Govt. Degree College Kuppam Est.1030.00 Lakhs
Govt. Degree College Kuppam Est.1030.00 Lakhs
Govt. Degree College Kuppam Est.1030.00 Lakhs
NAME OF THE WORK :- CONSTRUCTION OF PARAMANENT GOVT. POLYTECHNIC COLLEGE FOR WOMEN
JOGIPET (V), ANDOLE (M) IN MEDAK DIST
Construction of Septic Tank of size 8.90 x 2.70 x 2.10Mt (Clear Size) and
1985 )
Sl.No Description of work
1
No.
Measurements
Qty
Septic Tank
for Soak pit
1
1
X
X
1
1
10.20
3.00
3.90
3.00
2.20
1.20
For bottom of
septic tank
10.20
3.90
0.10
8.90
2.70
0.08
1.92
2.00 Cum
6509.35 1Cum
Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard blasted Granite stones from
approved quarry including cost and conveyance of all materials like Granite stones, cement, sand, water,
etc., to site sales & other taxes on all materials, all operational, incidental, and labour charges such as
cutting stones to required size and shape, mixing of cement mortar, constructing masonry, curing etc.,
complete but excluding seigniorage charges for finished item of work for foundation and basement (APSS
No. 601 & 615)
Alround
1
X
1
25.00 0.60
1.20
18.00
X
25.00
0.45
1.35
15.19
Total
33.19
Say
34.00 Cum
2680.45 Cum
Construction of 50.8mm thick RCM Baffle wall with 2.267 Kg steel and rabit wire mesh in CM (1:3) prop: with
fine rendering in neat cement in septic tank including cost and convenyance of all materials to site,
seigonarage charges sales and othe taxes on all materials , and all labour charges etc., complete for finished
item of work.
For baffle walls
3.00 -
0.6
3.60 Sqmt
286.15 1Sqmt
Construction of Perforated Dry Brick Masonry without using CM and keeping vertical dry joints of 15 to 20mm
as directed by the Engineer in Charge including cost and conveyance of all amterials to site seignorage
charges, sales and other taxes, all labour charges etc., complete item of work for Soak Pit.
1
S Tank
3388.15 1Cum
Plain Cement Concrete corresponding to M15 grade as per IS 456 equivalent to (1:2:4) proportion nominal
mix (cement: fine aggregate: Coarse aggregate) using 20mm size Hard Blasted Granite (IS383, 1970)
Machine Crushed graded metal from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing, laying, curing concrete, etc., complete but
excluding seigniorage charges for finished item of work (APSS No. 402)
Per
3.98
4.00 Cum
Say
Rate
87.52 Cum
10.80
98.32
100.00 Cum
122.45 1Cum
Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal
mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal
from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc. to site, including sales & other taxes on all materials, all operational, incidental, and labour
charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete but excluding seigniorage chargesfor finished item of work for
Foundations and Flooring Bed (APSS No. 402)
For bottom of
septic tank
4
Unit
L
B
D
Earth work excavation and depositing on bank (Manual means) with initial lead of 10m and initial lift of 3m in
Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational
incidental labour charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire
charges of T & P, labour charges etc., complete for finished item of work excluding seignerage charges and
dewatering charges etc., complete for Septic tank soak pit and sump.(APSS No. 308)
Say
3
3.00
0.12
1.50
2.16 Cum
P No 1
OR Say
2.25 Cum
3977.47 Cum
Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20mm thick (average)
mixed with water proofing compound manufactured by reputed manufacturers as approved by Engineer-incharge at 1Kg/bag of cement, laid over roof slab when it is green, finished smooth with a floating coat of neat
cement and thread lining at regular intervals of 45cmx45cm including cost and conveyance of all materials
like cement, sand, water proofing compound, water etc., to site, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar, laying, rounding off at junctions of wall and
slab, rendering smooth with thread lining, curing, lift charges, etc., complete but excluding seigniorage
charges for finished item of work (APSS No. 901 & 903).
Long walls
Short walls
Bottom of septic
tank
1
1
1
X
X
X
2
4
1
8.90
2.70
8.90
2.20
2.20
2.70 Say
328.75 1Sqmt
Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard
blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum
quantity of 350 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like
cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including
centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members
etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for finished item of work (APSS
No. 402 & 403) for 125 mm thick slab
125mm thick slab
9.90
3.60 Say
39.16
23.76
24.03
86.95
87.00 Sqmt
35.64
36.00 Sqmt
1066.20 1Sqmt
Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8mm to
40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of
approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs
and drawings including cost and conveyance of bars from approved sources to site of work, including cost
and conveyance of binding wire, cover blocks, chairs, overlaps, spacers, dowels, wastage etc., and all
operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and sales
& other taxes,on cost of all materials complete for finished item of work (APSS No.126)
36*0.125*110 =
1
X
1
0.5
0.50 MT
58571.30
1 MT
495 Kgs
10 Supply and fixing of 100 mm dia CI Vent pipe of 3 mts length double socket fitted with AC cowl and mosquito
proof wire mesh including cost and conveyance of all materials to site and labour charges for placing and
fixing in position etc., complete for finished item of work.
11
1
X
1
1 No.
2561.60 Each
Supply & Fixing of 22" dia RCC Cover for manhole with nominal reinforecement 3" thick with hooks for lfifting
including cost and conveyance of all materials, labour charges etc., complete for finished tiem of work
1
X
2
2 Nos.
803.70 Each
12 Supply and Fixing of CI Steps for Septic Tank / Manhole complete for finished item of work including cost and
conveyance of all materials to site, all labour charges, sales and other taxes on all materials etc., complete
for finished item of work.
1
5 Nos.
70.70 Each
TOTAL
#REF!
S Tank
APEWIDC, MADANAPALLI
APEWIDC, KUPPAM
P No 2
Superintending Engineer
APEWIDC, KADAPA
S Tank
P No 3
CONSTRUCTIONOFSEPTICTANK
12245.00
13553.00
13019.00
91135.00
1030.00
S Tank
P No 4
8949.00
28601.00
38383.00
29286.00
2562.00
1607.00
354.00
240724.00
S Tank
P No 5
S Tank
P No 6
Section
Sub - Division
Division
Circle
ABOUT ESTIMATE
Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M)
CHITTOOR District
Asst. Engineer (APEWIDC)
Section : KUPPAM
Dy. Executive Engineer (APEWIDC)
Sub-Division : CHITTOOR
Executive Engineer (APEWIDC)
Division : CHITTOOR
Superintending Engineer (APEWIDC)
Circle : KADAPA
WORKING ESTIMATE
NAME OF THE WORK: C/O HOSTEL BUILDING AT APSWRSC(B), WARDANNAPET AT MADIKONDA(V) OF HANAMKO
WARANGAL DIST.
SUB ESTIMATE: OLD DORMITARY
SNo
Description of work
No
L
B
D Qty
Rate
1 Earth work excavation and depositing on bank with initial lead of 10m and initial lift
of 3m in Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils
( SS 20-B) including all operational incidental labour charges such as shoring,
strutting, sheeting, planking and dewatering including cost of hire charges of T & P,
labour charges etc., complete for finished item of work including seignerage charges
excluding dewatering charges etc., complete for Foundation of Building.(APSS No.
308)
MB. No.326/A/MD, Pg. No.1 to 4
GF-AHDC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Page 8 of 517
2.10
2.20
2.20
2.20
2.20
2.20
2.20
2.10
2.35
2.60
1.60
1.60
2.60
2.35
2.35
2.35
2.35
2.35
2.35
2.35
2.35
2.35
3.45
3.45
2.90
2.90
3.45
3.45
2.50
2.50
2.35
2.35
2.35
2.35
2.35
2.35
2.45
2.35
1.95
1.95
2.35
2.45
2.35
2.35
1.75
2.10
2.20
2.20
2.20
2.20
2.20
2.20
2.10
2.35
2.60
1.60
1.60
2.60
2.35
2.35
2.35
2.35
2.35
2.35
2.35
2.35
2.35
3.45
3.45
2.90
2.90
3.45
3.45
2.10
2.10
2.35
2.35
2.35
2.35
2.35
2.35
2.45
2.35
1.95
1.95
2.35
2.45
2.35
2.35
1.75
1.90
1.75
1.76
1.78
1.92
1.68
1.85
1.75
1.68
1.71
1.65
1.65
1.68
1.70
1.72
1.82
1.69
1.71
1.72
1.75
1.76
1.73
1.79
1.95
1.70
1.74
1.69
1.73
1.74
1.79
1.69
1.71
1.80
1.82
1.83
1.82
1.79
1.82
1.80
2.02
1.89
1.75
1.80
1.92
1.85
8.37
8.47
8.51
8.61
9.29
8.13
8.95
7.71
9.27
11.55
4.22
4.22
11.35
9.38
9.49
10.05
9.33
9.44
9.49
9.66
9.71
9.55
21.30
23.20
14.29
14.63
20.11
20.59
9.13
9.39
9.33
9.44
9.94
10.05
10.10
10.05
10.74
10.05
6.84
7.68
10.43
10.50
9.94
10.60
5.66
J5/F6
J22/F6
J23/F7
J24/F3
J26/F2
K6/FR1
K8/F3
K9/F3
K11/F1
K16/F1
K18/F3
K19/F3
K21/FR1
L1/F5
L3/F2
L4/F6
L23/F6
L24/F2
L26/F5
M2/F5
M4/F5
M6/FR2
M8/F2
M10/F3
M13/F2
M15/F2
M17/F3
M20/F2
M22/FR2
M23/F5
M25/F5
N2/F7
N4/F7
N23/F7
N25/F7
P6/F5
P7/F3
P10/F3
P13/F4
P14/F4
P17/F3
P20/F3
P21/F5
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1.95
1.95
1.75
2.35
2.45
1.80
2.35
2.35
2.60
2.60
2.35
2.35
1.80
2.10
2.45
1.95
1.95
2.45
2.10
2.10
2.10
2.10
2.45
2.35
2.45
2.45
2.35
2.45
2.10
2.10
2.10
1.75
1.75
1.75
1.75
2.10
2.35
2.35
2.20
2.20
2.35
2.35
2.10
1.95
1.95
1.75
2.35
2.45
2.85
2.35
2.35
2.60
2.60
2.35
2.35
2.85
2.10
2.45
1.95
1.95
2.45
2.10
2.10
2.10
3.55
2.45
2.35
2.45
2.45
2.35
2.45
3.55
2.10
2.10
1.75
1.75
1.75
1.75
2.10
2.35
2.35
2.20
2.20
2.35
2.35
2.10
1.82
1.92
1.85
1.86
1.88
1.83
1.96
1.92
1.85
1.87
1.89
1.85
1.86
1.87
1.89
1.86
1.88
1.85
1.79
1.82
1.78
1.79
1.80
1.84
1.81
1.86
1.80
1.79
1.76
1.80
1.85
1.82
1.79
1.80
1.85
1.83
1.82
1.79
1.80
1.84
1.86
1.82
1.84
6.92
7.30
5.66
10.27
11.28
9.38
10.82
10.60
12.50
12.64
10.43
10.21
9.54
8.24
11.34
7.07
7.14
11.10
7.89
8.02
7.84
13.34
10.80
10.16
10.86
11.16
9.94
10.74
13.12
7.93
8.15
5.57
5.48
5.51
5.66
8.07
10.05
9.88
8.71
8.90
10.27
10.05
8.11
867.39
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1.95
1.95
1.95
1.95
1.95
1.95
1.95
2.35
1.95
1.95
1.95
1.95
1.95
1.95
1.95
2.35
1.50
1.60
1.56
1.66
1.64
1.39
1.46
1.46
5.70
6.06
5.91
6.29
6.21
5.26
5.53
8.03
E2/F3
D2/F3
B2/F2
J3/F1
H3/F4
G3/F3
1
1
1
1
1
1
x
x
x
x
x
x
1
1
1
1
1
1
2.35
2.35
2.15
1.95
2.55
2.35
2.35
2.35
2.15
1.95
2.55
2.35
1.63
1.63
1.50
1.47
1.63
1.56
8.97
8.97
6.91
5.57
10.56
8.58
GF-AHDC
Page 9 of 517
F3/F2
E4/F2
D4/F2
B4/F1
E5/F2
C5/F2
J6/F3
H6/F3
G6/RF1
F6/F3
J7/F2
I7/RF1
G7/RF1
F7/F3
E7/F3
C7/F3
B7/F2
J8/F2
H8/F4
G8/F5
E8/F4
C8/F2
B8/F1
I9/F1
G9/F2
F9/F2
E9/F2
D9/F2
B9/F1
I10/F5
G10/F5
GF-AHDC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2.15
2.15
2.15
1.95
2.15
2.15
2.35
2.35
2.25
2.35
2.15
2.25
2.25
2.35
2.35
2.35
2.15
2.15
2.55
2.75
2.55
2.15
1.95
1.95
2.15
2.15
2.15
2.15
1.95
2.75
2.75
Page 10 of 517
2.15
2.15
2.15
1.95
2.15
2.15
2.35
2.35
2.95
2.35
2.15
2.95
2.95
2.35
2.35
2.35
2.15
2.15
2.55
2.75
2.55
2.15
1.95
1.95
2.15
2.15
2.15
2.15
1.95
2.75
2.75
1.44
1.88
1.85
1.76
1.82
1.83
1.31
1.67
1.77
1.86
1.79
1.68
1.83
1.98
1.98
2.01
1.92
1.68
1.63
1.70
1.78
1.98
2.08
1.93
2.08
2.21
2.15
2.26
2.33
1.68
1.97
6.63
8.66
8.52
6.67
8.38
8.43
7.20
9.19
11.71
10.24
8.25
11.11
12.11
10.90
10.90
11.07
8.85
7.74
10.56
12.85
11.54
9.12
7.89
7.31
9.59
10.19
9.91
10.42
8.84
12.70
14.89
F10/F3
E10/F6
B10/F5
I11/F5
G11/F5
F11/F3
E11/F6
B11/F5
I12/F1
J13/F2
H13/F4
J14/F2
I14/RF1
G14/RF1
F14/F3
E14/F3
C14/F3
B14/F2
J15/F3
H15/F3
G15/RF1
F15/F3
E16/F2
C16/F2
E17/F2
D17/F2
B17/F1
J18/F1
H18/F4
G18/F3
F18/F2
I19/F1
G19/F1
F19/F3
E19/F3
D19/F3
B19/F2
I20/F1
G20/F1
F20/F1
E20/F1
D20/F1
B20/F1
To be done
A10/F7
A11/F7
G12/F2
F12/F2
E12/F2
D12/F2
B12/F1
G13/F5
E13/F4
C13/F2
B13/F1
For Foundation of External Walls
To be done
B1-B2
B2-B4
GF-AHDC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2.35
2.95
2.75
2.75
2.75
2.35
2.95
2.75
1.95
2.15
2.55
2.15
2.25
2.25
2.35
2.35
2.35
2.15
2.35
2.35
2.25
2.35
2.15
2.15
2.15
2.15
1.95
1.95
2.55
2.35
2.15
1.95
1.95
2.35
2.35
2.35
2.15
1.95
1.95
1.95
1.95
1.95
1.95
2.35
2.95
2.75
2.75
2.75
2.35
2.95
2.75
1.95
2.15
2.55
2.15
2.95
2.95
2.35
2.35
2.35
2.15
2.35
2.35
2.95
2.35
2.15
2.15
2.15
2.15
1.95
1.95
2.55
2.35
2.15
1.95
1.95
2.35
2.35
2.35
2.15
1.95
1.95
1.95
1.95
1.95
1.95
2.04
1.93
1.66
2.10
2.25
2.25
2.25
2.15
2.10
2.10
2.25
2.05
1.90
1.95
2.10
2.30
2.65
2.70
2.00
1.92
2.05
2.20
2.40
2.55
2.40
2.50
2.65
2.30
2.35
2.40
2.45
1.79
1.93
2.02
2.23
2.20
2.42
1.99
2.01
1.95
2.11
1.90
2.13
11.23
16.79
12.55
15.88
17.01
12.42
19.58
16.25
7.98
9.70
14.63
9.47
12.61
12.94
11.59
12.70
14.63
12.48
11.04
10.60
13.60
12.14
11.09
11.78
11.09
11.55
10.07
8.74
15.28
13.25
11.32
6.78
7.31
11.12
12.29
12.12
11.16
7.54
7.62
7.39
8.00
7.20
8.08
899.52
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1.55
1.55
2.15
2.15
2.15
2.15
1.95
2.75
2.55
2.15
1.95
1.55
1.55
2.15
2.15
2.15
2.15
1.95
2.75
2.55
2.15
1.95
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
4.80
4.80
9.24
9.24
9.24
9.24
7.60
15.12
13.00
9.24
7.60
1
1
x
x
1
1
3.18
3.18
0.60
0.60
0.75
0.75
1.43
1.43
Page 11 of 517
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C6-C7
C14-C16
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
D8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
GF-AHDC
1
1
1
1
1
1
1
1
1
0
1
1
1
1
0
0
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3.18
2.98
2.48
2.98
3.18
3.18
3.18
0.01
0.01
-0.02
0.08
0.88
0.88
0.08
-0.02
-0.02
0.99
0.99
0.01
0.78
0.78
0.01
3.28
2.88
2.48
2.88
3.28
3.11
3.08
3.08
3.11
2.56
1.75
1.56
2.75
0.78
1.66
2.75
1.56
1.95
1.66
2.46
1.85
3.12
2.05
1.56
2.26
2.32
1.35
1.76
2.46
1.64
1.65
1.96
2.46
1.85
2.65
2.46
1.85
2.65
Page 12 of 517
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
1.43
1.34
1.11
1.34
1.43
1.43
1.43
0.00
0.00
0.00
0.03
0.39
0.39
0.03
0.00
0.00
0.44
0.44
0.00
0.35
0.35
0.00
1.47
1.29
1.11
1.29
1.47
1.39
1.38
1.38
1.39
1.14
0.78
0.69
1.23
0.35
0.74
1.23
0.69
0.87
0.74
1.10
0.83
1.40
0.92
0.70
1.01
1.04
0.60
0.78
1.10
0.73
0.74
0.87
1.10
0.83
1.19
1.10
0.83
1.19
B13-D13
D13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2.46
1.64
1.65
1.96
2.26
2.32
1.35
1.76
2.05
1.56
3.12
2.46
1.85
1.56
1.95
1.66
1.66
2.75
2.56
1.75
0.78
1.56
2.75
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
1.10
0.73
0.74
0.87
1.01
1.04
0.60
0.78
0.92
0.70
1.40
1.10
0.83
0.69
0.87
0.74
0.74
1.23
1.14
0.78
0.35
0.69
1.23
172.88
1,939.79 Cum
2
#REF!
In F1-Footings
In F2-Footings
In F3-Footings
In F4-Footings
In F5-Footings
In F6-Footings
In RF1-Footings
23
1.95
1.95
0.15
13.12
1
1
1
1
1
1
x
x
23
22
5
7
2
6
2.15
2.35
2.55
2.75
2.95
2.25
2.15
2.35
2.55
2.75
2.95
2.95
0.15
0.15
0.15
0.15
0.15
0.15
15.95
18.22
4.88
7.94
2.61
5.97
68.69
1
1
1
1
1
x
x
x
x
x
2
5
1
1
2
1.95
2.15
2.55
2.75
1.40
1.95
2.15
2.55
2.75
1.4
0.15
0.15
0.15
0.15
0.15
1.14
3.46
0.97
1.13
0.58
To be done
In F1-Footings
In F2-Footings
In F4-Footings
In F5-Footings
In F7-Footings
7.28
75.97 Cum
GF-AHDC
Page 13 of 517
#REF!
B1-B2
B2-B4
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C5-C7
C14-C16
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
F20'-F20
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
GF-AHDC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
4.90
4.90
4.86
4.56
5.00
4.63
4.86
4.93
4.86
3.07
3.07
0.73
1.93
3.00
3.00
1.93
0.73
0.73
3.01
3.01
0.73
2.03
3.00
3.00
2.03
4.86
4.86
4.86
4.86
4.86
4.89
4.93
4.93
4.89
3.87
3.29
3.06
3.95
2.50
2.91
4.10
3.21
3.37
3.59
3.87
3.14
4.00
3.22
3.59
Page 14 of 517
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.44
0.44
0.44
0.41
0.45
0.42
0.44
0.44
0.44
0.28
0.28
0.07
0.17
0.27
0.27
0.17
0.07
0.07
0.27
0.27
0.07
0.18
0.27
0.27
0.18
0.44
0.44
0.44
0.44
0.44
0.44
0.44
0.44
0.44
0.35
0.30
0.27
0.36
0.23
0.26
0.37
0.29
0.30
0.32
0.35
0.28
0.36
0.29
0.32
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
C8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
B13-C13
C13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20
Under Internal Plinth beams
A10-A11
C7-C8,C13-C14
D1-D2,D2-D4,D9-D10,D11-D12,D17D19,D19-D20.
E1-E2,E2-E4.E7-E8,
E9E10,E10-E11,E11-E12,
E13E14,E17-E19,E19-E20.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3.00
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.87
3.14
3.95
3.87
3.14
3.95
3.59
3.00
4.00
3.22
3.00
4.00
3.22
3.59
3.22
4.00
4.00
4.00
3.69
3.21
3.37
3.59
2.91
4.10
3.87
3.29
3.06
3.95
2.50
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.27
0.36
0.29
0.32
0.27
0.36
0.29
0.32
0.35
0.28
0.36
0.35
0.28
0.36
0.32
0.27
0.36
0.29
0.27
0.36
0.29
0.32
0.29
0.36
0.36
0.36
0.33
0.29
0.30
0.32
0.26
0.37
0.35
0.30
0.27
0.36
0.23
1
1
1
X
X
X
1
2
6
5.00
4.56
5.23
0.45
0.45
0.45
0.15
0.15
0.15
0.34
0.62
2.12
5.00
0.45
0.15
3.04
E5-E7,E14-E16
F1-F2,F3-F6,F7-F8,F9-F10, F10F11,F11-F12,F13-F14, F15-F18,F19-F20
1
1
X
X
2
9
3.07
5.00
0.45
0.45
0.15
0.15
0.41
3.04
F6-F7,F14-F15
G1-G2,G3-G6,G7-G8,G9-G10, G10G11,G11-G12,G13-G14, G15-G18,G19G20
1
1
X
X
2
9
2.03
5.00
0.45
0.45
0.15
0.15
0.27
3.04
H3-H6,H7-H8,H13-H14,
B2-D2
D2-E2
F6-G6
F7-G7
E8-G8
E9-G9
1
1
1
1
1
1
1
X
X
X
X
X
X
X
4
1
1
1
1
1
1
5.00
3.87
3.29
3.21
3.21
6.01
6.01
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.15
0.15
0.15
0.15
0.15
0.15
0.15
1.35
0.26
0.22
0.22
0.22
0.41
0.41
GF-AHDC
H15-H18.
Page 15 of 517
A10-B10
B10-E10
E10-F10
F10-G10
G10-I10
A11-B11
B11-E11
E11-F11
F11-G11
G11-I11
F12-G12
E13-G13
E14-G14
F15-G15
B19-D19
D19-E19
E19-F19
Under flooring
Dormitory Halls
Toilets
Wash area
Wardens room cum Lounge
Clinic hall
Type-1 Stair case
Type-2 Stair case
Entrance Lobby
Corridor
Under entrance steps
Under 115 mm thick Brick walls
in Toilets
in Clinic room
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
7.00
7.38
2.50
3.06
3.80
7.00
7.38
2.50
3.06
3.80
6.01
6.01
5.71
3.21
3.87
3.29
3.21
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.47
0.50
0.17
0.21
0.26
0.47
0.50
0.17
0.21
0.26
0.41
0.41
0.39
0.22
0.26
0.22
0.22
1
1
1
1
1
1
1
1
1
1
1
X
X
X
X
X
X
X
X
X
X
X
10
4
2
1
1
2
1
1
1
2
1
7.67
8.00
15.75
7.67
7.67
4.56
7.67
7.67
63.32
5.00
5.00
5.00
5.00
3.28
5.00
5.00
3.07
5.00
5.00
2.50
1.00
0.90
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
38.35
16.00
10.32
3.84
3.84
2.80
3.84
3.84
15.83
1.00
0.45
4
4
1
1
1
1
1
1
1
X
X
X
X
X
X
X
X
X
10
2
1
1
1
1
1
1
1
1.50
7.78
1.50
2.12
5.00
3.35
5.00
1.50
2.12
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
Or say
1.80
1.87
0.05
0.06
0.15
0.10
0.15
0.05
0.06
152.98
153.00 cum
Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard
blasted Granite stones from approved quarry including cost and conveyance of all
materials like Granite stones, cement, sand, water, etc., to site including
seigniorage charges, sales & other taxes on all materials, all operational, incidental,
and labour charges such as cutting stones to required size and shape, mixing of
cement mortar, constructing masonry, curing etc., complete for finished item of work
for foundation and basement (APSS No. 601 & 615)
Below Ground Level
B1-B2
B2-B4
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C5-C7
C14-C16
GF-AHDC
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
4.90
4.90
4.86
4.56
5.00
4.63
4.86
4.93
4.86
3.07
3.07
Page 16 of 517
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
1.32
1.32
1.31
1.23
1.35
1.25
1.31
1.33
1.31
0.83
0.83
#REF!
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
F20'-F20
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
C8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
B13-C13
C13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
GF-AHDC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
0.73
1.93
3.00
3.00
1.93
0.73
0.73
3.01
3.01
0.73
2.03
3.00
3.00
2.03
4.86
4.86
4.86
4.86
4.86
4.89
4.93
4.93
4.89
3.87
3.29
3.06
3.95
2.50
2.91
4.10
3.21
3.37
3.59
3.87
3.14
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.87
3.14
3.95
3.87
3.14
3.95
3.59
3.00
4.00
3.22
3.00
4.00
3.22
3.59
Page 17 of 517
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.20
0.52
0.81
0.81
0.52
0.20
0.20
0.81
0.81
0.20
0.55
0.81
0.81
0.55
1.31
1.31
1.31
1.31
1.31
1.32
1.33
1.33
1.32
1.04
0.89
0.82
1.07
0.68
0.78
1.11
0.87
0.91
0.97
1.04
0.85
1.08
0.87
0.97
0.81
1.08
0.87
0.97
0.81
1.08
0.87
0.97
1.04
0.85
1.07
1.04
0.85
1.07
0.97
0.81
1.08
0.87
0.81
1.08
0.87
0.97
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20
Above Ground level
B1-B2
B2-B4
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C5-C7
C14-C16
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
F20'-F20
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
GF-AHDC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3.22
4.00
4.00
4.00
3.69
3.21
3.37
3.59
2.91
4.10
3.87
3.29
3.06
3.95
2.50
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
4.90
4.90
4.86
4.56
5.00
4.63
4.86
4.93
4.86
3.07
3.07
0.73
1.93
3.00
3.00
1.93
0.73
0.73
3.01
3.01
0.73
2.03
3.00
3.00
2.03
4.86
4.86
4.86
4.86
4.86
4.89
4.93
4.93
4.89
3.87
3.29
3.06
3.95
2.50
2.91
4.10
3.21
3.37
3.59
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
Page 18 of 517
0.87
1.08
1.08
1.08
1.00
0.87
0.91
0.97
0.78
1.11
1.04
0.89
0.82
1.07
0.68
0.00
1.32
1.32
1.31
1.23
1.35
1.25
1.31
1.33
1.31
0.83
0.83
0.20
0.52
0.81
0.81
0.52
0.20
0.20
0.81
0.81
0.20
0.55
0.81
0.81
0.55
1.31
1.31
1.31
1.31
1.31
1.32
1.33
1.33
1.32
1.04
0.89
0.82
1.07
0.68
0.78
1.11
0.87
0.91
0.97
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
C8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
B13-C13
C13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3.87
3.14
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.87
3.14
3.95
3.87
3.14
3.95
3.59
3.00
4.00
3.22
3.00
4.00
3.22
3.59
3.22
4.00
4.00
4.00
3.69
3.21
3.37
3.59
2.91
4.10
3.87
3.29
3.06
3.95
2.50
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
Or say
GF-AHDC
Page 19 of 517
1.04
0.85
1.08
0.87
0.97
0.81
1.08
0.87
0.97
0.81
1.08
0.87
0.97
1.04
0.85
1.07
1.04
0.85
1.07
0.97
0.81
1.08
0.87
0.81
1.08
0.87
0.97
0.87
1.08
1.08
1.08
1.00
0.87
0.91
0.97
0.78
1.11
1.04
0.89
0.82
1.07
0.68
164.08
165.00 cum
#REF!
Filling with useful available excavated earth (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15cm thick,
consolidating each deposited layer by watering and ramming including cost and
conveyence of water to work site and all operational, incidental, labour charges, hire
charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
MB. No.326/A/MD, Pg. No.5
867.39
To be done
Total Qty of excavated earth
1,072.40
1,939.79 Cum
29.16
In F2-Footings
23
2.00
2.00
0.38
34.50
In F3-Footings
22
2.20
2.20
0.43
45.25
In F4-Footings
2.40
2.40
0.48
13.68
In F5-Footings
2.60
2.60
0.55
26.03
2.80
0.55
8.62
2.80
0.28
9.70
In F6-Footings
2.80
In RF1-Footings
2.10
#REF!
166.95
To be done
In F1-Footings
In F2-Footings
In F4-Footings
In F5-Footings
In F7-Footings
1
1
1
1
1
x
x
x
x
x
2
5
1
1
2
1.80
2.00
2.40
2.60
1.40
1.80
2.00
2.40
2.60
1.40
0.38
0.38
0.43
0.48
0.48
2.43
7.50
2.44
3.21
1.86
17.44
184.39 cum
#REF!
For Pedestals
MB. No.326/A/MD, Pg. No.13 &14
In F1-Footings
24
0.60
0.60
0.60
5.18
In F2-Footings
23
0.75
0.75
0.60
7.76
In F3-Footings
22
0.75
0.75
0.60
7.42
In F4-Footings
0.75
0.75
0.60
1.68
In F5-Footings
0.75
0.75
0.60
2.36
In F6-Footings
0.75
0.75
0.60
0.67
In RF1-Footings
0.75
0.75
0.60
2.02
27.09
To be done
In F1-Footings
In F2-Footings
In F4-Footings
In F5-Footings
In F7-Footings
1
1
1
1
1
x
x
2
5
1
1
2
0.60
0.75
0.75
0.75
0.60
0.60
0.75
0.75
0.75
0.60
0.60
0.60
0.60
0.60
0.60
0.43
1.68
0.33
0.33
0.43
3.20
30.29 cum
GF-AHDC
Page 20 of 517
#REF!
4.90
0.23
0.30
0.34
B2-B4
4.90
0.23
0.30
0.34
B7-B8
4.86
0.23
0.30
0.34
B9-B10
4.56
0.23
0.30
0.31
B10-B11
5.00
0.23
0.30
0.35
B11-B12
4.63
0.23
0.30
0.32
B13-B14
4.86
0.23
0.30
0.34
B17-B19
4.93
0.23
0.30
0.34
B19-B20
4.86
0.23
0.30
0.34
C5-C7
3.07
0.23
0.30
0.21
C14-C16
3.07
0.23
0.30
0.21
E1-E1'
0.73
0.23
0.30
0.05
E4-E5
1.93
0.23
0.30
0.13
E8-E9
3.00
0.23
0.30
0.21
E12-E13
3.00
0.23
0.30
0.21
E16-E17
1.93
0.23
0.30
0.13
E20'-E20
0.73
0.23
0.30
0.05
F1-F1'
0.73
0.23
0.30
0.05
F2-F3
3.01
0.23
0.30
0.21
F18-F19
3.01
0.23
0.30
0.21
F20'-F20
0.73
0.23
0.30
0.05
G6-G7
2.03
0.23
0.30
0.14
G8-G9
3.00
0.23
0.30
0.21
G12-G13
3.00
0.23
0.30
0.21
G14-G15
2.03
0.23
0.30
0.14
I1-I2
4.86
0.23
0.30
0.34
I9-I10
4.86
0.23
0.30
0.34
I10-I11
4.86
0.23
0.30
0.34
I11-I12
4.86
0.23
0.30
0.34
I19-I20
4.86
0.23
0.30
0.34
J3-J6
4.89
0.23
0.30
0.34
J7-J8
4.93
0.23
0.30
0.34
J13-J14
4.93
0.23
0.30
0.34
J15-J18
4.89
0.23
0.30
0.34
B1-D1
3.87
0.23
0.30
0.27
D1-E1
3.29
0.23
0.30
0.23
F1-G1
3.06
0.23
0.30
0.21
G1-I1
3.95
0.23
0.30
0.27
E1'-F1'
2.50
0.23
0.30
0.17
F2-G2
2.91
0.23
0.30
0.20
G2-I2
4.10
0.23
0.30
0.28
F3-G3
3.21
0.23
0.30
0.22
G3-H3
3.37
0.23
0.30
0.23
H3-J3
3.59
0.23
0.30
0.25
B4-D4
3.87
0.23
0.30
0.27
D4-E4
3.14
0.23
0.30
0.22
C5-E5
4.00
0.23
0.30
0.28
G6-H6
3.22
0.23
0.30
0.22
GF-AHDC
Page 21 of 517
H6-J6
3.59
0.23
0.30
0.25
B7-C7
3.00
0.23
0.30
0.21
C7-E7
4.00
0.23
0.30
0.28
G7-H7
3.22
0.23
0.30
0.22
H7-J7
3.59
0.23
0.30
0.25
B8-D8
3.00
0.23
0.30
0.21
C8-E8
4.00
0.23
0.30
0.28
G8-H8
3.22
0.23
0.30
0.22
H8-J8
3.59
0.23
0.30
0.25
B9-D9
3.87
0.23
0.30
0.27
D9-E9
3.14
0.23
0.30
0.22
G9-I9
3.95
0.23
0.30
0.27
B12-D12
3.87
0.23
0.30
0.27
D12-E12
3.14
0.23
0.30
0.22
G12-I12
3.95
0.23
0.30
0.27
B13-C13
3.59
0.23
0.30
0.25
C13-E13
3.00
0.23
0.30
0.21
G13-H13
4.00
0.23
0.30
0.28
H13-J13
3.22
0.23
0.30
0.22
B14-C14
3.00
0.23
0.30
0.21
C14-E14
4.00
0.23
0.30
0.28
G14-H14
3.22
0.23
0.30
0.22
H14-J14
3.59
0.23
0.30
0.25
G15-H15
3.22
0.23
0.30
0.22
H15-J15
4.00
0.23
0.30
0.28
C16-E16
4.00
0.23
0.30
0.28
B17-D17
4.00
0.23
0.30
0.28
D17-E17
3.69
0.23
0.30
0.25
F18-G18
3.21
0.23
0.30
0.22
G18-H18
3.37
0.23
0.30
0.23
H18-J18
3.59
0.23
0.30
0.25
F19-G19
2.91
0.23
0.30
0.20
G19-I19
4.10
0.23
0.30
0.28
B20-D20
3.87
0.23
0.30
0.27
D20-E20
3.29
0.23
0.30
0.23
E20'-F20'
3.06
0.23
0.30
0.21
F20-G20
3.95
0.23
0.30
0.27
G20-I20
2.50
0.23
0.30
0.17
A10-A11
5.00
0.23
0.30
0.35
C7-C8,C13-C14
4.56
0.23
0.30
0.63
D1-D2,D2-D4,D9-D10,D11-D12,D17D19,D19-D20.
E1-E2,E2-E4.E7-E8,
E9-
5.23
0.23
0.30
2.17
5.00
0.23
0.30
3.11
E10,E10-E11,E11-E12,
E13E5-E7,E14-E16
E14,E17-E19,E19-E20.
F1-F2,F3-F6,F7-F8,F9-F10, F10F11,F11-F12,F13-F14,
F15-F18,F19F6-F7,F14-F15
F20
G1-G2,G3-G6,G7-G8,G9-G10, G10G11,G11-G12,G13-G14,
H3-H6,H7-H8,H13-H14, G15-G18,G19H15-H18.
G20
B2-D2
3.07
0.23
0.30
0.42
5.00
0.23
0.30
3.11
2.03
0.23
0.30
0.28
5.00
0.23
0.30
3.11
5.00
0.23
0.30
1.38
3.87
0.23
0.30
0.27
GF-AHDC
Page 22 of 517
D2-E2
3.29
0.23
0.30
0.23
F6-G6
3.21
0.23
0.30
0.22
F7-G7
3.21
0.23
0.30
0.22
E8-G8
6.01
0.23
0.30
0.41
E9-G9
6.01
0.23
0.30
0.41
A10-B10
7.00
0.23
0.30
0.48
B10-E10
7.38
0.23
0.30
0.51
E10-F10
2.50
0.23
0.30
0.17
F10-G10
3.06
0.23
0.30
0.21
G10-I10
3.80
0.23
0.30
0.26
A11-B11
7.00
0.23
0.30
0.48
B11-E11
7.38
0.23
0.30
0.51
E11-F11
2.50
0.23
0.30
0.17
F11-G11
3.06
0.23
0.30
0.21
G11-I11
3.80
0.23
0.30
0.26
F12-G12
6.01
0.23
0.30
0.41
E13-G13
6.01
0.23
0.30
0.41
E14-G14
5.71
0.23
0.30
0.39
F15-G15
3.21
0.23
0.30
0.22
B19-D19
3.87
0.23
0.30
0.27
D19-E19
3.29
0.23
0.30
0.23
E19-F19
3.21
0.23
0.30
0.22
42.70
or say
7
43.00 cum
#REF!
#REF!
To be done
Column upto bottom of Plinth Beam
C1
10
0.30
0.45
0.90
1.22
C2
22
0.30
0.45
0.90
2.67
C3
18
0.30
0.45
0.90
2.19
C4
22
0.30
0.45
0.90
2.67
C5
0.30
0.60
0.90
1.30
C6
10
0.30
0.60
0.90
1.62
C7
0.30
0.60
0.90
1.30
C8
0.38
0.38
0.90
0.26
13.22
Or say
8
Providing High Yield Strength Deformed steel bars (Fe 415grade as per IS 17861979) of different diameters, including labour charges for cutting, bending to
required sizes and shapes placing in position with cover blocks of approved
materials and size and tying with binding wire of 20SWG, foRMing grills for
reinforcement work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps, couplings,
MB.
No.327/A/MD,
Pg. spacer
No.5
welded
joints, chairs,
bars including cost and conveyance of binding wire,
cover
blocks and all incidental, operational, labour charges such as cutting, bending,
To
be done
placing in position, tying including sales and other taxes and all materials etc.,
complete for finished item of work in all floors.(APSS No.126)
GF-AHDC
Page 23 of 517
14.00 cum
24.252
2.197
26.45
MT
#REF!
#REF!
Flush Pointing to CRS Masonry in CM(1:3) Prop: including cost and conveyance of
all materials like cement, sand, water etc., to site, including seigniorage charges,
sales & other taxes on all materials, all operational, incidental charges and labour
charges such as mixing mortar, finishing, curing, etc., complete for finished item of
work. (APSS 901,906)
Above Ground level
B1-B2
B2-B4
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C5-C7
C14-C16
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
F20'-F20
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
GF-AHDC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
4.90
4.90
4.86
4.56
5.00
4.63
4.86
4.93
4.86
3.07
3.07
0.73
1.93
3.00
3.00
1.93
0.73
0.73
3.01
3.01
0.73
2.03
3.00
3.00
2.03
4.86
4.86
4.86
4.86
4.86
4.89
4.93
4.93
4.89
3.87
3.29
3.06
3.95
2.50
2.91
4.10
3.21
3.37
3.59
3.87
3.14
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.00
Page 24 of 517
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
4.41
4.41
4.37
4.10
4.50
4.17
4.37
4.44
4.37
2.76
2.76
0.65
1.74
2.70
2.70
1.74
0.65
0.65
2.71
2.71
0.65
1.83
2.70
2.70
1.83
4.37
4.37
4.37
4.37
4.37
4.40
4.44
4.44
4.40
3.48
2.96
2.75
3.55
2.25
2.61
3.69
2.88
3.03
3.23
3.48
2.82
3.60
2.89
3.23
2.70
3.60
2.89
3.23
2.70
C8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
B13-C13
C13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20
C1
C2
C3
C4
C5
C6
C7
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
10
22
6
17
7
6
6
4.00
3.22
3.59
3.87
3.14
3.95
3.87
3.14
3.95
3.59
3.00
4.00
3.22
3.00
4.00
3.22
3.59
3.22
4.00
4.00
4.00
3.69
3.21
3.37
3.59
2.91
4.10
3.87
3.29
3.06
3.95
2.50
0.45
0.45
0.45
0.45
0.60
0.60
0.60
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
or say
3.60
2.89
3.23
3.48
2.82
3.55
3.48
2.82
3.55
3.23
2.70
3.60
2.89
2.70
3.60
2.89
3.23
2.89
3.60
3.60
3.60
3.32
2.88
3.03
3.23
2.61
3.69
3.48
2.96
2.75
3.55
2.25
4.05
8.91
2.43
6.89
3.78
3.24
3.24
306.00
306.00 Sqm
#REF!
Part A
10 Vibrated reinforced cement concrete M20 Grade
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.38
SF
GF-AHDC
Page 25 of 517
0.45
0.45
0.45
0.45
0.6
0.6
0.6
0.38
3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.00
1.35
2.97
2.43
2.97
1.44
1.80
1.44
0.29
14.69 cum
14.40 cum
14.40 cum
#REF!
TF
C2
C3
C4
C6
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
1
1
1
1
1
1
1
1
1
1
2
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
2
2
6
4
4
4
4
4
4
2
4
2
1
2
2
2
2
1
2
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
0.30
0.30
0.30
0.30
5.49
5.46
5.46
5.49
5.46
5.46
5.49
5.03
5.23
22.94
18.91
22.94
10.69
15.92
10.69
15.92
5.46
5.46
18.76
18.76
8.24
3.66
8.35
4.79
8.35
11.63
14.25
8.12
18.76
5.78
7.90
7.90
3.67
5.60
0.45
0.45
0.45
0.6
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
2.80
2.80
2.80
2.80
0.33
0.30
0.30
0.33
0.30
0.30
0.33
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.33
0.30
0.30
0.30
0.30
0.30
0.30
0.33
0.30
0.30
0.30
0.48
0.30
0.30
FF
SF
TF
2
2
1
1
GF-AHDC
1
1
1
1
1
x
x
x
x
x
x
x
x
x
2
2
2
2
1
2
2
2
1
3.90
4.67
5.46
5.12
0.23
0.23
0.23
0.23
64.82 22.37
11.51
3.01
8.01 2.03
8.01 3.23
15.69
3.61
Page 26 of 517
0.30
0.30
0.30
0.30
0.27
0.27
0.81
0.72
2.07 cum
1.64
1.51
1.51
1.64
1.51
0.75
1.64
0.69
0.36
3.17
2.61
3.17
1.48
1.10
1.48
1.10
0.38
0.38
2.59
2.59
2.46
1.01
1.15
0.66
1.15
1.60
1.97
1.21
2.59
0.80
1.09
1.73
1.01
0.77
50.48 cum
49.47 cum
49.47 cum
1.08
1.29
0.75
0.71
3.82 cum
1,450.02
-69.29
-32.50
-51.71
-56.64
#REF!
#REF!
#REF!
over portico
1
1
1
1
1
x
x
x
x
x
2
2
2
1
1
5.23
5.30
3.00
7.67
7.35
3.61
7.67
7.67
5.00
5.23
or say
FF
SF
TF
1
1
x
x
2
1
3.53
5.46
4.9
5.115
34.59
27.93
62.52 sqm
#REF!
#REF!
2
1
1
1
x
x
x
x
2
2
1
1
3.41
3.07
3.41
5.00
1.5
1.67
2
2.23
or say
FF
SF
11
-37.76
-81.30
-46.02
-38.35
38.41
1,074.86
1,075.00 sqm
1,036.59 sqm
1,036.59 sqm
Reinforced cement concrete M20 Grade Desing mix ( by weigh batching) using 20
mm size (SS5) hard granite machine crushed graded metal (coarse aggregate)
from approved quarry using miminum quantity of 350 Kgs of cement per 1 cum of
concrete including cost and conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc. to site including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labor charges such as
Providing Centring, shuttering and scaffolding with props and steel plate as per the
GF
approved shuttering plan and other accessories as per the norms and stability
calculations including cost and conveyance of all accessories Using Cashewrina
Ballies
andDoor-MD
Wooden runners & staging including
cross 0.23
members0.15
etc
Over Main
1
x all1bracings,5.00
complete
for finished item of work, lift charges,
mixing,
Over Door-D1
1
x machine
11
1.50 laying
0.23concrete,
0.15
vibrating,
curing concrete etc, complete but excluding
its fabrication
Over Door-D2
1
x 3cost of steel
1.35and0.115
0.15
charges etc complete for finished item of work (APSS No.402 & 403) for Lintels
Over Door-D6
1
x 50
1.05 0.115
0.15
Over windows-W3
1
x 58
1.80 0.23
0.15
Over Grill windows-GW
2
x 2
3.19 0.23
0.15
Over Grill windows-GW1
2
x 2
3.70 0.23
0.15
Over Grill windows-GW2
2
x 2
2.72 0.23
0.15
Over Grill windows-GW3
1
x 2
3.51 0.23
0.15
Over Ventilator-V
2
x 2
2.80 0.23
0.15
Over Ventilator-V1
1
x 50
1.20 0.23
0.15
or say
FF,
Over Main Door-MD
Over Door-D1
Over Door-D2
Over Door-D6
Over windows-W3
Over Grill windows-GW
Over Grill windows-GW1
Over Grill windows-GW2
Over Grill windows-GW3
Over Ventilator-V
Over Ventilator-V1
GF-AHDC
0
1
0
1
1
2
2
2
1
2
1
x
x
x
x
x
x
x
x
x
x
x
1
11
3
48
58
2
2
2
2
2
48
5.00
1.50
1.35
1.05
1.80
3.19
3.70
2.72
3.51
2.80
1.20
Page 27 of 517
0.23
0.23
0.115
0.115
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
20.46
10.25
6.82
11.15
48.68
49.00 sqm
49.00 sqm
49.00 sqm
#REF!
0.17
0.57
0.07
0.91
3.60
0.44
0.51
0.38
0.24
0.39
2.07
9.34
10.00 cum
#REF!
0.00
0.57
0.00
0.87
3.60
0.44
0.51
0.38
0.24
0.39
1.99
8.98 cum
#REF!
SF
12 Reinforced cement concrete with M 25 grade Design mix ( by weigh batching ) as
per using 20mm size (SS 5) machine crushed hard granite graded metal (coarse
aggregate) from approved quarry using a minimum quantity of 350 Kg of cement
per 1 Cum of concrete including cost and conveyance of all materials like cement,
fine aggregate (sand) ,coarse aggregate, water etc. to site and cost of
seigniorage charges on all materials including centering using Cashewrina
Ballies and Wooden runners & staging including all bracings, cross members
etc., shuttering, machine mixing, laying concrete, 7.5cm thick at fixed end and
5cm thick at free end with an average thickness of 6.25cm including labour
charges for mixing, laying, curing etc., complete but excluding cost of steel and
its fabrication charges for finished item of work for 60cm wide sun-shades(APSS No.
402, 403 & 903)
8.98 cum
#REF!
GF
Over windows-W3
Over Grill windows-GW1
Over Grill windows-GW2
Over Grill windows-GW3
Over Ventilator-V
Over Ventilator-V1
1
2
2
1
0
0
x
x
x
x
x
x
58
2
2
2
2
50
1.80
3.70
2.72
3.51
2.80
1.20
0.6
0.6
0.6
0.6
0.6
0.6
or say
FF,SF
9.78
7.01
0.6
0.6
FF
SF
14 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to
(1:3:6) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal from
approved quarry including cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site, including seigniorage charges, sales & other
taxes on all materials, all operational, incidental and labour charges such as mixing,
laying, curing concrete, etc., complete for finished item of work for Bed Blocks and
Hold Fasts (APSS No. 402)
Main Door-MD
D1
D2
D6
Grill windows-GW
Grill windows-GW1
Grill windows-GW2
Grill windows-GW3
Ventilator-V
Ventilator-V1
1
11
3
50
4
4
4
2
4
48
2
x
x
x
x
x
x
x
x
x
x
x
6
6
6
6
4
4
4
4
4
4
4
0.23
0.23
0.12
0.12
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.115
0.115
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
or say
FF,
SF
GF-AHDC
Page 28 of 517
62.64
8.88
6.53
4.21
0.00
0.00
82.26
83.00 sqm
83.00 sqm
83.00 sqm
23.47
16.82
40.30 sqm
40.30 sqm
40.30 sqm
0.05
0.52
0.04
0.60
0.13
0.13
0.13
0.06
0.13
1.52
0.06
3.36
3.50 cum
3.40 cum
3.40 cum
#REF!
#REF!
#REF!
#REF!
15 Plain Cement Concrete M20 Design Mix ( by weigh batching ) using 20mm size
(SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from
approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of
concrete including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage
charges on all materials including steel centering, shuttering, machine mixing, laying
concrete, lift charges, curing etc., complete for finished item of work for steps (APSS
No. 402 )
GF
Type-1 staircase steps
0.5 x 42
1.50
0.3
0.15
Type-2 Staircase steps
0.5 x 22
2.00
0.3
0.15
Steps at entrances
0.5 x 8
1.00
0.5
0.15
0.5 x 6
1.00
0.3
0.15
0.5 x 3
5.23
0.3
0.15
1.42
0.99
0.30
0.14
0.35
3.20
I1 F1
Av. Irregular depth
1
1
x
x
1
1
1.95
1.95
1.95
1.95
0.05
0.30
or say
FF
SF
16 Brick Masonry in superstructure with CM (1:8) prop: using second class bricks from
approved source having minimum crushing strength of 40 Kg/Sqcm. including cost
and conveyance of all materials like cement, sand, bricks, water etc., to site,
including seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of work.
(APSS No. 501 & 504).
Dormitory Rooms
Long walls
Cross walls
Clinic Hall
Long walls
Cross walls
Wardens room cum Lounge
Long walls
Cross walls
Entrance Lobby
Type-1 Staircase
Long walls
Cross walls
Type-2 Staircase
Beside Type-1 Staircase
Beside Clinic hall
Beside Toilets
Toilet Block
Cross walls
Long walls
Cross walls
Corridor side walls
Corridor end walls
Lintel Deductions
Over Main Door-MD
Over Door-D1
Over Door-D2
Over Door-D6
Over windows-W3
Over Grill windows-GW
Over Grill windows-GW1
GF-AHDC
0.19
1.14
1.33
4.53 cum
2.41 cum
2.41 cum
1
2
x
x
18
10
7.38
5.00
0.23
0.23
3.18
3.18
97.01
73.03
1
1
x
x
2
2
7.38
5.00
0.23
0.23
3.18
3.18
10.78
7.30
1
1
1
x
x
x
2
2
1
7.38
5.00
5.00
0.23
0.23
0.23
3.18
3.18
3.18
8.08
7.30
3.65
1
1
1
1
2
1
x
x
x
x
x
x
2
2
1
2
2
2
4.11
3.05
5.00
2.03
3.00
3.01
0.23
0.23
0.23
0.23
0.23
0.23
3.18
3.18
3.18
3.18
3.18
3.18
6.00
4.45
3.65
2.96
8.76
4.40
1
4
2
1
1
x
x
x
x
x
2
2
4
2
2
3.28
7.49
5.00
15.53
2.50
0.23
0.23
0.23
0.23
0.23
3.18
3.15
3.15
3.18
3.18
4.78
43.38
28.98
22.68
3.65
1
1
0
0
1
2
2
x
x
x
x
x
x
x
1
11
3
50
58
2
2
5.00
1.50
1.35
1.05
1.80
3.19
3.70
0.23
0.23
0.115
0.115
0.23
0.23
0.23
0.15
0.15
0.15
0.15
0.15
0.15
0.15
-0.17
-0.57
0.00
0.00
-3.60
-0.44
-0.51
Page 29 of 517
#REF!
2
1
2
1
x
x
x
x
2
2
2
50
2.72
3.51
2.80
1.20
0.23
0.23
0.23
0.23
0.15
0.15
0.15
0.15
-0.38
-0.24
-0.39
-2.07
1
1
0
0
1
2
2
2
1
2
4
x
x
x
x
x
x
x
x
x
x
x
1
11
3
12
58
2
2
2
2
2
12
4.00
1.20
1.05
0.75
1.50
2.73
3.24
2.26
3.05
2.50
0.90
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
2.13
2.13
2.13
2.13
1.35
1.35
1.35
1.35
1.35
0.45
0.45
-1.96
-6.47
0.00
0.00
-27.01
-3.39
-4.02
-2.81
-1.89
-1.04
-4.47
1
1
1
x
x
x
10
15
15
0.45
0.45
0.45
0.23
0.23
0.23
3.18
3.18
3.18
-3.29
-4.93
-4.93
266.29
267.00 cum
267.00
-18.08
-15.39
10.80
1.96
246.29 cum
267.00
-18.08
-15.39
10.80
1.96
246.29 cum
or say
FF
14.79
0.23
3.18
SF
TF
Head room
Parapet wall
Over Door D1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
4
4
2
2
2
2
2
2
2
6
6
2
3
3
14.79
4.67
3.07
5.00
7.67
64.82
19.20
11.51
7.90
4.40
8.01
7.90
4.67
1.50
1.20
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
3.18
2.80
2.80
2.80
2.80
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.15
2.13
GF-AHDC
Page 30 of 517
12.03
7.91
6.44
9.88
29.82
8.83
5.29
3.63
2.02
11.05
10.90
2.15
-0.16
-1.76
108.03 cum
#REF!
#REF!
#REF!
#REF!
GF
Toilet Block
Long walls
Cross walls
In clinic & Warden room
4
2
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
10
4
2
2
2
1
3
50
3
50
1.50
7.78
2.00
1.62
5.00
3.00
1.35
1.05
1.05
0.75
2.85
2.85
2.88
2.88
3.18
3.48
0.15
0.15
2.13
2.13
or say
FF
Lintels Over Door-D2
D2
D6
SF
Lintels Over Door-D2
D2
D6
1
1
1
1
1
1
x
x
x
0
x
x
3
3
2
3
3
2
1.35
1.05
0.75
1.35
1.05
0.75
0.15
2.13
2.13
0.15
2.13
2.13
18 Providing High Yield Strength Deformed steel bars (Fe 415grade as per IS 17861979) of different diameters, including labour charges for cutting, bending to
required sizes and shapes placing in position with cover blocks of approved
materials and size and tying with binding wire of 20SWG, foRMing grills for
reinforcement work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps, couplings,
welded joints, chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such as cutting, bending,
Ground
Floor
placing in
position, tying including sales and other taxes and all materials etc.,
First
Floor
complete for finished item of work in all floors.(APSS No.126)
Second Floor
Third Floor
19 Providing Mild steel bars (Fe 250 grade as per IS 432) of different diameters,
including labour charges for cutting, bending to required sizes and shapes placing in
position with cover blocks of approved materials and size and tying with binding wire
of 20SWG, foRMing grills for reinforcement work as per approved designs and
drawings, including cost and conveyance of steel bars, including all wastages such
as overlaps, couplings, welded joints, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying including sales and other
Ground
taxes onFloor
all materials etc., complete for finished item of work in all floors.(APSS
First Floor
No.126)
Second Floor
171.00
177.27
11.50
9.29
31.75
10.43
-0.61
-7.88
-6.71
-79.88
316.16
317.00 sqm
254.04
0.61
6.71
3.20
264.55 sqm
254.04
0.61
6.71
3.20
264.56 sqm
GF-AHDC
10
7.67
Page 31 of 517
3.48
#REF!
#REF!
Mt
Mt
Mt
Mt
#REF!
1.00 Mt
1.00 Mt
1.00 Mt
#REF!
22.00
27.00
27.00
4.24
20 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top
coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance
of all materials like cement, sand, water etc., to site, seigniorage charges, sales &
other taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 &
904)
Dormitory Rooms
Long walls
#REF!
533.07
Cross walls
Clinic Hall
Long walls
Cross walls
Wardens room cum Lounge
Long walls
Cross walls
Entrance Lobby
Type-1 Staircase
Long walls
Cross walls
Type-2 Staircase
Toilet Block
Cross walls
Cross walls
Corridor side walls
Corridor end walls
Deductions
Main Door-MD
Door-D1
Door-D2
Door-D6
windows-W3
Grill windows-GW
Grill windows-GW1
Grill windows-GW2
Grill windows-GW3
Ventilator-V
Ventilator-V1
Toilet Block
Long walls
Cross walls
In clinic & Warden room
10
5.00
3.48
347.50
1
2
x
x
2
2
7.67
5.00
3.48
3.48
53.31
69.50
1
1
1
x
x
x
1.5
2
1
7.67
5.00
5.00
3.48
3.48
3.48
39.98
34.75
17.38
2
1
1
1
x
x
x
x
2
2
1
2
4.11
3.05
5.00
7.67
3.48
3.48
3.48
3.48
57.13
21.20
17.38
53.31
2
2
2
1
x
x
x
x
2
4
2
2
3.28
5.00
15.53
2.50
3.48
3.48
3.48
3.48
45.52
139.00
215.87
17.38
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
x
x
x
x
x
x
x
x
x
x
x
1
11
3
50
58
4
4
4
2
4
48
4.00
1.20
1.05
0.75
1.50
2.73
3.24
2.26
3.05
2.50
0.90
2.13
2.13
2.13
2.13
1.35
1.35
1.35
1.35
1.35
0.45
0.45
-4.26
-14.06
-3.35
-39.94
-58.73
-7.37
-8.75
-6.10
-4.12
-2.25
-9.72
2
2
2
2
2
1
x
x
x
x
x
x
40
4
2
2
2
2
1.50
7.78
2.00
1.62
5.00
3.00
3.18
3.18
3.18
3.18
3.48
3.48
or say
FF
1
14.79
3.48
0.5
0.75
2.13
381.00
197.49
25.40
20.51
69.50
20.85
2,218.35
2,219.00 sqm
2,219.00
-136.26
102.79
4.26
3.35
1.60
2,194.74 sqm
#REF!
2,194.74 sqm
#REF!
#REF!
SF
TF
Head room
Parapet wall
GF-AHDC
2
2
2
2
2
2
2
2
2
2
2
x
x
x
x
x
x
x
x
x
x
x
4
4
2
2
2
2
2
2
2
6
6
4.67
3.07
5.00
7.67
64.82
19.20
11.51
7.90
4.40
8.01
7.90
Page 32 of 517
3.10
3.10
3.10
3.10
1.00
1.00
1.00
1.00
1.00
1.00
1.00
115.82
76.14
62.00
95.11
259.28
76.80
46.04
31.60
17.58
96.06
94.80
Over Door D1
2
1
1
x
x
x
2
3
3
4.67
1.50
1.20
1.00
0.15
2.13
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
2
2
8
2
2
2
6
2
64.82
19.20
8.12
4.67
4.73
11.85
8.61
64.36
3.60
3.60
3.60
3.60
3.60
3.60
3.60
3.48
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
2
2
x
x
x
x
x
x
x
x
x
x
x
x
x
1
11
3
50
58
4
4
4
2
4
48
26
2
4.00
1.20
1.05
0.75
1.50
2.73
3.24
2.26
3.05
2.50
0.90
0.34
0.76
2.13
2.13
2.13
2.13
1.35
1.35
1.35
1.35
1.35
0.45
0.45
3.60
3.60
or say
FF
Door-D6
0.5
0.75
2.13
21 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM
(1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, seigniorage
charges, sales & other taxes on all materials,all operational, incidental and labour
charges such as mixing mortar, scaffolding charges, lift charges, including cutting of
Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing,
etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903
& 904)
Dormitory Halls
1
x 10
7.67
5
Beam sides
2
x 10
5.00
0.30
Clinic Hall
1
x 1
7.67
5
Beam sides
2
x 1
5.00
0.30
Wardens room cum Lounge
1
x 1
7.67
5
Beam sides
2
x 1
5.00
0.30
Entrance Lobby
1
x 1
7.67
5
Beam sides
2
x 3
5.00
0.30
Toilet blocks
1
x 4
8.00
5
Beam sides
2
x 8
5.00
0.33
Wash area
1
x 2
15.75 3.275
Beam sides
2
x 8
3.28
0.30
Corridor
1
x 1
64.36
2.5
Beam sides
2
x 10
2.50
0.30
Portico
1
x 1
7.53 5.46
Page 33 of 517
#REF!
466.70
138.24
233.86
33.62
34.06
85.28
185.87
447.30
-4.26
-14.06
-3.35
-39.94
-58.73
-7.37
-8.75
-6.10
-4.12
-2.25
-9.72
62.71
10.94
1,539.95
1,540.00 sqm
1,540.00
4.26
3.35
1.60
1,549.21 sqm
1,549.21 sqm
SF
GF-AHDC
18.68
-0.68
-7.67
981.56 sqm
383.50
100.00
38.35
10.00
38.35
10.00
38.35
30.00
160.00
80.00
103.16
52.40
160.90
50.00
41.11
#REF!
#REF!
#REF!
Beam sides
Beam sides
Bottom Type-1 Staircase waist slab
Bottom Mid landing
Bottom Type-2 Staircase waist slab
Bottom Mid landing
Sides to steps
2
2
2
1
1
1
0.5
0.5
0.5
0.5
0.5
2
2
2
2
0
2
x 2
x 2
x 2
x 2
x 1
x 1
x 42.0
x 22.0
x 8.0
x 6.0
x 3.0
5.46
7.53
3.41
3.07
3.41
5.00
x
x
x
x
x
x
1.80
3.70
2.72
3.51
2.80
1.20
58
4
4
2
4
48
0.30
0.48
1.5
1.67
2
2.23
0.3
0.3
0.5
0.3
0.3
0.15
0.15
0.15
0.15
0.15
0.6
0.6
0.6
0.6
0.6
0.6
or say
FF
SF
TF
Slab
beam side
2
2
1
1
x
x
x
x
2
2
2
2
3.90
4.67
5.46
5.12
0.30
0.30
0.30
0.30
22 Providing impervious coat to exposed RCC roof slab surfaces to required slopes
with CM (1:3) prop. 20mm thick (average) mixed with water proofing compound
manufactured by reputed manufacturers as approved by Engineer-in-charge at 1 Kg
per one bag of cement, laid over roof slab when it is green, finished smooth with a
floating coat of neat cement and thread lining at regular intervals of 45cmx45cm
including cost and conveyance of all materials like cement, sand, water proofing
compound, water etc., to site, including seigniorage charges, sales & other taxes on
over
portico in
GFoperational, incidental, and labour charges for mixing mortar,
all
materials
and
or say
laying, lift charges, rendering smooth and thread lining, curing including rounding
off
junctions
of wall and slab etc., complete for finished item of work. (APSS No. 901 &
SF
903)
TF
23 Flooring with Polished Shabad/Tandur blue Slabas 15 to 18 mm thick (0.457M x
0.457M) set over a base coat of CM (1:8), 12mm thick (joints of stone must be
flushed) over C.C. bed already laid or R.C.C. roof slab only after it is properly
cured, cleaned, moistered and where necessary treated with neat grey cement
slurry of honey like consistency spred at3.3 kgs of cement for 1 sqm. and jointed
with neat cement paste to full depth, including cost and conveyance of all materials
GF
like cement, sand, water, flooring stones etc. to site, seigniorage charges, sales and
other taxes on all materials, all operational, incidental and labour charges such as
Dormitory Halls
1
x 10
7.67 5.00
dressing of flooring stones to the required sizes, mixing of cement mortar, laying,
Clinic
Hall
1
x
1
7.67 5.00No.703 &
jointing, curing, lift charges etc., complete for finished item of work.(APSS
Wardens
room
cum
Lounge
1
x
1
7.67 5.00
701)
Entrance Lobby
1
x 1
7.67 5.00
Toilet blocks
1
x 4
8.00 1.77
Wash area
1
x 2
15.75
3.28
Corridor
1
x 1
64.36
2.50
Single staircase room
1
x 2
4.67 3.05
GF-AHDC
Page 34 of 517
21.84
30.12
20.46
10.25
6.82
11.15
6.30
3.30
2.00
0.90
0.45
125.28
17.76
13.06
8.42
0.00
69.12
1,643.36
1,644.00 sqm
#REF!
1,644.00
-41.11
-21.84
1,581.05 sqm
#REF!
1,581.05 sqm
#REF!
62.52
15.60
18.68
10.92
10.23
117.95 sqm
#REF!
38.41
39.00 sqm
1,036.59 sqm
62.52 sqm
383.50
38.35
38.35
38.35
56.64
103.16
160.90
28.49
#REF!
On midlanding
Double staircase area
On midlanding
At entrance area
Toilets
1
1
1
1
1
x
x
x
x
x
2
1
1
1
2
3.07
7.67
5.00
7.00
2.00
1.67
5.00
2.23
1.00
1.50
10.25
38.35
11.15
7.00
-6.00
908.49
909.00 sqm
#REF!
FF
909.00 sqm
#REF!
SF
909.00 sqm
#REF!
or say
24 Flooring with ceramic non-skid tiles of first quality as approved by Engineer-incharge 7.3mm thick manufactured by ISO approved firm of size 300mm x300mm
of colour and size as approved by the Engineer-in-charge set over a base coat of
CM (1:8) prop. 12mm thick over CC bed already laid including neat cement slurry
of honey like consistency spread at the rate of 3.30kgs of cement per Sqm. and
filling the joints with white cement paste mixed with pigment of matching shade
including cost and conveyance of all materials like cement, sand, water, ceramic
tiles, white cement etc., to site, (excluding cost of C.C. bed) including cost of
seigniorage charges and all other taxes on all materials, cost of base coat and all
labour charges for mixing of cement mortar, laying tiles to required slope as directed
by the Engineer-in-charge curing etc., in toilets for finished item of work for all
floors(APSS No.701 & 707). Ground Floor
Toilet Block
on hand wash platforms
Toilets in Clinic room & wardens room
4
1
1
1
x
x
x
x
12
2
2
2
1.50
11.02
2.68
2.00
1.2
0.6
0.6
1.5
or say
FF
SF
25 Providing skirting to internal walls 12.5cm high with polished Betamcherla pure white
stone minimum of 25 mm thick (.254Mx.254M) set over a base coat of CM(1:3),
12mm thick (joints of stone must be flushed) over C.C bed already laid or RCC roof
slab only after it is pr0perly cured, cleaned, moistered and where necessary treated
with neat grey cement slurry of honey like consistency spred at 3.3 kgs of cement for
1 sqm. and jointed with neat cement paste to full depth,including cost and
GF
conveyence of all materials like cement sand, water, flooring stones etc. to site ,
seigniorage
on 25.34
all materials 0.13
,all
Dormitory Hallscharges , sales and other
1
x taxes
10
operational,incidental and labour charges such as dressing of flooring stones to the
Clinic Hall
1
x 1
25.34
0.13
require sizes, mixing of cement mortar,laying,jointing,curing,lift charges etc.,
Wardens
room
cum
Lounge
1
x
1
25.34
0.13
complete for finished item.(APSS No.701&707)
Entrance Lobby
1
x 1
25.34
0.13
Toilet blocks
1
x 4
19.54
0.13
Wash area
1
x 2
38.05
0.13
Corridor
1
x 1
133.72
0.13
Single staircase room
1
x 2
15.44
0.13
On midlanding
1
x 2
9.48
0.13
Double staircase area
1
x 1
25.34
0.13
On midlanding
1
x 1
14.46
0.13
At entrance area
1
x 1
16.00
0.13
or say
FF
GF-AHDC
Page 35 of 517
86.40
13.22
3.21
6.00
108.83
109.00 sqm
109.00
-6.00
103.00 sqm
#REF!
#REF!
103.00 sqm
#REF!
31.68
3.17
3.17
3.17
9.77
9.51
16.72
3.86
2.37
3.17
1.81
2.00
90.38
91.00 sqm
#REF!
91.00 sqm
#REF!
91.00 sqm
SF
26 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as
approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm
thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including cost and conveyance
of all materials like cement, sand, water, tiles, etc. to site, seigniorage charges, sales
and other taxes on all materials, C921 such as mixing of cement mortar, laying in
position, curing, lift charges etc., complete for finished item of work (APSS No.701
& 707) in All Floors
5.40
Toilet Blocks
4
x 12
1.80
8.00
Passage
4
x 2
1.80
0.75
Deduct doors
4
x 12
1.80
38.05
Wash basin area
1
x 2
1.80
3.00
Deduct Openings
1
x 1
1.80
Clinic Hall&Warden room toilets
7.00
1
x 2
1.80
0.75
Deduct doors
1
x 2
1.80
or say
FF
652.20 sqm
SF
27 Supplying and fixing of polished Black kadapa slabs of 15mm thick in a single piece
with the edges flat nosed and set over a base coat of CM(1:8) 12mm thick, and
fixing in position with neat cement paste including cost and conveyence of all
materials like cement,sand ,water,stones etc.to site , seigniorage charges , sales
and other taxes on all materials ,all operational,incidental and labour charges such
as dressing of flooring stones to the require sizes, mixing of cement
mortar,laying,jointing,curing,lift charges etc., complete for finished item.(APSS
No.701&707)
For Treads
At entrance area
2
x 4
1.00
0.5
2
x 3
1.00
0.3
Staircase
1
x 3
7.80
0.3
2
x 23
1.50
0.3
1
x 23
2.00
0.3
or say
FF
Staircase
2
2
1
2
1
x
x
x
x
x
4
3
3
23
23
1.00
1.00
7.80
1.50
2.00
0.15
0.15
0.15
0.15
0.15
or say
FF
1.20
0.90
3.51
10.35
6.90
22.86
23.00 sqm
23.00
-2.10
20.90 sqm
20.90 sqm
SF
GF-AHDC
4.00
1.80
7.02
20.70
13.80
47.32
48.00 sqm
48.00
-5.80
42.20 sqm
42.20 sqm
SF
Risers
At entrance area
466.56
115.20
-64.80
136.98
-5.40
25.20
-2.70
671.04
672.00 sqm
672.00
-25.20
5.40
652.20 sqm
Page 36 of 517
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
28 Granolithic concrete flooring 20mm thick with C.C. (1:1:2) proportion using 6mm to 12mm size
graded hard granite machine crushed metal laid monolithically over a bed of C.C. (1:5:10) prop.
10cm thick already laid in alternate panels of size not exceeding 1.50m x1.50m and providing 5mm
thick glass strips between the panels and finishing the top surface to required smoothness and
slopes, including cost and conveyance of all materials to work site (excluding cost of CC bed)
including cost of seigniorage charges and all other taxes on all materials and all operational,
incidental, labour charges such as mixing concrete, centering, laying, curing etc., complete for
Betweenitem
dormitory
halls
1
x 4
7.90 3.23
102.07
finished
of work
for all floors.(APSS No.710)
Between Toilet blocks
8.01
2.26
36.18
4.40
3.23
28.39
4.67
2.23
20.83
187.47 sqm
29 Reinforced cement mortar facia 5cm thick in CM (1:3) for drop walls, fins & staircase
railing with rabbit wire mesh & nominal reinforcement as directed by Engineer-incharge with dubara sponge finishing, including cost & conveyance of all materials to
site, including seigniorage charges, sales and other taxes on all materials,
operational, incidental charges, cost & conveyance of cement, wire mesh, and water
to
site,area
centering, scaffolding and form1work,
curing etc., complete
At work
entrance
x lift2charges 5.20
0.90
but excluding cost of steel & its fabrication charges, as directed by Engineer -inStaircase
2
x
2
3.50
0.90
charge for finished item of work (APSS No.403 & 903) .
1
x 2
4.50
0.90
or say
FF
21.64 sqm
SF
GF-AHDC
9.36
12.60
8.10
30.06
31.00 sqm
31.00
-9.36
21.64 sqm
Page 37 of 517
#REF!
#REF!
#REF!
#REF!
30 Providing & Applying Synthetic Plaster Putty or Plaster of Paris Putty or Lime
punning of average 1 to 2mm thick over plastered surface to prepare the surface
even and smooth after thoroughly brushing the surface to remove all dirt and
remains of loose powdered materials, applying emery paper, sand the surface, clean
& wipe off loose dust, applying knifing paste filler by putty knife/muslin pad, air dry
for 2-3 hours, sand with 180 and 320 No, emery paper for the surface preparation
Same as 12
mmand
thick
plastering Qty.
including
cost
conveyance
of all materials to site, sales & other taxes, all
operational,
incidental12
and
labour
etc.,
complete for finished item of work for
Same as ornamental
mm
thick charges
plastering
Qty.
internal walls.
FF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.
SF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.
TF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.
All floors
31 Painting to new walls with 2 coats of Acrylic based Oil bound Washable Distemper
having VOC content less than 50 grams/litre over promer coat using white cemnt as
approved by Engineer-In-Charge, making 3 coats in all to give an even shade after
thourughly brushing the surface to remove all dirt and remains of loose powdered
materials, including cost and conveyance of all materials to work site and all
operational, incidental, labour charges etc., and overheads & contractors profit
Same as 12
thickitem
plastering
complete
for mm
finished
of workQty.
as per APSS 911 for internal walls in all floors.
Same as ornamental 12 mm thick plastering Qty.
FF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.
SF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.
TF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.
All floors
32 Providing and applying Altek / PMCC / Deco orient base or Equivalent exterior
Texture of average 2 to 3 mm thickness over plastered surface to prepare the
surface even and smooth after thoroughly brushing the surface to remove all dirt and
remains of loose powdered materials, applying emery paper, Sand the surface,
clean & wipe off loose dust, applying putty/ texture paint filler by putty knife / muslin
pad, air dry for
2 - 3 hrs for the surface preparation including cost and
conveyance of all materials to work site and all operational, incidental, labour
charges, scaffolding charges, overheads and
profit
etc., complete
for
1 contractors
x 1
64.82
11.70
finished item of work in all floors for external walls
GF-AHDC
Page 38 of 517
2,219.00
1,644.00
3,863.00 sqm
2,194.74
1,581.05
3,775.79 sqm
76.14
15.60
3,775.79 sqm
490.78
117.95
608.73
12,023.31 sqm
#REF!
2,219.00
1,644.00
3,863.00
2,194.74
1,581.05
3,775.79
2,194.74
1,581.05
3,775.79
490.78
117.95
608.73
12,023.31 sqm
#REF!
758.39 sqm
#REF!
33 Painting with weather proof plastic emulson grade -1 paint to exterior faces of new
walls with 3 coats of approved make shade and colour including self prime coat
including c/c of all materials like plastic emulsinn paint of Grade-1 to sitee including
cost of brushes scaffolding charges, lifiting charges and labour charges such as
preparing the wall applying three coats of plastik emlsion etc., complete for finished
item of work (APSS No 910,911 7 1201) in all floors
Same as 12 mm thick plastering Qty. for external walls
1,644.00
FF,
Same as 12 mm thick plastering Qty. for external walls
1,549.21
SF
1,549.21
TF
Same as 12 mm thick plastering Qty. for external walls
490.78
5,233.20 sqm
All floors
34 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 Mt. with
Medium Teak wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm long 2
Nos, Alluminimum Handles 150mm long 2 Nos, 300mm long M.S.Powder Coated
Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6Nos, 300 mm long
GF
M.S.Powder
Coated Flat latch 1No, Door stoppers 2 Nos, MS Hold fasts 6Nos,
Sales and Other Taxes cost and convenyance of all materials to site all Labour
D1
1
x Fixing
11 in position , with Hardware
charges such as Fixing of Door Frame on shutter
FF,SF
fixtures etc., complete for finsihed item of work.
D1
2
x 11
TF
D1
1
x 3
35 Supplying & fixing of Medium Teak Wood Panneled Main Door of Size 4.00 Mts X
2.70 Mts made with outer frame of section 4"x5"(100x125mm) two horizontal and
four verticals fixed frame,Both sides fixed with Iron grill (size:1900 x 500mm) ,
(1850x500mm)madeup of Vertical & Horizontal bars of 10mm Square welded to
MS Flat 20x5mm alround forming (100x125mm) grid and with 5mm thick pin
headed glass panels (2Nos of 500mmX1900mm,
of
1
x 2'nos
1 of 500mm
1.00x 500mm,1 no
1.00
2600mmx500mm),
MT
beading
.The
shutters
should
be
made
up
of
size
650mm
36 Supply and Fixing of Door with Double leaf shutter, Door Size1.05x2.13 Mt. withx
1900mm
(4nos)
frame
with
2"thick(50mm)
and xscantlings(planks)
be 1"
Medium Teak
wood
Frame
of sections
size 75mm
100mm with Flushshould
Door Shutter
(25mm
thick)
including
fixing type
all fixtures
such as ply
350mm
Brass
Aldrops
Solid Bond
Wood
black board
with commercial
on bothlong
faces
of 35mm
thick,
200mm
Long
Towetr
bolts(8
nos),
Brass
fancy
Door
Handles
200mm
long
(2nos)out
including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm long 2
side,
150mm long Handles
(2nos) inside,
BrassHinges
150mm
long
(4x4=16Nos)
Nos, Alluminimum
150mm
long 2 Nos,
300mm
long
M.S.Powderincluding
Coated
polishing
with
melamine
finish
including
all
labour
charges
for
wrought
all
Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6Nos,
300&put
mmuplong
other
charges
stc.,
complete
for
finished
item
of
work.
M.S.Powder
Coated Flat latch 1No, Door 1stoppers
D2
x 32 Nos, MS Hold fasts 6Nos,
Sales
and
Other
Taxes
cost
and
convenyance
FF,SF
2
xof all
3 materials to site all Labour
charges such as Fixing of Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work. D2
37 Providing and fixing factory made Polyvinyl chloride (PVC) Door Frame of the size
50 x 47mm with a wall thickness of 5mm, made out of extruded 5mm rigid PVC
foam sheet, mitre cut at two corners and joined with 2nos. of 150mm long brackets
of 15x15mm M.S. square tube. The two vertical door profiles are to be reinforced
with 19x19mm M.S. Square tube of 19 gauge. The door frame shall be fixed to the
wall using 65/100mm long M.S. Screws through the frame by using PVC fasteners.
A minimum of 4nos. of screws to be provided for each vertical member & minimum
2nos. for horizontal member etc. complete as per manufacturers specification and
direction of Engineer-in-Charge for finished item of work
11.00
22.00
3.00
36.00 Nos
#REF!
1.00 No
#REF!
3.00
6.00
9.00 Nos
#REF!
GF
D6
FF,SF
D6
GF-AHDC
50
5.00
250.00
48
5.00
480.00
Page 39 of 517
#REF!
730.00 Rmt
38 Providing and fixing 30mm thick Solid panel PVC door shutter consisting of frame
made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm for stiles,
& 15mm x 15mm for top & bottom rails. M.S. frame shall have a coat of steel
primers of approved make and manufacture. M.S. frame shall be covered with 5mm
thick heat moulded PVC C channel of size 30 x 50mm forming stiles, and 5mm
thick, 75mm wide PVC sheets for top rail, lock rail & bottom rail on either side, and
10mm (5mm x 2) thick, 20mm wide cross PVC sheet as gap insert for top rail &
GF
bottom
rail. Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded /
sealed
to the stiles & rails with 30mm wide
sheet beading2.13
on
D6
1 x 5mm
x 50thick PVC
0.75
either side, and joined together with solvent cement adhesive etc. An additional
5mm thick PVC strip of 20mm width is to be stuck on the interior side of the C
FF,SF
Channel using PVC solvent adhesive. Complete as per direction of Engineer-inD6
2 forx finished
48
2.13
charge, manufacturers specification & drawing
item0.75
of work .
39 Providing & Fixing of Openable Windows with Fly-mesh made of pre-painted steel
(Base Steel as per IS 513 of 0.6mm thick galvanized as per IS 277 with zinc of 150
GSM) primer coated with epoxy primer of 5-7 microns thick, finish painted with a
polyester paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd
backer and the section for outer frame of 72 x 55mm, centre mullion of 72 x 50mm,
section for fixed glass beading section of 12 x 12 mm and section for shutters of 47
x 20 mm and outer frame & mullion sections with rebate for glazed shutters, fly
mesh
and a 20 mm provision for guard bars/grills and fly mesh shutter section of 20
GF,FF,SF
x 40 mm and the sections cut to length metre joined with corner bracket, centre
mullions
fixed with mullion cap, stay, handles,
2 Nos of 1.50
heavy duty stainless
W3
3 latch
x 58
1.35
steel pivot hinges per shutter and panelled with 5mm thick plain float glass and S.S.
Mesh for fly mesh shutter (304 grade), fitted using rubber gaskets
#REF!
79.88
153.36
233.24 sqm
#REF!
352.35 sqm
#REF!
40 #REF!
Ventilators
GF
V
V1
2
1
x
x
2
50
2.50
0.90
0.45
0.45
4.50
20.25
24.75
FF,SF
V
V1
2
1
x
x
2
48
2.50
0.90
0.45
0.45
4.50
19.44
47.88
72.63 sqm
41 Painting to wood work, flush shutters with luppam finish including applying luppam
coat over a primary coat and two coats of synthetic enamel paint of 1st grade and
approved brand and shade over a primary coat (Total 3 coats) including cost and
conveyance of all materials to site, cost of primer coat, brushes, and all labour
charges etc., complete. (APSS No. 1201, 1207 & 1212) for all floors.
D1
2.25 x 11
1.20
2.13
D2
2.25 x 3
1.05
2.13
63.26
15.10
78.36
FF,SF
D1
2.25 x
22
1.20
2.13
126.52
TF
D1
Main Door-MD
2.25 x
2.25 x
3
1
1.20
4.00
2.13
2.70
17.25
24.30
sqm
GF-AHDC
Page 40 of 517
#REF!
#REF!
42 Painting two coats with synthetic enamel paint 1st grade to new iron work including
cost and conveyance of all materials to site and all labour charges including lift
charges etc., complete for finished item of work. (SS NO. 1201,& 1212 & 1207) for
all floors.
GW
GW1
GW2
GW3
43
2
2
2
1
x
x
x
x
2
2
2
2
2.73
3.24
2.26
3.05
1.35
1.35
1.35
1.35
14.74
17.50
12.20
8.24
52.68 sqm
#REF!
Providing 110mm Dia P.V.C. down water take pipes 2.5mm thick and of 4 kg /
Sq.cm pressure of ISI marked including cost and conveyance of necessary P.V.C.
Bends, shoes, iron, clamps and all other accessories and fixing in position
including cost and conveyance of all materials to site including all labour charges for
fixing at site etc., complete or finished item of work.(APSS No.1328)
44
Providing and Fixing of expansion join filler board for Buildings , Columns , Beams
and Slabs Armour Board " sillfill including cost and convenyance of all materials to
site, all incidental, operational , labour charges etc., complete for finished item of
work as per approved drawing for all floors
45
46
47
48
248.00
Rmt
#REF!
35.00
Sqm
#REF!
192.00
Sqm
#REF!
31.00
Sqm
#REF!
0.00
Rmt
#REF!
50.00
Rmt
#REF!
155.57
46.08
27.62
18.96
10.55
57.64
56.88
11.21
384.50
Sqm
#REF!
Supplying, laying, aligning & jointing of RCC Hume Pipes of 300mm dia NP2 Class
including all necessary fixtures like collars of respective diametre including cost and
conveyance of all materials to site, sales and other taxes on all materials, lifting, placing and
fixing in position, all labour charges, curing etc complete for finished item of work.
49 Providing Plinth protection with a bed of 100mm thick PCC(1:5:10) using 40mm
size HBG metal and on top of PCC, 20mm thick granolithic concrete flooring with
CC(1:1:2) prop.using 6mm to 12mm size graded hard granite machine crushed
metal laid monolithically already laid, in alternate panels of size not exceeding 1.5
x 1.5 Mts. and providing 5mm thick glass strips between the pannels and finishing
the top surface to required smoothness and slopes including Grooves, thread lining
as directed by the Engineer - in - charge including cost and conveyance of all
materials to site including seigniorage charges, sales & other taxes on all
x charges
2
64.82
0.60
materials and operational & incidental and2 labour
like
mixing of cement
x 2including
19.20
concrete, laying, curing, lift charges etc., 2
complete
cost of CC bed0.60
for
finished item of work. (APSS No.701 & 710) 2
x 2
11.51
0.60
2
2
2
2
2
GF-AHDC
x
x
x
x
x
2
2
6
6
2
7.90
4.40
8.01
7.90
4.67
Page 41 of 517
0.60
0.60
0.60
0.60
0.60
50 Construction of Rain water harvesting structure as per the approved drawing and
design of size 2 x 1.5 m x 2.0 mm including earth work excavation of filling of 40 mm
size HBG metal up to 50% of volume, filling of 20 mm size 15% of colume.
Sonstruction of side walls in brickmasonry in CM (1:6) 230 mm thick and 450 mm
height, plastering the side walls in (1:6) 16 mm thick base coat and top coat of 4 mm
51 Filling
with Gravel
trenches,
sidesproviding
of foundations
and basement
with initial
in
thick with
dubara insponge
tinish,
coir mat
to avoid spillage
of lead
water
layers
not
exceeding
15cm
thick,
consolidating
each
deposited
layer
by
watering
and
including cost and conveyance of all materials to site and all albour charges etc.,
ramming
cost
andofconveyence
of water to the work site and all operational,
complete including
for finished
item
work.
incidental, labour charges, seignorage charges, hire charges of T & P etc., complete
for finished item of work. (APSS NO. 309 & 310)
Dormitory Halls
Toilets
Wash area
Wardens room cum Lounge
Clinic hall
Type-1 Stair case
Type-2 Stair case
Entrance Lobby
Corridor
Under entrance steps
1
1
1
1
1
1
1
1
1
1
X
X
X
X
X
X
X
X
X
X
10
4
2
1
1
2
1
1
1
1
7.67
5
8.00
5
15.75 3.275
7.67
5
7.67
5
4.56 3.07
7.67
5
7.67
5
63.32
2.5
7.00
1
1.90
1.90
1.90
1.90
1.90
1.90
1.90
1.90
1.90
1.90
or say
52 Filling with light weight cider material in sunken slabs including cost and conveyance
of all materials and labour charges etc. complete for finished item of work
2
53
8.00
0.15
4.00 Nos
#REF!
728.65
304.00
196.01
72.87
72.87
53.14
72.87
72.87
300.77
13.30
1,887.33
1,888.00 cum
#REF!
48.00 cum
#REF!
19.20
Rmt
#REF!
19.20
Rmt
#REF!
Drilling 25mm dia holes in Sheet Rock with Pneumatic Compessor including hire
chrges of T&P and labour charges etc., complete for finished item of work.
MB. No.326/A/MD, Pg. No.10
54
1
x 24
0.80
Grouting 25mm dia holes in Sheet Rock with neat cement slurry including cost and
conveyance of all materials and labour charges etc., complete, but excluding cost of
steel and its fabrication chares for finished item of work.
MB. No.326/A/MD, Pg. No.11
1
x
PART B
24
0.80
PART A+B
Asst. Engineer(HNK)
APEWIDC, WARANGAL
GF-AHDC
Page 42 of 517
Executive Engineer
APEWIDC, WARANGAL
Superintending
APEWIDC, H
HANAMKONDA(M) IN
Per
GF-AHDC
Amount
Page 43 of 517
GF-AHDC
Page 44 of 517
GF-AHDC
Page 45 of 517
GF-AHDC
Page 46 of 517
GF-AHDC
Page 47 of 517
1 Cum
#REF!
1 Cum
#REF!
GF-AHDC
Page 48 of 517
GF-AHDC
Page 49 of 517
GF-AHDC
Page 50 of 517
1 cum
GF-AHDC
#REF!
Page 51 of 517
GF-AHDC
Page 52 of 517
GF-AHDC
Page 53 of 517
1 cum
GF-AHDC
#REF!
Page 54 of 517
1 Cum
#REF!
1 cum
#REF!
1 cum
#REF!
GF-AHDC
Page 55 of 517
GF-AHDC
Page 56 of 517
GF-AHDC
Page 57 of 517
1 cum
#REF!
1 cum
#REF!
1 MT
#REF!
GF-AHDC
Page 58 of 517
GF-AHDC
Page 59 of 517
1 Sqm
#REF!
#REF!
1 cum
1 cum
1 cum
#REF!
GF-AHDC
Page 60 of 517
1 cum
#REF!
1 cum
1 cum
1 cum
#REF!
1 cum
#REF!
GF-AHDC
Page 61 of 517
1 sqm
1 sqm
1 sqm
#REF!
1 sqm
#REF!
1 sqm
1 sqm
1 sqm
#REF!
1 cum
#REF!
1 cum
#REF!
GF-AHDC
Page 62 of 517
1 cum
#REF!
1 sqm
1 sqm
1 sqm
#REF!
sqm
sqm
sqm
#REF!
1 cum
1 cum
1 cum
#REF!
GF-AHDC
Page 63 of 517
1 cum
1 cum
1 cum
GF-AHDC
#REF!
Page 64 of 517
1 cum
#REF!
1 cum
#REF!
1 cum
#REF!
1 cum
#REF!
GF-AHDC
Page 65 of 517
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1
1
1
1
Mt
Mt
Mt
Mt
#REF!
1 Mt
1 Mt
1 Mt
#REF!
GF-AHDC
Page 66 of 517
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
GF-AHDC
Page 67 of 517
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
GF-AHDC
Page 68 of 517
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
1 sqm
1 sqm
#REF!
GF-AHDC
Page 69 of 517
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
GF-AHDC
Page 70 of 517
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
GF-AHDC
Page 71 of 517
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
GF-AHDC
Page 72 of 517
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
GF-AHDC
Page 73 of 517
1 sqm
#REF!
1 Nos
#REF!
#REF!
No
1 Nos
GF-AHDC
#REF!
Page 74 of 517
1 Rmt
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
1 sqm
#REF!
GF-AHDC
Page 75 of 517
#REF!
1 Rmt
#REF!
1 Sqm
#REF!
1 Sqm
#REF!
1 Sqm
#REF!
Rmt
#REF!
Rmt
#REF!
1 Sqm
GF-AHDC
#REF!
Page 76 of 517
#REF!
1 cum
#REF!
1 cum
#REF!
1 Rmt
#REF!
1 Rmt
#REF!
#REF!
#REF!
erintending Engineer
PEWIDC, HYDERABAD
GF-AHDC
Page 77 of 517
WORKING ESTIMATE
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOOR District
Sl. No
Description
36149188.00
3 Internal Electrification
Sub Total:
3 Kitchen Block cum Dining
1 Civil Work
2
3 Internal Electrification
Sub Total:
4 Principal Quarter
1 Civil Work
2
3 Internal Electrification
Sub Total:
5 Teaching Staff Quarters (G + 2) 1 block
1 Civil Work
2
Excess
Less
#REF!
Due to
change of
Site &
Designs
743252.00
1395681.00
38288121.00
#REF!
44081148.00
#REF!
#REF!
#REF!
1042228.00
1784147.00
46907523.00
#REF!
8507495.00
#REF!
#REF!
#REF!
Due to
change of
Site &
Designs
Due to
change of
Site
156928.00
661112.00
9325535.00
#REF!
1866275.00
#REF!
#REF!
#REF!
Due to
change of
Site
156944.00
153548.00
2176767.00
#REF!
6574642.00
#REF!
606831.00
Remarks
#REF!
#REF!
Due to
change of
Site
3 Internal Electrification
Sub Total:
6
7
8
9
10
478393.00
7659866.00
2139322.00
648609.00
567478.00
1652103.00
787709.00
Due to
change of
Site
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#VALUE!
#VALUE!
#REF!
#REF!
#REF!
#REF!
0.00
0.00
11
12
13
#VALUE!
#VALUE!
0.00
0.00
#REF!
#REF!
154850.00
0.00
0.00
100000.00
500000.00
1000000.00
2000000.00
1000000.00
5554871.00
5554871.00
1110974.00
1110974.00
555487.00
100000.00
500000.00
1000000.00
2000000.00
1000000.00
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
0.00
0.00
0.00
0.00
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
0.00
0.00
0.00
0.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
311933.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Excess
Less
Difference
#REF!
#REF!
#REF!
Sub Total:
Deduct Tender Premium @ ( - ) 2.70% Less
14
15
16
17
18
19
20
21
22
23
24
Provision
Provision
Provision
Provision
Provision
Provision
Provision
Provision
Provision
Provision
25
for
for
for
for
for
for
for
for
for
for
site development
Transformer
Internal roads
furniture and equipment
Tender premium and price escalation
VAT @ 5%
Supervision Charges @ 5%
Seignorage Charges @ 1%
Cess @ 1%
Q.C Charges @ 0.5%
Asst. Engineer(HNK)
APEWIDC, Warangal
314818.00
629567.00
6739606.00
111097418.00
0.00
111097418.00
#REF!
#REF!
#REF!
#REF!
154850.00
Executive Engineer
APEWIDC, Warangal
Superintending Engineer
APEWIDC, Hyderabad
Chief Engineer
APEWIDC, Hyderabad
Units
Description of Work
Quantity
Unit
Unit
Rate (Rs)
CIVIL WORK
Earth work excavation for foundation of Septic
Tank and depositing the earth on bank with an
initial lead of 10m and lift of 2m in Loamy, and
clayey soils like Black cotton, red earth, ordinary
gravelly soils including shoring, strutting, sheeting,
planking and dewatering including hire charges of
T&P, labour charges etc., complete for finished item
of work. (APSS. No.308)
0 CUM
1 ONE CUM
132.35
0 CUM
1 ONE CUM
3413.65
0.00 CUM
1 ONE CUM
6401.60
Page 1
Quantity
Unit
Unit
Rate (Rs)
0 CUM
1 ONE CUM
5036.65
0 CUM
1 ONE CUM
#REF!
0 SQM
1 ONE SQM
1206.75
0 SQM
1 ONE SQM
999.15
Cum
1 ONE Cum
9477.10
0.00
Page 2
Quantity
Unit
Unit
Rate (Rs)
0 MT
1 ONE MT
#REF!
0 SQM
1 ONE SQM
337.25
0 Nos
1 ONE EACH
2295.05
0 Nos
1 ONE Nos
2552.95
Page 3
Description of Work
Quantity
Unit
Unit
Rate (Rs)
0 SQM
1 ONE SQM
Rs
Page 4
289.05
Page 5
0
0
0
Page 6
#REF!
Page 7
#REF!
Page 8
SPECIFICATION REPORT
Est.cost: Rs.1030.00 Lakhs
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM
(M) CHITTOOR District
Authority:
The work const. of Govt. Degree College at Kuppam in Chittoor dist was administratively
sanctioned for Rs. 1030.00 lakhs vide G.O.Rt.No. 2973 Finance (FMU Education) Dept., dt: 29
12-2015 . The Secretary to Govt. (B & IF), A.P., Hyderabad has accorded administrative sanction
for Rs. 1030.00 lakhs.
Ground Floor
Pricipal room
1 No
Ante room
1 No
Office room
1 No
Staff room
1 No
Labs
6 Nos
1 No
Open auditorium
1 No
Toilet blocks
2 units
Stair case
2 Nos
Portico
1 No
First Floor
Class rooms
7 Nos
Lunch rooms
2 Nos
1 No
PET room
1 No
Toilet blocks
2 units
Stair case
2 Nos
Lobby
1 No
Second Floor
Computer lab
Audio & Video room
Stair case
Head rooms
RCC water tank
:
:
:
:
:
1
1
2
2
1
No
No
Nos
Nos
No
Provisions:
The Detailed Estimates are prepared with following common provisions:
A)
2. P.C.C (1:5:10) prop: nominal mix for levelling course in foundations and as bed concrete
for flooring.
3. P.C.C (1:4:8) prop: nominal mix for foundations for columns.
4. VRCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine crushed
graded metal for Footings, Pedestals, Plinth beams and Columns up to plinth level.
5. Random Rubble Stone masonry in CM(1:8) prop, for basement.
6. Filling with useful available excavated earth in trenches, sides of foundations and fo
basement.
7. Flush pointing to RRS masonry in CM (1:3) for basement.
B)
Superstructure:
1. VRCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine crushed
graded metal for Columns, Roof Beams, Roof Slabs.
2. Providing HYSD bars Fe 415 for all diameters more than 6mm for VRCC & RCC work.
3. Providing Mild Steel Fe 250 for 6mm bars for VRCC & RCC work.
4. P.C.C (1:3:6) prop: nominal mix for Bed Blocks and Hold Fasts.
5. RCC (1:2:4) prop. Nominal mix using 12mm HBG machine crushed graded metal fo
Lintels, 50mm thick platforms.
6. RCC M 25 grade design mix ( by weigh batching), using 20mm HBG machine crushed
graded metal for sun shades, 7.5cm thick at fixed end and 5.0 cm thick at free end, o
any width as per approved plan .
7. PCC M20 grade Design Mix ( by weigh batching), using 20mm HBG machine crushed
gradedmetal for steps .
8. Brick masonry in CM(1:8) prop. using 2nd class traditional bricks for Superstructure.
9. Reinforced Brick masonry 115mm thick in CM(1:4) prop. using 2 nd class traditional brick
for Partition walls.
10. Plastering 12 mm thick in two coats, base coat 8mm thick in CM(1:6) and top coat 4mm
thick in CM(1:4) for even face of walls.
11. Plastering 20 mm thick in two coats, base coat 16mm thick in CM(1:6) and top coat 4mm
thick in CM(1:4) for uneven face of walls.
12. Ornamental Plastering to ceiling, 12 mm thick in single coat in CM(1:4).
13. Providing impervious coat over RCC roof slab, in side of septic tank to required slope
with CM (1:3) prop. 20 mm thick (average) mixed with water proofing compound.
14. Flooring with Polished Shabad/Tandur blue Slabas 15 to 18 mm thick (0.457M x 0.457M
set over a base coat of CM (1:8), 12mm thick over already laid C.C. bed or R.C.C. roo
slabs.
15. Providing Skirting to internal walls to 12.5 cm height with Rough shabad / Tandur Stone
slabs of minimum 40 mm thick (0.457 x 457M) slabs 15mm to 18mm thick.
16. Dadooing to walls with coloured glazed tiles 1st. quality of size not less than 300mm x
200mm.
17. Whiting to new walls and ceiling in two coats with Birla white or equavalent quality fo
internal walls.
18. Painting with Plastic emulsion grade -1 paint to exterior faces of new walls with 3 coats o
approved make shade and colour.
19. Painting to wood work, flush shutters with luppam finish.
20. Painting two coats with synthetic enamel paint 1st grade to new iron work.
21. Supply and Fixing of Collapseble Gate of Size 2.0X2.10 mtrs
22. Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with
Medium teak wood Frame
23. Supply and Fixing of Door with Single leaf shutter, Door Size 0.90x2.13 mtrs with
Medium Teak Wood Frame of sections size 75mm x 100mm with Flush Door Shutter Solid
Bond Wood black board type with commercial ply
24. Providing & Fixing of Openable Windows with Double shutter made of pre-painted stee
(Base Steel as per IS 513 of 0.6mm thick galvanized as per IS 277 with zinc of 150 GSM
primer coated with epoxy primer of 5-7 microns thick
25. Supply and fixing of MS Ventilators with sections made of MS angles of 25mm X 25mm X 3mm and
10mm X 10mm square rods ( Sizes: 1200 mm x 450 mm & 900 mm x 450 mm).
AMENITIES:
1) Sub-Estimate is prepared for Water supply and Sanitary Arrangements as per the
requirements based on approved plan.
CC roads
The Data of all the items are adopted as per the Revised Standard Data Part-II
(Buildings) and the rates are worked out based on current SSR i.e Building SSR 2014-2015
Cement and Steel rates are adopted as approved by the Committee of the Chief Engineers for
May, 2015
SPECIFICATIONS:
The Standard specifications as per APSS are adopted and the work will be carried ou
true to the relevant standard specification of APSS and as per the agreement conditions.
Quarries:
The nearest leads, quarries are adopted while preparing the Datas, and as per the
location of the site 0% allowance on labour is proposed towards Rural area allowence
14% towards overhead charges and contractors profit put together has been proposed in
the estimates which is as per the Revised Standard Data - Part-III (Buildings), ordered
by the Government of A.P vide G.O.Ms.No.49, IRRIGATION & CAD (PW-REFORMS
DEPARTMENT Dated: 2-3-2009, for adoption by all Engineering /Public Work
Departments and other organizations.
Lump sum amounts at the rate of 5% towards VAT has been added in the Abstracts of
the estimates ,, which is as per the Revised Standard Data - Part-III (Buildings), and the
same is provided at 5% of ECV.
The estimate is submitted for according technical sanction.
Executive Engineer
Dy. Executive Engineer
APEWIDC, CHITTOOR APEWIDC, MADANAPALLI
Superintending Engineer
APEWIDC, KADAPA
0.00 Lakhs
KUPPAM(V) of KUPPAM
provisions:
nt.
rk.
s.
e crushed graded metal for
ks for Superstructure.
n CM(1:4).
ew iron work.
Size 1.22x2.13 mtrs with
Sl.
No
1
2
GENERAL ABSTRACT
Name of the work : CONSTRUCTION OF GOVT.JUNIOR COLLEGE AT
GUDIPALLI(V), GUDIPALLI(M), IN CHITOOR DIST.
Name of Component
Ground Floor
Amount in Rs.
17085825
First Floor
10850537
Second Floor
3516470
238294
692246
1700465
3586912
1391625
2043828
41106202
2055310
10
11
12
205531
13
411062
14
411062
15
16
17
18
19
2877434
41106
400000
50000
250000
50000
20
21
300000
200000
22
L.S.
300000
23
L.S.
54342293
103000000
4000000
107000000
Or say
1070.00
Executive Engineer
APEWIDC, CHITTOOR
Superintending Engineer
APEWIDC, KADAPA
APEWIDC, KUPPAM
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CH
District
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
2
3
4
5
6
7
GROUND FLOOR
1 Cutting of gravel & leveling of ground by,Earth work excavation for foundations
(Mechanical Means) for buildings in ordinary soils and depositing on bank for all
lifts and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking,
strutting etc., and overheads & contractors profit complete for finished item of
work excluding dewatering charges etc., as per SS 20 B(APSS 308)
For building area
720.00
720.00
Or say
720.00 Cum
2 Earth work excavation and depositing on bank (manual means) with initial lead
of 10m and initial lift of 3m in Loamy & Clayey Soils like BC Soils, Red Earth &
Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour
charges such as shoring, strutting, sheeting, planking and dewatering including
cost of hire charges of T & P, labour charges etc., complete for finished item of
work excluding seignerage charges and dewatering charges etc., complete for
Foundation of Building.(APSS No. 308)
80.00
10.00
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
11
20
20
7
19
14
18
2
4
6
2.60
2.50
2.30
2.15
2.00
1.80
1.65
1.40
1.80
2.95
2.60
2.50
2.30
2.15
2.00
1.80
1.65
1.40
1.50
2.55
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
133.85
225.00
190.44
58.24
136.80
81.65
88.21
7.06
19.44
81.24
F1
For external walls
L/w's
1.05
1.05
1.80
7.94
1
1
1
1
1
1
1
x
x
x
x
x
x
x
1
1
2
4
2
4
1
46.17
64.63
9.75
21.48
24.40
6.08
7.00
0.75
0.75
0.75
0.75
0.75
0.75
1.60
0.60
0.60
0.60
0.60
0.60
0.60
0.25
20.78
29.08
8.78
38.66
21.96
10.94
2.80
4.18
0.75
0.60
3.76
11 of 517
0.90
F1
F2
F3
F4
F5
F6
F7
F8
CF1
CF2
For Watch men room
G.F.
Per
Unit
Rate
98.90
Measurements
Sl.
Description of item
No.
1
2
1
Deductions
F1
F1
F2
F3
F4
F5
F6
F7
F8
CF1
CF2
Deduct blasting qty
Nos.
3
x
4
3.08
5
0.75
6
0.60
x 4
x
6
x 15
x 10
x
7
x 12
x 10
x 18
x
2
x
4
x
6
1.05
2.6
2.5
2.3
2.15
2
1.8
1.65
1.4
1.8
2.95
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
QTY
Unit
7
G.F.
