Rebar Arrangement and Construction Carryout
Rebar Arrangement and Construction Carryout
Rebar Arrangement and Construction Carryout
1. Understanding of Drawing
1) Examination of drawing
When construction contract is completed, the contents of the drawings are surveyed
and checked before construction work.
Although it is a rule to survey the drawings right from the 1st page, it is common to
check the scale and the number of floors of the building and then plan, elevation,
exterior appearance, lines and windows of the building .
Not only orientation, precautions and specifications, but front elevation, rear side
elevation, right side elevation, left side elevation, partial development, partial section,
and detail section, etc should be also looked over to be reminded in the construction
site.
As construction work progresses , present work should be checked and compared
with instructions on the drawings , and an entire understanding of drawings should be
preceded before the next step.
Plan, structural plan, foundation, section, etc are checked if there is any suspicious
portion because all the drawings are not made by only 1 person.
There is also necessity of discussion when there is any question or changes in the
work.
In order to make smooth and steady progress of the work, a lot of time and repeated
practice are required.
In case of small scale of construction , it is progressed from the ground to the upper
floor in general , however there is no determined rule.
Figure 1
Figure 2
2)What is drawing?
Drawings are used in every industrial field with the development of industries.
Although their types and applications are different, there are agreed rules that are
called IPC(International Graphic Code), accepted by everyone in each field.
Specified rules and standards with reference to symbols, numbers, lines and letters are
adapted to drawings to help everyone understand what they mean.
When one begins to construct a building, one should carefully consider the
implications of drawings.
In this book, plan of reinforcement is briefed to help the workers understand them
more easily.
Drawings of construction work are grouped roughly as civil engineering and
architecture.
Although there are some differences, all the contents could be understood since they
are all in accordance with IPC mentioned above.
3) Classification of drawing
Shop Drawing
Drawings that suggest overall dimensions of each member with symbols, numbers
and lines for the construction work
Detailed Drawing
Detailed drawings that describe shapes , types and dimensions of each element for
the bar-fabrication
Understanding of Drawing
Drawings are in their own sequence beginning with the title and contents on the 1st
page.
Structure drawing of Rebar is for this case.
There are several types of drawings which include machinery, electricity,
sanitation, fire protection, communication, etc according to the type of work and
there are details as follows.
A) Construction
i. Building layout
ii. Elevation
iii. Plane figure
iv. Cross Section
v. Part Detailed drawing
B) Structure
i. Drawing of column center
ii. Plane figure of structure
iii. Drawing of stairway and slab rebar arrangement
iv. List of pillar , beam and retaining walls
v. Detailed drawing of rahmen rebar arrangement
C) In general, the order of drawing is in a sequence mentioned above, and all the
drawings are in scale.
Scale (All the units in "mm")
Among several types of rulers used in drawings, scale is indispensable.
There are many types of scale. Among them 300mm scale is frequently used.
It has carved line in the middle of each side, colored red, blue and black to
distinguish its scale.
Scale in red
Scale in blue
Scale in black
Blue
Red
Black
4) Usage of symbol
General symbol
Description
Symbol
Length
Indication
Rebar indication
Area
Volume
Symbol
Distance of Rebar
Diameter of Rebar
High density
No. of Rebar
Radius
Part detailed
drawing
Main entrance
Level
indication(Plane)
Sub entrance
Scale
S 1/200
Finish
Level indication
(elevation, cross
section)
No of layer &
Member
Structural plane
EL. 0.0000
EL. 0.0000
Drawing Symbol
Symbol
Description
Symbol
Description
Bottom
Top
N.F.
Near Face
F.F.
Far Face
E.F.
Each Face
E.W.
Each way
B.O.F
Bottom of Foundation
T.O.C
Top of Concrete
T.O.F
Top of Foundation
E.J.
Expansion Joint
Ab
Size of a rebar()
C.J.
Construction Joint
fck
Strength of Concrete(kgf/)
fy
fcu(t)
fe
D(db)
Fp
CL
Center Line
&
And
Height
Distance
THK.
Thickness
Width
CONC.
Concrete
TYP.
Typical
N.T.S
Not to Scale
STL
Steel
EL.
Elevation Level
FL.
Floor Level
2. Characteristic of Rebar
Throughout the reinforcement work, reinforcing bar strongly bonds to mixed concrete
and this makes floor, wall and other members very strong.
In other words, reinforcement is a bar that is embedded in the mixed concrete to make
a member strong.
Bar and concrete have low thermal expansion coefficients, 110-5 , and therefore
have little thermal deformation or failure, cooperatively strengthening members.
Deformed
Rebar
Symbol
Classification
SD 30A
over 30
Green(D:General type)
SD 30B
30 ~ 40
White(D:General type)
SD 35
35 ~ 45
Red(HD:Density type)
SD 40
40 ~ 52
Yellow(HD:Density type)
SD 50
50 ~ 64
Black(HD:Density type)
2) Classification of rebar
Regular bars : The length of one strip is 8,000mm by KS(Korean Standard).
