Field Test Plan

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

FIELD TEST PLAN

BEFORE START OF INSTALLATION


Sl No Component/Oper ation Character istics Checked Catego ry Type of chec k Ext ent of che ck Referen ce Docume nt Acceptan ce Norms Format of Record Agen cy Remarks

01

Soil Thermal Resistivity Test

Thermal Resistivity

Electr ical

IEEE Std 4421981

Before And After Installation Of Each Cable Length 01 10 kv DC Test To Electrica for 1 minute on demonstr l ate the outer Sheath
integrity of the cable outersheath

Clause 5 IEC 60229

IEC 60229

Before And After Installation of Joints And Terminations 01 10 KV DC Test for 1 minute on outer sheath before and after joints and terminations. Cable continuity Test/low resistance measurement test
To demonstrate the integrity of outersheath of the cable with joints and terminations

Electrical

Clause 5 IEC 60229

IEC 60229

02

Electrical

03

Absence of cross phasing

Electrical

04

Insulation resistance test of both sections of cables to be jointed.

to measure Electrical the ohmmic value of the insulation under a direct voltage of great stability

Test Before Commissioning 01 10 KV DC test for 1 minutes on outer sheath of completed phase Conductor resistance test of each completed circuit. Capacitance test Cross bondings/single point bonding/Both end bonding Tan delta Test of each completed circuit. Electrical Clause 5 IEC 60229 IEC 60229

02

Electrical

Iec 62067 Clause 10.5

Iec 62067

03 04

Electrical Electrical

62067(10.10)

Iec 62067

05

Electrical

62067 Iec Clause(12.4.5) 62067

06

Ensuring with clients for minimum settings of their Protections relays

Electrical

07

Earth resistance test of each earth pit Equipt.-megger Final Commissioning Test

Electrical

01

The installation shall be tested with AC voltage at power frequency voltage equals to 1.7Uo for 1 hour between each conductor and metallic sheath OR AC system voltage Uo for 24 hours to keep the cable on idle charge with minimum protection setting to protect the cable in 24 hours.

Electrical

02

Checking of performance of LAs at following nominal discharge currents: a) 100 Amps with 8/20 micro sec wave shape. b) 10KA with 8/20 micro sec wave shape.

Electrical

03

Ensuring with clients for normal required settings of their protection relays Checks of temporary reinstatements of roadways for settlement and after the subsidence has ceased, permanent reinstatement be completed.

Electrical

04

Electrical

In addition to the above, we have to prepare for the following additional performance test which are being demanded by the clients
01

The desired performance test shall comprise keeping the commissioned cable system energized format least for 7 consecutive days on continuous basis with the loads available at the time of carrying out the test. In case of failure, after due rectification, it shall be restarted for 7 seven continuous days. Still if it fails, the cable system is declared not suitable for any operation and shall be declared dead.

Electrical

02

If the facility at our works is available, it is ok. If not, we may have to equip ourselves to carry out the short circuit on metal sheath of cable to ensure that metal sheath withstands the specified short circuit current against each contract. We need to evolve suitable procedure or test methodology for testing joint bays and manholes for withstanding a live loads of 30T

Electrical

03

Electrical

04

We need to evolve suitable procedure or test methodology for Joint Bay earthing for it`s effectiveness to discharge the fault currents.

Electrical

05

CORRECT preparation of AS-BUILT drawings which have a greater influence of functional guarantees extended by us in terms of retention amounts, bank guarantees etc

Electrical

You might also like