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
11
20
20
7
19
14
18
2
4
6
2.60
2.50
2.30
2.15
2.00
1.80
1.65
1.40
1.80
2.95
2.60
2.50
2.30
2.15
2.00
1.80
1.65
1.40
1.50
2.55
12 of 517
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
2.77
-1.89
1
-7.02
1
-16.88
1
-10.35
1
-6.77
1
-10.80
1
-8.10
1
-13.37
1
-1.26
1
-3.24
1
-7.97
-260.00
821.77
Or say
825.00 Cum
3 Earth work excavation for foundations for buildings in hard rock (requiring
blasting) and depositing on bank for all lifts and with an initial lead of 10m and
up to 3m depth including all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., and overheads & contractors profit
complete for finished item of work excluding dewatering charges etc., as per SS
20 B(APSS 308)
F1
F2
F3
F4
F5
F6
F7
F8
CF1
CF2
For Watch men room
Per
Unit
Rate
7.44
12.50
10.58
3.24
7.60
4.54
4.90
0.39
1.08
4.51
231.60
597.90
Measurements
Sl.
Description of item
No.
1
Nos.
3
1x
F1
4
1.05
5
1.05
D
6
0.10
Or say
QTY
Unit
Per
Unit
Rate
0.44
57.21
Cum
57.50
Cum
3627.55
Cum
8211.70
Cum
8573.00
A FOR FOOTINGS
F1
F2
F3
F4
F5
F6
F7
F8
CF1
CF2
For Watch men room
F1
B FOR PEDESTALS
P1
P2
P3
P4
P5
P6
P7
P8
P9
For Watch men room
Pedestal
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
11
20
20
7
19
14
18
2
4
6
x 4
2.40
2.30
2.10
1.95
1.80
1.60
1.45
1.20
1.60
2.75
0.9
2.40
2.30
2.10
1.95
1.80
1.60
1.45
1.20
1.30
2.35
0.9
31.68
50.26
39.69
11.98
24.62
14.34
11.35
0.86
2.08
19.39
0.25
Or say
0.81
207.06
207.50
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
11
32
6
10
25
2
19
2
24
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
1.78
5.18
0.97
1.62
4.05
0.32
3.08
0.24
2.92
0.38
0.45
0.60
Or say
0.41
20.58
21.00
1.50
1.53
2.23
6.59
0.5
0.475
0.45
0.45
0.4
0.4
0.3
0.3
0.25
0.5
13 of 517
Measurements
Sl.
Description of item
No.
1
2
C3
C4
C5
C6
C7
C8
C9
For Watch men room
C1
Nos.
3
1 x
1 x
1 x
1 x
1 x
1 x
0.78 x
1
6
10
25
2
19
2
24
4
0.45
0.45
0.45
0.45
0.45
0.3
0.3
5
0.3
0.3
0.3
0.3
0.3
0.3
0.3
6
1.55
1.55
1.60
1.60
1.70
1.70
1.75
0.23
0.3
1.50
Unit
x
x
x
x
1
1
2
4
46.17
64.63
9.75
21.48
0.75
0.75
0.75
0.75
0.10
0.10
0.10
0.10
3.46
4.85
1.46
6.44
1
1
1
x
x
x
2
4
1
24.4
6.08
7
0.75
0.75
1.6
0.10
0.10
0.10
3.66
1.82
1.12
0.10
0.10
0.63
0.46
G.F.
x 2
x 2
4.18
3.08
0.75
0.75
Deductions
P1
P2
P3
P4
P5
P6
P7
P8
P9
under flooring
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
8
15
6
10
10
2
14
2
24
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.45
0.45
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
-0.36
-0.68
-0.27
-0.45
-0.45
-0.09
-0.63
-0.07
-0.81
Lab-1
9.96
6.60
0.08
5.26
14 of 517
1.26
2.09
5.40
0.43
4.36
0.31
2.95
1
1
1
1
1
1
Per
Unit
Rate
0.41
26.02
Or say
26.50 Cum
6 Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to
(1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate)
using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved
quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including sales & other taxes on all materials, all
operational, incidental, and labour charges such as mixing, laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete but excluding seigniorage chargesfor finished item of
work for Foundations and Flooring Bed (APSS No. 402)
QTY
9477.10
Measurements
Sl.
Description of item
No.
1
Nos.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
2
2
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
1
2
1
1
4
8.95
9.07
9.00
6.60
6.60
6.60
6.00
13.27
6.60
2.36
2.36
2.36
12.41
4.86
4.00
2.58
45.19
18.30
7.60
5.63
6.57
3.6
5
6.60
6.60
6.60
5.80
5.85
5.88
4.92
6.60
4.11
2.10
2.17
2.10
6.83
4.00
1.70
1.70
2.17
2.17
6.00
3.58
6.46
3.2
6
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
2
2
2
2
1
2
2
2
2
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
7
7
7
7
1
6
2
6
16
2
2
2
3.34
3.04
6.38
6.38
4.627
3.1
6.38
2.17
2.17
4
7.06
5.9
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
2
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
Attached wc
Open auditorium
Toilet blocks
Hand wash
WC
passage
Passage
Staircase room
Portico
Watch room
Under plinth beem.
Plinth beam-P1
P1
P2
P3
P3
P4
P5
P6
P6
P7
P8
P9
Or say
G.F.
15 of 517
QTY
Unit
Per
Unit
Rate
4.73
9.58
9.50
3.06
3.09
3.10
2.36
7.01
2.17
0.40
0.41
0.40
6.78
3.11
1.09
0.70
15.69
6.35
3.65
3.22
3.40
0.92
1.08
0.98
2.05
2.05
0.11
0.86
0.59
0.60
1.60
0.18
0.32
0.27
126.77
127.00
Cum
3413.65
Measurements
Sl.
Description of item
No.
Nos.
QTY
1
2
3
4
5
6
7
7 Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard
blasted Granite stones from approved quarry including cost and conveyance of
all materials like Granite stones, cement, sand, water, etc., to site sales &
other taxes on all materials, all operational, incidental, and labour charges such
as cutting stones to required size and shape, mixing of cement mortar,
constructing masonry, curing etc., complete but excluding seigniorage charges
for finished item of work for foundation and basement (APSS No. 601 & 615)
below ground
For external walls
L/w's
1
1
1
1
1
x
x
x
x
x
1
1
2
4
2
46.02
64.48
9.60
21.33
24.55
0.45
0.45
0.45
0.45
0.45
0.60
0.60
0.60
0.60
0.60
12.43
17.41
5.18
23.04
13.26
6.23
0.45
0.60
6.73
x 2
4.18
0.45
0.60
2.26
x 2
3.08
0.45
0.60
1.66
C1
0.45
0.45
0.80
-1.30
C2
15
0.45
0.45
0.83
-2.51
C3
0.45
0.45
0.85
-1.03
C4
10
0.45
0.45
0.85
-1.72
C5
10
0.45
0.45
0.90
-1.82
C6
0.45
0.45
0.90
-0.36
C7
14
0.45
0.45
1.00
-2.84
C8
0.3
0.45
1.00
-0.27
C9
24
0.3
0.45
1.05
-3.40
P1
P2
P3
P4
P5
P6
P7
P8
P9
above ground
For external walls
L/w's
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
8
15
6
10
10
2
14
2
24
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.10
0.08
0.05
0.05
0.00
0.00
-0.10
-0.10
-0.15
-0.22
-0.30
-0.08
-0.14
0.00
0.00
0.38
0.04
0.73
1
1
1
x 1
x 1
x 2
46.02
64.48
9.6
0.45
0.45
0.45
0.70
1.20
1.20
14.50
34.82
10.37
Deductions
G.F.
16 of 517
Unit
Per
Unit
Rate
8
Measurements
Sl.
Description of item
No.
1
2
Near open to sky
S/W's
Near open to sky
For Watch men room
Deductions
C1
C2
C3
C4
C5
C6
C7
C8
C9
QTY
Nos.
1
1
1
3
x 4
x 2
x 4
4
21.33
24.55
6.23
5
0.45
0.45
0.45
6
1.20
1.20
1.20
7
46.07
26.51
13.46
1
1
x 2
x 2
0.45
0.45
1.20
1.20
4.51
3.33
1
1
1
1
1
1
1
1
1
X
X
X
X
X
X
X
X
X
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.70
0.70
0.70
0.70
0.70
0.70
0.70
0.70
0.70
4.18
3.08
1
1
1
1
1
1
x
x
x
x
x
x
x 2
x 2
1
1
2
4
2
4
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.3
0.3
46.02
64.48
9.6
21.33
24.55
6.23
1.00
1.00
1.00
1.00
1.00
1.00
4.06
3.66
1.00
1.00
Or say
G.F.
17 of 517
2709.55
63.95
199.60
46.02
64.48
19.20
85.32
49.10
24.92
8.12
7.32
304.48
Or say
310.00 Sqm
9 Filling with useful available excavated earth (excluding rock) in trenches, sides
of foundations and basement with initial lead in layers not exceeding 15cm thick,
consolidating each deposited layer by watering and ramming including cost and
conveyence of water to work site and all operational, incidental, labour charges,
hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 &
310)
Same as Earth Work Quantity
Per
Unit
Rate
8
-1.13
-2.13
-0.85
-1.42
-1.42
-0.28
-1.98
-0.19
-2.27
209.02
Or say
210.00 Cum
8 Flush Pointing to CRS Masonry in CM(1:3) Prop: including cost and conveyance
of all materials like cement, sand, water etc., to site, including sales & other
taxes on all materials, all operational, incidental charges and labour charges
such as mixing mortar, finishing, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS 901,906)
above ground
For external walls
L/w's
8
15
6
10
10
2
14
2
24
Unit
825.00
825.00
Cum
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
1
2
3
4
5
6
7
10 Filling with Gravel in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including cost and conveyence of water to the work site
and all operational, incidental, labour charges, hire charges of T & P etc.,
completebut but excluding seignorage charges, for finished item of work. (APSS
NO. 309 & 310)
Lab-1
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
Attached wc
Open auditorium
Toilet blocks
Hand wash
WC
passage
65.74
59.07
119.72
118.80
38.28
38.61
38.81
29.52
87.58
27.13
4.96
5.12
4.96
84.76
38.88
13.60
8.77
196.12
79.42
Passage
45.60
Staircase room
40.31
1145.76
Or say
1150.00 Cum
11 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching )
using 20mm size (SS5) hard blasted granite machine crushed graded metal
(Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs.
of cement per 1 cum of concreteincluding cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but
excluding cost of steel and its fabrication charges for finished item of work but
excluding seigniorage charges (APSS No. 402 & 403)
G.F.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
4x
4x
1
1
2
2
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
1
2
9.96
8.95
9.07
9
6.6
6.6
6.6
6
13.27
6.6
2.36
2.36
2.36
12.41
4.86
4
2.58
45.19
18.3
7.6
5.63
7
7
6.6
6.6
6.6
6.6
5.8
5.85
5.88
4.92
6.6
4.11
2.1
2.17
2.1
6.83
4
1.7
1.7
2.17
2.17
6
3.58
3.34 0.23
3.04 0.23
18 of 517
Per
Unit
Rate
8
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.30
0.30
6.45
5.87
380.70
Measurements
Sl.
Description of item
No.
1
Nos.
2
P2
P3
P3
P4
P5
P6
P6
P7
P8
P9
For Watchmen room
3
2x
2x
1x
4x
2x
2x
2x
1x
1x
1x
7
7
1
6
2
6
16
2
2
2
1x
1x
2
2
G.F.
4
4
2
2
2
2
2
1
2
1
2
1
2
2
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
11
32
6
10
25
2
19
2
24
7
7
16
12
7
7
16
2
13
2
2
2
7
7
2
Unit
5
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
6
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
3.66 0.23
3.6 0.23
0.30
0.30
0.51
0.50
41.80
Or say
42.50
2.925
2.925
2.925
2.925
3.075
2.925
3.075
3.075
3.075
4.34
12.64
2.37
3.95
10.38
0.79
7.89
0.55
5.18
2.335
0.64
Or say
48.73
49.00
0.30
0.30
0.41
0.30
0.41
0.30
0.30
0.30
0.30
0.41
0.41
0.30
0.23
0.23
0.23
6.53
5.87
21.70
5.13
9.49
2.10
4.79
0.97
3.89
1.32
2.88
0.49
2.50
2.25
0.75
4
6.38
6.38
4.627
3.1
6.38
2.17
2.17
4
7.06
5.93
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.3
0.3
4
QTY
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.23
3.38
3.04
7.28
3.10
7.28
2.17
2.17
7.06
2.17
7.06
5.93
3.53
3.38
3.04
7.06
0.3
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.30
0.23
0.23
0.23
0.23
19 of 517
Per
Unit
Rate
6.16
6.16
0.32
5.13
1.76
1.80
4.79
0.55
0.97
0.82
Cum
10172.70
Cum
1135.68
Measurements
Sl.
Description of item
No.
1
2
staircase Mid landing
beam
For Watchmen room
Nos.
3
x
4
3.53
5
0.23
6
0.45
1
1
x
x
2
2
4.05
3.20
0.23
0.23
0.30
0.30
Or say
1
1
4
2
1
64.11
6.57
4.63
20.38
4.06
25.38
6.46
1.00
6.48
3.66
Or say
QTY
Unit
7
0.73
0.56
0.44
72.40
72.50
Cum
8731.00
1627.11
42.44
-18.52
-264.12
14.86
1401.77
1402.00 Sqm
1058.45
1364.10
6409.55
24.80
10.59
35.39
Or say
35.50 Sqm
12 Plain Cement Concrete M20 Design Mix ( by weigh batching ) using 20mm size
(SS5) hard blasted granite machine crushed graded metal (Coarse aggregate)
from approved quarry, using a minimum quantity of 350 kgs. of cement per 1
cum of concrete including cost and conveyance of all materials like cement,
fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all
materials including steel centering, shuttering, machine mixing, laying concrete,
lift charges, curing etc., complete but excluding seigniorage charges for finished
item of work for steps (APSS No. 402 )
Steps at entrance
stair case steps
4
22
22
x
x
x
0.5
0.5
0.5
6.46
1.50
1.50
1.55
1.50
0.3
0.30
0.30
0.15
0.15
0.15
0.58
0.74
0.74
2.07
Or say
2.50
Cum
13 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using
20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) for Lintels
Per
Unit
Rate
0.23
20 of 517
0.23
0.32
Measurements
Sl.
Description of item
No.
1
2
D2
D3
D4
W1
W2
GW
V2
3
x
x
x
x
x
x
x
4
1.5
1.35
1.05
1.8
1.05
2.3
1.2
5
0.23
0.23
0.115
0.23
0.23
0.23
0.23
6
0.15
0.15
0.15
0.15
0.15
0.15
0.15
19
2
14
55
15
2
19
Unit
1
1
1
x
x
x
1
2
2
6.00
4.92
9.50
0.23
0.23
0.23
3.175
3.070
3.175
4.38
6.95
13.87
S/W in Lab-1
L/W in Lab -2
1
1
x
x
2
2
6.38
8.49
0.23
0.23
3.070
3.175
9.01
12.40
S/W in Lab-2
L/W in Lab -3,5
1
2
x
x
2
2
6.38
8.61
0.23
0.23
3.070
3.175
9.01
25.15
S/W in Lab-3,5
L/W in Lab -4,6
2
2
x
x
2
2
6.38
8.54
0.23
0.23
3.070
3.175
18.02
24.95
S/W in Lab-4,6
L/W in open auditorium
1
1
x
x
2
1
6.38
11.94
0.23
0.23
3.070
3.175
9.01
8.72
5.92
0.23
3.070
8.36
1
1
x
x
3
2
3.88
12.58
0.23
0.23
3.175
3.175
8.50
18.37
0
1
x
x
2
2
6.38
5.65
0.23
0.23
3.070
3.175
0.00
8.25
0
1
x
x
2
2
6.38
5.62
0.23
0.23
3.070
3.175
0.00
8.21
2
1
x
x
2
2
6.38
5.65
0.23
0.23
3.070
3.175
18.02
8.25
6.38
0.23
3.070
9.01
4.64
0.23
3.070
13.11
2
1
2
x
x
x
2
2
2
6.52
3.77
2.17
0.23
0.23
0.23
3.175
3.175
3.175
6.76
6.76
6.76
21 of 517
Per
Unit
Rate
0.98
0.09
0.25
3.42
0.54
0.16
0.79
6.55
Or say
7.00
Cum
14 Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size
290x225x140mm with compressive of 50 Kgs / Sqcm from approved source
including cost and conveyance of all materials like cement, sand, fly ash bricks,
water etc., to site, including sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS No. 501 & 504).
G.F.
1
1
1
1
1
1
1
Nos.
QTY
9412.50
Measurements
Sl.
Description of item
No.
1
Nos.
2
1
1
3
x
x
x
2
2
2
4
5.38
3.58
7.06
5
0.23
0.23
0.23
6
3.075
3.175
3.175
6.76
6.76
6.76
2
2
1
2
2
1
1
1
x
x
x
x
x
x
x
x
7
7
2
7
7
2
2
2
3.38
3.04
7.06
3.38
3.04
7.06
3.60
3.20
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.815
0.815
0.815
0.900
0.900
0.900
2.335
2.335
6.76
6.76
6.76
6.76
6.76
6.76
6.76
6.76
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
19
2
14
55
15
2
19
6
1
19
2
14
55
15
2
19
6
1.5
1.35
1.05
1.8
1.05
2.3
1.2
0.23
6
1.2
1.05
0.75
1.5
0.75
2
0.9
0.23
0.23
0.23
0.115
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
2.70
2.13
2.13
2.13
1.35
1.35
1.35
0.45
2
Stair case
QTY
Unit
7
Per
Unit
Rate
8
Dwarf walls
Deductions of Lintels
OVER DOORS & WINDOWS
CG
1
D2
1
D3
1
D4
0
W1
1
W2
1
GW
1
V2
1
bed blocks for rooms
38
CG
1
D2
1
D3
1
D4
0
W1
1
W2
1
GW
1
V2
1
-0.32
-0.98
-0.09
0.00
-3.42
-0.54
-0.16
-0.79
-1.81
-3.73
-11.17
-1.03
0.00
-25.62
-3.49
-1.24
-1.77
280.06
say
281.00 Cum
15 Reinforced Fly Ash Brick Masonry 10cm thick for partition walls in CM (1:4) prop:
Fly Bricks of size 290x100x140mm with compressive of 50 Kgs / Sqcm from
approved source and placing 2nos. of 6mm dia MS bars embedded in every 3rd
layer with free ends of reinforcement keyed into mortar joints of the main brick
work whereever applicable including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing cement mortar,
constructing masonry, scaffolding charges, lift charges, curing, etc., but
excluding cost and conveyance of steel and its fabrication charges & seignerage
charges complete for finished item of work. (APSS No. 501 & 509).
toilet blocks
G.F.
22 of 517
5359.40 1
Measurements
Sl.
Description of item
No.
1
Nos.
3
x
3
x
3
x
4
x
4
x
2
x
2
x
1
x
2
x
14
4
1.50
1.10
1.30
1.10
1.72
2.10
2.17
2.36
0.75
6
2.50
2.50
2.50
2.50
2.50
2.50
2.50
2.50
2.13
QTY
Unit
7
L/w's
1
11.25
1
8.25
2
26.00
2
22.00
1
8.60
Record room
1
10.50
1
5.43
1
11.80
deducting door-D4
1
-22.37
81.46
Or say
82.00 Sqm
16 Reinforced cement concrete with M 20 grade Design mix ( by weigh batching )
using 20mm size (SS 5) machine crushed hard blasted granite graded metal
(coarse aggregate) from approved quarry using a minimum quantity of 350 Kg
of cement per 1 Cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (sand) ,coarse aggregate, water etc. to site and
cost of
all materials including centering using Cashewrina Ballies and
Wooden runners & staging including all bracings, cross members etc.,
shuttering, machine mixing, laying concrete, for sunshade of 7.5cm thick at
fixed end and 5cm thick at free end with an average thickness of 6.25cm
including labour charges for mixing, laying, curing etc., complete but
excluding cost of steel and its fabrication charges but excluding seigniorage
charges for finished item of work For sunshade of 625 mm thick
Per
Unit
Rate
8
621.80 1
1
1
1
1
x
x
x
x
41
2
2
2
1.8
19.76
17.76
5.26
0.60
0.60
0.60
0.60
Or say
44.28
23.71
21.31
6.31
95.62
96.00
slab 75 mm thick
for lab platform
G.F.
9.00
0.900
48.60
13.20
0.900
71.28
23 of 517
Sqm
703.70
Measurements
Sl.
Description of item
No.
1
Nos.
QTY
Unit
7
119.88
Or say
120.00 Sqm
18 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using
20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) For 25 mm thick racks
1.50
0.40
Or say
6.00
6.00
6.00
Per
Unit
Rate
8
757.90
Sqm
463.95
Sqm
337.25
19 Providing impervious coat over RCC roof slab to required slopes with CM (1:3)
prop. 20mm thick (average) mixed with water proofing compound manufactured
by reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of
cement, laid over roof slab when it is green, finished smooth with a floating coat
of neat cement and thread lining at regular intervals of 45cmx45cm including
cost and conveyance of all materials like cement, sand, water proofing
compound, water etc., to site,
sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar, laying,
rounding off at junctions of wall and slab, rendering smooth with thread lining,
curing, lift charges, etc., complete but excluding seigniorage charges for
finished item of work (APSS No. 901 & 903).
Ground floor over
portico
6.57
6.46
42.44
Or say
42.44
43.00
D2
D3
D4
W1
W2
V2
G.F.
19
2
14
55
15
19
x
x
x
x
x
x
6
6
6
4
4
4
0.23
0.23
0.115
0.23
0.23
0.23
0.23
0.23
0.115
0.23
0.23
0.23
24 of 517
0.15
0.15
0.15
0.15
0.15
0.15
0.90
0.10
0.17
1.75
0.48
0.60
Measurements
Sl.
Description of item
No.
1
Nos.
QTY
Unit
7
3.99
Or say
4.00
Cum
21 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete but excluding seigniorage charges for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904)
L/w in Entrance area
S/W in Entrance area
L/W in Lab -1
S/W in Lab-1
L/W in Lab -2
1
1
1
1
1
x
x
x
x
x
1
2
2
2
2
6.00
4.92
9.96
6.60
8.95
3.50
3.50
3.50
3.50
3.50
21.00
34.44
69.72
46.20
62.65
S/W in Lab-2
L/W in Lab -3,5
S/W in Lab-3,5
L/W in Lab -4,6
S/W in Lab-4,6
L/W in open auditorium
L/W in principal room
S/W in principal room
L/W in office room
S/W in office room
L/W in staff room
S/W in staff room
L/W in Ncc room
S/W in Ncc room
L/W in Ncc coordinator
S/W in Ncc coordinator
L/W in toilet blocks
1
2
2
2
1
1
1
1
1
1
1
1
1
2
1
1
2
2
1
2
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
6.60
9.07
6.60
9.00
6.60
6.83
6.6
4.11
13.27
6.6
5.8
6.6
5.85
6.6
5.88
6.6
4.64
6.515
3.77
5.38
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
46.20
126.98
92.40
126.00
46.20
47.81
46.20
28.77
92.89
46.20
40.60
46.20
40.95
92.40
41.16
46.20
64.96
91.21
26.39
75.32
3.58
3.50
25.06
3.38
1.10
52.05
3.04
1.10
46.82
7.06
1.10
15.53
3.38
0.90
42.59
3.04
0.90
38.30
Dwarf walls
G.F.
25 of 517
Per
Unit
Rate
8
5161.95
Measurements
Sl.
Description of item
No.
QTY
Nos.
4
7.06
3
x
6
0.90
7
12.71
1.5
2.80
25.20
1.1
2.80
18.48
1.3
2.80
58.24
1.1
2.80
49.28
1.72
2.80
19.26
2.1
2.80
23.52
2.17
2.80
12.15
2.36
2.80
26.43
deducting door-D4
14
0.75
2.13
-22.37
3.6
2.75
19.80
3.2
2.75
17.60
1.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
4
x
x
x
x
x
x
x
x
x
1
19
2
14
55
15
2
19
5
6.00
1.20
1.05
0.75
1.50
0.75
2.00
0.90
0.5
Unit
Per
Unit
Rate
8
toilet blocks
L/w's
Record room
0.4
12.00
2.7
2.13
2.13
2.13
1.35
1.35
1.35
0.45
0.4
-8.10
-24.28
-2.24
-11.18
-55.69
-7.59
-2.70
-3.85
4.00
1880.08
Or say
1890.00 Sqm
22 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete but excluding seigniorage charges for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904)
out side L/w's
out side c/w 's
in varandah L/w's
1
1
1
1
1
2
2
x
x
x
x
x
x
x
x 7
2
2
2
2
2
4
4
64.11
25.38
45.66
18.30
7.06
4.63
1.00
3.38
26 of 517
3.60
3.60
3.475
3.475
3.475
3.60
3.60
0.9
461.59
182.74
317.34
127.19
49.07
133.34
28.80
42.59
289.05
Measurements
Sl.
Description of item
No.
1
2
2
1
above
beam
Nos.
3
x 7
x 2
4
3.04
7.06
x
x
x
x
7
7
2
2
QTY
0.9
0.9
7
38.30
12.71
3.38
3.04
7.06
6
1.47
1.47
1.47
3.60
69.56
62.56
41.51
86.40
out
x 2
4.06
2.88
23.35
x 2
3.66
2.88
21.05
-8.10
-24.28
-2.24
-11.18
-55.69
-7.59
-2.70
-3.85
82.37
1664.83
Or say
1665.00 Sqm
23 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in
CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including
cost and conveyance of all materials like cement, sand, water etc., to site, sales
& other taxes on all materials,all operational, incidental and labour charges such
as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete for Even Surfaces of Wall but excluding seigniorage charges for
finished item of work. (APSS 901,903 & 904)
Lab-1
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
G.F.
Per
Unit
Rate
8
brusummer
2
2
2
side 2
Stair case
walls
Unit
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
1
19
2
14
55
15
2
19
52
1
1
2
2
1
1
1
1
1
1
1
1
6.00
1.20
1.05
0.75
1.50
0.75
2.00
0.90
0.22
9.96
8.95
9.07
9.00
6.60
6.60
6.60
6.00
13.27
6.60
2.36
2.36
2.7
2.13
2.13
2.13
1.35
1.35
1.35
0.45
3.60
6.60
6.60
6.60
6.60
5.80
5.85
5.88
4.92
6.60
4.11
2.10
2.17
27 of 517
65.74
59.07
119.72
118.80
38.28
38.61
38.81
29.52
87.58
27.13
4.96
5.12
289.05 1
Measurements
Sl.
Description of item
No.
1
2
Attached wc
Open auditorium
Toilet blocks
Hand wash
WC
passage
Passage
Staircase room
Portico
Beam bottom
Staircase waist slab
bottom
landing slab bottom
Sunshades bottom &
top
Brusummer beam
Nos.
QTY
Unit
4
2.36
12.41
4.86
4.00
2.58
45.19
18.30
7.60
5.63
6.57
6.38
2.17
4.00
5
2.10
6.83
4.00
1.70
1.70
2.17
2.17
6.00
3.58
6.46
1
1
1
1
1
1
1
1
0
0
1
1
2
3
x
1
x
1
x
2
x
2
x
2
x
2
x
2
x
1
x
2
x
1
x 21
x 46
x
2
1.50
4.96
84.76
38.88
13.60
8.77
196.12
79.42
45.60
0.00
0.00
30.82
22.96
24.00
1
2
x
x
2
38
3.58
1.80
1.50
0.60
10.74
82.08
1
1
1
2
2
2
1
x
x
x
x
x
x
x
7
7
2
2
2
2
1
3.38
3.05
7.06
19.76
17.76
5.26
3.6
0.23
0.23
5.44
4.91
3.25
open to sky sunshade
0.6
47.42
0.6
42.62
0.6
12.62
Watch men room
3.2
11.52
1403.83
Or say
1410.00 Sqm
24 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using
20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) for 50 mm thick slab
0.23
0.23
0.23
2.50
0.30
1.50
1.00
0.30
0.30
1.80
2.00
Or say
G.F.
Per
Unit
Rate
28 of 517
Sqm
304.49
610.95
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
1
2
3
4
5
6
7
25 Flooring with Polished bethamcherla colour stone of 25 mm thick
(0.254x0.254M) set over a base coat of CM (1:8), 12mm thick (joints of stone
must be flushed) over C.C. bed already laid or R.C.C. roof slab only after it is
properly cured, cleaned, moistered and where necessary treated with neat
grey cement slurry of honey like consistency spred at3.3 kgs of cement for 1
sqm. and jointed with neat cement paste to full depth, including cost and
conveyance of all materials like cement, sand, water, flooring stones etc. to site,
sales and other taxes on all materials, all operational, incidental and labour
charges such as dressing of flooring stones to the required sizes, mixing of
cement mortar, laying, jointing, curing, lift charges etc., complete but excluding
seigniorage charges for finished item of work.(APSS No.703 & 701)
Lab-1
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
Attached wc
Open auditorium
passage
Passage
Staircase room
Portico
landing slab bottom
Watch men room
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
2
2
1
1
1
1
1
1
1
1
1
1
2
2
1
2
1
2
1
9.96
8.95
9.07
9
6.6
6.6
6.6
6
13.27
6.6
2.36
2.36
2.36
12.41
45.19
18.3
7.6
5.63
6.57
3.58
3.6
6.6
6.6
6.6
6.6
5.8
5.85
5.88
4.92
6.6
4.11
2.1
2.17
2.1
6.83
2.17
2.17
6
3.58
6.46
1.5
3.2
29 of 517
65.74
59.07
119.72
118.80
38.28
38.61
38.81
29.52
87.58
27.13
4.96
5.12
4.96
84.76
196.12
79.42
45.60
40.31
42.44
10.74
11.52
1149.21
Or say
G.F.
Per
Unit
Rate
1150.00 Sqm
947.10
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
1
2
3
4
5
6
7
26 Providing skirting to internal walls 12.5 Cm high with Polished bethamcherla
colour stone of 25 mm thick (0.254x0.254M) with length equal to flooring stones
set over a base coat of CM (1:3), 12mm thick with cement slurry of honey like
consistency spread @ 3.3 Kgs per sqm and jointed with neat cement paste
mixed with pigment of matching shade to full depth (joints of stone should be
flushed), including cost and conveyance of all materials like cement, sand,
water, flooring stones etc. to site, sales and other taxes on all materials, all
operational, incidental and labour charges such as dressing of flooring stones to
the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges
etc., complete but excluding seigniorage charges for finished item of work.
(APSS No.701 & 707)
Lab-1
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
Attached wc
Open auditorium
passage
4.14
3.89
7.84
7.80
3.10
3.11
3.12
2.73
4.97
2.68
1.12
1.13
1.12
4.81
23.68
10.24
Passage
3.40
Staircase room
4.61
Portico
3.26
landing slab bottom
2.54
Watch men room
1.70
100.96
Or say
101.00 Sqm
27 Supplying and fixing of Polished Black Kadapa slabs minimum of 15 mm thick
(0.457M x 0.457M) in Single piece with the edges flat nosed and set over a base
coat of CM (1:8), 12mm thick, and fixing in position with neat cement paste
including cost and conveyance of all materials like cement, sand, water, stones
etc. to site, seigniorage charges, sales and other taxes on all materials, all
operational, incidental and labour charges such as dressing of stones to the
required sizes, mixing of cement mortar, fixing in position, curing, lift charges
etc., complete for finished item of work for Treads (APSS No.701 & 707)
staircase steps
G.F.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
2
2
1
1
1
1
1
1
1
1
1
1
2
2
1
2
1
2
1
33.12
31.10
31.34
31.20
24.80
24.90
24.96
21.84
39.74
21.42
8.92
9.06
8.92
38.48
94.72
40.94
27.20
18.42
26.06
10.16
13.60
22
1.50
Per
Unit
Rate
8
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.300
30 of 517
19.80
999.05
Measurements
Sl.
Description of item
No.
1
2
Entrance
Nos.
3
x
4
6.57
5
0.300
QTY
Unit
Per
Unit
Rate
7.88
27.68
Or say
28.00
Sqm
615.12
1259.90
staircase
Entrance
2
1
10.35
3.94
14.29
Or say
14.50 Sqm
29 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs
with Sal wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm
long 2 Nos, MS powder coated Handles 150mm long 2 Nos, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges
6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos,
MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
x
x
1.50
6.57
0.150
0.150
19.00
Or say
19.00 Each 11672.45
30 Supply and Fixing of Door with Double leaf shutter, Door Size 1.05x2.13 mtrs
with Sal Wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm
long 2 Nos, MS Powder coated Handles 150mm long 2 Nos, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges
6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos,
MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
1
23
4
19
2
Or say
G.F.
31 of 517
2.00
2.00
Each 10741.70
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
1
2
3
4
5
6
7
31 Providing and fixing factory made polyvinyl chloride (PVC) Door Frame of the
size 50 x 47mm with a wall thickness of 5mm, made out of extruded 5mm rigid
PVC foam sheet, mitre cut at two corners and joined with 2nos. of 150mm long
brackets of 15x15mm M.S. square tube. The two vertical door profiles are to be
reinforced with 19x19mm M.S. Square tube of 19 gauge. The door frame shall
be fixed to the wall using 65/100mm long M.S. Screws through the frame by
using PVC fasteners. A minimum of 4nos. of screws to be provided for each
vertical member & minimum 2nos. for horizontal member etc. complete as per
manufacturers specification and direction of Engineer-in-Charge for finished
item of work
Toilet
14
x 14
5.00
20.38
20.38
Or say
20.50 Sqm
33 Reinforced cement mortar Facia 5 cm thick in CM (1:3) for drop walls, Fins &
staircase railing with rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara spong finishing including cost & conveyence of
all materials to site, including sales and other taxes on all materials and all
operational, incidental charges such as labour charges, like mixing cement
mortar, scaffolding charges, lift charges, curing, for making 50 mm thick RCM
Paradah walls (RCM Drop walls) including tying Rabbit (chicken) wire mesh to
the existing mild steel / HYSD Steel reinforcement applying mortar lumps,
finishing, plastering to both faces, sponge finishing etc complete for finished
item of work but excluding cost of steel and its fabrication charges and
seigniorage charges in All Floors
for hand wash
for stair case
70.00
70.00
Or say
70.00 Rmt
32 Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm
for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall have a coat
of steel primers of approved make and manufacture. M.S. frame shall be
covered with 5mm thick heat moulded PVC C channel of size 30 x 50mm
forming stiles, and 5mm thick, 75mm wide PVC sheets for top rail, lock rail &
bottom rail on either side, and 10mm (5mm x 2) thick, 20mm wide cross PVC
sheet as gap insert for top rail & bottom rail. Panelling of 10mm thick PVC sheet
to be fitted in the M.S. frame welded / sealed to the stiles & rails with 30mm
wide x 5mm thick PVC sheet beading on either side, and joined together with
solvent cement adhesive etc. An additional 5mm thick PVC strip of 20mm width
is to be stuck on the interior side of the C Channel using PVC solvent adhesive.
Complete as per direction of Engineer-in-charge, manufacturers specification &
drawing for finished item of work .
Toilet
1
2
x
x
0.70
2
2
369.25
2683.60
1604.30
2.080
2.45
4.00
1.00
1.00
Or say
G.F.
Per
Unit
Rate
32 of 517
4.89
16.00
20.89
21.00
Sqm
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
1
2
3
4
5
6
7
34 Flooring with Ceramic Tiles of 7.3mm thick 1st. quality of any shade as
approved by Engineer - in - charge set over a base coat of CM (1:8), 12mm
thick laid over flooring bed / V.R.C.C. slab, with neat cement slurry of honey like
consistency spread at the rate of 3.3 Kgs of cement per Sq.m and jointed with
neat white cement paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like cement, sand, water, ceramic
tiles etc. to site, sales and other taxes on all materials, all operational, incidental
and labour charges such as mixing of cement mortar, laying, curing, lift charges
etc., complete but excluding seigniorage charges for finished item of work.
(APSS No.701 & 707) in All Floors
toilet rooms
11.44
4.95
8.35
9.91
toilet passage
6.17
9.14
for hand wash
13.92
63.88
Or say
65.00 Sqm
35 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as
approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm
thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water, tiles, etc. to site, sales
and other taxes on all materials, C921 such as mixing of cement mortar, laying
in position, curing, lift charges etc., complete but excluding seigniorage charges
for finished item of work (APSS No.701 & 707) in All Floors
toilet rooms
toilet passage
2
1
1
1
1
1
1
x
x
x
x
x
x
x
4
3
2
2
1
1
2
1.10
1.10
1.74
2.10
1.27
1.88
1.74
2
1
x 4
x 3
4.80
5.20
x 2
8.28
1
1
1
1
0.5
x
x
x
x
x
8.92
12.26
13.48
11.48
0.75
2
1
1
2
14
Portico
G.F.
6.57
1.300
1.500
2.400
2.360
4.860
4.860
4.00
1.500
1.500
1.500
57.60
23.40
24.84
1.500
1.500
26.76
18.39
20.22
34.44
-7.88
197.78
Or say
200.00 Sqm
36 Plastering with CM(1:4) Prop: 20mm thick in single coat including cost and
conveyance of all materials like cement, sand, water etc., to site, including sales
& other taxes on all materials, all operational, incidental charges and labour
charges such as mixing mortar, finishing, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS 901,906)
for hand wash
D6
Per
Unit
Rate
875.85
540.35
1.500
1.500
1.50
6.46
33 of 517
42.44
42.44
Measurements
Sl.
Description of item
No.
1
Nos.
QTY
Unit
6
7
Or say
45.00 Sqm
37 Providing and Fixing of openable double shutter windows made of pre-painted
steel (Base steel as per IS 513 of 0.58 mm thick galvanized as per IS 277 with
Zinc of 120 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish
painted with a polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer. Section for outer frame should be of 48x50mm,
centre mullion should be of 48x50mm, section for shutter should be of 48x25mm
and fixed panel beading section should be 12x12mm. Outer frame and mullions
to have rebate for Galvalume corrugated sheet shutter and a 20mm provision
for Guard bars/Grills. The sections are to be cut to length metre joined with
corner bracket. Centre mullion is to be fixed with mullion cap. Handle, stay, 2
nos. of Stainless Steel heavy duty Pivot hinges shall be provided per shutter.
The windows should be panelled with 0.60 mm thick Galvalume corrugated
sheet having tensile strength of 550 MPA,(BMS-W.55). The above frames
should be fixed to the concrete/masonry wall by means of self expanding
screws, Including 10mm Square guard bars with 6 (152.4mm) pitch etc.,
complete for finished item of work.
Per
Unit
Rate
8
188.35
1
1
x
x
55
15
1.50
0.75
1.35
1.35
111.38
15.19
126.56
Or say
127.00
38 Supply and fixing of M.S. Grills including cost and conveyance of all materials
and all labour charges etc., complete
for main gate of size
6.00 x 2.70m
GW - 2.00 x 1.35m
GW1 - 1.35 x 1.35m
V1 - 2.10 x 0.45m
V2 - 0.90 x 0.45m
V3 - 1.22 x 0.30 over D
1
1
1
1
1
1
x
x
x
x
x
x
1
2
4
8
8
15
500.00
65.00
45.00
25.00
15.00
7.00
500.00
130.00
180.00
200.00
120.00
105.00
23
9.00
207.00
Sqm
1442.00 Kg
G.F.
34 of 517
7915.60 1
74.20
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
1
2
3
4
5
6
7
39 Providing expansion joint treatment with ploy sulphide compound of approved
make of finsihed size 25 x 12 mm including making of 25mm x 12mm groove
and primer coat over finished groove with finishing of edges true to straight line
and level over the finished surface of expansion joint including cost and
convenyance of all materials to site, all incidental , operational , labour charges
etc., complete for finished item of work as per approved drawing ( for all floors
on top slab i.e, in the flooring and for internal vertical joints of grooves in
dadooing surface).
1
15.23
15.23
Or say
15.50 Sqm
40 Providing and Fixing of 24 guage alluminium sheet over expansion joint groove
of width 15cm fixed to walls / columns at one edge and resting over the other
blcok walls / columns concealing expansion joint with slotted holes for free edge
of aluminium sheet to faciliate free movement of aluminium sheet over the
finished surface of expansion joint and wall face using sheet metal screws with
nylon receiver complete including cost and convenyance of all materials to site,
all incidental , operational labour charges etc.,, complete for finsihed item of
work as per approved drawing ( for all floors for vertical joints and bottom of
slab).
1
25.38
25.38
329.50
493.10
457.90
975.65
0.300
0.300
10.00
10.00
Or say
10.00 No
43 Whiting to new walls and ceiling in two coats with Birla White or equavalent
quality to give an even shade after thoroughly brushing the surface to remove all
loose powdered materials including cost and conveyance of all materials and
water to site, sales & other taxes, all operational, incidental and labour charges
such as cleaning the surface, painting, curing etc., complete for finished item of
work for internal walls. (APSS No.901 & 908) in All Floors
10.00
G.F.
0.300
22.84
22.84
Or say
23.00 Sqm
42 Supplying , laying , aligning & jointing of RCC Hume Pipes of 300mm dia NP2
class including all necessary fixtures like collars of respective diameter including
cost and convenyance of all materilas to site, sales and othe taxes on all
materials , lifting, placing and fixing in position for finished item of work.
1
25.38
15.23
15.23
Or say
15.50 Sqm
41 Providing and Fixing of expansion joint filler board for Buildings , Columns ,
Beams and Slabs Armour Board " sillfill including cost and convenyance of all
materials to site, all incidental, operational , labour charges etc., complete for
finished item of work as per approved drawing for all floors
1
Per
Unit
Rate
1410.00
35 of 517
1410.00
Measurements
Sl.
Description of item
No.
1
Nos.
2
3
As per 12mm plastering area in Qty.
6
1890.00
Or say
QTY
Unit
Per
Unit
Rate
7
1890.00
3300.00
3300.00 Sqm
26.90
126.55
155.90
85.30
44 Painting to New walls with two coats of Plastic Emulsion paint of superior quality
of approved brand and shade over base coat of cement primer grade -I making
three coats in all to give an even shade after thoroughly brushing the surface to
remove all loose powdered materials, including cost and conveyance of all
materials, including cost and conveyance of all materials, cost of brushes, water
to site, etc., sales & other taxes, all operational, incidental and labour charges
such as scaffolding charges, lift charges, curing etc., complete for finished item
of work in all floors for Walls.(APSS No. 912) in All Floors
1665.00
1665.00
1665.00
Or say
1665.00 Sqm
45 Painting to New wood work with two coats of ready mixed synthetic enamel
paint first quality all shades to give an even shade over base coat Primer with
Luppam finishing after thoroughly brushing the surface to remove all remains
including cost and conveyance of all materials to site, sales & other taxes, all
operational, incidental and labour charges etc., complete for finished item of
work.(3 coats) (APSS No. 1201 & 1212).in All Floors
D2
D5
19 x
2 x
2.25
2.25
1.20
1.05
2.13
2.13
Or say
109.27
10.06
119.33
119.50
Sqm
46 Painting to New Iron work with two coats of ready mixed synthetic enamel paint
first quality all shades over an existing steel primer including cost and
conveyance of all materials to site, sales & other taxes, incidental, operational
and all labour charges etc., complete for finished item of work. (APSS No. 1201,
1207 & 1212).in All Floors
Entrance gate
6.00
2.70
GW
GW 1
V1
V2
V3
V4
1
1
1
1
1
1
x
x
x
x
x
x
2
4
8
8
15
23
2.00
1.35
2.10
0.90
1.20
1.50
1.35
1.35
0.45
0.45
0.30
0.30
16.20
5.40
7.29
7.56
3.24
5.40
10.35
55.44
Or say
55.50 Sqm
47 Ornamental borders by providing 20 mm thick raised bands of 50 mm wide in
plain cement mortor bands in CM(1:4) including cost and conveyence of all
materials and labou charges for finished item of work.
bands for columns
for portico
G.F.
1
1
x
x
96
2
0.80
16.00
36 of 517
76.80
32.00
Measurements
Sl.
Description of item
No.
1
Nos.
QTY
Unit
7
108.80
Or say
109.00 rmt
48 Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as
per IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required
sizes and shapes placing in position with cover blocks of approved size and
binding wire of 20SWG, forming grills for reinforcement work as per approved
designs and drawings including cost and conveyance of bars from approved
sources to site of work, including cost and conveyance of binding wire, cover
blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational,
incidental, and labour charges such as cutting, bending, placing in position, tying
etc., and sales & other taxes,on cost of all materials complete for finished item
of work (APSS No.126) in Ground floor
Footings qty
Pedastals qty
Plinth beem qty
Columns Qty
Roof Beams Qty
Roof Slab 125mm th
Waist Slab 175mm th
Lintels Qty
Sunshades Qty
207.50 cum @
21.00 cum @
42.50 cum @
75.50 cum @
72.50 cum @
1402.00 sqm @
35.50 sqm @
7.00 cum @
96.00 sqm @
80
130
130
150
150
11
15
120
15
say
16600
2730
5525
11325
10875
15422
533
840
1440
65290
65.29
66.00
Per
Unit
Rate
8
20.50
MT
47131.20
Rm
3702.91
kgs
49 Supplying and fixing of stainless steel hand railing as per approved drawing with
top rail of 64mm dia (outer) 2mm thick pipe, vertical balusters of 50mm dia 2mm
thick at 600mm c/c spacing (7 Nos)and 3 nos 25mm dia (outer) 1.6mm thick
stainless steel pipes below top rail with equal spacings and 50mm wide 8mm
thick SS plate for fixing vertical balusters at 600mm centre with 100x100mm
stainless steel base plate to be fixed to the steps with Anchor fasteners. The
rate should include providing and using bonding agent, drilling of 25mm holes of
fixing railing , polishing of all nos of railing thouroughly and also including cost
and conveyance of all materials, electrodes, welding charges, cost of all
consumables, labour charges such as for fabrication of SS pipes, buffing,
polishing etc., complete for finished item of work.
G.F.
2
2
x
x
2
2
4.00
1.50
37 of 517
16.00
6.00
22.00
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
1
2
3
4
5
6
7
50 Providing Antitermite treatment as per IS 6315 (Part - 2) 2001 (Preconstructional chemical treatment measures) along the internal & external
vertical faces of the columns, plinth beams, basement and top surface of the
basement filling below flooring bed as per the specified procedure conforming to
IS 6315 (Part-2) 2001 and other relevant approved specification duly using
Chlorpyriphos/ Lindane emulsifiable concentrate 20% with 1% concentration @
7.5 Liters/ sqm of the vertical surface & @ 5.0 Liters/ sqm of the horizontal
surface of the substructure to a depth of 500 mm around columns & 300 mm
deep around plinth beams, basements & floor filling area including excavation
channel along the wall & rodding etc & cost & conveyance of all materials to the
site, cost of labour for spraying, rodding etc complete for finished item of work
as per the approval of the Engineer-in-Charge
1310.00
1310.00 Sqm
Per
Unit
Rate
8
254.50
TOTAL >>>
Executive Engineer
APEWIDC, CHITTOOR
Superintending Engineer
APEWIDC, KADAPA
G.F.
38 of 517
Asst. Executiv
APEWIDC, K
Amount
9
Cum
G.F.
71208
39 of 517
Per
Unit
8
Amount
9
Cum
191070
Cum
155454
G.F.
40 of 517
Per
Unit
8
Amount
9
Cum
208584
Cum
1703928
Cum
180033
G.F.
41 of 517
Per
Unit
8
Amount
9
Cum
G.F.
251143
42 of 517
Per
Unit
8
Amount
9
Cum
G.F.
433534
43 of 517
Per
Unit
8
Amount
9
G.F.
44 of 517
Per
Unit
8
Amount
9
Cum
569006
Sqm
19825
Cum
164670
G.F.
45 of 517
Per
Unit
8
Amount
9
Cum
G.F.
437805
46 of 517
Per
Unit
8
Amount
9
Cum
432340
Cum
55648
G.F.
47 of 517
Per
Unit
8
Amount
9
Cum
632998
Sqm
1483947
Sqm
48426
Cum
16024
G.F.
48 of 517
Per
Unit
8
Amount
9
Cum
G.F.
65888
49 of 517
Per
Unit
8
Amount
9
Cum
G.F.
1505991
50 of 517
Per
Unit
8
Amount
9
Sqm
50988
Sqm
67555
G.F.
51 of 517
Per
Unit
8
Amount
9
Sqm
90948
Sqm
2784
Sqm
14502
G.F.
52 of 517
Per
Unit
8
Amount
9
Cum
G.F.
20648
53 of 517
Per
Unit
8
Amount
9
Sqm
G.F.
546305
54 of 517
Per
Unit
8
Amount
9
Sqm
G.F.
481268
55 of 517
Per
Unit
8
Amount
9
Sqm
429325
Sqm
1222
G.F.
56 of 517
Per
Unit
8
Amount
9
Sqm
G.F.
1089165
57 of 517
Per
Unit
8
Amount
9
Sqm
G.F.
100904
58 of 517
Per
Unit
8
Amount
9
Sqm
17223
Sqm
18269
Each
221777
Each
21483
G.F.
59 of 517
Per
Unit
8
Amount
9
Rmt
25848
Sqm
55014
Sqm
33690
G.F.
60 of 517
Per
Unit
8
Amount
9
Sqm
56930
Sqm
108070
G.F.
61 of 517
Per
Unit
8
Amount
Sqm
9
8476
Sqm
1005281
Kg
G.F.
106996
62 of 517
Per
Unit
8
Amount
9
Sqm
5107
Sqm
7643
Sqm
10532
Rmt
9757
G.F.
63 of 517
Per
Unit
8
Amount
9
Sqm
88770
Sqm
210706
Sqm
18630
Sqm
4734
G.F.
64 of 517
Per
Unit
8
Amount
9
Rmt
2235
MT
3110659
Rm
81464
G.F.
65 of 517
Per
Unit
8
Amount
9
Sqm
333395
17085825
G.F.
66 of 517
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOO
Measurements
Sl.
Description of item
No.
Nos.
3
L
4
B
5
QTY
D
6
Unit
2
7
FIRST FLOOR
1 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching /
Mixer ) using 20mm size (SS5) hard granite machine crushed graded metal
(Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs.
of cement per 1 cum of concreteincluding cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost
of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering , machine
mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) for columns in first floor
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
2.925
2.925
2.925
2.925
3.075
2.925
3.075
3.075
3.075
Or say
F.F.
4.34
12.64
2.37
3.95
10.38
0.79
7.89
0.55
5.18
48.09
48.50 Cum
4
4
x
x
7
7
3.38
3.04
0.23
0.23
0.3
0.3
6.53
5.87
RB3
16
7.28
0.23
0.405
21.70
RB4
12
3.1
0.23
0.3
5.13
RB5
7.28
0.23
0.405
9.49
RB6
2.17
0.23
0.3
2.10
RB7
16
2.17
0.23
0.3
4.79
RB8
7.06
0.23
0.3
0.97
RB9
13
2.17
0.23
0.3
3.89
RB10
7.06
0.23
0.405
1.32
RB11
5.93
0.3
0.405
2.88
RB12
3.53
0.23
0.3
0.49
Brusummer beam
3.38
0.23
0.23
2.50
3.04
0.23
0.23
2.25
7.06
0.23
0.23
0.75
67 of 517
Pe
Un
Rate
8
1180.10
Sl.
Description of item
No.
1
2
staircase Mid landing
beam
Measurements
Nos.
