400kv Protection
400kv Protection
400kv Protection
LINE-1
2-52 CB
LINE-2
MAIN BAY(3RD BAY) FOR FEEDER-2
1. IN THIS TWO BUSES ARE PRIOVIDED. 2. THESE TWO BUSES ARE INTER CONNECTED BY THREE BREAKERS. 3. THEY ARE DESIGNATED AS 1-52 CB, 2-52 CB, 3-52 CB. 4. LINE-1 IS CONNECTED IN BETWEEN 1-52 CB & 2-52 CB. 5. LINE-2 IS CONNECTED IN BETWEEN 3-52 CB & 2-52 CB. 6. LINE-1 HAVING TWO FEEDING PATHS i.e A. VIA BUS-1 & 1-52 CB B. VIA BUS-2, 3-52 CB & 2-52 CB 7. LINE-2 HAVING TWO FEEDING PATHS i.e A. VIA BUS-2 & 3-52 CB B. VIA BUS-1, 1-52 CB & 2-52 CB 8. FOR INTURUPTING LINE-1 THE 1-52CB AND 2-52CB IS TO BE TRIPPED. 9. FOR INTURUPTING LINE-2 THE 3-52CB & 2-52CB IS TO BE TRIPPED. 10. FOR ANY PROBLEM IN LINE-1 OR LINE-2 ALONG WITH MAIN BREAKER THE MIDDLE BREAKER(2-52 CB) MUST TRIP. 11. NORMALLY IN ALL TYPES OF BUSBAR CONFIGUARATIONS ONE BREAKER IS SUFFICIENT FOR ONE FEEDER. 12. HERE TWO FEEDERS ARE CONTROLED BY THREE BREAKERS. 13. SO THESE TWO FEEDERS CONTROLLED BY THREE CIRCUIT BREAKERS IT IS CALLED ONE & HALF BREAKER SYSTEM. 14. THE BAY BETWEEN BUS-1 & LINE-1 IS CALLED MAIN BAY FOR FEEDER-1. 15. THE BAY BETWEEN LINE-1 & LINE-2 IS CALLED TIE BAY FOR FEEDER-1 & 2. 16. THE BAY BETWEEN BUS-2 & LINE-2 IS CALLED MAIN BAY FOR FEEDER-2. 17. IN THIS SYSTEM FULL DIA MEANS 2 FEEDERS CONTROLLED BY 3 CBs. 18. HALF DIA MEANS 1 FEEDER CONTROLLED BY 2 CBs.
3-52 CB BUS-2
GOPALA KRISHNA PALEPU ADE/MRT/ T&C/400KV SS/ O/O CE/400KV / L&SS/ VS APTRANSCO, HYDERABAD
ADVANTAGES:
THREE CIRCUIT BREAKERS IN A FULL DIA ARE ALWAYS INSERVICE. IF MAIN CB PROBLEM / FOR PERIODICAL MAINTANENCE, DURING THAT PERIOD THE FEEDER IS FEEDING FROM TIE CB. NEED NOT REQUIRE TRANSFER THE FEEDER. IF TIE CB PROBLEM / FOR PERIODICAL MAINTANENCE, DURING THAT PERIOD THE FEEDER IS FEEDING FROM MAIN CB. EVEN IF BOTH MAIN BREAKERS UNDER TROUBLE, DURING THAT PERIOD ONE FEEDER IS WORKS AS INCOMING AND OTHER FEEDER IS WORKS AS OUTGOING VIA TIE CB. (WITHOUT INTERUPTION TO FEEDERS) IF BUSBAR-1 OPERATED / FOR PERIODICAL MAINTANENCE, ONLY THE MAIN BREAKERS CONNECTED TO BUSBAR-1 WILL TRIP. DURING THAT PERIOD THE FEEDERS CONNECTED TO BUS-1 ARE FEEDING VIA TIE CB FROM BUS-2. IF BUSBAR-2 OPERATED / FOR PERIODICAL MAINTANENCE, ONLY THE MAIN BREAKERS CONNECTED TO BUSBAR-2 WILL TRIP. DURING THAT PERIOD THE FEEDERS CONNECTED TO BUS-2 ARE FEEDING VIA TIE CB FROM BUS-1. IN THIS BUSBAR PROTECTION IS SIMPLE AND NEED NOT REQUIRE SELECTION OF ISOLATOR. IT IS MORE RELIABLE SYSTEM FOR OPERATION & MAINTANENCE POINT OF VIEW.
