Petition 3 of 2015
Petition 3 of 2015
Petition 3 of 2015
3 of 2015
The present Petition has been filed by Nahar Spinning Mills Ltd.
The Petitioner has submitted that it has a Large Supply
connection at Jitwal Kalan, near Malerkotla, in Punjab, with
Account No. L38-KK01-00003, having sanctioned connected load
1
The Petitioner has submitted that ToD Tariff was also made
applicable during the year 2013-14 as per para 5.3.8 of the Tariff
Order for the year 2013-14 and open access charges were
determined in para 6.10 of the said Tariff Order. ToD tariff was
adopted by PSPCL vide CC no. 24/2013. However, at that time,
the rebate of 1/- per unit was allowed only for night consumption
during 10 PM of the day to 6 AM of the next day. PSPCL, while
implementing these instructions, did not allow this rebate of 1/per unit on the power brought by the Petitioner under open
2
Term
Open
Access
procedure
approved
by
the
Commission (para 2.1 (A) (vii) and in para (2) of the Undertaking
to be given by the Open Access Consumer for obtaining
permission). Further, para 7.3.15 of the Tariff Order for FY 201415 provides that consumers opting for ToD tariff will be allowed to
consume power up to Contract Demand. In line with this
provision, SLDC has amended the approval letter and NOC for
open access to this extent. Thus, under the ToD regime, the
consumers are allowed to draw power up to Contract Demand
during Peak Load Period including power drawn from PSPCL and
under open access.
237064
units
of
open
access
power
and
4.
It has also been submitted that as per paras 7.6.2 and 7.6.3 of
the Tariff Order for FY 2014-15 and as per CC No. 49 of 2014, a
rebate of 1 per unit is admissible on tariff to all consumers,
except Agriculture and Railway Traction for the consumption
above the threshold limit/target consumption. However, till date,
PSPCL has not informed the threshold consumption to the
Petitioner. If it would have been done, the Petitioner would have
planned its sourcing of power from PSPCL in advance and it
would have helped in achieving the aim/goal for which the rebate
was designed i.e. maximising the consumption of PSPCL power,
reducing the back down of its thermal plants/surrender of central
sector power and PSPCL would have managed its finances in a
better way.
5.
The Petitioner has prayed that the Commission may kindly issue
directions to PSPCL as under:
1.
2.
3.
4.
5.
6.
7.
(ii)
(iii)
(iv)
(ii)
(iii)
10
(iv)
(v)
The Petitioner has no ground to challenge its levy being just and
appropriate. The Petitioner has himself opted to be charged as
per ToD tariff.
Power from PSPCL and open access equally affect the maximum
demand on the system during peak load hours and restriction on
its use through levy of charges is in the interest of stability of
transmission system and to facilitate power supply to lakhs of
DS/NRS consumers including Hospitals, continuous power
industries, apart from electric traction trains.
PSPCL has further submitted that it is ready for issue of monthly
bills on the basis of recorded monthly power factor. In order to
resolve this dispute, PSPCL has already started converting the
open access units in MWh into MVAh by application of recorded
monthly power factor. During the month of February, 2015, the
billing has been made by PSPCL on the basis of this method as
requested in the petition by the Petitioner. PSPCL is also ready to
make suitable adjustments pertaining to bills of October and
November, 2014, in the bills being issued during March, 2015.
PSPCL has further submitted that the suggestion that actual
power factor be considered with 4 digit format instead of 2 digit
format may lead to unnecessary disputes in future. However, the
Commission may issue any instructions, if felt necessary, which
shall be abided by PSPCL.
PSPCL further submitted that updation of billing software for
calculation of threshold limit/target is under process.
With regard to charging of 3 per kVAh on power purchased
through open access, PSPCL has also submitted as below:
(i)
The
plea
taken
by
the
Petitioner
is
wrong
and
(iv)
9.
The Petitioner in the rejoinder has denied and disputed all the
averments made by the PSPCL in its reply, save and except for
what has been expressly admitted to herein after and any
omission on the part of the Petitioner should not be construed as
an admission of the same by the Petitioner.
The Petitioner has submitted that it totally relies upon the
averments made therein in the Petition and has reiterated the
same to be read as part and parcel of the rejoinder. The
Petitioner has submitted that reply of PSPCL (paras 1 to 3) is
vague, evasive and does not address the issues raised in the
Petition on merit.
The Petitioner has submitted that, in fact, nowhere in its Petition
the levy of 3 per kVAh over and above the normal tariff on the
power consumed from PSPCL has been challenged, but has only
requested for levying this ToD charge on power bought in by the
Petitioner under open access, as per scheme of ToD tariff
approved by the Commission. The Petitioner has further
mentioned in the rejoinder that it is also wrong to state on the part
of PSPCL that ToD tariff is beneficial only to the Petitioner,
whereas the fact is that it is equally beneficial to the PSPCL, as it
flattens the load curve of PSPCL and saves the PSPCL from
14
11.
18
(ii)
(iii)
(iv)
(v)
The plea taken by the Petitioner that power drawn through open
access saves the respondent from backing down its thermal
plants is wrong, rather power drawn through open access
19
20
23
PSPCL
vide
its
memo
dated
11.05.2015
(received
on
(iii)
(iv)
(vi)
16.
Charges,
Wheeling
Charges,
Cross
Subsidy
Sd/(Romila Dubey)
Chairperson
Chandigarh
Dated: 20.05.2015
30