Appendix 4.2 - Draft Construction Method Statement
Appendix 4.2 - Draft Construction Method Statement
Appendix 4.2 - Draft Construction Method Statement
Introduction
This document is a draft Construction Method Statement (CMS) for the proposed
Mynydd y Gwair Wind Farm.
This draft CMS deals with the construction and post-construction restoration of the
wind farm in compliance with the terms of the planning permission and its attendant
planning conditions.
This document supplements the Environmental Impact Assessment which was carried
out and reported in the Environmental Statement that forms part of the planning
application for the Mynydd y Gwair Wind Farm.
It is good engineering practice for the chosen contractor to decide how best to
undertake each work activity based on their personal experience and the associated
risks. This is in line with the requirements of the Construction (Design and
Management) Regulations 2007 (CDM 2007) to ensure good project planning and
thereby good environmental and health and safety practices. The methods and
processes to avoid or reduce environmental impacts provided in this document are
therefore for guidance only and may be amended prior to construction. However, this
draft CMS will form the basis of the final document which will be agreed with the local
planning authority prior to the commencement of construction activities.
2.
Project Description
The proposed Mynydd y Gwair Wind Farm site lies approximately 15km north of the
centre of Swansea. The site is located on the south facing slopes of Mynydd y Gwair
and Pentwyn Mawr, on common land which rises to 330m above sea level. The
majority of the site is moorland, primarily used for the grazing of sheep, cattle and
horses.
The wind farm is located between the town of Ammanford to the northwest,
Pontardawe to the east, Felindre to the south and Pontarddulais to the west. A
number of dispersed farms and dwellings are located in the vicinity of the wind farm,
outside of the site boundary.
Access to the site will be afforded via the A48 in Pontardulais, from where a track will
be constructed passing across Gopa Hill, Mynydd Pysgodlyn and Mynydd Garn Fach,
before entering the site from the south.
The wind farm will comprise:
16 wind turbines up to 127 metres tip height;
crane hardstanding areas at each turbine;
a single anemometer mast;
an access track from the A48 to site, incorporating improvements to existing
highways;
internal tracks between the turbines;
associated cabling between turbines running alongside the path of the access
tracks;
an electrical substation and control building, located to the north west corner
of the site, and associated grid connection; and
an area of 50m x 50m to act as a temporary construction compound and laydown area (to be reinstated after construction).
3.
Aspects of the construction works that could potentially affect the environment of the
site and for which management practices have been developed are detailed in the
sections below.
Purpose
To establish roles, responsibilities, authorities and accountabilities during the
construction phase.
Procedure
RWE npower renewables (RWE NRL) will nominate a Project Manager for the site
whose responsibilities will include overall environmental management of the site on
behalf of RWE NRL and the land-owners.
All works will be carried out in accordance with the planning consent, planning
conditions attached to the planning consent, and all applicable legislation. The
Contractor will carefully plan the works, and those of his sub-contractors, and provide
details in a Health and Safety Plan (as required under CDM 2007).
All contractors and sub-contractors will be required to adhere to the CMS in its finally
approved form.
Task specific method statements for individual works will be prepared where
necessary and may employ specialist resources to provide advice in preparing and
supervision work methods. This may include ecologists, hydrologists etc.
RWE NRL will appoint a Site Manager who will monitor the day-to-day management of
the site, including legal and environmental responsibilities, site health and safety, and
to ensure adherence to this CMS and all approved method statements and the
planning conditions.
RWE NRL will also appoint a suitably qualified Project Ecologist to assist the Site
Manager, who will identify any sensitivities and set up any monitoring regimes
required. The Project Ecologist will have a visiting role and will be on site during any
particularly environmentally sensitive operations and when monitoring is required.
RWE NRL will appoint a suitably qualified hydrologist to assist the Site Manager in
carrying out further surveys, construction methods, any required mitigations and
monitoring processes. The hydrologist will have a visiting role and will be on site
during any particularly environmentally sensitive operations and when monitoring is
required.
RWE NRL will appoint a suitably qualified Project Archaeologist to undertake
responsibilities associated with an agreed watching brief.
Prior to the commencement of specific construction activities, the Contractors Method
Statements will be reviewed by the Project Manager, the Site Manager and the
Environmental Team (Project Ecologist, Archaeologist and Hydrologist) to ensure that
all operations comply with the best environmental practice and the provisions of the
CMS. Once construction commences the Contractor will have to adhere to these
Method Statements. Should any unexpected environmental issues arise during
construction the Contractor will also be briefed to immediately report them to the Site
Management Team so that suitable measures can be implemented.
