TRANSFORMER Testing Manual Final 32 38 Pgs
TRANSFORMER Testing Manual Final 32 38 Pgs
TRANSFORMER Testing Manual Final 32 38 Pgs
32
PRE COMMISSIONING CHECKS /TESTS FOR TRANSFORMERS & REACTORS
Once oil filling is completed, various pre commissioning checks/ tests are performed to ensure the healthiness
of the Transformer/ Reactor prior to its energisation. Various electrical tests to be performed and their
significance are given below.
Sr.
Name of Test /
Operational Checks Operational Checks on cooler bank (pumps & Fans), Breathers
on protection System (silica gel or drycol), MOG, temperature gauges (WTI/OTI), gas
actuated relays (Buchholz, PRD, SPR etc.) and simulation test of
protection system
Test reveals the condition of insulation (i.e. degree of dryness of
paper insulation), presence of any foreign contaminants in oil and
also any gross defect inside the transformer (e.g. Failure to remove
the temporary transportation bracket on the live portion of tap
changer part)
3.3
Insulation
Resistance(IR)
measurement
3.4
3.5
3.6
Turns ratio (Voltage To determine the turns ratio of transformers to identify any
ratio) measurement abnormality in tap changers/ shorted or open turns etc
3.7
Vector Group
Polarity
3.8
Winding resistance
measurement
3.9
Magnetic Balance
test
3.15 Stability of
Differential, REF of
Transformer/
Reactor
33
34
1.1.6 After receiving the accessories at site same should be inspected and kept ready for immediate erection:
If erection work can not start immediately due to some reasons, then accessories should be repacked
into their own crates properly and packing list should be retained.
All packings should be kept above ground by suitable supports so as to allow free air flow underneath.
The storage space area should be such that it is accessible for inspection; water does not collect on or
around the area and handling/transport would be easy. Proper drainage arrangement in storage areas
to be ensured so that in no situation, any component get submerged in water due to rain, flooding etc..
Immediately after the receipt of main unit and also the accessories, same should be inspected and if
found satisfactory, the unit should be erected completely and filled with dry transformer oil as per the
instruction.
It is preferable to store the main unit on its own location/foundation. If the foundation is not likely to
be ready for more than three (3) months, then suitable action plan has to be taken from the
manufacturer regarding proper storage of the Main Unit.
If the transformer/ Reactor is to be stored up to three (3) months after arrival at site, it can be stored
with N2 filled condition. N2 pressure to be monitored on daily basis so that chances of exposure of
active part atmosphere are avoided. In case of drop in pressure, dew point of N2 has to be measured
to check the dryness of the Transformer/ Reactor.
In case of storage of transformer in oil filled condition, the oil filled in the unit should be tested for BDV
and moisture contents once in every three months. The oil sample should be taken from bottom valve.
36
If BDV is less and moisture contents are more than as given for service condition then oil should be
filtered.
1.1.7 During erection, the exposure of active part of transformers should be minimized. Further either dry air
generator should be running all the time or dry air cylinders may be used to minimize ingress of
moisture. The transformer should be sealed off after working hours. It is practical to apply a slight
overpressure overnight with dry air or N2 inside less than 300 mbar (30 kPa or 0.3 atmospheres).
Next day the pressure is checked and suspected leaks may be detected with leak detection instruments
, with soap water or with plastic bags tightened around valves (being inflated by leaking air) For oil
filled units whenever oil is drained out below the inspection covers, job will be treated as exposed.
Other exposure activities are as below:
1) Bushing erections
2) Jumper connections of Bushings
4) Fixing bushing turrets on cover
5) Fixing bushing turrets on side
6) Core insulation checking
7) Buchholz relay pipe work fixing on cover.
8) Gas release pipes/equaliser pipe fixing.
9) Entering inside the tank for connections/inspection etc.
For oil filled units depending upon the level up to which the oil is drained decides the exposure time. All such
exposure time should be recorded in a log sheet to decide the oil processing (drying) and oil filling of
transformer. For transformers with a gas pressure of 2.5 3 PSI, the acceptable limits of dew point shall be as
under: