Project Basic Design Italy
Project Basic Design Italy
Project Basic Design Italy
Area
Code
Saipem SpA
Via Toniolo n. 1
61032 Fano - Italy
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Ordering Unit:
Owner:
Saipem Fano
Project Title:
LF-E-82000
Document Title:
Rev.
Purpose of Issue
Remark/Description
Orig.
Date
0A
First Preparation
MAC
2013-06-10
0B
MAC
2013-06-17
0C
MAC
2013-06-24
0D
MAC
2013-07-19
0E
MAC
2013-08-22
00
MAC
2013-09-16
CONTRACTOR
Checked
Approved
Magliola, Carlo
Ricci Luigi
Mazzanti, Sara
2013-09-16
2013-09-16
2013-09-16
Saipem
Saipem
Saipem
Preliminary
Checked
Approved
Name/Signature
Date
Org. / Dept.
Document Status
Checked/Approved
Checked/Approved
Page 2 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Table of contents
INTRODUCTION
DESIGN DATA
2.1
2.2
2.3
7
14
20
35
3.1
3.2
Offshore Section
Onshore Section
35
35
37
4.1
4.2
37
40
42
5.1
5.2
42
71
CONSTRUCTION TIMING
75
76
83
Page 3 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
ABBREVIATIONS
Abbreviation
Disc.
Code
Description
ACS
AHT
AON
AVAS
BHD
Back-hoe Dredger
Bcm
BVS
CC
Concrete Coating
CCR
CCT
CCTV
CPI
DCVG
DM
Ministerial Decree
DN
Nominal Diameter
DP
Design Pressure
DPR
ESD
Emergency Shutdown
EEZ
FDS
GDS
HIPPS
ID
Internal Diameter
KP
KP of
LDS
LR
MOP
MTBM
NDT
Non-destructive Test
OD
External Diameter
PON
Page 4 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Abbreviation
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Description
OLB
Offshore Lay-barge
PRT
PSA
ROW
Right of Way
SCADA
SG
Specific Gravity
SP
SRG
SS
TAP
TBM
UXO
Unexploded Ordnance
VIV
WD
Water Depth
WF
Weight Factor
WT
Wall Thickness
Page 5 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
INTRODUCTION
Trans Adriatic Pipeline will transport gas via Greece and Albania and across the Adriatic Sea to
Italys southern Puglia Region and further to Western Europe. Crossing the Adriatic Sea from
central-western Albania, the offshore pipeline gets onshore in south-east Italy and ties in to the
Italian gas network South of Lecce.
Across the Adriatic Sea the gas will be transported via a 36 pipeline to an onshore receiving
terminal (TAP Receiving Terminal) that will be connected to the existing Snam Rete Gas network.
The project is aimed at enhancing security of supply as well as diversification of gas supplies for
the European markets. TAP has also incorporated provisions to accommodate physical reverse
flow. The total pipeline length is 871 km approximately.
The pipeline system in Italy would consist of an approximately 45 km long offshore pipeline, from
the Italian jurisdiction boundary (middle of the Adriatic Sea) to the Italian coast (KPof 60.144
KPof 104.975, considering KPof 0 the Albanian Landfall), an approximately 8.2 km long onshore
pipeline (KP 0 KP 8.203), considering KP 0 the entry point of the offshore microtunnel, and a
Pipeline Receiving Terminal (also referred to as PRT) near Melendugno in the province of Lecce
with an initial nominal capacity of 10 BCM (expandable to 20 BCM) of natural gas per year
(around 1.190.000 standard cubic metres per hour).
The intersection point between the offshore and onshore pipeline is the entry point of the offshore
microtunnel foreseen for the landfall; this point is defined as KPof 104.975 (end of the offshore
section) and KP 0 (start point of the onshore section).
The pipeline landfall will be on the coast between San Foca and Torre Specchia Ruggeri in the
municipality of Melendugno. The landfall will be constructed using micro-tunnelling technology to
minimize the visual and environmental impact on the coastline.
General Overview.
Page 6 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The project will also include a Fiber Optic Cable (FOC) to enable communication between the
TAP Receiving terminal where the supervisory control centre is located, the compressor stations
in Albania and Greece as well as the block valve stations installed along the 871 km long
pipeline.
The FOC shall be laid parallel to the pipeline, along the entire route (onshore and offshore) and
will be the primary means of communication between the pipeline stations.
Page 7 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
DESIGN DATA
2.1
The offshore pipeline is described by the following basic data, which are in compliance with
Italian DM 17/04/2008 and DNV OS F101:
Type 1
145 bar
145 bar
Gas transported:
Natural Gas
Nominal diameter:
DN 900 (36)
Internal diameter
871 mm (constant)
Material:
Microtunnel
34 mm
2.1.1
OD:
3000 mm
Length:
1485 m
The estimated volume of soil to be excavated for the Microtunnel construction is about 10500 m3.
Provisional dimensions of the launch shaft are:
Depth:
11 m
Length:
10 m
Width:
12 m
The estimated volume of soil to be excavated for the launch shaft construction is about 1300 m3.
The envisaged suitable location for the Microtunnel exit point is around at -18.0 m WD, and 867
m far from the shore line.
Figure 2-1 shows a plan view of the area of the landfall tunnel.
Page 8 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
2.1.2
Pipeline Stability
Calculations have been performed applying the criteria given in DNV-RP-F109 On Bottom
Stability Design of Submarine Pipelines, both in temporary and long term conditions.
A concrete coating with density of 3050 Kg/m3 is considered.
The pipeline stability assessment has been carried out assuming, for the concrete, a water
absorption of 2% by weight.
Stability calculations have been performed for the entire pipeline section resting on the natural
seabed, i.e. out of Microtunnel.
Table 2-1 shows the minimum concrete thicknesses for the lateral pipeline stability.
Page 9 di 97
E.ON New Build & Technology GmbH
Area
Code
Saipem SpA
Project Title:
Document Title:
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Lateral Stability Checks
Required Concrete thickness
Temporary
Operating
Zone
Section
WT
From
KPof
[-]
[km]
19-23 60.100
24-26 79.400
27-29 97.800
30-31 102.713
32-34 102.490
To KPof
Lengt
h
From
WD1
To
WD2
[km]
79.400
97.800
102.713
103.490
104.975
[m]
19300
18400
4913
777
1485
[m]
-806
-125
-99
-44
-20
[m]
-125
-99
-44
-20
0
[mm]
34
20.6
23.8
23.8
34
@
WD1
@
WD2
@
WD1
@
WD2
Selected
CCT
[mm]
N/A
50.4
50.4
81.7
N/A
[mm]
N/A
50.4
50.4
79.8
N/A
[mm]
N/A
50.4
50.4
110.3
N/A
[mm]
N/A
50.4
50.4
105.6
N/A
[mm]
N/A
55
55
120
N/A
Table 2-2 shows, for the selected concrete coating thickness the relevant submerged weight and
specific gravity
Vertical Stability Check- Empty Condition
Pipe type
Nominal
Steel
Thickness
(mm)
Concrete
Coating
Thickness
(mm)
Pipeline
Submerged
Weight
(Empty)
(kN/m)
Pipeline
Specific
Gravity
(Empty)
Pipeline
Weight in
Air
(kN/m)
Total
External
Diameter
(1)
(m)
0,945
WT=34 mm CT=0mm
34
0.487
1.06
8.464
WT=20.6 mm CT=55mm
20.6
55
1.112
1.13
9.467
1.028
WT=23.8 mm CT=55mm
23.8
55
1.750
1.21
10.228
1.035
WT=23.8 mm CT=120mm
23.8
120
6.325
1.63
17.020
1.165
For the WT 23.8mm, the 120mm and 55mm, required for the lateral stability, fulfil the
SG requirement.
For the WT 20.6mm, the 55mm, required for the lateral stability, fulfils the SG
requirement.
The SG of the WT 34mm, uncoated, is below 1.1. In this case the DNV-RP-F109
requires just to ascertain that the event of pipe floatation in water is unlikely. In
general, floatation (null submerged weight) might occur as a consequence of
combinations of dimensional variations, in particular wall thickness and diameter.
Calculations have shown that, even considering the worst combination of such
parameters, within the allowed tolerances, the minimum submerged weight of 0.252
kN/m can be ensured that is enough to avoid floatation.