Each bundle has almost same weight. (basis of 1-2 ton)
Irregular bars : Irregular bars that are made of leftovers or nonuniform bars.
Reinforcing bars that are mainly used in the construction site are SD40 high
strength steel and SD30A mild steel, Each bar is colored yellow(HD) and green(D)
respectively in order to identify them.
Mild steel usually used as processed goods such as hoop , stirrup , etc.
Type
Deformed
Bar
Symbol
Classification
SD 30A
Green(D)
SD 40
Yellow(HD)
SD 50
Black
(KS D3504)
Content
Type
1tonf
2tonf
nominal diameter
Per each
Per meter
Qty per
Qty per
(D)mm
(kgf)
(kgf)
1tonf
(kgf)
2tonf
(kgf)
HD10
210
420
9.53
4.48
0. 56
941
1,882
HD13
120
240
12.7
7.96
0.995
955
1,910
HD16
75
150
15.9
12.48
1.56
936
1,872
HD19
56
112
19.1
18
2.25
1,008
2,016
HD22
41
82
22.2
24.32
3.04
997
1,994
HD25
32
64
25.4
31.84
3.98
1,019
2,038
HD29
25
50
28.6
40.32
5.04
1,008
2,016
HD32
20
40
31.8
49.84
6.23
997
1,994
Weight limit
1 each
- 0.8%
1 ton
7.0%
D10 ~ D16
6.0%
5.0%
D16 ~ D29
5.0%
4.0%
4.0%
3.5%
Remark
Sampling of test piece and
calculation of weight limit
should be in accordance with
KS D3504
Unit Weight
Rebar Size
Unit Weight
HD10
0.56 f/m
HD25
3.98 f/m
HD13
0.995 f/m
HD29
5.04 f/m
HD16
1.56 f/m
HD32
6.23 f/m
HD19
2.25 f/m
HD35
7.51 f/m
HD22
3.04 f/m
HD38
8.95 f/m
Classification
Minimum
coating/thickness Remark
Foundation
All rebar
100
Foundation
All rebar
80
Wall, pillar
over HD29
Beam (outside exposure
below HD25
beam)
Slab(foundation slab) below HD16
50
40
over HD35
40
below HD35
20
Beam, Pillar
Tiehoop
Stirrup
Spiral rebar
40
Shell, Member
All rebar
20
60
Note : direct exposure to the air of outdoor means the case of direct exposure of
climate change and humidity change.
< Pile
foundation >
< Independent
foundation >
Coating
thickness 80
Cushion
Hoop
Coating
thickness 40
Lean Concrete
Lean Concrete
Coating
thickness 20
Wall
Stirrup
Coating
thickness
Slab
Coating
thickness
Regarding wall, horizontal rebar should be arranged to the outside of vertical rebar.
Regarding outside wall in underground which compressed by the land, more
arranged rebar should be arranged to the outside after comparing the arrangement
quantity between vertical rebar and horizontal rebar.
2) Rebar distance
Classification
Net Distance
Distance
Over 1.5 times of nominal diameter
Deformed
rebar
3) Type of tying
Regarding the working of tying , there are folded tying(lap splice) , compressed
tying(welded splice) , mechanical spiral tying(mechanical splice).
But compressed tying(welded splice) , mechanical spiral tying(mechanical splice)
have to be effected over 125% of resistance strength(fy) in plan criterion.
Folded tying (lap splice)
It is tying method to fold the fixed length from end part to new tying part by using
regular rope currently.
Rebar
Type
210
SD30
(fy=3,000
240
270
210
SD40
(fy=4,000
240
270
Rebar
Size
A Class Tying
Under D19
31.5d (41.0d)
41.0d (53.3d)
Over D22
39.3d (51.1d)
51.1d (66.4d)
Under D19
29.4d (38.2d)
38.2d (49.7d)
Over D22
36.8d (47.8d)
47.8d (62.2d)
Under D19
27.8d (36.1d)
36.1d (47.0d)
Over D22
34.7d (45.1d)
45.1d (58.6d)
Under HD19
42.0d (54.6d)
54.6d (71.0d)
Over HD22
52.4d (68.1d)
68.1d (88.5d)
Under HD19
39.2d (51.0d)
51.0d (66.2d)
Over HD22
49.1d (63.8d)
63.8d (83.0d)
Under HD19
37.0d (48.1d)
48.1d (62.5d)
Over HD22
46.3d (60.2d)
60.2d (78.2d)
Tying length
of deformed
rebar to be
compressed
21.6d
28.8d
1. The length of folded tying of rebars which have different diameter must over high value between the fixed
length of high diameter rebar and the folded tying length of low diameter rebar .
2. The tying position must be placed to low stress / to compressed stress of concrete.
3. By the criterion of concrete structure plan , it is mentioned that it is available for folded tying in case of
D29~D35 rebar.
However, you have to check in advance the problem such as the net distance of rebar is not secured and
also the tying length will be exaggerated if you apply folded tying of thick rebar.
Generally, there are more advantageous case by using mechanical tying instead of folded tying in case of
over D29 rebar.