3
1 x 2
L
4
3.53
B
5
0.23
D
6
0.45
QTY
Unit
Pe
Un
Rate
7
0.73
71.40
c FOR ROOF SLAB 125 MM THICK
Entire area
1 x 1
Duct area
1 x 4
open to sky
1 x 2
64.11
4.63
20.38
71.50 Cum
8979.25
Or say
1627.11
-18.52
-264.12
1344.47
1344.50 Sqm
1087.95
1400.15
6492.55
357.25
25.38
1
6.48
Or say
3.53
1.55
24.80
1.50
10.59
35.39
Or say
35.50 Sqm
2 Plain Cement Concrete M20 Design Mix ( by weigh batching ) using 20mm size
(SS5) hard blasted granite machine crushed graded metal (Coarse aggregate)
from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum
of concrete including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials
including steel centering, shuttering, machine mixing, laying concrete, lift charges,
curing etc., complete but excluding seigniorage charges for finished item of work
for steps (APSS No. 402 ) in First floor
22 x
0.5 1.5
0.3
0.15
0.74
22 x
0.5 1.5
0.3
0.15
0.74
1.485
Or say
1.50 Cum
3 Providing impervious coat over RCC roof slab to required slopes with CM (1:3)
prop. 20mm thick (average) mixed with water proofing compound manufactured by
reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement,
laid over roof slab when it is green, finished smooth with a floating coat of neat
cement and thread lining at regular intervals of 45cmx45cm including cost and
conveyance of all materials like cement, sand, water proofing compound, water
etc., to site, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing mortar, laying, rounding off at junctions of wall and
slab, rendering smooth with thread lining, curing, lift charges, etc., complete but
excluding seigniorage charges for finished item of work (APSS No. 901 & 903). In
first floor
On entire slab
989.50
989.50
Or say 990.00
F.F.
68 of 517
Sqm
Measurements
Sl.
Description of item
No.
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
4 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm
size (SS5)
hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement
per 1 cum of concrete including cost and conveyance of all materials like cement,
fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all
materials including centering using Cashewrina Ballies and Wooden runners &
staging including all bracings, cross members etc., shuttering , machine mixing,
laying concrete, lift charges, curing etc., complete but excluding cost of steel and
its fabrication charges but excluding seigniorage charges for finished item of work
(APSS No. 402 & 403) for Lintels in first floor
D2
D3
D4
W1
W2
GW
V2
0.98
0.09
0.25
3.42
0.54
0.16
0.79
6.23
Or say
6.50
Cum
5 Reinforced cement concrete with M 20 grade Design mix ( by weigh batching )
using 20mm size (SS 5) machine crushed hard blasted granite graded metal
(coarse aggregate) from approved quarry using a minimum quantity of 350 Kg of
cement per 1 Cum of concrete including cost and conveyance of all materials like
cement, fine aggregate (sand) ,coarse aggregate, water etc. to site and cost of
all materials including centering using Cashewrina Ballies and Wooden runners
& staging including all bracings, cross members etc., shuttering, machine mixing,
laying concrete, for sunshade of 7.5cm thick at fixed end and 5cm thick at free
end with an average thickness of 6.25cm including labour charges for
mixing, laying, curing etc., complete but excluding cost of steel and its
fabrication charges but excluding seigniorage charges for finished item of work for
First floor
for sun shades
On out side windows
W1
open to sky
1
1
1
1
1
1
1
x
x
x
x
x
x
x
19
2
14
55
15
2
19
1.5
1.35
1.05
1.8
1.05
2.3
1.2
0.23
0.23
0.115
0.23
0.23
0.23
0.23
41
1.8
0.6
44.28
1
1
1
x
x
x
2
2
2
19.76
17.76
5.26
0.6
0.6
0.6
23.712
21.312
6.312
95.62
96.00
69 of 517
0.15
0.15
0.15
0.15
0.15
0.15
0.15
Or say
F.F.
Pe
Un
Rate
Sqm
9739.45
727.85
Measurements
Sl.
Description of item
No.
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
6 Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size
290x225x140mm with compressive of 50 Kgs / Sqcm from approved source
including cost and conveyance of all materials like cement, sand, fly ash bricks,
water etc., to site, including sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS No. 501 & 504).for first floor
0.23
3.175
4.38
4.92
0.23
3.07
6.95
9.5
0.23
3.175
13.87
6.38
0.23
3.07
9.01
8.49
0.23
3.175
12.40
6.38
0.23
3.07
9.01
8.61
0.23
3.175
25.15
6.38
0.23
3.07
18.02
8.54
0.23
3.175
24.95
6.38
0.23
3.07
9.01
11.94
0.23
3.175
17.44
9.44
0.23
3.175
13.79
6.38
0.23
3.07
13.51
9.44
0.23
3.175
13.79
6.38
0.23
3.07
0.00
8.46
0.23
3.175
12.36
6.38
0.23
3.07
0.00
8.69
0.23
3.175
12.69
6.38
0.23
3.07
18.02
4.64
0.23
3.07
13.11
6.515
0.23
3.175
19.03
3.77
0.23
3.175
5.51
At passage
2.17
0.23
3.175
6.34
Stair case
5.38
0.23
3.075
15.22
3.58
0.23
3.175
5.23
7.06
0.23
3.175
10.31
2
2
1
2
2
1
x
x
x
x
x
x
7
7
2
7
7
2
3.38
3.04
7.06
3.38
3.04
7.06
0.23
0.23
0.23
0.23
0.23
0.23
0.815
0.815
0.815
0.9
0.9
0.9
8.87
7.98
2.65
9.80
8.81
2.92
Dwarf walls
Deductions of Lintels
F.F.
70 of 517
Pe
Un
Rate
8
Measurements
Sl.
Description of item
No.
1
2
OVER DOORS & WINDOWS
D2
1
D4
1
W1
1
W2
1
GW
1
V2
1
bed blocks for rooms
D2
1
D4
0
W1
1
W2
1
GW
1
V2
1
Nos.
3
F.F.
x
x
x
x
x
x
3
3
4
4
2
13
1.5
1.05
1.8
1.05
2.3
1.2
0.23
0.115
0.23
0.23
0.23
0.23
D
6
QTY
Unit
7
19
1.50
1.10
1.30
1.10
1.72
0.75
0.23
Pe
Un
Rate
8
0.15
0.15
0.15
0.15
0.15
0.15
11.25
8.25
26.00
22.00
8.60
deducting door-D4
-20.77
55.33
Or say
55.50
Sqm
8 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to
(1:3:6) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal
from from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including sales & other taxes
on all materials, all operational, incidental and labour charges such as mixing,
laying, curing concrete, etc., complete but excluding seigniorage charges for
finished item of work for Bed Blocks and Hold Fasts (APSS No. 402)
D2
1
1
2
2
1
1
19
13
58
11
2
18
B
5
-0.98
-0.24
-3.60
-0.40
-0.16
-0.75
-4.00
x 19
1.20
0.23
2.13
-11.17
x 13
0.75
0.23
2.13
0.00
x 58
1.50
0.23
1.35
-27.01
x 11
0.75
0.23
1.35
-2.56
x 2
2.00
0.23
1.35
-1.24
x 18
0.90
0.23
0.45
-1.68
296.32
Or say
297.00 Cum
7 Reinforced Fly Ash Brick Masonry 10cm thick for partition walls in CM (1:4) prop:
Fly Bricks of size 290x100x140mm with compressive of 50 Kgs / Sqcm from
approved source and placing 2nos. of 6mm dia MS bars embedded in every 3rd
layer with free ends of reinforcement keyed into mortar joints of the main brick
work whereever applicable including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing cement mortar,
constructing masonry, scaffolding charges, lift charges, curing, etc., but excluding
cost and conveyance of steel and its fabrication charges & seignerage charges
complete for finished item of work. (APSS No. 501 & 509). for first floor
toilet blocks
L/w's
x
x
x
x
x
x
L
4
5651.45 1
2.50
2.50
2.50
2.50
2.50
2.13
0.23
71 of 517
0.15
0.90
666.70 1
Measurements
Sl.
Description of item
No.
1
2
D4
W1
W2
GW
V2
6
4
4
4
4
Nos.
3
x 13
x 58
x 11
x 2
x 18
L
4
0.115
0.23
0.23
0.23
0.23
B
5
0.115
0.23
0.23
0.23
0.23
D
6
0.15
0.15
0.15
0.15
0.15
QTY
Unit
7
0.15
1.84
0.35
0.06
0.57
3.88
Or say
4.00
Cum
9 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with
Sal wood Frame of sections size 75mm x 100mm with Flush Door Shutter Solid
Bond Wood black board type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm long 2
Nos, MS powder coated Handles 150mm long 2 Nos, 300mm long M.S.Powder
Coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6Nos, 300 mm
long M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS Hold fasts
6Nos, Sales and Other Taxes cost and convenyance of all materials to site all
Labour charges such as Fixing of Door Frame on shutter Fixing in position , with
Hardware fixtures etc., complete for finsihed utem of work.
19.00
Or say 19.00
Each
10 Providing and Fixing of openable double shutter windows made of pre-painted
steel (Base steel as per IS 513 of 0.58 mm thick galvanized as per IS 277 with
Zinc of 120 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish
painted with a polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer. Section for outer frame should be of 48x50mm, centre
mullion should be of 48x50mm, section for shutter should be of 48x25mm and
fixed panel beading section should be 12x12mm. Outer frame and mullions to
have rebate for Galvalume corrugated sheet shutter and a 20mm provision for
Guard bars/Grills. The sections are to be cut to length metre joined with corner
bracket. Centre mullion is to be fixed with mullion cap. Handle, stay, 2 nos. of
Stainless Steel heavy duty Pivot hinges shall be provided per shutter. The
windows should be panelled with 0.60 mm thick Galvalume corrugated sheet
having tensile strength of 550 MPA,(BMS-W.55). The above frames should be
fixed to the concrete/masonry wall by means of self expanding screws, Including
10mm Square guard bars with 6 (152.4mm) pitch etc., complete for finished item
of work.
Pe
Un
Rate
8
5245.00
11672.45
19
117.45
11.14
128.59
Or say 129.00
Sqm
14 Supply and fixing of M.S. Grills including cost and conveyance of all materials and
all labour charges etc., complete
F.F.
1
1
x
x
58
11
1.5
0.75
1.35
1.35
72 of 517
7915.60 1
Measurements
Sl.
Description of item
No.
1
Nos.
3
x 2
x 4
x 8
x 8
x 17
x 28
2
GW - 2.00 x 1.35m
GW1 - 1.35 x 1.35m
V1 - 2.10 x 0.45m
V2 - 0.90 x 0.45m
V3 - 1.22 x 0.30 over D
V4 - 1.50 x 0.30 over w
L
4
65.00
45.00
25.00
15.00
7.00
9.00
B
5
D
6
QTY
Unit
7
1
130.00
1
180.00
1
200.00
1
120.00
1
119.00
1
252.00
1001.00
Kg
15 Providing and fixing factory made polyvinyl chloride (PVC) Door Frame of the size
50 x 47mm with a wall thickness of 5mm, made out of extruded 5mm rigid PVC
foam sheet, mitre cut at two corners and joined with 2nos. of 150mm long brackets
of 15x15mm M.S. square tube. The two vertical door profiles are to be reinforced
with 19x19mm M.S. Square tube of 19 gauge. The door frame shall be fixed to the
wall using 65/100mm long M.S. Screws through the frame by using PVC fasteners.
A minimum of 4nos. of screws to be provided for each vertical member & minimum
2nos. for horizontal member etc. complete as per manufacturers specification and
direction of Engineer-in-Charge for finished item of work
Toilet
65.00
65.00
Or say
65.00 rmt
19 Providing and fixing 30mm thick Solid panel PVC door shutter consisting of frame
made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm for
stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall have a coat of
steel primers of approved make and manufacture. M.S. frame shall be covered
with 5mm thick heat moulded PVC C channel of size 30 x 50mm forming stiles,
and 5mm thick, 75mm wide PVC sheets for top rail, lock rail & bottom rail on either
side, and 10mm (5mm x 2) thick, 20mm wide cross PVC sheet as gap insert for
top rail & bottom rail. Panelling of 10mm thick PVC sheet to be fitted in the M.S.
frame welded / sealed to the stiles & rails with 30mm wide x 5mm thick PVC sheet
beading on either side, and joined together with solvent cement adhesive etc. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior side of
the C Channel using PVC solvent adhesive. Complete as per direction of
Engineer-in-charge, manufacturers specification & drawing for finished item of
work .1
Toilet
13
13
74.20
369.25
2683.60
5.00
0.70
2.080
Or say
F.F.
Pe
Un
Rate
73 of 517
18.93
18.93
19.00 Sqm
Measurements
Sl.
Description of item
No.
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
20 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm
size (SS5)
hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement
per 1 cum of concrete including cost and conveyance of all materials like cement,
fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all
materials including centering using Cashewrina Ballies and Wooden runners &
staging including all bracings, cross members etc., shuttering , machine mixing,
laying concrete, lift charges, curing etc., complete but excluding cost of steel and
its fabrication charges but excluding seigniorage charges for finished item of work
(APSS No. 402 & 403) for 50 mm thick platform
2.50
0.30
1
2
x
x
2
2
2.45
4.00
1.00
1.00
Or say
4.89
16.00
20.89
21.00
22 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, finishing, curing, etc., complete
but excluding seigniorage charges for Even Surfaces of Wall for finished item of
work. (APSS 901,903 & 904)
F.F.
1
1
1
1
x
x
x
x
1
2
2
2
6
4.92
9.96
6.60
3.500
3.500
3.500
3.500
21.00
34.44
69.72
46.20
8.95
3.500
62.65
74 of 517
1.50
1.50
Or say
2.00
Sqm
21 Reinforced cement mortar Facia 5 cm thick in CM (1:3) for drop walls, Fins &
staircase railing with rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara spong finishing including cost & conveyence of all
materials to site, including sales and other taxes on all materials and all
operational, incidental charges such as labour charges, like mixing cement mortar,
scaffolding charges, lift charges, curing, for making 50 mm thick RCM Paradah
walls (RCM Drop walls) including tying Rabbit (chicken) wire mesh to the existing
mild steel / HYSD Steel reinforcement applying mortar lumps, finishing, plastering
to both faces, sponge finishing etc complete for finished item of work but excluding
cost of steel and its fabrication charges and seigniorage charges in All Floors
Pe
Un
Rate
Sqm
631.40
1734.00
Sl.
Description of item
No.
1
Measurements
B
5
D
6
3.500
QTY
2
S/w in Lunch room-2
Nos.
3
1 x 2
L
4
6.60
2
2
x
x
2
2
9.07
6.60
3.500
3.500
126.98
92.40
2
1
x
x
2
2
9.00
6.60
3.500
3.500
126.00
46.20
12.41
3.500
86.87
6.60
3.500
46.20
9.90
3.500
69.30
6.60
3.500
69.30
9.97
3.500
69.79
6.60
3.500
46.20
8.92
3.500
62.44
6.60
3.500
46.20
8.92
3.500
62.44
6.60
3.500
92.40
4.64
3.500
64.96
6.52
3.500
91.21
3.77
3.500
26.39
Stair case
5.38
3.500
75.32
3.58
3.500
25.06
Dwarf walls
0.00
2
3.38
1.100
52.05
3.04
1.100
46.82
7.06
1.100
15.53
3.38
0.900
42.59
2
1
x
x
7
2
3.04
7.06
0.900
0.900
38.30
12.71
toilet blocks
L/w's
7
46.20
0.00
2
1.5
2.800
25.20
1.1
2.800
18.48
1.3
2.800
58.24
1.1
2.800
49.28
1.72
2.800
19.26
13
0.75
2.130
-20.77
D2
0.5 x
19
1.2
2.13
-24.28
D4
0.5 x
13
0.75
2.13
-10.38
deducting door-D4
Deductions
F.F.
75 of 517
Unit
Pe
Un
Rate
8
Sl.
Description of item
No.
Measurements
W1
1.5
D
6
1.35
W2
0.5 x
11
0.75
1.35
-5.57
GW
0.5 x
1.35
-2.70
V2
0.5 x
18
0.9
0.45
-3.65
L
4
B
5
QTY
Nos.
3
0.5 x 58
Unit
Pe
Un
Rate
7
-58.73
1858.26
Or say
1860.00 Sqm
23 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, finishing, curing, etc., complete
but excluding seigniorage charges for Even Surfaces of Wall for finished item of
work. (APSS 901,903 & 904)
out side L/w's
out side c/w 's
in varandah L/w's
near stair case
Cutout
Dwarf walls
1
1
1
1
1
2
2
2
2
1
x
x
x
x
x
x
x
x
x
x
2
2
2
2
2
4
4
7
7
2
64.11
25.38
45.66
18.3
7.06
4.63
1
3.38
3.04
7.06
3.6
3.6
3.475
3.475
3.475
3.6
3.6
0.9
0.9
0.9
461.59
182.74
317.34
127.19
49.07
133.34
28.80
42.59
38.30
12.71
2
2
2
2
x
x
x
x
7
7
2
2
3.38
3.04
7.06
6
1.47
1.47
1.47
3.6
69.56
62.56
41.51
86.40
0.5
0.5
0.5
0.5
0.5
0.5
2
x
x
x
x
x
x
x
19
13
58
11
2
18
52
1.2
0.75
1.5
0.75
2
0.9
0.22
2.13
2.13
1.35
1.35
1.35
0.45
3.60
315.45
Or say
F.F.
76 of 517
-24.28
-10.38
-58.73
-5.57
-2.70
-3.65
82.37
1630.76
1635.00
Sqm
315.45 1
Measurements
Sl.
Description of item
No.
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
24 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM
(1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost
and conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, finishing, curing, etc., complete
for Even Surfaces of Wall but excluding seigniorage charges for finished item of
work. (APSS 901,903 & 904)
Lobby area
Lunch room-1
Lunch room-2
class room-1,5
Class room-2,6
open auditorium
class room-3
class room-4
physical dic.
class room-5
toilet blocks
WC
Hand wash
passage
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Passage
1
Staircase room
0
Beam bottom
1
1
Staircase waist slab botto 2
landing slab bottom
1
Sunshades bottom & top 2
Brusummer beam
1
1
1
open to sky sunshade
2
2
2
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
2
2
1
1
1
1
1
2
2
2
2
2
1
2
21
46
2
2
38
7
7
2
2
2
2
6.00
9.96
8.95
9.07
9.00
12.41
9.90
9.97
8.92
8.92
4.86
1.74
1.74
45.19
18.3
7.6
5.63
6.38
2.17
4
3.58
1.8
3.38
3.05
7.06
19.76
17.76
5.26
4.92
6.60
6.60
6.60
6.600
6.60
6.60
6.60
6.60
6.60
4.00
2.40
4.00
2.17
2.17
6
3.58
0.23
0.23
1.5
1.5
0.6
0.23
0.23
0.23
0.6
0.6
0.6
Or say
F.F.
77 of 517
29.52
65.74
59.07
119.72
118.80
81.91
65.34
65.80
58.87
58.87
38.88
8.35
13.92
196.12
79.42
45.60
0.00
30.82
22.96
24.00
10.74
82.08
5.44
4.91
3.25
47.42
42.62
12.62
1392.81
1395.00
Sqm
Pe
Un
Rate
8
304.49
Measurements
Sl.
Description of item
No.
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
25 Flooring with Polished bethamcherla colour stone of 25 mm thick (0.254x0.254M)
set over a base coat of CM (1:8), 12mm thick (joints of stone must be flushed)
over C.C. bed already laid or R.C.C. roof slab only after it is properly cured,
cleaned, moistered and where necessary treated with neat grey cement slurry of
honey like consistency spred at3.3 kgs of cement for 1 sqm. and jointed with neat
cement paste to full depth, including cost and conveyance of all materials like
cement, sand, water, flooring stones etc. to site, sales and other taxes on all
materials, all operational, incidental and labour charges such as dressing of
flooring stones to the required sizes, mixing of cement mortar, laying, jointing,
curing, lift charges etc., complete but excluding seigniorage charges for finished
item of work.(APSS No.703 & 701)
Lobby area
Lunch room-1
Lunch room-2
class room-1,5
Class room-2,6
open auditorium
class room-3
class room-4
physical dic.
class room-5
passage
29.52
65.74
59.07
119.72
118.80
81.91
65.34
65.80
58.87
58.87
196.12
79.42
Passage
45.60
landing slab bottom
10.74
1055.53
Or say
1060.00 Sqm
26 Providing skirting to internal walls 12.5 Cm high withPolished bethamcherla colour
stone of 25 mm thick (0.254x0.254M) with length equal to flooring stones set over
a base coat of CM (1:3), 12mm thick with cement slurry of honey like consistency
spread @ 3.3 Kgs per sqm and jointed with neat cement paste mixed with pigment
of matching shade to full depth (joints of stone should be flushed), including cost
and conveyance of all materials like cement, sand, water, flooring stones etc. to
site, sales and other taxes on all materials, all operational, incidental and labour
charges such as dressing of flooring stones to the required sizes, mixing of
cement mortar, laying, jointing, curing, lift charges etc., complete but excluding
seigniorage charges for finished item of work.(APSS No.701 & 707)
Lobby area
Lunch room-1
Lunch room-2
class room-1,5
Class room-2,6
F.F.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
1
1
1
2
2
1
1
1
1
1
2
2
1
2
1
1
1
2
2
6
9.96
8.95
9.07
9
12.41
9.9
9.97
8.92
8.92
45.19
18.3
7.6
3.58
Pe
Un
Rate
8
4.92
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
2.17
2.17
6
1.5
10.92
16.56
15.55
15.67
15.60
78 of 517
0.125
0.125
0.125
0.125
0.125
1.37
2.07
1.94
3.92
3.90
969.95
Measurements
Sl.
Description of item
No.
1
2
open auditorium
class room-3
class room-4
physical dic.
class room-5
passage
Passage
landing slab bottom
1
1
1
1
1
1
1
1
1
Nos.
3
x 1
x 1
x 1
x 1
x 1
x 2
x 2
x 1
x 2
L
4
19.01
16.50
16.57
15.52
15.52
47.36
20.47
13.60
5.08
B
5
D
6
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
QTY
Unit
7
11.44
4.95
8.35
toilet passage
6.17
9.14
for hand wash
13.92
53.97
Or say
54.00
Sqm
28 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as
approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm
thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water, tiles, etc. to site, sales and
other taxes on all materials, C921 such as mixing of cement mortar, laying in
position, curing, lift charges etc., complete but excluding seigniorage charges for
finished item of work (APSS No.701 & 707) in All Floors
toilet rooms
toilet passage
F.F.
2
1
1
1
1
1
x
x
x
x
x
x
4
3
2
1
1
2
1.10
1.10
1.74
1.27
1.88
1.74
2.38
2.06
2.07
1.94
1.94
11.84
5.12
1.70
1.27
43.51
Or say 44.00
Sqm
27 Flooring with Ceramic Tiles of 7.3mm thick 1st. quality of any shade as approved
by Engineer - in - charge set over a base coat of CM (1:8), 12mm thick laid over
flooring bed / V.R.C.C. slab, with neat cement slurry of honey like consistency
spread at the rate of 3.3 Kgs of cement per Sq.m and jointed with neat white
cement paste to full depth mixed with pigment of matching shade including cost
and conveyance of all materials like cement, sand, water, ceramic tiles etc. to site,
sales and other taxes on all materials, all operational, incidental and labour
charges such as mixing of cement mortar, laying, curing, lift charges etc.,
complete but excluding seigniorage charges for finished item of work.(APSS
No.701 & 707) in All Floors
toilet rooms
Pe
Un
Rate
1024.70
902.25
1.300
1.500
2.400
4.860
4.86
4.00
4.800
1.50
14.40
5.200
1.50
23.40
8.280
1.50
24.84
12.260
1.50
18.39
13.480
1.50
20.22
11.480
1.50
34.44
79 of 517
Measurements
Sl.
Description of item
No.
1
Nos.
3
L
4
B
5
D
6
Or say
QTY
Unit
7
135.69
136.00
Pe
Un
Rate
8
Sqm
546.95
Sqm
637.73
1259.90
155.90
11
1.50
0.300
19.80
19.80
Or say
20.00
staircase
23
1.50
0.150
10.35
10.35
Or say
10.50
Sqm
31 Painting to New wood work with two coats of ready mixed synthetic enamel paint
first quality all shades to give an even shade over base coat Primer with Luppam
finishing after thoroughly brushing the surface to remove all remains including
cost and conveyance of all materials to site, sales & other taxes, all operational,
incidental and labour charges etc., complete for finished item of work.(3 coats)
(APSS No. 1201 & 1212).in All Floors
D2
109.27
109.27
Or say 109.50
Sqm
32 Painting to New Iron work with two coats of ready mixed synthetic enamel paint
first quality all shades over an existing steel primer including cost and conveyance
of all materials to site, sales & other taxes, incidental, operational and all labour
charges etc., complete for finished item of work. (APSS No. 1201, 1207 & 1212).in
All Floors
GW
GW 1
V1
V2
F.F.
19 x 2.25 1.20
1
1
1
1
x
x
x
x
2
4
8
8
2.1
2.00
1.35
2.10
0.90
1.35
1.35
0.45
0.45
80 of 517
5.40
7.29
7.56
3.24
Sl.
Description of item
No.
1
2
V3
V4
Measurements
Nos.
3
1 x 17
1 x 28
L
4
1.20
1.50
B
5
D
6
0.30
0.30
QTY
Unit
Pe
Un
Rate
6.12
12.60
42.21
Or say 42.50
Sqm
33 Whiting to new walls and ceiling in two coats with Surya cem or equavalent quality
to give an even shade after thoroughly brushing the surface to remove all loose
powdered materials including cost and conveyance of all materials and water to
site, sales & other taxes, all operational, incidental and labour charges such as
cleaning the surface, painting, curing etc., complete for finished item of work for
internal walls. (APSS No.901 & 908) in All Floors
85.30
26.90
Sqm
126.55
Rmt
548.80
2.70
2.70
3.00 Sqm
457.90
1395.00
1860.00
3255.00
Or say 3255.00
Sqm
34 Painting to New walls with two coats of Plastic Emulsion paint of superior quality of
approved brand and shade over base coat of cement primer grade -I making three
coats in all to give an even shade after thoroughly brushing the surface to remove
all loose powdered materials, including cost and conveyance of all materials,
including cost and conveyance of all materials, cost of brushes, water to site, etc.,
sales & other taxes, all operational, incidental and labour charges such as
scaffolding charges, lift charges, curing etc., complete for finished item of work in
all floors for Walls.(APSS No. 912) in All Floors
1635.00
Or say 1635.00
35 Supply and fixing of 110mm dia ISI mark PVC rain water spouts of 2.5 Kg/cm2
pressure including Cost of necessary pvc bends, shoes and M.S.clamps and all
other accessories and fixing in position including cost and conveyance of all
materials to site , seigniorage charges sales and other taxes on all materials, all
operational, incidental and labour cahrges such as fixing in alignment etc.,
complete for finished item of work.(APSS NO1328) in All Floors
1
25
7.60
190.00
190.00
Or say 190.00
36 Providing and Fixing of expansion joint filler board for Buildings , Columns , Beams
and Slabs Armour Board " sillfill including cost and convenyance of all materials to
site, all incidental, operational , labour charges etc., complete for finished item of
work as per approved drawing for all floors
1
3.00
0.300
Or say
F.F.
81 of 517
Measurements
Sl.
Description of item
No.
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
37 Providing expansion joint treatment with ploy sulphide compound of approved
make of finsihed size 25 x 12 mm including making of 25mm x 12mm groove and
primer coat over finished groove with finishing of edges true to straight line and
level over the finished surface of expansion joint including cost and convenyance
of all materials to site, all incidental , operational , labour charges etc., complete
for finished item of work as per approved drawing ( for all floors on top slab i.e, in
the flooring and for internal vertical joints of grooves in dadooing surface).
9.00
9.00
Or say 9.00
Sqm
38 Providing and Fixing of 24 guage alluminium sheet over expansion joint groove of
width 15cm fixed to walls / columns at one edge and resting over the other blcok
walls / columns concealing expansion joint with slotted holes for free edge of
aluminium sheet to faciliate free movement of aluminium sheet over the finished
surface of expansion joint and wall face using sheet metal screws with nylon
receiver complete including cost and convenyance of all materials to site, all
incidental , operational labour charges etc.,, complete for finsihed item of work as
per approved drawing ( for all floors for vertical joints and bottom of slab).
10
9.80
329.50
493.10
318.15
0.150
43.00
43.00
Or say 43.00
Sqm
40 Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per
IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes and
shapes placing in position with cover blocks of approved size and binding wire of
20SWG, forming grills for reinforcement work as per approved designs and
drawings including cost and conveyance of bars from approved sources to site of
work, including cost and conveyance of binding wire, cover blocks, chairs,
overlaps, spacers, dowels, wastage etc., and all operational, incidental, and labour
charges such as cutting, bending, placing in position, tying etc., and sales & other
taxes,on cost of all materials complete for finished item of work (APSS No.126) in
first floor
F.F.
3.00
8.82
8.82
Or say 9.00
Sqm
39 Supply and Fixing of 230mm wide PVC water bar at expansion joint over roof slab
including cost , all taxes and convenyance of all materials to site and all labour
charges , cutting and fixing charges etc., complete for finsihed item of work.
1
Pe
Un
Rate
4.30
Columns Qty
48.50
cum @
150
7275
71.50
cum @
150
10725
1344.50
sqm @
11
14789.5
82 of 517
Measurements
Sl.
Description of item
No.
1
Nos.
3
B
5
sqm @
15
532.5
Lintels Qty
6.50
cum @
120
780
Sunshades Qty
96.00
sqm @
10
960
2
Waist Slab 175mm th
Qty
D
6
QTY
L
4
35.50
Unit
7
35062.00 kgs
Or say
35.50
MT
41 Supplying and fixing of stainless steel hand railing as per approved drawing with
top rail of 64mm dia (outer) 2mm thick pipe, vertical balusters of 50mm dia 2mm
thick at 600mm c/c spacing (7 Nos)and 3 nos 25mm dia (outer) 1.6mm thick
stainless steel pipes below top rail with equal spacings and 50mm wide 8mm thick
SS plate for fixing vertical balusters at 600mm centre with 100x100mm stainless
steel base plate to be fixed to the steps with Anchor fasteners. The rate should
include providing and using bonding agent, drilling of 25mm holes of fixing railing ,
polishing of all nos of railing thouroughly and also including cost and conveyance
of all materials, electrodes, welding charges, cost of all consumables, labour
charges such as for fabrication of SS pipes, buffing, polishing etc., complete for
finished item of work.
2
2
x
x
Executive Engineer
APEWIDC, CHITTOOR
2
2
4.00
1.50
16.00
6.00
22.00
Superintending Engineer
APEWIDC, KADAPA
F.F.
83 of 517
Pe
Un
Rate
Rm
47971.95
3702.91
1
TOTAL >>>
M) CHITTOOR District
Per
Unit
8
Amount
9
Cum 57235
F.F.
84 of 517
Per
Unit
Amount
Cum 642016
Sqm 1462749
Sqm 49705
Cum 9739
Sqm 353678
F.F.
85 of 517
Per
Unit
8
Amount
9
Cum 63306
Sqm 69874
F.F.
86 of 517
Per
Unit
8
Amount
9
F.F.
87 of 517
Per
Unit
8
Amount
9
Cum 1678481
Sqm 37002
F.F.
88 of 517
Per
Unit
8
Amount
9
Cum 20980
Each 221777
Sqm 1021112
F.F.
89 of 517
Per
Unit
8
Amount
9
Kg
74274
rmt
24001
Sqm 50988
F.F.
90 of 517
Per
Unit
Amount
Sqm 1263
Sqm 36414
F.F.
91 of 517
Per
Unit
8
Amount
9
F.F.
92 of 517
Per
Unit
8
Amount
9
Sqm 586737
Sqm 515761
F.F.
93 of 517
Per
Unit
8
Amount
9
Sqm 424757
F.F.
94 of 517
Per
Unit
8
Amount
9
Sqm 1028147
F.F.
95 of 517
Per
Unit
8
Amount
9
Sqm 45087
Sqm 48722
F.F.
96 of 517
Per
Unit
8
Amount
9
Sqm 74385
Sqm 12755
Sqm 13229
Sqm 17071
F.F.
97 of 517
Per
Unit
Amount
Sqm 3625
Sqm 87560
Sqm 206909
Rmt 104272
Sqm 1374
F.F.
98 of 517
Per
Unit
Amount
Sqm 2966
Sqm 4438
Sqm 13680
F.F.
99 of 517
Per
Unit
8
Amount
9
MT
1703004
Rm
81464
10850537
AL >>>
utive Engineer
C, KUPPAM
F.F.
100 of 517
SUB ESTIMATE
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOO
SECOND FLOOR
Sl.
No.
Measurements
Description of item
QTY
Nos.
Unit
1
2
3
4
5
6
7
1 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching /
Mixer ) using 20mm size (SS5) hard granite machine crushed graded metal
(Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs.
of cement per 1 cum of concreteincluding cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but
excluding cost of steel and its fabrication charges but excluding seigniorage
charges for finished item of work (APSS No. 402 & 403) FOR COLUMNS in
second floor
5
9
6
5
5
6
14
4
0.45
0.45
0.45
0.45
0.45
0.3
0.45
0.45
0.3
0.3
0.3
0.3
0.3
0.3
0.30
0.30
2.925
2.925
2.500
3.075
3.075
3.075
1.50
1.50
Or say
S.F.
2
1
1
2
2
2
2
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
2
2
2
3
3
4
3
3
3
3
3
10
4
1
5.93
3.53
7.06
3.38
3.05
7.28
6.00
3.53
3.03
3.53
3.03
8.00
10.00
15.00
101 of 517
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
1.97
3.55
2.03
2.08
2.08
1.30
2.84
0.81
16.64
17.00
0.41
0.30
0.41
0.30
0.30
0.41
0.30
0.30
0.30
0.23
0.23
0.15
0.15
0.30
2.21
0.49
1.32
1.40
1.26
5.43
2.48
0.73
0.63
0.56
0.48
2.76
1.38
1.04
22.16
Or say
23.00
Cum
Cum
Sl.
No.
Measurements
Description of item
QTY
Nos.
1
2
3
c FOR ROOF SLAB 125 MM THICK
Unit
7
26.90
9.50
255.55
1
1
1
x
x
x
1
1
1
6.10
6.95
22.10
6.50
4.10
39.65
28.50
26.52
350.22
1.20
Or say
355.00
Sqm
6.95
4.10
28.495
28.50
Or say
30.00
Sqm
2
2
x
x
2
1
4.00
4.10
1.50
1.50
24.00
12.3
36.30
Or say
40.00
Sqm
2 Providing impervious coat over RCC roof slab to required slopes with CM (1:3)
prop. 20mm thick (average) mixed with water proofing compound manufactured
by reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of
cement, laid over roof slab when it is green, finished smooth with a floating coat
of neat cement and thread lining at regular intervals of 45cmx45cm including
cost and conveyance of all materials like cement, sand, water proofing
compound, water etc., to site,
sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar, laying,
rounding off at junctions of wall and slab, rendering smooth with thread lining,
curing, lift charges, etc., complete but excluding seigniorage charges for
finished item of work (APSS No. 901 & 903).
355.00
355.00
355.00
S.F.
102 of 517
Sqm
Measurements
Sl.
No.
Description of item
QTY
Nos.
5
0.23
0.23
0.23
0.23
6
0.15
0.15
0.15
0.15
Unit
D1
W1
W2
GW
1
1
1
1
x
x
x
x
4
10
4
2
4
1.50
1.80
1.05
2.30
W1
1.80
0.60
2
2
1
1
1
1
1
1
x
x
x
x
x
x
x
x
2
1
2
2
2
2
1
2
5.03
3.53
9.51
6.38
8.46
6.38
6.00
16.14
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
2.500
2.500
3.175
3.070
3.175
3.070
3.175
0.818
11.57
4.06
13.89
9.01
12.36
9.01
4.38
6.07
191.16
0.23
1.00
43.97
102.60
0.23
1.00
47.20
1.5
0.23
0.15
-0.21
1
1
x
x
10
4
1.8
1.05
0.23
0.23
0.15
0.15
-0.62
-0.14
0.21
0.62
0.14
0.16
0.83
Or say
1.00
Cum
4 Reinforced cement concrete with M 20 grade Design mix ( by weigh batching )
using 20mm size (SS 5) machine crushed hard blasted granite graded metal
(coarse aggregate) from approved quarry using a minimum quantity of 350 Kg
of cement per 1 Cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (sand) ,coarse aggregate, water etc. to site and
cost of
all materials including centering using Cashewrina Ballies and
Wooden runners & staging including all bracings, cross members etc.,
shuttering, machine mixing, laying concrete, for sunshade of 7.5cm thick at
fixed end and 5cm thick at free end with an average thickness of 6.25cm
including labour charges for mixing, laying, curing etc., complete but
excluding cost of steel and its fabrication charges but excluding seigniorage
charges for finished item of work
7.56
7.56
Or say
8.00
Sqm
5 Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size
290x225x140mm with compressive of 50 Kgs / Sqcm from approved source
including cost and conveyance of all materials like cement, sand, fly ash bricks,
water etc., to site, including sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS No. 501 & 504).
103 of 517
Measurements
Sl.
No.
Description of item
2
GW
QTY
Nos.
5
0.23
6
0.15
4
10
4
2
2.3
1.2
1.5
0.75
2
0.23
0.23
0.23
0.23
2.13
1.35
1.35
1.35
Unit
7
-0.16
-2.35
-4.66
-0.93
-1.24
151.20
Or say
151.50 Cum
5 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to
(1:3:6) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal
from from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including sales & other taxes
on all materials, all operational, incidental and labour charges such as mixing,
laying, curing concrete, etc., complete but excluding seigniorage charges for
finished item of work for Bed Blocks and Hold Fasts (APSS No. 402)
D1
0.23
0.23
0.15
0.19
W1
10
0.23
0.23
0.15
0.32
W2
0.23
0.23
0.15
0.13
0.63
Or say
1.00
Cum
6 Supply and Fixing of 50mm thick Jali including cost and conveyance of all
materials to site, sales & other taxes, all operational, incidental and labour
charges etc., complete for finished item of work in All Floors.
2
4.38
1.00
17.52
17.52
Or say
18.00
Sqm
191.16
0.23
0.05
2.20
102.6
0.23
0.05
2.36
4.56
Or say
S.F.
104 of 517
5.00
Sqm
Sl.
No.
Measurements
Description of item
QTY
Nos.
Unit
1
2
3
4
5
6
7
8 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete but excluding seigniorage charges for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904)
5.63
2.80
63.06
3.53
2.80
19.77
9.97
3.475
69.29
6.6
3.475
45.87
8.97
3.475
62.34
6.6
3.475
45.87
lobby
4.92
3.475
34.19
Above brusummer
beam
16.14
1.38
44.39
191.16
1.00
191.16
open to sky
102.6
1.00
205.20
1.2
2.13
-5.11
W1
0.5
10
1.5
1.35
-10.13
W2
0.5
0.75
1.35
-2.03
GW
0.5
1.35
-2.70
Computer lab
761.17
Or say
770.00
9 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete but excluding seigniorage charges for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904)
S.F.
5.93
105 of 517
2.925
69.38
Sqm
Measurements
Sl.
No.
Description of item
QTY
Nos.
7
22.00
3.76
6
2.925
10.43
3.600
75.10
6.83
3.600
49.18
9.43
3.600
67.90
6.83
3.600
49.18
Above brusummer
beam
16.14
1.3875
44.79
191.16
191.16
open to sky
102.6
205.20
1.2
2.13
-5.11
W1
0.5
10
1.5
1.35
-10.13
W2
0.5
0.75
1.35
-2.03
GW
0.5
1.35
-2.70
Computer lab
Unit
753.91
Or say
760.00
10 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in
CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including
cost and conveyance of all materials like cement, sand, water etc., to site, sales
& other taxes on all materials,all operational, incidental and labour charges such
as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete for Even Surfaces of Wall but excluding seigniorage charges for
finished item of work. (APSS 901,903 & 904)
1
1
1
1
1
1
2
4
2
1
2
x
x
x
x
x
x
x
x
x
x
x
2
1
1
1
1
1
6
4
6
2
7
5.63
7.06
25.40
9.97
8.97
6.00
6.60
2.17
6.00
16.14
1.80
3.53
6
2.17
6.6
6.6
4.97
0.30
0.30
0.30
0.23
0.6
39.75
42.36
55.12
65.80
59.20
29.82
23.76
10.42
21.60
7.42
15.12
370.37
S.F.
106 of 517
Sqm
Measurements
Sl.
No.
Description of item
QTY
Nos.
Unit
6
7
Or say
370.50 Sqm
11 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs
with Sal wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm
long 2 Nos, MS powder coated Handles 150mm long 2 Nos, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges
6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos,
MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
1
4.00
Or say
4.00
Each
12 Providing and Fixing of openable double shutter windows made of pre-painted
steel (Base steel as per IS 513 of 0.58 mm thick galvanized as per IS 277 with
Zinc of 120 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish
painted with a polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer. Section for outer frame should be of 48x50mm,
centre mullion should be of 48x50mm, section for shutter should be of 48x25mm
and fixed panel beading section should be 12x12mm. Outer frame and mullions
to have rebate for Galvalume corrugated sheet shutter and a 20mm provision for
Guard bars/Grills. The sections are to be cut to length metre joined with corner
bracket. Centre mullion is to be fixed with mullion cap. Handle, stay, 2 nos. of
Stainless Steel heavy duty Pivot hinges shall be provided per shutter. The
windows should be panelled with 0.60 mm thick Galvalume corrugated sheet
having tensile strength of 550 MPA,(BMS-W.55). The above frames should be
fixed to the concrete/masonry wall by means of self expanding screws, Including
10mm Square guard bars with 6 (152.4mm) pitch etc., complete for finished
item of work.
10
1.5
1.35
20.25
W2
0.75
1.35
4.05
24.3
Or say
28.35 Sqm
13 Supply and fixing of M.S. Grills including cost and conveyance of all materials
and all labour charges etc., complete
S.F.
GW - 2.00 x 1.35m
65.00
130.00
V3 - 1.22 x 0.30over D
7.00
42.00
V4 - 1.50 x 0.30over w
9.00
54.00
107 of 517
Measurements
Sl.
No.
Description of item
QTY
Nos.
Unit
7
226.00 kgs
14 Supply and Fixing MS Purlins 50mm dia including Labour Charges for fixing
complete including cost and conveyance of all materials to site, sales and other
taxes, all labour charges etc., complete for finished item of work
for elevation
for elevation
2
1
x
x
3
3
7.20
8.00
43.20
24.00
67.20
Or say
68.00 Rmt
13 Whiting to new walls and ceiling in two coats with Birla White or equavalent
quality to give an even shade after thoroughly brushing the surface to remove all
loose powdered materials including cost and conveyance of all materials and
water to site, sales & other taxes, all operational, incidental and labour charges
such as cleaning the surface, painting, curing etc., complete for finished item of
work for internal walls. (APSS No.901 & 908) in All Floors
As per ornamental plastering area in QTY
As per 12mm thick plastering area in QTY
370.50
770.00
1140.50
Or say 1140.50 Sqm
14 Painting to New walls with two coats of Plastic Emulsion paint of superior quality
of approved brand and shade over base coat of cement primer grade -I making
three coats in all to give an even shade after thoroughly brushing the surface to
remove all loose powdered materials, including cost and conveyance of all
materials, including cost and conveyance of all materials, cost of brushes, water
to site, etc., sales & other taxes, all operational, incidental and labour charges
such as scaffolding charges, lift charges, curing etc., complete for finished item
of work in all floors for Walls.(APSS No. 912) in All Floors
760.00
760.00
Or say
760.00 Sqm
15 Painting to New wood work with two coats of ready mixed synthetic enamel
paint Grade I all shades to give an even shade over base coat Primer with
Luppam finishing after thoroughly brushing the surface to remove all remains
including cost and conveyance of all materials to site, sales & other taxes, all
operational, incidental and labour charges etc., complete for finished item of
work.(3 coats) (APSS No. 1201 & 1212).in All Floors
doors
23.00
23.00
Or say
23.50 Sqm
16 Painting to New Iron work with two coats of ready mixed synthetic enamel paint
first quality all shades over an existing steel primer including cost and
conveyance of all materials to site, sales & other taxes, incidental, operational
and all labour charges etc., complete for finished item of work. (APSS No. 1201,
1207 & 1212).in All Floors
S.F.
2.25 x
1.20
108 of 517
2.13
Sl.
No.
1
Measurements
Description of item
QTY
Nos.
4
7.20
8.00
2.00
1.20
1.50
6
1.00
1.00
1.35
0.30
0.30
2
for elevation
for elevation
GW
V3
V4
Unit
7
2.25 x
6
97.20
2.25 x
3
54.00
2.25 x
2
12.15
1 x
4
1.44
1 x
6
2.70
167.49
Or say
168.00 Sqm
17 Supply and fixing of 110mm dia ISI mark PVC rain water spouts of 4 Kg/cm2
pressure including Cost of necessary pvc bends, shoes and M.S.clamps and all
other accessories and fixing in position including cost and conveyance of all
materials to site , seigniorage charges sales and other taxes on all materials, all
operational, incidental and labour cahrges such as fixing in alignment etc.,
complete for finished item of work.(APSS NO1328) in All Floors
22.00
Or say
22.00 rmt
18 Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per
IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes
and shapes placing in position with cover blocks of approved size and binding
wire of 20SWG, forming grills for reinforcement work as per approved designs
and drawings including cost and conveyance of bars from approved sources to
site of work, including cost and conveyance of binding wire, cover blocks, chairs,
overlaps, spacers, dowels, wastage etc., and all operational, incidental, and
labour charges such as cutting, bending, placing in position, tying etc., and sales
& other taxes,on cost of all materials complete for finished item of work (APSS
No.126) for second floor
S.F.
11.00
Columns Qty
Roof Beams Qty
Roof Slab 125mm th Qty
17.00
23.00
355.00
cum @
cum @
sqm @
140
140
11
2380
3220
3905
40.00
sqm @
15
600
Lintels Qty
Sunshades Qty
1.00
8.00
cum @
sqm @
120
10
120
80
10305.00 kgs
10.31
10.50 MT
109 of 517
Sl.
No.
Measurements
Description of item
QTY
Nos.
Unit
1
2
3
4
5
6
7
19 Supplying and fixing of stainless steel hand railing as per approved drawing with
top rail of 64mm dia (outer) 2mm thick pipe, vertical balusters of 50mm dia 2mm
thick at 600mm c/c spacing (7 Nos)and 3 nos 25mm dia (outer) 1.6mm thick
stainless steel pipes below top rail with equal spacings and 50mm wide 8mm
thick SS plate for fixing vertical balusters at 600mm centre with 100x100mm
stainless steel base plate to be fixed to the steps with Anchor fasteners. The rate
should include providing and using bonding agent, drilling of 25mm holes of
fixing railing , polishing of all nos of railing thouroughly and also including cost
and conveyance of all materials, electrodes, welding charges, cost of all
consumables, labour charges such as for fabrication of SS pipes, buffing,
polishing etc., complete for finished item of work.
2
2
x
x
Executive Engineer
APEWIDC, CHITTOOR
2
2
4.00
1.50
Superintending Engineer
APEWIDC, KADAPA
S.F.
110 of 517
16.00
6.00
22.00
Rm
Per
Unit
Rate
8
Amount
9
1224.53
1 Cum
20817.00
9227.45
1 Cum
212231.00
S.F.
111 of 517
Per
Unit
Rate
8
Amount
9
1117.50
1 Sqm
396713.00
1590.45
1 Sqm
47714.00
1436.15
1 Sqm
57446.00
377.25
1 Sqm
133924.00
S.F.
112 of 517
Per
Unit
Rate
8
10066.40
S.F.
Amount
9
1 Cum
10066.00
752.00 1 Sqm
6016.00
113 of 517
Per
Unit
Rate
8
Amount
9
5943.40 1 Cum
900425.00
5328.00
1 Sqm
5328.00
456.75
1 Sqm
8222.00
6619.70
1 Sqm
33099.00
S.F.
114 of 517
Per
Unit
Rate
8
341.85
S.F.
Amount
9
1 Sqm
263225.00
115 of 517
Per
Unit
Rate
8
341.85 1 Sqm
S.F.
Amount
9
259806.0
116 of 517
Per
Unit
Rate
8
Amount
362.95
1 Sqm
9
134471.00
11672.45
1 Each
46690.00
6358.95
1 Sqm
180276.00
S.F.
117 of 517
Per
Unit
Rate
8
Amount
74.20
1 kgs
9
16769.00
475.15
1 Rmt
32310.00
26.90
1 Sqm
30679.00
126.55
1 Sqm
96178.00
155.90
1 Sqm
3664.00
S.F.
118 of 517
Per
Unit
Rate
8
Amount
9
85.30
1 Sqm
14330.00
548.80
1 rmt
12074.00
48812.70
1 MT
512533.00
S.F.
119 of 517
Per
Unit
Rate
8
3702.91
TOTAL >>>
Amount
9
1 Rm
81464.00
3516470.00
S.F.
120 of 517
SUB ESTIMATE
WATER SUPPLY & SANITARY ARRANGEMENTS
Description of item
Measurements
Nos.
3
L
4
B
5
D
6
QTY
Unit
7
Per
Unit
Rate
8
2 x
16.00
16.00
Nos 4345.80
2 Constructing 904.0 mm (30) dia solid block masonry inspection chamber as per
IS - 4111: Part-1:1986 with cement mortar (1:6) prop using fly ash blocks of
225mm thick from approved source having a minimum crushing strength of 10
N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside
and outside fitted with 20 dia RCC manhole covers and frames including
excavating pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding
rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal
and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard
specification and including cost and conveyance of all materials like cement,
sand, bricks, water etc., to site, cost of seigniorage charges on all materials and
all incidental and operational, labour charges like mixing cement mortar,
constructing masonry, lift charges, curing etc., complete for finished item of work
as per Standard specification.
1 x 6
6.00
Nos
3 Supplying and fixing 580 mm x 440 mm long Orissa pan white glazed Water
Closet 1st qualityISI marked confirming to IS:2556-Part-3-1981 with "P" or "S"
trap Hindware / Parryware / Neycer with brick masonry seat, CC squatting plate
and fixing 12.70mm dia NP Push cock 1st quality , P trap or S trap of Indian
W.C. shall be encased on CC (1:2:4) 150mm alround well above the joint to stop
leakage at the joint etc., complete including cost and conveyance of all materials
to site, cost of CC bed, labour charges and seigniorage charges etc., complete
for finished item of work.
7646.30
2172.36
293.15
ground floor
first floor
WSA
19.00
18.00
37.00
121 of 517
Nos
Nos
Nos
Sl.
No.
Measurements
Description of item
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
5 Supplying and fixing Indian make Flat Back Wash Hand Basin (HSW/Parryware/
Neycer) 1st quality conforming to IS:2556-Part-4:1972 of size 550mm x 400mm
with waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting with
parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal
bore Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/
Esso or equivalent complete with standard CI brackets including wooden block ,1
No.12.70mm PVC connection with brass union nuts CP coated , 1 No.12.70mm
NP bib tap 300 gms Seiko or equivalent including cost and conveyance of all
materials to site, labour charges etc. complete for finished item of work
1 x 30
Per
Unit
Rate
8
30.00
30.00
30.00
Nos
2977.95
6.85
4999.06
1012.35
1653.10
307.90
6 Providing and placing on terrace (at all floor levels) polyetheylene water storage
tank with double layer approved brand and manufacture with cover and suitable
locking arrangement and making necessary holes for inlet and outlets and over
flow pipes but without fittings and base support for tanks including cost and
conveyance of all materials and labour charges for placing and fixing in position
as directed by Engineer-in-Charge.
1 x 2 1000.00
2000.00 Lts
7 Supply and fixing of European Water Closet of 1st quality conforming to IS: 2556Part-2-1973 of Hindustan/Neycer of Parryware make white glazed with 'P' trap.
toilet
1 x
7.00
7.00
Nos
7.00
8 Supply and fixing best indian make plastic seat and lid for European water
closets with rubber or plastic buffers as per IS 2548 -1996
toilet
1 x
7.00
7.00
Nos
7.00
9 Supply and fixing of PVC low level system parry ware, slim line with internal
components & short bend: 10 litres capacity single flush
in Ground & First floor
1 x 37
37.00
37.00
37.00 Nos
10 Supplying and fixing NP Push cock of size 12.70mm dia of Indian make Seiko or
equivalent including cost and conveyance of all materials, labour charges etc.,
complete for finished item of work in all floors.
in Ground & First floor
1 x 37
37.00
37.00
37.00
WSA
122 of 517
NOs
Sl.