4.
Pre-Construction
Prior to the commencement of construction works on site, RWE NRL will liaise with the
local planning authority and any relevant statutory consultees to discharge all precommencement conditions.
Appropriate protected species surveys will be undertaken in accordance with the
recommendations below and any relevant planning conditions or legal requirements.
Where necessary, mitigation measures shall be agreed with the local planning
authority to accommodate any protected species found on site. Detailed site
investigations are also likely to be required in order to complete the design of the
turbine foundations.
Micro-siting of turbine locations and the associated access tracks and infrastructure
(including crane pad locations and temporary working areas including areas for
storage of top soil) will take place, taking into account any protected species
mitigation, ground conditions and localised ecological, topographical and hydrological
considerations, including in particular the objective to avoid peat deposits in excess of
300mm in depth.
The two areas of archaeological interest requiring fencing would be identified and the
fencing erected before construction activities begin on site.
Detailed arrangements for the induction of construction staff will be drawn up in
consultation with the Site Ecologist, Site Hydrologist and Site Archaeologist.
5.
Ecological Sensitivity
Purpose
To ensure the protection of important nature conservation resources, including
protected species and other notable ecological features on the wind farm site.
Specialist environmental support will be sought as required.
All site workers will be inducted in relation to the ecological requirements and
sensitivities on the site, including emergency procedures and any exclusion zones,
prior to being permitted to undertake any work on site.
Preliminary vegetation clearance measures to manage the risk to protected species
(nesting birds and reptiles) will be undertaken in consultation with the Site Ecologist
and in accordance with the strategy set out in the ES.
5.1.
Protected Species
Site workers will also follow an emergency procedure if Otter or Water Vole are
encountered during the course of the works and work will be stopped where
necessary.
5.1.3. Badgers
Purpose
To ensure the protection of the badgers on the site in accordance with legal
requirements and to have systems in place to be able to react to any changes in
badger activity that affect construction activities.
Procedure
Contractors will be fully briefed and inducted on the legal requirements relating to
badgers and their setts and will be shown the locations of all known badger setts on
the site. They will also be advised of the guidance stand-off distances to be adopted
when using different types of machinery or where undertaking any other potentially
disturbing activities.
A survey will be carried-out prior to construction to identify the presence of badgers
or badger activity within the development boundary and in particular close to
construction working areas. Relevant licences will be obtained if required. Should any
presence/activity be identified, appropriate mitigation will be implemented such as
fencing and/or demarcation. Micrositing allowances will be utilised to ensure that
infrastructure does not cause unacceptable impacts.
Should workings be required in the vicinity of badgers/badger setts, appropriate
method statements will be developed and implemented, where necessary in
accordance with licenses.
Contractors working on deep excavations will be issued with a standard procedure to
be employed daily for minimising entrapment hazard (e.g. installation of escape
planks in excavations left uncovered overnight).
5.1.4. Reptiles
Purpose
To ensure the protection of reptile species on the wind farm site in accordance with
the requirements of the Wildlife and Countryside Act 1981 (as amended).
Procedure
Prior to commencement of the construction activities the working areas will be subject
to habitat manipulation to discourage their use by reptiles and encourage
displacement. Where this is unavoidable, an inspection by an Ecologist will be
undertaken of the affected area to ascertain its potential to harbour reptiles and
advice on any additional mitigation necessary to ensure legal compliance.
5.2.
Important Habitats
5.2.2.
Purpose
To restrict impacts on other Biodiversity Action Plan habitats on site and to promote
their rapid recovery after disturbance.
Procedure
The objective whenever handling mineral soils on the site, including those with a very
thin (e.g. 20mm or less) peaty topsoil layer will be to minimise handling, maintain
moisture content and prevent mixing of horizons.
The standard protocol for storage of non-peat soils will be storage as close to source
as possible onto a geotextile membrane in stockpiles no higher than 1.5m. Darker
(humose) horizons may need to be stripped separately with the surface vegetation
and stored under transparent polythene to maintain wetness and reduce mobilisation
of carbon and other constituents. Storage areas will be distributed in flattest areas as
far away as possible from watercourses or drains. Silt traps will be used to capture
any suspended solids generated. Any soil storage areas may first need to be checked
for nesting birds or reptiles (see 5.1.2 and 5.1.4 above).
6.
Construction Methods
6.1.
