Project Management Institute - PMI Practice Standard For WBS PDF
Project Management Institute - PMI Practice Standard For WBS PDF
Project Management Institute - PMI Practice Standard For WBS PDF
Work Breakdown
Structures
Work Breakdown
Structures
ISBN: 1-880410-81-8
Published by: Project Management Institute, Inc.
Four Campus Boulevard
Newtown Square, Pennsylvania 19073-3299 USA
Phone: 610-356-4600 or Visit our website: www.pmi.org
E-mail: [email protected]
2001 Project Management Institute, Inc. All rights reserved.
PMI and the PMI logo are service and trademarks registered in the United States and other nations; PMP and the PMP logo are
certification marks registered in the United States and other nations; PMBOK, PM Network, and PMI Today are trademarks registered in the United States and other nations; and Project Management Journal and Building professionalism in project management. are trademarks of the Project Management Institute, Inc.
PMI books are available at special quantity discounts to use as premiums and sales promotions, or for use in corporate training programs as well as other educational programs. For more information, please write to the Book Publishing Coordinator, PMI Publishing
Division, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA. Or contact your local bookstore.
Printed in the United States of America. No part of this work may be reproduced or transmitted in any form or by any means, electronic,
manual, photocopying, recording, or by any information storage and retrieval system, without prior written permission of the publisher.
The paper used in this book complies with the Permanent Paper Standard issued by the National Information Standards Organization
(Z39.481984).
10
Contents
List of Figures
Foreword
Preface
vii
ix
xi
Chapter 1Introduction
1.1 Concept
1.2 Objective
1
2
3
4
6
3.1 Overview
3.2 Communications
3.3 Reporting
7
8
9
11
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
Overview
Preparing a WBS
Factors to Be Considered
WBS Measurement Considerations
Challenges to Be Considered
WBS Level of Detail
WBS Life-Cycle Considerations
Project Risk and the WBS
Resource Planning, Management, and the WBS
Additional Considerations
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
11
11
12
13
14
15
16
16
18
18
19
23
25
29
31
37
39
43
55
57
59
63
65
67
71
Glossary
75
References
77
Index
79
vi
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
List of Figures
Figure 3-5 with WBS Interactions (PMBOK Guide 2000)
Pharmaceutical Work Breakdown Structure Example
Sample WBS for Refinery T/A
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
8
44
66
vii
Foreword
On behalf of the Project Management Institute (PMI) Board of Directors, I am
pleased to present PMIs first practice standard, the Project Management Institute
Practice Standard for Work Breakdown Structures.
The Project Management Institute Practice Standard for Work Breakdown Structures is an important step in PMIs continuing commitment to define the body of
knowledge supporting the project management profession, and to develop standards for its application. The dedicated volunteers who worked on PMIs Ethics,
Standards, and Accreditation (ESA) Project first distilled the Project Management
Body of Knowledge (PMBOK) in 1983. Building on that work, PMI published
the PMBOK Standards in 1987.
The publication of A Guide to the Project Management Body of Knowledge
(PMBOK Guide) 1996 Edition continued the evolution. Today the PMBOK
Guide 2000 Edition is an American National Standard and the de facto global
standard for project management.
It has been PMIs intent for many years to supplement the information in the
PMBOK Guide by providing both industry-specific extensions and practice standards that guide the practice of the profession through more in-depth information
on the listed inputs, tools and techniques, and outputs. The Project Management
Institute Practice Standard for Work Breakdown Structures is the first such practice
standard. It provides guidance in the initial generation, subsequent development,
and application of the Work Breakdown Structure.
Finally, I would like to thank the project team, led by Kim Colenso, who
worked so diligently to bring this standard to fruition. Dedicated and competent
volunteers have always been the backbone of PMIs success, and this publication
is yet another example.