A class tying : must be zigzag(rotation) tying arrangement and arranged rebar quantity is over 2 times of
required rebar quantity which defined in total block of tying part and also under 50% of rebar tying
quantity within required folded length.
B class tying : it is available for the tying of anti-earthquake plan and generally it is applicable to all
construction site.
Regarding SD500 , you must apply 1.25times of B class tying.
Regarding beam main bar tying , you must apply B class tying if you don't
mention tying position specially.
But, you can apply A class tying if you want to tying the compressed part of
concrete. (the compressed part of concrete : upper part main bar places near center
part of span, lower part main bar places near pillar)
The tying length of wall vertical length is available around 40db of under HD19
especially.
Example of folded tying(lab splice)
Vertical
rebar
Slab upper
part
Folded tying of vertical rebar in case the distance of rebar arrangement is different
Wall
S : Distance of Rebar
Ls : Tying length of Tension bar
Length
As shown in figure(A) , place 2 bars 3mm away , heat up both of the ends by using
mechanical equipment and add pressure to weld splice them figure(B), usually
available for all bars.
Mechanical spiral tying(mechanical splice).
As the mechanical splice method , it is rebar tying method to connect the spiral
part with nut & coupling by cutting screw by expanding the end of rebar over the
regular size.
need to take additional action to increase the section of additional material if error
is over that angle.
In case slab or wall rebar will be cutted by temporary exit such as material pick-up
exit, etc, you must extend the rebar which is over the length of splice to both ends
of exit.
If width of exit is narrow or the length of rebar extended is shorten , the length of
splice will be shorten when pouring exit concrete later.
Fixed length of
rebar which has
standard hook
fixed length of
tension bar
Compression
Tension
The length to
extend to reverse
side from max.
Stress point of
fixed length.
Hook should
place over the
center of pillar.
Fixed length
St
eff ress
(
we ect par
igh the t to
t)
Return point
beam
(unit:mm)
24N/
240kgf/
27N/
270kgf/
30N/
300kgf/
35N/
350kgf/
40N/
400kgf/
300
300
300
300
300
400
380
360
330
310
540
510
490
450
420
730
680
650
600
560
Remark
Rebar
27N/
270kgf/
24N/
240kgf/
General bar
30N/
300kgf/
(unit:mm)
35N/
350kgf/
40N/
400kgf/
Upper bar
HD10
400
510
370
490
360
460
330
430
310
400
HD13
510
670
490
630
460
600
430
550
400
520
HD16
630
820
600
770
570
730
520
680
490
640
HD19
750
970
710
920
670
870
620
810
580
760
HD22
1080
1410
1020
1330
970
1260
900
1170
840
1090
HD25
1230
1600
1160
1510
1100
1430
1020
1320
950
1240
HD29
1430
1850
1350
1750
1280
1660
1180
1540
1110
1440
HD32
1570
2050
1480
1930
1410
1830
1300
1690
1220
1590
(unit:mm)
24N/
240kgf/
27N/
270kgf/
30N/
300kgf/
35N/
350kgf/
40N/
400kgf/
50N/
500kgf/
210
200
200
200
200
200
HD13
270
260
240
230
210
210
HD16
340
300
300
280
260
260
HD19
400
370
360
330
310
310
HD22
460
430
410
380
360
360
HD25
520
490
460
430
400
400
HD29
600
570
540
500
470
470
HD32
670
630
600
550
520
520
50%
2
2
2) Upper bar : horizontal rebar without concrete harded over 300mm under splice part
and fixed length
3) The rebar with folded splice without contacting directly each other in bending
material must not depart over little value between 150mm or 1/5 of folded splice
length.