Purpose
To identify the most suitable methods for installation of the site construction
compound, storage, plant re-fuelling and maintenance areas.
Procedure
The intended location of the temporary construction compound is shown on layout
drawing Figure 1.2 within the Environmental Statement. The construction compound
will occupy an area of approximately 50m x 50m and is to be located to the south of
turbine number 7. The compound will comprise:
Following on from any works required in respect of nesting birds and/or reptiles, a
temporary fence will be erected around the construction compound (approximately 2
metres in height).
The construction compound area will be identified by surveyors and clearly pegged.
Surface soils will be excavated and set aside in storage bunds for reinstatement on
completion of the project. These soils will be separated and stored for re-use
following best practice guidelines as discussed above. Any existing drainage lines or
paths will be diverted around the extent of the compound, if necessary. Unsuitable
soils will be excavated and stockpiled until a suitable formation is reached. The
proposed construction compound area is situated on a shallow slope, such that cutand-fill techniques can simply be employed to facilitate a level surface to the
compound. As with the access tracks, a geotextile will be placed over the area and
crushed stone will be laid and compacted in layers to provide an adequate smooth
surface. Geogrids may be required to ensure optimal weight distribution and the area
will be graded to provide drainage falls to adjacent ditches.
Welfare facilities will be provided in accordance with the Construction (Design and
Management) Regulations 2007. Facilities for waste management, refuelling, power,
water supply and chemical storage will be provided. All welfare facilities will be
provided for the duration of the contract and until the permanent facilities are
completed within the substation compound.
Welfare units will be self contained, typically housing its own under unit storage tank.
The tanks will be regularly emptied by a registered waste disposal contractor.
Fuels delivered to site will be stored within a bowser bunded to 110% capacity
strategically located within the construction compound. Wherever practical, all
refuelling of plant will be undertaken within a designated location in the compound by
trained operatives. The operatives will be trained on the safe procedure for refuelling
including emergency procedures for dealing with spillages. Emergency equipment
such as spill kits will be readily available.
Site security will be on site 24 hours a day to protect the works from theft or
vandalism. Lighting will be used around the compound to assist with the overall
security of the facilities.
Reinstatement
Following completion of the works and commissioning of the turbines, the site
compound will be removed and the land returned to its original condition. Material
used to construct the compound will be excavated and used within the site track
network to make good any potholes. Stockpiled subsoil and topsoil will then be
replaced to replicate the original ground conditions and contours. An appropriate
grass seed mix may be applied to quickly restore exposed areas and thereby prevent
erosion of the topsoil.
6.2.
Purpose
The proposed electrical substation and control building will occupy an area of
approximately 60m by 60m in the north west corner of the site (outwith the existing
common land). Construction needs to be undertaken so as to minimise the impact on
the ecology in the area.
Procedure
The access track will be constructed across the site and down to the substation area
to provide access to the substation construction area. All significant deliveries made
from the south will be brought across the site rather than using the local roads.
The works will include:
-
As with the site construction compound, the area will be surveyed and pegged out.
The topsoil and subsoil will then be stripped and separately stockpiled adjacent to the
works for later reinstatement. The subsoils will be used to create the level area
required for the electrical switchgear and the control building.
It is likely that a separate but smaller set of cabins will be required at the substation
for the electrical contractors. This will involve the same procedures as set out under
Section 6.1 of this document, but on a much smaller scale. All materials and
equipment will be stored in secure cabins within this area.
The electrical switchgear and transformer will be anchored on a number of concrete
plinths within the substation compound. These plinths will be constructed by
excavating the required area, installing the steel reinforcement and then pouring the
ready mix concrete, in a similar manner to the turbine foundations. Concrete may
also be used to construct the substation roads with intermediate areas then covered
with a layer of graded aggregate laid over a geotextile layer.
The control building will be founded on a reinforced concrete foundation and
constructed from blockwork with a pitched roof.
To ensure health and safety requirements the whole compound will be fenced on
completion of the earthworks with a 2.4m high palisade fence with high security
gates.
The connection to the grid will be undertaken by Western Power Distribution and will
be subject to a separate construction method statement. However, it is anticipated
that the methodologies employed will be similar to those included within this
document.
Reinstatement
A detailed reinstatement plan will be produced and agreed for the substation area
prior to the commencement of these works. Earthworks and landscaping will be used
to minimise the visual impact of the substation.
Stripped topsoil will be spread over exposed areas adjacent to the substation on
completion of the earthworks. Planting in accordance with the approved plan will be
undertaken during the earliest planting season to provide screening as soon as
possible.