Hugh Woodward
Hugh Woodward, PMP
Chair PMI Board of Directors
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
ix
Preface
This Project Management Institute Practice Standard for Work Breakdown Structures provides guidance in the initial generation, subsequent development, and
application of the Work Breakdown Structure (WBS). The target audience for this
standard includes project managers, project team members, contract personnel,
and others who participate or have an interest in any aspect of the management
of projects. In using this Practice Standard, it must be recognized that as projects
vary, so may the resulting WBSs. There are, however, certain universal principles
that this Practice Standard addresses.
The Project Management Institute Practice Standard for Work Breakdown Structures is consistent with the current release of A Guide to the Project Management
Body of Knowledge (PMBOK Guide) 2000 Edition. The Practice Standard also
includes information derived from accepted project management industry
sources. The Project Management Institute Standards Program will periodically
update the Project Management Institute Practice Standard for Work Breakdown
Structures as part of the planned evolution of the standards documents. Your
comments are both requested and welcome.
The Project Management Institute Practice Standard for Work Breakdown Structures is organized as follows:
Introduction
Introduces the WBS concept.
What Is a WBS?
Defines the WBS and its characteristics.
Why Use a WBS?
Defines the benefits derived from using a WBS.
How to Create a WBS? Documents the steps required for building a WBS and
presents guidelines for determining if the WBS is sufficient for subsequent planning and control.
Appendix AD
Provides background information on the Project Management Institute Standards Program and the Project
Management Institute Practice Standard for Work Breakdown Structures project.
Appendix EO
Provides documented industry examples to aid the reader
in further understanding, creating, and using WBSs. Each
appendix represents an approach tailored to a specific purpose, application, or industry. Examples are in different
stages of completion and represent the evolutionary development of a WBS. None of the examples should be taken
as the only right WBS for that type of project.
References
Offers literary support for the information contained in
the Project Management Institute Practice Standard for
Work Breakdown Structures.
Glossary
Provides clarification of key terms that exist in the project
management profession, including those that have subtle
or variable meanings depending on the organization and
industry.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
xi
Chapter 1
Introduction
1.1 CONCEPT
Successful project management uses planning techniques to define the project
objectives in sufficient detail to support effective management of the project. The
Work Breakdown Structure (WBS) provides the foundation for defining work as
it relates to project objectives and establishes the structure for managing the
work to its completion.
The WBS is used in projects to define:
The projects work in terms of deliverables and further decomposition of these
deliverables into components. Depending on the decomposition method
used, it may also define the projects life-cycle process in terms of process
deliverables appropriate to that project and organization.
As a definition for use within this Project Management Institute Practice Standard for Work Breakdown Structures, a project can be internally focused, externally
focused, or both. Deliverables for these projects can take the form of products
and/or services.
Internally focused projects may produce deliverables as inputs to other project
steps, other individuals, or for organizations within a company. Externally
focused projects typically produce outputs and deliverables to people or organizations outside the company, such as customers or project sponsors. Many projects produce both internally and externally focused deliverables. A WBS should
be routinely prepared in all cases.
Developing a WBS is an essential step during the initial phases of a project
as soon as the basic scope has been identified. The initial WBS may be created
with limited scope information. However, it will require rework as additional
scope information is developed or made available by more complete analysis of
the project work to be performed.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Chapter 1Introduction
This Practice Standard provides insight into WBS development and application. It has been prepared as a guide and should be used accordingly. It is
expected that use of the principles found in this standard will enable the user to
prepare a useful and high-quality WBS.
1.2 OBJECTIVE
The primary objectives of the Project Management Institute Practice Standard for
Work Breakdown Structures are to provide a common ground for understanding
the concepts and benefits of the WBS, and to present a standard application of
the WBS as a project management tool. The intent is to encourage the consistent
development of the WBS as a project management tool and, as a result, improve
the planning and control of projects.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Chapter 2
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
2.2 CONCEPT
2.2.1 Overview
The WBS elements assist the project stakeholders in developing a clear vision of
an end product of the project and of the overall process by which it will be created. The WBS divides the project scope into hierarchal, manageable, definable
packages of work that balance the control needs of management with an appropriate and effective level of project data. The various levels of the WBS aid in
focusing communication with stakeholders and clearly identifying accountability
to the level of detail required for managing and controlling the project.