(unit:mm)
24N/
240kgf/
27N/
270kgf/
30N/
300kgf/
35N/
350kgf/
40N/
400kgf/
300
300
300
300
300
HD13
400
380
360
330
310
HD16
540
510
490
450
420
HD19
730
680
650
600
560
Remark
27N/
270kgf/
24N/
240kgf/
General bar
30N/
300kgf/
(unit:mm)
35N/
350kgf/
40N/
400kgf/
Upper bar
HD10
400
510
370
490
360
460
330
430
310
400
HD13
510
670
490
630
460
600
430
550
400
520
HD16
630
820
600
770
570
730
520
680
490
640
HD19
750
970
710
920
670
870
620
810
580
760
HD22
1080
1410
1020
1330
970
1260
900
1170
840
1090
HD25
1230
1600
1160
1510
1100
1430
1020
1320
950
1240
HD29
1430
1850
1350
1750
1280
1660
1180
1540
1110
1440
HD32
1570
2050
1480
1930
1410
1830
1300
1690
1220
1590
(unit:mm)
24N/
240kgf/
27N/
270kgf/
30N/
300kgf/
35N/
350kgf/
40N/
400kgf/
390
390
390
390
390
HD13
520
490
470
430
410
HD16
700
660
630
580
550
HD19
940
890
840
780
730
Remark
(unit:mm)
St
ren
gth
Rebar
General bar
HD10
510
670
490
630
460
600
430
550
400
520
HD13
670
870
630
820
600
780
550
720
520
670
HD16
820
1070
770
1000
730
950
680
880
640
830
HD19
970
1260
920
1190
870
1130
810
1050
760
980
HD22
1410
1830
1330
1720
1260
1640
1170
1510
1090
1420
HD25
1600
2080
1510
1960
1430
1860
1320
1720
1240
1610
HD29
1850
2410
1750
2270
1660
2150
1540
2000
1440
1870
2050 SD500
1930
1830
1690 1.25
2650 rebar(fy=500N/=5,000kgf/),
2510
2380 apply
2200
HD32 using
When
times1590
2060
27N/
270kgf/
24N/
240kgf/
30N/
300kgf/
35N/
350kgf/
40N/
400kgf/
Upper bar
fck = 21N/
SD400 (fy=400N/
= 70N/ (210kgf/
=4,000kgf/
- 700kgf/ )
SD500 (fy=500N/
HD10
300
410
HD13
380
540
HD16
470
660
HD19
550
780
HD22
640
910
HD25
720
1030
HD29
840
1190
HD32
930
1320
=5,000kgf/
(diameter)
min
(diameter)
tension
tension
or
Str
en
gt
Rebar h
24N/
240kgf/
27N/
270kgf/
30N/
300kgf/
35N/
350kgf/
40N/
400kgf/
50N/
500kgf/
HD10
210
200
200
200
200
200
HD13
270
260
240
230
210
210
HD16
340
300
300
280
260
260
HD19
400
370
360
330
310
310
HD22
460
430
410
380
360
360
HD25
520
490
460
430
400
400
HD29
600
570
540
500
470
470
HD32
670
630
600
550
520
520
(over 12d)
Drawing
Rebar
diameter
HD10
9.53
HD13
12.7
HD16
Leftover length
Condition
Condition
30
120
60
40
160
60
15.9
50
190
70
HD19
19.1
60
HD22
22.2
HD25
25.4
HD29
28.6
HD32
31.8
3d
3d
4d
70
12d
230
270
4d
80
90
80
310
110
120
350
120
130
390
130
(unit:mm)
Drawing
Leftover length
Rebar size
Rebar
diameter
HD10
9.53
HD13
12.7
HD16
15.9
35
100
HD19
19.1
60
120
HD22
22.2
HD25
25.4
20
2d
3d
both-sides
Condition
30
70
80
6d
12d
Condition
60
60
80
80
6d
or
60mm
100
120
280
140
320
160
U type
Closed type
Transformational
closed type
100
140
120
370
520
430
640
910
740
910
1290
1050
110
160
130
380
540
440
650
920
750
920
1300
1060
120
170
140
390
550
450
660
930
760
930
1320
1070
130
180
150
400
570
460
670
950
770
940
1330
1090
140
200
160
410
580
470
680
960
790
950
1340
1100
150
210
170
420
590
490
690
980
800
960
1360
1110
160
230
190
430
610
500
700
990
810
970
1370
1120
170
240
200
440
620
510
710
1000
820
980
1390
1130
180
260
210
450
640
520
720
1020
830
990
1400
1140
190
270
220
460
650
530
730
1030
840
1000
1410
1150
200
280
230
470
670
540
740
1050
850
1010
1430
1170
210
300
240
480
680
550
750
1060
870
1020
1440
1180
220
310
250
490
690
570
760
1080
880
1030
1460
1190
230
330
270
500
710
580
770
1090
890
1040
1470
1200
240
340
280
510
720
590
780
1100
900
1050
1490
1210
250
350
290
520
740
600
790
1120
910
1060
1500
1220
260
370
300
530
750
610
800
1130
920
1070
1510
1240
270
380
310
540
760
620
810
1150
940
1080
1530
1250
280
400
320
550
780
640
820
1160
950
1090
1540
1260
290
410
340
560
790
650
830
1170
960
1100
1560
1270
300
420
350
570
810
660
840
1190
970
1110
1570
1280
310
440
360
580
820
670
850
1200
980
1120
1580
1290
320
450
370
590
830
680
860
1220
990
1130
1600
1300
330
470
380
600
850
690
870
1230
1000
1140
1610
1320
340
480
390
610
860
700
880
1240
1020
1150
1630
1330
350
500
400
620
880
720
890
1260
1030
360
510
420
630
890
730
900
1270
1040
1) Cross tie
Ties to fix the stirrup onto beam ties to prevent hoop from slipping down
4) Wall tie
- The same procedures as saddle tie with twist and tie
it as the method of right picture
- Ties the bars that extend from the wall to keep the
required positions and distances between them
5) References
Every crossing point of the bars at the bottom span should be tied, and wound
more than 3 times.
When tying the bars at the top span, tie the bar changing the tying direction(one
time to left and next to the right)
When tying the bars in a slab, you may skip every other, but it is better to wind the
hoop before tying the bars.
It is advised to wind the hoop 3 times at the important crossing point.
There are several kinds of ties, and in construction works, #20 tie is normally used
in folded state.