No.
Measurements
Description of item
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
11 Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with
fittings in ground or on wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc. with necessary excavation in
all types of soils except rock requiring blasting, refilling, chiselling masonry walls
and making good the walls & floors to the original surface and fixing MS clamps
on TW blocks on walls including cost and conveyance of all materials and labour
charges complete for finished item of work.
Per
Unit
Rate
8
596.50
409.05
240.90
214.75
WSA
80.00
123 of 517
80.00
Rmt
Sl.
No.
Measurements
Description of item
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
15 Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with
fittings in ground or on wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc. with necessary excavation in
all types of soils except rock requiring blasting, refilling, chiselling masonry walls
and making good the walls & floors to the original surface and fixing MS clamps
on TW blocks on walls including cost and conveyance of all materials and labour
charges complete for finished item of work.
Per
Unit
Rate
8
160.20
278.40
NOs
6.00
18 Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm.
Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off
sets, door bends, single junctions, double junctions as per site requirement, fixing
with PVC clamps if necessary with required number of Bombay nails including
cost and conveyance of all materials to site, labour charges etc.complete for
finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) for 110
mm dia single socket pipe
597.65
1 x 1
120.00
120.00 Rmt
19 Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm.
Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off
sets, door bends, single junctions, double junctions as per site requirement, fixing
with PVC clamps if necessary with required number of Bombay nails including
cost and conveyance of all materials to site, labour charges etc.complete for
finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) for 90 mm
dia single socket pipe
183.35
153.40
1 x 15
15
15
15.00 NOs
17 Supplying and fixing PPR ball valve of 40 mm dia confirming to DIN standards
8077/8092 , Indian make heavy type including cost and conveyance of all
materials , labour charges etc. complete for finished item of work.
1 x
1 x
WSA
6
6
60.00
124 of 517
60.00
Rmt
Sl.
No.
Measurements
Description of item
QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
20 Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm.
Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off
sets, door bends, single junctions, double junctions as per site requirement, fixing
with PVC clamps if necessary with required number of Bombay nails including
cost and conveyance of all materials to site, labour charges etc.complete for
finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) for 160
mm dia single socket pipe
1 x
80.00
80.00
Rmt
Per
Unit
Rate
8
436.70
1 x 1
20.00
20.00 Nos
22 Supplying and fixing 150.00mmx100.00mm SWG gully trap 1st class confirming
to ISI 651 & 4127with CI grating and constructing single brick masonry wall
chamber of size 20" x 14" x 12 in CM (1:6) prop. Over a CC (1:5:10)prop. bed,
and plastering 12mm thk. in CM (1:4) prop. both inside and outside surfaces and
fitted with 304.8MM X 288.6 MM (12"X9") CI frame and hinged cover including
labour for fixing and laying the SWG junctions/plugs/bends with air tightcement
joints etc., complete including cost and conveyance of all materials to site, labour
charges etc., complete for finished item of work as directed by Engineer-incharge.
154.55
12.00 Nos
23 Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x
457.2mm , plywood back with NP screws 1st quality including cost and
conveyance of all materials, labour charges etc., complete for finished item of
work in all floors.
645.35
Nos
8.00
24 Supply and fixing of white glazed flat back bowl urinals of size 440 mm x 265 mm
x 315 mm with internal rim flushing mm fixied with screws complete inidan make
(HS W/Parry/Neycer) conforming to IS 2556 -1995 as approved be Engineer - in
- charge 12.7 mm PVC connection with brass plumber union nuts CM Coated.
including 12.70 mm push cock 1st qulaity of approved make including supply &
fixing 31.75 m dia PVC flexible waser pipe of 914.40 mm lenght of 1st including
cost and conveyance of all materials to site labour charges etc., complete for
finished item of work for all floors
582.85
20.00 Nos
25 Supply and fixing of 100 mm dia CI Vent pipe of 3 mts length double socket fitted
with AC cowl and mosquito proof wire mesh including cost and conveyance of all
materials to site and labour charges for placing and fixing in position etc.,
complete for finished item of work.
1056.65
2552.95
21 Supplying and fixing CI Nahani traps 100 mm dia Inlet- 75 mm (3") outlet pipe - 4
Kgs 1st quality ISI marked conforming to IS:1729-1979 with C.P. Grating fixing
with white cement as per site requirements with standard practice for all floors
including cost and conveyance of all materials to site, labour charges etc.,
complete for finished item of work.
1 x
1 x
WSA
1 x
1 x
12.00
8.00
20.00
2.00
125 of 517
Nos
Sl.
No.
Description of item
Measurements
Nos.
3
L
4
B
5
D
6
QTY
Unit
7
Per
Unit
Rate
8
TOTAL >>
Executive Engineer
APEWIDC, CHITTOOR
Superintending Engineer
APEWIDC, KADAPA
WSA
126 of 517
V) of KUPPAM (M)
Amount
9
69533.00
45878.00
65171.00
10847.00
WSA
127 of 517
Amount
9
89339.00
13700.00
34993.00
7086.00
61165.00
11392.00
WSA
128 of 517
Amount
9
59650.00
40905.00
28908.00
17180.00
WSA
129 of 517
Amount
9
6408.00
4176.00
3586.00
22002.00
9204.00
WSA
130 of 517
Amount
9
34936.00
3091.00
7744.00
4663.00
21133.00
5106.00
WSA
131 of 517
Amount
9
692246.00
Executive Engineer
EWIDC, KUPPAM
WSA
132 of 517
Sl.
Description of item
No.
1
Nos.
QTY
Unit
7
1 Cutting of gravel & leveling of ground by,Earth work excavation for foundations
(Mechanical Means) for buildings in ordinary soils and depositing on bank for all
lifts and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking,
strutting etc., and overheads & contractors profit complete for finished item of
work excluding dewatering charges etc., as per SS 20 B(APSS 308)
90.00
50.00
0.45
2025.00
90.00
35.00
0.30
945.00
2970.00
Or say
2970.00 Cum
2 Earth work excavation and depositing on bank (manual means) with initial lead
of 10m and initial lift of 3m in Loamy & Clayey Soils like BC Soils, Red Earth &
Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour
charges such as shoring, strutting, sheeting, planking and dewatering including
cost of hire charges of T & P, labour charges etc., complete for finished item of
work excluding seignerage charges and dewatering charges etc., complete for
Foundation of Building.(APSS No. 308)
200.00
0.90
0.90
162.00
Or say
162.00 Cum
3 Earth work excavation for foundations for buildings in hard rock (requiring
blasting) and depositing on bank for all lifts and with an initial lead of 10m and
up to 3m depth including all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., and overheads & contractors profit
complete for finished item of work excluding dewatering charges etc., as per SS
20 B(APSS 308)
25% of E/W Quantity
2970 x 0.10 = 297.00
Or say
133 of 517
297.00
300.00
Cum
Playground Levelling
Measurements
Sl.
Description of item
No.
Nos.
QTY
Unit
1
2
3
4
5
6
7
4 Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to
(1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate)
using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved
quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including sales & other taxes on all materials, all
operational, incidental, and labour charges such as mixing, laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete but excluding seigniorage chargesfor finished item of
work for Foundations and Flooring Bed (APSS No. 402)
200.00
0.9
0.10
Or say
18.00
18.00
18.00
Cum
5 Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard
blasted Granite stones from approved quarry including cost and conveyance of
all materials like Granite stones, cement, sand, water, etc., to site sales &
other taxes on all materials, all operational, incidental, and labour charges such
as cutting stones to required size and shape, mixing of cement mortar,
constructing masonry, curing etc., complete but excluding seigniorage charges
for finished item of work for foundation and basement (APSS No. 601 & 615)
200.00
0.75
0.60
90.00
II nd. Step
200.00
0.6
0.60
72.00
200.00
0.45
0.60
54.00
216.00
Or say
216.00 Cum
6 Flush Pointing to CRS Masonry in CM(1:3) Prop: including cost and conveyance
of all materials like cement, sand, water etc., to site, including sales & other
taxes on all materials, all operational, incidental charges and labour charges
such as mixing mortar, finishing, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS 901,906)
200.00
200.00
200.00
Or say
200.00 Sqm
7 Filling with Gravel in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including cost and conveyence of water to the work site
and all operational, incidental, labour charges, hire charges of T & P etc.,
completebut but excluding seignorage charges, for finished item of work. (APSS
NO. 309 & 310)
134 of 517
1.00
Playground Levelling
Sl.
Description of item
No.
1
2
For play fields North 1
side
For play fields South 1
side
Measurements
QTY
Nos.
3
x 1
90
50
6
0.30
7
1350.00
x 1
90
35
0.30
945.00
Or say
Executive Engineer
APEWIDC, CHITTOOR
Unit
2295.00
2295.00 Cum
Superintending Engineer
APEWIDC, KADAPA
135 of 517
Playground Levelling
TIMATE
COLLEGE AT GUDIPALLI(V),
T.
Per
Unit
Rate
8
Amount
9
98.90
1 Cum 293733
231.60
1 Cum 37519
597.90
1 Cum 179370
136 of 517
Playground Levelling
Per
Unit
Rate
8
Amount
9
3413.65
1 Cum 61446
2709.55
1 Cum 585263
63.95
1 Sqm 12790
137 of 517
Playground Levelling
Per
Unit
Rate
8
Amount
9
380.70
1 Cum 873707
TOTAL >>>
2043828
138 of 517
Playground Levelling
No
L
B
D Qty
Unit
Description of work
Forming embankment with Side earth by mechanical means upto SDR
including pre-watering of soil , removal of top soil, excavation of soils ,
depositing the soils on the embankment, spreading soil, breaking clods,
sectioning , grading and consolidation with 8 to 10 Tonnes Vibratory Road
Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including
all hire and operational charges of T&P and , complete for finished item
of work as per MoRT&H specification 305 (4th revision) (Payment will be
made based on level for finished item of work).
x 1
250.00
6.00
0.30
Rate
450.00
450.00
100.00
100.00
Say 100.00 Cum
Vibrated cement concrete M.25 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1
and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including all
other incidental and operational charges of all T&P etc., complete for
finished item of work as per Approved drawing but excluding cost of steel
and its fabrication charges as per MoRT&H specification
1500,
1600,1700, & 2704 (4th Revision) and as directed by the Engineer-inCharge for CC Pavements.
250.00
250.00
4.00
4.00
185.00
0.10
0.15
3278.00
150.00
150.00
Say
139 of 517
150.00 Cum
6288.00
CC Road
SNo
4
No
L
B
D Qty
Unit
Description of work
Construction of Gravel shoulders including cost, and conveyance of all
materials to work site and spreading in uniform layers by approved
means, on prepared surface and compacting with vibratory roller to
achieve the desired density at OMC etc., complete for finished item of
work as per MoRT&H Specification 401& 407 (4th revision) and as
directed by the Engineer-in-charge.
( Payment will be made based on levels for finished item of work ).
Gravel Shoulders
250.00
1.00
0.25
Say
125.00
125.00 Cum
Rate
299.00
TOTAL
Executive Engineer
APEWIDC, CHITTOOR
Asst. Exe.Eng
APEWIDC, KU
Superintending Engineer
APEWIDC, KADAPA
140 of 517
CC Road
Per
Unit
Amount
Cum
83250
Cum
327800
Cum
943200
141 of 517
CC Road
Per
Unit
Amount
Cum
37375
TOTAL: 1391625
Asst. Exe.Engineer
APEWIDC, KUPPAM
142 of 517
CC Road
LEAD CHART
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOOR District
RATES AS PER COMMON SSR OF 2015-2016 with cement and steel rates of November
Lead in KM
Sl.
No.
Description
(1)
(2)
1 Sand for Mortar
2
Avg.
Thickn
SSR Sl.No.
ess in
mm
(3)
M-005
M-006
3
4
(4)
Source of Material
MR
CT
(5)
Kangundi
(6)
45.00
(7)
0.50
Kangundi
45.00
Kangundi
LOCAL
Total
Add
Convence
Initial Cost Differenc
Charges
1%
including
in
including
towards
Stacking SeignioStacking
storage
Charges
rage
Charges
Charges
Loading unloadin
charges g charges
(8)
46.00
(9)
464.09
(10)
610.00
(11)
0.00
(12)
0.00
(13)
0.00
(14)
0.00
0.50
46.00
464.09
677.00
0.00
0.00
0.00
0.00
45.00
5.00
0.50
0.50
46.00
6.00
464.09
56.41
460.00
103.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Gundlasagaram
10.00
0.50
11.00
111.01
252.00
0.00
0.00
0.00
0.00
Gundlasagaram
10.00
0.50
11.00
111.01
288.00
0.00
0.00
0.00
0.00
Gundlasagaram
10.00
0.50
11.00
111.01
1040.00
0.00
0.00
0.00
0.00
Gundlasagaram
10.00
0.50
11.00
111.01
845.00
0.00
0.00
0.00
0.00
V.Kota
54.00
0.50
55.00
545.99
1365.00
0.00
0.00
0.00
0.00
V.Kota
54.00
0.50
55.00
545.99
1097.00
0.00
0.00
0.00
0.00
V.Kota
54.00
0.50
55.00
545.99
935.00
0.00
0.00
0.00
0.00
V.Kota
54.00
0.50
55.00
545.99
735.00
0.00
0.00
0.00
0.00
LOCAL
8.00
0.50
9.00
143.25
5200.00
0.00
0.00
41.88
41.88
143 of 517
LEAD
Lead in KM
Sl.
No.
Description
Avg.
Thickn
SSR Sl.No.
ess in
mm
Source of Material
MR
CT
Total
Add
Convence
Initial Cost Differenc
Charges
1%
including
in
including
towards
Stacking SeignioStacking
storage
Charges
rage
Charges
Charges
Loading unloadin
charges g charges
LOCAL
8.00
0.50
9.00
328.40
11000.00
0.00
0.00
96.01
96.01
LOCAL
8.00
0.50
9.00
738.90
24000.00
0.00
0.00
216.02
216.02
435.00
0.50
436.00
147.51
385.90
0.00
0.00
0.76
0.38
bethamcherla
144 of 517
LEAD
Lead in KM
Sl.
No.
Description
Avg.
Thickn
SSR Sl.No.
ess in
mm
Source of Material
MR
CT
Total
Add
Convence
Initial Cost Differenc
Charges
1%
including
in
including
towards
Stacking SeignioStacking
storage
Charges
rage
Charges
Charges
Loading unloadin
charges g charges
17
15
Yerraguntla
290.00
0.50
291.00
59.40
137.90
0.00
0.00
0.46
0.23
18
BMT-B.01
40
Yerraguntla
290.00
0.50
291.00
158.41
96.00
0.00
0.00
1.22
0.61
18
LOCAL
1.00
0.50
2.00
0.29
729.00
0.00
0.00
0.00
0.00
17
LOCAL
5.00
0.50
5.00
0.00
2352.00
0.00
0.00
0.00
0.00
Local
0.50
0.00
5.00
0.00
77.00
0.00
0.00
0.00
0.00
CSSR-A.05
At Site
0.00
0.00
0.00
0.00
5760.00
0.00
0.00
0.00
50.25
M-126
At Site
0.00
0.00
0.00
0.00
34000.00
0.00
0.00
0.00
60.23
CSSR-A.62
At Site
0.00
0.00
0.00
0.00
32000.00
0.00
0.00
0.00
60.23
CSSR-A.68
At Site
0.00
0.00
0.00
0.00
37000.00
0.00
0.00
0.00
60.23
26 M.S. Plates
CSSR-A.69
At Site
0.00
0.00
0.00
0.00
35000.00
0.00
0.00
0.00
60.23
BMT-B.11
21 water
22 Cement
23
CERTIFICATES:1
Certified that the above leads are true and correct to the best of my knowledge
Certified that the quarry requries blasting for RR, CRS, 6mm, 10mm, 12mm, 20mm & 40mm Metal
Certified that the 20mm, 12mm, 10mm, 6mm Metal requires Machine Crushing
Certified that the work site does not falls within 12 Kms belt of any Municipality/ Corporation. Hence no extra on labour charges is allowed
145 of 517
LEAD
Lead in KM
Sl.
No.
Description
Avg.
Thickn
SSR Sl.No.
ess in
mm
Source of Material
MR
CT
Total
Add
Convence
Initial Cost Differenc
Charges
1%
including
in
including
towards
Stacking SeignioStacking
storage
Charges
rage
Charges
Charges
Loading unloadin
charges g charges
Certified that the sand in notified sand reaches around Kuppam is completed and proposed a new notified reach at Koundinya river at Samudrapalli near Palamaner
Superintending Engineer
Executive Engineer
Asst.Exe.Engineer
APEWIDC, Kadapa
APEWIDC, Chittoor
APEWIDC, Madanapalli
APEWIDC, Kuppam
146 of 517
LEAD
LEAD CHART
Total
Unit per
(15)
0.00
(16)
1074.09
(17)
Cum.
0.00
1141.09
Cum.
0.00
0.00
924.09
159.41
Cum.
Cum.
0.00
363.01
Cum.
0.00
399.01
Cum.
0.00
1151.01
Cum.
0.00
956.01
Cum.
0.00
1910.99
Cum.
0.00
1642.99
Cum.
0.00
1480.99
Cum.
0.00
1280.99
Cum.
0.00
147 of 517
LEAD
Area
allowence
on loading
&
unloading
charges
@0%
Total
Unit per
0.00
0.00
0.00
534.55
148 of 517
1Sqm.
LEAD
Area
allowence
on loading
&
unloading
charges
@0%
Total
Unit per
0.00
197.99
1Sqm.
0.00
256.24
1Sqm.
0.00
729.29
1Sqm.
0.00
2352.00
1Sqm.
0.00
77.00
KL
0.00
5810.25
M.T
0.00
34060.23
M.T
0.00
32060.23
M.T
0.00
37060.23
M.T
0.00
35060.23
M.T
tal
149 of 517
LEAD
Area
allowence
on loading
&
unloading
charges
@0%
Total
Unit per
Asst.Exe.Engineer
APEWIDC, Kuppam
150 of 517
LEAD
DATA
1
23 Kgs
0.273 Nos.
0.637 Nos.
0.91 Nos.
0.01
0.14
875
480.00
375.00
320.00
1667.37
20 Kg
1 Each
1 Each
1 Each
1684.04
Say
151 of 517
C-Data
1006.25
131.04
238.88
291.2
16.67
1684.04
235.77
1919.81
191.981
192.00
152 of 517
C-Data
CC ROAD DATA
Name of Work ::- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM
(M) CHITTOOR District
S.No.
Quantity
Description of Item
Rate
per
1 Forming embankment with Side earth by mechanical means upto SDR including prewatering of soil , removal of top soil, excavation of soils , depositing the soils on the
embankment, spreading soil, breaking clods, sectioning , grading and consolidation
with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 3002 of MoRT&H, including all hire and operational charges of T&P and , complete for
finished item of work as per MoRT&H specification 305 (4th revision) (Payment will
be made based on level for finished item of work).
Unit : Cum
Taking out put = 100 Cum
(A) Labour
0.02 day
Mate
Mazdoor unskilled
0.50 day
Amount
(B) Machinery
100.00 cum
Rate as per G.O. Ms No 10, Dt
26/7/2005
1.00 hr
Motor Grador for Grading @ 100 cum
per
hour
Water
tanker 6 KL
4.00 hr
Vibratory roller 8T
1.00 hr
400.00
320.00
day
day
8.00
160.00
168.00
86.43
2600.00
658.35
2678.30
cum
hr
hr
hr
8643.00
2600.00
0.00
cum
2633.40
2678.30
16554.70
(C)
100.00 Cum
(D) Over head charges @4% (10%-VAT) on (A) + (B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 100 cum (E) + (F)
Rate per Cum
Rate per 1 cum
2
Providing Plain Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering,
machine mixing, laying, Vibrating, curing etc., including all other incidental and
operational charges of all T&P etc., complete for finished item of work as per
MoRT&H specification 1500,1700, 2100 (4th Revision) and as directed by the
Engineer-in-Charge for base coarse below CC Pavement.
CC Road - Data
153 of 517
0.00
668.91
17391.61
1739.16
19130.77
191.31
191.00
1 Cum
S.No.
Quantity
Description of Item
Rate
per
Amount
400.00
420.00
320.00
day
day
day
256.00
420.00
4800.00
5476.00
cum
cum
MT
12906.14
7250.11
14118.91
34275.16
hr
hr
hr
1971.60
0.00
1316.70
3288.30
Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos
1.00 nos
15.00 nos
Mate
Mason
Mazdoor
Total
(B) Material
13.50 cum
6.75
cum
2.43
MT
1721.58
44761.04
4476.10
49237.14
3282.48
3282.00
1 Cum
Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials
to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (4th
Revision) and as directed by the Engineer-in-Charge for C.C Pavement.
(B) Material
8.10 cum
CC Road - Data
Mate
Mason
Mazdoor
Total
400.00
420.00
320.00
day
day
day
344.00
630.00
6400.00
7374.00
1910.99
cum
15479.02
154 of 517
S.No.
Quantity
Description of Item
Cost of 10mm SS-5 HBG M/C metal
5.40 cum
6.75 cum
Sand at site
6.33 MT
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
0.00 hr
Generator set 35 KVA
Rate
per
Amount
1480.99
1074.09
5810.25
cum
cum
MT
7997.35
7250.11
36778.88
67505.36
328.60
620.00
hr
hr
1971.60
0.00
1971.60
76850.96
Cum
2689.78
3181.63
82722.37
8272.24
90994.61
6066.31
Rate to be adopted
6066.00
1 Cum
Mate
400.00
day
160.00
2.00 day
Mazdoor skilled
320.00
day
640.00
8.00 day
Mazdoor unskilled
320.00
day
2560.00
Total
3360.00
(B) Machinery
6.00 hr
Vibratory roller 8T
2678.30
hr
16069.80
3.00 hr
Water tanker 6 KL
658.35
hr
1975.05
Total
18044.85
(C) Material
CC Road - Data
155 of 517
S.No.
Quantity
384.00 cum
Description of Item
Gravel
Rate
159.41
per
Amount
61213.44
3304.73
85923.02
8592.30
94515.32
315.05
Rate to be adopted
315.00
1 Cum
Vibrated cement concrete M.25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials
to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per Approved drawing but excluding cost of steel and its
fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2704 (4th
Revision) and as directed by the Engineer-in-Charge for CC Pavements.
0.86
1.50
20.00
Unit = cum
Taking output = 15 cum
(A)
Labour
nos
Mate
nos
Mason
nos
Mazdoor
Total
8.10
5.40
6.75
6.05
(B)
cum
cum
cum
MT
6.00
6.00
hr
hr
2.00
14.00
(D)
%
%
CC Road - Data
day
day
day
Material
Cost of 20mm HBG metal
1910.99
cum
Cost of 10mm HBG metal
1480.99
cum
Sand at site
1074.09
cum
Cement at site
5810.25
MT
Total
Machinery
Concrete mixer 0.4/0.28 cum
328.60
hr
Generator set 33 KVA
620.00
hr
Total
Form work
Form work @ 2% on (A)+(B)+( C)
78944.09
Cum
Add for Over head charges @ 14% on (A)+(B)+( C)+(D)
156 of 517
344.00
630.00
6400.00
7374.00
15479.02
7997.35
7250.11
35152.01
65878.49
1971.60
3720.00
5691.60
1578.88
11273.22
S.No.
Quantity
Description of Item
Cost per 15 cum
Rate for 1 cum M 25 Concrete
Rate to be adopted
Rate
per
Amount
91796.19
6119.75
6120.00
1 Cum
Asst. Exe.Engineer
APEWIDC, Kuppam
Executive Engineer
APEWIDC, Chittoor
Superintending Engineer
APEWIDC, Kadapa
CC Road - Data
157 of 517
Qty
Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.52x2.13
mtrs with MediumTeak wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.
Rate
Unit
Per
1.52
2.13
= 0.0319
0.03195
cum
= 0.00864
0.01140
cum
0.04335
cum
2.89
sqm
Total
= 0.04054
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x1.41x2.05 = 2.89 Sqm
ABSTRACT
a)MATERIAL
1
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M ( BMT-E.02)
88994.00
Cum
80094.00
Cum
1488.00
Sqm
2.89
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
6.00
MS Hold Fasts
25.00
Each
1.00
425.00
Each
2.00
198.00
Each
2.00
140.00
Each
6.00
34.00
Each
1.00
188.00
Each
10
2.00
50.00
Each
685.00
Sqm
685.00
2.89
11
12
a)
LABOUR
Labour
charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
0.00
13
Add overheads @
14%
158 of 517
D-W data
Sno
Qty
Description of Item
Rate
Unit
Per
2.13
0.03195
0.01500
0.04695
cum
cum
cum
3.87
sqm
88994.00
80094.00
1
1
Cum
Cum
1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Each
Sqm
Supply and Fixing of Door with Double leaf shutter, Door Size 2.0x2.13 mtrs
with MediumTeak wood Frame of sections size 75mm x 100mm with Flush
Door Shutter Solid Bond Wood black board type with commercial ply on
both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.
1
2
3
4
5
6
7
8
9
10
3.87
6.00
1.00
2.00
2.00
6.00
1.00
2.00
3.87
11
12
0.00
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
13
Add overheads @
685.00
685.00
14%
159 of 517
D-W data
Sno
1
2
3
4
5
6
7
8
9
10
Qty
4.9
6.00
1.00
2.00
2.00
6.00
1.00
2.00
4.90
11
12
Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 2.4x2.13 mtrs
with MediumTeak wood Frame of sections size 125mm x 100mm with Flush
Door Shutter Solid Bond Wood black board type with commercial ply on
both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 250mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.
0.00
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 250 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
13
Add overheads @
Rate
Unit
Per
2.4
2.13
0.03195
0.01800
0.04995
cum
cum
cum
4.9
sqm
88994.00
80094.00
1
1
Cum
Cum
1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Each
Sqm
685.00
685.00
14%
160 of 517
D-W data
Sno
Qty
Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13
mtrs with Medium teak wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Alluminimum Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.
Rate
Unit
Per
1.22
2.13
0.03195
0.00915
0.04110
cum
cum
cum
2.28
sqm
88994.00
80094.00
1
1
Cum
Cum
1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Each
685.00
Sqm
685.00
1
2
3
4
5
6
7
8
9
10
2.28
6.00
1.00
2.00
2.00
6.00
1.00
2.00
2.28
12
0.00
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
14
Add overheads @
14%
161 of 517
D-W data
Sno
3
1
2
3
4
5
6
7
8
9
10
Qty
1.6
6.00
1.00
2.00
1.00
3.00
1.00
1.00
1.60
12
Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 0.90x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.
D6
0.00
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
14
Add overheads @
Rate
Unit
Per
0.9
2.13
0.03195
0.00675
0.03870
cum
cum
cum
1.6
sqm
88994.00
80094.00
1
1
Cum
Cum
1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Each
685.00
Sqm
685.00
14%
162 of 517
D-W data
Sno
Qty
Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 0.76x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 150mm long 1 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
250 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Fixing in position of Aluminium Sheet 24 guage of full width of
shutter to a height of 0.60 mtrs for interior face and 0.15 mtrs to external
face , Sales and Other Taxes cost and convenyance of all materials to site
all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complte for finsihed item of work.
Rate
Unit
Per
0.76
2.13
0.03195
0.00570
0.03765
cum
cum
cum
1.29
sqm
88994.00
80094.00
1
1
Cum
Cum
1488.00
25.00
114.00
391.00
140.00
34.00
179.00
302.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Sqm
685.00
Sqm
685.00
4
1
1
2
3
4
5
6
7
8
9
10
11
1.29
6.00
1.00
1.00
2.00
3.00
1.00
0.48
1.29
0.00
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 150 long Aluminium Towerbolts (BMT-G.08)
Cost of 250mm Long Aluminium Aldrops(BMT-G.41)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 250 MM long (BMT-G.49)
Cost of 24 guage Alluminium Sheet (BMS-W.18)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
Add overheads @
14%
163 of 517
D-W data
Sno
4
1
2
3
4
5
6
7
8
9
10
Qty
1.95
6.00
1.00
2.00
2.00
6.00
1.00
2.00
1.95
11
12
13
14
Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.05x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, MS Powder coated Handles 150mm long 2
Nos, 300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges
6Nos, 300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on
shutter Fixing in position , with Hardware fixtures etc., complete for finsihed
utem of work.
0.00
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
Add overheads @
Rate
Unit
Per
1.05
2.13
0.03195
0.00788
0.03983
cum
cum
cum
1.95
sqm
88994.00
80094.00
1
1
Cum
Cum
1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Each
685.00
Sqm
685.00
14%
164 of 517
D-W data
Sno
5
1
2
3
4
5
6
7
8
9
10
Qty
1.79
6.00
1.00
2.00
1.00
3.00
1.00
1.00
1.79
12
Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 1.00x2.13
mtrs with Medium teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 200mm long 2 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed item of work.
0.00
Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 200 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
14
Add overheads @
Rate
Unit
Per
0.9
2.13
0.03195
0.00750
0.03945
cum
cum
cum
1.79
sqm
88994.00
80094.00
1
1
Cum
Cum
1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00
1
1
1
1
1
1
1
1
Sqm
Each
Each
Each
Each
Each
Each
Each
Sqm
685.00
685.00
14%
Providing and fixing factory made Polyvinyl chloride (PVC) Door Frame of
the size 50 x 47mm with a wall thickness of 5mm, made out of extruded
5mm rigid PVC foam sheet, mitre cut at two corners and joined with 2nos.
of 150mm long brackets of 15x15mm M.S. square tube. The two vertical
door profiles are to be reinforced with 19x19mm M.S. Square tube of 19
gauge. The door frame shall be fixed to the wall using 65/100mm long M.S.
Screws through the frame by using PVC fasteners. A minimum of 4nos. of
screws to be provided for each vertical member & minimum 2nos. for
horizontal member etc. complete as per manufacturers specification and
direction of Engineer-in-Charge for finished item of work
165 of 517
D-W data
Sno
Qty
1 rmt
Description of Item
cost of PVC door frame (BMT-N.01)
Add overheads @
Rate per / Each
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x
19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall
have a coat of steel primers of approved make and manufacture. M.S.
frame shall be covered with 5mm thick heat moulded PVC C channel of
size 30 x 50mm forming stiles, and 5mm thick, 75mm wide PVC sheets for
top rail, lock rail & bottom rail on either side, and 10mm (5mm x 2) thick,
20mm wide cross PVC sheet as gap insert for top rail & bottom rail.
Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded /
sealed to the stiles & rails with 30mm wide x 5mm thick PVC sheet beading
on either side, and joined together with solvent cement adhesive etc. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior
side of the C Channel using PVC solvent adhesive. Complete as per
direction of Engineer-in-charge, manufacturers specification & drawing for
finished item of work .
Rate
325.00
14%
Unit
1
Per
Rmt
2362.00
14%
sqm
7288
558
1
-1
SQM
8
Providing & Fixing of Openable Windows with Fly-mesh made of
pre-painted steel (Base Steel as per IS 513 of 0.6mm thick
galvanized as per IS 277 with zinc of 150 GSM) primer coated
with epoxy primer of 5-7 microns thick, finish painted with a
polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer and the section for outer frame of 72 x
55mm, centre mullion of 72 x 50mm, section for fixed glass
beading section of 12 x 12 mm and section for shutters of 47 x 20
mm and outer frame & mullion sections with rebate for glazed
shutters, fly mesh and a 20 mm provision for guard bars/grills and
fly mesh shutter section of 20 x 40 mm and the sections cut to
length metre joined with corner bracket, centre mullions fixed with
mullion cap, stay, handles, latch 2 Nos of heavy duty stainless
steel pivot hinges per shutter and panelled with 5mm thick plain
float glass and S.S. Mesh for fly mesh shutter (304 grade), fitted
using rubber gaskets
including fixing the windows in the concrete/masonry wall by
means of self expanding screws, including 10mm Square guard
bars with 6 (152.4mm) pitch , complete for finished item of work
a)
166 of 517
D-W data
Sno
Qty
Description of Item
Add 0.5 mm thick Galvalume corrugated sheet BMS-W.55
Add 14% overheads
Rate per sqmt.
b)
Rate
456
Total
14%
Unit
1
Per
SQM
7069
SQM
456
Total
14%
SQM
4737
14%
SQM
167 of 517
D-W data
Sno
10
Qty
Description of Item
Rate
Unit
Providing and fixing Structural Glazing fabricated from Roll formed sections made of Pre-painted Steel /
Powder coated (Base steel as per IS 513 of D quality, galvanized as per IS 277 with Zinc of 120
Gm/Sqm) with total coated thickness of 0.72 mm and the glass holding section made of 304 grade
stainless steel of 0.58 mm thick galvanised steel section as stiffeners inside the colour coated steel powder
coated sections as per the design requirement & calculations to suit wind pressures as given in IS: 875, the
primer coat with epoxy primer of 5 7 microns thick, finish painted with a polyester paint of 12-16
microns thick and back coated with Alkyd backer of 5-7 microns or powder coated with pure polyester
powder up to 50-60 microns thick and the vertical section of 50 mm x 99 mm x 0.72 mm, 33 mm x 56
mm x 0.72 mm for frame horizontal section, stiffener section of 47 mm x 97 mm x 1 mm, cover profiles
sections of 20 mm x 58 mm x 0.58 mm, glass holding section of 37 mm x 37 mm & 37 mm x 18 mm
including fixing 5mm thick Ocean Blue reflective glass, brackets made of CRCA powder
coated/Electroplated to connect vertical to horizontal, vertical to slab, to fix verticals at top & bottom as
per site requirement and gasket made of Ethyl Propylene Diamine Monomer, U.V. resistant silicon sealant
including fixing in concrete/masonry wall with self-expanding cap & screws inclusive of cost and
conveyance of all materials to site, all labour charges, incidental charges, cost of all consumables etc. and
fixing
7288
14%
Per
SQM
Supply and fixing of MS grill Window of 2.73X 1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35
Harizontal 2 x 2.73
10 mm SQ rod@ 100c/c
Verticals 14 x 1.32
Harizontal 26x 2.69
MS Aldrop,Tower Bolt and Holdfast
total weight
Rate analysis
cost of MS steel
Fabrication charges BMM -V-14
Fixing Charges BMM -V-15
Over Head Charges
2.7
5.46
8.16
3.5
28.56
18.48
69.94
88.42
0.78
68.968
0.55
98.078
98.08
98.08
98.08
5890.54
32.06
24.00
4.00
0.14
Say
Supply and fixing of MS grill Window of 3.23X 1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35
Harizontal 2 x 3.23
10 mm SQ rod@ 100c/c
Verticals 14 x 1.32
Harizontal 30x 2.93
MS Aldrop,Tower Bolt and Holdfast
168 of 517
2.7
6.46
9.16
3.5
32.06
18.48
87.9
106.38
0.78
82.976
0.55
D-W data
Sno
Qty
Description of Item
total weight
Rate analysis
cost of MS steel
Fabrication charges BMM -V-14
Rate
Unit
115.59
115.59
32.06
24.00
115.59
4.00
6942.12
0.14
Per
115.59
Say
Supply and fixing of MS grill Window of 2.26 x1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35
2.7
Harizontal 2 x 2.26
4.52
7.22
3.5
25.27
0.78
46.332
10 mm SQ rod@ 100c/c
Verticals 14 x 1.32
18.48
40.92
59.4
0.55
total weight
72.152
Rate analysis
cost of MS steel
72.15
32.06
72.15
24.00
72.15
4.00
4333.45
0.14
Say
Supply and fixing of MS grill Window of 3 x1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35
2.7
Harizontal 2 x 3
6
8.7
3.5
30.45
0.78
73.226
10 mm SQ rod@ 100c/c
Verticals 14 x 1.32
18.48
75.4
93.88
169 of 517
D-W data
Sno
Qty
Description of Item
Rate
Unit
Per
0.55
total weight
104.23
Rate analysis
cost of MS steel
104.23
32.06
104.23
24.00
104.23
4.00
6259.84
0.14
Say
170 of 517
D-W data
Amount
3.24
2843.36
913.07
4300.32
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1979.65
0.00
11779.40
1603.77
13383.20
171 of 517
D-W data
Amount
4.26
2843.36
1201.41
5758.56
150.00
425.00
396.00
280.00
204.00
188.00
100.00
2650.95
0.00
14197.28
1932.96
16130.25
172 of 517
D-W data
Amount
5.11
2843.36
1441.69
7291.20
150.00
425.00
396.00
280.00
204.00
188.00
100.00
3356.50
0.00
16675.75
2270.40
18946.20
173 of 517
D-W data
Amount
2.6
2843.36
732.86
3392.64
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1561.80
0.00
10273.66
1398.76
11672.45
174 of 517
D-W data
Amount
1.92
2843.36
540.63
2380.80
150.00
425.00
396.00
140.00
102.00
188.00
50.00
1096.00
0.00
8311.79
1131.65
9443.45
175 of 517
D-W data
Amount
1.62
2843.36
456.54
1919.52
150.00
114.00
391.00
280.00
102.00
179.00
144.96
883.65
0.00
7464.03
1016.23
8480.30
176 of 517
D-W data
Amount
2.24
2843.36
630.74
2901.60
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1335.75
0.00
9454.45
1287.22
10741.70
177 of 517
D-W data
Amount
1.92
2843.36
600.71
2663.52
150.00
425.00
396.00
140.00
102.00
188.00
50.00
1226.15
0.00
8784.74
1196.04
9980.80
178 of 517
D-W data
Amount
325.00
44.25
369.25
2362.00
321.59
2683.60
7288.00
-558.00
179 of 517
D-W data
Amount
456.00
7186.00
978.37
8164.40
7069.00
-558.00
456.00
6967.00
948.56
7915.60
4737.00
644.94
5381.95
180 of 517
D-W data
Amount
7288.00
992.26
8280.30
3144.37
2353.86
392.31
824.68
6715.22
6716.00
181 of 517
D-W data
Amount
3705.70
2774.07
462.35
971.90
7914.02
7915.00
2313.19
1731.65
288.61
606.68
4940.13
4941.00
182 of 517
D-W data
Amount
3341.50
2501.43
416.91
876.38
7136.21
7137.00
183 of 517
D-W data
1 Supplying & fixing of Medium Teak Wood Panneled Main Door of Size 4.00 Mts X 2.70 Mts made with outer frame of
section 4"x5"(100x125mm) two horizontal and four verticals fixed frame,Both sides fixed with Iron grill (size:1900 x
500mm) ,(1850x500mm)madeup of Vertical & Horizontal bars of 10mm Square welded to MS Flat 20x5mm alround
forming (100x125mm) grid and with 5mm thick pin headed glass panels (2Nos of 500mmX1900mm, 2'nos of 500mm
500mm,1 no of 2600mmx500mm), MT beading .The shutters should be made up of size 650mm x 1900mm (4nos) fra
with 2"thick(50mm) and scantlings(planks) should be 1" (25mm thick) including fixing all fixtures such as 350mm long
Brass Aldrops , 200mm Long Towetr bolts(4 nos), Brass fancy Door Handles 250mm long (2nos)out side, 250mm long
(2nos) inside, BrassHinges 150mm long (4x4=16Nos) including polishing with melamine finish including all labour cha
for wrought &put up all other charges stc., complete for finished item of work.
Nos
Qty
Rate
per
4.0
0.1
0.125
0.15
97894
cum
Verticals end
Verticals midle
BMT-E.02 (2 TO 3mt length)
2
2
2.7
2.1
0.1
0.1
0.125
0.125
88994
cum
0.07
0.05
0.120
cum
0.01
0.009
cum
80094
cum
80094
cum
160189
cum
I. Outer frame:Horizontals
BMT-E.03
Iron Grill
Horizontal
Horizontal
10mm Sq.bars Ver.
8
8
8
8
4
8
18
8
36
0.7
0.66
0.53
1.93
0.1
0.125
0.125
0.125
0.42
0.42
0.42
0.62
0.125
0.05
0.05
0.05
0.033
0.027
0.097
0.156
cum
0.035
0.026
0.061
cum
15.2
9
13.2
18
55.4
43.489
0.025
0.025
1.9
0.5
1.65
0.5
10 mm Sq.bars 0.785kg/rm ==
or say
Alround MS frame
(4*(0.5+1.9) +4*(0.5+1.85)) =
19
Total Qty.of
Wood
184 of 517
43.5
Kgs
Rm
'
'
Rm
Rm
32.06
Kg
Rm
14.915
15
Kgs
58.5
Kgs
day
day
day
0.49607
cum
32.06
Kg
28
Kg
2230.2
4646.25
2816
9692.45
cum
3.75
430
sqm
2473
Each
644
Each
530
Each
454
Each
819
Each
16
16
383
Each
198
Each
90
each
Asst. Exe.Engineer
APEWIDC, Kuppam
Executive Engineer
APEWIDC, Chittoor
Superintending Engineer
APEWIDC, Kadapa
185 of 517
Amount
14684.10
10679.28
700.82
12494.66
9822.79
1394.61
480.90
1638.00
4808.13
186 of 517
1612.50
2473
644
2120
908
1638
6128
396
360
72982.79
10217.59
83200.38
83201
187 of 517
100 M
100
Nos
188 of 517
0.00
1
2
2800.00
44.00
2800.00
88.00
2
12
12
50
179.00
25.00
6.00
7.00
358.00
300.00
72.00
350.00
3968.00
0.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
day
day
day
day
0%
0%
3
1
3968.00 1
0
960.00 2
750.00 0
0
750.00 6
2
2
2
2
480.00
375.00
375.00
420.00
3300.00
840.00
0.00
0.00
7268.00
72.70
1051.00
1051.00
6
6
100
18.00
21.00
0.61
a) Material
elec-1.5.1 14/0.3mm (1.00 Sqmm)
FRLS PVC 100 M
insulated flexible copper wire
elec-1.7.1 6A Switch @18/- each
each
elec-1.7.13 6A 3 way Ceiling Rose@21/-each
each
elec-8.1.51 25 x 20 cms (10" x8") Hylam sheet 3mm Sq.in
thick
Add contr profit @14% on material
0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.81 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
C) Cost for 6 Points
189 of 517
108.00
126.00
61.00
1346.00
0.00
1346.00
0.6
1.2
0.6
480.00
375.00
375.00
963.00
288.00
450.00
225.00
0.00
0.00
2309.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
3
1
384.85 1
0
2
0
0
6
1.50
100
338.40
507.60
190 of 517
0.67
2
0.67
924.00
480.00
375.00
375.00
1322.85
1848.00
1848.00
0.00
1848.00
321.60
750.00
251.25
0.00
0.00
3170.85
Ele-Data
Index Specific
-code
ation
No.
3.1.2
Description
Unit
100
3
1
31.75 1
0
2
0
0
6
924.00
924.00
0.00
924.00
0.34
1
0.34
480.00
375.00
375.00
665.70
163.20
375.00
127.50
0.00
0.00
1589.70
15.90
allowence
on
labour
191 of 517
100
1358.00
0.00
day
day
day
0%
0.67
2
0.67
480.00
375.00
375.00
2716.00
2716.00
0.00
2716.00
321.60
750.00
251.25
0.00
Ele-Data
Index Specific
-code
ation
No.
Description
Add contr profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100
0%
1322.85
100
3
1
0.00 1
0
4038.85 40.40 2
0
0
6
Unit
0.34
1
0.34
1358.00
480.00
375.00
375.00
665.70
1358.00
1358.00
0.00
1358.00
163.20
375.00
127.50
0.00
0.00
2023.70
20.25
192 of 517
100 M
2.00
2510.00
1.00
1051.00
1051.00
6071.00
0.00
6071.00
0.00
day
5020.00
1.01
480.00
484.80
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.81 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100
3
1
1125.00 1
0
378.75 0.00 2
0
0.00 0
8059.55 6
375.00
375.00
1988.55
80.60
8059.55
3.1.5
elec-1.5.3
3833.00
1.00
2510.00
7666.00
2510.00
10176.00
0.00
10176.00
1.34
4
1.34
480.00
375.00
375.00
2645.70
643.20
1500.00
502.50
0.00
0.00
12821.70
128.25
2.00
193 of 517
100 M
2.00
5828.00
1.00
2510.00
2510.00
14166.00
0.00
14166.00
0.00
day
day
11656.00
1.34
4
480.00
375.00
643.20
1500.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100
3
1
502.50 1
0
0.00 0.00 2
0
16811.70 0
168.15 6
375.00
2645.70
100 M
4.00
5828.00
23312.00
1.00
2510.00
2510.00
25822.00
0.00
25822.00
2.34
7
2.34
480.00
375.00
375.00
4625.70
1123.20
2625.00
877.50
0.00
0.00
30447.70
304.48
100 M
194 of 517
2.00
9030.00
18060.00
18060.00
0.00
18060.00
1
3
1
480.00
375.00
375.00
480.00
1125.00
375.00
0.00
Ele-Data
Index Specific
-code
ation
No.
Description
Add contr profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100
0%
1980.00
3
1
0.00 1
0
20040.00 200.40 2
0
0
6
Unit
100 M
1.00
9030.00
9030.00
9030.00
0.00
9030.00
0.5
1.5
0.5
480.00
375.00
375.00
990.00
240.00
562.50
187.50
0.00
0.00
10020.00
100.20
1
1
195 of 517
2.00
1.00
2510.00
1051.00
5020.00
1051.00
6071.00
0.00
6071.00
1.005
3
1.005
480.00
375.00
375.00
482.40
1125.00
376.88
0.00
day
day
day
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
0%
0%
3
1
0.00 1
0
0.00 8055.28 2
0
80.60 0
6
1
1
2.00
1.00
3833.00
2510.00
1.34
4
1.34
.
480.00
375.00
375.00
2645.70
7666.00
2510.00
10176.00
0.00
10176.00
643.20
1500.00
502.50
0.00
0.00
12821.70
128.25
1
1
196 of 517
2.00
1.00
5828.00
2510.00
1.34
4
1.34
480.00
375.00
375.00
11656.00
2510.00
14166.00
0.00
14166.00
643.20
1500.00
502.50
0.00
Ele-Data
Index Specific
-code
ation
No.
Description
Add contr profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100
0%
2645.70
1
1
19
4.00
1.00
5828.00
2510.00
23312.00
2510.00
25822.00
0.00
25822.00
2.5
7.5
2.5
480.00
375.00
375.00
1200.00
2812.50
937.50
0.00
0.00
30772.00
307.75
0.00
3
1
0.00 1
0
16811.70 168.15 2
0
0
6
Unit
day
day
day
0%
0%
4950.00
FRLS
PVC 100 M
9030.00
36120.00
3383.00
3383.00
197 of 517
0.00
39503.00
0.00
39503.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
b) Labour charges :
elec-8.1.74 Skilled Electrician (2.0 + 0.5)
day
elec-8.1.75 Semi skilled Electrician (6 + 1.5)
day
elec-8.1.81 Helpers (2.0 + 0.5)
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
2.1.4
2
6
2
480.00
375.00
375.00
3960.00
0.00
43463.00
434.65
each
each
1
1
3
1
1
0
960.00 2250.00 2
750.00 0
0
0.00 6
27.00
18.00
.
480.00
375.00
57.29
27.00
18.00
45.00
0.00
45.00
32.16
25.13
0.00
0.00
102.30
198 of 517
each
each
3
3
27.00
18.00
Sq.in
100
0.61
81.00
54.00
61.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
.
480.00
375.00
171.86
75.38
0.00
0.00
367.90
100 M
each
each
12
3
1
196.00 1
0
0.00 196.00 2
0
0
96.48 6
1
15
15
1051.00
18.00
27.00
1051.00
270.00
405.00
1726.00
0.00
1726.00
1.5
1.5
1.5
480.00
375.00
375.00
720.00
562.50
562.50
0.00
0.00
3571.00
238.10
1845.00
199 of 517
Ele-Data
Index Specific
-code
ation
No.
elec-1.3.4
Description
Unit
each
137.00
Sq.in
each
each
50
1
1
0.61
102.00
65.00
a) Material
3
1
1
0
137.00 2
30.50 0
102.00 0
6
65.00
334.50
0.00
0.00
334.50
b) Labour charges :
Skilled Electrician
elec-8.1.77 Semi Skilled Electrician
elec-8.1.81 Helpers
day
day
day
0.1
0.1
0.1
480.00
375.00
375.00
48.00
37.50
37.50
0.00
123.00
0.00
457.50
0%
0%
elec2.12.67
Nos
590.00
590.00
Nos
162.00
162.00
752.00
0.00
752.00
0.25
0.25
0.25
480.00
375.00
375.00
120.00
93.75
93.75
0.00
0.00
130.00
200 of 517
307.50
1189.50
Ele-Data
Index Specific
-code
ation
No.
21
Description
Unit
3
1
1
0
2
0
0
6
each
each
2200.00
2200.00
1
12
678.00
162.00
678.00
1944.00
4822.00
0.00
4822.00
0.5
1
1
480.00
375.00
375.00
240.00
375.00
375.00
0.00
0.00
15.00
990.00
15.00
5827.00
201 of 517
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
each
each
2491.00
1
12
890.00
201.00
0.5
1
1
480.00
375.00
375.00
990.00
15.00
3
1
1
0
2491.00 2
0
0
6
890.00
2412.00
5793.00
0.00
5793.00
240.00
375.00
375.00
0.00
0.00
15.00
6798.00
each
each
202 of 517
2491.00
2491.00
1
12
890.00
201.00
890.00
2412.00
5793.00
0.00
5793.00
0.5
1
1
480.00
375.00
375.00
240.00
375.00
375.00
0.00
day
day
day
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
0%
0%
LS
3
1
0.00 1
0
0.00 15.00 2
0
0
6798.00 6
each
each
203 of 517
2491.00
2491.00
1
12
956.00
201.00
956.00
2412.00
5859.00
0.00
5859.00
1
1
1
480.00
375.00
375.00
480.00
375.00
375.00
0.00
0.00
14.00
1230.00
14.00
7103.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
22
Supply and fixing 8 way SPN Distribution
board with IP-43 protection (Metal Door)
suitable for 1 No. 40A single phase DP
Isolator as incomer and 6 Nos 6-32 A
10kA SP MCBs as outing going including
internal connection and labour charges
for surface / flush mounting etc.,
complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
elec2.12.11
3
1
1
0
2
0
0
6
elec40A D.P.Isolator
2.10.10
elec-2.9.9 10 kA - 6-32A range SP MCBs
each
each
204 of 517
1245.00
1245.00
1
6
367.00
201.00
367.00
1206.00
2818.00
0.00
2818.00
0.5
0.5
1
480.00
375.00
375.00
240.00
187.50
375.00
0.00
0.00
9.50
3630.00
802.50
9.50
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec.2.12.5 6 Way TPN Vertical DB with IP -43 (Metal Nos
0
door) protection suitable for 125A, 4
Pole, 25kA MCCB as incomer.
elec-2.8.13 125 Amps, 4 Pole , 25 kA MCCB
elec-2.9.14 10 kA, 63A TP MCBs:
elec-2.9.9 10kA, 6 to 32A SP MCBs:
Nos
Nos
Nos
9823.00
1
8
0
7194.00
1477.00
201.00
1
1
1
480.00
375.00
375.00
1230.00
19.00
3
1
9823.00 1
0
2
7194.00 0
0
11816.00 6
Say
0.00
28833.00
0.00
28833.00
480.00
375.00
375.00
0.00
0.00
19.00
30082.00
30082.00
Nos
9823.00
9823.00
Nos
Nos
Nos
1
4
12
7194.00
1477.00
201.00
0.00
7194.00
5908.00
2412.00
25337.00
0.00
25337.00
480.00
205 of 517
day
480.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,
1
1
375.00
375.00
1230.00
19.00
3
1
375.00 1
0
375.00 0.00 2
0.00 0
0
19.00 6
Say
26586.00
26586.00
Nos
9823.00
9823.00
Nos
Nos
Nos
1
24
5668.00
1477.00
162.00
5668.00
0.00
3888.00
19379.00
0.00
19379.00
1
1
1
480.00
375.00
375.00
1230.00
19.00
Say
480.00
375.00
375.00
0.00
0.00
19.00
20628.00
20628.00
206 of 517
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
3
1
1
0
2
0
0
6
207 of 517
8740
8740
363
1089
1
1
1
1
3
2500
175
2500
175
135
2500
175
2500
175
405
450
2700
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-2.6.1 32A 240 V Porcelain Rewirable fuse units
- 3 Nos.
elec-2.5.1 upto 32A HRC fuse link - 3 Nos:
Outgoing :
elec-2.1.2 63A TPN SFU -10 NOS - L&T Make
99
50
10
2329
Sub TOTAL:
Bus bars and insulators 25%
Cost of enclosure @ 45%
41871
10467.75
18841.95
4187.10
3
1
297 1
0
02
0
0
23290 6
2093.55
628.07
78089.42
0.00
78089.45
0.00
a) Material
elec.8.1.52 Earth Work Excavation of Hard gravel
Soil with small boulder for trench 1st
step of size 1.5 x 0.6 x 0.9 m
Excavation of Hard disteggrated rocks
and boulders for trench 2nd Step of size
1.2 x 0.6 x 1.2 m (Civil SSR)
cum
0.85
0.00
0.00
cum
0.9
0.00
0.00
0.00
0.00
2.5
1
355.00
75.00
208 of 517
887.50
75.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec.8.1.59 Drilling of 16 Nos through holes of 12mm Each
dia to G.I pipe
elec-8.1.12 G.I Nuts, Bolts an Washers
elec.8.1.61 18" dia hume pipe ring
elec-8.1.13 Hard Coke
elec-8.1.14 Salt
Set
Each
Kg
Kg
16
6.00
4
1
40
20
13.00
220.00
9.00
4.00
0.5
0.5
375.00
375.00
Nos
Nos
0%
0%
375.00
Say
27
3
1
96.00 1
0
52.00 2
220.00 0
0
360.00 6
80.00
1770.50
0.00
1770.50
187.50
187.50
0.00
0.00
2145.50
2145.50
a) Material
elec-8.1.45 No.8 SWG G.I wire 100 M Length (0.104
Kg / Mtr)
elec-8.1.07 U' Nails
209 of 517
Kg
10.4
68.00
707.20
100No
s
1.5
44.00
66.00
773.20
0.00
773.20
0.00
day
0%
0%
375.00
750.00
750.00
0.00
0.00
1523.20
15.25
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
28
Supply, Transportation and fixing of 4' of
1x 36/ 40 Watt Box type Tube Light
luminaire powder coated CRCA sheet
steel housing with
electronic ballast
suitable for 40 Watt tube including all
labour charges for fixing fitting on
varnished teak wood round blocks with
flexible 3 core wire etc.,, complete with
all connections including cost of 40W
tube.