The upper levels of the WBS typically reflect the major deliverable work areas
of the project or phases in the projects life cycle. These levels also provide logical
summary points for assessing performance accomplishments, as well as measuring
cost and schedule performance. The content of the upper levels varies depending
upon the type of project and the industry in which it resides. Therefore, to avoid
confusion and rework, it is often prudent to consider defining the labels for the
different levels of the WBS prior to its construction. The lower WBS elements provide appropriate focus for scope, cost, and schedule development.
Whenever work is structured, easily identifiable, and clearly within the capabilities of individuals, project stakeholders can confidently expect the objectives
associated with that work canand willbe achieved.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
The WBS:
Decomposes (or disassembles) the overall project scope into deliverables and
supports the definition of the work effort required for effective management.
Clearly and comprehensively defines the scope of the project in terms of
deliverables that the project participants and stakeholders can understand.
Supports documenting the accountability and responsibility for the various
deliverables by having a direct relationship between the WBS elements
related to the Organizational Breakdown Structure (OBS) identified through
the Responsibility Assignment Matrix (RAM).
The WBS provides a structure for organizing the scope and subsequent information of the projects progress, periodic status, and projected performance for
which a project manager is responsible. The WBS also supports tracking problems to their root causes to assist the project manager in identifying and implementing changes necessary to assure desired performance.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
2.3 SUMMARY
In summary, the WBS:
Defines the hierarchy of deliverables
Supports the definition of all work required to achieve an end objective or
deliverable(s)
Provides a graphical picture or textual outline of the project scope
Provides the framework for all deliverables across the project life cycle
Provides a vehicle for integrating and assessing schedule and cost performance
Provides the association to the responsible stakeholders
Facilitates the reporting and analysis of project progress and status data
Provides a framework for specifying performance objectives.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Chapter 3
3.1 OVERVIEW
The PMBOK Guide lists the Work Breakdown Structure (WBS) as the output of
project scope definition (Project Management Institute 2000). It defines project
scope management as:
The processes required to ensure that the project includes all the work
required, and only the work required, to complete the project successfully
(Project Management Institute 2000).
Both of these goals are of great concern to the project manager. If the WBS
does not meet either of these two goals, the project may fail. If necessary work is
omitted, the project will almost certainly be delayed and may experience cost
overruns. If unnecessary work is performed, the customers time and money will
be wasted. The WBS assists in developing a clear vision of the end product of the
project and of the overall process by which it will be created, therefore, it aids in
these areas.
Figure 3-5 of the PMBOK Guide 2000 Edition (reproduced in part and modified here) illustrates how the entire project plan pivots on the WBS. The WBS is
the primary input to four core processes and one facilitating process:
Activity Definition
Resource Planning
Cost Estimating
Cost Budgeting
Risk Management Planning.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Scope
Time
5.2
Scope Planning
Scope
Statement
Time
6.1
Activity Definition
Scope
OUTPUT: WBS
Cost
WBS
Time
6.4
Schedule
Development
Time
WBS
5.3
Scope Definition
6.2
Activity
Sequencing
6.3
Activity Duration
Estimating
7.1
Resource
Planning
WBS
Cost
7.3
Cost Budgeting
WBS
Cost
7.2
Cost Estimating
WBS
Integration
4.1
Project Plan
Development
Risk
11.1
Risk Management
Planning
Figure 3-5 with WBS Interactions from PMBOK Guide 2000 Edition (Project Management Institute 2000)
As Figure 3-5 of the PMBOK Guide illustrates, the entire project plan builds
on these processes. This makes the WBS the foundation for:
Coordinated and Integrated PlanningThe WBS provides the basis for integrated project management across the nine Project Management Knowledge
Areas and five Project Management Process Groups. It also provides the means
for using project management software to its full capability.
Performance ReportingThe WBS organizes monitoring processes, as well as
the cost and schedule performance metrics associated with the work.
Overall Change ControlThe WBS provides for the identification of suitable
management control points that are used to facilitate communication and control scope, quality, technical soundness, schedule, and cost performance.