Type
Foundation
Foundation
Beam
Remark
By calculation if Mat
thickness is over 1,500
Install to top span,
bottom span, sides
Pillar
Steel Reinforcement
Wall
Basement
Outside Wall
&
Concrete material
Beam
Slab
<Bending Table>
Bending Pin
Bending Plate
<Mat>
<Manual Cutter>
<Hammer>
<Inch Ruler>
<Plumb>
<Bar-tying hook>
Tools mentioned above are rather old type ones, and newly developed tools are in
the construction site now.
Processed
dimension
Bar backstopper pin
Working point
Keep the 1.5d of tolerance from the working point
(in case of D10, keep the 15mm of tolerance)
Be careful
3) Processing
2) Base plate(Footing)
<Example : 1>
<Example-1>
1,414 ( 2 ).
HD22 1,840mm20(foundation) = 36,800mm
Weight = 36.8m(36,800mm)3.04(unit weight) = 111.872kgf
HD19 2,600mm(long bar)2 = 5,200mm
Weight = 5.20m(5,200mm)2.25(unit weight) = 11.700kgf
HD19 2,310mm(short bar)4 = 9,240mm
Weight = 9.24mm(9,240mm)2.25(unit weight) = 20.79kgf
Actual requirement of bar is HD22 = 111.872kgf
HD19 = (11.700kgf+20.79kgf) = 32.49kgf
LOSS(left bar strip) : The original length of bar before cutoff is usually 8,000mm.
In case of above, 4pcs 1,840mm bars are produced and 640mm of bar strip is
left.
5 bars are needed for foundation, hence 6405 = 3,200mm of bar strip is left. Its
net weight is 3.20m(3,200mm)3.04(unit weight) = 9.72kg.
Actual requirement of bar is 8m3.04(unit weight)5 bars = 121.6kg
<Example : 2>
What is the weight of D10 8m bar?
0.56kg8m = 4.48kg
How many D13 bars(8m criterion) in 2ton?
2,000kg(0.995kgX8m) = 251EA(standard is 240EA)
Arrangement in foundation (base plate F)
( All the unit in drawing should be in 'mm')
HD19-6EA
HD22@200
F1 plane
cover50
Calculation :
cover80
Section
D10@300
D10@300
upper part, lower part @150
HD22-8EA
4) Pillar
Similar to footing, there are many shapes of pillar, that is, triangle, right triangle,
square, rectangle, pentagon. circle, etc.
The worker is recommended to earn a lot of working experience.
Calculation of pillar
In calculation, tie hoop, stirrup, main bars
in column and the others should be
included here.
D10@300
D10@300
upper part, lower part
@150
HD22-8EA
Example) Total length 62,000mm + both fixed length(anchor) 1,000mm = Gross Total
63,000mm. When using HD19 rebar, splice length is 1940d = 760mm. Rebar
8,000mm - splice length 760mm = 7,240mm. Gross Total 63,000mm 7,240mm =
8.7 piece (long bar 8piece & rest 5,080mm) Above splice length is 5,080mm
including anchor.
You can calculate it as above , but you have to carry-out the splice position as soon as
closely by calculating several methods if spice position is not fit well.
<Sample of processing>
END
CENTER
splice rebar
long bar
outside end
outside end
7) Calculation of hoop
If pillar size is width 400mm length 500mm, actual processing size is 320mm,
420mm except cover 40mm each(both 80mm).
When processing hook by hand, it will be included 40mm from total length.
When using Taeyeon's bending machine, it will be included 50mm from total
length .
coating
thickness 40
process size
8) Calculation of stirrup
If beam size is length 500mm , actual processing size is 420mm , 420mm except
cover 40mm each(both 80mm). If beam size is width 300mm , actual processing
size is 220mm , 220mm except cover 40mm each(both 80mm).
Including hoop 50mm , you can use Taeyeon's bending machine.
END
CENTER
Process size
9) Fact of processing
According to rebar thickness and to bending angle , 2 times of rebar thickness will be
used because of bending by circle of bending part than the length per actual straight line.
<Tolerance of rebar process size>
Item
Symbol
A, B
below HD25
A, B
15
over HD29
A, B
20
20
Drawing
main
bar
Tolerance( )
others
Tolerance( )
5
15
20
20
lean concrete
The reason that the top of piles is embedded into foundation is that , in case of an
earthquake , the pile causes bending fracture.
Especially , when the ground is unstable , there should be specified directions on
the drawings.(in case pile cover bending moment & compresssion or cover tension
properly only)
6-D13(circular arrangement)
PC Steel wire
2 times of
pile diameter
Fillup CONC
HOOP D13@1504
(foundation CONC)
Hole closure
PC or PHC PILE
when securing
splice length
In case of below
splice length
standard
hook
slab
<After reinforcement>
main bar
pillar
tying
footing
lean concrete
MAT
spacer
pillar
The tie hoops at the bottom hold the bars of the pillar in lean concrete and marking
on the mould form is compared with drawing to ascertain the center of the pillars.
<Foundation plate>
pillar location
marking
eccentric
The outer pillar must check main bar line.
