of an inspection plan
maintained in R/3 QM. Inspection plans are master data of R/3 QM.

(C) SAP AG

LO305

14.7
In-Process Inspection - Inspection Lot
Inspection lot

Manually
Autom. at
order release

Process order
Master recipe

Material

Inspection operation

Operation / phase

Insp. characteristic

..
.

..
.

Unplanned
insp. charact.

Insp. type:
"In-process
inspection of
production order"

Insp. characteristics

..
.

..
.

..
.
SAP AG 1999

In an in-process quality inspection, the inspection lot is created on the basis of the underlying master
recipe. In the master recipe, you maintain inspection specifications in the form of inspection
characteristics for the corresponding operations or phases.
You can either create the inspection lot manually or the system creates it automatically when you
release the process order. For the system to be able to do so, you must activate the inspection type
Inspection during production in the material master of the material to be produced. The inspection
characteristics for the operations or phases of the master recipe are then transferred to the corresponding
inspection operations of the inspection lot.
Later, you can also add unplanned inspection characteristics from within the process order.

(C) SAP AG

LO305

14.8
Assignment of Production Resource / Tool to
Inspection Characteristics

Master
recipe

Operation / phase

Prod. resource/
tool (PRT)

Insp. characteristics

SAP AG 1999

If tools or equipment are required for in-process quality inspection, you can assign production
resource/tools to the phases and operations of a master recipe. You can then assign these production
resource/tools to the inspection characteristics of the same phase or the same operation.
After the release of the process order, the assignment of the production resource/tool is transferred to the
inspection lot. When inspection results are recorded, the production resource/tools of the phase or
operation concerned is displayed.
Production resource/tools are mobile resources in production or plant maintenance. They are divided into
the following categories:
Materials
Equipment
Documents
Miscellaneous production resource/tools

(C) SAP AG

LO305

14.9
Inspection Points, Partial Lots, and Batches

Operation 10

Operation 20

Inspection char. C1

Operation 30

C3

C4

C2

C5

C1

C1

C1

C2

C2

C2

C3

C3

C4

C4

C5

C5

Insp.
points

Partial lot 2
Partial lot 1

Batch B2

Batch B1

Inspection lot

SAP AG 1999

This graphic shows the general relationship between inspection points, partial lots, and batches.
If you set the Inspection points indicator on the QM Data header detail screen of the master recipe, all
in-process inspection results recordings are carried out with relation to inspection points. Unlike
inspection without inspection points, you can record inspection results for the inspection characteristics
of the same inspection operation several times. The intervals between the inspection points can be timerelated (that is, at certain points in time), quantity-related (that is, after a certain quantity has been
produced), or freely defined.
Inspection results recording is performed for the inspection characteristics of the inspection lot with
exactly one inspection lot being created for each process order. If partial quantities with different
specifications are produced in a process order, you can assign inspection points to a corresponding
partial lot to record inspection results. You can create several partial lots.
Partial lots describe a certain production quantity during production. This quantity is processed in
several operations or phases. For each operation or phase, you can perform an inspection with inspection
points for different inspection characteristics and assign the results to the partial lot. A new partial lot is
created when the first inspection point of this partial lot is processed.
An example where partial lots are used is the manufacture of co-products, that is, the production of
several materials in one process order. Each co-product can be represented by a partial lot.
If the finished product is managed in batches, you can assign partial lots to individual batches.
Selected inspection results can automatically be copied to the class characteristics of the batch for batch
specification.

(C) SAP AG

LO305

14.10
Specification of Batches Produced
Operation 10
C1: "Temperature"

Operation 20

Operation 30

C3: "pH value"

C4: "Viscosity"

C2: "Concentration"
C1

C5: "Color"
C3

C4

C2

C5

QM master insp. characterist.

pH value
Viscosity

Batch B1

Insp. lot / Partial lot 1

C2: Concentration: 20 %
C3: pH value:
6.5
C4: Viscosity: 100 cP

Concentration

Link

Autom. value transfer

Batch characteristics
Concentration: 20 %
pH value:
6.5
Viscosity: 100 cP

SAP AG 1999

In an in-process inspection, inspection characteristics for the operations and phases of the master recipe,
which the process order or inspection lot are based on, contain inspection specifications. You can either
create inspection characteristics in the master recipe or refer to already existing master inspection
characteristics.
Master inspection characteristics are master data maintained in R/3 QM. They facilitate the maintenance
of routine inspections and enable a linking to the class characteristics of batches. Due to this link,
quality inspection results can automatically be copied from the inspection characteristics to the
corresponding class characteristics of the batch produced.
If you choose inspection with inspection points, inspection points are assigned to a corresponding
partial lot to record inspection results. You can assign several partial lots to an inspection lot. A partial
lot describes a discrete production quantity that can be assigned to a batch. Once a usage decision for
this inspection point has been made, the inspection results of an inspection point are transferred to
the class characteristics of the batch linked to the master inspection characteristics.
If you want to carry out an inspection without inspection points, inspection results are recorded for the
entire inspection lot. You can assign the production quantity to a batch. Once a usage decision for the
entire inspection lot has been made, the inspection results are transferred to the class
characteristics of the batch linked to the master inspection characteristics.

(C) SAP AG

LO305

10

14.11
Creating a Material Specification
Quality Management

Classification system

Master insp. charact. X

General characteristic A

Material

Batch class
Master insp. charact. Y

General characteristic B

Classification
data

B
Material Specification

SAP AG 1999

To be able to transfer QM inspection results to the batch specification automatically, you must make the
following settings:
You must define the general characteristics in which the inspection results are to be transferred as a
numeric value.
You should create the master inspection characteristics with reference to corresponding general
characteristics. As a result, the value ranges of the general characteristic are transferred when you
carry out a quality inspection with a material specification.
You create a material specification for the material in QM. You can assign one master inspection
characteristic to each general characteristic. With this connection, you clearly specify which master
inspection characteristic transfers its result to which general characteristic.
If you have created master inspection characteristics with reference to general characteristics of the
material in the system, they are automatically transferred to the material specification.

(C) SAP AG

LO305

11

14.12
In-Process Inspection - Example

QM

Classification System
Class
023_08
(colors)

General characteristics

Master inspec. char.

C001

Viscosity

9-114

Viscosity

C002

Density

9-112

Density

C003

Wavelength

9-111

Wavelength

Insp. lot
Material TP-F3##

Char. values:
175 cP
2.00 g/ccm
600 nm

Batch_01

SAP AG 1999

The material to be produced TP-F3## belongs to class 023_08. The general characteristics C001, C002,
C003 of the classification system are assigned to this class. Material specification allows the general
characteristics to be assigned to the QM master inspection characteristics 9-111, 9-112, and 9-114.
Parallel to the production process, the inspection requests are created as inspection characteristics in the
operations or phases of the master recipe the inspection lot is based on, and transferred to the inspection
lot. The inspection results are recorded for the inspection characteristics of the inspection lot while the
process order is carried out. Since the finished product is to be handled in batches, the partial lot that has
been produced can be assigned to a batch "batch_01". The inspection results are transferred to the
classification characteristics of the batch produced during batch specification.

(C) SAP AG

LO305

12

14.13
Aspects of Quality Inspection During Production:
Unit Summary

The quality of materials that have been produced

can be checked in-process.


The prerequisite for a quality inspection is the

creation of an inspection lot whose inspection


characteristics are maintained.
The partial lots produced can be assigned to

individual batches. In this case, inspection results


can be transferred to the classification
characteristics of the batch produced.

SAP AG 1999

(C) SAP AG

LO305

13

14.14In-Process Quality Inspection: Exercises


Unit: Aspects of Quality Inspection During Production
Topic: Master Data Maintenance

At the conclusion of these exercises, you will be able to:


Set up the material master for the quality inspection
Describe master inspection characteristics
Create a material specification
Prepare a master recipe for an in-process quality inspection
Make an inspection results recording for a phase in the PI sheet
Headache tablets are produced in the pharmaceutical subdivision of your
company.
A master recipe for the production process is available.
As the person responsible, you will check the changes in the material
master and master recipe that are specific to QM.