Product Scope ManagementThe WBS development process facilitates conceptualization and definition of product details.
Successful project management depends on the project managers ability to
effectively direct the project team to complete the project deliverables. Through
the WBS, the work to accomplish these deliverables is structured, assigned,
scheduled, tracked, and reported. Work is then directly related to the schedule
and the budget, supporting effective resource allocation and tracking.
3.2 COMMUNICATIONS
The WBS facilitates communication of information regarding project scope,
dependencies, risk, progress, and performance between the project manager and
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
stakeholders throughout the life of the project. Project stakeholders include all
who directly participate or have an interest in the outcome of the project, and
include but are not limited to:
Project Manager
Project Team Members
Customers
Suppliers
Management
Regulators
The Public/Community
Sponsors
Owners.
3.3 REPORTING
The WBS provides the project management team a framework on which to base
project status and progress reporting. The WBS can provide different perspectives
of the project structure. For example, information can be reported by:
Life-Cycle Phase
Deliverable
Work Package
All of the above compared to past similarly structured projects
All of the above relative to cost, schedule, risk, scope, and quality perspectives.
WBS related information (like budget and schedule) can be rolled up or collapsed, to a level of detail that can be understood by the appropriate project participants and stakeholders. In addition, it can be rolled up or collapsed, to a level
of detail that can be understood by the appropriate audience, such as senior or
middle managers.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Chapter 4
4.1 OVERVIEW
The Work Breakdown Structure (WBS) can be created new, or it can reuse components from other WBSs. When reusing existing components, WBS elements
may be drawn from previous similar projects or from standard project templates
that the organization has determined support accepted best practices.
The following sections in this chapter are presented as guides for use during
the development of a WBS, and contain a number of topics for consideration:
4.2 contains Guidelines for Preparation
4.3 contains Basic Assumptions or Factors
4.4 contains Measurement Considerations
4.5 includes Project Challenges for Consideration
4.6 aids in determining the Appropriate Level of Detail
4.7 discusses WBS Life-Cycle Considerations
4.8 addresses Risk Assessment
4.9 contains guidance for use when considering Resource Planning.
Some of the sections can be used as checklists for the development and refinement of the WBS.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
11
The WBS can assist the project manager and stakeholders in developing a
clear vision of the end product(s) of the project and of the overall process by
which it will be created. With this in mind, the following should stimulate
thought when developing a WBS to manage the project:
Think through the entire project. (Look at dividing high-level deliverables.)
Think deliverables. (What is to be provided/what is required?)
Think with the end in mind. (How will this component contribute to the finished deliverable?)
Think through the production of the deliverables. (What methods? What special processes? What quality requirements? What inspections?)
These thoughts and questions are intended to help the project manager
develop a clear statement of what the product of the project isand to help
answer the question, How does one eat an elephant? Answer: One bite at a
time! The WBS is the technique for dividing the elephant into bite-sized pieces.
The following steps describe the general process for developing a WBS:
Step 1: Identify the final product(s) of the projectwhat must be delivered to
achieve project success. A thorough review of high-level project scope documents (inputs such as statement of work [SOW], technical requirements documents, and so on) is recommended to ensure consistency between the WBS
and the project requirements.
Step 2: Define the products major deliverables, which are often predecessor
deliverables necessary for the project, but that in themselves do not satisfy a
business need (e.g., a design specification).
Step 3: Decompose major deliverables to a level of detail appropriate for management and integrated control. These WBS elements normally tie to clear
and discrete identification of stand-alone deliverable products.
Step 4: Review and refine the WBS until project stakeholders agree that
project planning can be successfully completed and that execution and control
will successfully produce the desired outcomes.
12
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Deliverables must be unique and distinct from their peers, and should be
decomposed to the level of detail needed to plan and manage the work to
obtain or create them.
Deliverables should be clearly defined to eliminate duplication of effort within
WBS elements, across organizations, or between individuals responsible for
completing the work.