<Example>
C - pillar
BC1 - #1 underground pillar
1C1 - #1 first-story pillar
Be careful of this point if there are rebar quantity's differences according to pillar
assembly x0, x1 or y0,y1 direction.
2) Indication of floor
2SL(upper concrete)
2FL(upper parts closing condition)
Height of floor
1) GL - GROUND LEVEL
2) FL - FLOOR LEVEL
(ground level per floor)
3) SL - SLAB LEVEL
(upper part of structure per floor)
< Stand the same to diagonal direction if each side is even. >
< Stand the same to all directions if each side is odd. >
< Stand the same to one direction if each side is even & odd. >
tie bar
Tie bar for assisting pillar should be at every distance to install tie hoop .
Diamond type
General type
Bind the tie hoops clockwise(as shown below) and spacing at the top and bottom
levels of vertical reinforcement should be within
[Note]
It is desirable that reinforcing bar should be in a variety of sizes, but 8m bar is usually
available in the market.
In other words, if you need a bar other than 8m in size, you should give a customerorder for it, which does not go well with economical strategy.
Reinforcing bars from D10~D16 do not have much problem in using them as
reinforcement for slabs or bearing walls. We have some advantages here.
Bar loss and the frequency of splice will be decreased if using bars of 8m ~ 12m
length by mixing.
over 75
under 75
max. 150
Dowel rebar
splice
fixing
max. slope
max. 150
splice/
fixed length of tension bar
slope rebar splice
pillar
tie hoop
beam
from current
rebar arrangement
carry-out
of construction
In case over 600mm of pillar size , you should fill up support tie hoop by shop
drawing.
You should get rid of support tie hoop in order to worker's entrance to pillar tube
to connect #8 wire for working of pillar outer appearance.
After this, the worker should not forget to bind the assist wire before he gets out.
In case the splice length for pillar splice is shorter than required, be sure to destroy
the concrete to maintain splice length but it is impossible possibility to execute
actually.
Therefore, you should check the availability of welding splice, compressed splice,
mechanical splice.
7) Correction of pillar
Bend the bar gently at a very low level
Pillar correction angle should not exceed
of overall angle
Heat should not be added to correct the main bar because it makes the strength of
rebar, just destroy the part that needs correction and bend it
of overall angle.
fixed length
2nd floor HO
main
head
1st floor HO
space
When the beam is arranged, the bottom bar should be all tied,
and the stirrup upper binding supported by spacer should be
tied 2,3 times tightly.
tension splice
(over B class splice length)
tension splice
Apply to anti-earthquake
slab rebar
max.
max.
beam lower
part bar
8db(main bar)
Lc/6
24db(hoop bar)
45
Center support(S.T.)
1st stirrup
arrangement beside
of pillars main bar
big beam
The splice for upper part rebar of beam's end and lower part rebar of beam's center
apply tension splice length.
<Main bar arrangement>
0.3L1 OR 0.3L2
0.3L1 OR 0.3L2
middle/
big value
middle/
big value
12db
Ldh
min 15
0.125L1
0.125L1
min 15 or continuance
min 15 or continuance
0.125L1
0.125L2
L1
L2
<Distance of stirrup>
S2
S1
50
50
50
end
0.25L1
center
0.5L1
L1
S4
S3
end
0.25L1
end
0.25L2
center
0.5L2
L2
Apply the above except the case of marking separately on beam chart.
S1-S4 : stirrup distance
2) Types of stirrup
<a> Open type
slab on one-side
over 45cm
over 30cm
However, it is formal to divide it into 4 parts from the end of beam reinforcement
to the other end.
wall girder
pillar
spacer
cover
thickness 40
Y beam
height 40
Y beam
X beam
Tension fixation
bent bar
(Top floor)
penetration
of bent bar
top bar
bent bar
(General floor)
Using the bent bars in beams is Japanese style, while cutoff bar is now in common.
0.3L or 0.3L1
big value
0.3L or 0.3L1
big value
In case of girder
0.3L or 0.3L1
standard hook
fixed length
big value
0.3L or 0.3L1
big value
Note
1) * : apply general bars splice length(A class splice) as standard splice length &
fixed length of rebar(22page 6)) for above size
2) ** : fixed as standard hook form about center part bottom bar's 25%
3) splice length according to splice position of rebar arrangement
- tying on upper part rebar(beam)
tying except upper part rebar(beam)
- tying on lower part rebar(beam)
tying except lower part rebar(beam)
tension fixed
length
Wrong method
Correct method
7) Hunch beam
Bend the bars at the bottom in a hunch former and anchor them onto the pillar.
Bend a half of the bars at the bottom to let the anchorage length penetrate the pillar
and anchor near the hunch point.
One size bigger stirrup should be used at the hunch point.