The selected wall thickness and concrete distribution in the Italian EEZ is shown in Table 2-3:
Page 10 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Area
Code
Saipem SpA
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Selected Pipes
Pipe
[km]
60.100
79.400
97.800
102.713
[km]
79.400
97.800
102.713
103.490
102.490
104.975
Length
From
WD1
To
WD2
WT
[m]
[m]
[m]
[mm]
19300
18400
4913
777
-806
-125
-99
-44
-125
-99
-44
-20
34
20.6
23.8
23.8
1485
-20
34
CCT
[mm] kN/m
N/A 8.464
55
9.559
55 10.302
120 17.020
N/A
8.464
S.G. (Empty
condition)
To KP of
Submerged
weight
From
KP of
Weights
Dry Weight
Zone
Note
kN/m
0.487
1.387
2.026
6.749
1.06
1.17
1.24
1.63
Exposed
0.487
1.06
Microtunnel
Section
2.1.3
Intervention works are necessary along the offshore pipeline route to comply with the applicable
rules i.e. with DnV OS F101, DnV RP F105, DnV RP F109 and DM 17/04/2008.
In particular interventions with gravel dumping and/or post trenching excavations may be
necessary for:
A.
Preventing the failure for Local Buckling limit state, DnV OS F101.
B.
C.
Interventions with gravel dumping and/or concrete mattresses may be necessary to:
The amount and the locations of such interventions are not yet defined.
2.1.4
2.1.4.1
An excavation shall be carried out at Microtunnel exit, on the seabed, at a distance of 867m from
the shore line (approx. water depth range = 18 27 m) due to the following reasons:
Page 11 di 97
E.ON New Build & Technology GmbH
Area
Code
Saipem SpA
Project Title:
Document Title:
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Recovery the TBM in the proximity of the tunnel exit seawards (KPof 103.090)
Table 2-4 summarizes the basis of the calculations and the estimated excavation and backfilling
volume. The possible maintenance dredging volume is not included.
Distance from
shore line
Length
WD
Range
Base
Width
Max
Volume
Slope Trench
Depth Trench Backfilling
From
To
(m)
(m)
(m)
(m)
(m)
(m)
(m)
867
977
110
-18/-27
4.0
1:4
(m )
15500
15500
2.1.4.2
An
Gravel Dumping
embankment with gravel dumping shall be erected out of the excavated trench from a
distance of 977m to 1223m from the shore line. The scope is to facilitate the operation of pullingin the pipeline through the Microtunnel.
Table 2-5 summarizes the characteristics and the volume of the embankment.
Distance from
shore line
Length
WD
Range
Top
Width
Slope
(m)
(m)
(m)
(m)
(m)
(m)
(m )
1223
246
-27/-32
10
1:3
2.7
7500
From
To
(m)
977
Max
Volume
Height
3
2.1.5
Corrosion Protection
Pipe
Diameter
36
Internal
Nominal
Diameter
Length
(mm)
(m)
871
(constant)
12.2
Wall Thickness
(mm)
Pipe Coating
Field Joint
Type and
Coating Type
Thickness
and Thickness
3LPE - 3.0 mm
HSS - 3.0 mm
Page 12 di 97
E.ON New Build & Technology GmbH
Area
Code
Saipem SpA
Project Title:
Document Title:
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Sacrificial anodes will be installed along the offshore pipeline. Table 2-7 and
Table 2-8 give the anodes distribution and characteristics for the pipeline section inside the Italian
EEZ.
Concrete Pipeline
Coating Condition
thickness
(mm)
From
KP of
To
KP of
60.100
79.400
79.400
102.787
102.787
103.387
Anode
Tag
Anode
Spacing
(joints)
Exposed
AN36A
55
Exposed
AN36B
10
120
Exposed
AN36D
10
Anode Tag
AN36A
tapered
AN36B
AN36C
AN36D
Outer diameter
1.045 m
1.025 m
1.058 m
1.155 m
Anode thickness
50 mm
50 mm
70 mm
115 mm
Anode length
0.781 m
0.500 m
0.500 m
0.500 m
250.5 kg
165.1 kg
238.5 kg
419.0 kg
2.1.6
The Fiber Optic Cable (FOC) is laid along a route parallel to the pipeline at a distance of 50m
approx. The installation will be performed with a dedicated vessel and the burial could be
performed by another. The FOC, where necessary, will be buried 1m beneath the seabed to
protect against trawl fishing, ships anchoring and other activities.
Page 13 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Note:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The progressive 0.00 (Microtunnel Entry) corresponds to KPof 104.975m of the gas offshore pipeline
The progressive 1.485 (Microtunnel Exit) corresponds to KPof 103.490m of the gas offshore pipeline
Page 14 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
2.2
Area
Code
Saipem SpA
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
2.2.1
Design data
The basic data assumed for the feasibility of the route are shown below in compliance with DM
17/04/2008.
2.2.2
Type 1
145 bar
145 bar
0.57
Gas transported:
Natural Gas
DN 900 (36)
Internal diameter
871 mm
20 + 20 m
Material:
Wall Thickness:
26.8 mm
Pipeline Length:
8.2 km
One BVS will be installed close to the pipeline landfall at KP 0.1 in order to enable the isolation of
the offshore pipeline from the onshore part for maintenance and safety purposes.
The block valve station is unmanned and contains as above ground features only a small cabinet
for power and control system and a fence to avoid any interference, covering a total surface area
of approximately 13 x 14 m (plus surrounding vegetation). The following figure illustrates the
foreseen BVS layout plan.
Page 15 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The BVS will be remotely operated from a control centre in the PRT through a fibre-optic cable
communication system and will be connected to the local power grid. The pipeline the block valve
and by-pass valves as well as the connected piping will be buried below ground. Valve integrity is
also monitored by the pipeline Leak Detection System.
In coherence with the selection of the onshore line pipes, the selection of the tubes constituting
the block valve station is based on the same design standards and design specifications. The
diameter of these tubes will be 12 for the by-pass line and 2 for branches to measuring
instruments.
A permanent access road is foreseen, as shown in the Figure 2-4. Part of this access road will be
a new one (yellow line) part will be an enlargement of the existing road (green line).
Page 16 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
2.2.3
With regard to the construction methods of gas pipelines in Italy, Ministerial Decree 17/04/2008
prescribes a minimum pipeline cover not less than 0.9 m and 0.4 in rocky soil from the top of the
pipe. In any case gas pipelines in Italy are usually laid with a minimum cover of 1.5 m, in order to
provide the maximum guarantees of safety from possible interference with human activities
(excavating, ground-breaking for agricultural purposes etc.). The typical trench dimensions
respecting the legal requirements can be seen in following figure.
Page 17 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
2.2.4
In accordance with Italian regulations no clusters of houses should be identified within a range of
100 m to the pipeline. In proximity to the planned pipeline route there are only very few single
houses, at a distance longer than 20 m (in compliance with the DM 17/4/2008).
2.2.5
Distances from power lines, parallelism and crossings with other utilities
In addition to the one provincial road and one minor asphalt road crossing by landfall microtunnel
upstream of KP 0 there is one more provincial road crossing at KP 6.5 and eight more minor
municipality road crossings. Details of all the asphalt road crossings and the proposed
construction method are provided in the table below.
Page 18 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Area
Code
Saipem SpA
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Chainage [m]
WGS84 / UTM 34N
Region / Province
Municipality
Crossing
Method
-500**
Puglia /Lecce
Melendugno
Landfall microtunnel
Puglia /Lecce
Melendugno
Landfall microtunnel
601
Puglia /Lecce
Melendugno
Open cut
Municipal road
1.131
Puglia /Lecce
Melendugno
Open cut
Municipal road
2.027
Puglia /Lecce
Melendugno
Open cut
Municipal road
4.012
Puglia /Lecce
Melendugno
Open cut
Municipal road
4.620
Puglia /Lecce
Melendugno
Open cut
Municipal road
name unknown
5.611
Puglia /Lecce
Melendugno
Open cut
Municipal road
name unknown
5.906
Puglia /Lecce
Melendugno
Open cut
10
Provincial road
6.452
Puglia /Lecce
Melendugno
Trenchless
11
Municipal road
name unknown
7.602
Puglia /Lecce
Melendugno
Open cut
No
Type
Name
Provincial road
SP366
Municipal road
name unknown
Municipal road
2.2.6
Corrosion protection
The onshore part of the pipeline system at the landfall in Italy consists of two parts:
The pipeline, with a length of 8.2 km, between Landfall and PRT.
Corrosion protection of the on-shore pipeline and station piping is first of all achieved by high
quality coatings. The table below lists the coating types as will be used in the TAP project
Application
Factory coating
Type
Field coating
Standard
3LPE
Type
Standard
Polymeric tapes
ISO 21809-3
PUR
ISO 21809-3
Glass fibre
reinforced epoxy
(EP-GFRP =
epoxy resin with
glass fibre
reinforcement)
ISO 21809-3
EN ISO 21809-1
Casings
Product pipe installed by
ramming (pipe jacking),
auger boring (open front
drilling) or horizontal
directional drilling (HDD).