Deliverables should be limited in size and definition for effective controlbut
not so small as to make cost of control excessive and not so large as to make
the item unmanageable or the risk unacceptable.
The WBS development process should provide a vehicle for flexibility, particularly when the scope of the project effort may change. A well-managed
project, however, will incorporate a rigorous change control process to document and manage scope changes. When work scope changes do take place, the
WBS must be updated.
Each entry in the WBS representing subcontracted or externally committed
deliverables should directly correspond to matching entries in the subcontractors WBS.
All deliverables are explicitly included in the WBS.
All significant reporting items (e.g., review meetings, monthly reports, test
reports, and so on) are included and identified in the WBS.
All WBS elements should be compatible with organizational and accounting
structures.
A coding scheme for WBS elements that clearly represents the hierarchical
structure when viewed in text format should be used.
Technical input should be obtained from knowledgeable technical subject
matter experts (SMEs), and communicated to and validated by other key
SMEs assigned to the project.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
13
Separate WBS elements should be included for integration tasks where several
components are being brought together to create a higher-level WBS element.
By identifying the integration work separately where ever the above occurs,
performance measurement information will provide a timely indication that
problems are emerging. Cost and schedule variances occurring in WBS elements that contain integration work can also indicate potential future rework
in areas that have previously been completed. When these trends are projected, the result could be a far greater impact on revised estimates at completion than from projections of trends in other areas. Technical experts can
provide guidance regarding potential integration problems, which can help
the project manager decide whether or not to create these separate integration and assembly (I&A) WBS elements.
Identification and tracking of performance metrics in a disciplined and systematic fashion helps provide significant early warning of potential problems
and their nature.
14
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
15
Is the WBS element clearly and completely understood to the satisfaction of the
project manager, project team members, and other stakeholdersincluding the
customer?
Is there a stakeholder interested in analyzing status and performance of only
a portion of the work covered by the WBS element?
As identified earlier, the level of the detail in a WBS is a function of the size of
the project and a balance between complexity, risk, and the project managers
need for control. The level of detail may also vary during the evolution of a
project. A top-down and bottom-up analysis of the WBS can clarify whether the
WBS is both complete and defined at the proper level of detail.
Short-duration projects may lend themselves to decomposition to appropriate
levels of detail at the outset, while projects of longer duration and higher complexity may preclude decomposition of all deliverables until further in the future.
Again, this may mean that on any given project, some portions of the WBS may
have different levels of decomposition. This is especially true when doing rolling
wave planning, where the plan is detailed for the immediately upcoming work
only and work far in the future is defined at a high level until later in the project
life cycle.
16
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
The first step in this technique is to review the WBS elements to the level
being considered and segment them into risk events. This review should consider
the critical areas (requirements analysis/development, design and engineering,
technology, logistics, and so on) and other factors that may help to describe risk
events. Using information from a variety of sources such as program plans, prior
risk assessments, and expert interviews, the risk events are examined within critical areas to determine the probability of occurrence, severity of consequence
(impact), and interdependency.
The risks associated with an effort may also define the level of detail necessary. Additional detail in high-risk areas provides for better assumption definition, as well as improved cost estimates and time assessment. This forced
structuring provides an opportunity to define the assumptions and expectations
at a controllable level.
Risk planning can be incorporated directly into the WBS by defining and
including contingency activities as successors to the risk-impacted activities. The
duration of the contingency activities are set to compensate for the degree of
uncertainty and potential impact of the risk event. As an example, a permit-contingency activity could be created as a successor to the permit-application
activity. The duration of the permit-application activity is set to the normal time
period expected for a permit application, and the duration of the contingency
activity is set to reflect the probability and impact of the risk of delay.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
17
18
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Appendix A
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
19
20
Prospective developer(s) will submit a proposal to the PMI Standards Manager. The Manager may also request such proposals. The Manager will submit
all received proposals to the PMI Standards Program Member Advisory Group
who, with the Manager, will decide whether to accept or reject each proposal.