Makes:
Surya /
Havells / HPL /
Fortune Art
a) Material
elec-3.6.5 4' x 40 watts box type flourscent light
fitting.
elec-3.7.16 Lamp cost of 40W
elec-8.1.31 Tw Round blocks
Elec-1.4.34 screws with rawal plugs
Elec-1.6.8 23/0060 twin core flexible copper cable
Rate per each
Add contr profit @14% on material
Total for material
each
each
each
each
M
1
2
2
1.5
1060.00
45.00
7.00
0.00
0.00
0.00
a) Labour charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per each
Fixing of 40W tube light luminaire on wall
/ Ceiling with TW round blocks with
all
accessories
including
giving
connections and all labour charges etc.,
complete.
Rate per each
a) Material
Elec-1.6.8 23/0060 twin core flexible copper cable
M
Elec-1.4.34 screws with rawal plugs
each
Elec-8.1.35 T.W round blocks
each
Cement and sand etc.,
LS
0.1
0.1
480
375
85.50
3
1
1
0
2
0
0
6
1060.00
45.00
14.00
0
0
1119.00
0.00
1119.00
48.00
37.50
0.00
0.00
1204.50
7.9.3
210 of 517
1
2
2
5.6
0.1
0.1
1040.00
54.00
7.00
480
375
85.50
10.4
1.08
14
2.11
27.59
0.00
29.70
48
37.5
0.00
0.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
3
1
115.20 1
0
2
0
0
6
29
each
each
each
1
1
1
20.00
110.00
21.00
20.00
110.00
-21.00
109.00
0.00
109.00
0.05
0.05
480
345
24.00
17.25
0.00
0.00
150.25
39.25
30
each
each
211 of 517
0.00
1
1
102
44
102.00
44.00
146.00
0.00
146.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Rate per each
31
day
day
0%
0%
0.062
0.062
480
345
51.15
197.15
each
each
3
1
1
0
29.76 21.39 2
0
0.00 0
0.00 6
1
1
102
39.6
102
39.6
141.6
0.00
141.6
0.062
0.062
480
345
29.76
21.39
0.00
0.00
192.75
51.15
a) Material
elec-5.1.1 1200 mm (48") Ceiling Fan
Transportation Charges on Unit Cost
Add contr profit @14% on material
Total material cost
212 of 517
each
0.00
1
1%
1600.00
16.00
1600
16.00
1616.00
0.00
1616.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
33
Supply and erecting Electronic
type
regulator for ceiling fans 1200 mm
sweep complete erected on existing
board.Make : Anchor Penta Cherry / Gold
Medal Olive / Million Zoom
a) Material
elec-1.7.12 Steeped type Electronics type Regulator
M
Add contr profit @14% on material
0.00
Total material cost
b) Labour charges.
elec-8.1.75 Semi skilled Electrician
day
Sundries.
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per Each
Note : Labour is Considered for 10
jobs / day
34
220.00
220.00
0.00
220.00
0.1
375.00
37.50
21.20
0.00
0.00
278.70
58.70
3
1
1
0
2
0
0
6
Labour Charges
Labour charges for Fixing of Ceiling fan
and regulator including transportation
and giving connections with twin core
wire etc., complete.
a) Material
elec-1.6.8 23/0060 Twin Core wire
100 M
Unforseen item works, such as painting LS
to down rod, screws etc.,
Add contr profit @14% on material
0.00
Total for material
b) Labour charges.
elec-8.1.75 Skilled Electrician
day
elec-8.1.82 Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per Each
Note : Labour is Considered for 8
fans / day
35
1
1
1040.00
3.00
1040.00
3.00
1043.00
0.00
1043.00
0.125
0.125
440.00
345.00
98.13
55.00
43.13
0.00
0.00
1141.13
142.64
213 of 517
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
a) Material
elec-5.1.11 300mm (12") 1350 RPM H.D. Exhaust each
Fan
Transportation Charges on Unit Cost
Rate per Each
Add contr profit @14% on material
0.00
Total for material
35
1
1%
2645.00
26.45
2671.45
a) Material
elec-5.1.13 300mm (12") 900 RPM H.D. Exhaust Fan 100 m
Transportation Charges on Unit Cost
Rate per Each
Add contr profit @14% on material
0.00
Total for material
36
3
1
1
0
2645.00 26.45 2
0
2671.45 0
0.00 6
1
1%
2645.00
26.45
2645.00
26.45
2671.45
0.00
2671.45
1
1
1040.00
6.60
1040.00
6.60
1046.60
0.00
1046.60
0.25
0.25
0.25
440.00
345.00
385.00
292.50
24.34
110.00
86.25
96.25
0.00
0.00
24.34
1363.44
227.24
a) Material
elec-1.6.8 23/0060 Twin flat wire
elec-8.1.50 Cement
100 M
kg
214 of 517
Ele-Data
Index Specific
-code
ation
No.
37
Description
Unit
Supply
of
1x40W
weather
proof
flourescent streetlight fitting comprising
canopy of sheet Aluminium in stove
enamel finish with copper / VPIT ballast,
capacitor,
tube
and
starter
etc.,
complete.
Makes: Phillips / GE / Wipro
a) Material
elec-3.1.1 1x40W WP flourscent street light fitting.
elec-3.7.7 Lamp cost of 40W
Add contr profit @14% on material
Total for material
38
each
each
1
1
1400.00
45.00
1
10
1
1
226.00
10.40
25.00
35.00
226.00
104.00
25.00
35.00
390.00
0.00
390.00
0.2
0.2
0.2
440.00
385.00
345.00
88.00
77.00
69.00
0.00
0.00
624.00
0.00
3
1
1
0
2
0
0
6
1400.00
45.00
1445.00
0.00
1445.00
a) Material
elec-8.1.55 25mm dia G.I pipe light grade
elec-1.6.8 23/0060 twin core flexible copper cable
Pipe bending charges
M.S flat and welding charges
M
M
LS
LS
39
234.00
215 of 517
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
a) Material
elec-3.1.7 150W HPSV Lamp fitting single piece die each
cast Aluminium body with copper wound
ballast and capacitor, Ignitor, with pot
optics
40
5327.00
710.00
1
4
355.00
25.10
LS
25.00
day
day
day
day
0%
0%
0.25
0.25
0.25
0.25
440.00
385.00
345.00
385.00
0.00
710.00
6037.00
0.00
6037.00
6037.00
a) Material
elec.8.1.57 40mm G.I pipe for Bracket
elec.1.5.3 2.5 Sq.mm flexible copper cable
M
M
0.00
41
each
3
1
1
0
5327.00 2
0
0
6
278.75
MV / SV
Say
355.00
100.40
455.40
0.00
455.40
25.00
110.00
96.25
86.25
96.25
0.00
0.00
869.15
869.15
216 of 517
100 M
0.00
1010.00
1010.00
0.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
day
day
day
0%
0%
0.34
1
0.34
440.00
375.00
345.00
641.90
3
1
1010.00 1
0
149.60 2
375.00 0
0
117.30 6
0.00
0.00
1651.90
16.55
42
1
1
1
48.00
57.00
14.00
0.1
0.1
0.1
440.00
375.00
345.00
116.00
48.00
57.00
14.00
119.00
0.00
119.00
44.00
37.50
34.50
0.00
0.00
235.00
200.00
2580.00
200.00
100 M
217 of 517
2580.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
440.00
375.00
345.00
641.90
117.30
0.00
0.00
3221.90
32.25
a) Material
elec-7.1.4 cat-6 RJ 45 information oulet
elec-1.3.1 MS box
3
1
0.00 1
0
2580.00 2
0
149.60 0
375.00 6
1
1
340.00
57.00
340.00
57.00
0.00
397.00
0.00
397.00
0.2
0.2
0.12
440.00
375.00
345.00
88.00
75.00
41.40
0.00
0.00
204.40
601.40
100 M
0.00
218 of 517
2580.00
2580.00
0.00
2580.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.34
elec-8.1.75 Semi Skilled Electrician
day
1
elec-8.1.82 Helpers
day
0.34
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
46
440.00
375.00
345.00
641.90
0.00
3221.90
32.25
a) Material
elec1.7.17 TV socket outlet
elec-1.3.1 MS box
elec-1.4.3 6" X 6" sunglass delux board
Add contr profit @14% on material
0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for each
21
3
1
1
0
149.60 375.00 2
0
117.30 0
0.00 6
1
1
1
26.00
63.00
25.00
0.04
0.04
0.04
440.00
375.00
345.00
46.40
26.00
63.00
25.00
114.00
0.00
114.00
17.60
15.00
13.80
0.00
0.00
160.40
24 switch
Taking Output = each
a) Material
elec-7.1.5 24 port switch
each
each
each
219 of 517
0.00
5200.00
5200.00
0.00
0.00
5200.00
0.00
5200.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,
1
1
1
440.00
375.00
345.00
1160.00
14.00
3
1
440.00 1
0
375.00 345.00 2
0.00 0
0
0.00 6
14.00
6374.00
24 switch
Taking Output = each
a) Material
elec-7.1.24 17U floor mounting rack
each
each
each
10125.00
1
1
1
440.00
375.00
345.00
1160.00
14.00
10125.00
0.00
0.00
10125.00
0.00
10125.00
440.00
375.00
345.00
0.00
0.00
14.00
11299.00
220 of 517
Rmt
0.00
547.00
547.00
0.00
547.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
Rmt
0.00
326.00
326.00
0.00
326.00
Rmt
0.00
347.00
347.00
0.00
347.00
Rmt
0.00
207.00
207.00
0.00
207.00
Rmt
0.00
162.00
162.00
0.00
3
1
1
0
2
0
0
6
221 of 517
Ele-Data
Index Specific
-code
ation
No.
48
3
1
Total for material
162.00 1
0
2
0
Earth work excavation of Trench in hard ground soil, laying of U.G cables from 70 0sqm to 400
6
Description
Unit
a) Material
elec-8.1.52 Excavation of earth 100 x 0.3 X 0.9 m
elec-8.1.54 Cost of bricks (Civil SSR)
cum
1000
Nos
1
1
110.00
5427.01
110.00
5427.01
cum
Kg
each
1
25
12
924.09
5.81
83.00
924.09
145.25
996.00
7602.35
0.00
7602.35
2.5
320.00
800.00
480.00
750.00
640.00
0%
0%
1870.00
0.00
0.00
10272.35
102.75
Earth work excavation of Trench in hard ground soil, laying of U.G cables upto 50 Sq,mm on s
a) Material
elec-8.1.52 Excavation of earth 100 x 0.3 X 0.9 m
elec-8.1.54 Cost of bricks (Civil SSR)
222 of 517
cum
1000
Nos
1
1
110.00
5427.01
110.00
5427.01
Ele-Data
Index Specific
Description
-code
ation
No.
elec-8.1.53 Cost of sand (Civil SSR)
elec-8.1.50 Cement (Civil SSR)
elec-8.1.27 Cost of cable route indicator
Unit
cum
Kg
each
3
1
924.09 1
0
145.25 996.00 2
0
7602.35 0
0.00 6
924.09
5.81
83.00
7602.35
320.00
800.00
480.00
750.00
640.00
2.5
0%
0%
1870.00
0.00
0.00
10272.35
102.75
49
100
2
165.00
446.00
100
nos
59.00
236.00
kg
68.00
476.00
18104.00
0.00
18104.00
1
4
480.00
375.00
480.00
1500.00
0.00
0.00
21.00
20105.00
201.05
223 of 517
1980.00
16500.00
892.00
Ele-Data
Index Specific
-code
ation
No.
50
Description
Unit
a) Material
elec-2.6.4 100 A Fuse units
100 A neutral links
elec-1.4.31 T.W blocks ( 12" x 15" )
each
each
each
each
nos
224 of 517
3
1
1
484.00
118.00
109.00
1452.00
118.00
109.00
1679.00
0.00
1679.00
1
4
480.00
375.00
480.00
1500.00
0.00
0.00
50.00
3709.00
1980.00
1
2%
2
10438.00
0.25
0.25
480
375
158.00
213.75
3
1
1
0
2
0
0
6
10438.00
208.76
316.00
10962.76
0.00
10962.76
120.00
93.75
0.00
0.00
25.00
11201.55
Ele-Data
Index Specific
Description
-code
ation
No.
54
Supply and fixing of concealed box
PVC/MS with hook for fan
Unit
A.Material
elec-8.1.25 Fan hook box
each
Add contr profit @14% on material
0.00
Total for material
b) Labour charges
elecSkilled Electrician
day
8.1.74
elecHelper
day
8.1.82 Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate for each
3
1
1
0
2
0
0
88.00 6
88.00
0.00
88.00
0.05
0.05
480.00
375.00
42.75
24.00
18.75
0.00
0.00
130.75
Description
Unit
kg
372.4
50.00
18620.00
Elec8.1.29
Base
plate
600x600x8mm
plate(@62.80 kg /sq mtr)
MS
kg
37.68
61.00
2298.48
Elec8.1.29
kg
47.8
61.00
2915.80
Elec8.1.29
Elec8.1.29
kg
kg
12
15
61.00
61.00
732.00
915.00
Elec8.1.29
kg
13.5
61.00
823.50
Total Ms items
Add wastage @ 3%
Total weight
Kg
61.00
61.00
kg
498.38
14.951
513.33
30401.18
912.04
57618.00
Fabrication charges
Total cost for ms items
Add contr profit @14% on material
LS
513.3
9.00
4619.70
62237.70
0.00
225 of 517
0.00
3
1
1
0
2
0
0
6
Ele-Data
Index Specific
-code
ation
No.
Elec8.1.74
Elec8.1.82
Elec8.1.76
Elec8.1.85
Description
Unit
day
day
day
day
0%
0%
3
1
62237.70 1
0
2
0
880.00 0
1380.00 6
2
4
2
2
440.00
345.00
385.00
295.00
2740.00
770.00
590.00
0.00
0.00
65857.70
600.00
600.00
0.00
600.00
300.00
300.00
0.00
300.00
Each
0.00
1500.00
1500.00
0.00
1500.00
each
0.00
5900.00
5900.00
0.00
5900.00
226 of 517
Ele-Data
Index Specific
Description
-code
ation
No.
elec-6.5.10 HG fuse set
Add contr profit @14% on material
Total for AB switch
Unit
each
0.00
3
1
4000.00 1
0
0.00 4000.00 2
0
0
6
4000.00
658.00
658.00
0.00
658.00
2.5
280.00
700.00
Skilled Electrician
day
1
400.00
Helper
day
2
320.00
Man Mazdoor for concreting and embeddingday
of cable 2
way indicators
280.00
400.00
640.00
560.00
a) Material
elec-4.1.38 3.5corex150 sqmm cable
Rmt
Add contr profit @14% on material
0.00
Total for 150 sqmm cable
b) Labour charges for laying cable.
Man Mazdoor for spreading the sand and each
back filling the excavated soil.
227 of 517
0%
0%
1600.00
0.00
0.00
5.00
2305.00
23.05
681.05
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
8
Supply, installation,and commissioning
of 3Phases and neutral 415V,
free
standing type cubical panel board made
of 16 Gauge CRCA sheet steel, panel
shall be painted after processing 7 tank
process with RAL 7032 siemens grey. The
panel shall be consisting of suitable
rating of allumunium bus bars ( At the
rating of 0.8 A/Sq.mm) supported with
DMC/SMC and colour coded with heat
shrinkable sleeves. The bus bars fault
level shall be 50 KA and shall be as per
the requirement of local CEIG, fire
regulations, other authorities etc. The
panel shall be suitable for accomdating
the following switch gears including
supply of all components, hard wares etc
including all necessary civil works,
adequate reinforcement foundation bolts
suitable G.I earth strip , 100 x 50mm MS
base channel, earth bar,
door loop
earthings
.
Bus
bar
to
switch
interconnections,
3
1
1
0
2
0
0
6
Metering Set:
0- 400 A Digital Ammeter . - 1 No.
Ammeter selector switch - 1 No.
0-500V Digital Volt meter - 1 No.
Voltmeter selector switch - 1 No.
R, Y, B Indication lamps LED type, puse
buttons.
400 /5A C.T coils : 2 sets
20A Bakelite fuse fittings - 3 Nos.
2A HRC fuse link - 3 Nos:
228 of 517
each
each
each
each
each
22890.00
22890.00
1
1
1
1
3
2500.00
175.00
2500.00
175.00
135.00
2500.00
175.00
2500.00
175.00
405.00
6
3
3
450.00
130.00
45.00
2700.00
390.00
135.00
Ele-Data
Index Specific
Description
-code
ation
No.
ElecAPFC relay 8 stage.
6.3.13 Outgoing :
elec-2.8.14 250A 25KA MCCB-02 NOS -Legrand Make
elec-2.8.13 125A 25KA MCCB-02 NOS -Legrand Make
elec-2.8.12 63A 25KA MCCB -04 NOS - Legrand Make
Unit
13600.00
each
each
1
4
18010.00
6322.00
each
5668.00
3
1
13600.00 1
0
2
18010.00
0
25288.00 0
6
22672.00
0.00
111440.00
11144.00
50148.00
5572.00
178304.00
0.00
178304.00
1
2
4
440.00
345.00
345.00
2510.00
440.00
690.00
1380.00
0.00
0.00
###
a) Material
elec.8.1.52 Earth Work Excavation of Hard gravel
Soil with small boulder for trench 1st
step of size 1.5 x 0.9 x 0.9 m
Excavation of Hard disteggrated rocks
and boulders for trench 2nd Step of size
1.2 x 0.6 x 1.2 m (Civil SSR)
229 of 517
cum
1.21
220.00
cum
0.9
0.00
266.20
0.00
Ele-Data
55.00
2.5
1
381.00
75.00
3
1
55.00 1
0
2
952.50 0
0
75.00 6
18
5.00
90.00
4
1
20
20
13.00
275.00
9.00
4.00
52.00
275.00
180.00
80.00
2025.70
0.00
2025.70
0.5
0.5
345.00
345.00
172.50
172.50
0.00
0.00
Index Specific
-code
ation
No.
Description
Unit
Set
Each
Kg
Kg
day
day
0%
0%
345.00
Say
2370.70
a)Material
elec-8.1.41 GI strip
kg
Add contr profit @14% on material
0.00
Total material cost
b) Labour charges
elec-8.1.75 Semi skilled electrician
day
elec-8.1.82 Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
considered 50 mtr laying per day
Total for GI flat
Rmt
1.4
68.00
95.20
0.00
95.20
0.02
0.04
345.00
345.00
6.90
13.80
0.00
0.00
20.70
115.90
12
Cable termination
Supply and fixing of 3.5x150 sqmm
cable end termination
a)Material
230 of 517
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-4.2.7 Heavy duty flange type brass cable each
gland for 3.5c x150 sqmm PVC armoured
elec-4.3.8 cable
Crimping type copper lugs of 150 sqmm each
with nut/bolt/washer and crimping
elec-4.3.5 Crimping type copper lugs of 70sqmm each
with nut/bolt/washer and crimping (for
neutral lead)
Add contr profit @14% on material
Total for 150 sqmm cable termination
13
264.00
104.00
55.00
631.00
0.00
631.00
138.00
33.00
99.00
22.00
22.00
138.00
259.00
0.00
259.00
0.00
a)Material
elec-4.2.6 Heavy duty flange type brass cable each
gland for 3.5c x50 sqmm PVC armoured
cable
elec-4.3.4 Crimping
type copper lugs of 50 sqmm each
with nut/bolt/washer and crimping
elec-4.3.2 Crimping type copper lugs of 25sqmm each
with nut/bolt/washer and crimping (for
neutral lead)
Add contr profit @14% on material
Total for 50 sqmm cable termination
15
0.00
a)Material
elec-4.2.6 Heavy duty flange type brass cable each
gland for 3.5c x35 sqmm PVC armoured
elec-4.3.3 cable
Crimping type copper lugs of 35sqmm each
with nut/bolt/washer and crimping
14
3
1
264.00 1
0
312.00 2
0
0
55.00 6
138.00
138.00
40.00
120.00
30.00
30.00
288.00
0.00
288.00
0.00
a)Material
elec-4.2.5 Heavy duty flange type brass cable each
gland for 4cx16sqmm PVC armoured
cable
231 of 517
94.00
94.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-4.3.1 Crimping type copper lugs of 16 sqmm each
with nut/bolt/washer and crimping
22.00
104.00
104.00
0.00
104.00
2.5
295.00
737.50
Skilled Electrician
day
1
440.00
Helper
day
2
345.00
Man Mazdoor for concreting and embeddingday
of cable 2
way indicators
295.00
440.00
690.00
590.00
elec4.1.12
elec8.1.85
elec8.1.74
elec8.1.82
elec8.1.85
0.00
3
1
88.00 1
0
182.00 2
0.00 0
0
182.00 6
0%
0%
1720.00
0.00
0.00
5.00
2462.50
24.63
128.65
a)Material
elec-4.2.5 Heavy duty flange type brass cable each
gland for 4cx6sqmm PVC armoured cable
elec-4.3.1 Crimping type copper lugs of 6 sqmm each
with nut/bolt/washer and crimping
Add contr profit @14% on material
Total for 6 sqmm cable termination
232 of 517
0.00
94.00
94.00
22.00
88.00
182.00
0.00
182.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
18
Supply erection testing commisioning of
250 KVA 11kv/433 volts outdoor type
transformer with ONAN cooling and first
filled oil ,bushings on HT side and cable
box on LT side with bidirectional rollers,
silica gel breather,off load tap changer
with locking arrangement complete as
per IS-SPECIFICATIONS
MR
6.2.1
each
###
0.00
LS
6500.00
0.00
0.00
, Executive
Engineer
Supply
and Run of Deputy
1 of 6Executive
Sq.mm WPTC
,A.P.E.W.I.D.Corporation
, Engineer
cable along
with No.10 SWG
. N EAluminium
LLORE
A.P.E.W.I.D.Corpor
G.I bearer wire through ,PVC
ation cleats with
all accessories including
labour
South
Sub- charges
, Division
etc., complete.
.N E L L O R E
a) Material
elec-1.6.5 6 Sq.mm (7/18) wptc Aluminium cable
elec-8.1.41 No.10 G.I wire. Length 100 RM
elec-8.1.18 Insulation tapes
elec-8.1.85 Aluminium link clips
b) labour charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled
elec-8.1.82 Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.3
3
1
1
0
2
0
0
6
, Assistant Engineer
,A.P.E.W.I.D.Corporation
.NELLORE
100 M
kg
each
box
1
6.7
2
2
day
day
day
1
1
1
3017
68
17
55
440
345
345
3017
455.6
34
110
0
440
345
345
2
4748.6
47.49
2
6.7
1
elec-8.1.15
100
Nos
b) labour charges
elec-8.1.74 Skilled Electrician
day
233 of 517
1611
3222
68
455.6
330
330
440
440
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-8.1.75 Semi skilled
day
elec-8.1.82 Helper
day
Sundries such as insulation tapes and
rounding off
3
1
345 1
0
345 2
0
0
5137.6 6
345
345
51.38
28
Supply, Transportation and fixing of 4' 40 Watt Patty type flourescent single
Tube Light fitting with Energy saving
electronic ballast suitable for 40 Watt
tube on varnished teak wood round
blocks with flexible 3 core wire etc.,,
complete with all connections including
cost of 40W tube. The fitting shall be
under warranty for three years.
Makes:
Crompton/Bajaj/Surya/Havells HPL
a) Material
elec-3.6.8 4' x 40 watts box type flourscent light each
elec-3.7.7 fitting.
Lamp cost of 40W
each
elec-8.1.31 Tw Round blocks
each
Rate per each
Add contr profit @14% on material
0.00
Total for material
a) Labour charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi Skilled Electrician
Labour for 1 No
20
elec2.12.36
day
day
234 of 517
273.00
273.00
1
2
45.00
7.00
45.00
14.00
332.00
0.00
332.00
440
345
44.00
34.50
410.50
0.10
0.10
Nos
901.00
901.00
Nos
201.00
201.00
1102.00
0.00
1102.00
0.25
0.25
440.00
345.00
110.00
86.25
0.00
Nos
Nos
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-8.1.82 Helpers
Nos
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as Cement, Sand, T.W. LS
Plugs, Screws etc.,
0.25
345.00
282.50
3
1
86.25 1
0
0.00 0.00 2
0
130.00 0
6
1514.50
;lk;
each
each
235 of 517
1650.00
1650.00
1
12
571.20
121.00
571.20
1452.00
3673.20
0.00
3673.20
0.5
1
1
440.00
345.00
345.00
220.00
345.00
345.00
0.00
0.00
14.00
910.00
14.00
4597.20
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
21
Supply and fixing TPN Distribution board
with IP-43 protection (Metal Door)
suitable for 3 phase ELCB / RCCB / FP
Isolator as incomer and 10kA SP MCBs as
outing
going
including
internal
connection and labour charges for flush
mounting etc., complete.
Makes: Legrand /Schneider.
40A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.5 4way TPN, D.B with IP-43 Protection (MD) each
7
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
3
1
1
0
2
0
0
6
each
each
1650.00
1650.00
1
8
571.20
121.00
571.20
968.00
3189.20
0.00
3189.20
0.5
1
1
440.00
345.00
345.00
220.00
345.00
345.00
0.00
0.00
14.00
910.00
14.00
4113.20
each
each
0.00
236 of 517
day
day
day
2491.00
2491.00
1
8
890.00
201.00
890.00
1608.00
4989.00
0.00
4989.00
0.5
1
1
440.00
345.00
345.00
220.00
345.00
345.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
0%
0%
LS
910.00
14.00
3
1
0.00 1
0
0.00 14.00 2
0
0
5913.00 6
B -2
each
each
2491.00
2491.00
1
12
571.20
201.00
571.20
2412.00
5474.20
0.00
5474.20
0.5
1
1
440.00
345.00
345.00
220.00
345.00
345.00
0.00
0.00
14.00
910.00
14.00
6398.20
237 of 517
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-2.12.5 SPN 8 way D.B with IP-43 Protection (MD) each
suitable for single phase ECCB / RCCB/
DP Isolator.
elec-2.10.2 40A D.P.Isolator
elec-2.9.1 10 kA - 6-32A range SP MCBs
each
each
3
1
1245.00 1
0
2
367.00 0
0
1206.00 6
1245.00
1
6
367.00
201.00
2818.00
0.00
2818.00
0.5
0.5
1
440.00
345.00
345.00
737.50
5.00
220.00
172.50
345.00
0.00
0.00
5.00
3560.50
1245.00
1245.00
1
6
367.00
201.00
367.00
1206.00
2818.00
0.00
2818.00
0.5
0.5
1
440.00
345.00
345.00
220.00
172.50
345.00
0.00
0.00
each
each
238 of 517
737.50
Ele-Data
Index Specific
-code
ation
No.
23
Description
Unit
3
1
5.00 1
0
3560.50 2
0
0
6
5.00
Nos
9823.00
9823.00
Nos
Nos
Nos
1
8
0
8700.00
1477.00
201.00
8700.00
11816.00
0.00
30339.00
0.00
30339.00
1
1
1
440.00
345.00
345.00
239 of 517
1130.00
19.00
Say
440.00
345.00
345.00
0.00
0.00
19.00
31488.00
31488.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
a) Material
elec.2.12.3 8 Way TPN Vertical DB with IP -43 (Metal
7
door) protection suitable for 125A, 4
Pole, 25kA MCCB as incomer.
Nos
9823.00
Nos
Nos
Nos
1
24
7194.00
1477.00
201.00
1
1
1
440.00
345.00
345.00
1130.00
19.00
3
1
1
0
9823.00 2
0
0
0.00 6
Say
1477.00
4824.00
16124.00
0.00
16124.00
440.00
345.00
345.00
0.00
0.00
19.00
17273.00
17273.00
23
240 of 517
Nos
9823.00
9823.00
Nos
Nos
Nos
1
4
12
7194.00
1477.00
201.00
7194.00
5908.00
2412.00
25337.00
0.00
25337.00
day
day
day
1
1
1
440.00
345.00
345.00
440.00
345.00
345.00
0.00
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
3
1
0.00 1
0
19.00 26486.00 2
0
26486.00 0
6
LS
Say
elec-2.8.8
elec-6.3.3
elec-6.3.8
elec-6.3.1
241 of 517
each
26208.00
each
each
each
1
1
1
2500.00
175.00
2500.00
26208.00
2500.00
175.00
2500.00
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
elec-6.3.8 Voltmeter selector switch - 1 No.
each
elec-6.3.9 R, Y, B Indication lamps LED type, puse each
buttons.
elec-6.3.10 400 /5A C.T coils : 2 sets
elec-2.6.2 32A Bakelite fuse fittings - 3 Nos.
elec-2.5.1 2A HRC fuse link - 3 Nos:
elec-6.3.13 APFC relay 8 stage.
Outgoing :
ele -2.8.7 250 A MCCB 2Nos- L &T Make
elec-2.8.6 125A 25KA MCCB-02 NOS -L&T Make
MR
100A 25KA MCCB-02 NOS -L&T Make
elec-2.8.5 63A 25KA MCCB -04 NOS - L&T Make
each
each
each
1
3
175.00
135.00
6
3
3
1
450.00
123.00
50.00
13600.00
2
2
20818.00
8700.00
6350.00
6813.00
SWAGED POLES
2713 / 1980).
3
1
175.00 1
0
405.00 2
2700.00 0
0
369.00 6
150.00
13600.00
41636.00
17400.00
0.00
27252.00
0.00
135070.00
13507.00
60781.50
6753.50
216112.00
0.00
Overhe
ads
and
contra
ctors
profit
on
materi
als
216112.00
day
day
day
0%
0%
1
2
4
440.00
345.00
345.00
2930.00
440.00
690.00
1380.00
420.00
0.00
###
(Confirming to IS
242 of 517
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
13.1
Fabrication, supply and transportation of
swaged poles up to site confirming to IS
2713 / 1980 specifications. The pole
should be painted with primary coat of
red oxide and black bituminous paint and
Aluminuim paint up to ground level with
base plate, including cost of all materials
and transportation etc., complete. as per
specification 410 SP 27 of over length of
9.00 Mtrs in 3 sizes i.e. 5.00 Mtrs of
114.30 mm dai with 5.40 thick, 2.00 Mtrs
of 88.90 mm dai with 4.85 mm thick and
2.00 Mtrs of dai 76.10 mm with 3.25 mm
thick. the pole should be planted 1.50
Mtrs depth in the ground. The over all
wieght of the pole is 113 Kgs. as per
standard data 13.1.8 of Electrical SSR
2010-11
a) Material
Elec-6.1.1 Cost of swaged pole
13.2
13.2.1
113
Kg
24.8
71
8023
65
1612
65
2418
Elec-6.1.2 a) Material
6Mtrs 'B' Class M.S. pipe of 60.25mm
dia with base plate and suitable pole cap
13.3
Kg
3
1
1
0
2
0
0
6
Garden Posts
Fabrication and Supply of M.S. Poles for
garden posts with 'B' class 4mtrs long
60.25mm outer dia with base plate and
suitable pole cap including cost and
conveyance of all material including
fixing of luminaire and labour charges
etc., complete.
a) Material
Elec-6.1.2 4Mtrs 'B' Class M.S. pipe of 60.25mm dia
with base plate and suitable pole cap
13.2.2
Kg
37.2
243 of 517
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
13.3.1 Supply and fixing of 50mm dia 0.5 mtrs
single arm M.S. pipe bracket with sleeve
and fasteners with necessary angle
including painting etc., complete on
existing
pole
including
fixing
of
luminaire.
a) Material
Elec-6.1.3 0.5Mtr length 50mm 'B' class pipe.
Kg
45cm length , 10cm dia and cap.
Kg
Painting with red oxid and enamel paint.
job
b) Labour charges for fixing with
Spl. T & P
elec-8.1.74 Skilled Electrician
elec-8.1.80 Fitter
Rate per Each
Note : Labour is Considered for 5
jobs / day
13.3.2
2.55
5.4
1
65.00
65.00
80.00
440.00
385.00
3
1
1
0
2
0
0
6
165.75
351
80.00
88.00
77.00
761.75
day
day
0.2
0.2
Kg
Kg
job
5.1
5.4
1
65.00
65.00
160.00
331.5
351
160.00
day
day
0.33
0.33
440.00
385.00
145.20
127.05
Kg
Kg
job
7.65
5.4
1
65.00
65.00
240.00
497.25
351
240.00
day
day
0.5
0.5
440.00
385.00
220.00
192.50
244 of 517
Ele-Data
Index Specific
-code
ation
No.
13.3.4
Description
Unit
3
1
1500.75 1
0
2
0
0
6
Kg
Kg
job
5.1
5.4
1
61.00
61.00
160.00
311.1
329.4
160.00
day
day
0.2
0.2
440.00
385.00
88.00
77.00
965.5
220
4238.36
4884.46
80
60
158.40
3051.62
263.76
668.00
60.00
480.00
375.00
420.00
158.4
1001.25
138.6
245 of 517
0.72
0.72
0.054
8.35
1
0.33
2.67
0.33
519.30
6019.33
Ele-Data
Index Specific
Description
Unit
-code
ation
No.
5.1.2
Providing independent earthing for
Important equipment with 40mm dia 'B'
class 2.5m long G.I pipe and 19mm dia
'B' class G.I pipe of 0.3mtr. long
connected with reducer providing G.I
funnel
with
mesh
enclosed
in
C.C.Chamber of 400m x 400m x 400mm
with R.C.C. Slab cover duly providing
staggered holes filling with salt and
charcoal from the bottom of the pipe
giving earth connection from electrode
through G.I strip of 25 x 6mm x 200mm
length with all accessories and labour
charges
complete,
as
per
IS
specifications 732/1982 (Part II)
ELEC8.1.52
a) Material
Earth work excavation of hard gravel soil
with small boulders for trench 1st step of
size 1.5 x 0.9 x 0.9 m (5'x3'x3')
cum
1.27
1.87
279.40
0.00
55.00
55.00
0.9
4884.46
4396.01
0.23
4118.22
947.19
sqm
2.09
247.21
516.66
Mtr
2.5
381.00
952.50
Mtr
0.3
226.00
67.80
Each
Each
1
1
40.00
83.00
40.00
83.00
220.00
220.00
ELEC8.1.59
16
6.00
96.00
ELEC8.1.60
Set
11.00
44.00
ELEC8.1.13
Hard Coke.
kg
9.00
36.00
ELEC8.1.58
246 of 517
220.00
cum
3
1
1
0
2
0
0
6
Ele-Data
Index Specific
-code
ation
No.
ELEC- Salt.
8.1.14
DATA
Description
Unit
3
1
80.00 1
0
2
380.00
0
0.00 0
440.00 6
kg
20
4.00
L.S
380.00
Nos
1
1
440.00
15.50
15.5
8649.06
4961.3
4961.3
2
1
135
50
270
50
5281.3
0.05
0.05
0.05
297
284
260
14.85
14.2
13
8.1.77
8.1.86
8.1.84
42.05
5323.35
Asst. Exe.Engineer
APEWIDC, Kuppam
247 of 517
Ele-Data
Index Specific
-code
ation
No.
Description
Unit
Executive Engineer
APEWIDC, Chittoor
3
1
1
0
2
0
0
Engineer
6
Superintending
APEWIDC, Kadapa
248 of 517
Ele-Data
3 Remarks 3
1
1
1
1
7
0
0
2
2
0
0
0
0
6
6
249 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
The
R&B
Department
Proposed
Labour, for
both piping
&
wiring
considering
40% Labour,
for
Wire
draw.
Keeping
this,
the
labour
is
proposed for
wiring 100
RM.
Million /
RPG/
paragon
250 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
251 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
252 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
253 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
254 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
255 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
256 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
257 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
258 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
259 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
260 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
261 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
262 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
263 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
264 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
265 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
266 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
267 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
268 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
269 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
270 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
271 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
272 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
273 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
274 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
275 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
276 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
277 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
278 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
279 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
280 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
281 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
282 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
283 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
284 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
285 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
ctrification
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
286 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
287 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
288 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
289 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
290 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
291 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
292 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
293 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
294 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
295 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
296 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
L&T Hager
L&T Hager
L&T Hager
297 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
298 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
299 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
300 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
301 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
302 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
303 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
304 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
305 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
306 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
307 of 517
Ele-Data
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6
ecutive Engineer
DC, Madanapalli
308 of 517
Ele-Data
3 Remarks
1
1
0
2
0
0
Engineer
6
tending
WIDC, Kadapa
3
1
1
0
2
0
0
6
309 of 517
Ele-Data
Sl.
No.
1
AREA ALLOWENCE
ADD 14% OVERHEADS
0%
14%
DESCRIPTION
ITEM
CODE
COEFFIC
UNIT
IENT
RATE
PER
BMW-A.02
BMW-A.05
1.00
0%
Rmt
408.00
232.00
1.00
1.00
1.00
0%
Rmt
680.00
288.00
1.00
1.00
1.00
0%
Rmt
466.00
288.00
1.00
1.00
1.00
0%
Rmt
614.00
232.00
1.00
1.00
0.14
add overheads @
Total rate per 1 Rmt
BMW-A.03
BMW-A.06
0.14
add overheads @
Total rate per 1 Rmt
BMW-A.01
BMW-A.06
0.14
add overheads @
Total rate per 1 Rmt
BMW-A.04
BMW-A.05
0.14
310 of 517
WS-Data
Sl.
No.
2
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
BMW-B.03
1.00
0%
Nos 6237.00
0.00
1.00
1.00
0.14
311 of 517
WS-Data
Sl.
No.
3
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
BMW-B.04
1.00
0%
Nos 10181.00
0.00
1.00
1.00
0.14
312 of 517
WS-Data
Sl.
No.
ITEM
COEFFIC
UNIT
RATE
CODE IENT
BMW-B.02
1.00
Nos 10590.00
0.00
0%
DESCRIPTION
basic rate as per ssr item
Area allowence on labour charges
PER
1.00
1.00
0.14
add overheads @
Total rate per 1 Nos
5
BMW-B.01
1.00
0%
Nos 6730.00
0.00
1.00
1.00
1.00
0%
Nos
1.00
1.00
0.14
add overheads @
Total rate per 1 Nos
BMW-A.72
BMW-A.74
313 of 517
568.00
30.00
WS-Data
Sl.
No.
ITEM
COEFFIC
UNIT
CODE IENT
0.14
DESCRIPTION
add overheads @
RATE
PER
BMW-D24
BMW-D28
1.00
0%
Nos 1782.00
377.00
1.00
1.00
0.14
add overheads @
Total rate per 1 Nos
B Basic rate as per ssr item 12.7MM DIA PVC
conection with brass union nut CP coated
BMW-I48
BMW-I49
Area allowence on labour charges
1.00
0%
Nos
102.00
20.00
1.00
1.00
0.14
add overheads @
Total rate per 1 Nos
C Basic rate as per ssr item 12.7 MM ANGLE STOP
COCK first quality Indian make 400 gms Seiko
BMW-E 05
BMW-E 06
Area allowence on labour charges
1.00
0%
Nos
474.00
43.00
1.00
1.00
0.14
add overheads @
Total rate per 1 Nos
D Basic rate as per ssr item 38.1 MM CP WASTE
COUPLING half or full thread 1st quality indian make
paryware or equivalent
BMW-E31
BMW-E32
Area allowence on labour charges
1.00
0%
Nos
237.00
29.00
1.00
1.00
1.00
0%
Nos
26.00
0.00
1.00
1.00
0.14
add overheads @
Total rate per 1 Nos
E Basic rate as per ssr item 31.75 MM dia PVC fleible
waste pipe of 914.4 mm length of first quality
BMW-G05
Area allowence on labour charges
add overheads @
314 of 517
0.14
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
1.00
0%
Nos
243.00
12.00
1.00
1.00
1.00
0%
Nos
513.00
116.00
1.00
1.00
1.00
0%
Nos
164.00
44.00
1.00
1.00
1.00
0%
Nos
258.00
29.00
1.00
1.00
0.14
add overheads @
Total rate per 1 Nos
9
0.14
add overheads @
Total rate per 1 Nos
10
0.14
add overheads @
Total rate per 1 Nos
11
BMW-E 09
BMW-E 10
add overheads @
315 of 517
0.14
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
BMW-E 07
BMW-E 08
1.00
0%
Nos
407.00
29.00
1.00
1.00
1.00 RM
0%
405.00
0.00
3.00
1.00
1.00 RM
RM
0%
484.00
0.00
3.00
1.00
1.00 RM
RM
0%
1153.00
0.00
3.00
1.00
0.14
add overheads @
Total rate per 1 Nos
12
BMW-G12
BMW
0.14
add overheads @
Total rate per 1 RMT
(b) 110mm dia 3 Mts single socket
Basic rate as per ssr item
Area allowence on labour charges
BMW-G13
BMW
0.14
add overheads @
Total rate per 1 RMT
(b) 160mm dia 3 Mts single socket
Basic rate as per ssr item
Area allowence on labour charges
BMW-G 32
BMW
add overheads @
0.14
316 of 517
WS-Data
Sl.
No.
13
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
BMW-I 220
BMW-I 415
1.00 Rmt
Rmt
0%
141.00
31.00
1.00
1.00
1.00 Rmt
Rmt
0%
160.00
31.00
1.00
1.00
1.00 Rmt
Rmt
0%
212.00
31.00
1.00
1.00
1.00 Rmt
Rmt
0%
360.00
31.00
1.00
1.00
1.00 Rmt
Rmt
0%
525.00
31.00
1.00
1.00
0.14
add overheads @
Total rate per 1 RMT
b) 22.20 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges
BMW-I 221
BMW-I 415
0.14
add overheads @
Total rate per 1 RMT
c) 28.60 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges
BMW-I 222
BMW-I 415
0.14
add overheads @
Total rate per 1 RMT
BMW-I 224
BMW-I 415
0.14
add overheads @
Total rate per 1 RMT
E 54 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges
BMW-I 225
BMW-I 415
add overheads @
0.14
317 of 517
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
F 22.20 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges
BMW-I 227
BMW-I 415
COEFFIC
UNIT
IENT
1.00 Rmt
Rmt
0%
RATE
PER
189.00
31.00
1.00
1.00
0.14
add overheads @
Total rate per 1 RMT
14
BMW-F21
BMW-F22
1.00
0%
Nos
636.00
44.00
1.00
1.00
1.00
0%
Nos
186.00
44.00
1.00
1.00
1.00
0%
Nos
245.00
44.00
1.00
1.00
1.00
0%
Nos
526.00
67.00
1.00
1.00
0.14
add overheads @
Total rate per 1 No
15
BMW-I 403
BMW-F20
0.14
add overheads @
Total rate per 1 No
b) 25mm PPR Ball valve
Basic rate as per ssr item
Area allowence on labour charges
BMW-I 404
BMW-F18
0.14
add overheads @
Total rate per 1 No
BMW-I 406
BMW-F26
add overheads @
0.14
318 of 517
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
BMW-I 407
BMW-F28
COEFFIC
UNIT
IENT
RATE
PER
1.00
0%
Nos
613.00
90.00
1.00
1.00
1.00
0%
Nos
992.00
112.00
1.00
1.00
1.00
0%
Nos
930.00
150.00
1.00
1.00
1.00
0%
Nos
76.00
22.00
1.00
1.00
0.14
add overheads @
Total rate per 1 No
e 63 mm PPR Ball valve
Basic rate as per ssr item
Area allowence on labour charges
BMW-I 408
BMW-F30
0.14
add overheads @
Total rate per 1 No
15
BMW-D33
BMW-D36
0.14
add overheads @
Total rate per 1 No
16
0.14
319 of 517
WS-Data
Sl.
No.
17
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
1.00
0%
Nos
568.00
30.00
1.00
1.00
1.00
0%
Nos
112.00
59.00
1.00
1.00
1.00
0%
Nos
24.00
19.00
1.00
1.00
0.14
add overheads @
Total rate per 1 No
18
BMW-G
114
BMW-C42
0.14
add overheads @
Total rate per 1 No
Basic rate as per ssr item Nahany trap cover
BMW-G
121
BMW-I13
Area allowence on labour charges
add overheads @
0.14
320 of 517
WS-Data
Sl.
No.
19
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
0.14
add overheads @
BMW-d09
0.14
1.00
0%
Nos 1584.00
377.00
1.00
1.00
Nos
328.00
1.00
1.00
0%
Nos 1584.00
377.00
1.00
1.00
1.00
0%
Nos 1455.00
0.00
1.00
1.00
1.00
321 of 517
0.14
WS-Data
Sl.
No.
20
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
BMW-g01
BMW-g02
1.00
0%
Lit
6.00
1.00
1.00
1.00
1.00
0%
Nos
791.00
255.00
1.00
1.00
1.00
0%
Nos 7552.00
506.00
1.00
1.00
0.14
add overheads @
Total rate per 1 Ltr
21
BMW-D40
BMW-D41
0.14
add overheads @
Total rate per 1 No
22
0.14
322 of 517
WS-Data
Sl.
No.
ITEM
COEFFIC
UNIT
CODE IENT
BMW-I130
1.00
Nos
BMW-I120
0%
DESCRIPTION
Basic rate as per ssr item
Area allowence on labour charges
add overheads @
RATE
734.00
506.00
PER
1.00
1.00
0.14
41
Cost of Bricks
Deduct 15% for perforation
Ist class Brick layer
Man Mazdoor
Women Mazdoor
26
654 Nos.
5427.01
1000
98.10 Nos.
1.28 Each
0.64 Each
1.93 Each
5427.01
420.00
320.00
320.00
-1000
1
1
1
1.00
0%
Nos
484.00
227.00
1.00
1.00
0.14
323 of 517
WS-Data
Sl.
No.
27
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
1.00
0%
Nos
255.00
227.00
1.00
1.00
1.00
0%
Nos 3825.00
0.00
1.00
1.00
1.00
0%
Nos 2247.00
0.00
1.00
1.00
1.00
0%
Nos
1.00
1.00
0.14
add overheads @
Total rate per 1 No
28
Constructing 457.2mm x 457.2mm (1'-6" x 1'6") brick in CM (1:6) prop. Masonry inspection
chamber upto 914.4mm (3'-0") and fitted with
light weight 457.2mm x 457.2mm (1'-6" x 1"6") frame and cover of 20kg., including cost
and convenyance of all materials to site, all
labour charges, sales and otehr taxes on all
materials etc., complete for finished item of
BMW-B06
Basic rate as per ssr item
work
Area allowence on labour charges
0.14
add overheads @
Total rate per 1 No
24
0.14
324 of 517
17.00
14.00
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
add overheads @
COEFFIC
UNIT
IENT
RATE
PER
0.14
1.00
0%
Nos
9.00
11.00
1.00
1.00
1.00
0%
Nos
251.00
44.00
1.00
1.00
1.00
0%
1.00
0%
Nos 2247.00
0.00
Nos 71.00
14.00
1.00
1.00
1.00
1.00
0.14
0.14
0.14
325 of 517
WS-Data
Sl.
No.
33
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
1.00
0%
Nos 2020.00
140.00
1.00
1.00
1.00
0%
Nos
1.00
1.00
1.00
0%
Nos 1455.00
0.00
0.14
add overheads @
Total rate per 1 No
34
65.00
11.00
0.14
1.00
1.00
0.14
326 of 517
WS-Data
Sl.
No.
36
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
1.00
0%
Nos
107.00
72.00
1.00
1.00
1.00
0%
Nos
367.00
72.00
1.00
1.00
67.00
31.00
31.00
1.00
1
0.14
add overheads @
Total rate per 1 No
37
add overheads @
Total rate per 1 No
38
TABLE
16(1) page
52
12 (b) page 5
327 of 517
1.00
RMT
1 RMT
0%
WS-Data
Sl.
No.
ITEM
COEFFIC
UNIT
CODE IENT
0.14
DESCRIPTION
add overheads @
RATE
PER
Construction
of
60,000
liters
capacity
OHSR(VRCC) with 15.0 mts staging without
seismic analysis including fixtures OF rcc OR
ALLUMINIUM LADDER INSIDE 0.45 Mtrs wide,
MS ladder on the outside . Lighting including
condutor & earthing etc., RCC ventilators with
copper or stainless steel skyproof mesh,
Manhole frame and cover 0.75x0.75mts with
frame as per IS specifications (light duty - 2
Nos), Ralling with 32mm dia GI pipes (A class in
2 nos alround OHSR fixed in RCC (1:2:4) poles
of size 100x75x75mm with 1.50mts intervals
alround periphery on top of the OHSR for smaller
capacities,Water level indicator of good quality
with ebonite /copper float approved pattern - 1 no
Lt
30.26
1.00
30.26*(5760-6400)*0.00007 =
328 of 517
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
30.26*(32000-42000)*0.00002=
add overheads @
Total rate per 1 Lt
40 a) Supply and fixing of the following fixtures
1.00
Kg
1.00
Kg
1.00
Kg
73.7
1.00
73.70
1.00
73.70
1.00
1.00
nos 10500.00
1.00
73.70
1.00
Kg
1.00
table 31
add overheads @
0.14
1.00
kg
103.00
1.00
table 31
0.14
1.00
Kg
123.00
1.00
329 of 517
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
BMW-d14
1.00
Nos 1964.00
1.00
BMW-d 16
1.00
Nos
981.00
1.00
BMW-G08
1.00
Nos 1455.00
1.00
1.00
Nos
271.00
1.00
1.00
Nos
474.00
1.00
1.00
Nos
50.00
1.00
0.14
add overheads @
Total cost (A +B)
Supply and Fixing 12.7 mm dia NP push cock Ist
quality including cost and conveyance of all materials
to site, all labour charges, sales and other taxes on
all materials etc., complete for finished item of work
for all floors.