3LPP (for
ambient
temperature > 0
C)
EN ISO 21809-1
EN ISO 21809-1 /
ISO 21809-3
(TAP
specification)
Page 19 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Area
Code
Saipem SpA
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
polyester resins)
layer
For all components which
due to their geometric form
cannot be coated like a
pipeline: for valves, fittings, T
pieces, etc
Air to ground transitions
Internal pipe wall (to reduce
friction for flow of gas)
PUR
EN 10290
PUR
EN 10290
3LPE
EN ISO 21809-1
EN 10290
PUR
EN 10290
PUR or
3LPE + EP-GFRP
Epoxy resin
EN 10301
As above
To prevent corrosion at coating defects of the pipeline, a cathodic protection system will be
installed. The cathodic protection system will consist of:
Pipelines inside the PRT will be in electrical contact with stations groundings and station
foundations. For several reasons, like safety which require grounding of metal objects in
hazardous areas, it will not be possible to eliminate these electrical contacts
In order to achieve protection under these circumstances, a so-called local cathodic protection
system will have to be installed. A local cathodic protection system is aiming at achieving
sufficient soil-to-pipe potentials by changing (relative to remote earth) the soil side of the
potentials.
A local cathodic protection system will consist of:
Single anode controls, in combination with distribution boxes, to prevent that the local
cathodic protection system will cause corrosion interaction with other objects in the
vicinity of the terminal.
Page 20 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
2.3
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
2.3.1
Technical data
The Pipeline Receiving Terminal is required to control the flow of the gas delivered into the Snam
Rete Network. The upstream pipeline is designed for a pressure of 145 bar (g) and the
downstream pipeline is designed for a pressure of 75 bar (g).
The main design conditions are the following:
Design flow rate for the first design stage: 1,320,000 Sm/h;
Nominal flow rate for the first design stage: 1,190,000 Sm3/h
Design flow rate for the final design stage: 2,640,000 Sm/h;
Nominal flow rate for the final design stage: 2,380,000 Sm3/h
Utility, such as instrument air, fuel gas supply, diesel power generation, fire fighting
equipment, condensate tank, heating system;
2 vent stacks
Page 21 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
2.3.2
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The PRT will be installed within the border of the Municipality of Melendugno, approximately 8 km
inland from the seashore. The connection to the SNAM Rete Gas (SRG) network will be at the
fence of the PRT.
2.3.3
The maximum gas flow design rate of TAP Terminal is 10 Bcm/year for initial installed equipment.
The capacity increasing to 20 Bcm/year will be done by adding additional equipment (pumps,
heaters, entire trains etc.). The purpose of the gas metering station is to perform fiscal
measurement of the quantity and quality of gas to be delivered from TAP Terminal to SRG
Network.
The purpose of the terminal inlet section is to receive the incoming gas feed and to act a point of
isolation (and emergency shutdown by means of ESD valves) between the BVS close to the
coast and the Terminal. The inlet facilities also contain a Pig Receiver.
For availability reasons the terminal will be provided in a block design for the different process
units (filter, two electrical heaters and two gas fired boilers, heat exchangers, pressure/flow
control and metering) with 3 identical gas processing units each fed from a single header
immediately downstream of the terminal inlet facilities. Between each process unit the gas will be
again collected in a common header and then again split up to the next process unit.
The first process unit consist of filter separators which remove potential solids and liquids from
the gas stream before the gas enters the conditioning facilities (heater, pressure/flow control
unit). Liquids will be collected in this process unit and further fed into the closed drain system
which leads to a condensate tank.
The heating of the gas to be received shall be done to guarantee the minimum delivery gas
temperature, downstream the pressure reducing system; this operation may be required only in
transport transient condition (packing/depacking operation, start-up etc.) and in case of quick
fluctuation of the pressure in the downstream SRG network. The gas heating will be done by heat
exchangers, based on hot water circulation. Hot water shall be supplied by a closed circuit
production system using electrical heaters and gas fired boilers. The heating system is designed
Page 22 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
to provide in total 8.6 MW duty. The electrical heaters which are designed to provide a duty of
approximately 2 MW, will cover most of the operational heating requirements. The gas fired
boilers, designed for the remaining duty, are intended to cover mainly start-up and abnormal
operation conditions. Thus, local air emissions from heating will be sporadic.
In order to protect downstream equipment and systems against over-pressure (145 barg vs. 75
barg) a pressure/flow control unit controls the flow rate to the downstream network and
simultaneous reduces the pressure to the downstream network pressure. Additionally a HIPPS
(High Integrity Pressure Protection System) shall be installed between pressure/flow control unit
and metering unit. This system consists of two serial mounted independent quick self-closing
valves (one is purely mechanical, the second one is an instrumented safety system), which are
maintained open as long as the downstream pressure is below the set point.
The quantity of the natural gas to Snam Rete network will have to be measured for custody
purposes. This will be done by using ultrasonic flow meters (USM). To fulfil the strict
requirements of custody transfer measurement two identical USM will be installed in serial, in
each meter run to compare the accuracy of the individual meter. The quality of the natural gas to
SRG network will be analyzed for custody purpose by a Gas Analysing Unit.
A fuel gas unit will be provided for the conditioning of the fuel gas to the requirements of the
heating medium. The fuel gas is taken from the outlet side of the pipeline receiving terminal as
the lowest pressure level is expected there. As the fuel gas might be also taken during terminal
shut down from Snam Rete Network the fuel gas stream will be measured with a flow meter
suitable working a measurement required for invoicing.
The closed drain system will be collected in a suitable condensate tank, 10 cubic metres in
volume. The closed drain system will be sized for the final TAP Terminal flow rate (20 Bcm/year),
considering the quantity of liquids discharged from Main Gas filters, and the hypothesis that a
liquid slug can enter the Terminal. The collected fluid shall be removed by road tanker.
For surface/rain water two separate drainage systems are required for the TAP Terminal:
Process areas
Page 23 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Their purpose is to collect and discharge the applicable waste water preferably to the public
waste water network.
Surface water from potential polluted areas will be carried to an oil separator and then into the
sewage system. This sewage system will also be used for the discharge of sanitary waste water.
Instrument and plant air systems are designed to supply approx. 200 Sm3/h, at 12.5 to 15 barg
pressure of dried air to the instrument and plant air distribution. The air compressors are operated
such that the duty compressor auto starts/stops as required.
The depressurization of the station piping/equipment, both in emergency and in maintenance
condition, will happen through two dedicated vent stacks, to be installed in a fenced area within
TAP Terminal. The cold vent stacks are designed to blow down the terminal piping and
equipment. The onshore pipeline section can be depressurised via the PRT (mobile vent
connection at the pig receiving area) or by line packing of the neighbouring sections to avoid local
emission; the offshore pipeline is foreseen, if necessary, to be de-pressurized at the compressor
station in Albania. The vent stacks are designed to blow down the entire volume between the
inlet- and outlet ESD valves from design pressure (145 barg) to 6.9 barg within approximately 15
min. Gas dispersion as well as heat radiation levels have been evaluated as per the requirements
of EN 23251. According to radiation calculations, the vent stack height will be 10 m, with a sterile
area radius of 86 m where a heat load of 5 kW/m could occur.
The main tank of diesel oil with a capacity of 16 m3 is designed to feed diesel fuel to both the
emergency generator daily tank and the firewater emergency pump daily tank.
The diesel oil will be supplied to the TAP Terminal by road tankers.
The potable water system is intended to provide potable water to the buildings expected to be in
the TAP Terminal (such as Workshop/Storage Building and Administration Building), to satisfy
personnel needs.
The system will be fed from existing water network via a dedicated supply line or from a new well
on the station site or nearby.
the various plant areas of the Terminal, for general purposes and to satisfy the
equipment washout needs,
Page 24 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The fire water system will be sized according to Italian standard UNI EN 10779 for industrial
areas (192 m3/hour over a guaranteed period of 2 hours, plus 50 m3 buffer) and has to be
evaluated with local fire brigade. The fire water system will have a stored volume of roughly 450
m. The fire water tank is always on line. Filling of the fire water cistern is a manually controlled
operation.
2.3.4
Mechanical equipment
2.3.4.1
The main piping and fittings of the PRT station are categorized into two main sections. In the inlet
area, the piping and fittings will be designed for a maximum pressure of 145 barg and a
maximum temperature of 65 up to 100C. On the outlet side of the PRT station the piping and
fittings are to be designed for a maximum operating pressure of 75 barg and a maximum
temperature of 65C.
The particular maximum quantity to be transported in the individual piping sections, and a flow
speed of approx. 15 m/s was used as the basis for determining the nominal diameters.
The underground pipes are designed with an earth cover of 1m. The aboveground pipes are laid
close to the ground level, to facilitate the maintenance of the valves and equipment.
The pipes calculation is carried out according to EN 1594 for primarily static stress. Pipe fittings
examined as reducers, tees, flanges and branches are calculated according to the relevant PED
instructions.