The Manager will inform the prospective developer(s) as to the decision and
the rationale for the decision. If an approved proposal requires funding in
excess of that budgeted for standards development, the Manager will submit
the proposal to the PMI Executive Director for funding.
For all approved and funded proposals, the Manager will support the developers efforts so as to maximize the probability that the end product will be
accepted. Developer(s) will be required to sign the PMI Volunteer Assignment
of Copyright.
When the proposed material has been completed to the satisfaction of the
developer(s), the developer(s) will submit the material to the PMI Standards
Manager. The PMI Standards Program Member Advisory Group, with the
Manager, will review the proposed material and decide whether to initiate further review by knowledgeable individuals or request additional work by the
developer(s).
The Manager will appoint, subject to review and approval by the PMI Standards Program Member Advisory Group, at least three knowledgeable individuals to review and comment on the material. Based on comments received,
the Member Advisory Group will decide whether to accept the material as an
Exposure Draft.
The PMI Standards Manager will develop a plan for obtaining appropriate
public review for each Exposure Draft. The plan will include a) a review
period of not less than one month and not more than six months, b)
announcement of the availability of the Exposure Draft for review in the PM
Network (and/or any other similarly appropriate publication media), and c)
cost of review copies. The PMI Standards Program Member Advisory Group
must approve the Managers plan for public review. Each Exposure Draft will
include a notice asking for comments to be sent to the PMI Standards Manager at PMI Headquarters and noting the length of and expiration date for the
review period.
Exposure Drafts will be published under the aegis of the PMI Publishing Department and must meet the standards of that group regarding typography and
style.
During the review period, the Manager will solicit the formal input of the
Managers of other PMI Programs (e.g., Certification, Education, Components,
and Publishing) that may be affected by the future publication of the material
as a PMI Standard.
At the conclusion of the review period, the PMI Standards Manager will review
comments received with the PMI Standards Program Member Advisory Group
and will work with the developer(s) and others as needed to incorporate appropriate comments. If the comments are major, the PMI Standards Program
Member Advisory Group may elect to repeat the Exposure Draft review process.
When the PMI Standards Manager and the PMI Standards Program Member
Advisory Group have approved a proposed PMI Standards Document, the Manager will promptly submit the document to the PMI Executive Director for final
review and approval. The PMI Executive Director will verify compliance with
procedures and ensure that member input was sufficient. The PMI Executive
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
21
Appendix B
Evolution of the
Project Management Institute
Practice Standard for
Work Breakdown Structures
During the development and subsequent publication by the Project Management
Institute (PMI) of A Guide to the Project Management Body of Knowledge
(PMBOK Guide), it was recognized that project management practitioners and
other stakeholders would be aided by more in-depth treatment of the listed
inputs, tools and techniques, and outputs. Consequently, in early 1998, PMI asked
for volunteers to develop the first such practice standard, specifically on the Work
Breakdown Structure (WBS). A volunteer team was assembled and during the
year worked through a number of drafts and revision cycles.
In early 1999, the PMI Project Management Standards Program Team reviewed
the draft and recommended the completion of the Practice Standard. In late spring
1999, Kim Colenso was approved as the new project manager for the Practice
Standard. He was tasked to form a new team to make minor modifications to the
current draft, and add example WBSs. The plan was to publish the Project Management Institute Practice Standard for Work Breakdown Structures in an Exposure
Draft to the PMI membership and other affected parties by the summer of 2000,
and a final document would be published as a PMI Standard in 2001.
A team was assembled during the summer and fall of 1999 through solicitation of participation from the PMI Specific Interest Groups and other volunteer
sources. During this period, a controversy developed within the project team on
whether or not an activity was or should be part of the WBS. Through further
discussion among the project team and among the PMI Project Management
Standards Program Member Advisory Group, the issue was resolved, and an
article describing the outcome was published in PM Network in April 2000 (see
References).