1-1

Material master: inspection type In-process inspection of production order


You must activate the inspection type In-process inspection of production order in the
material master of your finished product. This will allow an in-process quality
inspection to be carried out for process orders in the production of your material THT2## (Tablet Cetepharm-N). First check the settings for the material T-HT2##.
Select view(s): Quality Management
Plant: 1100
Choose Insp. setup
Insp. type: ___________________________________
Active indicator set: yes/no

1-2
(C) SAP AG

Master inspection characteristics


LO305

14

For tablet production, sieve size, water contents, and active ingredients contents are to
be inspected during the production process. In QM master data maintenance, the
corresponding master inspection characteristics have been defined.
Display the following master inspection characteristics for plant 1100. What are the
descriptions for each characteristic?
Master inspec. char

Description

N-100
N-200
N-300
Logistics -> Quality management -> Quality planning -> Basic data -> Inspection
characteristic -> Display
The batch we will produce is to be specified according to the inspection results for the
active ingredient potency. Which class characteristic is referred to by the master
inspection characteristic N-300?
Master inspec. char

Description

Class char.

N-300

(C) SAP AG

LO305

15

1-3

Material specification
A material specification for your finished product must be created to allow the inprocess inspection results of a batch to be transferred from the master inspection
characteristic N-300 to the class characteristic N-006.
The link between master inspection characteristics and the class characteristics for a
certain material is created during material specification.
Check the material specification defined for your product T-HT2##.
Material master menu -> Environment -> QM maint. functions -> Display matl spec.

1-4

Master recipe
A recipe has been maintained in the system for the production of the product T-HT2##
(tablet Cetepharm-N).
Display recipe 2 of the recipe group T-TAB##.
1-4-1 Control key
In which phase is a control key selected that does not correspond with PI01 in
the operation overview?
Phase number: ___________________
Control key: ___________________
Which indicator has been set for PI02 that has not been set for PI01?
____________________________________________
Choose F4 for control key PI02 . Choose Detail info for control key PI02.

(C) SAP AG

LO305

16

1-4-2 Inspection characteristics that have been defined


Which inspection characteristics are to be checked in phase 0021?
Master inspec. char

Description

Choose Quant. data.


1-4-3 Process instruction QMJUMPPH
For phase 0021 "Mix" of the master recipe 2 of the group T-TAB##, only the
process instruction "INSTR" (instructions with notes) is defined for the time
being. Further process instructions will be automatically generated when
creating a process order.
Data has been defined in Customizing for each control recipe destination ## +
70 (70 plus your group number).
On the Operations tab, choose Goto Process management Control
recipe dest. to display the process instructions you want to generate.
At which position is a process instruction of the category QMJUMPPH
generated in the control recipe? (This process instruction allows you to branch
to the QM inspection results recording in a PI sheet.)

Position:
Description:
Which filter is set for the process instruction QMJUMPPH on the operation and
phase level? Check this in Customizing for the control recipe destination.
______________________________________________

(C) SAP AG

LO305

17

1-5

Inspection results recording for phase 021


In the following exercise, you will perform an in-process quality inspection from the PI
sheet (based on the master data displayed in the previous exercises 1-1 to 1-4).
1-5-1 Creating a process order for material T-HT2##
Create a process order of the process order type PI01 for the material T-HT2##
in plant 1100.
Create Process Order: Header General Data screen
Total quantity:

500 pieces

Basic dates: start:

today + 1 week

Choose Enter and pay attention to the messages in the status bar. The master
recipe T-TAB## (tablet production) is copied with the material list and the
process order is scheduled.
In the operation overview and in the material list, check whether the data in
master recipe T-TAB## has been copied correctly.
1-5-2 Releasing the process order and generating the control recipe
Release your order.
Choose Release.
Generate a control recipe for control recipe destination (## +70).
Choose Generating a control recipe.
Save your order and write down the process order number.
Process order number: _________________________
1-5-3 Sending the control recipe and maintaining the PI sheet
In the control recipe monitor, select the control recipe that corresponds to your
process order and send it.
Process Management menu -> Control recipe -> Control recipe monitor
(C) SAP AG

LO305

18

Find and edit the PI sheet.


Process Management -> PI sheet -> Find
Confirm the start and finish of phase maintenance with your signature. Sign
with your user name and confirm with your password.
1-5-4 Recording inspection results
Double-click the yellow Record inspection results field in phase 0021.
Enter a number to identify your inspection point and confirm by choosing
Enter.
On the Record Results for Inspection Point: Characteristic Overview screen,
enter results for the three inspection characteristics (sieve size, water content,
potency of active ingredient) within the tolerance range (Result column).
After you enter the last inspection results, choose Enter to trigger automatic
valuation. The recording is complete and can be saved.
Valuation and Partial Lot Allocation screen
Assign a partial lot to the inspection point.
Choose Create partial lot.
Assign a batch to the partial lot. Enter CHARGE01 as a description for the
batch master record.
Choose Create batch.
The system takes you from the inspection results record to the PI sheet results.
Confirm the end of phase 0021 in the PI sheet with your signature and save the
PI sheet.
1-5-5 Display batch with inspection results
Display the batch master record CHARGE01 for material T-

HT2##.

Material master menu: Batch Display


Goto the classification data of the batch.
Classification tab
Check whether the value entered in the inspection results recording for
the active ingredient content was transferred to the batch master record.

(C) SAP AG

LO305

19

14.15 Solutions
Unit: In-Process Quality Inspection
Topic: Master Data Maintenance

1-1

Material Master: Inspection type In-process inspection of production order


Material Master / Material -> Display -> Display current
Select view(s): Quality Management
Plant: 1100
Choose Inspection setting.
Insp. type: 03 = In-process insp. for production order
Active indicator set: yes

1-2

Master inspection characteristics


Display the following master inspection characteristics for plant 1100. What are the
descriptions for each characteristic?
Master inspec. char

Description

N-100

Sieve size

N-200

Water content

N-300

Potency of active ingredient

Logistics -> Quality management -> Quality planning -> Basic data Inspection
characteristic -> Display

(C) SAP AG

Master inspec. char

Description

Class char.

N-300

Potency of

N-006

LO305

20

active
ingredient

(C) SAP AG

LO305

21

1-3

Material specification
Check the material specification defined for your product T-HT2##.
Material master menu/ Environment -> QM maint. functions -> Display matl spec.

1-4

Master recipe
A recipe has been maintained in the system for the production of the product T-HT2##
(tablet Cetepharm-N).
Display recipe 2 of the recipe group T-TAB##.
Production versions. Choose Recipe (for production version 0002).
1-4-1 Control key
In which phase is a control key selected that does not correspond with PI01 in
the operation overview?
Phase number: 0021
Control key: PI02
Which indicator has been set for PI02 that has not been set for PI01?
Insp. char. required
Choose F4 for control key PI02. Choose Detail info for control key PI02.
1-4-2 Inspection characteristics that have been defined
Which inspection characteristics are to be checked in phase 0021?
Choose Insp. char for phase 0021.

(C) SAP AG

LO305

22

Master inspec. char

Description

N-100

Sieve size

N-200

Water content

N-300

Potency of active ingredient

1-4-3 Process instruction QMJUMPPH


Operations tab
Select phase 0021.
Goto Process Management Control recipe dest.
At which position is a process instruction of the category QMJUMPPH
generated in the control recipe?
Position:
Description:

06
At the finish of a
phase

Which filter is set for the process instruction QMJUMPPH at the operation and
phase level?
(Suggestion: Open a new session)
Customizing: Process Management Control Recipe / PI Sheet

Define and Set Control Recipe Destination


Control recipe destination "## +70"
Process instructions to be generated
Choose Execute object for the process instruction category QMJUMPPH.
Selection criteria at operation/phase level:
The control key for the phase for which QMJUMPPH is to be generated must
have the "Insp. characteristics expected" indicator set.

