CO S ALR 87099931 JPN Generate Price Versus Cost Estimate
CO S ALR 87099931 JPN Generate Price Versus Cost Estimate
CO S ALR 87099931 JPN Generate Price Versus Cost Estimate
Purpose The standard report Price versus Cost Estimate (S_ALR_87099931) is used to check the amount of the variance between a new cost estimate and the existing standard price, and thereby to see how releasing the cost estimate for all materials with price control S would affect the value of the total inventory. This report is typically executed before the standard price is updated with the cost estimate values calculated in a costing run. Note that the price control is selected as standard price (S) to eliminate materials valuated at moving average price (V) as these are affected by standard cost estimate release. In addition, you can define exceptions to emphasize critical variances, so that materials, with calculated variance or anticipated revaluation amount exceeding predefined threshold values, will be highlighted with traffic lights symbols. Trigger Perform this transaction when you need to generate price versus Cost Estimate Report. Menu Path Use the following SAP Easy Access menu path(s) to begin this transaction: Accounting > Controlling > Product Cost Controlling > Product Cost Planning > Information System > Summarized Analysis > Analyze Costing Run > S_ALR_87099931 - Price vs Cost Estimate
1/26
Work Instruction
Screen Flow
2/26
Work Instruction
Procedure 1. In SAP, start the transaction using the menu path or transaction code. SAP Easy Access
2. Double-click the Accounting node 3. Double-click the Controlling node 5. Double-click the Product Cost Planning node 6. Double-click the Information System node
Wednesday, July 15, 2009 CO_S_ALR_87099931_JPN_Generate Price versus Cost Estimate.udc
. . . . .
3/26
Work Instruction
7. Double-click the Summarized Analysis node 8. Double-click the Analyze Costing Run node .
9. Double-click the S_ALR_87099931 - Price vs Cost Estimate node . You can also enter S_ALR_87099931 in the Command field and click Enter transaction. Analyze/Compare Material Cost Estimates to access this
4/26
Work Instruction
10 Click the Selections Chosen button . 11 Click the Costing Run 1 edit field .
. .
5/26
Work Instruction
12 As required, complete/review the following fields: . Refers to R/O/C the Costing Run 1 when specifying a compariso n value. In Product Cost Planning, costing runs are used to cost materials based on planning data. Field Example: MMKH6001 R Costing Run 1 Name under which the costing run is carried out. 13 Click the Costing Run edit field . . Description
Work Instruction
A tool R/O/C that provides the opportuni ty to cost multiple materials at the same time. In Product Cost Planning, costing runs are used to cost materials based on planning data. This type of costing run is based on a userdefined name and a date. In Actual Costing/M aterial Ledger, costing runs are
Wednesday, July 15, 2009
Description
7/26
Work Instruction
used to cost materials with actual data. This type of costing run is based on a costing run profile and a period. Field Example: MK6001_2 R Costing Run 15 Click the Costing Date edit field . .
16 As required, complete/review the following fields: . Date from R/O/C which a costing run is valid. Field Example: 14.05.2008 Description
8/26
Work Instruction
R Costing Date This is the date from which a costing run is valid. This date has two uses:
9/26
Work Instruction
as a default value for scheduling in the cost estimate as a criterion for reorganizing the costing runs 17 Click the Costing Date edit field . .
18 As required, complete/review the following fields: . Date from R/O/C which a costing run is valid. Field Example: 10.06.2008 R Costing Date Alternatively, you may click on the possible entries icon beside the Costing Run field to choose from a list of existing costing runs in the system. When you select one costing run from the list, this will automatically copy the name of the costing run to the Costing Run field and its corresponding costing date to the Costing Date field. 19 Click the Plant edit field . . Description
20 As required, complete/review the following fields: . A plant is R/O/C an organizati onal unit for Description
10/26
Work Instruction
dividing an enterprise according to productio n, procurem ent, maintena nce, and materials planning. It is a place where materials are produced, or goods and services are provided. Field Example: 6001 R Plant This key uniquely identifies a plant in the system. A plant is a place where materials are produced, or goods and services are provided. These fields work in connection with the Display Positive and
11/26
Work Instruction
If this checkbox is selected, all cost estimates that reach the given absolute threshold value(s) are flagged. 21 Click the Only Display Exceptions check box . .
12/26
Work Instruction
If this indicator is selected, only the cost estimates for which yellow and red traffic lights were set based on the defined exceptions are displayed. Notice that the system defaults the Cost Component View field in the Output area to 1 Cost of GoodsManufactured. This field indicates which cost components are displayed and passed on to other areas of the SAP System. You may choose from the following existing views:
Review the data displayed on the screen. Note: It is possible to manipulate the data displayed by selecting any one of the following icons: - View details of a selected vendor account. This will require you to position your cursor on an item in the report before you click on the button.
13/26
Work Instruction
- Set filter.
- Export the data to a local file in one of several formats that you can choose from.
14/26
Work Instruction
- Change layout.
- Choose layout.
- Save layout. You may also click on the following buttons to view details reports on the following: - Cost Estimates - Multilevel BOM - Cost Components Analyze/Compare Material Cost Estimates
15/26
Work Instruction
16/26
Work Instruction
. .
24 Click the Detailed Report: Cost Estimate button . This screen is divided into three areas:
Overview of the Cost Estimate (the top half of the right side of the screen) Detailed Lists (bottom half of the right side of the screen), hide/show this
and
respectively
Costing Structure (left side of the screen), hide show this area using the
buttons
and
respectively.
This screen area also contains tab pages which provide the following cost estimate data: Costs Contains the calculated costs. The costs displayed are based on the costing lot size. However, you can also see the costs based on the price unit in the material master, or based on a figure you have already defined, by selecting a cost base from the list field. Note that if a cost base is changed, all costing items are adjusted proportionally, including those that contain fixed costs (such as setup costs). The button displays the log containing the messages for the material.
17/26
Work Instruction
The The
button displays the itemization. button displays the cost component split.
The Partner button displays the partner cost component split with cost component groups. The button displays the costed multilevel BOM (displayed in the screen area costing structure).
18/26
Work Instruction
Costing data Contains the costing variant and costing version used in the cost estimate.
19/26
Work Instruction
Dates Contains the costing dates used for the cost estimate.
20/26
Work Instruction
Qty Struct. Contains the quantity structure data used for the cost estimate.
21/26
Work Instruction
Valuation Contains the following: Currency in which the costing results are displayed Costing sheet, overhead key, and template used to calculate overhead
22/26
Work Instruction
History Contains information on who created, marked, and released the cost estimated.
23/26
Work Instruction
24/26
Work Instruction
Result You have successfully generated a Price versus Cost Estimate report.
25/26
Work Instruction
Scenario Instructions In this simulation you are required to: Generate a Price versus Cost Estimate Report on SAP ECC 6.0. Required Data This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise. 6001 10.06.2008 14.05.2008 MK6001_2 Field Plant Costing Date 2 Costing Date 1 Costing Run 2 MMKH6001 Costing Run 1 Value