BMW-E 29
0.14
add overheads @
Total cost (A +B)
Supply and Fixing angle stop cock 12.7 mm dia first
quality Indian Make heavy duty Seiko/ Senior/ Nice or
equivalent including cost and conveyance of all
materials to site, labour charges etc., complete for
finished item of work. 178 - BMW E.05
BMW-E 01
0.14
add overheads @
Total cost (A +B)
Supply and FixingSupplying and fixing CP Jollys of
approved make with complete including cost and
conveyance of all materials, labour charges for fixing
etc., complete for finished item of work in all floors
663 - BMW I.69
BMW-I 69
add overheads @
330 of 517
0.14
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI fittings in ground or on wall including cost of te
reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refillin
masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveya
and labour charges complete for finished item of work.
a) 15mm Nominal bore
Basic rate as per ssr item
BMW-F79
BMW-F80
add overheads @
1.00 Rmt
204.00
1.00
Rmt
41.00
1.00
1.00 Rmt
227.00
1.00
Rmt
41.00
1.00
1.00 Rmt
297.00
1.00
Rmt
41.00
1.00
1.00 Rmt
466.00
1.00
Rmt
44.00
1.00
1.00 Rmt
466.00
1.00
Rmt
44.00
1.00
1.00 Rmt
503.00
1.00
Rmt
67.00
1.00
1.00 Rmt
892.00
1.00
Rmt
67.00
1.00
0%
14.00%
BMW-F81
BMW-F82
add overheads @
0%
14.00%
BMW-F83
BMW-F84
add overheads @
0%
14.00%
BMW-F87
BMW-F88
add overheads @
0%
14.00%
BMW-F87
BMW-F88
add overheads @
0%
14.00%
BMW-F89
BMW-F90
add overheads @
0%
14.00%
BMW-F91
BMW-F90
add overheads @
0%
14.00%
331 of 517
WS-Data
Sl.
No.
1
ITEM
CODE
DESCRIPTION
COEFFIC
UNIT
IENT
RATE
PER
BMW-F21
BMW-F22
1.00
Nos
0%
636.00
1.00
44.00
1.00
858.00
1.00
44.00
1.00
1233.00
1.00
44.00
1.00
2533.00
1.00
67.00
1.00
3711.00
1.00
90.00
1.00
0.14
add overheads @
Total rate per 1 No
15
BMW-F19
BMW-F20
1.00
Nos
0%
0.14
add overheads @
Total rate per 1 No
b) 25mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges
BMW-F17
BMW-F18
1.00
Nos
0%
0.14
add overheads @
Total rate per 1 No
BMW-F25
BMW-F26
1.00
Nos
0%
0.14
add overheads @
Total rate per 1 No
BMW-F27
BMW-F28
add overheads @
1.00
0%
Nos
0.14
332 of 517
WS-Data
Sl.
No.
ITEM
CODE
DESCRIPTION
e 65 mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges
COEFFIC
UNIT
IENT
BMW-F29
BMW-F30
1.00
RATE
Nos
0%
PER
5730.00
1.00
112.00
1.00
891.00
76.00
1.00
1.00
0.14
add overheads @
Total rate per 1 No
21
1.00
0%
Nos
0.14
Asst. Exe.Engineer
APEWIDC, Kuppam
Executive Engineer
APEWIDC, Chittoor
Superintending Engineer
APEWIDC, Kadapa
333 of 517
WS-Data
UNIT
Rmt
0.00
Rmt
0.00
Rmt
0.00
Rmt
0.00
Amount
(Rs.)
408.00
0.00
408.00
55.55
463.55
680.00
0.00
680.00
92.58
772.60
466.00
0.00
466.00
63.45
529.45
614.00
0.00
614.00
83.60
697.60
334 of 517
WS-Data
UNIT
Nos
Amount
(Rs.)
6237.00
0.00
0.00
6237.00
849.17
7086.20
335 of 517
WS-Data
UNIT
Nos
0.00
Amount
(Rs.)
10181.00
0.00
10181.00
1386.14
11567.15
336 of 517
WS-Data
UNIT
Nos
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
10590.00
0.00
10590.00
1441.83
12031.85
6730.00
0.00
6730.00
916.29
7646.30
568.00
0.00
568.00
337 of 517
WS-Data
UNIT
Nos
0.00
Nos
0.00
Nos
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
77.33
645.35
1782.00
0.00
1782.00
242.62
2024.65
102.00
0.00
102.00
13.89
115.90
474.00
0.00
474.00
64.54
538.55
237.00
0.00
237.00
32.27
269.30
26.00
0.00
26.00
3.54
338 of 517
WS-Data
UNIT
Rs
Nos
0.00
Nos
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
29.55
2977.95
243.00
0.00
243.00
33.08
276.10
513.00
0.00
513.00
69.84
582.85
164.00
0.00
164.00
22.33
186.35
258.00
0.00
258.00
35.13
339 of 517
WS-Data
UNIT
Nos
0.00
RMT
0.00
Amount
(Rs.)
293.15
407.00
0.00
407.00
55.41
462.45
135.00
0.00
135.00
18.38
153.40
RMT
RM
161.33
0.00
161.33
21.97
183.35
RMT
RM
384.33
0.00
384.33
52.33
436.70
340 of 517
WS-Data
UNIT
Amount
(Rs.)
Rmt
141.00
0.00
141.00
19.20
160.20
Rmt
Rmt
160.00
0.00
160.00
21.78
181.80
RMT
Rmt
212.00
0.00
212.00
28.86
240.90
RMT
Rmt
360.00
0.00
360.00
49.01
409.05
RMT
Rmt
525.00
0.00
525.00
71.48
596.50
341 of 517
WS-Data
UNIT
RMT
Rmt
Amount
(Rs.)
189.00
0.00
189.00
25.73
214.75
Nos
0.00
Nos
0.00
Nos
0.00
Nos
0.00
636.00
0.00
636.00
86.59
722.60
186.00
0.00
186.00
25.32
211.35
245.00
0.00
245.00
33.36
278.40
526.00
0.00
526.00
71.61
597.65
342 of 517
WS-Data
UNIT
Nos
0.00
Nos
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
613.00
0.00
613.00
83.46
696.50
992.00
0.00
992.00
135.06
1127.10
930.00
0.00
930.00
126.62
1056.65
76.00
0.00
76.00
10.35
86.35
343 of 517
WS-Data
UNIT
Nos
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
568.00
0.00
568.00
77.33
645.35
112.00
0.00
112.00
15.25
127.25
24.00
0.00
24.00
3.27
27.30
154.55
344 of 517
WS-Data
UNIT
Nos
0.00
Nos
Amount
(Rs.)
1584.00
0.00
1584.00
215.66
1799.70
328.00
44.66
2172.36
Nos
0.00
Nos
0.00
1584.00
0.00
1455.00
0.00
3039.00
413.76
3452.80
345 of 517
WS-Data
UNIT
Lit
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
6.00
0.00
6.00
0.82
6.85
791.00
0.00
791.00
107.69
898.70
7552.00
0.00
7552.00
1028.20
8580.20
346 of 517
WS-Data
UNIT
Nos
0.00
Amount
(Rs.)
734.00
0.00
734.00
99.93
833.95
Nos.
3549.26
Nos.
Each
Each
Each
-532.39
537.60
204.80
617.60
4376.87
Nos
0.00
484.00
0.00
484.00
65.90
549.90
347 of 517
WS-Data
UNIT
Nos
0.00
Nos
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
255.00
0.00
255.00
34.72
289.75
3825.00
0.00
3825.00
520.77
4345.80
2247.00
0.00
2247.00
305.93
2552.95
17.00
0.00
348 of 517
WS-Data
UNIT
Nos
0.00
Nos
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
17.00
2.31
19.35
9.00
0.00
9.00
1.23
10.25
251.00
0.00
251.00
34.17
285.20
2247.00
0.00
71.00
0.00
2318.00
315.60
2633.60
349 of 517
WS-Data
UNIT
Nos
0.00
Nos
0.00
Nos
0.00
Amount
(Rs.)
2020.00
0.00
2020.00
275.02
2295.05
65.00
0.00
65.00
8.85
73.85
1455.00
0.00
1455.00
198.10
1653.10
350 of 517
WS-Data
UNIT
Nos
0.00
Nos
0.00
RMT
RMT
Amount
(Rs.)
107.00
0.00
107.00
14.57
121.60
367.00
0.00
367.00
49.97
417.00
67.00
31.00
0.00
98.00
351 of 517
WS-Data
UNIT
Amount
(Rs.)
13.34
111.35
0.104
Lt
30.26
-1.36
352 of 517
WS-Data
UNIT
Amount
(Rs.)
-6.05
22.85
0.00
22.85
3.11
26.00
Kg
73.70
10.03
83.75
Kg
73.70
10.03
83.75
Kg
73.70
10.03
83.75
nos
10500.00
1429.58
11929.60
Kg
73.70
10.03
83.75
kg
103.00
14.02
117.05
Kg
123.00
16.75
139.75
353 of 517
WS-Data
UNIT
Amount
(Rs.)
Nos
1964.00
Nos
981.00
Nos
1455.00
4400.00
599.06
4999.06
Nos
271.00
36.90
307.90
Nos
474.00
64.54
538.54
Nos
50.00
6.81
354 of 517
WS-Data
UNIT
Amount
(Rs.)
56.81
Rmt
204.00
0.00
204.00
28.56
232.60
Rmt
Rmt
227.00
0.00
227.00
31.78
258.80
RMT
Rmt
297.00
0.00
297.00
41.58
338.60
RMT
Rmt
466.00
0.00
466.00
65.24
531.25
RMT
Rmt
466.00
0.00
466.00
65.24
531.25
RMT
Rmt
503.00
0.00
503.00
70.42
573.45
RMT
Rmt
892.00
0.00
892.00
124.88
1016.90
355 of 517
WS-Data
UNIT
Nos
Amount
(Rs.)
636.00
0.00
0.00
636.00
86.59
722.60
Nos
858.00
0.00
0.00
858.00
116.82
974.85
Nos
1233.00
0.00
0.00
1233.00
167.87
1400.90
Nos
2533.00
0.00
0.00
2533.00
344.87
2877.90
Nos
3711.00
0.00
0.00
3711.00
505.25
4216.25
356 of 517
WS-Data
UNIT
Nos
Amount
(Rs.)
5730.00
0.00
0.00
5730.00
780.14
6510.15
Nos
0.00
891.00
0.00
891.00
121.31
1012.35
utive Engineer
C, Madanapalli
nding Engineer
DC, Kadapa
357 of 517
WS-Data
Sl.No
###
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
0.00
10.92
23.65
34.57
45.49
56.41
67.33
78.25
89.17
100.09
111.01
121.93
132.85
143.77
154.69
165.61
176.53
187.45
198.37
209.29
220.21
231.13
242.05
252.97
263.89
274.81
285.73
296.65
307.57
318.49
327.59
336.69
345.79
354.89
363.99
373.09
382.19
391.29
400.39
409.49
418.59
427.69
436.79
445.89
454.99
464.09
473.19
482.29
491.39
500.49
509.59
0.00
10.92
23.65
34.57
45.49
56.41
67.33
78.25
89.17
100.09
111.01
121.93
132.85
143.77
154.69
165.61
176.53
187.45
198.37
209.29
220.21
231.13
242.05
252.97
263.89
274.81
285.73
296.65
307.57
318.49
327.59
336.69
345.79
354.89
363.99
373.09
382.19
391.29
400.39
409.49
418.59
427.69
436.79
445.89
454.99
464.09
473.19
482.29
491.39
500.49
509.59
0.00
6.82
14.78
21.60
28.43
35.25
42.07
48.89
55.71
62.53
69.35
76.17
82.99
89.81
96.63
103.45
110.27
117.09
123.91
130.73
137.55
144.37
151.19
158.01
164.83
171.65
178.47
185.29
192.11
198.93
204.62
210.31
216.00
221.69
227.38
233.07
238.76
244.45
250.14
255.83
261.52
267.21
272.90
278.59
284.28
289.97
295.66
301.35
307.04
312.73
318.42
0.00
16.05
34.78
50.83
66.88
82.93
98.98
115.03
131.08
147.13
163.18
179.23
195.28
211.33
227.38
243.43
259.48
275.53
291.58
307.63
323.68
339.73
355.78
371.83
387.88
403.93
419.98
436.03
452.08
468.13
481.51
494.89
508.27
521.65
535.03
548.41
561.79
575.17
588.55
601.93
615.31
628.69
642.07
655.45
668.83
682.21
695.59
708.97
722.35
735.73
749.11
0.00
6.49
14.06
20.55
27.05
33.54
40.03
46.52
53.01
59.50
65.99
72.48
78.97
85.46
91.95
98.44
104.93
111.42
117.91
124.40
130.89
137.38
143.87
150.36
156.85
163.34
169.83
176.32
182.81
189.30
194.71
200.12
205.53
210.94
216.35
221.76
227.17
232.58
237.99
243.40
248.81
254.22
259.63
265.04
270.45
275.86
281.27
286.68
292.09
297.50
302.91
Bricks
0.00
17.54
38.00
55.54
73.09
90.63
108.17
125.71
143.25
160.79
178.33
195.87
213.41
230.95
248.49
266.03
283.57
301.11
318.65
336.19
353.73
371.27
388.81
406.35
423.89
441.43
458.97
476.51
494.05
511.59
526.21
540.83
555.45
570.07
584.69
599.31
613.93
628.55
643.17
657.79
672.41
687.03
701.65
716.27
730.89
745.51
760.13
774.75
789.37
803.99
818.61
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
52.00
53.00
54.00
55.00
56.00
57.00
58.00
59.00
60.00
61.00
62.00
63.00
64.00
65.00
66.00
67.00
68.00
69.00
70.00
71.00
72.00
73.00
74.00
75.00
76.00
77.00
78.00
79.00
80.00
81.00
82.00
83.00
84.00
85.00
86.00
87.00
88.00
89.00
90.00
91.00
92.00
93.00
94.00
95.00
96.00
97.00
98.00
99.00
100.00
101.00
102.00
103.00
104.00
105.00
106.00
107.00
108.00
518.69
527.79
536.89
545.99
555.09
564.19
573.29
582.39
591.49
600.59
609.69
618.79
627.89
636.99
646.09
655.19
664.29
673.39
682.49
691.59
700.69
709.79
718.89
727.99
737.09
746.19
755.29
764.39
773.49
782.59
791.69
800.79
809.89
818.99
828.09
837.19
846.29
855.39
864.49
873.59
882.69
891.79
900.89
909.99
919.09
928.19
937.29
946.39
955.49
964.59
973.69
982.79
991.89
1000.99
1010.09
1019.19
1028.29
518.69
527.79
536.89
545.99
555.09
564.19
573.29
582.39
591.49
600.59
609.69
618.79
627.89
636.99
646.09
655.19
664.29
673.39
682.49
691.59
700.69
709.79
718.89
727.99
737.09
746.19
755.29
764.39
773.49
782.59
791.69
800.79
809.89
818.99
828.09
837.19
846.29
855.39
864.49
873.59
882.69
891.79
900.89
909.99
919.09
928.19
937.29
946.39
955.49
964.59
973.69
982.79
991.89
1000.99
1010.09
1019.19
1028.29
324.11
329.80
335.49
341.18
346.87
352.56
358.25
363.94
369.63
375.32
381.01
386.70
392.39
398.08
403.77
409.46
415.15
420.84
426.53
432.22
437.91
443.60
449.29
454.98
460.67
466.36
472.05
477.74
483.43
489.12
494.81
500.50
506.19
511.88
517.57
523.26
528.95
534.64
540.33
546.02
551.71
557.40
563.09
568.78
574.47
580.16
585.85
591.54
597.23
602.92
608.61
614.30
619.99
625.68
631.37
637.06
642.75
762.49
775.87
789.25
802.63
816.01
829.39
842.77
856.15
869.53
882.91
896.29
909.67
923.05
936.43
949.81
963.19
976.57
989.95
1003.33
1016.71
1030.09
1043.47
1056.85
1070.23
1083.61
1096.99
1110.37
1123.75
1137.13
1150.51
1163.89
1177.27
1190.65
1204.03
1217.41
1230.79
1244.17
1257.55
1270.93
1284.31
1297.69
1311.07
1324.45
1337.83
1351.21
1364.59
1377.97
1391.35
1404.73
1418.11
1431.49
1444.87
1458.25
1471.63
1485.01
1498.39
1511.77
308.32
313.73
319.14
324.55
329.96
335.37
340.78
346.19
351.60
357.01
362.42
367.83
373.24
378.65
384.06
389.47
394.88
400.29
405.70
411.11
416.52
421.93
427.34
432.75
438.16
443.57
448.98
454.39
459.80
465.21
470.62
476.03
481.44
486.85
492.26
497.67
503.08
508.49
513.90
519.31
524.72
530.13
535.54
540.95
546.36
551.77
557.18
562.59
568.00
573.41
578.82
584.23
589.64
595.05
600.46
605.87
611.28
833.23
847.85
862.47
877.09
891.71
906.33
920.95
935.57
950.19
964.81
979.43
994.05
1008.67
1023.29
1037.91
1052.53
1067.15
1081.77
1096.39
1111.01
1125.63
1140.25
1154.87
1169.49
1184.11
1198.73
1213.35
1227.97
1242.59
1257.21
1271.83
1286.45
1301.07
1315.69
1330.31
1344.93
1359.55
1374.17
1388.79
1403.41
1418.03
1432.65
1447.27
1461.89
1476.51
1491.13
1505.75
1520.37
1534.99
1549.61
1564.23
1578.85
1593.47
1608.09
1622.71
1637.33
1651.95
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
109.00
110.00
111.00
112.00
113.00
114.00
115.00
116.00
117.00
118.00
119.00
120.00
121.00
122.00
123.00
124.00
125.00
126.00
127.00
128.00
129.00
130.00
131.00
132.00
133.00
134.00
135.00
136.00
137.00
138.00
139.00
140.00
141.00
142.00
143.00
144.00
145.00
146.00
147.00
148.00
149.00
150.00
151.00
152.00
153.00
154.00
155.00
156.00
157.00
158.00
159.00
160.00
161.00
162.00
163.00
164.00
165.00
1037.39
1046.49
1055.59
1064.69
1073.79
1082.89
1091.99
1101.09
1110.19
1119.29
1128.39
1137.49
1146.59
1155.69
1164.79
1173.89
1182.99
1192.09
1201.19
1210.29
1219.39
1228.49
1237.59
1246.69
1255.79
1264.89
1273.99
1283.09
1292.19
1301.29
1310.39
1319.49
1328.59
1337.69
1346.79
1355.89
1364.99
1374.09
1383.19
1392.29
1401.39
1410.49
1419.59
1428.69
1437.79
1446.89
1455.99
1465.09
1474.19
1483.29
1492.39
1501.49
1510.59
1519.69
1528.79
1537.89
1546.99
1037.39
1046.49
1055.59
1064.69
1073.79
1082.89
1091.99
1101.09
1110.19
1119.29
1128.39
1137.49
1146.59
1155.69
1164.79
1173.89
1182.99
1192.09
1201.19
1210.29
1219.39
1228.49
1237.59
1246.69
1255.79
1264.89
1273.99
1283.09
1292.19
1301.29
1310.39
1319.49
1328.59
1337.69
1346.79
1355.89
1364.99
1374.09
1383.19
1392.29
1401.39
1410.49
1419.59
1428.69
1437.79
1446.89
1455.99
1465.09
1474.19
1483.29
1492.39
1501.49
1510.59
1519.69
1528.79
1537.89
1546.99
648.44
654.13
659.82
665.51
671.20
676.89
682.58
688.27
693.96
699.65
705.34
711.03
716.72
722.41
728.10
733.79
739.48
745.17
750.86
756.55
762.24
767.93
773.62
779.31
785.00
790.69
796.38
802.07
807.76
813.45
819.14
824.83
830.52
836.21
841.90
847.59
853.28
858.97
864.66
870.35
876.04
881.73
887.42
893.11
898.80
904.49
910.18
915.87
921.56
927.25
932.94
938.63
944.32
950.01
955.70
961.39
967.08
1525.15
1538.53
1551.91
1565.29
1578.67
1592.05
1605.43
1618.81
1632.19
1645.57
1658.95
1672.33
1685.71
1699.09
1712.47
1725.85
1739.23
1752.61
1765.99
1779.37
1792.75
1806.13
1819.51
1832.89
1846.27
1859.65
1873.03
1886.41
1899.79
1913.17
1926.55
1939.93
1953.31
1966.69
1980.07
1993.45
2006.83
2020.21
2033.59
2046.97
2060.35
2073.73
2087.11
2100.49
2113.87
2127.25
2140.63
2154.01
2167.39
2180.77
2194.15
2207.53
2220.91
2234.29
2247.67
2261.05
2274.43
616.69
622.10
627.51
632.92
638.33
643.74
649.15
654.56
659.97
665.38
670.79
676.20
681.61
687.02
692.43
697.84
703.25
708.66
714.07
719.48
724.89
730.30
735.71
741.12
746.53
751.94
757.35
762.76
768.17
773.58
778.99
784.40
789.81
795.22
800.63
806.04
811.45
816.86
822.27
827.68
833.09
838.50
843.91
849.32
854.73
860.14
865.55
870.96
876.37
881.78
887.19
892.60
898.01
903.42
908.83
914.24
919.65
1666.57
1681.19
1695.81
1710.43
1725.05
1739.67
1754.29
1768.91
1783.53
1798.15
1812.77
1827.39
1842.01
1856.63
1871.25
1885.87
1900.49
1915.11
1929.73
1944.35
1958.97
1973.59
1988.21
2002.83
2017.45
2032.07
2046.69
2061.31
2075.93
2090.55
2105.17
2119.79
2134.41
2149.03
2163.65
2178.27
2192.89
2207.51
2222.13
2236.75
2251.37
2265.99
2280.61
2295.23
2309.85
2324.47
2339.09
2353.71
2368.33
2382.95
2397.57
2412.19
2426.81
2441.43
2456.05
2470.67
2485.29
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
166.00
167.00
168.00
169.00
170.00
171.00
172.00
173.00
174.00
175.00
176.00
177.00
178.00
179.00
180.00
181.00
182.00
183.00
184.00
185.00
186.00
187.00
188.00
189.00
190.00
191.00
192.00
193.00
194.00
195.00
196.00
197.00
198.00
199.00
200.00
201.00
202.00
203.00
204.00
205.00
206.00
207.00
208.00
209.00
210.00
211.00
212.00
213.00
214.00
215.00
216.00
217.00
218.00
219.00
220.00
221.00
222.00
1556.09
1565.19
1574.29
1583.39
1592.49
1601.59
1610.69
1619.79
1628.89
1637.99
1647.09
1656.19
1665.29
1674.39
1683.49
1692.59
1701.69
1710.79
1719.89
1728.99
1738.09
1747.19
1756.29
1765.39
1774.49
1783.59
1792.69
1801.79
1810.89
1819.99
1829.09
1838.19
1847.29
1856.39
1865.49
1874.59
1883.69
1892.79
1901.89
1910.99
1920.09
1929.19
1938.29
1947.39
1956.49
1965.59
1974.69
1983.79
1992.89
2001.99
2011.09
2020.19
2029.29
2038.39
2047.49
2056.59
2065.69
1556.09
1565.19
1574.29
1583.39
1592.49
1601.59
1610.69
1619.79
1628.89
1637.99
1647.09
1656.19
1665.29
1674.39
1683.49
1692.59
1701.69
1710.79
1719.89
1728.99
1738.09
1747.19
1756.29
1765.39
1774.49
1783.59
1792.69
1801.79
1810.89
1819.99
1829.09
1838.19
1847.29
1856.39
1865.49
1874.59
1883.69
1892.79
1901.89
1910.99
1920.09
1929.19
1938.29
1947.39
1956.49
1965.59
1974.69
1983.79
1992.89
2001.99
2011.09
2020.19
2029.29
2038.39
2047.49
2056.59
2065.69
972.77
978.46
984.15
989.84
995.53
1001.22
1006.91
1012.60
1018.29
1023.98
1029.67
1035.36
1041.05
1046.74
1052.43
1058.12
1063.81
1069.50
1075.19
1080.88
1086.57
1092.26
1097.95
1103.64
1109.33
1115.02
1120.71
1126.40
1132.09
1137.78
1143.47
1149.16
1154.85
1160.54
1166.23
1171.92
1177.61
1183.30
1188.99
1194.68
1200.37
1206.06
1211.75
1217.44
1223.13
1228.82
1234.51
1240.20
1245.89
1251.58
1257.27
1262.96
1268.65
1274.34
1280.03
1285.72
1291.41
2287.81
2301.19
2314.57
2327.95
2341.33
2354.71
2368.09
2381.47
2394.85
2408.23
2421.61
2434.99
2448.37
2461.75
2475.13
2488.51
2501.89
2515.27
2528.65
2542.03
2555.41
2568.79
2582.17
2595.55
2608.93
2622.31
2635.69
2649.07
2662.45
2675.83
2689.21
2702.59
2715.97
2729.35
2742.73
2756.11
2769.49
2782.87
2796.25
2809.63
2823.01
2836.39
2849.77
2863.15
2876.53
2889.91
2903.29
2916.67
2930.05
2943.43
2956.81
2970.19
2983.57
2996.95
3010.33
3023.71
3037.09
925.06
930.47
935.88
941.29
946.70
952.11
957.52
962.93
968.34
973.75
979.16
984.57
989.98
995.39
1000.80
1006.21
1011.62
1017.03
1022.44
1027.85
1033.26
1038.67
1044.08
1049.49
1054.90
1060.31
1065.72
1071.13
1076.54
1081.95
1087.36
1092.77
1098.18
1103.59
1109.00
1114.41
1119.82
1125.23
1130.64
1136.05
1141.46
1146.87
1152.28
1157.69
1163.10
1168.51
1173.92
1179.33
1184.74
1190.15
1195.56
1200.97
1206.38
1211.79
1217.20
1222.61
1228.02
2499.91
2514.53
2529.15
2543.77
2558.39
2573.01
2587.63
2602.25
2616.87
2631.49
2646.11
2660.73
2675.35
2689.97
2704.59
2719.21
2733.83
2748.45
2763.07
2777.69
2792.31
2806.93
2821.55
2836.17
2850.79
2865.41
2880.03
2894.65
2909.27
2923.89
2938.51
2953.13
2967.75
2982.37
2996.99
3011.61
3026.23
3040.85
3055.47
3070.09
3084.71
3099.33
3113.95
3128.57
3143.19
3157.81
3172.43
3187.05
3201.67
3216.29
3230.91
3245.53
3260.15
3274.77
3289.39
3304.01
3318.63
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
223.00
224.00
225.00
226.00
227.00
228.00
229.00
230.00
231.00
232.00
233.00
234.00
235.00
236.00
237.00
238.00
239.00
240.00
241.00
242.00
243.00
244.00
245.00
246.00
247.00
248.00
249.00
250.00
251.00
252.00
253.00
254.00
255.00
256.00
257.00
258.00
259.00
260.00
261.00
262.00
263.00
264.00
265.00
266.00
267.00
268.00
269.00
270.00
271.00
272.00
273.00
274.00
275.00
276.00
277.00
278.00
279.00
2074.79
2083.89
2092.99
2102.09
2111.19
2120.29
2129.39
2138.49
2147.59
2156.69
2165.79
2174.89
2183.99
2193.09
2202.19
2211.29
2220.39
2229.49
2238.59
2247.69
2256.79
2265.89
2274.99
2284.09
2293.19
2302.29
2311.39
2320.49
2329.59
2338.69
2347.79
2356.89
2365.99
2375.09
2384.19
2393.29
2402.39
2411.49
2420.59
2429.69
2438.79
2447.89
2456.99
2466.09
2475.19
2484.29
2493.39
2502.49
2511.59
2520.69
2529.79
2538.89
2547.99
2557.09
2566.19
2575.29
2584.39
2074.79
2083.89
2092.99
2102.09
2111.19
2120.29
2129.39
2138.49
2147.59
2156.69
2165.79
2174.89
2183.99
2193.09
2202.19
2211.29
2220.39
2229.49
2238.59
2247.69
2256.79
2265.89
2274.99
2284.09
2293.19
2302.29
2311.39
2320.49
2329.59
2338.69
2347.79
2356.89
2365.99
2375.09
2384.19
2393.29
2402.39
2411.49
2420.59
2429.69
2438.79
2447.89
2456.99
2466.09
2475.19
2484.29
2493.39
2502.49
2511.59
2520.69
2529.79
2538.89
2547.99
2557.09
2566.19
2575.29
2584.39
1297.10
1302.79
1308.48
1314.17
1319.86
1325.55
1331.24
1336.93
1342.62
1348.31
1354.00
1359.69
1365.38
1371.07
1376.76
1382.45
1388.14
1393.83
1399.52
1405.21
1410.90
1416.59
1422.28
1427.97
1433.66
1439.35
1445.04
1450.73
1456.42
1462.11
1467.80
1473.49
1479.18
1484.87
1490.56
1496.25
1501.94
1507.63
1513.32
1519.01
1524.70
1530.39
1536.08
1541.77
1547.46
1553.15
1558.84
1564.53
1570.22
1575.91
1581.60
1587.29
1592.98
1598.67
1604.36
1610.05
1615.74
3050.47
3063.85
3077.23
3090.61
3103.99
3117.37
3130.75
3144.13
3157.51
3170.89
3184.27
3197.65
3211.03
3224.41
3237.79
3251.17
3264.55
3277.93
3291.31
3304.69
3318.07
3331.45
3344.83
3358.21
3371.59
3384.97
3398.35
3411.73
3425.11
3438.49
3451.87
3465.25
3478.63
3492.01
3505.39
3518.77
3532.15
3545.53
3558.91
3572.29
3585.67
3599.05
3612.43
3625.81
3639.19
3652.57
3665.95
3679.33
3692.71
3706.09
3719.47
3732.85
3746.23
3759.61
3772.99
3786.37
3799.75
1233.43
1238.84
1244.25
1249.66
1255.07
1260.48
1265.89
1271.30
1276.71
1282.12
1287.53
1292.94
1298.35
1303.76
1309.17
1314.58
1319.99
1325.40
1330.81
1336.22
1341.63
1347.04
1352.45
1357.86
1363.27
1368.68
1374.09
1379.50
1384.91
1390.32
1395.73
1401.14
1406.55
1411.96
1417.37
1422.78
1428.19
1433.60
1439.01
1444.42
1449.83
1455.24
1460.65
1466.06
1471.47
1476.88
1482.29
1487.70
1493.11
1498.52
1503.93
1509.34
1514.75
1520.16
1525.57
1530.98
1536.39
3333.25
3347.87
3362.49
3377.11
3391.73
3406.35
3420.97
3435.59
3450.21
3464.83
3479.45
3494.07
3508.69
3523.31
3537.93
3552.55
3567.17
3581.79
3596.41
3611.03
3625.65
3640.27
3654.89
3669.51
3684.13
3698.75
3713.37
3727.99
3742.61
3757.23
3771.85
3786.47
3801.09
3815.71
3830.33
3844.95
3859.57
3874.19
3888.81
3903.43
3918.05
3932.67
3947.29
3961.91
3976.53
3991.15
4005.77
4020.39
4035.01
4049.63
4064.25
4078.87
4093.49
4108.11
4122.73
4137.35
4151.97
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
280.00
281.00
282.00
283.00
284.00
285.00
286.00
287.00
288.00
289.00
290.00
291.00
292.00
293.00
294.00
295.00
296.00
297.00
298.00
299.00
300.00
301.00
302.00
303.00
304.00
305.00
306.00
307.00
308.00
309.00
310.00
311.00
312.00
313.00
314.00
315.00
316.00
317.00
318.00
319.00
320.00
321.00
322.00
323.00
324.00
325.00
326.00
327.00
328.00
329.00
330.00
331.00
332.00
333.00
334.00
335.00
336.00
2593.49
2602.59
2611.69
2620.79
2629.89
2638.99
2648.09
2657.19
2666.29
2675.39
2684.49
2693.59
2702.69
2711.79
2720.89
2729.99
2739.09
2748.19
2757.29
2766.39
2775.49
2784.59
2793.69
2802.79
2811.89
2820.99
2830.09
2839.19
2848.29
2857.39
2866.49
2875.59
2884.69
2893.79
2902.89
2911.99
2921.09
2930.19
2939.29
2948.39
2957.49
2966.59
2975.69
2984.79
2993.89
3002.99
3012.09
3021.19
3030.29
3039.39
3048.49
3057.59
3066.69
3075.79
3084.89
3093.99
3103.09
2593.49
2602.59
2611.69
2620.79
2629.89
2638.99
2648.09
2657.19
2666.29
2675.39
2684.49
2693.59
2702.69
2711.79
2720.89
2729.99
2739.09
2748.19
2757.29
2766.39
2775.49
2784.59
2793.69
2802.79
2811.89
2820.99
2830.09
2839.19
2848.29
2857.39
2866.49
2875.59
2884.69
2893.79
2902.89
2911.99
2921.09
2930.19
2939.29
2948.39
2957.49
2966.59
2975.69
2984.79
2993.89
3002.99
3012.09
3021.19
3030.29
3039.39
3048.49
3057.59
3066.69
3075.79
3084.89
3093.99
3103.09
1621.43
1627.12
1632.81
1638.50
1644.19
1649.88
1655.57
1661.26
1666.95
1672.64
1678.33
1684.02
1689.71
1695.40
1701.09
1706.78
1712.47
1718.16
1723.85
1729.54
1735.23
1740.92
1746.61
1752.30
1757.99
1763.68
1769.37
1775.06
1780.75
1786.44
1792.13
1797.82
1803.51
1809.20
1814.89
1820.58
1826.27
1831.96
1837.65
1843.34
1849.03
1854.72
1860.41
1866.10
1871.79
1877.48
1883.17
1888.86
1894.55
1900.24
1905.93
1911.62
1917.31
1923.00
1928.69
1934.38
1940.07
3813.13
3826.51
3839.89
3853.27
3866.65
3880.03
3893.41
3906.79
3920.17
3933.55
3946.93
3960.31
3973.69
3987.07
4000.45
4013.83
4027.21
4040.59
4053.97
4067.35
4080.73
4094.11
4107.49
4120.87
4134.25
4147.63
4161.01
4174.39
4187.77
4201.15
4214.53
4227.91
4241.29
4254.67
4268.05
4281.43
4294.81
4308.19
4321.57
4334.95
4348.33
4361.71
4375.09
4388.47
4401.85
4415.23
4428.61
4441.99
4455.37
4468.75
4482.13
4495.51
4508.89
4522.27
4535.65
4549.03
4562.41
1541.80
1547.21
1552.62
1558.03
1563.44
1568.85
1574.26
1579.67
1585.08
1590.49
1595.90
1601.31
1606.72
1612.13
1617.54
1622.95
1628.36
1633.77
1639.18
1644.59
1650.00
1655.41
1660.82
1666.23
1671.64
1677.05
1682.46
1687.87
1693.28
1698.69
1704.10
1709.51
1714.92
1720.33
1725.74
1731.15
1736.56
1741.97
1747.38
1752.79
1758.20
1763.61
1769.02
1774.43
1779.84
1785.25
1790.66
1796.07
1801.48
1806.89
1812.30
1817.71
1823.12
1828.53
1833.94
1839.35
1844.76
4166.59
4181.21
4195.83
4210.45
4225.07
4239.69
4254.31
4268.93
4283.55
4298.17
4312.79
4327.41
4342.03
4356.65
4371.27
4385.89
4400.51
4415.13
4429.75
4444.37
4458.99
4473.61
4488.23
4502.85
4517.47
4532.09
4546.71
4561.33
4575.95
4590.57
4605.19
4619.81
4634.43
4649.05
4663.67
4678.29
4692.91
4707.53
4722.15
4736.77
4751.39
4766.01
4780.63
4795.25
4809.87
4824.49
4839.11
4853.73
4868.35
4882.97
4897.59
4912.21
4926.83
4941.45
4956.07
4970.69
4985.31
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
337.00
338.00
339.00
340.00
341.00
342.00
343.00
344.00
345.00
346.00
347.00
348.00
349.00
350.00
351.00
352.00
353.00
354.00
355.00
356.00
357.00
358.00
359.00
360.00
361.00
362.00
363.00
364.00
365.00
366.00
367.00
368.00
369.00
370.00
371.00
372.00
373.00
374.00
375.00
376.00
377.00
378.00
379.00
380.00
381.00
382.00
383.00
384.00
385.00
386.00
387.00
388.00
389.00
390.00
391.00
392.00
393.00
3112.19
3121.29
3130.39
3139.49
3148.59
3157.69
3166.79
3175.89
3184.99
3194.09
3203.19
3212.29
3221.39
3230.49
3239.59
3248.69
3257.79
3266.89
3275.99
3285.09
3294.19
3303.29
3312.39
3321.49
3330.59
3339.69
3348.79
3357.89
3366.99
3376.09
3385.19
3394.29
3403.39
3412.49
3421.59
3430.69
3439.79
3448.89
3457.99
3467.09
3476.19
3485.29
3494.39
3503.49
3512.59
3521.69
3530.79
3539.89
3548.99
3558.09
3567.19
3576.29
3585.39
3594.49
3603.59
3612.69
3621.79
3112.19
3121.29
3130.39
3139.49
3148.59
3157.69
3166.79
3175.89
3184.99
3194.09
3203.19
3212.29
3221.39
3230.49
3239.59
3248.69
3257.79
3266.89
3275.99
3285.09
3294.19
3303.29
3312.39
3321.49
3330.59
3339.69
3348.79
3357.89
3366.99
3376.09
3385.19
3394.29
3403.39
3412.49
3421.59
3430.69
3439.79
3448.89
3457.99
3467.09
3476.19
3485.29
3494.39
3503.49
3512.59
3521.69
3530.79
3539.89
3548.99
3558.09
3567.19
3576.29
3585.39
3594.49
3603.59
3612.69
3621.79
1945.76
1951.45
1957.14
1962.83
1968.52
1974.21
1979.90
1985.59
1991.28
1996.97
2002.66
2008.35
2014.04
2019.73
2025.42
2031.11
2036.80
2042.49
2048.18
2053.87
2059.56
2065.25
2070.94
2076.63
2082.32
2088.01
2093.70
2099.39
2105.08
2110.77
2116.46
2122.15
2127.84
2133.53
2139.22
2144.91
2150.60
2156.29
2161.98
2167.67
2173.36
2179.05
2184.74
2190.43
2196.12
2201.81
2207.50
2213.19
2218.88
2224.57
2230.26
2235.95
2241.64
2247.33
2253.02
2258.71
2264.40
4575.79
4589.17
4602.55
4615.93
4629.31
4642.69
4656.07
4669.45
4682.83
4696.21
4709.59
4722.97
4736.35
4749.73
4763.11
4776.49
4789.87
4803.25
4816.63
4830.01
4843.39
4856.77
4870.15
4883.53
4896.91
4910.29
4923.67
4937.05
4950.43
4963.81
4977.19
4990.57
5003.95
5017.33
5030.71
5044.09
5057.47
5070.85
5084.23
5097.61
5110.99
5124.37
5137.75
5151.13
5164.51
5177.89
5191.27
5204.65
5218.03
5231.41
5244.79
5258.17
5271.55
5284.93
5298.31
5311.69
5325.07
1850.17
1855.58
1860.99
1866.40
1871.81
1877.22
1882.63
1888.04
1893.45
1898.86
1904.27
1909.68
1915.09
1920.50
1925.91
1931.32
1936.73
1942.14
1947.55
1952.96
1958.37
1963.78
1969.19
1974.60
1980.01
1985.42
1990.83
1996.24
2001.65
2007.06
2012.47
2017.88
2023.29
2028.70
2034.11
2039.52
2044.93
2050.34
2055.75
2061.16
2066.57
2071.98
2077.39
2082.80
2088.21
2093.62
2099.03
2104.44
2109.85
2115.26
2120.67
2126.08
2131.49
2136.90
2142.31
2147.72
2153.13
4999.93
5014.55
5029.17
5043.79
5058.41
5073.03
5087.65
5102.27
5116.89
5131.51
5146.13
5160.75
5175.37
5189.99
5204.61
5219.23
5233.85
5248.47
5263.09
5277.71
5292.33
5306.95
5321.57
5336.19
5350.81
5365.43
5380.05
5394.67
5409.29
5423.91
5438.53
5453.15
5467.77
5482.39
5497.01
5511.63
5526.25
5540.87
5555.49
5570.11
5584.73
5599.35
5613.97
5628.59
5643.21
5657.83
5672.45
5687.07
5701.69
5716.31
5730.93
5745.55
5760.17
5774.79
5789.41
5804.03
5818.65
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
394.00
395.00
396.00
397.00
398.00
399.00
400.00
401.00
402.00
403.00
404.00
405.00
406.00
407.00
408.00
409.00
410.00
411.00
412.00
413.00
414.00
415.00
416.00
417.00
418.00
419.00
420.00
421.00
422.00
423.00
424.00
425.00
426.00
427.00
428.00
429.00
430.00
431.00
432.00
433.00
434.00
435.00
436.00
437.00
438.00
439.00
440.00
441.00
442.00
443.00
444.00
445.00
446.00
447.00
448.00
449.00
450.00
3630.89
3639.99
3649.09
3658.19
3667.29
3676.39
3685.49
3694.59
3703.69
3712.79
3721.89
3730.99
3740.09
3749.19
3758.29
3767.39
3776.49
3785.59
3794.69
3803.79
3812.89
3821.99
3831.09
3840.19
3849.29
3858.39
3867.49
3876.59
3885.69
3894.79
3903.89
3912.99
3922.09
3931.19
3940.29
3949.39
3958.49
3967.59
3976.69
3985.79
3994.89
4003.99
4013.09
4022.19
4031.29
4040.39
4049.49
4058.59
4067.69
4076.79
4085.89
4094.99
4104.09
4113.19
4122.29
4131.39
4140.49
3630.89
3639.99
3649.09
3658.19
3667.29
3676.39
3685.49
3694.59
3703.69
3712.79
3721.89
3730.99
3740.09
3749.19
3758.29
3767.39
3776.49
3785.59
3794.69
3803.79
3812.89
3821.99
3831.09
3840.19
3849.29
3858.39
3867.49
3876.59
3885.69
3894.79
3903.89
3912.99
3922.09
3931.19
3940.29
3949.39
3958.49
3967.59
3976.69
3985.79
3994.89
4003.99
4013.09
4022.19
4031.29
4040.39
4049.49
4058.59
4067.69
4076.79
4085.89
4094.99
4104.09
4113.19
4122.29
4131.39
4140.49
2270.09
2275.78
2281.47
2287.16
2292.85
2298.54
2304.23
2309.92
2315.61
2321.30
2326.99
2332.68
2338.37
2344.06
2349.75
2355.44
2361.13
2366.82
2372.51
2378.20
2383.89
2389.58
2395.27
2400.96
2406.65
2412.34
2418.03
2423.72
2429.41
2435.10
2440.79
2446.48
2452.17
2457.86
2463.55
2469.24
2474.93
2480.62
2486.31
2492.00
2497.69
2503.38
2509.07
2514.76
2520.45
2526.14
2531.83
2537.52
2543.21
2548.90
2554.59
2560.28
2565.97
2571.66
2577.35
2583.04
2588.73
5338.45
5351.83
5365.21
5378.59
5391.97
5405.35
5418.73
5432.11
5445.49
5458.87
5472.25
5485.63
5499.01
5512.39
5525.77
5539.15
5552.53
5565.91
5579.29
5592.67
5606.05
5619.43
5632.81
5646.19
5659.57
5672.95
5686.33
5699.71
5713.09
5726.47
5739.85
5753.23
5766.61
5779.99
5793.37
5806.75
5820.13
5833.51
5846.89
5860.27
5873.65
5887.03
5900.41
5913.79
5927.17
5940.55
5953.93
5967.31
5980.69
5994.07
6007.45
6020.83
6034.21
6047.59
6060.97
6074.35
6087.73
2158.54
2163.95
2169.36
2174.77
2180.18
2185.59
2191.00
2196.41
2201.82
2207.23
2212.64
2218.05
2223.46
2228.87
2234.28
2239.69
2245.10
2250.51
2255.92
2261.33
2266.74
2272.15
2277.56
2282.97
2288.38
2293.79
2299.20
2304.61
2310.02
2315.43
2320.84
2326.25
2331.66
2337.07
2342.48
2347.89
2353.30
2358.71
2364.12
2369.53
2374.94
2380.35
2385.76
2391.17
2396.58
2401.99
2407.40
2412.81
2418.22
2423.63
2429.04
2434.45
2439.86
2445.27
2450.68
2456.09
2461.50
5833.27
5847.89
5862.51
5877.13
5891.75
5906.37
5920.99
5935.61
5950.23
5964.85
5979.47
5994.09
6008.71
6023.33
6037.95
6052.57
6067.19
6081.81
6096.43
6111.05
6125.67
6140.29
6154.91
6169.53
6184.15
6198.77
6213.39
6228.01
6242.63
6257.25
6271.87
6286.49
6301.11
6315.73
6330.35
6344.97
6359.59
6374.21
6388.83
6403.45
6418.07
6432.69
6447.31
6461.93
6476.55
6491.17
6505.79
6520.41
6535.03
6549.65
6564.27
6578.89
6593.51
6608.13
6622.75
6637.37
6651.99
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
451.00
452.00
453.00
454.00
455.00
456.00
457.00
458.00
459.00
460.00
461.00
462.00
463.00
464.00
465.00
466.00
467.00
468.00
469.00
470.00
471.00
472.00
473.00
474.00
475.00
476.00
477.00
478.00
479.00
480.00
481.00
482.00
483.00
484.00
485.00
486.00
487.00
488.00
489.00
490.00
491.00
492.00
493.00
494.00
495.00
496.00
497.00
498.00
499.00
500.00
501.00
502.00
503.00
504.00
505.00
506.00
507.00
4149.59
4158.69
4167.79
4176.89
4185.99
4195.09
4204.19
4213.29
4222.39
4231.49
4240.59
4249.69
4258.79
4267.89
4276.99
4286.09
4295.19
4304.29
4313.39
4322.49
4331.59
4340.69
4349.79
4358.89
4367.99
4377.09
4386.19
4395.29
4404.39
4413.49
4422.59
4431.69
4440.79
4449.89
4458.99
4468.09
4477.19
4486.29
4495.39
4504.49
4513.59
4522.69
4531.79
4540.89
4549.99
4559.09
4568.19
4577.29
4586.39
4595.49
4604.59
4613.69
4622.79
4631.89
4640.99
4650.09
4659.19
4149.59
4158.69
4167.79
4176.89
4185.99
4195.09
4204.19
4213.29
4222.39
4231.49
4240.59
4249.69
4258.79
4267.89
4276.99
4286.09
4295.19
4304.29
4313.39
4322.49
4331.59
4340.69
4349.79
4358.89
4367.99
4377.09
4386.19
4395.29
4404.39
4413.49
4422.59
4431.69
4440.79
4449.89
4458.99
4468.09
4477.19
4486.29
4495.39
4504.49
4513.59
4522.69
4531.79
4540.89
4549.99
4559.09
4568.19
4577.29
4586.39
4595.49
4604.59
4613.69
4622.79
4631.89
4640.99
4650.09
4659.19
2594.42
2600.11
2605.80
2611.49
2617.18
2622.87
2628.56
2634.25
2639.94
2645.63
2651.32
2657.01
2662.70
2668.39
2674.08
2679.77
2685.46
2691.15
2696.84
2702.53
2708.22
2713.91
2719.60
2725.29
2730.98
2736.67
2742.36
2748.05
2753.74
2759.43
2765.12
2770.81
2776.50
2782.19
2787.88
2793.57
2799.26
2804.95
2810.64
2816.33
2822.02
2827.71
2833.40
2839.09
2844.78
2850.47
2856.16
2861.85
2867.54
2873.23
2878.92
2884.61
2890.30
2895.99
2901.68
2907.37
2913.06
6101.11
6114.49
6127.87
6141.25
6154.63
6168.01
6181.39
6194.77
6208.15
6221.53
6234.91
6248.29
6261.67
6275.05
6288.43
6301.81
6315.19
6328.57
6341.95
6355.33
6368.71
6382.09
6395.47
6408.85
6422.23
6435.61
6448.99
6462.37
6475.75
6489.13
6502.51
6515.89
6529.27
6542.65
6556.03
6569.41
6582.79
6596.17
6609.55
6622.93
6636.31
6649.69
6663.07
6676.45
6689.83
6703.21
6716.59
6729.97
6743.35
6756.73
6770.11
6783.49
6796.87
6810.25
6823.63
6837.01
6850.39
2466.91
2472.32
2477.73
2483.14
2488.55
2493.96
2499.37
2504.78
2510.19
2515.60
2521.01
2526.42
2531.83
2537.24
2542.65
2548.06
2553.47
2558.88
2564.29
2569.70
2575.11
2580.52
2585.93
2591.34
2596.75
2602.16
2607.57
2612.98
2618.39
2623.80
2629.21
2634.62
2640.03
2645.44
2650.85
2656.26
2661.67
2667.08
2672.49
2677.90
2683.31
2688.72
2694.13
2699.54
2704.95
2710.36
2715.77
2721.18
2726.59
2732.00
2737.41
2742.82
2748.23
2753.64
2759.05
2764.46
2769.87
6666.61
6681.23
6695.85
6710.47
6725.09
6739.71
6754.33
6768.95
6783.57
6798.19
6812.81
6827.43
6842.05
6856.67
6871.29
6885.91
6900.53
6915.15
6929.77
6944.39
6959.01
6973.63
6988.25
7002.87
7017.49
7032.11
7046.73
7061.35
7075.97
7090.59
7105.21
7119.83
7134.45
7149.07
7163.69
7178.31
7192.93
7207.55
7222.17
7236.79
7251.41
7266.03
7280.65
7295.27
7309.89
7324.51
7339.13
7353.75
7368.37
7382.99
7397.61
7412.23
7426.85
7441.47
7456.09
7470.71
7485.33
508
509
510
511
512
513
514
515
508.00
509.00
510.00
511.00
512.00
513.00
514.00
515.00
4668.29
4677.39
4686.49
4695.59
4704.69
4713.79
4722.89
4731.99
4668.29
4677.39
4686.49
4695.59
4704.69
4713.79
4722.89
4731.99
2918.75
2924.44
2930.13
2935.82
2941.51
2947.20
2952.89
2958.58
6863.77
6877.15
6890.53
6903.91
6917.29
6930.67
6944.05
6957.43
2775.28
2780.69
2786.10
2791.51
2796.92
2802.33
2807.74
2813.15
7499.95
7514.57
7529.19
7543.81
7558.43
7573.05
7587.67
7602.29
Total
Per
446.70
296.30
166.70
909.70
Hour
414.10
296.30
166.70
877.10
Hour
402.50
296.30
166.70
865.50
Hour
414.10
296.30
166.70
877.10
Hour
414.10
296.30
166.70
877.10
Hour
1
2
3
4
5
A)
1
2 Lead up to 2 Km:
Out put
=
5.00 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
0.00%
0.00%
0.00%
0.00%
0.00%
Per
Hour
Hour
Hour
Rate
446.70
296.30
166.70
35.01
Per
Hour
Hour
Hour
38.21
Hour
1.00 Cum
3 Lead up to 3 Km:
Out put
=
5.00 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
Rate
446.70
296.30
Per
Hour
Hour
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
67.01
44.45
25.01
0.00
136.47
27.29
0.00
Rs.
27.29
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
93.81
62.22
35.01
0.00
191.04
38.21
0.00
Rs.
38.21
Rs.
Rs.
Amount
125.08
82.96
Hour
Rate
446.70
296.30
166.70
56.68
Per
Hour
Hour
Hour
61.86
Hour
Rate
446.70
296.30
166.70
66.68
Per
Hour
Hour
Hour
72.78
Hour
1.00 Cum
50.94
1.00 Cum
5 Lead up to 5 Km:
Out put
=
5.00 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
Hour
1.00 Cum
4 Lead up to 4 Km:
Out put
=
5.00 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
166.70
46.68
Rate
446.70
296.30
166.70
10.00
Per
Hour
Hour
Hour
10.92
Hour
1.00 Cum
Rate
446.70
296.30
166.70
8.34
Per
Hour
Hour
Hour
Rs.