1-5

Inspection results recording for phase 021


1-5-1 Creating a process order for material T-HT2##

(C) SAP AG

LO305

23

Logistics -> Production - Process -> Process Order Process Order ->
Create -> With material
Create Process Order: Header General Data screen
Total quantity:

500 pieces

Basic dates: start

today + 1 week

In the operation overview and in the material list, check whether the data in
master recipe T-TAB## has been copied correctly.
Choose Operations.
Choose Materials.
1-5-2 Releasing the process order and generating the control recipe
Release your order.
Choose Release.
Generate a control recipe for control recipe destination "## + 70".
Choose Generating a control recipe.
1-5-3 Sending the control recipe and maintaining the PI sheet
In the control recipe monitor, select the control recipe that corresponds to your
process order and send it.
Process Management menu Control recipe -> Control recipe monitor
Find and edit the PI sheet.
Process Management PI Sheet Find
1-5-4 Record inspection results.
(C) SAP AG

LO305

24

1-5-5 Display batch with inspection results

(C) SAP AG

LO305

25

15
Engineering Change Management, Recipe Approval

Contents:
Change master record
Engineering change request
Changing master recipes
Recipe approval
Digital signature

SAP AG 1999

(C) SAP AG

LO305

15.2
Engineering Change Management, Recipe
Approval: Unit Objectives

At the conclusion of this unit, you will be able to:


Create change master records
Create engineering change requests /

engineering change orders


Define the validity period of recipe objects
Carry out an approval procedure for a master

recipe
Define digital signatures

SAP AG 1999

(C) SAP AG

LO305

15.3
Overview Diagram 15
1 Introduction

9 Production Version

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15

Resources: Functions

16 Summary and Conclusion

Master Recipes: Operations and

Aspects of Quality Inspection

Engineering Change Management,


Recipe Approval

SAP AG 1999

(C) SAP AG

LO305

15.4
Engineering Change Management, Recipe
Approval: Business Scenario

Headache tablets are produced in the

pharmaceutical subdivision of your company.


A master recipe for the production process is

available.
To ensure regulatory compliance, you must

follow an existing status profile for recipe


approval to change the master recipe.
As the person responsible, specify the

changeability of your master record accordingly.

SAP AG 1999

(C) SAP AG

LO305

15.5
Objects Linked to Engineering Change Management

Material masters
Task lists
- Master recipe
- Routing
- Reference oper. set
- Inspection plan
- Equipment task list
- Gen. maint. task list

BOMs
Eng. change
mgmt

Classes
Characteristics
Classification

- Material BOM
- Document structure
- Equipment BOM
- Functional location BOM
- Order BOM

Documents

Configuration profile
Object dependencies

SAP AG 1999

Engineering change management is a central, integrated part of product data management (PDM) within
the standard system.

(C) SAP AG

LO305

15.6
Why Use Engineering Change Management for
Changes?
Monitoring and documentation of changes
Planning and realization at a specified time
Saving several change statuses of an object
Integration with the logistics process chain
Grouping of related changes
For different objects
At the same or different times
With cross-application and special
documentation

SAP AG 1999

Engineering change management is a central logistics function that can be used to change various types
of master data and document the changes.
A valid-from date for the change master record (or the engineering change request/engineering change
order) is used to make changes valid on a predefined date. This aids long-term planning.
You can use engineering change management to store R/3 objects (for example, BOMs or routings) more
than once. This means that the objects can be stored in all relevant change statuses.
The changes take effect automatically at the predefined time in all areas of the logistics process chain
(for example, sales order, material requirements planning, and shop floor and production control).
You can use engineering change managment to group changes to different R/3 objects that are affected
by one change. You can change all the objects at the same time, or you can define different change dates
for individual objects. You can create general documentation for all changes made as well as special
documentation for each specific object change.
You can use engineering change management to fulfill your legal obligations to document changes.

(C) SAP AG

LO305

15.7
Engineering Change Management: With and
Without History
ECM
Without history
(without change docu.)

Without history
(with change docu.)

Old

Old

New

New

Change
documents

With history
(with change docu.)

Old

New

Change
documents

SAP AG 1999

You can perform object changes (for example, BOM and routing changes) in the system either with or
without history. The system generates change documents even for changes without history.
Changes without history
These are changes that do not have to be documented because they take place during the development
stage of the product, for example.
The status of the object before the change is not saved. You can only find out about the status of the
object before the change by using change documents.
Changes with history
These are changes that must be documented because they take place during production, for example.
Both the status before and after the change is saved. The system also generates change documents. These
change documents differ for some objects from those generated for changes without history.
Engineering change management in the SAP System allows for complete documentation of changes.
Some of these changes may be needed for product liability purposes, for example.

(C) SAP AG

LO305

15.8
Change Master Record (Change Number)

Change
master record
- Change number

Functions
Advance

planning / validity period of changes

Def.

of object types (such as recipes, BOMs, etc.)


that can be changed

Def.

of objects (such as recipe "REC-101") that can be


changed

Def.

of authorizations required for change master record


maintenance

Complete

documentation of changes

SAP AG 1999

Change master records (synonymous with change numbers) are used to plan changes in advance and
combine related changes to different objects, such as master recipes, materials, and bills of material.
They are created within engineering change management and can contain such information as:
The date from which the changes are to be valid
The types of objects and, if required, object management records for the individual objects to be
changed
A special authorization that you need to work with the change master record
You can create, change, or display a master recipe with reference to a change master record. The validfrom date in the master record is then used as the key date. This implies:
When you create a recipe, the new recipe is valid from this date.
When you display or change a recipe, the system selects the change status valid on this date.
Unlike recipe maintenance without a change number, the system creates a new change status for all
changed objects. This change status is valid from the valid-from date of the change number.

(C) SAP AG

LO305

15.9
Structure of a Change Master Record

Change header

Change number
Valid-from date
Authorization group
Reason for change

Object types

Master recipes
Material BOMs
Documents

Object mgmt records

For example, master recipe "Colors"

SAP AG 1999

In the change header, a short description of the change, the valid-from date, and the status is maintained.
You determine which objects can be changed with the change master record by selecting the object
types.
One of the functions of the object management record is to enable you to document changes to a specific
object.

(C) SAP AG

LO305

15.10
Change Documentation

Change with history


1993

When was the change carried out?

Recipe "COLORS"
PI
10

ProcInstCat
XY

Recipe "COLORS"
PI
10

ProcInstCat
XX

From
to
05/01/93
12/01/93

State after the change?

From
to
05/01/93
12/01/93

Change on 12/01/93
State before the change?

Why was the change carried out?

SAP AG 1999

A change becomes effective on a precisely defined date.


The changed object is stored twice: in its state before and after the change. The state of the object
before the change ends with the valid-to date. The state after the change begins with the valid-from date.
Changes are documented in a change master record.

(C) SAP AG

LO305

10

15.11
Engineering Change Mgmt - Validity Period of
Recipe Objects
Key date
Key date
Validity
period
Time
Validity
Validity of
of
recipe
recipe header
header
Validity of
operation 1

Validity of
operation 2

SAP AG 1999

Every recipe object (such as, header, operation, material component) has a validity period. You can
determine the start of this validity period using the key date you enter when creating or changing a
recipe or recipe object.
When you create a recipe, the recipe becomes valid from the key date.
When you select a recipe for change or display, the system displays the recipe version valid on the
key date.
If you change a recipe with a change number, the system uses the valid-from date in the change
master record as the key date. The new change status becomes valid from that date.
If you change a master recipe without a change number, the change is valid for the entire validity
period of the change status selected.
The default value for the key date is the current date.

