MultiMill IQOQPQ
MultiMill IQOQPQ
MultiMill IQOQPQ
FOR
MULTI MILL MACHINE
MODEL: CIMM-200
Purchase Order No.: HPP/181439 DATED 06-10-04
Works :
Plot No.1903, Phase IV,
Opp. Maradia Steel Unit-3,
G.I.D.C., Vatva,
Ahmedabad 380 026.
Gujarat, INDIA.
Phone: 91-79-583 59 08
91-79-583 53 41-2-3
TeleFax: 91-79-583 58 53
E-Mail : [email protected]
[email protected]
Visit us on Internet at :
www.cipmach.com / www.roll-compactor.com
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 2 of 32
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 3 of 32
C) Performance Qualification:
It should cover the performance parameters set for the equipment performance. Validation of
equipment against these parameters should also be described.
It should also describe.
01. Equipment validation.
02. Performance qualification evaluation.
03. Final report.
D) Design Qualification:
01. Relevant drawings.
02. Final report.
E) Conclusion:
The Multi Mill Machine meets the acceptance criteria in reference to above parameters are declared
validated and released for use.
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 4 of 32
INSTALLATION QUALIFICATION
EQUIPMENT NAME
EQUIPMENT MANUFACTURER
EQUIPMENT LOCATION
TABLE OF CONTENTS
01.0 Equipment Features
02.0 Pre Qualification
03.0 Statement of Purpose
04.0 Installation Checklist
05.0 Drawings
06.0 Materials of Construction
07.0 Major Components Verification
08.0 Supporting Utilities
9.0
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 5 of 32
INSTALLATION QUALIFICATION
01.0 EQUIPMENT FEATURES
EQUIPMENT NAME
MODEL NO.
: CIMM-200
SERIAL NO.
: 295
DEPARTMENT
PURPOSE
: Milling of powder.
VALIDATION TEAM
NAME
DESIGNATION
SIGNATURE
DATE:
Q.A.
Manager
Production
Manager
Works
Manager
Maintenance
Manager
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 6 of 32
INSTALLATION QUALIFICATION
02.0 PRE QUALIFICATION
EQUIPMENT NAME
OUTPUT
VENDOR SELECTED
VENDER'S ADDRESS
MANUFACTURE'S NAME
NAME
DESIGNATION
SIGNATURES
DATE
Project Incharge
Works Manager
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 7 of 32
INSTALLATION QUALIFICATION
(A)
MATERIAL OF CONSTRUCTION
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 8 of 32
INSTALLATION QUALIFICATION
03.0 STATMENTS OF PURPOSE
The purpose of this protocol is to provide an outline for the inspection of equipment for
static attributes to verify that:
Each installed sub-component complies with the engineering design and equipment data
sheets / specifications.
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 9 of 32
INSTALLATION QUALIFICATION
05.0
INSTALLATION CHECKLIST
It shall be ensured that all civil, mechanical, electrical and instrumental requirement of the
equipment to be installed is fulfill. i.e. as bellow.
Consideration
No.
Statement
01.
Verify that the "As Built" drawings are complete and represent the design
concept.
Verify that major components are securely anchored and protected from
shock.
Verify that there is no observable physical damage
02.
03.
04.
05.
06.
07.
08.
09.
Yes/No
Comments: All the above-mentioned consideration is being checked and found satisfactory.
Date :
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 10 of 32
INSTALLATION QUALIFICATION
06.0
DRAWINGS
Details
Ref. Drg.No.
Status
G.A drawing
Date :
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 11 of 32
INSTALLATION QUALIFICATION
7.1 MAJOR COMPONENT VARIFICATION
Item
Hopper
Sieve
Beaters
Feed Hopper
Specification
CIP Make
CIP Make
CIP Make
CIP Make
Supporting
Certificates
SS 316 L
SS 316 L
SS 316 L
SS 316 L
Actual
Status
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 12 of 32
INSTALLATION QUALIFICATION
07.2 CONTACT PARTS MATERIALS OF CONSTRUCTION
Item Description
Hopper
Sieve
Beaters
Feed Hopper
Ref. certificate
As per attached herewith.