2.3.4.2
Piping design
Page 25 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
2.3.4.3
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
All piping to be installed within the station is to be manufactured, tested, and accepted according
to the valid EN 1594 and PED worksheets.
2.3.4.4
After completion of the piping system, a strength test is to be carried out on the components or
individual piping sections.
The strength test is to be performed as hydro-test (water based) according to the EN 1594
worksheet.
After completion of the entire piping system, leak tests are to be carried out with nitrogen.
2.3.4.5
Tests of welds
The welded connections are to be tested according to EN ISO 17635. All welded seams are to be
100% tested according to the TAP / E.ON standard.
All connection seams are to be produced as golden welds. The testing of welded seams is to be
performed using ultrasonic and X-ray tests.
2.3.4.6
Piping and plant components are situated above ground to be protected against external
corrosion by coating, reference is made to section 2.2.6.
Coating of piping laid underground and coatings performed on the construction site are to be
carried out according to national and international guidelines.
2.3.4.7
Equipment and piping will be insulated for the purposes of heat conservation, maintenances
process of stabilized temperatures during atmospheric temperature changes, condensation
presentation and burn presentation of personnel.
The acoustic insulation includes the entire piping system situated above ground, as well as any
fittings or processing equipment.
The implementation of the acoustic insulation is to be carried out on the basis of the noise study.
Page 26 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
2.3.4.8
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
A pipe stress analysis will be accomplished for all new pipe systems. Within the scope of this pipe
stress analysis (PSA) there will be calculated the maximum allowable stress as well for every
single component and the nozzle loads from equipment. Based on the PSA the foundations as
well as support loads are determined. These loads will be transferred to the civil division.
2.3.5
Control system
The TAP control system will permit full operational monitoring and control of the terminal.
Moreover, inside the PRT the control and supervision centre of the entire pipeline will be located.
Detailed operating procedures for the pipeline control system will be developed. These
procedures will be in place ahead of pipeline operation. The operating procedures will typically
address the following:
The pipeline including the entire offshore part between Albania and Italy will be monitored and
controlled 24 hours a day and 365 days a year from a central control room. The monitoring
system is a SCADA System (System Control and Data Acquisition), during operation, leak
detection will be by continuous measurements of pressure and flow rates at the inlet and outlet of
the stations and pipeline. If a leak is detected, an alarm is triggered. To allow internal inspection,
pigging facilities will be installed. The pipeline system has been designed to allow use of
instrumented pigs.
Page 27 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
2.3.6
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
2.3.6.1
SCADA
The Supervisory Control and Data Acquisition System is a backend system that has overall
control of the pipeline and station operation. It is one of the main instance regarding core
business aspects. It comprises a series of control and acquisition functions that include, amongst
others, the
Overall pipeline security including all BVS and tie-in valves of each station
Logging
Simulation
Engineering
Etc.
The SCADA system will be placed in the Supervisory Control Center and be backed up with a
Backup Supervisory Control Center. The BSCC will take over in failed attempts of use the SCC.
SCADA heavily relies on the communication infrastructure alongside the pipeline, the so called
Passive and Active Optical Network (PON/AON).
2.3.6.2
LDS
The Leak Detection System shall eliminate the threat of undetected and unwanted
depressurization of parts or the entire pipeline. It monitors by technical means the status of the
pipeline and warns or acts in case of imminent danger to the pipeline itself or the business (loss
of gas). A mechanism will be implemented relying on sensors along the pipeline to detect
malfunctions. A certain level of automation can be achieved to prevent losses and danger to
human life. The LDS will report to the SCADA system.
2.3.6.3
PON
The Passive Optical Network is the physical transport layer of the communication backbone. It
serves as the carrier for the numerous systems with communication needs. Infrastructure-wise
optical distribution frames will offer the possibility to implement various systems for wide area
network connections. It comprises a number of fiber optical cables, installed along the entire
Page 28 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
pipeline. Spare capacities for future expansions or third party business (like bright/dark fiber
interconnections for telcos or data carriers) can be allocated.
2.3.6.4
AON
The Active Optical Network is the actual communication backbone. It features a setup of different
channels, protocols and capacities to allow flexible interconnection of all relevant systems.
Distances of up to one hundred (100) kilometers per hop can be spanned. By making the AON
available in all stations and block valve stations various services can be delivered to any point in
the ring, like telephony, video conferencing, data access, remote control, etc. It is also able to
deliver redundancy.
2.3.7
2.3.7.1
The Gas Detection System detects gas leakages on the station inside the fuelgas building as well
as in the open range, e.g. gas heaters, metering piping and other above ground piping within the
station limits. One warning and one alarm can be caused by the GDS, the detection of 20% and
40% lower explosion limit in the proximity of its sensors. The GDS reports to the stations ESD
system as well as to the stations DCS and to the SCADA system.
2.3.7.2
FDS
The Fire Detection System detects smoke and fires within the station buildings, inside the fuelgas
building and in the open range, e.g. gas heaters, metering piping and other above ground piping
within the station limits. One warning and one alarm can be caused by the FDS, a fire warning
and a fire alarm. The FDS reports to the stations ESD system as well as to the stations DCS and
to the SCADA system.
2.3.7.3
AVAS
The Audio Visual Alerting System generates an audible and visible alert notification, distributed
across the entire station. It serves as evacuation alert to all personnel in hazardous or potentially
hazardous areas. The AVAS is triggered by the FDS, GDS or manually in case of gas, fire or any
other situation deemed hazardous. Among others it reports into the SCADA system.
Page 29 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
2.3.8
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Security Systems
2.3.8.1
CCTV
The Closed Circuit TeleVision System comprises a set of (nightvision) cameras placed within the
stations fence and spans a surveillance perimeter around each station or object. Virtual fencing
enables the system to automatically display trespassers or intruders violating a certain area
around the station. It can be coupled with the SCADA system to generate alarms while a station
is unmanned.
2.3.8.2
ACS
The Access Control System provides security measures and their administration to the stations
personnel. Electronic badges enable employees or guests to open doors, gates, barriers or gain
access to the SCADA or station control system. Also evacuation purposes are served by tracking
the presence of employees or guests within the station limits. The ACS reports to the SCADA
system.
2.3.9
Power requirements of the pipeline receiving terminal (PRT) will be met by a medium Voltage
electricity transmission line and substation which will connect the installations with medium
voltage network in the station area. For back-up power supply diesel engine driven power
generators are provided.
Transformers
Building installations;
Outdoor lighting.
Page 30 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
PRT station will contain electrical circuits with the following voltages:
24 V DC UPS system.
400V three phase AC system with diesel emergency generator (main power system);
24 V DC UPS system.
The electricity furniture will be done via the public grid and supported by emergency power supply
and backup provisions.
General
The architectural concept was elaborated with the aim to avoid the station being identified as an
industrial plant. Contrary to typical industrial design, the design concept will incorporate design
elements of higher aesthetic quality, making references to traditional residential typologies.
In the Salento area there are very diffused characteristic settlements named Masserie, twostoreys regtangular plan buildings surrounded by productive single storey buildings.Other typical
rural buildings in the region are the Pagghiare and a very well preserved example is within PRT
site.
The main station buildings are arranged to immitate a sort of Masseria settlement with an organic
layout that limits the number of buildings. A sort of dialogue between new main buildings and
existing Pagghiara could be initiated by their positioning. The same dialogic approach will be
followed for materials choice, by alternating plaster and stone for buildings facades.
Page 31 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
This architectural concept involving the stringent selection of materials and colours as well as the
definition of a high standard of workmanship are the basis of the design. The projected and
recessed faade elements which are emphasized by the produced shading are also a central part
of the architectural concept. The intention is to adapt the station design within its surroundings
and provide technically modern, bright workplaces in a comfortable atmosphere. Colours,
materials, shape of buildings and facades will be adapted to the existing rural buildings in the
area.
Page 32 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
2.3.10.2
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Layout
Page 33 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
PRT dimension, with reference to fenced area including the surrounding path, is 12 hectares
approximately. The plant layout could be slightly updated during the next detailed design phases,
but will in any case be inside the construction yard location.
2.3.10.3
The PRT site is a flat and uncultivated field bordered to South-West by a partially asphalted
vicinale road that links the town of Vernole to Calimera road. To North, to West and to East the
site is bordered by olive-tree cultivated fields and to South by an almost flat uncultivated field.
The area is characterized by land division created by a network of dry stone walls. The PRT site
in the West, North and East is also bordered by existing dry stone walls in alternating heights. A
periphery fence will be erected at a suitable distance from the original dry walls. This area could
be used for landscaping with planting and walkways. The surrounding path at the west side of the
station shall be used as a secondary station access simultaneously.
Due to the landscaping a Landscape Impact Mitigation Report will be carried out separately.