(C) SAP AG

LO305

11

15.12
Engineering Change Request / Order

Change
request
-Change number
- Change type

Functions
Advance planning / validity period of changes
Def.

of object types (f.ex. recipes, BOMs, etc.) that can


be changed

Def.

of objects that can be changed (f.ex. recipe "REC-101)

Def.

of authorizations required for change master record


maintenance

Complete
Approval
System

documentation of changes
procedure for changes

status network / user status profile

Authorizations
Workflow

for user status

link

SAP AG 1999

Engineering change orders have the functionality of change master records. However, they comprise the
following additional functions:
The possibility of triggering a workflow task such as sending a message to the person responsible at
a particular processing stage
A procedure for the approval and release of changes during which an unapproved engineering
change request is converted into an approved engineering change order.
The assignment of a user status profile to extend the system status network
The assignment of authorizations for user statuses
You can create, change, or display a master recipe with reference to an engineering change order. The
valid-from date of the engineering change order is then used as the key date. The engineering change
order must meet the following requirements:
It must have been approved and contain at least one object management record
If a corresponding change rule has been maintained for the recipe, the change type of the object
management record must also be identical to that in the recipe header.
To maintain component assignments, material quantity calculation, and the bill of material from
within the recipe, you also need an object management record with approved changes for the bill of
material.

(C) SAP AG

LO305

12

15.13
Structure of an Engineering Change Request
Change header

Change number
Change type for change header
Valid-from date
Authorization group
Reason for change

Object types
User status profile
Workflow tasks

Master recipes
Material BOMs
Documents

Object mgmt records


For example, master recipe "Colors"
Change type for object
Reason for change

SAP AG 1999

General header data of the change request:


The change request is identified by the change number you enter.
The change type controls the change process for the entire order using a system status profile. You
can assign a user status profile and workflow tasks for different processing steps to the change type.
The valid-from date specifies the date on which the changes come into effect.
By entering an authorization group, you can define that a special authorization is required to
maintain the engineering change request.
Entering a reason for the change enables you to document planned changes fully.
Allowed object types:
You must define the object types that may be changed with the engineering change request. These
include, for instance, master recipes, material BOMs, and material master records.
Creating object management records for objects you want to change:
You must create an object management change record for every object you want to change using
the engineering change request. An example for a change object would be a certain master recipe.
You maintain a change type for each object management record. The change type controls the
change process for the specific object.
Entering a reason for the change for an object management record enables you to document planned
changes of a particular object fully.

(C) SAP AG

LO305

13

15.14
Comparison of Change Master Records and
Engineering Change Requests / Orders

Change
master record
- Change number

Eng. change
order/request
- Change number
- Change type

Change type

System status

User status

Object mgmt records

Generating obj. mgmt records

Entering valid-from date

Immediately

Bef. conversion

Changing objects

Immediately

Aft. conversion

SAP AG 1999

In contrast to the engineering change requests/orders, you may not enter any change types for change
master records. There is no system status network for change master records.
Since object management records are not automatically generated for the engineering change
request/order, the icon for this does not appear in the object type overview.
You cannot use the automatic generation function here, because the engineering change request/order is
to control the business processes of requesting, inspecting, and releasing changes for certain assigned
objects. This excludes an implied assignment during object change itself (by using the change number).
Note: The example in the graphic corresponds to the default setting for the engineering change
request/order.

(C) SAP AG

LO305

14

15.15
Changing Master Recipes

Change rule
None

With change number

With engineering change order (without change type)

With engineering change order (with change type)

SAP AG 1999

In process industries, requirements for documentation and checking of master recipes vary widely
depending on the branch of industry and the product. They range from fairly unrestricted maintenance of
recipes to detailed planning, documentation and even strict approval procedures.
To meet these requirements, the R/3 System offers various types of recipe maintenance. You can enter a
change rule in the recipe to specify the maintenance procedure that is to be used for a recipe (General
View screen).
You can create or change master recipes as follows:
Without a change number:
All you need is an authorization for the corresponding recipe transactions. Changes are valid for the
entire validity period of the selected change status.
With a change number:
By using a change master record, you can combine planning and execution when creating and
changing related objects such as recipes, materials, and bills of material. The validity date is
specified using a change master record (synonymous with change number). A new version is
created for all changed recipe objects (for example, operation, relationship).
With an engineering change order:
With engineering change orders, the functionality of the change master record is enhanced by a
detailed approval procedure. By entering a change type, you can specify that the approval procedure
must be carried out in a specific user-defined way.

(C) SAP AG

LO305

15

As soon as you have assigned a change rule to a recipe and thus defined that it is subject to a specific
change procedure, this recipe is locked for all change procedures that are less restrictive. To revoke the
restriction, you must change the recipe in the way specified in the change procedure.

(C) SAP AG

LO305

16

15.16
System Status Network Object

Object
Change possible

Change
Change not
not possible
possible

Change
Change not
not necessary
necessary

Object
change
Change completed

Errors
Errors in
in change
change

Errors
Errors corrected
corrected

Change released

SAP AG 1999

The procedure for approving and releasing engineering change requests or orders is controlled via links
between statuses and business transactions. The statuses mark particular processing statuses during the
approval procedure. They include both fixed system statuses and user-defined user statuses. You can
proceed from one status to the next by carrying out a business transaction.
The predefined status network for the object management record is valid for all objects to be changed
that are of the object type material, document, BOM, and task list.
You can easily change the status from Change possible to Change not possible or Change not necessary
in any direction, as shown in the graphic.
Only the status Change possible requires further consideration of the object change and the setting of
another status. When at least one object management record contains this status, the request that belongs
to it must be converted to an order.
After you make the setting Change complete, the change can be set to Errors in change. In this case, the
errors must be corrected before the changes can be released.
You can extend the status network to include user status.

(C) SAP AG

LO305

17

15.17
System Status Network for Engineering Change
Requests / Orders
Eng.
Eng. change request
Check
Reject request

Checked

Withdraw
approval

Approve

Request
complete
Convert

Request not
complete

Eng.
Eng. change order
Complete

Release

SAP AG 1999

An extensive, pre-defined status network exists for the engineering change request/order (process
control).
You are only allowed to assign object management records to the order before you set the status
Checked.
When all assigned object management records have the status Change possible or Change not required,
the request can be set to Checked and Approved and can be converted to an order.
After setting the status to Checked or Approved, the request can be rejected.
After settting the status to Approved, the approval can be withdrawn.
If at least one object is to be changed, the request must be converted to an order.
Before converting, you must maintain the valid-from date of the request.
After converting, you can set the request to Not complete. In this case, you must set the request to
Complete again in order for the process to continue.
When the order and the object management record have been released, the object can be changed.
You can lock the request/order at any time and withdraw the lock again.
You can extend the status network to include user statuses.

(C) SAP AG

LO305

18

15.18
Recipe Approval (General Procedure)

Create engineering change request


(...)
Change objects (for example, recipe "COLORS")
Check planned changes
Approve changes
Convert change request into change order
Object changes (f.ex. for recipes "COLORS") possible
Complete and release changes/ engineering change order
Recipe approval (f.ex. for recipe "COLORS") granted

SAP AG 1999

The change procedure using an engineering change request comprises three main steps:
Creating an engineering change request
Checking an engineering change request and converting it into an engineering change order
Changing objects and completing the change
For a master recipe marked with change type With engineering change order, this process represents an
approval procedure. Once the procedure has been released, the maintained recipe is marked as Approved
recipe for the change period defined by the valid-from date of the change request.
Recipes that have already been approved but are changed using another change order are considered
unapproved during the period between the conversion and release for the change period defined by the
valid-from date. Approval is granted when the change order is released.

(C) SAP AG

LO305

19

15.19
Recipe Approval (Statuses I)

Status of change header

Status of change objects

Check request

Check object
(f.ex. recipe "COLORS")
(User status)

Req. checked

Check by chemist
Check by qual. assurance
Changes possible

Check by plant mgmt


Approve request
Convert request

Objects can be changed


(f.ex. recipe "COLORS")

SAP AG 1999

The procedure for approving and releasing engineering change requests or orders is controlled via links
between statuses and business transactions. The statuses mark particular processing statuses during the
approval procedure. They include:
A fixed network of system statuses
Company-specific user statuses
You can proceed from one status to the next by carrying out a business transaction.
SAP has defined a standard approval procedure, which has been implemented via a network of system
statuses:
1. An engineering change request is created that describes planned changes to various objects,
including master recipes.
2. The planned changes to the individual objects are checked and marked as possible or
unnecessary.
3. After the check has been concluded, the engineering change request is approved and converted
into an engineering change order. Now you can make the changes, that is, the master recipe can
be maintained with reference to the engineering change order.