B.
1. 2. 3. 4.
DISADVANTAGES
CT CONNECTIONS & PROTECTION TRIP LOGICS ARE SOME WHAT COMPLICATED. COST TOWARDS CTs, CIRCUIT BREAKERS & PANELS ARE TO BE INCREASED DUE TO EXTRA BAY. THE COST COMPARISION TABLE SHOWN IN NEXT PRESENTATION. THE OPERATIONS FOR OPERATOR POINT OF VIEW IS LITTLE BIT COMPLICATED WHEN COMPARED TO CONVENTIONAL SYSTEM. SPACE OCUPATION FOR BAY IS MORE i.e COST OF LAND IS INCREASE.
COST COMPARISION BETWEEN CONVENTIONAL SYSTEM & ONE AND HALF BREAKER SYSTEM FOR FEEDER
S.No
1.
EQUIPMENT
CIRCUIT BREAKERS CURRENT TRANSFORMERS 3 CT METHOD
CONVENTIONAL SYSTEM
1 No
% INCREASE IN COST
50%
INCLUDES THE COST OF CT MARSHELLING BOXES. 3 Nos 1 No 4 Nos 5 Nos 6 Nos I SET 3 SETS 50% 100% 125% 200% 30% 2 Nos 2 Nos 3 Nos 3 Nos 2 SETS 100% 100% 200% 200% 30%
2.
3.
NORMALLY EXTRA PANEL IS TIE BAY PANEL. IT IS ARROUND 30% COST OF MAIN PANEL. BECAUSE IT IS NOT HAVING PROTECTION RELAYS( MM-1 & MM-2 AND OTHER RELAYS) . ONLY TIE CB TRIPPING RELAYS.
4.
1 No
3 Nos
50%
2 Nos
30%
5.
8 KM
30 KM
100%
20 KM
150%
SUBSTATION DESIGN/LAYOUT
(I-CONFIGUARATION)
FEEDER1 FEEDER3 FEEDER5 FEEDER7 FEEDER9 FEEDER11
BUS-1
BAY10 BAY13 BAY16 BAY1 BAY4 BAY7
BAY11
BAY14
BAY12
BAY15
BUS-2
FEEDER2
FEEDER4
FEEDER6
FEEDER8
FEEDER10
FEEDER12
BAY18
BAY3
BAY6
BAY9
BAY17
BAY2
BAY5
BAY8
SUBSTATION DESIGN/LAYOUT
(H-CONFIGUARATION)
FEEDER1
BAY2
FEEDER2
FEEDER5
BAY8
FEEDER6
FEEDER9
FEEDER10
BAY14
BAY13
BAY9
BUS-1
BUS-2
BAY10 BAY12 BAY16 BAY4 BAY18 BAY17 BAY6
BAY5
BAY11
FEEDER3
FEEDER4
FEEDER7
FEEDER8
FEEDER11
FEEDER12
BAY15
BAY1
BAY3
BAY7
CB 3 CTs METHOD CB 4 CTs METHOD CB 5 CTs METHOD CB 6 CTs METHOD CB 6 CTs METHOD CB 6 CTs METHOD
3-52CB
3P1
P2
P2
3-CT 3 P1 3-89A
P1
3 3
P2
2-89B 3-89T
LINE 1 T/F-1
3-52CB
3P1
P2
P2
3-CT 3 P1 3-89A
P2
2-89A 1-89L
P1
P2
2-52CB
2-89B 3-89T
LINE 1 T/F-1
3-52CB
3P1
P2
P2 P1
3 3-CT
3-89A
P2
2-52CB
2-89B 3-89T
3P1
P2
P2 P1
3 3T-CT
LINE 1 T/F-1
BUS-2 3-89
1A-CT 3 P1
3A-CT
1-52CB
P2
3 P1 3
P2 P1
P2
3-52CB
P1
1B-CT
3B-CT
1-89A 2A-CT
P2
3-89A 2B-CT
P1
2-89A 1-89L
2-52CB
P1
P2
2-89B 3-89T
T/F-1 LINE 1
1-52CB
P2