The project team implemented a formal change-control procedure to guide
and control the evolution of the Practice Standard. This procedure required all
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
23
Appendix BEvolution of the Project Management Institute Practice Standard for Work Breakdown Structures
24
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Appendix C
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
25
Reviewers
26
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
27
28
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Appendix D
Guidelines for a
Project Management Institute
Practice Standard
Each practice standard provides guidelines on the mechanics (e.g., nuts and
bolts, basics, fundamentals, step-by-step usage guide, how it operates, how
to do it) of some significant process (input, tool, technique, or output) that
is relevant to a project manager.
A practice standard does not necessarily mirror the life-cycle phases of many
projects. But, an individual practice standard may be applicable to the completion of one or more phases within a project.
A practice standard does not necessarily mirror the knowledge areas within A
Guide to the Project Management Body of Knowledge (PMBOK Guide), although
an individual practice standard will provide sufficient detail and background
for one or more of the inputs, tools and techniques, and/or outputs. Therefore,
practice standards are not required to use the name of any knowledge area.
Each practice standard should include information on what the significant
process is and does, why it is significant, how to perform it, when it should be
performed and, if necessary for further clarification, who should perform it.
Each practice standard should include information that is accepted and
applicable for most projects most of the time within the project management
community. Processes that are generally restricted or applicable to one
industry, country, or companion profession (i.e., an application area) may be
included as an appendix for informational purpose, rather than part of the
practice standard. With strong support and evidence, an application areaspecific process may be considered as an extension practice standard, in the
same manner as extensions to the PMBOK Guide are considered.
Each practice standard will benefit from the inclusion of examples and templates. It is best when an example or template includes a discussion of its
strengths and weaknesses. A background description may be necessary to
put this discussion in the appropriate context. The examples should be
aligned with the relevant information in the standard or its appendix and
placed in proximity to that information.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
29
30
All practice standards will be written in the same general style and format.
Each practice standard project will assess the need to align with or reference
other practice standards.
Each practice standard will be consistent with the PMBOK Guide.
Each practice standard is intended to be more prescriptive than the PMBOK
Guide.
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
Appendix E
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
31
2.2 Jacket
2.2.1 Structural Engineering & Drafting
2.2.1.1 Jacket In-Service Analyses
2.2.1.2 Jacket Pre-Service Analyses
2.2.1.3 Jacket Design Details
2.2.1.4 Jacket Cathodic Protection
2.2.1.5 Jacket Weights and Material Takeoffs
2.2.1.6 Jacket Approved for Construction (AFC) Drawings
2.2.1.7 Jacket Detailed Engineering and Design Report
2.2.2 Mechanical Engineering & Drafting
2.2.2.1 Flood & Vent System
2.2.2.2 Grouting System
2.3 Piling
2.3.1 Structural Engineering & Drafting
2.3.1.1 Piling In-Service Analyses
2.3.1.2 Piling Pre-Service Analyses
2.3.1.3 Piling Design Details
2.3.1.4 Piling Weights and Material Takeoffs
2.3.1.5 Piling AFC Drawings
2.3.1.6 Piling Detailed Engineering and Design Report
2.4 Topsides
2.4.1 Structural Engineering & Drafting
2.4.1.1 Deck In-Service Analyses
2.4.1.2 Deck Pre-Service Analyses
2.4.1.3 Deck Design Details
2.4.1.4 Deck Weights and Material Takeoffs
2.4.1.5 Deck AFC Drawings
2.4.1.6 Deck Detailed Engineering and Design Report
2.4.2 Mechanical/Process Engineering & Drafting
2.4.2.1 Process Simulation/Calculations
2.4.2.2 Equipment Design/Sizing
2.4.2.3 Pipe Stress Analysis
2.4.2.4 Hazard Analysis
2.4.2.5 Specifications, Data Sheets, and Request for
Quotations
2.4.2.6 Vendor Data Reviews
2.4.2.7 Weight, Material Takeoffs, Bill of Materials
2.4.2.8 AFC Drawings for:
2.4.2.8.1 Process Flow Diagrams/Utility Flow
Diagrams
2.4.2.8.2 Mechanical Flow Diagrams/Piping &
Instrument Drawings
2.4.2.8.3 Equipment Layouts/Arrangements/Skid
Layouts
2.4.2.8.4 Piping Supports
2.4.2.8.5 Piping General Arrangements,
Elevations, and Isometrics
2.4.2.8.6 Other AFC Drawings
2.4.2.9 Data Books, Equipment Manuals, Engineering and
Design Report
32
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
2.4.3
2.4.4
2.4.5
2.4.6
2.4.7
3.0 Procurement
3.1 General
3.1.1 Procurement Procedures
3.1.2 Expediting & Inspection Procedures
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
33
3.2 Jacket
3.2.1 Owner Furnished Equipment (OFE)
3.2.2 Contractor Furnished Reimbursable Equipment (CFRE)
3.2.3 All Other Contractor Supplied Equipment
3.2.4 Bulk MaterialsContractor Supplied
3.2.4.1 Structural
3.2.4.2 Anodes
3.3 Piling
3.3.1 Bulk MaterialsContractor Supplied
3.3.1.1 Structural
3.3.1.2 etc.