(C) SAP AG

LO305

20

15.20
Recipe Approval (Statuses II)

Status of change header

Status of change objects

Convert request

Objects can be changed


(f.ex. recipe "COLORS")

Complete order

Complete changes

Check by plant mgmt

Check by chemist
Check by qual. assurance

Release order

Release changes
Master recipe is approved

SAP AG 1999

4. After the changes to all objects have been made, the entire engineering change order is
completed.
5. The engineering change order is released.
The recipe has now been approved and can be used to create orders requiring an approved recipe.
If the approval procedure defined by SAP does not meet all your requirements, you can add companyspecific checks at the change order header or change object level. To do so, assign a change type with a
corresponding user status profile to the engineering change request or the change object.
Status profiles are defined and assigned to change types within Customizing for engineering change
management. They contain company-specific user statuses. In the status profile, you link these user
statuses to the business transactions you carry out, thus inserting them in the existing network of system
statuses.
You can specify that a special authorization is required to set or delete a user status.

(C) SAP AG

LO305

21

15.21
Digital Signature (I)

Particular business transactions:


Digital signature required

Special approval procedure required

Unique and forgeryforgery-proof


user identification
Documentation:
name of user, signed transaction, date, time

SAP AG 1999

You can specify that a user must execute a digital signature to be able to carry out particular business
transactions.
The digital signature enables you to meet the security requirements laid down in the Good
Manufacturing Practices (GMP) with regard to the execution of these transactions. The digital signature
ensures that:
A transaction can only be carried out by users with a special authorization
The user identification is unique and forgery-proof
The name of the user is documented together with the signed transaction and the date and time, and
cannot be falsified afterwards.

(C) SAP AG

LO305

22

15.22
Digital Signature (II)

PPPP-PI:

Engineering Change Mgmt

PI sheet
Batch record

Eng. change request / order

Digital signature

QM:
Inspection results recording
Usage decision

SAP AG 1999

The digital signature can be implemented for the following areas:


Quality management
Saving inspection results for an inspection lot
Recording and changing the usage decision for an inspection lot
Engineering change management
Changing the status of an engineering change order/request
Releasing an engineering change order
PP-PI
Completing a phase in the PI sheet
Accepting invalid values within input validations in the PI sheet
Approving a batch record

(C) SAP AG

LO305

23

15.23
Activating the Digital Signature
PPPP-PI:
PI
PI sheet:
sheet:
Customizing
Customizing for
for control
control recipe
recipe destination
destination

DS
DS (digital
(digital signature)
signature)
Batch
Batch record
record approval:
approval:

Digital
Digital signature
signature always
always required
required

Engineering Change Management:


Customizing:
Customizing: Change
Change types
types

QM:
Material
Material authorization
authorization groups
groups

Digital
Digital signature
signature for
for results
results recording
recording

Digital
signature
for
usage
decision
Digital signature for usage decision

SAP AG 1999

To specify that a digital signature is required for the above mentioned transactions, you must have
activated the function in the relevant application. This can be done in the following ways:
In PP-PI:
For completing a phase as well as for accepting invalid input values in the PI sheet, set the DS
(digital signature) indicator in Customizing for Control Recipe Destinations.
When approving a batch record, the user must always execute a digital signature.
In engineering change management:
To save status changes of the engineering change request before order processing, set the Dig. sig.
indicator in Customizing for change types for object master records.
For change order release, set the Dig. sig. indicator in Customizing for change types for object
master records.
In QM:
For inspection results recording, set the Digital signature for results recording indicator in the
material authorization groups.
For the usage decision, set the Digital signature for usage decision indicator in the material
authorization groups.

(C) SAP AG

LO305

24

15.24
Engineering Change Management, Recipe
Approval: Unit Summary

You can use change master records to plan the

validity period of changes.


Change orders also facilitate special approval

procedures for changes.


The approval and release of engineering change

orders takes place via the status profile.


You can use the digital signature to ensure that

particular transactions are only carried out by


authorized persons.

SAP AG 1999

(C) SAP AG

LO305

25

15.25 Exercises
Unit: Engineering Change Management
Topic: Change Numbers and Recipe Approval

At the conclusion of these exercises, you will be able to:


Create change numbers/master records
Go through the recipe approval process
Create engineering change requests / engineering change orders
Headache tablets are produced in the pharmaceutical subdivision of your
company.
A suitable production version with a master recipe and BOM for process
manufacturing already exist.
To ensure regulatory compliance, you must follow an existing status
profile for recipe approval to change the master recipe.
As the person responsible, specify the changeability of your master
record accordingly.
1-1

Creating change master records (change numbers)


Create two change master records to change a master recipe.
Create Change Master: Initial Screen
Change number: AEND_01_##
(or)AEND_02_##
Type:

Change master

Function:

Without release key

Create Change Master Record: Change Header screen


Description:

Change number of group ##

Valid from:

Today + 1 week for AEND_01_##


Today + 2 weeks for AEND_02_##

(C) SAP AG

LO305

26

Change no. status:

01 active

After you release the data, the Create Change Master: Object Types screen appears.
Specify that your master recipes and BOMs are changeable objects.
Edit -> More -> Object sub-types
Object type specification:

Task list and BOM

Set the following indicators for the object types "Master recipe" and "Material BOM":

Actv.

Object

MgtRec

Note: By setting these indicators, you define that


i) Master recipes and material BOMS (and production versions) can be changed with
this change number
ii) Object management records are automatically created for the changed objects
Save your change master records.
1-2

Changing master recipe objects with a change number


1-2-1 Change the master recipe T-DET1## with the change number AEND_01_##.
Production Process Master Data Production Versions
Task list group: T-DET1##
Choose Assign change number.
Change number: AEND 01
Choose Recipe.
Change the charge quantity range of your recipe to 1,000 -40,000 L.
Display the administrative data for the recipe header.
Save your recipe and your production version.
1-2-2 Change your master recipe T-DET1## with the change number AEND_02_##.
Enter the original charge quantity range (1,000 -20,000 L).
Display the administrative data.

(C) SAP AG

LO305

27

Save your recipe and your production version again.


1-2-2-1

1-3

Display the header data of the recipe T-DET1## and the


administrative data for the following key dates:

Today

Today +10 days

Today + 20 days

Documentation of changes
1-3-1 Documentation in the change master record
Display the change master record AEND_01_##.
Which master recipe was changed with the change number, that is, for which
master recipe was an object management record generated?
_____________________
Change number Display
Choose All objects.
Note: You find details on an object management record by double-clicking each
object. Detailed descriptions of changes can be defined for an object
management record.
1-3-2 Recipe changes
Which changes were made to the recipe header of recipe T-DET1##?
Master recipe menu / Reporting Recipe -> Recipe changes

(C) SAP AG

LO305

28

Task list type:

Plant:

1100

Recipe group:

T-DET1##

Recipe:

Change documentation for the following object: recipe header


Program -> Execute
______________________________________
______________________________________
______________________________________
1-4

Recipe approval
1-4-1 Change rule
1-4-1-1

Select the production versions for recipe T-TAB##. Open the master
recipe for production version 0001 of material T-HT2## on the key
date "Today".
Which processing mode (display or change?) appears?
__________________________________
Find out the meaning and function of the Change rule and
Change type fields using the F1 help in the recipe header.
Which change rule or change type is set?
Change rule:
Change type:
Save the recipe.

(C) SAP AG

LO305

29

1-4-1-2

Try to access the recipe in the change mode.


Master Data Master Recipes Recipe and Material List
Change
Why can you only display the recipe data and not make any
changes?
_____________________________________________
_____________________________________________
Notice the message in the status bar. Get more information on error
diagnosis and how to proceed further by double-clicking this
message.