3-52CB
P1
1-CT
3-CT
P2 P1
1-89A 2A-CT
P2
3-89A 2B-CT
P1
2-89A 1-89L
P2
2-52CB
P1
P2
2-89B 3-89T
3 1L-CT P1
LINE 1
3T-CT
3 P1
P2
T/F-1
BUS-2
P2
3 1-CT
P1
3 3-CT
3-89
1-52CB
3-52CB
1-89A 2A-CT
P2
3-89A 2B-CT
P1
2-89A 1-89L
P2
2-52CB
P1
P2
2-89B 3-89T
3 1L-CT P1
LINE 1
3T-CT
3 P1
P2
T/F-1
CT DS CB
CT DS DS
CT CB
CT DS DS
CT CB
CT DS
CORE WISE APLICATION OF CTs IN ONE AND HALF CIRCUIT BREAKER SCHEME
PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)
CURRENT TRANSFORMER CONNECTIONS IN 3CT METHOD 1 CT 2 CT 3 CT BUSBAR-1 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CORE 1
( PS)
PROTECTION
CORE 2
( PS)
2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR FOR TRANSFORMER METERING & ENERGY METER FOR AT/F SPARE BUSBAR-2 CHECKUP PROTECTION (SPARE) BUSBAR-2 PROTECTION
CORE 3
( 0.5 / 0.2)
CORE 4
(0.5 / 0.2)
METERING & ENERGY METER FOR FEEDER 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR FOR FEEDER 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION FOR FEEDER
CORE 5
( PS)
CORE 6
( PS)
CURRENT TRANSFORMER CONNECTIONS IN 4CT METHOD 1- CT 2-BCT 2-ACT 3-CT CT SECONDARY CT SECONDARY SPARE SPARE CORE-1 CORE IS CORE IS
(PS)
CONNECTED TO BUSBAR-1 PROTECTION BUSBAR-1 CHECKUP PROTECTION (SPARE) CONNECTED TO BUSBAR-2 PROTECTION
CORE-2
(PS)
SPARE
SPARE
CORE-3
(0.5/0.2)
2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION
2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN PROTECTION
CORE-4
(PS)
CORE-5
(PS)
1-LCT
TEED PROT-1 (BAY 1&2) TEED PROT-2 (BAY 1&2)
2-CT
TEED PROT-1 (BAY 2&3) TEED PROT-2 (BAY 2&3)
3-TCT
TEED PROT-1 (BAY 2&3) TEED PROT-2 (BAY 2&3)
3-CT
BUSBAR-2 PROTECTION BUSBAR-2 CHECKUP PROTECTION (SPARE)
SPARE
TEED PROT-2 (BAY 1&2) AFTER LBB/BFR (1-52) TEED PROT-1 (BAY 1&2)
SPARE
TEED PROT-2 (BAY 1&2) AFTER LBB/BFR (2-52) TEED PROT-1 (BAY 1&2)
SPARE
TEED PROT-2 (BAY 2&3) AFTER LBB/BFR (3-52) TEED PROT-1 (BAY 2&3)
MAIN-1 PROTECTION
MAIN PROTECTION
1A-CT
2B-CT
2A-CT
3A-CT
3B-CT
BUSBAR-2
PROTECTION
2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER
2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER
BUSBAR-1 CHECKUP
PROTECTION
BUSBAR-2 CHECKUP
PROTECTION
(SPARE)
(SPARE)
CORE-3 (0.5/0.2)
SPARE
SPARE
1L-CT
TEED PROT-1 (BAY 1&2) TEED PROT-2 (BAY 1&2) METERING & ENERGY METER MAIN-2 PROTECTION MAIN-1 PROTECTION
2A-CT
SPARE SPARE
2B-CT
SPARE SPARE
3T-CT
TEED PROT-1 (BAY 2&3) TEED PROT-2 (BAY 2&3) METERING & ENERGY METER BACKUP PROTECTION MAIN PROTECTION
3-CT
BUSBAR-2 PROTECTION BUSBAR-2 CHECKUP
PROTECTION (SPARE)
SPARE
SPARE
SPARE
SPARE
BUS
3 3 3
3 1-52CB 2 1
P2
MAIN-2/BACKUP PROTECTION
MAIN-1 PROTECTION
3 3 3
1 2 3
3
1-89 1 2
3 3 3 3 3
P1
BF
FEEDER2 / LINE2 MAIN-1 BF VBB2 CVT VBB2 VL2 / VL1 OR VBB1 79 25 BUSBAR-2 87BB2 MAIN-2 CVT VL2 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)
FEEDER2 / LINE2 MAIN-1 BF VBB2 CVT VBB2 VL2 / VL1 OR VBB1 79 25 BUSBAR-2 87BB2 MAIN-2 CVT VL2 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)
87L
21M2
CVT
FEEDER2 / LINE2 MAIN-1 VL2 / VL1 OR VBB1 VBB2 BF MAIN-2 CVT VL2 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)
VBB2 CVT
79 25
BUSBAR-2 87BB2
87 TD2 LZ
CVT
BF
FEEDER2 / LINE2
.
BF VBB2 CVT VBB2 VL2 / VL1 OR VBB1 79 25 87 TD1 HZ BUSBAR-2 87BB2 87 TD2 LZ
87 TD2 LZ
CVT
BF
FEEDER2 / LINE2
.
BF VBB2 CVT VBB2 VL2 / VL1 OR VBB1 79 25 87 TD1 HZ BUSBAR-2 87BB2 87 TD2 LZ
CVT
VL1
BF
FEEDER2 / LINE2 79 CVT VL2 25 87 TD2 LZ BF 87 TD1 HZ BUSBAR-2 87BB2 MAIN-1 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE) MAIN-2
LINE PROTECTION
BUSBAR CHECKUP PROT
(CT CONNECTIONS IN 3CTs METHOD)
BUS-1 1-89
BUS-2 3-89
1-52CB
P2
3-52CB
P1
3 3 3 3 3
CORES 12 3 4 5 2-89A
1-89A 1-89L
. . .
LINE 1
1-CVT
P1
3 3 3 3 3 3
P2
METERING
MAIN-2 PROTECTION MAIN-1 PROTECTION
3 3 3
2-89B
T/F-1
TRANSFORMER PROTECTION
1
1-89
3-89
1-52CB
3-52CB CORES 2 3 4 5 6
P2
3 3 3 3 3 3
2-89A
CORES 2 3 4 5
P1
6
P22-89B
3-89A 3-89T
3 3 3
LINE 1
. .
T/F-1
MAIN-1 PROTECTION
3 3 3 3 3
BUS-1
BUS-2
3 3 3
3 3 3
1 2 3
3 2 1
LINE PROTECTION
BUSBAR CHECKUP PROT
(CT CONNECTIONS IN 4CTs METHOD)
BUS-1 1-89
BUS-2 3-89
1-52CB
P2
3-52CB
P1
3 3 3 3 3
1-89A 1-89L
. . .