6.3.
Purpose
To construct the site tracks with minimal visual impact or disturbance to vegetation.
Access tracks are required throughout the site for the movement of materials
including the delivery of the turbine components to their proposed locations, and for
maintenance and operation of the wind farm. Excavation, construction and
maintenance of access tracks to the wind turbines (WTGs) will be undertaken to
minimise disturbance to vegetation and hydrology at the site. The tracks need to be
sufficient to allow the delivery of large and heavy turbine components and
transformers.
Procedure
The tracks have undergone a preliminary 3D design iteration to ensure the track
geometry can be achieved within the works boundary. The computer aided design
also ensured that the design could be achieved whilst balancing the cut and fill of the
earthworks where required.
The tracks within the wind farm site will take the routes set out in the Environmental
Statement, subject to any local variations in response to local ecological or
hydrological sensitivities. The tracks will be surfaced and designed to standards that
ensure control of water and integrity of the track surface.
The design requirements for the tracks will depend on the chosen turbine type but are
likely to require a track capable of carrying vehicles of up to 145t and up to 55m long
with axle weights of up to 20t. Geometric parameters for the site tracks are based:
The track width will be increased proportionately at bends and junctions. Passing
places have been limited to the hardstanding areas and at strategic points along the
initial access track on to site.
a) Cut Type Design
Cut type track design will be used where geographical / topographical conditions
require. The circumstances where Cut type design will be used will be determined
by the Project Manager and such operations will be designed to achieve a good
balance where possible and to cause the minimum amount of impact to the area.
Following on from any works required under sections 5.1.2 and 5.1.4 above in respect
of nesting birds and/or reptiles, the track area will be surveyed and pegged out prior
to being cleared of all vegetation. The track width will be stripped of topsoil and
subsoils and these will be separately stockpiled in the vicinity for eventual
reinstatement in accordance with the best practice methods set out at section 5.2
above. Material removed from small cuttings will be hauled to fill areas where
suitable to balance the cut and fill. The track will be constructed with crushed graded
rock with chemical composition appropriate to the site conditions, laid and compacted
in layers to form the required profile. Selected smaller graded rock will be imported
to finish off the tracks to the required profiles and to provide a smooth, bound and
impermeable running surface. The stripped topsoil will be re-used to dress the slopes
and verges of the track.
The depth of stone will be determined during the detailed design and will depend on
the underlying ground conditions. Typically the track depth will be between 300 and
500mm deep laid on a geo-textile membrane.
Sections of track identified through softer or peaty ground may be moved to drier,
firmer ground, within the 30m micro-siting allowance. Alternatively, trial pitting may
be used to establish the depth to suitable formation. If this is not possible a floating
road design may be used.
b) Floating Road Type Design
A floating road design will be required where the track crosses peaty or softer
ground conditions. Depending on the strength and depth of the soft material it may
be preferable to build a floating road rather than the cut type track previously
described.
As the track will incur limited disturbance during the operational phase, a partial
covering of grass, moss and lichen will form reducing the visual effect of the track.
Depending upon the level of usage following construction, after 2 to 3 growing
seasons the tracks will have developed a reasonable vegetation cover concentrated at
the edges and centre of the track.
Safety considerations during operation of the wind farm mean that it is not feasible to
develop full vegetation cover over the width of the track.
6.4.
Crane Hardstandings
Description
Crane hardstandings are required to provide a suitably robust and level area, upon
which cranes are used to lift turbine components into place.
Procedure
The location of the crane hardstandings has been designed to make best use of the
existing topography (minimising cut and fill requirements), prevailing wind conditions
(to enable safe lifting) and likely erection procedure. As with access tracks, topsoil
(including peaty horizons) and subsoil will be excavated and stored in separate bunds
for later reinstatement.
The area adjacent to each turbine will be surveyed and set out to the required
dimensions (typically a single rectangular pad up to 50m by 25m) and excavated to a
suitable formation. Plate bearing tests will be conducted at regular intervals across
the excavation to prove the bearing capacity of the underlying strata. If unsuitable,
geogrids may be used to facilitate better distribution of weight. A geotextile will be
laid and coarse rock fill will then be placed and compacted in layers. The final surface
will be formed from selected smaller granular material and trimmed to allow surface
water run-off, to either drainage ditches or soakaways. The fill materials will be of a
type consistent with ensuring there is no scope for significant changes in soil and
water chemistry in the locality of the construction areas.