As above
As above
As above
Material of Construction
SS 316L
SS 316L
SS 316L
SS 316 L
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 13 of 32
INSTALLATION QUALIFICATION
7.3
Supporting Certificates
Motor
Starter
Status
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 14 of 32
INSTALLATION QUALIFICATION
08.0
SUPPORTING UTILITIES
List the supporting utilities and record whether or not they are properly connected and identified.
Utility
Electrical connection
Water Connection
Air connection to clean the Machine
Date :
Checked by
Date
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 15 of 32
INSTALLATION QUALIFICATION
09.0
Sr.No.
01
02
03
04
Description
Electrical Connection
Water Connection
Foundation
Compressed Air
connection
Specification
Four core cable to be connected to the machine
To clean the machine
Not applicable
Pressure 8 kg/cm2 for cleaning purpose.
Actual
Service Engineer
Plant Manager
Quality Engineer
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 16 of 32
INSTALLATION QUALIFICATION
10. SUPPORTING CERTIFICATES & DRAWINGS :
Sr. No.
1
2
3
Descriptions
RELEVENT DRAWINGS
MOC CERTIFICATES
BOUGHTOUT ITEMS CERTIFICATES
Actuals
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 17 of 32
INSTALLATION QUALIFICATION
11.0
FINAL REPORT
11.1
Summary:
The equipment shall be procured as per specification to M/s ALEMBIC LIMITED,
Installation is carried out as per manufacturers recommendations and user applicability.
supporting utilities will be connected.
Date :
Confidential
CIP MACHINERIES
PVT. LTD
OPERATIONAL QUALIFICATION
EQUIPMENT NAME
: MULTI MILL MACHINE GMP MODEL.
EQUIPMENT MAKE
: CIP MACHINERIES PVT. LTD.
EQUIPMENT LOCATION :
TAB LE O F C O N T E N T S
1.0
2.0
3.0
4.0
Statement of Purpose
5.0
6.0
SOP Development
7.0
8.0
Final Report
PAGE 18 of 32
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 19 of 32
OPERATIONAL QUALIFICATION
01.0 SYSTEM DESCRIPTION
CIP MACHINERIES PVT LTD, Multi Mill Machine is a machine for milling of the powder with
output of 75-100 kg/hour. The unit consists of:
Base Plate
Support Pillar
Motor mounting
Hopper assembly
Sieve
Feed Hopper
The system has utilities like electrical connection and air connection connected to it.
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 20 of 32
OPERATIONAL QUALIFICATION
01.1 SYSTEM DESCRIPTION
Item
Base Plate
Support Pillar
Motor mounting
Description
Hopper Assembly
Sieve
Feed Hopper
Status
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 21 of 32
OPERATIONAL QUALIFICATION
02.0 SEQUENTIAL OPERATION ASPECTS
Sr.No.
01
02
03
04
05
06
07
08
Operation / Activity
Cable from machine to main switch.
Specification
It should be four core three
phase.
Fix the plug as per the cable and It should be suitable to the
main switch.
three phase supply
To clean the machine
Hopper assembly should be
dismantled to clean the
machine before use and should
be assembled as per the
instruction.
To start the machine.
Starter should be ON to start
the machine.
To stop the machine.
Starter should be OFF to stop
the machine.
Reverse / Forward Direction
Machine should be rotate in
Reverse / forward direction
depend upon the required
milling.
Pour the powder into the feed Powder quantity should be
hopper.
decided depending upon the
characteristic of the same.
Powder Collection after sieving
Powder should be collected
with the suitable drum,
collection bowl, polyethylene
bag etc. from the discharge
chute.
Actual
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 22 of 32
OPERATIONAL QUALIFICATION
03.0 CRITICAL OPERATIONAL ASPECTS
Sr.No.
01
02
03
03
04
05
Operation / Activity
To clean the machine
Specification
Hopper assembly should be
dismantled to clean the machine
before use and should be
assembled as per the instruction.
To start the machine.
Starter should be ON to start the
machine.
Reverse / Forward Direction
Machine should be rotate in
Reverse / forward direction
depend upon the required
milling.
To stop the machine.