LINE 1
1-CVT
P1
3 3 3 3 3
METERING
MAIN-2 PROTECTION MAIN-1 PROTECTION
3 3 3
T/F-1
TRANSFORMER PROTECTION
1
1-89
3-89
1-52CB
3-52CB
P2
CORES 4 3 2
P1
3 3 3 3 3
2-89A
3 3 3
P2
LINE 1
. .
T/F-1
MAIN-1 PROTECTION
3 3 3 3 3
BUS-1
BUS-2
3 3 3
3 3 3
1 2 3
3 2 1
BUS-1 1-89
LINE PROTECTION
(CT CONNECTIONS IN 5CTs METHOD)
BUS-2 3-89
1-52CB
P2
3-52CB
1-CT
3 3 3
CORES 1 2 3
P1
1-89A 1-89L
1L-CT
P1
1-CVT
LINE 1
3 3 3
3 3 3 3 3
P2
CORES 4 3 2
3 3
.
2-89A 2-52CB 3-89A
P1
3 3 3 3 3
5 4 3 2 CORES 2-CT 1 2-89B
P2
3-89T
T/F-1
1-89
3 3 3
3-89
1-52CB
3-52CB
P2
.
1-89A 1-89L 2-89A 2-52CB P1 5 2-CT 4 3 2 CORES
.
P2
3 3 3
2-89B
3-CT
3-89A 3-89T
P1
LV CT
3 3 3 3 3
P2
3T-CT
1-CVT
P1
LINE 1
T/F-1
BUS-1
T/F PROTECTION
3
BUS-2
3 3
3 3 3
CORES 3 4 5 1 CORES 2 3 4 5
3 3 3 3 3
3 3 3
3 CT METHOD
4 CT METHOD
6 CT (S) METHOD
5 CT METHOD
6 CT (T1) METHOD
6 CT (T2) METHOD
1 CT FOR BUS-1 1B CT FOR BUS-1 1 CT FOR BUS-1 & & & 3 CT FOR BUS-2 3B CT FOR BUS-2 3 CT FOR BUS-2
1 CT & 2B CT 1A CT & 2B CT 1L CT
ABOVE CT SECONDARIES ARE CONNECTED PARALLEL FOR FEEDER-1 BELOW CT SECONDARIES ARE CONNECTED PARALLEL FOR FEEDER-2 3 CT & 2 CT
STUB-1 & STUB-2 PROTECTION FOR LINE & AT/F
3 CT & 2A CT
STUB-1 & STUB-2 PROTECTION FOR LINE & AT/F
3A CT & 2A CT
STUB-1 & STUB-2 PROTECTION FOR LINE & ICT
3L CT
TEED-1 & TEED-2 PROTECTION FOR LINE & AT/F
3L CT
TEED-1 & TEED-2 PROTECTION FOR LINE & AT/F
3L CT
TEED-1 & TEED-2 PROTECTION FOR LINE & AT/F
STUB-1 & STUB-2 PROTECTION IS A NORMALLY INBUILT PROTECTION FOR MAIN-1 & MAIN-2 RELAYS IN CASE OF LATEST NUMERICAL RELAYS. STUB PROTECTION WORKS WHEN LINE ISOLATOR OPEN CONDITION ONLY.