2.3.10.4
To lower the visual impact the amount and height of buildings and structures will be minimized.
Roofs were designed as flat roofs, indigenous to this region.
All buildings will be single-storey buildings. Due to the outsourcing of some storage capacity and
maintenance works (e.g. for huge and heavy valves) the Workshop and Storage Building will not
be fitted with a crane, thus the height could be reduced to 5.50 m.
2.3.10.5
Height of buildings
5.5 m
Administration/Building
6.0 m
Boiler House:
8.0 m
Vents/Stacks:
10.0 m
Page 34 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Pipe bridges and cable bridges have been omitted to avoid an industrial image of the plant.
Great care will be taken in the architectural form of the buildings and their facades to ensure the
adaption of the design within its surroundings.
Landscaping and plantation between and in front of the buildings could supplement this aim.
2.3.10.6
Colours
The colours of the station design will be adapted to the surrounding natural colours of the existing
landscape. i.e.:
Colour of the sealing of station area outside of buildings and ,the colour of the vents
are dependent on the results/proposals of the Landscape Impact Mitigation Report
Stacks will be visually integrated in the boiler house volume in order to minimize industrial
characteristics.
Page 35 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
3.1
Offshore Section
The selected route will be obtained by the best satisfaction of the following requirements:
A. to reduce the length (in order to reduce the line pipe quantity);
B. to minimise interference with seabottom scars and other seabed features, i.e. geological
constraints;
C. to have a minimum number of curves;
D. to have a maximum and possibly stable route radius for each curve (the curve stability
could be a special item in areas of potential clayey soils);
E. To minimise the pipeline installation and construction constraints, i.e. obstacles, fishing
areas, dumping areas, UXO areas, archaeological areas;
F. to optimise the crossings with other pipelines and cables, i.e. to use a crossing direction
as close as possible to the normal one with respect to the routes to be crossed, mainly
aiming at reducing the crossing lengths (due to real congested area, it is expected a
governing requirement);
G. to minimise interferences with navigation channels;
H. to identify the widest installation corridor in the most critical and uneven areas;
I. to minimise the number, the lengths and the heights of the free spans in the most
uneven areas. The number of points with local bend concentration shall be minimised
and, if not completely avoided, the relevant stress level has to be minimised;
J. to optimise the pipeline freespan scenario within areas of seabed erosion (it is expected
a typical item in the areas where sandy/sediment soil is expected;
K. to optimise the lay away from the landfall;
L. to comply with any 3rd Party and Authority requirements;
M. to minimise environmental impacts.
3.2
Onshore Section
The following general design criteria have been observed for the selection of the onshore pipeline
route:
Page 36 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
A. to check the route as regards the possibility of restoring the crossed areas, returning
them to the morphological conditions and land use existing before the works, thereby
minimizing the impact on the territory;
B. to transit, as far as possible, in agricultural areas, avoiding crossings in areas affected
by urban and/or industrial development plans;
C. to avoid areas susceptible to hydrogeological instability;
D. to avoid the buffer areas of the springs and wells tapped for drinking water;
E. to avoid, wherever possible, marshlands and peat soil;
F. to reduce to a minimum the restrictions brought about by gas pipeline easements on
private property by using, wherever possible, the easement corridors already
constructed by other pre-existing infrastructure (natural gas pipelines, channels, roads
etc.);
G. to guarantee to the personnel assigned to operation and maintenance of the pipeline
the possibility to access under safe conditions.
The pipeline route has, therefore, been checked and defined after a detailed examination of the
aforementioned aspects and on the basis of the results of on-site inspections and surveys carried
out in the area of interest.
In this sense, analyses and studies have been carried out on all the various situations, of both
natural and anthropic origins, that could create criticalities both for the construction and for the
subsequent management of the work as well as for the environment in which the work is situated,
examining, evaluating and comparing the various possible design solutions from the standpoint of
public health, environmental protection, assembling techniques, and time frames required for
implementation and environmental restoration.
In detail, the route optimisation has been carried out after the completion of the following
operations:
acquisition of the geographical maps in order to classify the lithotypes present along
the chosen route and identify any sensitive areas;
Page 37 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
specialist surveys along the route (special crossings, critical areas etc.).
In particular, the exploration of the route provided the opportunity to carry out the required checks
on:
4.1
The pipeline enters the Italian jurisdiction territory in the middle of the straits of Otranto, about 45
km from the Italian coast (KPof 60.14) and reach the territorial waters around KPof 80.63 of the
offshore pipeline (see Figure 4-1).
The nearshore section starts from approx. KPof 100.40.
At about 95m water depth, the almost straight route is slightly deviated southwest by means of an
3000 m radius, in order to approach the Italian coast following a rectilinear alignment
perpendicular to the shoreline.
The final section of the route, approximately 3.600 m long, is straight and crosses a quite gentle
slope up to reach a narrow calcarenite beach located in an area North of San Foca village
(comune of Melendugno), (see Figure 4-2).
The rectilinear section in the proximity of the coast is needed for the installation of the pipeline
inside the landfall tunnel by means of a pull-in method.
Page 38 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The soil in the nearshore and landfall area is characterized by the presence of calcarenite also
known as dune rock or dune limestone. It is a rock formed by the percolation of water through
a mixture of calcareous shell fragments and quartz sand causing the dissolved lime to cement the
mass together.
Page 39 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Given the features of the affected coastal area, the most appropriate solution is by means of a
trenchless technique. The narrow beaches and a road running along the coast do not offer
sufficient space for an open trench method.
Page 40 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The selection of the landfall microtunnel solution aims at minimizing the impacts of the
construction works on the shore and in the nearshore areas allowing to avoid environmental
sensitive areas (presence on the seabed of sparse vegetation of Posidonia oceanica).
The tunnel entry point, about 617 m far from the shore line, has been located taking into account
the environmental constraints of the area, and is very suitable for the location of the working area.
4.2
Onshore Section
As described in section 4.1 the pipeline landfall will be implemented by means of a microtunnel
underneath the coastline and the Provincial Road SP366 between San Foca and Torre Specchia
Ruggeri. Also a minor asphalt road is crossed by this landfall tunnel. The tie-in with the onshore
pipeline at the end of this tunnel marks the KP 0 of the onshore route and will be located
approximately 600 m off the coast (direction south-west). A block valve station is planned to be
erected just downstream of this tie-in point.
The planned pipeline route passes in the south of a large topographical depression consisting of
a wetland named Palude di Cassano (Cassano Marsh), which is under environmental protection
(Melendugno Municipality Plan).
From the first open-cut crossing with the Strada Comunale S. Viceta at KP 0.6 (south-east of
the wetland), the pipeline route runs parallel to this paved municipal road for approximately 3.5
km. In order to minimise impact on properties and landscape it changes the side of this road
three times more, at KP 1.1, KP 2 and KP 4. The route continues its course mainly through olive
plantations seeking the side of the road where possible, crossing another provincial road, the
Strada provinciale Lecce Melendugno (SP2) at KP 6.5. At a total onshore route length of
approx. 8.2 kilometres, the pipeline reaches the PRT area west of the township of Melendugno.
This terminal station will be situated closed to the border between Melendugno and Vernole,
approximately 1.5 kilometres south of the provincial road connecting these towns.
The examined section does not present particular problems and the morphology of the territory
consists predominantly of rolling plains, slightly undulating locally.
Page 41 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 42 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
5.1
5.1.1
Pipelaying
The offshore pipeline will be installed using a laybarge. Pipe sections are welded together on the
barge and the lengthening pipe string is paid out to the seabed as the barge moves along the
route. Special measures will need to be employed (i.e. concrete mattressing or rock dumping) at
crossings such as cables, within the surveyed corridor. The pipe-lay operation will be performed
on a 24-hour basis to ensure minimal navigational impact on other users and to maximise
efficient use of suitable weather conditions and vessel and equipment time. In addition to the
installation vessel, additional support, supply and guard vessels will be involved with the
operation.
Normal pipe laying activity will consist of the following main operations:
Welding
Pipeline installation
Prior to the start of pipe laying, the roller heights and stinger configuration will be
established in accordance with laying parameters determined as per stress analysis.
At the station no. 1, the pipe joints alignment will be completed using pneumatic lineup clamp.
Page 43 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The root pass will be completed at the 1st station, following which the Lay Barge will
move to a distance equivalent to one pipe joint length. Subsequent hot and fill passes
will be carried at other welding stations.
Welding
Welding at the firing ramp of the Lay Barge will be carried out using mechanized welding system.
The system is completely mechanised and needs the operator intervention only to control the
welding parameters. Once the parameters are carefully fixed, the quality of the weld is highly
consistent.
The welding procedure and welder qualification will be carried out before mobilisation for the
offshore installation work. The qualifications will be performed at selected onshore base.