1-4-2 Creating an engineering change request


1-4-2-1

In engineering change management, create change request


REQUEST## of the change type 100, "change of recipes".
Make the following entries on the Create Engineering Change
Request: Change Header screen:
Description:

Recipe change T-TAB##

Valid from:

Today + 1 week

Change no. status:

01 active

Reason for change:

Display SOP in ProdInst for TTAB##

Allow the changeability of the object types Master recipe and


"Material BOM".
Edit More Object sub-types/ Task list and BOM indicators
Set the Actv. indicator and Object indicator for the object types
Master recipe and Material BOM. Delete all indicators set for other
object types.
Define the recipe T-TAB## and the BOM for material T-HT2## as
changeable objects.
Choose Objects.
(C) SAP AG

LO305

30

TL type TL group
2

T-TAB##

Description
Add new
proc. inst. for SOP call

Change type
100

Materials tab
Material

Plant

BOM usg. Description

Change type

T-HT2##

1100

see above

No change

Define the following long text for the object management record
referring to the the planned changes to the recipe:
Task list tab
Choose Details for T-TAB##
Choose Object long text
Due to a new safety rating of material T-RD1##, you must be able to
call up the Standard Operating Procedure (SOP) from the archive
system in the PI sheet for phase 110. An appropriate process
instruction must be added for phase 110. The change must be valid
from the date today + 1 week.

1-4-2-2

Which statuses are set for your change objects?


In each object management record for the recipe or BOM,
choose Status mgmt.
System status:
____________________________________
User status:
____________________________________
Which statuses are set for the change request?
Choose Change header and then Status mgmt.

(C) SAP AG

LO305

31

System status:
____________________________________
User status:
____________________________________
Save your change request.
1-4-3 Try to change your recipe T-TAB## (group counter 2, production version 2)
with reference to this request.
Which error message do you receive?
______________________________________________________
Display the message log. What is the message text for the error message?
______________________________________________________
Find out more about the reasons for the error and how to fix it by doubleclicking the error message.
______________________________________________________
______________________________________________________
1-5

Checking, approving and converting the engineering change request


1-5-1 Set the status Check request for the engineering change request.
Engineering Change Request Change / Choose Set status / Choose Check
request.
1-5-2 What additional system status is set for the engineering change request?
____________________________________
1-5-3 What additional system status is set for the engineering change objects?
____________________________________
Choose Objects.
Select objects.
Choose Detail and then Status mgmt.
Choose Previous / Next object.

(C) SAP AG

LO305

32

1-5-4 Can you set the object system status Change possible for your recipe or BOM at
the moment?
____________________________________
In the object management record of the recipe or BOM, choose Set status.

1-5-5 Before you can set the status, the user status that is set must be withdrawn by
the authorized persons.
Withdraw each user status.
Choose Status mgmt.
1.5.6

Set the object status to Change possible.

1.5.7

Which status is additionally set for the change header?


_____________________________________

1.5.8

Set the system status to ECR checked.

1.5.9

The request must now be approved and converted to an engineering change


order before the engineering change object can be edited. Before you can set the
status, the user status that is already set must be withdrawn by an authorized
person.
Withdraw the user status and set the system status Approve request and
Convert request.
Save your engineering change order.

1-6

Changing with an engineering change order


Change your master recipe T-TAB## (group counter 2, production version 0002) with
reference to your engineering change order ORDER##.
Add the process instructions DOC_SHOW of type 6 Dynamic function call for phase
11.
Save your recipe and the production version.

1-7

Closing and releasing object changes and engineering change orders


Call up your engineering change order in the change mode.

(C) SAP AG

LO305

33

Which statuses does the engineering change order have?


_____________________________________
_____________________________________
_____________________________________
_____________________________________
Which statuses do the characteristics have?
_____________________________________
_____________________________________
_____________________________________
_____________________________________
1-7-1 Set the status Complete change for the engineering change objects.
In the meantime, save your engineering change order and try to change your
recipe T-TAB## with reference to the engineering change order.
Find out more about the system messages created while doing this.
1-7-2 Continue to process your engineering change order.
Which system statuses do the engineering change objects have now?
_____________________________________
_____________________________________
_____________________________________
Which user status was set when you closed?
_____________________________________
_____________________________________
_____________________________________
The engineering change object can only be released after being inspected by the
responsible areas defined by the object user status. These authorized users
withdraw their user status after inspection, and the object can then be released.
Withdraw the user status for the engineering change object and set the object
system status Release change.
1-7-3 Set the system status Close for the engineering change order.
Which system statuses does the engineering change order have now?
(C) SAP AG

LO305

34

_____________________________________
_____________________________________
_____________________________________
Which user status was set when you closed?
_____________________________________
The engineering change order and corresponding approval can only be released
after being inspected by the responsible area defined by the order user status.
An authorized person withdraws the user status after inspection and releases the
order.
Withdraw the user status for the order and set the order system status to Release
change.
Save your engineering change order.

1-8

Status report on engineering change order


Generate a detailed status report on your engineering change order.

(C) SAP AG

LO305

35

15.26Solutions
Unit: Engineering Change Management
Topic: Change Numbers and Recipe Approval

1-1

Creating change master records (change numbers)


Create two change master records to change a master recipe.
Production - Process -> Master Data -> Engineering Change Management
Change Number -> Create
Specify that your master recipe is a changeable object.
Edit -> More -> Object sub-types
Object type specification:

1-2

Task list.and BOM

Changing master recipe objects with change numbers


1-2-1 Change the master recipe T-DET1## with the change number AEND_01_##

Production versions
Select Production version.
Choose Assign change number.
Enter the change number and choose Enter.
Choose Recipes.
Recipe header tab
Enter the new charge quantity range
Administrative data tab
The recipe is now assigned the change number with its validity range.
Save the recipe and production version.
(C) SAP AG

LO305

36

Choose Refresh.
1.2.2

same as in 1-2-1
1.2.2.1

Select production version.


Choose Recipe.
Enter key date.
Choose Display recipes.
Recipe header and Administrative data tab

1-3

Documentation of changes
1-3-1 Documentation in the change master record
Display the change master record AEND_01_##.
Which master recipe was changed with the change number, that is, for which
master recipe was an object management record generated?
T-DET1##
Change number Display
Choose All objects.
1-3-2 Recipe changes
Which changes were made to the recipe header of recipe T-DET1##?
Changes were made to the lot size (Charge quantity range) using the change
number from part 1-1.

1-4

Recipe approval
1-4-1 Change rule
1-4-1-1

Production versions for master recipe T-TAB##


Select production version 0001.
Choose Recipes.
You are in the display mode.

(C) SAP AG

LO305

37

Recipe header tab

1-4-1-2

Change rule:

With engineering change order" (with


change type)

Change type:

200

Try to access the recipe in the change mode.


Why can you only display the recipe data and not make any
changes?
The change rule 3 (= with engineering change order) does not allow
changes to the recipe without the entry of an engineering change
order.

1-4-2 Creating an engineering change request


Production-Process -> Master Data -> Engineering Change Management ->
Change Number -> Create
1-4-2-1

In engineering change management, create change request


REQUEST## of the change type 100.
Enter data and press Enter.
Allow the changeability of the object types Master recipe and
"Material BOM".
Edit More Object sub-types/ Set Task list and BOM
indicators.
Choose Copy.
Set the "Active" and "Object" indicators for the material BOM and
master recipe and choose "Enter".
Define the recipe T-TAB## and the BOM for material T-HT2## as
changeable objects.
Choose Objects.
Task list tab.
Enter data for T-TAB## and press Enter.
Material BOM tab
Enter data for material T-HT2## and press Enter.

(C) SAP AG

LO305

38

Task list tab


Select task list group T-TAB##.

(C) SAP AG

LO305

39

Choose Detail view.


Choose Long text object.
Enter text, save and go back.
1-4-2-2

Which status types are set for your change objects?


In each object management record, choose Status mgmt.
System status:
Created
User status:
CHEM: Check by chemist
QUAL: Check by quality assurance
PROC: Check by process technology
Choose Back.
Which statuses are set for the change request?
Choose Change header and then Status mgmt.
System status:
Created
User status:
Check by plant management
Save engineering change request

1-4-3 Try to change your recipe T-TAB## (group counter 2, production version 0002)
with reference to this request.