Crane hardstandings will be formed as the construction of site tracks progress.
However the pads may be formed initially to provide lay-down areas for materials
associated with WTG foundation materials and finalised closer to the lifting operations,
once the foundation has been cast. Where relevant, the active top layer of peat will be
carefully removed and stacked close to the excavation for re-use in restoration.
Excess peat will be used to form track-side batters.
Where turbine bases and associated hardstandings are located on shallow (<300mm)
peat this will be followed by excavation of the peat/underlying mineral soils to
formation depth. The peat turf and underlying peat will be stored in low (max 1.5m)
mounds outwith the working area. Where glacial till is excavated, material excess to
backfilling requirements may be utilised for crane hard standing at the wind turbine
location or in the access track construction programme. These materials will be
temporarily stored within the working area.
Reinstatement
On completion of the lifting operations and following successful commissioning of the
turbine, the crane hardstandings will be left in situ for future turbine maintenance.
However, the topsoil will be spread over the hardstandings and the areas left to
revegetate. If necessary, the areas will be seeded to prevent the erosion of the
topsoil layer.
6.5.
Turbine Foundations
Description
Reinforced concrete foundations are required to support the large turbine structures.
The bases need to be constructed with minimal disturbance to the vegetation and
surrounding hydrology.
Procedure
The position of each WTG will be surveyed and set out to the agreed co-ordinates
(subject to 30m micrositing allowance). The extent of the foundation will be marked
on the ground and an allowance made for working space and shuttering. Any
evidence of surface water flows which would convey surface water towards the area
will be diverted in advance of any excavations. The required area will be stripped of
topsoil and subsoil and these stockpiled separately for reinstatement. The area will
be excavated to a suitable formation and cleared of all loose, fractured rock.
Drainage ditches will be excavated around the perimeter to keep the excavation dry.
An outfall ditch will be created where possible or a sump formed for pumping out of
the excavations. Batters will be formed on all sides where appropriate and in cases
where these are adjacent to site tracks, bunds will be formed along the top edge. In
some instances, it may be the case that site tracks need to be widened to allow safe
passage of construction plant and vehicles. Alternatively, the Contractor may decide
to provide temporary support to the excavated face.
A plate bearing test will be carried out to prove the bearing capacity of the strata
below and work only allowed to continue on a successful result. Failure of the test will
result in either further excavation or placement of rock fill and retesting of the bearing
capacity.
Blinding concrete will be placed and levelled to the required dimensions and level and
finished with a vibrating power screed. The base will be set out to the required
dimensions and offered for inspection prior to steel fixing.
Reinforcing steel bars will be delivered to site and stored adjacent to the excavation.
A telehandler will deposit the largest bundles of bars onto the blinding concrete to cut
down on manual handling. Steel fixers form the reinforcement cage to the required
dimensions and levels as indicated on the design drawings and schedules. All steel
will be adequately supported on chairs, cover blocks and tied securely. The area will
be cleared of all debris prior to edge formwork being erected and secured.
All ducts, earth connectors, drainage pipes and bolt assemblies will be inserted in
accordance with the drawings.
Edge formwork will be pre-fabricated and be sufficiently robust for repeated use
across the site. The formwork will be positioned to the required dimensions and
adequately shored. Height checks will be set where necessary and on completion the
base will be offered for inspection in advance of the concrete pour.
Prior to the concrete pour, accurate local weather forecasts will be obtained and
checked for temperature, wind speed and general outlook. The decision to pour will be
based on this information. This data will also be used to determine the curing agents
and protection measured required for the pour.
The concrete will be delivered to the turbine locations in truck mounted mixers and
discharged through a mobile concrete pump into the formwork until the required
profile and level is achieved. Vibrating pokers will be used to ensure the concrete is
adequately compacted. Concrete deliveries will be slump tested and cubes taken at
the required frequency for later testing. The exposed faces will be finished and an
appropriate curing agent applied in accordance with the manufacturers
recommendations. Covers will be applied when necessary to protect from hot or cold
weather.
Formwork will be carefully removed on satisfactory curing (no earlier than 24 hours)
and care taken so as not damage any ducts or inserts.
Reinstatement
Voids around the turbine foundations will be backfilled as required to facilitate cabling
and earthing works and completed on successful testing. Subsoil excavated from the
existing location will be used and topsoil, including any peaty horizons, spread to tie
to existing ground levels. The area will then be turfed or seeded in consultation with
the Site Ecologist.
6.6.
