Final Exam

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Geotechnical

Engineering Research Laboratory


One University Avenue
Lowell, Massachusetts 01854
Tel: (978) 9342621
Fax: (978) 9343046
email: [email protected]
web site: http://faculty.uml.edu/ehajduk

Edward L. Hajduk, D.Eng, PE


Lecturer

DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING

14.531 ADVANCED SOIL MECHANICS


FINAL EXAM (TAKE HOME):DUE THURSDAY, DECEMBER 19, 2013 @ 6PM.
Problem #1. Field load tests on strip footings yielded the test data provided below in
Figure 1 and Table 1 (from Ladd, 1979). Based on these test results, estimate the
following quantities for a strip footing with B = 4m and d = 2m.
a. The ultimate bearing capacity of the strip footing
b. The settlement at q = 20 tonnes per square meter (TSM).
settlement is proportional to log B.

Assume that

q = Total Applied Stress


q = Net Applied stress = q - d

= 1.50 TCM (above footing)


= 2.00 TCM (above footing)

Figure 1. Test Conditions for Strip Footing.


Table 1. Test Data for Problem #1.
(cm) at q =
10 TSM

Test No.

B (m)

d (m)

qult (TSM)

42

0.400

105

0.300

147

0.525

14.531 2013 Final Exam

Page 1 of 5

Geotechnical Engineering Research Laboratory


One University Avenue
Lowell, Massachusetts 01854
Tel: (978) 9342621
Fax: (978) 9343046
email: [email protected]
web site: http://faculty.uml.edu/ehajduk

Edward L. Hajduk, D.Eng, PE


Lecturer

DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING

Problem #2. Your company plans to test load a 150 ft diameter oil tank with water.
The stress increase at the ground surface ( q) will be 3,000 psf. The tank rests on the
surface of 60 ft of dry sand with the properties shown in Figure 2. Using the provided
information, do the following:
a. Estimate the settlement of the center of the tank using the stress path method
(and the data provided in Figure 2) to plot
'v/ 'vo and K vs. depth and
compute the vertical strains at depth (d) of 10, 20, 30, 40, and 50 ft.
b. Estimate the settlement of the center of the tank using corrected SPT N values
that averaged 40 to 50 blows per foot.
c. Back calculate a value of modulus of elasticity (E) that yields the same
settlement obtained with the stress path method using equations 14.15 and
14.21 in L&W.
d. Compare your answer for part c with the value of E obtained from Figure 2,
assuming that 'vo = 2,000 psf,
'vo = 2,000 psf, and K = Ko = 0.35. See
Example 12.2 for calculation of E.
Assume the following stress distribution provided in Table 2 and an elastic half space
with = 0.30.
Table 2. Stress Distribution for Problem #2.
z (ft)

14.531 2013 Final Exam

(psf)

(psf)

3000

2400

7.5

3000

2010

10

3000

1890

20

2950

1445

30

2850

1025

40

2700

729

50

2450

490

Page 2 of 5

Geotechnical Engineering Research Laboratory


One University Avenue
Lowell, Massachusetts 01854
Tel: (978) 9342621
Fax: (978) 9343046
email: [email protected]
web site: http://faculty.uml.edu/ehajduk

Edward L. Hajduk, D.Eng, PE


Lecturer

DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING

Figure 2. Stress-Strain as a Function of K for Problem 2.


14.531 2013 Final Exam

Page 3 of 5

Geotechnical Engineering Research Laboratory


One University Avenue
Lowell, Massachusetts 01854
Tel: (978) 9342621
Fax: (978) 9343046
email: [email protected]
web site: http://faculty.uml.edu/ehajduk

Edward L. Hajduk, D.Eng, PE


Lecturer

DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING

Problem #3. Lambe and Whitman Problem 16.3.


Problem #4. Calculate the theoretical height of capillary rise and the capillary pressure
in a clay soil with D10 = 0.1 m.
Problem #5. An inclined permeameter tube filled with three layers of soil of different
permeabilities as shown below in Figure 3. Express the total head at Points A, B, C,
and D (with respect to the indicated datum) in terms of the given dimensions and
permeabilities. Plot the total heads and the seepage velocity versus distance along the
line A-D for the case where 3k1 = k2 = 2k3. Assume n1 = 0.25, n2 = 0.4, and n3 = 0.35.

H2

H1

k1

k2

k3
D

Figure 3. Inclined Permeameter Tube for Problem #5.


Problem #6. Lambe and Whitman Problem 17.6.
Problem #7. Figure 4 shows a double sheet pile wall system for construction
dewatering. A steady-state 2D flow of water occurs into the inside of the excavation
between the two walls. For this problem, do the following:
a. Draw the flow net for this problem. You may use computer programs if they are
available to you.
b. Compute the rate of flow per foot of wall length.
c. Determine the maximum exit gradient and the factor of safety against
liquefaction.
d. Plot the pore water pressure against both sides of the sheet pile wall.
14.531 2013 Final Exam

Page 4 of 5

Geotechnical Engineering Research Laboratory


One University Avenue
Lowell, Massachusetts 01854
Tel: (978) 9342621
Fax: (978) 9343046
email: [email protected]
web site: http://faculty.uml.edu/ehajduk

Edward L. Hajduk, D.Eng, PE


Lecturer

DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING

Elev. + 28ft
20ft

Elev. + 20ft

Elev. + 28ft

Elev. + 20ft

Elev. + 16ft

Elev. + 10ft

Sand
= 124.8 pcf
k = 2x10-4 cm/sec
t

Elev. 0ft

Impervious Rock
Figure 4. Double Sheet Pile Wall Layout for Problem #8 (Not To Scale).

14.531 2013 Final Exam

Page 5 of 5

You might also like