Method Statement For Piling

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Activity: piling pegs setting out, monitoring of R.C.

piling works and construction of


pile caps & columns
Activity steps
1.0

Step 1 Gridline
setting out

2.0

Step 2 Pilling pegs


setting out

3.0

Step 3 Monitoring
R.C. piling works

Technical methods of applications / works


description
- To peg out the gridline setting out points
for every useful gridline by licensed
surveyor on the completed structures or
on the ground with 300mm offset from
the original gridline and verified by
licensed surveyor.
- Each pegs setting out will be verified by
contractor surveyor every morning
before start works
- Carpenter to set out the piling pegs
by using the gridline setting out pegs
provided by licensed surveyor.
- Licensed surveyor will randomly
verified the piling pegs done by
carpenter (if required)
- Carpenter to set out the column
centre point on X and Y gridline offset
out from the pile cap.
- The offset X and Y pegs will be tied
with string.
- To pitch and handle the R.C. Pile onto
the ground at piling peg position.
- Before the driving of the pile, to
ensure that the pile setting out on
the correct position by measuring the
pile to the line X and line Y string
line.
- After check on the position, proceed
to drive the pile. Our foreman or site
argent will full time supervise the
piling driving works.
- Close monitor on the verticality of
pile and monitor while driving the pile
by measuring the pile to the X and Y
string line from time to time.
- To record the pile set (minimum 3
continuous set graphs) with proper
recorded.
- After the pile is set, final checking on
the position to the X and Y string line.
- Repeat process 4 to 7 until individual

4.0

Step 4 PDA test

5.0

Step 5 Cutting off


pile head

6.0

Step 6 lean concrete


preparation
Activity steps

7.0

Step 7 As built pile


survey

8.0

Step 8. Remedial work


for ex - built piling

9.0

Step 9 column centre


point

10.
0

Step 10 installation
of formwork and rebar

11.
0

Step 11 casting of
the pile cap

pile installed correctly.


- To carry out the PDA Test for selected
pile as request by S.O. / Engineer (if
required)
- To excavate to required level and cut
off the pile head.
- If necessary the pile cap soffit
formation level to be prepare 1st for
piling work and repeat step 2 to step
4.
- To prepare lean concrete for the base
of the pile cap (75mm thk as per
construction drawing)
Technical methods of applications / works
description
- To carry out the as built piles survey
for every cut off piles by our licensed
surveyor.
- As built piles survey drawing to be
endorsed by licensed surveyor and
submitted to S.O. / engineer for
review and comments prior pile cap
construction.
- If any pile group out of position was
detected after the as built survey and
rectification work is required ,
contractor will submit the proposed
rectification method and design for
consultant (JKB) review and approve
prior pile cap construction.
- To provide column centre point by
licensed surveyor on the lean
concrete for every pile cap.
- To install formwork and rebar to the
pile cap based on the column centre
point provided by the licensed
surveyor.
- To submit the inspection form to S.O.
or engineer for inspection before
casting.
- To cast the pile cap after inspected by
contractor engineer, S.O. or engineer
on site.
- To cure to concrete.