Qualified welders, NDT Operators and Supervisors will be mobilised to perform the work.
Lay barge Movement
After the above mentioned activities are completed on all work stations, the Lay Barge will be
moved on its anchors for a distance equivalent to one single joint length, so that new joint can be
conveyed to the firing ramp. The movement of the Lay Barge will be achieved by reeving back
the bow mooring cables and simultaneously paying out the stern mooring cables (see Figure
5-2).
After the Lay barge has moved for a distance of one joint length, the operation will be repeated at
each work station. The anchors movement will be periodically performed with assistance at AHT's
and with deployed positioning systems.
Page 44 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The Lay Barge position and heading will be continuously monitored by means of the surface
positioning systems. After each joint move, a fix will take the giving joint number, the heading and
co-ordinates referred to a station on the firing line. The Lay Barge will be kept on its correct
headings so that the pipeline is laid within the required tolerance with respect to the centre line of
the theoretical route.
Pipeline installation
The pipeline installation will be performed by means of a pull-in from offshore lay-barge anchored
at water depth around 40 m. The anchor pattern does not interfere with Posidonia area. A land
based winch, having a pulling capacity of 400 tons, approximately, shall be placed in the working
area, in the proximity of the tunnel shaft.
Page 45 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Offshore lay-barge starts the pipeline current laying as soon as the pipe pulling head reaches the
launch shaft. The onshore pulling facilities will be demobilized after the laying of a sufficiently long
pipe string. The current laying has to be done till the target area located in proximity of Albania.
Page 46 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 47 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
5.1.2
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Pre-dredging works
A trench shall be excavated, with a Back-hoe Dredger (BHD), before the pipeline installation,
between KP of 103.490 and KP 103.381, at a distance of 868m and 977m from the shore line,
respectively. The water depth ranges between 18 and 27m.
The scopes of the trench are:
To prepare an almost strait surface for the pull-in and the laying of the pipeline,
To recover the MTBM in the proximity of the tunnel exit seawards (KPof 103.500).
The BHD is an excavator which is fixed to a pontoon (see Figure 5-4). The excavator is based on
a lowered turntable at the front of the pontoon. Dredging is achieved in the same way a land
based excavator. The BHD has a stick and boom with a bucket mounted on it.
The main components of the BHD consist of:
The hull, contains the engines and the accommodation for the crew
Different types of buckets can be used for different soils. For harder material the smaller bucket
(7m3) will be used which can penetrate in the material with his teeths.
Dredging with a backhoe dredge is not a continuous process, but consists of a cycle of
Operations.
Page 48 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The bucket is dredging into the subsoil by a backward movement of boom and upward movement
of stick and bucket. When the bucket is filled, a further upward movement of the boom and stick
is ensuring sufficient height above the bottom to start swinging.
The material will be discharged sideway of the trench and will be used for the backfilling after the
layng of the pipeline.
5.1.3
Post-trenching works
A post-trenching machine may be utilised to lower the pipe into the soil to an assigned
embedment, and provide a suitable cover.
The trenching systems usually consist in ROV equipment to perform trenching tasks.
These machines utilize predominantly jetting based excavation systems, possibly in combination
with trenching wheels.
5.1.4
Gravel dumping
The offshore Rock dumping is based on the Fall Pipe Method illustrated in the sketch of Figure
5-5. The method is used for placing gravel heaps in deep water, with a good precision, with the
following purposes:
The vessels which perform gravel dumping are usually multi-purpose, in particular equipped with
a flexible fallpipe with an ROV at the lower end for better positioning. Gravel is dumped through
the fallpipe at a controlled rate. The vessel moves along the route under dynamic control. The
ROV is controlled from the ship, and ensure an accurate positioning.
Page 49 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
FALL PIPE
ROV
5.1.5
Marine Spreads
The following main marine vessels and their auxiliary spreads will be employed for the execution
of the above mentioned works:
Backhoe dredger
Motopontoon
Pipelay barge
Supply vessel
Survey vessel
Crew boat
Page 50 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
5.1.6
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Microtunnel
The landfall realization of the gas pipeline on the Italian coast is based on micro-tunnel
technology, see Figure 5-8 for a sketch of the near shore and landfall solution.
The tunnel route on horizontal plane has been defined considering as follows:
Straight path on the horizontal plane, in order to allow an easier pull-in and prevent any
jeopardizing contact between pipeline and lateral tunnel walls during pull-in;
The onshore entry point has been defined in order to cross the Provincial Road SP n.
366, outside the area of hydrogeological constraint (Figure 5-6).
The location of the coast line crossing has been selected to maintain the largest distances
from buildings, particularly from those which can accommodate over 100 people.
The offshore exit point of the micro-tunnel has been defined in order to avoid
environmental sensitive areas. In fact, the offshore exit point of the tunnel was set at least
50m away from the border of this vegetation, on the basis of the results of the sediment
dispersion study.
Page 51 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The tunnel route on vertical plane has been defined considering as follows:
Straight or moderately curved path on the vertical plane. The self-weight of the pipeline
allows it to follow small curvatures of the tunnel. In this case, tunnel-pipeline contact
forces are only related to pipeline self-weight and friction. In case of excessive curvatures,
high local contact forces can be activated, due to pulling loads and pipe stiffness.
In order to obtain a safe cover height, the depth of the tunnel exit point has been set to
3.5m, with an inclination close to the sea bottom slope and set to minimize gravel
dumping in front of the tunnel exit.
The vertical shape of the tunnel to be also defined on the basis of specific analysis of pullin procedure and of pipeline configuration.
Page 52 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The resulting length of the tunnel is 1485m. The selected diameter is equal to 2.4m inside, 3.0m
outside.
A brief description of activities to be performed for micro tunnel realization is reported in the
following:
The Micro-tunnel (MT) is executed with the pipe jacking technique which basically consists of
pushing reinforced concrete pipes, which have been previously transported to the site, into the
soil. The Tunnel Boring Machine (TBM) is lowered into a previously excavated and stable jacking
shaft with the required dimensions. The pipes are pushed by means of a set of hydraulic
cylinders and a TBM that at the same time of pushing is excavating the front. The soil is removed
from the excavation front and transported to the shaft by means of a dedicated circuit.
Page 53 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The sea bottom area in front of the micro-tunnel exit, where the pipeline has to be laid on and
pulled to enter into the tunnel, is prepared with pre-trench and gravel dumping, to avoid any
pipeline stuck and to prevent damages to the coating.
After completion of the MT and the recovery of the machine from the seabed, the pipeline is
pulled in with the help of a winch and sheave system.
Finally the pre-trench is also backfilled. Figure 5-9 shows and overview of the basic layout and
principles of the pipe jacking technique.
Site preparation
Page 54 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Works completion inside the micro-tunnel (recovery of slurry and cables and installation of
FOC conduits)
Pipeline pulling
FOC pulling
Site restoration
5.1.7
Shaft
The jacking shaft, is needed in order to ensure the correct alignment of the Micro-tunnel (Figure
5-9), and is prepared at the starting point of the micro-tunnel.
TBM shall be designed and tailored in consideration of the expected soil/rock conditions; a
hydraulic jacking system pushes the concrete lining pipe continuously (Figure 5-10), a closed
loop slurry system removes the spoil from the rotating drilling shield on the front. Intermediate
jacking system are designed and installed, when length of drilled section requires, in order to
sectionalize the total pushing force.
A lubrication system using special muds, pumped through hoses on the external lining surface, is
foreseen to facilitate the concrete lining insertion and progress in the sub soil.
The bottom of the shaft has to be realized approximately at the mean sea level. Resulting shaft
depth is about 10m.
Figure 5-11 shows joints details used to ensure the tightness of the tunnel.
Page 55 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Area
Code
Saipem SpA
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
steel collar
rubber seal
Page 56 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
5.1.8
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
After completion of micro-tunnel construction, TBM has to be recovered. Before recover, TBM is
not stiffly kept in place, has a significant buoyancy and could be moved by sea waves-currents.
Therefore, the exit location is designed to provide the TBM rests under about 3m of sand, but
recover has to be performed as soon as possible.
The recovery of the drilling head at the exit point requires dredging works. For this purpose, the
final jacking pipes (the first of which are following the drilling head at the beginning of the job) is
dimensioned to ensure the stability of the part of the tunnel without soil cover in the dredged
trench.
Work on the pre-dredged trench will be carried out by a backhoe dredger, Figure 5-12, in order to
prepare exit point of the tunnel, the laying of the pipeline, and to recover the TBM in the proximity
of the tunnel exit, seawards.
Excavated material is temporary displaced on a side of the pipeline route, to be reused in the
following sea bottom works.