Purpose
To install the components of the wind turbine with no significant adverse ecological
effects.
Procedure
The components of the wind turbine (towers, nacelles and blades) will be delivered
directly from the highway network via the access tracks to the working areas at the
prepared wind turbine bases.
The cranes will be brought to the site in a disassembled condition. The main crane
body is expected to be a self propelled wheeled unit which can drive to site. All
counterweights and boom sections will be delivered by articulated lorries. An
additional tail crane may be required which is a smaller hydraulic telescopic rough
terrain crane. Before moving on the site the main cranes will require disassembling to
reduce the overall weight and the axle loading to a maximum of 15 tonnes. The tail
crane may in some instances move with the counterweights fitted if it is safe to do so.
The towers will be erected from the delivery trailer onto the foundation bolts. The
HGVs and cranes will operate from the track and the hard standing at each base
location.
The nacelle will be unloaded from its trailer and laid adjacent to the base within the
base working area prior to erection on the tower using the crane. Some minor work
on the nacelle will be required on the ground prior to the lift. Upon delivery, the
blades will be fitted onto the rotor. The rotor assembly will then be lifted onto the
previously erected nacelle by crane. Alternatively the hub may be lifted and attached
to the nacelle followed by a one-to-one installation of the blades.
It is anticipated that the installation of each turbine will take 2 lifting days in good
weather, however, the construction programme allows for an element of weather
downtime.
6.7.
Cable Installation
Description
Cables are required between each of the turbines and the substation compound
at the northwest corner of the wind farm site (on land outside of the common)
and will be located alongside the access tracks. The cables will be laid with
minimal disturbance to vegetation and hydrology at the site.
Procedure
The position of trenches will be surveyed and marked out and the line stripped of
turfs and topsoil and set aside for reinstatement. The trench will be excavated to
the required dimensions and the spoil set aside for backfill, if suitable. Where
depth allows, further segregation of the vegetation layer and topsoil will be
undertaken to prevent burying of the upper vegetation layers in deeper soil upon
replacement. Excavators on open ground will be fitted with low ground pressure
bog tracks if necessary. Extreme care will be taken to minimise damage to areas
of significant peat during cable trenching. Trenches will be excavated to follow
the profile of the existing ground where practical. Typically, sand bedding will be
placed and levelled following insertion of earth conductors (if required). The
cables will be laid onto the sand bedding and a further layer of sand installed to
provide suitable protection above the cable. Following testing by the electrical
works contractor, the trench will be backfilled and compacted in layers with
suitable material and reinstated with previously excavated topsoil and turfs.
Cable ducts will be used where the cables pass under sections of track or
hardstandings.
To minimise exposed ground and the potential for surface run-off, cable trenches
will be excavated and backfilled on a rolling basis in short sections. Where
trenches may become conduits for rainfall, clay bunds will be installed at regular
intervals to prevent sub-surface flows.
Reinstatement
Cable trenches will be constructed at the track edges and will therefore be
incorporated into the restoration of the batters. For any small sections of cable to
be installed away from the tracks, the trench construction and backfilling method
employed on site will entail the re-use of topsoil and turfs without the
requirement for additional treatment.
6.8.
Anemometry Masts
The single anemometry mast will be constructed in the position shown on Figure 1.2
in the Environmental Statement. Construction of the anemometry mast base will be
similar in style to that of the turbine bases, but reduced in size to suit the reduced
loads. The mast will be delivered to site in sections and assembled on the ground
prior to the erection using a suitable crane.
6.9.
Control of Water
Description
During the construction phase of the wind farm, measures will be adopted by the
Contractor in order to prevent silt from being washed into existing watercourses.
These measures will be based on construction best practice and guidance
provided by the Environment Agency and CIRIA. Areas exposed due to the
removal of vegetation are more susceptible to erosion during heavy rainfall or
through rapid surface run-off so areas will be reinstated as soon as possible to
minimise this effect.
Surface water flows will be captured through a series of drainage ditches to
prevent water entering excavations or eroding exposed surfaces. The flows will
be controlled through the use of settlement ponds, small dams, sediment traps
and other hydraulic features to reduce water velocity (thereby reducing erosive
power), maximise infiltration and evaporation and to remove as much sediment
as possible. Surface water flows will then be discharged across open areas
adjacent to the works to allow further reduction in sediment transfer and
increased infiltration of flows.