Rs.
Rs.
Rs.
Rs.
46.68
0.00
254.72
50.94
0.00
Rs.
50.94
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
151.88
100.74
56.68
0.00
309.30
61.86
0.00
Rs.
61.86
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
178.68
118.52
66.68
0.00
363.88
72.78
0.00
Rs.
72.78
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
26.80
17.78
10.00
0.00
54.58
10.92
0.00
Rs.
10.92
Rs.
Rs.
Rs.
Rs.
Amount
22.34
14.82
8.34
0.00
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
9.10
1.00 Cum
Rs.
Rs.
Rs.
45.50
9.1
0.00
Rs.
9.10
Per
Hour
Hour
Hour
27.29
Rate
446.70
296.30
166.70
35.01
Per
Hour
Hour
Hour
38.21
Hour
1.00 Cum
3 Lead up to 3 Km:
Out put
=
5.00 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
Rate
446.70
296.30
166.70
25.01
Rate
446.70
296.30
166.70
46.68
Per
Hour
Hour
Hour
50.94
Hour
1.00 Cum
4 Lead up to 4 Km:
Out put
=
5.00 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate
446.70
296.30
166.70
56.68
Per
Hour
Hour
Hour
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
67.01
44.45
25.01
0.00
136.47
27.29
0.00
Rs.
27.29
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
93.81
62.22
35.01
0.00
191.04
38.21
0.00
Rs.
38.21
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
125.08
82.96
46.68
0.00
254.72
50.94
0.00
Rs.
50.94
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
151.88
100.74
56.68
0.00
309.30
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
Per
Hour
Hour
Hour
72.78
Hour
Rate
446.70
296.30
166.70
10.00
Per
Hour
Hour
Hour
10.92
Hour
1.00 Cum
Rate
446.70
296.30
166.70
66.68
1.00 Cum
Hour
1.00 Cum
5 Lead up to 5 Km:
Out put
=
5.00 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
61.86
Rate
446.70
296.30
166.70
8.34
Per
Hour
Hour
Hour
9.10
1.00 Cum
Rs.
Rs.
61.86
0.00
Rs.
61.86
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
178.68
118.52
66.68
0.00
363.88
72.78
0.00
Rs.
72.78
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
26.80
17.78
10.00
0.00
54.58
10.92
0.00
Rs.
10.92
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
22.34
14.82
8.34
0.00
45.50
9.1
0.00
Rs.
9.10
Rate
446.70
296.30
166.70
25.01
Per
Hour
Hour
Hour
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
67.01
44.45
25.01
0.00
136.47
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
2 Lead up to 2 Km:
Out put
=
8.00 MT
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
Per
Hour
Hour
Hour
23.88
Hour
Rate
446.70
296.30
166.70
46.68
Per
Hour
Hour
Hour
31.84
Hour
1.00 MT
4 Lead up to 4 Km:
Out put
=
8.00 MT
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
Rate
446.70
296.30
166.70
35.01
1.00 MT
3 Lead up to 3 Km:
Out put
=
8.00 MT
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
17.06
Rate
446.70
296.30
166.70
56.68
Per
Hour
Hour
Hour
38.66
Hour
1.00 MT
5 Lead up to 5 Km:
Out put
=
8.00 MT
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
Rate
446.70
296.30
166.70
66.68
Per
Hour
Hour
Hour
Rs.
Rs.
17.06
0.00
Rs.
17.06
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
93.81
62.22
35.01
0.00
191.04
23.88
0.00
Rs.
23.88
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
125.08
82.96
46.68
0.00
254.72
31.84
0.00
Rs.
31.84
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
151.88
100.74
56.68
0.00
309.30
38.66
0.00
Rs.
38.66
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
178.68
118.52
66.68
0.00
363.88
45.49
Rate
446.70
296.30
166.70
10.00
Per
Hour
Hour
Hour
6.82
Hour
1.00 MT
Hour
1.00 MT
45.49
Rate
446.70
296.30
166.70
8.34
Per
Hour
Hour
Hour
5.69
1.00 MT
Rs.
0.00
Rs.
45.49
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
26.80
17.78
10.00
0.00
54.58
6.82
0.00
Rs.
6.82
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
22.34
14.82
8.34
0.00
45.50
5.69
0.00
Rs.
5.69
Rate
446.70
296.30
166.70
25.01
Per
Hour
Hour
Hour
40.14
Rate
446.70
296.30
166.70
35.01
Per
Hour
Hour
Hour
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
67.01
44.45
25.01
0.00
136.47
40.14
0.00
Rs.
40.14
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
93.81
62.22
35.01
0.00
191.04
56.19
Per
Hour
Hour
Hour
74.92
Hour
Rate
446.70
296.30
166.70
56.68
Per
Hour
Hour
Hour
90.97
Hour
1.00 Cum
5 Lead up to 5 Km:
Out put
=
3.40 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
Rate
446.70
296.30
166.70
46.68
1.00 Cum
4 Lead up to 4 Km:
Out put
=
3.40 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
Hour
1.00 Cum
3 Lead up to 3 Km:
Out put
=
3.40 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
56.19
Rate
446.70
296.30
166.70
66.68
Per
Hour
Hour
Hour
107.02
Hour
1.00 Cum
Rate
446.70
296.30
166.70
10.00
Per
Hour
Hour
Hour
Rs.
0.00
Rs.
56.19
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
125.08
82.96
46.68
0.00
254.72
74.92
0.00
Rs.
74.92
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
151.88
100.74
56.68
0.00
309.30
90.97
0.00
Rs.
90.97
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
178.68
118.52
66.68
0.00
363.88
107.02
0.00
Rs.
107.02
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
26.80
17.78
10.00
0.00
54.58
16.05
16.05
Hour
1.00 Cum
Rate
446.70
296.30
166.70
8.34
Per
Hour
Hour
Hour
13.38
1.00 Cum
Rs.
0.00
Rs.
16.05
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Amount
22.34
14.82
8.34
0.00
45.50
13.38
0.00
Rs.
13.38
Rate
402.50
Per
Hour
Rs.
Amount
60.38
296.30
Hour
Rs.
44.45
166.70
Hour
Rs.
25.01
25.01
Rs.
Rs.
Rs.
Rs.
0.00
129.84
16.23
0.00
Rs.
16.23
2 Lead up to 2 Km:
Out put
=
8000 Ltrs
0.21 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
16.23
Rate
402.50
Per
Hour
Rs.
Amount
84.53
296.30
Hour
Rs.
62.22
166.70
Hour
Rs.
35.01
35.01
Rs.
Rs.
Rs.
Rs.
0.00
181.76
22.72
0.00
Rs.
22.72
3 Lead up to 3 Km:
Out put
=
8000 Ltrs
22.72
Rate
Per
Amount
402.50
Hour
Rs.
112.70
296.30
Hour
Rs.
82.96
166.70
Hour
Rs.
46.68
46.68
Rs.
Rs.
Rs.
Rs.
0.00
242.34
30.29
0.00
Rs.
30.29
4 Lead up to 4 Km:
Out put
=
8000 Ltrs
0.34 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
30.29
Rate
402.50
Per
Hour
Rs.
Amount
136.85
296.30
Hour
Rs.
100.74
166.70
Hour
Rs.
56.68
56.68
Rs.
Rs.
Rs.
Rs.
0.00
294.27
36.78
0.00
Rs.
36.78
5 Lead up to 5 Km:
Out put
=
8000 Ltrs
0.40 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
36.78
Rate
402.50
Per
Hour
Rs.
Amount
161.00
296.30
Hour
Rs.
118.52
166.70
Hour
Rs.
66.68
66.68
Rs.
Rs.
Rs.
Rs.
0.00
346.20
43.28
0.00
Rs.
43.28
43.28
Rate
402.50
Per
Hour
Rs.
Amount
24.15
296.30
Hour
Rs.
17.78
166.70
10.00
Hour
6.49
Rs.
10.00
Rs.
Rs.
Rs.
Rs.
0.00
51.93
6.49
0.00
Rs.
6.49
Rate
402.50
Per
Hour
Rs.
Amount
20.13
296.30
Hour
Rs.
14.82
166.70
Hour
Rs.
8.34
8.34
Rs.
Rs.
Rs.
Rs.
0.00
43.29
5.41
0.00
Rs.
5.41
5.41
Rate
414.10
Per
Hour
Rs.
Amount
62.12
296.30
Hour
Rs.
44.45
166.70
Hour
Rs.
25.01
25.01
Rs.
Rs.
Rs.
Rs.
0.00
131.58
43.86
0.00
Rs.
43.86
2 Lead up to 2 Km:
Out put
=
3000 Nos
0.21 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
43.86
Rate
414.10
Per
Hour
Rs.
Amount
86.96
296.30
Hour
Rs.
62.22
166.70
Hour
Rs.
35.01
35.01
Rs.
0.00
Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos
Rs.
Rs.
Rs.
184.19
61.40
0.00
61.40
Rs.
61.40
3 Lead up to 3 Km:
Out put
=
3000 Nos
0.28 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
Rate
414.10
Per
Hour
Rs.
Amount
115.95
296.30
Hour
Rs.
82.96
166.70
Hour
Rs.
46.68
46.68
Rs.
Rs.
Rs.
Rs.
0.00
245.59
81.86
0.00
Rs.
81.86
4 Lead up to 4 Km:
Out put
=
3000 Nos
0.34 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
81.86
Rate
414.10
Per
Hour
Rs.
Amount
140.79
296.30
Hour
Rs.
100.74
166.70
Hour
Rs.
56.68
56.68
Rs.
Rs.
Rs.
Rs.
0.00
298.21
99.40
0.00
Rs.
99.40
5 Lead up to 5 Km:
Out put
=
3000 Nos
0.40 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
99.40
Rate
414.10
Per
Hour
Rs.
Amount
165.64
296.30
Hour
Rs.
118.52
166.70
Hour
Rs.
66.68
66.68
Rs.
Rs.
Rs.
Rs.
0.00
350.84
116.95
0.00
116.95
1000 Nos
Rs.
116.95
Rate
414.10
Per
Hour
Rs.
Amount
24.85
296.30
Hour
Rs.
17.78
166.70
Hour
Rs.
10.00
10.00
Rs.
Rs.
Rs.
Rs.
0.00
52.63
17.54
0.00
Rs.
17.54
17.54
Rate
414.10
Per
Hour
Rs.
Amount
20.71
296.30
Hour
Rs.
14.82
166.70
Hour
Rs.
8.34
8.34
Rs.
Rs.
Rs.
Rs.
0.00
43.87
14.62
0.00
Rs.
14.62
14.62
LOADING & UNLOADING CHARGES BY MANUAL MEANS (EXCLUDING IDLE HIRE CHARGES
OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Labour:
0.01 day Head mazdoor
375.00
0.25 day Mazdoor
320.00
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
83.75
15.23
Per
day
day
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
3.75
80.00
83.75
0.00
83.75
83.75
15.23
0.00
Rs.
15.23
Rate
Per
375.00
320.00
day
day
41.88
7.61
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
1.88
40.00
41.88
0.00
41.88
41.88
7.61
0.00
Rs.
7.61
B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for masonry work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Labour:
0.02 day Head mazdoor
0.50 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
(ii) Unloading charges:
Out put
=
5.50 Cum
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
C) For Cement (per Tonne):
(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor
Rate
Per
375.00
320.00
day
day
167.50
30.45
Rate
Per
375.00
320.00
day
day
83.75
15.23
Rate
Per
375.00
320.00
day
day
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
7.50
160.00
167.50
0.00
167.50
167.50
30.45
0.00
Rs.
30.45
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
3.75
80.00
83.75
0.00
83.75
83.75
15.23
0.00
Rs.
15.23
Amount
Rs.
Rs.
22.50
480.00
502.50
50.25
Rate
Per
375.00
320.00
day
day
502.50
50.25
Rate
Per
375.00
320.00
day
day
602.25
60.23
Rate
Per
375.00
320.00
day
day
602.25
60.23
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
502.50
0.00
502.50
502.50
50.25
0.00
Rs.
50.25
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
22.50
480.00
502.50
0.00
502.50
502.50
50.25
0.00
Rs.
50.25
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
26.25
576.00
602.25
0.00
602.25
602.25
60.23
0.00
Rs.
60.23
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
26.25
576.00
602.25
0.00
602.25
602.25
60.23
0.00
1.00 MT
Rs.
Rate
Per
375.00
320.00
day
day
83.75
41.88
Rate
Per
375.00
320.00
day
day
83.75
41.88
60.23
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
3.75
80.00
83.75
0.00
83.75
83.75
41.88
0.00
Rs.
41.88
Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
3.75
80.00
83.75
0.00
83.75
83.75
41.88
0.00
Rs.
41.88
LOADING & UNLOADING CHARGES BY MANUAL MEANS (INCLUDING IDLE HIRE CHARGES
OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Labour:
0.01 day Head mazdoor
375.00
0.25 day Mazdoor
320.00
Per
Amount
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
3.75
80.00
83.75
0.00
83.75
414.10
Hour
Rs.
207.05
296.30
Hour
Rs.
148.15
166.70
Hour
Rs.
83.35
83.75
83.35
94.96
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
438.55
522.30
522.30
94.96
0.00
Rs.
94.96
Rate
Per
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
1.88
40.00
41.88
0.00
41.88
414.10
Hour
Rs.
68.74
296.30
Hour
Rs.
49.19
166.70
Hour
Rs.
27.67
27.67
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
145.60
187.48
187.48
34.09
0.00
Rs.
34.09
41.88
34.09
Amount
B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for machinery work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Labour:
0.02 day Head mazdoor
0.50 day Mazdoor
Rate
Per
Amount
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
7.50
160.00
167.50
0.00
167.50
167.50
414.10
Hour
Rs.
207.05
296.30
Hour
Rs.
148.15
166.70
83.35
Hour
110.19
Rs.
83.35
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
438.55
606.05
606.05
110.19
0.00
Rs.
110.19
Rate
Per
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
3.75
80.00
83.75
0.00
83.75
414.10
Hour
Rs.
103.53
296.30
Hour
Rs.
74.08
166.70
Hour
Rs.
41.68
41.68
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
219.29
303.04
303.04
55.1
0.00
Rs.
55.10
83.75
55.10
Amount
Rate
Per
Amount
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
22.50
480.00
502.50
0.00
502.50
502.50
414.10
Hour
Rs.
414.10
296.30
Hour
Rs.
296.30
166.70
166.70
Hour
137.96
Rs.
166.70
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
877.10
1379.60
1379.60
137.96
0.00
Rs.
137.96
Rate
Per
Amount
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
26.25
576.00
602.25
0.00
602.25
602.25
414.10
Hour
Rs.
414.10
296.30
Hour
Rs.
296.30
166.70
Hour
Rs.
166.70
166.70
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
877.10
1479.35
1479.35
147.94
0.00
Rs.
147.94
147.94
Rate
Per
Amount
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
26.25
576.00
602.25
0.00
602.25
602.25
414.10
Hour
Rs.
414.10
296.30
Hour
Rs.
296.30
166.70
166.70
Hour
147.94
Rs.
166.70
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
877.10
1479.35
1479.35
147.94
0.00
Rs.
147.94
Rate
Per
Amount
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
26.25
576.00
602.25
0.00
602.25
602.25
414.10
Hour
Rs.
414.10
296.30
Hour
Rs.
296.30
166.70
Hour
Rs.
166.70
166.70
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
877.10
1479.35
1479.35
147.94
0.00
Rs.
147.94
147.94
Rate
Per
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
3.75
80.00
83.75
0.00
83.75
414.10
Hour
Rs.
136.65
296.30
Hour
Rs.
97.78
83.75
Amount
166.70
55.01
Hour
186.60
Rs.
55.01
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
289.44
373.19
373.19
186.60
0.00
Rs.
186.60
Rate
Per
Amount
375.00
320.00
day
day
Rs.
Rs.
Rs.
Rs.
Rs.
22.50
480.00
502.50
0.00
502.50
502.50
414.10
Hour
Rs.
414.10
296.30
Hour
Rs.
296.30
166.70
Hour
Rs.
166.70
166.70
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
877.10
1379.60
1379.60
689.8
0.00
Rs.
689.80
689.80
Per
Amount
Hour
Rs.
45.55
296.30
Hour
Rs.
32.59
166.70
Hour
Rs.
18.34
414.10
Hour
Rs.
24.85
296.30
Hour
Rs.
17.78
166.70
Hour
Rs.
10.00
28.34
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
149.11
149.11
27.11
0.00
Rs.
27.11
27.11
Rate
Per
414.10
Hour
Rs.
33.13
296.30
Hour
Rs.
23.70
166.70
Hour
Rs.
13.34
13.34
Rs.
Rs.
Rs.
Rs.
Rs.
0.00
70.17
70.17
12.76
0.00
Rs.
12.76
12.76
Amount
B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for machinery work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Machinery:
0.17 Hrs. hire charges of Tipper 10 Tonnes
capacity @ Rs.
Rate
Per
Amount
414.10
Hour
Rs.
70.40
296.30
Hour
Rs.
50.37
166.70
Hour
Rs.
28.34
414.10
Hour
Rs.
49.69
296.30
Hour
Rs.
35.56
166.70
Hour
Rs.
20.00
48.34
Rs.
Rs.
Rs.
0.00
254.36
254.36
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
46.25
Rs.
Rs.
46.25
0.00
Rs.
46.25
315806963.xlsx
E- DATA
Standard Data - Electrical Items SSR 09-10
3
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOOR District
1
Area allowence
20%
1
Overheads and contractors profit on materials
0%
0
Overheads and contractors profit on labour
0%
2
Specification No.
Description
Unit
Quantity Rate Rs. Amount Rs. 0 Remarks
0
1
2
3
4
5
66
7
1
Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI
MARK) concealed in Roof Slabs with all required
accessories including masonary work and labour charges
etc., complete. Make : Sudhakar/Maru plast/Avon plast
100 M
2500.00
2500.00
ele-1.2.39
Each
12
20.00
240.00
elec-1.2.44
Each
12
4.50
54.00
0.00
2794.00
0.00
2794.00
b) Labour charges :
Skilled Electrician
day
224.00
448.00
day
206.00
412.00
Helpers
day
206.00
412.00
20%
0%
254.40
1526.40
0.00
4320.40
43.25
Note : 1. If 25mm dia PVC / MS pipes are used for light / fan point,
add the cost of sheet metal / well seasoned wooden board / box.
Supply and Fixing of 25mm dia 1.5mm thick P.V.C. pipe (ISI
MARK) concealed in wall with all required accessories
including masonary work for light, fan and separate plug
point with well seasoned TW box including all labour
charges etc., complete.
Make : Sudhakar/Maru
plast/Avon plast
Taking Output = 100 M
a) Material
elec-1.2.3
100 M
1950.00
elec-8.1.10
U' Links
elec-1.4.12
ele-1.2.39
elec-1.2.44
100 Nos
40.00
80.00
Each
40.00
80.00
Each
12
20.00
240.00
Each
12
4.50
54.00
kg
50
5.81
290.50
Cement
1950.00
2694.50
Add contr profit @14% on material
0.00
0.00
2694.50
b) Labour charges :
Skilled Electrician
day
224.00
448.00
day
206.00
412.00
Helpers
day
206.00
412.00
day
224.00
448.00
20%
Page 1 of 517
344.00
315806963.xlsx
Specification No.
Description
Unit
Quantity
0%
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
2064.00
0.00
47.60
The
R&B
Department
Proposed
Labour, for both
piping & wiring
considering
40% Labour, for
Wire
draw.
Keeping
this,
the labour is
proposed
for
wiring 100 RM.
Million / RPG/
paragon
a) Material
elec-1.5.1
100 M
893.00
893.00
elec-1.7.1
each
17.50
105.00
elec-1.7.15
each
19.00
114.00
elec-1.4.19
no
40.00
40.00
1152.00
0.00
0.00
1152.00
b) Labour charges :
Skilled Electrician
day
0.6
224.00
134.40
day
1.2
206.00
247.20
Helpers
day
0.6
206.00
123.60
20%
0%
101.04
606.24
0.00
1657.20
276.20
4758.50
E- DATA
Remarks
Page 2 of 517
1.50
276.20
414.30
315806963.xlsx
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
elec-1.5.3
2.00
2130.00
4260.00
elec-1.5.1
1.00
893.00
893.00
5153.00
0.00
0.00
5153.00
Labour Charges
Skilled Electrician (0.67 + 0.34)
day
1.01
224.00
226.24
day
206.00
618.00
day
1.01
206.00
208.06
20%
0%
210.46
1262.76
0.00
6415.76
64.20
elec-1.5.4
2.00
3100.00
6200.00
elec-1.5.3
1.00
2130.00
2130.00
8330.00
0.00
0.00
8330.00
Labour Charges
day
1.34
224.00
300.16
day
206.00
824.00
day
1.34
206.00
276.04
20%
0%
280.04
1680.24
10010.24
0.00
100.15
elec-1.5.5
2.00
4715.00
elec-1.5.3
1.00
2130.00
9430.00
2130.00
11560.00
0.00
0.00
11560.00
Labour Charges
Skilled Electrician (1.0 + 0.34)
day
1.34
224.00
300.16
day
206.00
824.00
day
1.34
206.00
276.04
20%
0%
280.04
1680.24
0.00
13240.24
Page 3 of 517
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
132.45
elec-1.5.5
4.00
4715.00
elec-1.5.3
1.00
2130.00
18860.00
2130.00
20990.00
0.00
0.00
20990.00
Labour Charges
Skilled Electrician (2.0 + 0.34)
day
2.34
224.00
524.16
day
206.00
1442.00
day
2.34
206.00
482.04
20%
0%
489.64
2937.84
23927.84
0.00
239.30
100 M
893.00
893.00
elec-1.7.1
each
17.50
122.50
elec-1.7.15
each
19.00
133.00
elec-1.4.19
No
40.00
40.00
1188.50
0.00
0.00
1188.50
b) Labour charges :
Skilled Electrician
day
0.7
224.00
156.80
day
1.4
206.00
288.40
Helpers
day
0.7
206.00
144.20
20%
0%
117.88
707.28
0.00
1895.78
270.85
Page 4 of 517
E- DATA
Remarks
7
315806963.xlsx
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
Specification No.
Description
Unit
Quantity
1.50
270.85
406.30
elec-1.7.4
each
25.00
25.00
elec-1.7.1
each
17.50
17.50
0.00
42.50
0.00
42.50
b) Labour charges :
Skilled Electrician
day
0.067
224.00
15.01
Helpers
day
0.067
206.00
13.80
20%
0%
5.76
34.57
0.00
77.10
11
elec-1.5.1
100 M
893.00
893.00
elec-1.7.1
each
15
17.50
262.50
elec-1.7.4
each
15
25.00
375.00
1530.50
0.00
0.00
1530.50
b) Labour charges :
Skilled Electrician
day
1.5
224.00
336.00
day
1.5
206.00
309.00
Helpers
day
1.5
206.00
309.00
20%
0%
190.80
1144.80
0.00
2675.30
178.40
Page 5 of 517
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
12
Supply and Fixing of 16A 3pin and 6A 3pin plug socket with
and 16A switch control duly recessed in wall with MS switch
deep box of 6" x8" x2 1/2" size covered with hylam sheet
including earth connections and all labour charges etc.,
complete.
Makes : Gold Medal /Million / Vimal
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
each
150.00
150.00
elec-1.4.18
each
24.00
24.00
elec-1.7.11
each
130.00
130.00
304.00
0.00
0.00
304.00
b) Labour charges :
Skilled Electrician
day
0.1
224.00
22.40
day
0.1
206.00
20.60
Helpers
day
0.1
206.00
20.60
20%
0%
12.72
76.32
0.00
380.35
13
elec-1.5.1
100 M
893.00
0.00
893.00
0.00
893.00
b) Labour charges :
Skilled Electrician
day
0.34
224.00
76.16
day
206.00
206.00
Helpers
day
0.34
206.00
70.04
20%
0%
70.44
422.64
0.00
1315.64
13.20
elec-1.5.3
100 M
0.00
Page 6 of 517
2130.00
4260.00
0.00
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
4260.00
b) Labour charges :
Skilled Electrician
day
0.67
224.00
150.08
day
206.00
412.00
Helpers
day
0.67
206.00
138.02
20%
0%
140.02
840.12
0.00
5100.12
51.05
elec-1.5.4
100 M
3100.00
0.00
6200.00
0.00
6200.00
b) Labour charges :
Skilled Electrician
day
224.00
224.00
day
206.00
618.00
Helpers
day
206.00
206.00
20%
0%
209.60
1257.60
0.00
7457.60
74.60
elec-1.5.5
100 M
4715.00
0.00
9430.00
0.00
9430.00
b) Labour charges :
Skilled Electrician
day
224.00
224.00
day
206.00
618.00
Helpers
day
206.00
206.00
20%
0%
209.60
1257.60
0.00
10687.60
106.90
elec-1.5.6
Page 7 of 517
100 M
7330.00
14660.00
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
0.00
0.00
14660.00
b) Labour charges :
Skilled Electrician
day
224.00
224.00
day
206.00
618.00
Helpers
day
206.00
206.00
20%
0%
209.60
1257.60
0.00
15917.60
159.20
elec-1.5.7
100 M
11725.00
0.00
23450.00
0.00
23450.00
b) Labour charges :
Skilled Electrician
day
224.00
224.00
day
206.00
618.00
Helpers
day
206.00
206.00
20%
0%
209.60
1257.60
0.00
24707.60
247.10
19
elec-1.5.6
elec-1.5.4
100 M
7330.00
100
1.00
3100.00
29320.00
3100.00
32420.00
0.00
0.00
32420.00
b) Labour charges :
Skilled Electrician (2.0 + 0.5)
day
2.5
224.00
560.00
day
7.5
206.00
1545.00
day
2.5
206.00
515.00
20%
0%
524.00
3144.00
0.00
Sundries
C) Cost for 100 RM
35564.00
355.65
Page 8 of 517
E- DATA
Remarks
7
315806963.xlsx
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
Specification No.
Description
Unit
Quantity
Nos
818.00
818.00
10/16/20A SP MCB
Nos
184.00
184.00
0.00
elec-2.93.36
ele-2.9.1
1002.00
0.00
1002.00
b) Labour charges :
Skilled Electrician
Nos
0.25
224.00
56.00
Nos
0.25
206.00
51.50
Helpers
Nos
0.25
206.00
51.50
20%
0%
LS
31.80
190.80
0.00
130.00
1322.80
21
10kA-6-32A SP
each
elec-2.91.6
elec-2.9.1
0.00
2261.00
2261.00
each
731.00
731.00
each
12
184.00
2208.00
5200.00
0.00
5200.00
b) Labour charges :
Skilled Electrician
day
0.5
224.00
112.00
day
206.00
206.00
Helpers
day
206.00
206.00
20%
0%
628.80
0.00
LS
14.00
14.00
5842.80
104.80
10kA-6-32A SP
Page 9 of 517
E- DATA
Remarks
7
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
elec-2.93.22
each
2261.00
elec-2.91.7
each
800.00
elec-2.9.1
each
12
184.00
315806963.xlsx
E- DATA
Remarks
7
5269.00
Add contr profit @14% on material
0.00
0.00
5269.00
b) Labour charges :
Skilled Electrician
day
0.5
224.00
112.00
day
206.00
206.00
Helpers
day
206.00
206.00
20%
0%
628.80
0.00
LS
14.00
14.00
104.80
5911.80
10kA-6-32A SP
each
2261.00
2261.00
elec-2.91.8
each
846.00
846.00
elec-2.9.1
each
12
184.00
2208.00
0.00
5315.00
0.00
5315.00
b) Labour charges :
Skilled Electrician
day
0.5
224.00
112.00
day
206.00
206.00
Helpers
day
206.00
206.00
20%
0%
628.80
LS
14.00
104.80
0.00
14.00
5957.80
6-
each
1113.00
elec-2.91.2
40A D.P.Isolator
each
329.00
Page 10 of 517
315806963.xlsx
Specification No.
Description
Unit
Quantity
each
elec-2.9.1
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
184.00
0.00
0.00
2546.00
b) Labour charges :
Skilled Electrician
day
0.5
224.00
112.00
day
0.5
206.00
103.00
Helpers
day
206.00
206.00
20%
0%
505.20
LS
5.00
84.20
0.00
5.00
3056.20
23
elec-2.93.35
Nos
8917.00
elec-2.8.2
Nos
6750.00
6750.00
elec-2.9.6
Nos
1328.00
10624.00
elec-2.9.1
Nos
184.00
0.00
0.00
8917.00
26291.00
0.00
26291.00
b) Labour charges :
Skilled Electrician
day
224.00
224.00
day
206.00
206.00
Helpers
day
206.00
206.00
20%
0%
763.20
LS
19.00
127.20
0.00
19.00
27073.20
Page 11 of 517
Say
E- DATA
Remarks
27073.20
315806963.xlsx
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
7600
7600
330
990
2500
2500
175
175
2500
2500
175
175
135
405
450
2700
83
249
45
135
2025
20250
Metering Set:
10
37679
Sub TOTAL:
9419.75
16955.55
3767.90
1883.95
565.19
70271.34
Add contr profit @14% on material
0.00
Page 12 of 517
0.00
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
70271.35
a) Material
Earth Work Excavation of Hard gravel Soil with small
boulder for trench 1st step of size 1.5 x 0.6 x 0.9 m
cum
0.85
203.84
173.26
cum
0.9
203.84
183.46
25.00
25.00
25% extra for narrow trench & pit and back filling with Sand,
Coke, Salt etc., and leveling
40mm dia 'B' Class G.I pipe
elec-8.1.12
Mtr
2.5
360.00
900.00
Each
75.00
75.00
Each
16
5.00
80.00
Set
12.00
48.00
Each
100.00
100.00
320.00
elec-8.1.16
Hard Coke
Kg
40
8.00
elec-8.1.17
Salt
Kg
20
4.00
80.00
1984.72
0.00
0.00
1984.72
Each
Nos
0.5
206.00
103.00
Helpers
Nos
0.5
206.00
103.00
20%
0%
41.20
247.20
0.00
Sundries
Rate per each
27
2231.92
Say
2231.95
Supply and Run of No.8 SWG G.I wire including cost of all
accessories and labour charges etc., complete.
a) Material
elec-8.1.45
elec-8.1.10
U' Nails
Kg
10.4
55.00
572.00
100Nos
1.5
40.00
60.00
632.00
0.00
0.00
632.00
b) labour charges
Helpers
day
20%
0%
206.00
412.00
82.40
494.40
0.00
1126.40
11.30
Page 13 of 517
E- DATA
Remarks
7
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
28
a) Material
4' x 40 watts box type flourscent light fitting.
Lamp cost of 40W
Tw Round blocks
Rate per each
each
each
each
1
1
2
810.00
45.00
6.00
0.00
315806963.xlsx
elec-3.6.8
elec-3.7.16
elec-8.1.35
0.00
810.00
45.00
12.00
867.00
867.00
elec-1.7.16
each
19.00
elec-3.7.1
40W bulb
each
12.00
elec-1.7.15
each
-19.00
12.00
0.00
0.00
12.00
b) Labour charges :
Skilled Electrician
day
0.05
224.00
11.20
Helpers
day
0.05
206.00
10.30
20%
0%
4.30
25.80
0.00
37.80
30
elec-1.7.22
Call bell
each
50
50.00
elec-1.4.25
each
36
36.00
86.00
0.00
0.00
86.00
b) Labour charges :
Skilled Electrician
day
0.062
224
13.89
Helpers
day
0.062
206
12.77
Page 14 of 517
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
20%
0%
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
5.33
31.99
31
0.00
118.00
each
90
90
each
36
36
126
0.00
0.00
126
b) Labour charges :
Skilled Electrician
day
0.062
224
13.89
Helpers
day
0.062
206
12.77
20%
0%
5.33
31.99
elec-5.1.3
158.00
each
0.00
1
1%
1600.00
16.00
1600
16.00
1616.00
0.00
1616.00
156.00
156.00
0.00
elec-1.7.13
0.00
0.00
156.00
day
0.1
206.00
20%
0%
8.36
50.16
0.00
206.20
20.60
21.20
Sundries.
Labour Charges
Page 15 of 517
E- DATA
Remarks
7
315806963.xlsx
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
Specification No.
Description
Unit
Quantity
9.00
9.00
LS
3.00
3.00
12.00
Add contr profit @14% on material
0.00
0.00
12.00
day
0.125
224.00
28.00
Helper
day
0.125
206.00
25.75
20%
0%
10.75
64.50
0.00
76.50
35
elec-5.1.14
each
2300.00
1%
23.00
23.00
2323.00
0.00
0.00
2300.00
2323.00
elec-1.6.8
9.00
9.00
Cement
kg
25
4.40
110.00
119.00
0.00
0.00
119.00
b) Labour charges.
Skilled Electrician
day
0.25
224.00
56.00
Helper
day
0.25
206.00
51.50
Mason
day
0.25
206.00
51.50
20%
0%
LS
31.80
1
190.80
0.00
24.34
24.34
334.15
Page 16 of 517
E- DATA
Remarks
7
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
37
315806963.xlsx
a) Material
elec-3.1.1
each
1390.00
elec-3.7.16
each
45.00
1390.00
45.00
1435.00
0.00
0.00
1435.00
Fixing of 40W street light luminaire to the wall with 1.0 Mtr.,
25mm dia GI pipe bracket and anti tilting MS flat etc.,
including giving connections and labour charges etc.,
complete.
a) Material
BMW-F.83
212.00
212.00
elec-1.6.8
9.00
18.00
LS
25.00
25.00
LS
35.00
35.00
290.00
0.00
0.00
290.00
b) Labour charges
Skilled Electrician/carpenter
day
0.2
224.00
44.80
Mason
day
0.2
224.00
44.80
day
0.2
206.00
41.20
20%
0%
26.16
156.96
0.00
447.00
1882.00
elec-3.1.13
each
5484.00
elec-3.4.10
each
710.00
5484.00
710.00
6194.00
0.00
0.00
6194.00
6194.00
Page 17 of 517
E- DATA
Remarks
7
315806963.xlsx
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
Specification No.
Description
Unit
Quantity
40
360.00
21.30
a) Material
BMW-F.87
360.00
85.20
445.20
0.00
0.00
445.20
LS
25.00
25.00
Skilled Electrician
day
0.25
224.00
56.00
Carpenter
day
0.25
224.00
56.00
Helper
day
0.25
206.00
51.50
Welder
day
0.25
224.00
56.00
20%
0%
43.90
207.40
41
0.00
733.60
Say
733.60
1010.00
1010.00
elec-7.1.1
100 M
0.00
0.00
1010.00
b) Labour charges :
Skilled Electrician
day
0.34
224.00
76.16
day
206.00
206.00
day
0.34
206.00
70.04
20%
0%
70.44
422.64
0.00
Sundries
C) Cost for 100 RM
1432.64
14.35
42
elec-1.7.18
44.00
44.00
elec-1.3.1
MS box
50.00
50.00
Page 18 of 517
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
elec-1.4.22
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
12.00
12.00
106.00
0.00
0.00
106.00
b) Labour charges :
Skilled Electrician
day
0.1
224.00
22.40
day
0.1
206.00
20.60
Helpers
day
0.1
206.00
20.60
20%
0%
12.72
76.32
0.00
Sundries
C) Cost for each
43
182.35
elec-7.1.4
100 M
2580.00
0.00
2580.00
0.00
2580.00
b) Labour charges :
Skilled Electrician
day
0.34
224.00
76.16
day
206.00
206.00
Helpers
day
0.34
206.00
70.04
20%
0%
70.44
422.64
0.00
Sundries
C) Cost for 100 RM
3002.64
30.05
elec-7.1.5
340.00
340.00
elec-1.3.1
MS box
50.00
50.00
0.00
390.00
0.00
0.00
390.00
b) Labour charges :
Skilled Electrician
day
0.2
224.00
44.80
day
0.2
206.00
41.20
Helpers
day
0.12
206.00
24.72
20%
0%
22.14
132.86
0.00
Sundries
C) Cost for each
522.90
Page 19 of 517
E- DATA
Remarks
7
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
45
100 M
1700.00
315806963.xlsx
0.00
1700.00
0.00
1700.00
b) Labour charges :
Skilled Electrician
day
0.34
224.00
76.16
day
206.00
206.00
Helpers
day
0.34
206.00
70.04
20%
0%
70.44
422.64
0.00
Sundries
C) Cost for 100 RM
2122.64
21.25
elec1.7.19
TV socket outlet
26.00
26.00
elec-1.3.1
MS box
50.00
50.00
elec-1.4.22
12.00
12.00
88.00
0.00
0.00
88.00
b) Labour charges :
Skilled Electrician
day
0.04
224.00
8.96
day
0.04
206.00
8.24
Helpers
day
0.04
206.00
8.24
20%
0%
5.09
30.53
0.00
Sundries
C) Cost for each
47
elec-4.1.28
118.55
Rmt
0.00
274.00
0.00
274.00
274.00
Rmt
0.00
207.00
207.00
0.00
207.00
Page 20 of 517
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
Rmt
0.00
elec-4.1.22
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
174.00
174.00
174.00
Rmt
0.00
136.00
136.00
0.00
136.00
Earth work excavation of Trench in hard ground soil, laying of U.G cables upto 50 Sq,mm on sand cushion covering the cable with br
a) Material
cum
27
203.84
5503.68
1000 Nos
0.92
5427.01
4992.85
cum
1074.09
6444.54
Kg
25
5810.25
145.26
each
12
75.00
900.00
17986.33
0.00
0.00
17986.33
each
2.5
206.00
515.00
Skilled Electrician
day
224.00
224.00
Helper
day
206.00
412.00
206.00
412.00
20%
0%
312.60
1360.60
19866.93
198.70
0.00
5.00
49
0.00
E- DATA
Remarks
/ existing pipe
as saddles,
directed by
wire for eath
a) Material
elec-8.1.8
Wooden separators
each
200
1.50
300.00
elec-1.1.38
100 nos
375.00
750.00
elec-1.4.34
12mm screws
100 nos
50.00
200.00
elec-8.1.45
kg
55.00
385.00
1635.00
0.00
0.00
1635.00
b) Labour charges
Skilled Electrician
day
Page 21 of 517
224.00
224.00
315806963.xlsx
Specification No.
Description
Unit
Quantity
Helper
day
20%
0%
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
206.00
209.60
1257.60
0.00
21.00
2913.60
29.15
50
824.00
elec-2.6.4
elec-1.4.7
each
405.00
1215.00
each
118.00
118.00
each
90.00
90.00
0.00
1423.00
0.00
1423.00
b) Labour charges
Skilled Electrician
day
224.00
224.00
Helper
day
206.00
824.00
20%
0%
209.60
1257.60
51
0.00
50.00
2730.60
elec-6.3.11
each
1012.00
elec-2.6.1
32 A Fuse units
each
80.00
1012.00
80.00
MS box 300mmx450mm
each
218.00
218.00
0.00
1310.00
0.00
1310.00
b) Labour charges
Skilled Electrician
day
224.00
224.00
Helper
day
0.33
206.00
67.98
20%
0%
58.40
350.38
0.00
50.00
1710.40
Page 22 of 517
E- DATA
Remarks
7
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
52
each
8050.00
315806963.xlsx
a) Material
elec-5.2.3
elec-5.3.4
161.00
2%
nos
8050.00
110.00
220.00
8431.00
0.00
0.00
8431.00
day
0.25
224.00
56.00
Helper
day
0.25
206.00
51.50
20%
0%
21.50
129.00
0.00
25.00
8585.00
53
a) Material
As per MR
34325.00
54
34325.00
34325.00
elec-8.1.28
each
0.00
100.00
100.00
0.00
100.00
b) Labour charges
Skilled Electrician
day
0.05
224.00
11.20
Helper
day
0.05
206.00
10.30
20%
0%
4.30
25.80
0.00
125.80
Page 23 of 517
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
E- DATA
Remarks
7
Description
Unit
Quantity
kg
372.4
36.40
13555.36
kg
37.68
35.06
1321.07
kg
47.8
37.06
1771.48
kg
12
37.06
444.72
kg
15
37.06
555.90
kg
13.5
37.06
500.31
Total Ms items
Kg
37.06
554.10
a.Material
Elec-6.5.15
for
mounting
11KV
Add wastage @ 3%
498.38
14.9514
Total weight
kg
513.3314
Fabrication charges
LS
513.3
0.00
18702.95
9.00
4619.70
23322.65
0.00
0.00
23322.65
day
224.00
448.00
Helper
day
206.00
824.00
day
224.00
448.00
day
206.00
412.00
20%
0%
426.40
2110.40
elec- 6.5.2
each
0.00
600.00
elec-6.5.3
1800.00
each
0.00
300.00
elec-6.5.1
900.00
0.00
1800.00
0.00
0.00
25881.10
900.00
Each
0.00
Page 24 of 517
1500.00
4500.00
0.00
3
1
1
0
2
0
0
6
Remarks
315806963.xlsx
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
elec-6.5.9
4500.00
each
0.00
5900.00
0.00
elec-6.5.10
5900.00
each
0.00
4000.00
4000.00
0.00
5900.00
4000.00
elec-4.1.40
Rmt
0.00
641.00
641.00
0.00
641.00
each
2.5
206.00
515.00
Skilled Electrician
day
224.00
224.00
Helper
day
206.00
412.00
206.00
412.00
20%
0%
0.00
5.00
1880.60
312.60
1360.60
18.81
659.85
Page 25 of 517
E- DATA
Remarks
7
Specification No.
Description
Unit
Quantity
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
each
25350.00
25350.00
2500.00
2500.00
315806963.xlsx
elec-6.3.3
each
elec-6.3.8
each
175.00
175.00
elec-6.3.1
each
2500.00
2500.00
elec-6.3.8
each
175.00
175.00
elec-6.3.9
each
135.00
405.00
450.00
2700.00
130.00
390.00
45.00
135.00
12450.00
12450.00
Outgoing :
elec-2.8.6
each
7900.00
15800.00
MR
each
6350.00
12700.00
elec-2.8.5
each
5750.00
23000.00
0.00
98280.00
9828.00
44226.00
4914.00
157248.00
Add contr profit @14% on material
0.00
0.00
157248.00
b)labour charges
Skilled electrician
day
224.00
224.00
day
206.00
412.00
helper
day
206.00
824.00
20%
0%
292.00
1752.00
0.00
159000.00
a) Material
Page 26 of 517
E- DATA
Remarks
7
315806963.xlsx
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
Specification No.
Description
Unit
Quantity
cum
1.21
122.11
147.75
cum
0.9
150.00
135.00
25.00
25.00
Mtr
2.5
301.00
752.50
Each
75.00
75.00
Each
16
5.00
80.00
25% extra for narrow trench & pit and back filling with Sand,
Coke, Salt etc., and leveling
40mm dia 'B' Class G.I pipe
elec-8.1.12
Set
12.00
48.00
Each
100.00
100.00
elec-8.1.16
Hard Coke
Kg
20
8.00
160.00
elec-8.1.17
Salt
Kg
20
4.00
80.00
1603.25
0.00
0.00
1603.25
Each
day
0.5
206.00
103.00
Helpers
day
0.5
206.00
103.00
20%
0%
41.20
247.20
0.00
Sundries
Rate per each
10
Say
1850.50
elec-8.1.45
GI strip
kg
1.4
55.00
0.00
77.00
0.00
77.00
b) Labour charges
Semi skilled electrician
day
0.02
206.00
4.12
Helper
day
0.04
206.00
8.24
20%
0%
2.47
14.83
0.00
Rmt
91.85
elec-6.1.1
MR
kg
135
65.00
8775.00
each
540.00
540.00
396.00
elec-1.5.2
rmt
30
13.20
elec-6.1.3
kg
8.41
60.00
504.60
10215.60
0.00
0.00
10215.60
Page 27 of 517
E- DATA
Remarks
7
315806963.xlsx
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
Specification No.
Description
Unit
Quantity
Skilled electrician
day
0.5
224.00
112.00
day
0.5
206.00
103.00
helper
day
206.00
206.00
day
0.5
224.00
20%
0%
b)Labour charges
112.00
106.60
527.60
0.00
10855.20
Cable termination
12
elec-4.2.9
Heavy duty flange type brass cable gland for 3.5c x150
sqmm PVC armoured cable
each
200.00
200.00
elec-4.3.8
each
94.00
282.00
elec-4.3.5
each
50.00
50.00
532.00
0.00
0.00
13
532.00
elec-4.2.4
Heavy duty flange type brass cable gland for 3.5c x35 sqmm
PVC armoured cable
each
100.00
100.00
elec-4.3.3
each
30.00
90.00
elec-4.3.1
each
20.00
20.00
0.00
210.00
0.00
14
210.00
elec-4.2.5
Heavy duty flange type brass cable gland for 3.5c x50 sqmm
PVC armoured cable
each
115.00
115.00
elec-4.3.4
each
35.50
106.50
elec-4.3.2
each
27.00
27.00
248.50
0.00
0.00
248.50
elec-4.2.3
Page 28 of 517
each
95.00
95.00
E- DATA
Remarks
7
315806963.xlsx
Specification No.
Description
Unit
Quantity
elec-4.3.1
each
0.00
1
0
2
Rate Rs. Amount Rs. 0
0
5
66
20.00
80.00
175.00
0.00
175.00
elec-4.1.14
Rmt
0.00
98.00
98.00
0.00
98.00
each
2.5
206.00
515.00
Skilled Electrician
day
224.00
224.00
Helper
day
206.00
412.00
206.00
412.00
20%
0%
312.60
1360.60
1880.60
17
0.00
5.00
18.81
116.85
elec-4.2.1
each
45.00
45.00
elec-4.3.1
each
20.00
80.00
0.00
125.00
0.00
125.00
18
MR
each
340628.00
LS
6500.00
340628.00
6500.00
347128.00
Page 29 of 517
E- DATA
Remarks
7
P
NIT
No
Name of work
for execution
Lr no from SE
NIT No
ECV
KADAPA
978/SE/D3/Model School/
/2011-12, Dt.21.02.2012
CHITTOOR
#REF!
#REF!
ECV in words
BidProcessingFee
#NAME?
Superintending
Engineer,
O/o.Managing
Managing Director, Director,
APEWIDC,
APEWIDC,
20000 Hyderabad
Hyderabad
EMD
Bank
Gurantee in
favour of
Managing
Director,
APEWIDC,
#REF! Hyderabad
Period of
completion
#REF!
#REF!
DownloadingOfBid
20/09/2012 at 3.00 PM to
#REF! 6/010/2012 up to 3:30 PM
DateOfBidReceipt
20/09/2012 at 3.30 PM to
6/10/2012 up to 4:00 PM
TechnicalBid
06/09/2012 at 4.30 PM
PriceBid
10/10/2012 at
4.00 PM
#REF!
#REF!
#REF!
Plasterin
SteelCent
Flooring
PinVibrators PanVibrators WeighBatchers ConcreteMixers
g
ering
#REF!
#REF!
1000
QCLabs
#REF! 03/02/2011
#REF!
#REF!
SSR
SSRCement SSRHYSDBars
5000.00
47500.00
44500.00 Guntur
L1
Tender
discount
8.19% Less
LrNo
TCV
L2
M/s Deepak
22326965.42 Constructions
Tender
discount
5.60% Less
L3
G.Madhusudhan
Reddy.
Tender
discount
5.49% Less
L4
Ch.Marthanda
Rao & Co.
Tender
discount
4.50% Less
L5
M/s VCR
Associates.
Tender
discount
3.86% Less
L6
B.Sanjeeva
Reddy.
Tender
discount
3.69% Less
L7
Tender
discount
L8
Tender
discount
L9
Tender
discount
L10
Tender
discount
Srico Projects
Pvt. Ltd.
3.29% Less
Aditya
Housing &
Infrastructure
Dev. Corp. P. 3.10%
Ltd.
Less
3.06%
Murali. M Less
M/s
Sripathi
Constructi 0.69%
ons.
Less
L11
Tender
discount
(B) Machinery
Rate as per G.O. Ms No 10, Dt 26/7/2005
100.00 cum
Motor Grador for Grading @ 100 cum per
1.00 hr
hour
Water tanker 6 KL
4.00 hr
Vibratory roller 8T
1.00 hr
(C)
100.00 Cum
385.00
295.00
day
day
7.70
147.50
155.20
81.44
2600.00
658.35
2678.30
cum
hr
hr
hr
8144.00
0.00
cum
2600.00
2633.40
2678.30
16055.70
0.00
648.44
16859.34
1685.93
18545.27
185.45
185.00
1 Cum
Providing Plain Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational charges
of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for base
coarse below CC Pavement.
Unit = cum
Taking output = 15 cum
36 of 517
CC Road data
(A) Labour
0.64 nos
1.00 nos
15.00 nos
385.00
345.00
295.00
Mate
Mason
Mazdoor
Total
(B) Material
Cost of 40mm SS-5 HBG M/C metal
13.50 cum
946.40
6.75 cum
Sand at site
922.90
2.43 MT
Cement at site
6446.32
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
328.60
0.00 hr
Generator set 35 KVA
620.00
2.00 hr
Water tanker 6 KL
658.35
Total
(D) Over head charges @ 4% (10%-VAT)
4.00 %
Add for Over head charges @ 6% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E) + (F)
Rate for 1 cum
Rate to be adopted
day
day
day
246.40
345.00
4425.00
5016.40
cum
cum
MT
12776.40
6229.58
15664.55
34670.53
hr
hr
hr
1971.60
0.00
1316.70
3288.30
1719.01
44694.24
4469.42
49163.66
3277.58
3278.00
1 Cum
Construction of Gravel shoulders including cost, and conveyance of all materials to work
site and spreading in uniform layers by approved means, on prepared surface and
compacting with vibratory roller to achieve the desired density at OMC etc., complete for
finished item of work as per MoRT&H Specification 401& 407 (4th revision) and as
directed by the Engineer-in-charge.
( Payment will be made based on levels for finished item of work ).
Unit = cum
Taking output = 300 cum
(A) Labour
0.40 day
Mate
385.00
2.00 day
Mazdoor skilled
345.00
Mazdoor unskilled
295.00
8.00 day
Total
(B) Machinery
Vibratory roller 8T
2678.30
6.00 hr
Water tanker 6 KL
658.35
3.00 hr
Total
(C) Material
Gravel
149.10
384.00 cum
(D) Over head charges @ 6% (10%-VAT)
4.00 %
Add for Over head charges @ 6% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
37 of 517
day
day
day
154.00
690.00
2360.00
3204.00
hr
hr
16069.80
1975.05
18044.85
57254.40
3140.13
81643.38
8164.34
CC Road data
89807.72
299.36
299.00
1 Cum
Vibrated cement concrete M.25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost, seigniorage conveyance of all materials to site and labour
charges, centering, machine mixing, laying, vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as
per Approved drawing but excluding cost of steel and its fabrication charges as per
MoRT&H specification 1500, 1600,1700, & 2704 (4 th Revision) and as directed by the
Engineer-in-Charge for CC Pavements.
0.86
1.50
20.00
Unit = cum
Taking output = 15 cum
(A)
Labour
nos
Mate
nos
Mason
nos
Mazdoor
Total
8.10
5.40
6.75
6.05
(B)
cum
cum
cum
MT
6.00
6.00
hr
hr
2.00
14.00
(D)
%
%
Material
Cost of 20mm HBG metal
Cost of 10mm HBG metal
Sand at site
Cement at site
Total
Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
Total
Form work
Form work @ 2% on (A)+(B)+( C)
385.00
345.00
295.00
day
day
day
331.10
517.50
5900.00
6748.60
1908.88
1478.88
922.90
6446.32
cum
cum
cum
MT
15461.93
7985.95
6229.58
39000.21
68677.67
328.60
620.00
hr
hr
1971.60
3720.00
5691.60
81117.87
Cum
1622.36
11583.63
94323.86
6288.26
6288.00
1 Cum
Executive Engineer
APEWIDC, CHITTOOR
38 of 517
CC Road data
Superintending Engineer
APEWIDC, KADAPA
39 of 517
CC Road data