Sea bottom is pre-trenched in front of the Micro-tunnel and then embankment realized to gently
get a smooth pipeline configuration, see Figure 5-13, and facilitate the pipeline laying and its
insertion into the tunnel. These activities are performed just after and with the same vessel used
to prepare the tunnel exit point for TBM recovery. The water depth is approximately 20m-25m.
Pipeline and FOC at the exit point and for a certain length, after their installation, are covered by
the excavated material.
Page 57 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Figure 5-13: Schematic of pre-lay preparation work in front of micro-tunnel exit point.
A barge with a crane will be positioned where the Tunnel Boring Machine will be lifted. The
connection of the TBM with the crane will be made by divers. Once recovered, the TBM will be
transported to the support harbour. The following Figure 5-14 shows the sequence of performed
works.
Page 58 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 59 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 60 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Figure 5-14: Sequence of drawings and photos of the works performed for recovery an TBM and
transport it to the near harbour.
Following the removal of the tunnelling equipment from the micro-tunnel, messenger wires are
pre-laid inside the tunnel and a special bell-mouth entry section is installed at the sea end, to
safely guide the pipeline from the dredged trench into the micro-tunnel.
Page 61 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
There is a potential risk that, as the pipeline is pulled into the micro-tunnel, the weight and
dynamic loads may displace the tunnel sections at the entrance leading to a blockage or damage
to the pipeline.
This issue is addressed by welding together the leading sections of tunnel segments (this is a
standard practice), and by providing a bell-mouth structure at the micro-tunnel exit, for guiding
the pipeline into the tunnel. The use of such guiding system allows a smooth transition for the
pipeline pull from the seabed into the tunnel.
The bell-mouth structure will provide the following:
A slope from the dredged trench into the micro-tunnel invert to avoid the pulling head
snagging on the face of the tunnel in both the vertical or horizontal plane.
Sufficient foundation area to avoid the load from the pulling head and pipeline transferring
suddenly to the first segment of the tunnel.
The bell-mouth is a steel structure that is positioned using the same crane barge that will remove
the TBM. The end tunnel segment to be designed to accept the bell-mouth.
Pull-in and installation
Pipeline pull-in inside the micro-tunnel is usually the most challenging activity in landfall
realization. Nevertheless, a wide experience is actually available in the world and no specific
critical issue is anticipated.
The pulling force required for Pipeline pull-in is preliminary calculated summing friction forces
(due to the submerged weight of the pipeline in contact with the sea bottom-tunnel floor) and the
pulling force required to the lay barge to prevent overstressing on the pipeline on the laying span.
A scheme of the pipeline insertion inside the tunnel is shown in Figure 5-15.
The submerged weight of the pipe with 34mm wall thickness is about 503 N/m.
Applying a friction factor of 0.7, the resulting winch force is about 320 tons.
As preliminary value, considering a relevant margin for contingency, 380 tons pulling force are
considered.
Page 62 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Figure 5-15: scheme of the pipeline laying and insertion inside the tunnel, from TAP-CAL00_ERM643-S-TAE-0014 - Environmental and Social Impact Assessment.
In order to prevent relevant contact between pipeline and tunnel wall, and possible damages to
the coatings, plastic collars are placed around the pipeline with a certain spacing, see Figure
5-16. To be noted that a plastic collars should be designed for insertion in the tunnel from the
offshore exit point, where the pipeline has to move on the soil for about 100m before entering into
the tunnel.
Figure 5-16: Pipeline laid in the tunnel. White plastic collars are clearly visible
The connection of the wires with the pulling winch will be realized with a sloped shaft connection.
Figure 5-17 shows the solution designed for TAP project. Other relevant photos of pulling winch
and sloped shaft connection to pulling winch are reported in Figure 5-18, Figure 5-19 and Figure
5-20.
Scheme of the tunnel shaft and sloped ramp with the pulling winch is shown in Figure 5-21.
Page 63 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Figure 5-19: Photo with a relevant example of a sloped shaft connection to the pulling winch
Page 64 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Figure 5-20: Photo with a relevant sloped shaft connection realized at Langeled entry point into the
micro-tunnel
Figure 5-21: Scheme of Micro-tunnel shaft and sloped ramp with pulling winch
The rough procedure for pipeline installation inside the micro-tunnel (see Figure 31) is:
Messenger wires pre-laid inside the tunnel are recover on board of the pipelay vessel.
Main pull wires are inserted and pulled onshore by the winch.
Laybarge starts to weld together linepipes, the winch placed onshore pulls them.
Pipe laying continues until the pipe string is installed in the micro-tunnel and reaches the
micro-tunnel head
Page 65 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Figure 5-22: Main points of the procedure for pipeline installation inside the micro-tunnel
Finally, at the end of pipeline installation, micro-tunnel will be left flooded with sea water.
After the tunnel exit point closure (without sealing), also the entry point will be closed. Venting
pipes will be installed at the entry point, allowing any leaking gas (inside the tunnel) to be
discharged in the air. Notably, a gas methane detector sensor will also be installed for leak
detection.
Yard and facilities
Facilities and features required during micro-tunnel construction include the following:
Work sites;
Page 66 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Pipeline Protection;
Access Roads.
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The major plant items needed are bulldozers, heavy excavators, spoil removal trucks, large
heavy-lift cranes, standby generators, micro-tunnel boring machine, excavators, rock breakers,
etc.
The main equipment used for construction is described in the following, particularly the yacking
pit and the pulling spread arrangement.
A temporary worksite is needed for the construction of the offshore micro-tunnel and occupy an
area of about 26,000m2 (see Figure 5-24). The launch shaft is to be located here. The temporary
worksite will also be used for placing the pre-commissioning spread of the offshore pipeline.
A total of approximately 8000 m3 of soil will be temporary set aside in order to prepare the
working area. This material will be redistributed on the area after the works completion.
Page 67 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Figure 5-24: Schematic of equipment in the Construction yard and Stocking area.
5.1.9
Jacking pit
Secant piles are a common and fast technique to construct the jacking shaft. Since piles are to
be inserted in the solid rock, exaction and concrete floor will be executed in dry conditions.
The axis of the micro-tunnel to be positioned in the most favourable position in terms of
geological conditions. The pit floor to be sloped with the same angle of the micro-tunnel entry.
An anchoring arrangement is constructed behind the winch location.
Page 68 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The Pull-in of the 36 gas pipeline inside the tunnel is performed using a winch, as in the scheme
reported in Figure 5-25.
Slurry treatment
The excavated soil will be mixed with slurry (water) in the TBM extraction chamber. Large slurry
pumps in the tunnel section behind the TBM will transport the soil mud mixture through slurry
pipes to the departure site. The mud will be de-sanded in a recycling plant. The cleaned slurry
will be reversed to the front.
The efficiency of the soil separation plant will be of major importance.
Indeed, once the water in the tunnel circuit will get saturated with fine sand or clay particles, the
slurry will not be able to take any soil from the machine front anymore. The front pressure will
increase and the jacking performance will drop significantly. High front pressures could produce
cracks in the overburden which could lead into bentonite escape.
Once the slurry will have been saturated with silt/clay, it will be replaced by water. The saturated
slurry will be removed from the slurry containers and disposed into the storage pool for slurry.
While the tunnelling operations continue with water, the dewatering installation treats the
saturated slurry.
In a first phase, some polymers will be added to the slurry in order to make small particles bond
together.
The flocculated slurry will then enter into a band filter press.
The polymer injection will be fully controlled. Dosage, polymer adaptation and monitoring will be
followed during the complete tunnelling operations.
The band filter press basically consists of an upper and a lower permeable belt. Both belts turn at
the same speed. The lower belt will transport the slurry from one side of the machine to the other
side. During the transport cycle, the space between the two belts will progressively be reduced to
squeeze out the water. The dewatered silt/clay will fall on a conveyer belt and will come out of the
machine. The soil separated can then be loaded on trucks.
Page 69 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The estimated water that will be utilized for the offshore microtunnel can be estimated in 10,000
cubic meter.
Cleaning and Hydro-testing
The Hydrostatic testing operation will commence upon successful completion and acceptance of
flooding, cleaning and gauging operation. Hydrostatic testing will be performed as per DNV OSF101.
Seawater injected during hydro-test shall also be provided by the water-winning system and
therefore shall have been subjected to a filtration process with the specification at 50 particle
size and UV sterilised accordingly.
Pressurisation water shall be supplied via the same water-winning system used for flooding,
cleaning and gauging and post hydrotest water shall be discharged using the dumpline facility
installed in Albania.
Pressurisation of the pipeline shall be conducted at a rate of 0.5barg/min up to 95% of test
pressure. At this stage and in accordance with DNV-OS-101 (2012) final pressurisation to the
strength test pressure shall be performed at a lower pressurisation rate.