Where areas are disturbed, the following measures may be implemented to
minimise these effects:
-
Silt run-off from stockpiles and excavated spoil heaps can be contained
through the placement of geotextile silt fences, mats or straw bales on the
downhill side of the stockpile. Stockpiles will be covered with plastic
sheeting or geotextile materials to prevent erosion through heavy rainfall.
Any check dams and mini-settlement ponds will be regularly inspected and
maintained to ensure their effectiveness. All excess silts will be removed
and disposed of within site earthworks. Where check dams have become
fully blocked with silt, they shall be replaced in accordance with the
following procedure:
1. Silt deposits to be removed from the upstream side of check dams.
2. Removed silt to be disposed of by spreading in an area of the site
where surface run-off will not convey silt deposits back to a
watercourse.
3. The existing stone check dams are to be removed and disposed of
in the general fill. Stone materials removed from the check dams
should not be disposed of over vegetated areas of the site.
4. Replacement check dam to be installed using fresh stone.
5. Where there is a regular incidence of check dam blockage further
check dams can be installed within the ditches together with
alternative solutions previously described.
Reinstatement
Ditches will remain in place to convey surface water flows during the operational
life of the wind farm. The ditches will therefore be seeded or turfed as soon as
they have been formed to ensure their maximum effectiveness. Check dams and
any settlement pools may also be retained to remove silt and reduce the velocity
of surface water flows.
7.
An investigation into peat instability has been undertaken which has shown the site is
generally safe to develop (See Appendix 11.4 of the Environmental Statement).
However, appropriate construction practices for peatland areas will be implemented at
the Mynydd y Gwair site to ensure that all reasonable measures are taken to prevent
the possible occurrence of peat failure.
A number of recommendations for construction and design practices that would limit
the possibility of peat failure were made following the site investigations and these
are listed below:
These recommendations will be taken into account when detailed construction method
statements are developed for the Mynydd y Gwair site.
8.
All concrete used in connection with the construction of the Wind Farm will be
sulphate resistant. Concrete deliveries will be delivered at the location of the
foundation and transferred to the formwork by truck mounted concrete pump or
by crane and skip method. Optionally direct discharge from the delivery truck
into the formwork may be used as appropriate.
Formwork will be constructed and secured to ensure that no concrete loss occurs
at joints. Any concrete loss will be either removed or contained.
All vehicles, tools and buckets will only be cleaned within a designated area
adjacent to the excavation and the cementitious wash water discharged into a
specially prepared catchpit lined with a geomembrane. This area will then be
excavated and the spoil removed from site by a licensed waste company. The
catchpit will then be backfilled with spare materials from the foundation
excavation.
If a concrete spillage occurs during transfer it will be cleared immediately in
accordance with the requirements detailed in the Emergency Response Plan.
Silt
A number of silt and sediment specific measures are detailed above in the
respective sections, particularly where they refer to tracks or control of water.
There will be no discharge or disposal of any material directly into any river,
stream or drainage ditch. All discharges will be via a settlement tank or lagoon
prior to discharge over ground, thereby allowing percolation or evaporation prior
to entering the nearest watercourse. Where silty water is to be pumped out of
excavations, the water will be pumped out from a sump within the excavation in
order to avoid disturbance to sediments.
Settling lagoons will typically be made from straw bales lined with a suitable
textile membrane or follow other best practise guidance (such as CIRIA Control of
Water Pollution from Linear Construction Projects). The settling lagoons will be
constructed to an appropriate size to suit local requirements. Where necessary a
series of settling lagoons will be used to ensure that no silty water is discharged.
Pumps will be small-bore and will operate continually to prevent large volumes of
silty water building up in the excavation.
Water will be prevented from entering excavations by the use of cut-off ditches
where appropriate.
All site tracks will be kept free of soil and mud deposits, weather permitting.
Small dams will be placed in trackside ditches to aid silt retention. Fording of
rivers and streams will not be permitted.
Temporary topsoil, peat and subsoil mounds will be sited away from watercourses
and drains. Surface water will directed away from construction activity to avoid
silty run-off entering watercourses or ecologically sensitive areas. Where there is
a high risk of fines or silt washing off stockpiles their size and the duration for
which they will be in such a location will be minimised as far as is reasonably
practicable.
Waste and Litter
Contractors will be required to provide a Site Waste Management plan which will
include details on waste minimisation, recycling and disposal of all waste streams.
The requirements of this plan will be implemented on site as required.
With respect to the control of litter on site, all such waste will be collected and
stored within sealed containers within the site compound and serviced by a
registered waste carrier. No disposal of litter will be permitted at other locations.