S.T. one size bigger stirrup
stirrup
processing
(current)
(revised)
9) Symbol of beam
Continuous end of beam
Center of beam
Exterior of beam
Interior of beam
Outside of beam
EXT(exterior) CENT(center)
END(end)
400500(stirrup process size : 320420)
tension splice
(B class splice)
stirrup : arrange 200mm distance-D10
END(end)
CENT(center)
300500(stirrup process size : 220420)
END(end)
CENT(center)
400500(stirrup process size : 320420)
tension splice
tension splice
(B class splice)
Each floor bottom structure plane figure symbol & beam chart symbol
You should check pillar size & rebar Qty per each floor, and also arrange after
checking rebar Qty & drawing of outer pillars front and side.
spacer
all bottom bars should be tied
2) When placing the concrete, it is usual to place concrete again after curing, and
repeat the same procedure.
During this procedure, protruded bars may become damaged or underground beam
and floor slab may not fit very well because of shrinkage.
Also, it will be not cleaned well because of dust if you will do concrete job with
arrangement of ground slab without neighbor ground cleaning completely.
3) In the author's view, it is recommended that, after completing lean concrete
working mat, the worker build up the fence around the reinforcement zone, in
which the bars are arranged, to cast in concrete at the same time.
It would be quite efficient since 2 cast-in procedures can be reduced to 1 procedure
and it also saves time and cost considering input of material & carpenter.
tension
fixation
pillar
mainbar
tension fixation
Calculation of all 2 types of bent bar is the same except the way of extracting pure
height of main bar from stirrup height(thickness).
Either span of
100 cover
beam height
inner length
left
updown cover
ST height
right
updown cover
8,000mm-(500mm-40mm-40mm)-(500mm-40mm-40mm)=7,160mm
7,160mm4=1,790mm Hence, the value of is 1,790mm
Calculation of hunch
Hunch = the height of stirrup1.4 - 20(bar diameter of top and bottom stirrup2)
fixed length is 40d in usual, hence provided that used bar is HD19,19mm40d=760mm
The length of anchor is 760mm- pillar fixation 400mm=360mm
400mm + 1,790mm = 2,190mm
400mm is the rest value except cover 100mm from width of pillar.
The length indication when spreading above calculation is as follows.
Total length 9,806mm for 8,000mm bar, the splice length is 2,566mm.
(example) 9,806mm-8,000mm=1,806mm, Total length is 1,806mm+760mm(splice
length)=2,566mm
100 cover
beam height
280(ST height)
actual height
END
CENTER
inner length
ST height
left
right(updown distance)
= 2,232mm.
= 2,976mm.
Total length required is 9,744mm and provided that the standard bar length is
8,000mm, we need to splice here and the splice length is 2,504mm.
example)
9,744mm - 8,000mm = 1,744mm
1,744mm + 760mm(splice length) = 2,504mm(total length)
To summarize, Main-Bend's return bend point is
lx point, Side-Bend is
point, you can find the bending to exterior side(to center part).
lx
main block
0.3L or 0.3L1
big value
90standard
hook
0.3L or 0.3L1
big value
wall
0.3L or 0.3L1
big value
90standard
hook
0.3L or 0.3L1
big value
0.3L or 0.3L1
big value
wall
H75mm or t/4
standard
hook
splice length of tension bar
standard hook
slab arrangement distance
using closed type STR
outside
wall
inside
slab
90 standard hook
wall.
Allow to
wall.
Allow to
cover thickness
cover thickness
calculate end
When bending in slab, using the hunch former will enhance the accuracy and
workability.
Hunch former can be made with bars on construction site.
If the bar is bent with hands, the length and the height of hunch will different
whenever it is made.
Please work with hunch former because bent bar decline to left/right side if you
bending too slantly to fit the height with hunch angle 45.
inner end
center
upper part
end
lower part
end
center
<A-A section>
inner end
Lx
Lx/4
inner end
Lx/4
center
end
Lx/4
Lx/2
Lx/4
Lx/4
Lx/2
Lx/4
end
center
inner end
<A-A section>
direction
direction
tension splice
SLAB DOWN
plane
section
cross section
In the plane drawing of open part, you can see the inside as above when you see to
arrow direction with dotted line and also you can know in detail with chart about the
size of beam and also which rebar will be installed.
Especially, you should check section drawing well.
If you cut plane, you can see elevation(verticality), reversely if you cut elevation, you
can see plane.
In any drawing and plane, we mark section for the part to understand difficultly to
help you for processing and arrangement on right section of drawing.
It is best way to get the training of supervisor and you must study symbols on
drawings.
Reference : dot line means lower part rebar , solid line means upper part rebar
Classification Symbol
1st
floor
Type
Thickness
1S2
1S1
Transverse direction(Lx)
Longitudinal direction(Ly)
X1
X2
Y1
Y2
150
HD10@200
HD10@200
HD10@200
HD10@200
120
HD10@250
HD10@250
HD10@300
HD10@300
Author's viewpoint : If you did not study shop drawing completely, you will solve
question if you will start construction by discussing to check wrong one after
visiting construction site after checking the drawing under construction over
80%.(especially, carpenter's process is over 80%).
tension splice
main bar
width fixing bar
sub bar
Place the stirrup closing bar densely and keep the thickness exactly. Especially in
the reinforcement of water tank, fabricate the reinforcement as specifically
suggested. And place the reinforcement at a time. In case the tank is big, the
reinforcement should be in zigzag and in the top span tying wire should be wound
at least one time before tying. If not, main bar would swing and would not
maintain the required shape. Simple cut bar reinforcement or hooking in the bar is
also a wrong reinforcement.
corner
Assist bars might deflect when concrete is cast-in or due to loose bindings.