On reaching test pressure, stabilisation of the test medium shall be required prior to starting the
24hr hold period. It is estimated that stabilisation may take up to two days with particular
reference to the rate of heat transfer across the pipe wall and the difference between filling water
and deepwater sea temperatures. Therefore the overall pipeline hydrotest duration including
depressurisation is calculated to take approximately five days.
The sea water volume that will be discharged during cleaning and hydotest of the whole pipeline
can be estimated in 130,000 cubic meter.
De-Watering
The pipeline dewatering pig train will be launched from the Italian landfall site and shall
incorporate slugs of fresh water to desalinate the pipeline. The pig train design shall also include
dry compressed air slugs to remove residual water. The fresh water slugs will be stored in
multiple storage bladders and these will be positioned on a prepared stone free area with a slight
elevation.
The fresh water pumping equipment shall be flushed prior to use with the first batch of fresh
water being injected behind the first pig in the dewatering pig train.
The sea water volume that will be discharged during de-watering of the whole pipeline can be
estimated in 65,000 cubic meter.
Page 70 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Air-Drying
After completion of dewatering operations the receiver shall be removed at the Albania pipeline
end in order to optimise the pipeline drying operation. The termination flange shall be fully open.
Low pressure dry air will be injected from Italy with the dew-point being monitored at both ends.
The pipeline shall be deemed dry if no significant dew point deterioration is incurred.
Page 71 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
5.2
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Onshore Section
The operating phases involved in the construction of the pipeline are described briefly in the
subsections below.
A single storage and work site is foreseen mainly as stock and bending yard for the line pipes.
The location is at the end of the route at KP 8.2 in a large arable land patch area where also the
receiving terminal will be built up. It will be used as the only stockyard for the onshore pipeline in
Italy and will be easily accessible through the existing road network (SP366, SP245 and
connected asphalt roads).
No accommodation for workers is considered at the aforementioned site. The whole extent of the
land parcels affected presumably amounts to
The area of 21 hectare assigned for pipeline construction includes only partly (up to the extent of
the ROW) the temporary worksite which is foreseen for the construction of the landfall
microtunnel which is part of the offshore pipeline.
The construction period for the pipeline is estimated with 6 months and for the terminal 18
months. Site preparation (clearing of topsoil and levelling works) should be done in advance to
this period. The completion of the landscaping and road construction is considered to follow
afterwards.
5.2.1
Pipeline installation
The trench digging operations and pipeline assembly require the opening of a working strip.
The overall width of this working strip will be limited to 26 m which is good engineering practice in
cultivated areas, one side approx. 11 m wide for the disposal of trench excavated material while
the other one side, a strip approx. 15 m wide to allow the pipeline assembling and for the
vehicles/machinery transit required for the pipeline construction.
Before opening the working strip, the top soil layer will be set aside at the edge of the strip, for reuse during the restoration phase.
Page 72 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
At stretches which are limited to several hundred metres or connected to access roads, the
working strip can be reduced to 22 metres due to technical reasons.
Page 73 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
The trench will be cut by excavators and or adequate earth moving machinery suitable for the
morphological and lithological characteristics of the ground to be crossed (excavators in loose
ground, hydraulic hammers in rock). A pre-defined sand bedding will be applied to the trench
bottom, when the required conditions are not reached (rocky area).
The pipes will be bent where required acc. to the trench dimensions and joined together using a
motor-driven welding machine by a continuous wire arc welding process. The pipe joining will be
made by connecting and welding several pipes so that, a pipe string is formed aside the trench.
After having performed the anti-corrosion coating check by means of holiday detector to ensure
that the coating is perfectly intact, the pipe string section will be lifted and laid down into the
trench by sidebooms (especially equipped bulldozers).
The laid pipeline will be buried with a pre-defined padding first, composed alike the bedding of
selected material, and then will be backfilled with trench excavation material. Generally, it is
strived through insitu preparation process that the quality of the bedding material is achieved so
Page 74 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
that all of the excavated material is re-used for the backfilling. Finally the top soil will be spread
and the whole working strip will be re-instated.
5.2.2
Crossings
The crossings are implemented as small stand alone worksites that come into operation as the
line progresses. The crossing installation methods are different and can generally be carried out
by trenchless (tunneling or boring) or open-cut techniques, with or without casing pipe. The
choice of the installation system depends on a number of factors, including: laying depth,
presence of water or rock, intensity of traffic, authority requirements, etc.
There is three envisaged trenchless crossings, two of which are actually part of the approximately
1.5 km landfall tunnel as described under the offshore section.
5.2.3
Hydro-test
Following the pipeline construction and backfill, a hydro-test shall be performed, by filling and
pressurising the line with water at a pressure of presumably 1.3 times the maximum pipeline
operating pressure for a period of 48 hours (according to DM 17/04/2008). Hydro-test is usually
carried out on separated pipeline sections dependant on the work progress at road crossings or
special sections. The approximate volume of water required for the hydro-test of the onshore
pipeline is 4,900 cubic metres.
Page 75 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
CONSTRUCTION TIMING
The following Table 6-1 provides a summary of the expected timescales for the construction of
the major project Phases.
Construction site and work sites
1 month
Landfall micro-tunnel
9 months
Offshore pipeline
2 months
Pre-trench excavation
2 months
Pre-trench backfilling
1 month
1 month
18 months
6 months
6 to 12 months
5 months
The whole project will be constructed within approximately three years, in respect of the touristic
season (from June to September) the activities on the coast will be suspended.
Page 76 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Photo no. 01
KP 0.0
View to East
Maquis crossed by landfall tunnel
Photo no. 02
KP 0.0
View to West
Area of microtunnel entry point
inside leisure area
Page 77 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Photo no. 03
KP 0.3
View to North
Pipeline route leaving the leisure
area
Photo no. 04
KP 0.6
View to West
Asphalt road and dry stone wall
crossing near an existing water
treatment plant
Photo no. 05
KP 1.1
View to West
Asphalt road crossing in densely
vegetated area
Page 78 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Photo no. 06
KP 2.0
View to West
Asphalt road and dry stone wall
crossing
Photo no. 07
KP 3.8
View to East
Young olive plantations
Photo no. 08
KP 3.9
View to South-West
Approaching asphalt road and dry
stone wall crossing
Page 79 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Photo no. 09
KP 4.6
View to South
Asphalt road and stone wall
crossing
Photo no. 10
KP 4.6
View to West
Typical olive orchard on the route
Photo no. 11
KP 4.9
View to North-East
Pagghiara hidden in the olive
trees in vicinity to the route
Page 80 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Photo no. 12
KP 5.3
View to West
Pagghiara hidden in the olive
trees in vicinity to the route
Photo no. 13
KP 5.6
View to North
Asphalt road crossing
Photo no. 14
KP 5.6
View to North-West
Pagghiara hidden in the olive
trees in vicinity to the route
Page 81 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Photo no. 15
KP 5.8
View to West
Asphalt road crossing
Photo no. 16
KP 5.9
View to South
Area with olive trees in the vicinity
to the route (number and proximity
to the pipeline to be verified)
Photo no. 17
KP 6.4
View to East
Provincial road crossing
(trenchless)
Page 82 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Photo no. 18
KP 7.5
View to West
Asphalt road crossing
Photo no. 19
KP 7.6
View to South
Pagghiara in vicinity to the route
Photo no. 20
KP 8.2
View to North
Area for Pipeline receiving terminal
Page 83 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
B2 PIPELINE TYPICALS
CPL00-ENT-100-F-DFT-0011--Working Strip
IPL00-ENT-100-F-DFT-0001--Typical Tench for 36 inch Pipeline
CPL00-ENT-125-F-DFT-0003--Pipeline Crossing with underground Obstacles
CPL00-ENT-125-F-DFT-0004--Minor Road Crossing (open-cut)
CPL00-ENT-125-F-DFT-0005--Major Road Crossing with casing pipe (thrust boring)
CPL00-ENT-125-F-DFT-0006--Pipeline Crossings with Future Road (open cut)
CPL00-ENT-125-F-DFT-0012--Concrete Slab Protection for dirt roads
CPL00-ENT-109-K-DFT-0008--Pipeline Marker Post
CBV00-ENT-100-F-DFT-0016Layout of the Block Valve Station
B3 STATION LAYOUT
IPR01-ENT-000-P-DPP-0001-- Pipeline Receiving Terminal Flow Diagram
IPR01-ENT-000-Q-DQA-0006--Layout Pipeline Receiving Terminal
Doc.Type
Page 84 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 85 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 86 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 87 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 88 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 89 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 90 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 91 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 92 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 93 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 94 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 95 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 96 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00
Page 97 di 97
E.ON New Build & Technology GmbH
Project Title:
Document Title:
Saipem SpA
Area
Code
Comp.
Code
System
Code
Disc.
Code
Doc.Type
Ser.
No.
IAL00-SPF-000-A-TRE-0001
Rev.: 00