TEED1 IS NORMALLY HIGH IMPEDENCE DIFFERENTIAL RELAY & TEED-2 IS NORMALLY LOW IMPEDENCE DIFFERENTIAL RELAY THESE ARE NOT INBUILT IN MAIN-1 & MAIN-2 RELAYS
BLIND ZONE
A FAULT BETWEEN CIRCUIT BREAKERS AND CT (END FAULT) MAY THEN STILL BE FED FROM ONE SIDE EVEN WHEN THE BREAKER HAS BEEN OPENED. CONSEQUENTLY, FINAL FAULT CLEARING BY CASCADED TRIPPING HAS TO BE ACCEPTED IN THIS CASE. THIS SITUATION LBB/BFR OPERATES AND TIME TAKEN TO CLEAR FAULT IS ABOUT 300 mSECs. THIS IS BLIND ZONE AREA MINIMUM CTs METHOD. REDUCING THE COST OF CTs TIE CB BLIND ZONE AREA IS TAKEN CARE. MAIN CB & TIE CB BLIND ZONE AREA IS TAKEN CARE BLIND ZONE FOR MAIN CB & TIE CB TIE CB BLIND ZONE AREA IS TAKEN CARE MAIN CB & TIE CB BLIND ZONE AREA IS TAKEN CARE
ADVANTAGES
WHEN THE FAULT IS TAKEN PLACE BETWEEN THE MAIN CB, TIE CB & LINE ISOLATOR DURING SERVICE ONLY DISTANCE SCHEME SHOULD TAKE CARE
WHEN THE FAULT IS TAKEN PLACE BETWEEN THE MAIN CB, TIE CB & LINE ISOLATOR DURING SERVICE ONLY TEED PROTECTION IN ADDITION TO DISTANCE SCHEME SHOULD TAKE CARE
P1 P1 P2
P2
CLASS PS PS
SECONDARY CONNECTIONS CURRENT RATING : 1A 2000/ 1A 1S1 1S3 1000/ 1A 1S1 1S2 1S2 1S3 2S1 2S2 2S2 2S3 3S1 3S3 500/ 1A __
CORE-4 CORE-5
PS PS
5S1 5S3
2S1 2S23 2S
METERING
3S1 3S4
3S1 3S2
1 1 S1 1SS2 3
1 5S S2 5 S3 5 S4 5
__
3 3
3 3
U U
U
3S1 3S2 3S3 3S4
AT/F 3-CT
500A
2-CT 2-52CB
P1 2000-1000-500/1A
1000A 1000A
2000-1000-500/1A
1500A
3-52CB
3 3
2.0A
S1
0A 0A
S1
S2 S3
S2
1.0A
0A
1.0A
1.0A
1.0A 1.0A
3
3.0A
P2
P1 S3
P2 S1
P1
P2 S1
AT/F 3-CT
500A
2-CT 2-52CB
P1 2000-1000-500/1A
0A 0A
2000-1000-500/1A
0500A
3-52CB
3 3
0A
S1
1.0A 1.0A
S2
S1 S3
S2
0A
0A 0A 1.0A
1.0A
0A
0A
0A 1.0A 0A 0A
1.0A 1.0A
3
1.0A
P2
P1 S3
P2 S1
P1
P2 S1
AT/F 3-CT
500A
2-CT 2-52CB
P1 2000-1000-500/1A
500A 500A
2000-1000-500/1A
0A
3-52CB
3 3
1.0A
S1
1.5A 1.5A
S1
S2 S3
S2
0.5A
0.5A 1.0A 0A
1.5A
0.5A
0.5A
1.0A 1.0A
3
0A
P2
P1 S3
P2 S1
P1
P2 S1
500A
3-CT
2000-1000-500/1A
750A
3-52CB
3 3
0.25A
S1
0.75A 0.75A
S1
S3 S3
S3
0.25A
0.75A
0.25A
0.25A
1.0A 0.5A
3
0.75A
P2
P1 S3
P2 S1
P1
P2 S1
AT/F 2-ACT
2000-1000-500/1A
1000A
500A
2-BCT 2-52CB
1000A
3-CT
1500A
2000-1000-500/1A 2000-1000-500/1A
3-52CB
3
1.0A
S1
0A 0A
S1
S3
S2
3.0A
0A
1.0A
1.0A
3
3.0A
P2
P1 S3
P2
P1 S2
P1
P2 S1
P1
P2 S1
AT/F 2-ACT
2000-1000-500/1A
0A
500A
2-BCT 2-52CB
0A
3-CT
500A