Starter should be OFF to stop the
machine.
Pour the powder into the hopper Powder quantity should be
assembly.
decided depending upon the
characteristic of the same.
Powder Collection after sieving
Powder should be collected with
the suitable drum, collection
bowl, polyethylene bag etc. from
the discharge chute.
Actual
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 23 of 32
OPERATIONAL QUALIFICATION
NAME OF EQUIPMENT: MULTI MILL MACHINE
04.0
STATEMENT OF PURPOSE
The purpose of this protocol is to validate the above equipment for the operational qualification to
1. Demonstrate that the equipment / system will perform reproductively and consistently within its
full dynamic range of operation according to manufacturers specifications.
2. Documents initial performance of the equipment / system.
3. Assure that the equipment / system performance is adequate to support the process for which the
system is designed.
4. Demonstrate the suitability of the SOP is established for the equipment / system.
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 24 of 32
OPERATIONAL QUALIFICATION
06.0 SOP DEVELOPMENT
Subject
:
: Standard Operating procedure for the operation of
Multi Mill Machine.
Testing Date
Operating Personnel :
Observing Personnel :
Observation
Observation - Yes / No
(If no state why in comments)
Date :
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 25 of 32
OPERATIONAL QUALIFICATION
07.0
Conducted By:
Conducted By:
Date:
Date:
Verified By:
Name:
Signature:
Date:
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 26 of 32
OPERATIONAL QUALIFICATION
08.0
FINAL REPORT
Summary
Analysis / Evaluation
Certification
The operation of the equipment MULTI MILL MACHINE GMP MODEL. was carried
out as per standard operating procedure.
The equipment performs within the assigned limits when operated as per approved
standard operating procedure.
Operating parameters that have a significant impact on the equipment ability to operate and
achieve the process are satisfactory and conforms to the acceptance criteria.
The equipment: MULTI MILL MACHINE - GMP MODEL.
Model No. CIMM-200
Location
Purpose
:
:
Q.C. MANAGER
WORKS MANAGER
MAINTENANCE
MANAGER
Q.A. MANAGER
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 27 of 32
PERFORMANCE QUALIFICATION
EQUIPMENT NAME
EQUIPMENT MANUFACTURER
EQUIPMENT LOCATION
TABLE OF CONTENTS
01. Equipment Validation.
02. Performance Qualification Evaluation.
03. Data Evaluation And Conclusion:
04. Final Report.
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 28 of 32
PERFORMANCE QUALIFICATION
01.0
EQUIPMENT VALIDATION
The simulation of the process was carried out by sieving of the powder from the machine.
Simulation of the process consist of the following:
Sr.No.
Activity
01
02
Position of Sieve
03
Pouring of Powder
04
Powder collection
Functional Acceptance
Criteria
As per the details given with
the operating manual
It should be properly fixed
with the wings nut.
It should from the feed
hopper.
It should be from the
discharge chute.
Status / Observation
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 29 of 32
PERFORMANCE QUALIFICATION
2.0
NAME OF MATERIAL:
PERFORMANCE CRITERIA - BEFORE MILLING:
1. APPERANCE:
2. SIEVE ANAYALSIS
PERFORMANCE CRITERIA - AFTER MILLING:
1
APPERANCE
SIEVE ANAYALSIS
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 30 of 32
PERFORMANCE QUALIFICATION
03.0
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 31 of 32
PERFORMANCE QUALIFICATION
04.0
FINAL REPORT
Summary
Analysis / Evaluation
Certification
The performance of the equipment MULTI MILL GMP MODEL. was carried out as
standard operating procedure.
per
The equipment performs within the assigned limits when operated as per approved
standard operating procedure.
Performance parameters that have a significant impact on the equipment ability to operate
and achieve the process are satisfactory and confirms to the acceptance criteria.
The equipment: MULTI MILL MACHINE - GMP MODEL.
Model No. CIMM200
Location
Purpose
:
:
Q.C. MANAGER
WORKS MANAGER
MAINTENANCE
MANAGER
Q.A. MANAGER
Confidential
CIP MACHINERIES
PVT. LTD
PAGE 32 of 32