Production versions
Select Production version 0002.
Choose Assign change number.

(C) SAP AG

LO305

40

Which error message do you receive?


The change number was not assigned to all entries you have selected.
Incorrect entries are still selected.
Display the message log. What is the message text for the error message?
System status: ECR is not yet approved
Find out more about the reasons for the error and how to fix it by doubleclicking the error message.
The system checks the system status of the engineering change request. The
engineering change request must be approved and converted to an engineering
change order.
1-5

Checking, approving and converting the engineering change request


Check
1-5-1 Set the status Check request for the engineering change request.
Engineering Change Request Change / Choose Set status. / Choose
Check request.
Choose Continue.
1-5-2 What additional system status is set for the engineering change request?
Choose Status mgmt.
Status:

Check ECR

Choose Back.
1-5-3 What additional system status is set for the engineering change objects?
Choose Objects.
Select both objects.
Choose Detail view.
Choose Status mgmt.
To navigate between the individual objects:
Choose Previous / Next object.
Status:

Inspection request for ECR

Choose Back.

(C) SAP AG

LO305

41

1-5-4 Can you set the object system status Change possible for your recipe or
BOM at the moment?
Choose Set status.
No
Choose Continue.
1-5-5 Choose Status mgmt.
Remove all indictors for the user status for both objects
Choose Back.
1-5-6 For both objects:
Choose Set status for status Change possible.
Approval and conversion
1-5-7 Which status is additionally set for the change header?
Choose Change header.
Choose Status mgmt.
Status:

All objects checked

Choose Back.
1-5-8 Set the request system status to ECR checked.
Choose Set status.
Choose Req. checked.
Choose Continue.
1-5-9 Choose Status mgmt.
Remove indicator for user status
Choose Back.
Choose Set status.
Choose Approve request.
Choose Convert request.
Choose Continue.
Save order
1-6

Changing with an engineering change order

Production versions
(C) SAP AG

LO305

42

Select Production version 0002.


Choose Assign change number.
Choose Recipes.
Operations tab
Select phase 11 and choose Process instructions.
Add process instruction DOC_SHOW.
Save recipe and production version.
1-7

Closing and releasing object changes and engineering change orders


Call up your engineering change order in the change mode.
Change Number Change
Which statuses does the engineering change order have?
Choose Status mgmt.
All objects checked
ECR checked
ECR approved
ECOP: ECO to be processed
Choose Back.
Which statuses do the characteristics have?
Choose Objects.
Select both objects.
Choose Detail view.
Choose Status mgmt.
Created
Object: Change possible
Object: To be processed
Object: In preparation
Choose Back.
1-7-1 Set the status Complete change for the engineering change objects.
In the object management record:
Choose Set status.
Choose Complete changes.

(C) SAP AG

LO305

43

Choose Continue.

(C) SAP AG

LO305

44

1-7-2 Continue processing your engineering change order.


Which system status does the engineering change object T-TAB## have now?
In the object management record:
Choose Status mgmt.
Created
Object: Change possible
Object: Change completed
Which user status was set during when you closed?
CHEM: Check by chemist
QUAL: Check by quality assurance
PROC: Check by process technology
For the object in status management:
Remove all indictors for the user status
Choose Back.
Choose Set status.
Choose Release changes.
Choose Continue.
1.7.3

Set the system status Complete order for the engineering change order.
Choose Change header.
Choose Set status.
Choose Close.
Choose Continue.
Which system statuses does the engineering change order have now?
Choose Status mgmt.
All objects checked
ECR checked
ECR approved
ECO confirmed

(C) SAP AG

LO305

45

ECO completed
All objects released
Which user status was set while closing?
Check by plant management
Remove indicator for user status
Choose Back.
Choose Set status.
Choose Release order.
A message appears that the engineering change order has been released.
Choose Continue.
Save order
1.8

Status report on engineering change order


Choose Change Number Change
Choose Enter. If a warning appears, confirm with enter.
Environment Reporting Status Report
or
Choose Status report for the system status.

(C) SAP AG

LO305

46

16
Summary and Conclusion

Contents:
Life cycle of a process order
Information about further courses

SAP AG 1999

(C) SAP AG

LO305

16.2
Summary and Conclusion: Unit Objectives

At the conclusion of this unit, you will be able to:


Create a process order for a material
Carry out system-aided batch determination and

resource selection
Release the order, create a control recipe, and

send it
Maintain the PI sheet and send messages that

have been created

SAP AG 1999

(C) SAP AG

LO305

16.3
Overview Diagram 16
1

Introduction

PP-PI Overview

10 Phases

Master Data: Overview

11 Master Recipes: Materials

Materials

12 Master Recipes: Control View

R/3 Classification System

13 Aspects of Co-Product Manufacturing

Batches

14 During Production

Resources: Customizing

15 Recipe Approval

Resources: Functions

16 Summary and Conclusion

9 Production Version
Master Recipes: Operations and

Aspects of Quality Inspection


Engineering Change Management,

SAP AG 1999

(C) SAP AG

LO305

16.4
Summary and Conclusion: Business Scenario

You have made the settings and maintained the


data necessary for the process manufacturing of
the new product in the R/3 System.
As the person responsible, create a process
order and have the corresponding PI sheet
maintained by a process operator.

SAP AG 1999

(C) SAP AG

LO305

16.5
Functions of PP-PI

Production planning
Master data
Material

Quality
management

Process
planning/
orders
Process
management

Process control
LIMS
Laboratory system (autom.)
PCS
information syst.

Process data
documentation/
evaluation

Resource
Master recipe

PI sheet
(manual)

PI sheet

SAP AG 1999

PP-PI comprises the following functional areas :


Resource management: The PI-specific master data of resources describes all means of production
and persons involved in the production process.
Master recipe management: The PI-specific master data of master recipes describes the
manufacture of one or more materials in one production run without relating to a particular order.
Master recipes are the basis for process orders.
Process planning comprises the planning of process orders. Process orders are created on the basis
of master recipes. They describe and monitor the actual production process.
Process management coordinates the transfer of data between PP-PI and the process control level.
It can be used in fully automated, partially automated, and manually operated plants.
Process data documentation and evaluation enables a detailed documentation and evaluation of
all planned and actual values of a process.
PP-PI is integrated with, for example:
R/3 Quality Management. Via a special interface, external laboratory information systems
(LIMS) can be linked to R/3 QM.
The higher-level planning components of R/3. Production requirements for PP-PI are created in R/3
Material Requirements Planning. Via a special interface, you can also transfer requirements
from an R/2 System or an external planning system to PP-PI.
The master data and functions of R/3 Materials Management (such as material, inventory
management).

(C) SAP AG

LO305

(C) SAP AG

LO305

16.6
Data Flow in PP-PI

Production reqmts

Materials
Material master
Bill of material
Resources
Proc. units
Personnel

PP

Planned order

PP-PI

Process order

Master recipe
Manually

MM
Process data documentation & evaluation

Process management

QM
Process
messages

Automatic control
Manual control (PI sheet)

Control recipe:
proc. instructions

Process control
system

Process
control level

SAP AG 1999

A production process is triggered by production requirements. Production requirements are created in


material requirements planning in the form of planned orders. Planned orders define the basic dates and
planned production quantities.
During process planning, planned orders are converted into process orders. The basic dates and
production quantities are copied from the planned order. The actual production dates are calculated using
the basic dates. You can also create a process order manually.
A process order provides a detailed description of the actual production of one or more materials in one
production run. It is the main control instrument in production, describing and monitoring all planned
and actual data relating to production.
A master recipe is used as the basis for a process order. It defines, for example, the planned resources
and material components.
After a process order has been released for production, the process instructions maintained in the order
are bundled into control recipes by process management. The control recipes are either transferred to a
process control system via a specific interface or are displayed online in the form of a process
instruction sheet (PI sheet) that can be read and maintained by process operators.
Process management in turn receives process messages from the process control level and transfers
them to various destinations. For instance, it is possible to record confirmations for the process order,
transfer actual values of the process to functions for process data documentation and evaluation, post
material consumptions or production yields as goods movements and transfer quality data to Quality
Management results recording.