2000-1000-500/1A 2000-1000-500/1A
3-52CB
3
0A
S1
1.0A 1.0A
S1
S3
S2
0A 0A 0A
1.0A
1.0A
0A 0A
0A
0A 1.0A 0A
1.0A 1.0A
3
1.0A
P2
P1 S3
P2
P1 S2
P1
P2 S1
P1
P2 S1
AT/F 2-ACT
2000-1000-500/1A
500A
500A
2-BCT 2-52CB
500A
3-CT
0A
2000-1000-500/1A 2000-1000-500/1A
3-52CB
3
0.5A
S1
1.5A 1.5A
S1
S3
0.5A
S2
1.0A 1.0A
0A
1.5A
0.5A 1.0A
0.5A
0.5A 0A 1.0A
1.0A 1.0A
3
0A
P2
P1 S3
P2
P1 S2
P1
P2 S1
P1
P2 S1
LINE-2 2-ACT
2000-1000-500/1A
250A
1000A
2-BCT 2-52CB
250A
3-CT
750A
2000-1000-500/1A 2000-1000-500/1A
3-52CB
3
0.25A
S1
0.75A 0.75A
S1
S3
S3
0.75A
0.75A
0.75A
0.25A 0.25A
0.5A 1.0A
P2
P1 S3
P2
P1 S3
P1
P2 S1
P1
P2 S1
TRIP COIL-1 1-52CB TRIP COIL-2 BUS-1 86 ABB -B REL521 MTR/ MAIN HSTR -1 ABB REL316 MAIN-2
TRIP COIL-1 3-52CB TRIP COIL-2 BUS-2 ABB RET316 MAIN-2 86-B MTR/ HSTR
86-A : GROUP-A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 86-B : GROUP-B MASTER TRIP RELAY / HIGH SPEED TRIP RELAY
REL 521
ACTIVE START TRIP
INITIATE TIE CB GR-A 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) START MAIN CB AUTO RECLOSURE START TIE CB AUTO RECLOSURE
DISPLAY
CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION
REL 316
ACTIVE START TRIP
INITIATE MAIN CB GR-B 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) INITIATE TIE CB GR-B 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) START MAIN CB AUTO RECLOSURE START TIE CB AUTO RECLOSURE
DISPLAY
INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION
AUTO RECLOSURE
CB CLOSE CONDITION. TIME LAPSED MORE THAN RECLAIM TIME. OPERATING PRESSURE OF CB SUITABLE FOR AUTORECLOSURE OPERATION. DC SUPPLY TO AUTORECLOSURE SHOULD BE AVAILABLE. PREPARE 3-PH TRIP RELAY SHOULD BE RELEASED CONDITION. NO BLOCKING SIGNAL TO AUTORECLOSURE RELAY. POLE DISTURBANCE RELAY TIME SHOULD BE MORE THAN TWICE OF DEAD TIME OF AUTO RECLOSURE. CARRIER FAIL SIGNAL SHOULD NOT COME AT BOTH ENDS. CARRIER SWITCH SHOULD BE IN SERVICE CONDITION. SINGLE PHASE & ZONE-1 FAULT ONLY. TRIP MAIN CB SINGLE POLE. TRIP TIE CB SINGLE POLE. CLOSE MAIN CB AFTER DEAD TIME. IF A/R SUCCESS FOR MAIN CB THEN AFTER SUPPLEMENTARY TIME DELAY CLOSE TIE CB.(NORMALLY SUPPLEMENTARY TIME DELAY IS DEAD TIME) IF A/R UNSUCCESS THEN TRIP MAIN & TIE CBs. IF MAIN CB OPEN CONDITION, THEN NO SUPPLEMENTARY DELAY TIME FOR TIE A/R. IT WILL OPERATE ITs OWN DEAD TIME.