Field Test Plan
Field Test Plan
Field Test Plan
01
Thermal Resistivity
Electr ical
Before And After Installation Of Each Cable Length 01 10 kv DC Test To Electrica for 1 minute on demonstr l ate the outer Sheath
integrity of the cable outersheath
IEC 60229
Before And After Installation of Joints And Terminations 01 10 KV DC Test for 1 minute on outer sheath before and after joints and terminations. Cable continuity Test/low resistance measurement test
To demonstrate the integrity of outersheath of the cable with joints and terminations
Electrical
IEC 60229
02
Electrical
03
Electrical
04
to measure Electrical the ohmmic value of the insulation under a direct voltage of great stability
Test Before Commissioning 01 10 KV DC test for 1 minutes on outer sheath of completed phase Conductor resistance test of each completed circuit. Capacitance test Cross bondings/single point bonding/Both end bonding Tan delta Test of each completed circuit. Electrical Clause 5 IEC 60229 IEC 60229
02
Electrical
Iec 62067
03 04
Electrical Electrical
62067(10.10)
Iec 62067
05
Electrical
06
Electrical
07
Earth resistance test of each earth pit Equipt.-megger Final Commissioning Test
Electrical
01
The installation shall be tested with AC voltage at power frequency voltage equals to 1.7Uo for 1 hour between each conductor and metallic sheath OR AC system voltage Uo for 24 hours to keep the cable on idle charge with minimum protection setting to protect the cable in 24 hours.
Electrical
02
Checking of performance of LAs at following nominal discharge currents: a) 100 Amps with 8/20 micro sec wave shape. b) 10KA with 8/20 micro sec wave shape.
Electrical
03
Ensuring with clients for normal required settings of their protection relays Checks of temporary reinstatements of roadways for settlement and after the subsidence has ceased, permanent reinstatement be completed.
Electrical
04
Electrical
In addition to the above, we have to prepare for the following additional performance test which are being demanded by the clients
01
The desired performance test shall comprise keeping the commissioned cable system energized format least for 7 consecutive days on continuous basis with the loads available at the time of carrying out the test. In case of failure, after due rectification, it shall be restarted for 7 seven continuous days. Still if it fails, the cable system is declared not suitable for any operation and shall be declared dead.
Electrical
02
If the facility at our works is available, it is ok. If not, we may have to equip ourselves to carry out the short circuit on metal sheath of cable to ensure that metal sheath withstands the specified short circuit current against each contract. We need to evolve suitable procedure or test methodology for testing joint bays and manholes for withstanding a live loads of 30T
Electrical
03
Electrical
04
We need to evolve suitable procedure or test methodology for Joint Bay earthing for it`s effectiveness to discharge the fault currents.
Electrical
05
CORRECT preparation of AS-BUILT drawings which have a greater influence of functional guarantees extended by us in terms of retention amounts, bank guarantees etc
Electrical