To avoid this undesirable deflection, width-fixing bar, which is similar to stirrup in
shape is fabricated to place in assist bars.
Begin the placement of assist bars from 100mm above the floor place the stirrup
Stirrup(closing bar) at every third step
<Single arrangement>
U bar
wall horizontal rebar
<Double arrangement>
U bar
<Straight wall>
90standard hook
roof floor slab
tension splice
over 150
The end of wall vertical rebar on top floor should obtains unification by fixing
correctly on slab and processed to get 90standard hook.
The upper part rebar of slab to contact outer wall should be fixing splice or making
tension folding splice and wall outer vertical rebar.
pillar
horizontal bar
inside
inside outside
beam
vertical bar
outside
outside
inside
foundation beam
When the inserting bars as arranged straight bar are inserted at the underground beam
tension
splice
tension
splice
fixed length
no problem if fixed
length will be obtained
As shown above left, there is a possibility for stirrup vertical bar to be protruded
by the lack of cover thickness of fixing part.
It is recommended to adjust to fix the bar into the stirrup.
sio
nf
ixe
dl
en
gth
2) Balcony(Cantilever)
tension fixation
spacer
spacer
vertical/horizontal
D10-@220
tension fixation
upper support rebar
spacer
spacer
The most important part in cantilever is the bar at the top above distribution bars.
It is common to anchor the top bars into a beam, however, they can be anchored in
a slab so long as there is no difference between their levels.
To obtain adequate fixed length is most important.
Bars at the bottom should be anchored securely to provide for earthquake and
tornado.
When the level of cantilever and slab plate are different, bars in the slab should be
anchored onto the beam.
If the bars at the top are bent to be anchored onto the opposite slab, there might be
a crack due to tensile strength.
The bars at the top should be maintained with bar support.
D13(reinforcement bar)
tension fixed
length
L<1000
min. 600
.1
20
minimize
open part
max. 600
1-HD16
Explanation :
1) In case the size of open part is D<150mm, omit vertical & horizontal rebar
2) mark : arrange to single arrangement if established rebar arrangement as
siugle(double arrangement as double)
Square type open part
min. 600(TYP)
min. 600
open part
90standard hook
D10120
lamp slab rebar
arrangement
ten
si
len on f
gt ixe
h d
tension fixed
length
tension fixed
length
tension fixed
length
Qty(kg)
factory, school
over 700
apartment, house
below 700
KR
<processing separately>
Classification
Qty(kg)
600
D13 stirrup
800
bending
5ton/1 person
<cutting separately>
2) Weight of concrete
Specific weight of plain concrete(without reinforcement) is 2,300kg/1m3
Specific weight of concrete with reinforcement in it is 2,400kg/1m3
Specific gravity of lightweight concrete with perlite or gas-foaming agent is only
0.6~1.2
splice in some parts on high building & walls to prevent crack of the building.
Splice length of top bar in beams should be required fixed length if it extends to
the center of column and therefore sustains tensile force.
Splice of the bottom bars in beams should be within
where load is almost 0, and the top bars should avoid the end span of
beams.(min. rebar cost will be over 0.35%)
Pillar
Pillar also has important role to divide total weight and compression power of
building.
Distance of main bar also arrange bar fairly, distance per rebar and rebar will be
over 40mm or over 1.5times of rebar using.
The minimum size of column is more than 200mm and cross sectional area
should be more than 600cm2
Splice length applies B class splice length.
7) Cleaning
It is better to install concrete after cleaning always before installing concrete.
When you checking construction site, there are many other materials to decline the
quality of concrete such as soil, sawdust, trash.
You must delete it inevitably.
After concrete job, you must break concrete of ground and brush concrete on rebar
with hammer drill, wire brush , hammer on next floor splice part, wall, pillar.
temperature
pressure
power
time(second)
< Time passage of heat, pressure power >
Rebar diameter
HD16
40 ~ 50sec
HD25
HD19
50 ~ 60sec
HD29
HD22
60 ~ 1min 20sec
HD32
taper
type
others
hydraulic
mortar
gas
injection type compression compression type
inflation type
compression type
demerit
the compression
processing end might has
low confidence if it is
caused by processing
vulcanization of mold in
case high carbon steel bar
low confidence in case of
bending
taper type
low confidence of
omission & untying for
testing tension strength
and repeat test
inflation screw
swage screw
joint-rib screw
taper screw
cut processing
cut processing
cut processing
cut processing
mold compression
pre-cut processing
angle processing
case screw
case screw
case screw
cut screw
process type
merit
demerit
double faced
compression jack
coupler
fixed pin
rebar
lock nut
connection jack
lock coupler
fixed body
merit
demerit
difficulty of reinforcement
because the possibility of
displacement of pressure
strength for 1pc & 100pcs and
also the movement of pressure
tool