3.4 Topsides
3.4.1 Owner Furnished Equipment (OFE)
3.4.1.1 Rotating Equipment
3.4.1.2 Pressure Vessels
3.4.1.3 Electrical Generation
3.4.1.4 etc.
3.4.2 Contractor Furnished Reimbursable Equipment (CFRE)
3.4.2.1 Rotating Equipment
3.4.2.2 Pressure Vessels
3.4.2.3 Other CFRE
3.4.3 All Other Contractor Supplied Equipment
3.4.4 Bulk MaterialsContractor Supplied
3.4.4.1 Structural
3.4.4.2 Piping, Valves, & Fittings
3.4.4.3 Electrical
3.4.4.4 Instrument
3.4.4.5 etc.
4.0 Fabrication
4.1 General
4.1.1 Safety Manual and Plan
4.1.2 Yard and Work-Force Mobilization
4.1.3 Qualification of Welding Procedures and Welders
4.1.3.1 Structural
4.1.3.2 Piping
4.1.4 Shop Drawings
4.1.4.1 Structural
4.1.4.2 Piping Isometrics
4.1.4.3 Piping Spools
4.1.5 Receipt of Materials
4.1.6 QA/QC, NDT, and Dimensional Control
4.1.7 Weight Control Reports
4.1.8 As-Built Drawings and Certification Dossier
34
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
4.2 Jacket
4.2.1 Frames
4.2.1.1 Frame 1
4.2.1.2 Frame 2
4.2.1.3 Frame A
4.2.1.4 Frame B
4.2.2 Horizontal Levels
4.2.2.1 Level 1 (EL + 10')
4.2.2.2 Level 2
4.2.2.3 Level 3
4.2.2.4 Level 4
4.2.3 Appurtenances
4.2.3.1 Disposal Pile
4.2.3.2 Caissons
4.2.3.3 Risers
4.2.3.4 Boat Landing
4.2.3.5 Corrosion Protection
4.2.3.6 Stairs, Walkways, and Landings
4.2.4 Installation Aids
4.2.5 Loadout & Seafasten
4.3 Piling
4.3.1
4.3.2
4.3.3
4.3.4
4.3.5
Pile A1
Pile A2
Pile B1
Pile B2
Loadout & Seafasten
4.4 Topsides
4.4.1 Main Deck
4.4.1.1 Plate Girders
4.4.1.2 Deck Panels
4.4.1.3 Tertiary Steel
4.4.2 Cellar Deck
4.4.2.1 Plate Girders
4.4.2.2 Deck Panels
4.4.2.3 Tertiary Steel
4.4.3 Sub-Cellar Deck
4.4.4 Legs
4.4.5 Bracing
4.4.6 Equipment Installation
4.4.7 Interconnect Piping
4.4.8 Electrical
4.4.9 Instrumentation
4.4.10 Precommissioning
4.4.11 Appurtenances
4.4.11.1 Flare Boom
4.4.11.2 Stairs, Walkways, & Landings
4.4.11.3 Installation Aids
4.4.12 Loadout & Seafasten
2001 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA
35