(C) SAP AG

LO305

(C) SAP AG

LO305

16.7
Life Cycle of a Process Order

Archiving / Deleting

Production reqmnts

Process data
documentation
Process order
settlement

Process order
creation
Proc. order

Scheduling

Operations

Good receipts

Phases
Process
instructions

Proc. messages
to diff. destin.

Costs

Resource
assignments

Material
availability check

Material
components
Relationships
Relationships

Process order
release

In-process quality
inspections

Creating & download.


control recipes

Order
confirmations

Cap.rqmts planning

Material withdrawals

SAP AG 1999

The graphic shows the main steps that are carried out for controlling process manufacturing in the R/3
System.
The process order is the main instrument for executing and monitoring production. The procedure of
process order management can be divided into the following steps:
Process planning
Process order execution/Process management
Order closing

(C) SAP AG

LO305

16.8
Order Processing - Further Information

Archiving / Deleting

Production reqmnts

Process data
documentation
Process order
settlement

Process order
creation
Proc. order

Scheduling

Operations

Good receipts

Phases
Process
instructions

Proc. messages
to diff. destin.

Costs

Material
components

LO310
Detail Functions
in order
Process
release
Process Manufacturing
Creating & download.
control recipes

Order
confirmations

Material
availability check

Resource
assignments

Anordnungs- beziehungen
Relationships

In-process quality
inspections

Cap.rqmts planning

Material withdrawals

SAP AG 1999

Further information on this topic is provided in the course LO310 "Detail Functions in Process
Manufacturing".

(C) SAP AG

LO305

10

16.9
Process Management - Further Information

Process
planning

Process
management

Process
control

Execution

Control
recipes
Process
order

Process
control
system

Process
messages

PI sheet

LO315
Process Management

And other
message
destinations

SAP AG 1999

Further information on this topic is provided in the course LO315 "Process Management".

(C) SAP AG

LO305

11

16.10
QM and Batches - Further Information
Integration with Quality Management

LO705
Quality Inspections
Inspection specifications
Concentration
pH value
Viscosity

Insp. results recording


20 %
7,3
100 cP

R/3 QM insp. lot: Insp. char.

R/3 QM insp. lot: char. values

LO721
QM in Process
Manufacturing

QM-IDI

QMQM-IDI

LIMS: analytical results

Ext. Labor. information system


(LIMS): analyt. specification

50
40
30
20
10

Batch Management in the Logistics Process


Procurement

Production
Warehouse management

Sales
Warehouse management

Purchase
order

Warehouse

Batch
assignment

Process/
production
order

Warehouse

Batch
assignment

LO955
Batch Management

A
A

Sales
order

Batch determination

Batch determination

SAP AG 1999

Further information on the topics "Quality Management" and "Batch Management" are provided in the
courses LO705 "Quality Inspections" and LO955 "Batch Management".

(C) SAP AG

LO305

12

16.11Summary: Exercises
Unit: Summary

At the conclusion of these exercises, you will be able to:


Create and process orders
Carry out batch determination and resource selection
Generate a control recipe and a PI sheet
Work with the message monitor
You have made the settings and maintained the data necessary for
the process manufacturing of the new product in the R/3 System.
As the person responsible, create a process order and have the
corresponding PI sheet processed by a line operator.

Note: The following exercises will illustrate the complete execution of a process order based on
the master data created in the previous exercises.
1-1

Creating process orders


Create a process order of the order type PI01 for material T-FD1## (detergent) in plant
1100.

Total quantity:

(for example) 10000L

Basic dates: start

(for example) today + 1


week

Choose Enter and pay attention to the messages in the status bar. The master recipe TDET1## (detergent production) is copied with the material list and the process order is
scheduled.
On the Operation Overview and Material List screens, check whether the data from the
master recipe T-DET1## has been copied correctly.

(C) SAP AG

LO305

13

1-2

System-aided batch determination


Note:
In the previous exercises, you posted batch stocks for your material component TRD1## which is to be handled in batches. The batches are classified with the class
023_14 (detergent production) of the class type 023 (batch). The characteristics M100
(concentration) and M200 (density) are assigned to class 023_14 to which you assigned
the corresponding batch characteristics.
You also classified the BOM item 0010 T-RD1## in the BOM for material T-FD1##
with the same class. By doing this, you defined selection conditions for a system-aided
batch determination.
Execute batch determination for component T-RD1## in the order.
Pay attention to the messages.
Assign a selected batch.
Save your order and write down the order number. __________________.

1-3

System-aided resource selection


Note:
In the previous exercises, you classified your reaction vessel with the class REAC_##
(Reaction vessel) of the class type 019 (Work center class) and defined specific
characteristics for these resources by assigning them values.
The resource T-DTG1## that is assigned to operation 200 only serves planning
purposes (task list usage C## Recipe until release group##). An order cannot be
released with this resource. Before the release of an order can take place, a planning
resource must be replaced with a suitable real resource.
You also classified operation 200 with the class REAC_## and, by assigning the
corresponding values to the characteristics, defined selection conditions for a systemaided resource selection of a suitable reaction vessel. The resource network is
considered at the same time.
Execute a resource selection for operation 200.
Select a resource.

1-4

Releasing a process order


Release your order.

1-5
(C) SAP AG

Generating a control recipe


LO305

14

Generate a control recipe for the order.


Save your order.
1-6

Sending a control recipe


Send your recipe in the control recipe monitor.

1-7

Maintaining the PI sheet


Find and maintain the PI sheet.
Confirm the start and finish of phase maintenance with your signature. Sign with your
user PI## and confirm with your.
Read the notes that have been prepared in the PI sheet.
Confirm the material withdrawal quantities of the raw materials T-RD1## and TRD2##. Use the material information that is listed and F4 as help. Do the same for the
withdrawal of the raw materials T-RD3##, T-RD4##, and T-RD5##.
Confirm the produced quantity of the product T-FD1##.
Set the PI sheet to complete after the last signature.
PI sheet -> Set to complete

1-8

Sending process messages


In the message monitor, send the process messages that were created during the
maintenance of the PI sheet.

(C) SAP AG

LO305

15

1-9

Check withdrawn raw material quantities and time confirmations


Check the withdrawn quantities of raw materials in your process order. Also check the
time confirmations for the order.

(C) SAP AG

LO305

16

16.12Solutions
Unit: Summary

1-1

Creating process orders


Create a process order of the order type PI01 for material T-FD1## (detergent) in plant
1100.
Logistics -> Production - Process -> Process Order Process Order -> Create ->
With material
On the Operation Overview and Material List screens, check whether the data from the
master recipe T-DET1## has been copied correctly.
Choose Operations.
Choose Materials.

1-2

System-aided batch determination


Execute batch determination for component T-RD1## in the order.
In the material list:
Choose Trigger batch determination for component T-RD1##
For a batch found:
Choose Copy.

(C) SAP AG

LO305

17

1-3

System-aided resource selection


Execute a resource selection for operation 200.
Process order Change
Operation overview
for operation 200:
Choose Execute resource selection.
Select a resource.

1-4

Releasing a process order


Release your order.
Choose Release.

1-5

Generating a control recipe


Generate the control recipe for the order.
Choose Generate control recipe.

1-6

Sending a control recipe


Send your control recipe in the control recipe monitor.
Process Management menu Control recipe -> Control recipe monitor

(C) SAP AG

LO305

18

1-7

Editing the PI sheet


Find and edit the PI sheet.
Process Management PI sheet Find
Set the PI sheet to complete after the last signature.
PI sheet -> Set to complete

1-8

Sending process messages


In the message monitor, send the process messages that were created during the
maintenance of the PI sheet.
Process management Message -> Message monitor

1-9

Check withdrawn raw material quantities and time confirmations


Check the withdrawn quantities of raw materials in your process order. Also check the
time confirmations for the order.
Process order -> Display
Material List
For the material components, choose Material -> Material details
Operation Overview
For the phases, choose Operation -> Operation details
Dates group box.

(C) SAP AG

LO305

19