Site Induction and Training
9.
The appointed contractors will implement an Emergency Spill Response Plan for use in
the event of a pollution incident. The plan will be formulated based on construction
best practise, CIRIA publications and Environment Agency guidelines guidelines.
The contractor will provide and maintain on site, suitable oil spill response kits to deal
with pollution emergencies. In addition, individual items of plant including mobile fuel
bowsers will carry oil spill kits. The contractor will replenish materials which are
removed or expended as soon as possible.
In the event that a spill occurs on site, actions will be taken to limit the amount of
spill by isolating and controlling/stopping the source. The spill will be contained by
applying absorbent material and, in the case of spillage to a watercourse, by the use
of booms. Action will be taken to ensure that no ecologically sensitive area can be
contaminated.
Clean-up operations can proceed by excavation and removal of contaminated ground
and/or mop-up material and removal from the site in a skip, for controlled disposal of
hazardous waste. Consultation with the Environment Agency for further instructions
would follow. A spill/incident report will be produced for any environmental incident.
Near miss reporting will also be undertaken on site to ensure that lessons are learnt
from near miss incidents to prevent more serious re-occurrences.
10.
A number of properties have been identified which utilise private water supplies
sourced from a spring, borehole or well, which are potentially at very low, but nonnegligible, risk of contamination during construction. Water quality monitoring may
be undertaken throughout the works to ensure no negative impacts occur.
Environmental controls will be put in place as discussed in previous sections to
construction best practises and the Environment Agency pollution control guidelines.
An Emergency Plan shall be put in place to ensure prompt response to any complaint
of perceived impact on private water supplies, including monitoring of the water
supply in question and the immediate cessation of associated water-sensitive
construction activities.
11.
Prohibited Activities
Description
The works contractors will be expected to have due consideration for the
environment in which the works are located. The contractor will therefore ensure
the sympathetic development of the site and restrict practices which could have a
negative effect on the ecology of the site following construction.
Procedure
Work on site by any personnel who have not completed the site induction
process, including health and safety and environmental management
training.
Entry of plant or personnel to any areas outside of designated working
areas;
Unauthorised construction work near protected species sites;
Disposal of waste materials on site;
Use of seed mixes that havent been authorised by the Project Ecologist;
Lighting of fires;
The presence of pets;
Vehicles parking and operating outside of designated parking areas;
Fuelling outside of designated areas;
Direct discharge to waterlogged areas, flushes, streams or other surface
waters.
In addition to the above, a set of site rules will be developed based on previous
experience and introduced to all authorised persons working on the site. Visitors
will be escorted. A suitable site passport carrying the site rules and authorising
the person carrying the passport will be available.
12.
Environmental Monitoring
Description
The Site Management team will call on specialist consultants (i.e. ecologists,
hydrologists, ornithologists etc) as required to ensure that construction is being
carried out in accordance with the requirements set out in the Environmental
Statement, the conditions attached to the planning permission, environmental
best practise and the approved Method Statements.
Procedure
A series of site visits will be completed by the consultants throughout the relevant
periods of construction, particularly when new activities commence on site. The
appointed consultants will confirm that the planned arrangements are being
followed and if any non-compliance is identified, these will be discussed with the
site management team and remedial measures identified and implemented. A
short site visit report will be produced identifying good practices and potential
improvements.
13.
Working Hours
The construction programme will be based on a working week of 5.5 days, 07:00 to
19:00 on weekdays and 07:00 to 12:00 on Saturdays (subject to planning).
Generally, night time or Sunday work will not be permitted. However, working at
night, outside daylight hours and on Sundays may be required to disassemble, move
and re-assemble the main cranes if, for any reason, this work is not completed within
normal working hours. It is essential that the crane movement takes place as
programmed in order not to slow down turbine erection work. Furthermore, critical
operations, (eg a foundation concrete pour that cannot be stopped before completion
or the lifting of turbine parts where the work has to continue to a safe condition) may
require working outside of standard hours.
If work is undertaken outside of normal working hours it is likely to involve operation
of generators, machines and cranes.
No blasting operations are proposed under the works.
Floodlighting may be provided during extended working hours or periods of early
darkness to ensure safe working conditions. The floodlights will be positioned in such
a way as to limit light pollution in the direction of local residents or ecologically
sensitive receptors. Lighting will be powered by mobile generators which will have
drip traps and will be re-fuelled by an approved mobile fuel bowser using a suitable
pump and hose.
14.
Staff Movements